HomeMy WebLinkAbout20181446 Ver 1_USACE Permit_20190124U.S. ARMY CORPS OF ENGINEERS WILMINGTON DISTRICT Action ID. SAW -2018-01879 County: Buncombe U.S.G.S. Quad: Montreat GENERAL PERMIT (REGIONAL AND NATIONWIDE) VERIFICATION Permittee: City of Asheville Water Resources Dept. / Attn: William Pierce Address: P.O. Box 7148 Asheville, NC 28802 Telephone Number: 828-259-5420 Size (acres): 3.7 acres Nearest Town: Asheville Nearest Waterway: Swannanoa River Coordinates: 35.654647 -82.349886 River Basin/HUC: French Broad / 06010105 Location description: The new water line is located along the east side of the North Fork Left Fork Road, near Black Mountain, NC. Description of projects area and activity: This permit authorizes excavation and mechanized landclearing associated with the construction of a new water line. Impacts authorized by this permit total 0.175 acre of permanent wetland impacts and 0.294 acre of temporary wetland impacts; as well as temporary impacts to 105 linear feet of stream channel. Attached are recommendations from the North Carolina Wildlife Resource Commission for your consideration. Please see special conditions below regarding protection of existing cultural resources, protection of federally threatened/endangered species and compensatory mitigation requirements. Applicable Law: ® Section 404 (Clean Water Act, 33 USC 1344) ❑ Section 10 (Rivers and Harbors Act, 33 USC 403) Authorization: Regional General Permit Number or Nationwide Permit Number: 12 SEE ATTACHED RGP or NWP GENERAL, REGIONAL AND SPECIAL CONDITIONS Special Conditions: 1. In order to avoid potential impacts to federally endangered bat species, tree clearing in the project area should occur between October 15 and April 15. 2. In order to avoid potential impacts to the existing USGS gauging station which is considered an eligible structure for listing on the National Register of Historic Places, a 5 -foot buffer with protective fencing as depicted on the Plan Sheet C-101 shall be placed around the station. Routine and on-going inspections of the station by the engineer and/or contractor during project construction is required to confirm that the structure has been undisturbed or if damaged has occurred. The Corps should be notified immediately if it appears that on-going work has damaged or will damage this structure. If any blasting/percussive activities are to occur near the structure then prior coordination with the Corps and the North Carolina State Historic Preservation Office (SHPO) is required to determine any potential effects from the percussive activities on the structure. 3. Bank stabilization activities are not authorized with this permit. Any work to stabilize the stream banks not included in this permitted plan set may require additional/separate Department of the Army permit authorizations. 4. In order to compensate for impacts associated with this permit, mitigation shall be provided in accordance with the provisions outlined on the most recent version of the attached Compensatory Mitigation Responsibility Transfer Form. The requirements of this form, including any special conditions listed on this form, are hereby incorporated as special conditions of this permit authorization. Your work is authorized by the above referenced permit provided it is accomplished in strict accordance with the attached conditions, above noted special conditions, and your submitted application and attached information dated October and January 2019. Any violation of the attached conditions or deviation from your submitted plans may subject the permittee to a stop work order, a restoration order, a Class I administrative penalty, and/or appropriate legal action. This verification will remain valid until the expiration date identified below unless the nationwide/regional authorization is modified, suspended or revoked. If, prior to the expiration date identified below, the nationwide/regional permit authorization is reissued and/or modified, this verification will remain valid until the expiration date identified below, provided it complies with all requirements of the modified nationwide/regional permit. If the nationwide/regional permit authorization expires or is suspended, revoked, or is modified, such that the activity would no longer comply with the terms and conditions of the nationwide/regional permit, activities which have commenced (i.e., are under construction) or are under contract to commence in reliance upon the nationwide/regional permit, will remain authorized provided the activity is completed within twelve months of the date of the nationwide/regional permit's expiration, modification or revocation, unless discretionary authority has been exercised on a case-by-case basis to modify, suspend or revoke the authorization. Activities subject to Section 404 (as indicated above) may also require an individual Section 401 Water Quality Certification. You should contact the NC Division of Water Resources (telephone 828-296-4500) to determine Section 401 requirements. This Department of the Army verification does not relieve the permittee of the responsibility to obtain any other required Federal, State or local approvals/permits. If there are any questions regarding this verification, any of the conditions of the Permit, or the Corps of Engineers regulatory program, please contact Amanda Jones at 828-271-7980, ext. 4225 or amanda.jones@usace.army.mil. FUEMMELER.AMAND Corps Regulatory Official: A.JONE5.12428350900 ,oM9o;;^ 9A;oONES,1 5- Date: January 24, 2019 Amanda Jones Expiration Date of Verification: March 18, 2022 Determination of Jurisdiction: A. ® There are waters, including wetlands, on the above described project area that may be subject to Section 404 of the Clean Water Act (CWA) (33 USC § 1344) and/or Section 10 of the Rivers and Harbors Act (RHA) (33 USC § 403). This preliminary determination is not an appealable action under the Regulatory Program Administrative Appeal Process (Reference 33 CFR Part 331). However, you may request an approved JD, which is an appealable action, by contacting the Corps district for further instruction. Please note, if work is authorized by either a general or nationwide permit, and you wish to request an appeal of an approved JD, the appeal must be received by the Corps and the appeal process concluded prior to the commencement of any work in waters of the United States and prior to any work that could alter the hydrology of waters of the United States. B. ❑ There are Navigable Waters of the United States within the above described project area subject to the permit requirements of Section 10 of the Rivers and Harbors Act (RHA) (33 USC § 403) and Section 404 of the Clean Water Act (CWA) (33 USC § 1344). Unless there is a change in the law or our published regulations, this determination may be relied upon for a period not to exceed five years from the date of this notification. C. ❑ There are waters, including wetlands, within the above described project area that are subject to the permit requirements of Section 404 of the Clean Water Act (CWA) (33 USC § 1344). Unless there is a change in the law or our published regulations, this determination may be relied upon for a period not to exceed five years from the date of this notification. D. ❑ The jurisdictional areas within the above described project area have been identified under a previous action. Please reference jurisdictional determination issued . Action ID: SAW - Basis for Determination: See attached preliminary jurisdictional determination form. In general, the site contains wetlands as determined by the 1987 Corps of Engineers Wetland Delineation Manual and the Regional Supplement to the Corps of Engineers Wetlands Delineation Manual: Eastern Mountain and Piedmont Region(version 2.0). These wetlands are adjacent to stream channels located on the property that exhibit indicators of ordinary high water marks. The stream channels on the project site is known as the Swannanoa River which ultimately drains to the French Broad River and eventually to the Gulf of Mexico. Remarks: E. Attention USDA Program Participants This delineation/determination has been conducted to identify the limits of Corps' Clean Water Act jurisdiction for the particular site identified in this request. The delineation/determination may not be valid for the wetland conservation provisions of the Food Security Act of 1985. If you or your tenant are USDA Program participants, or anticipate participation in USDA programs, you should request a certified wetland determination from the local office of the Natural Resources Conservation Service, prior to starting work. F. Appeals Information (This information applies only to approved jurisdictional determinations as indicated in B and C above). This correspondence constitutes an approved jurisdictional determination for the above described site. If you object to this determination, you may request an administrative appeal under Corps regulations at 33 CFR Part 331. Enclosed you will find a Notification of Appeal Process (NAP) fact sheet and request for appeal (RFA) form. If you request to appeal this determination you must submit a completed RFA form to the following address: US Army Corps of Engineers South Atlantic Division Attn: Jason Steele, Review Officer 60 Forsyth Street SW, Room 10M15 Atlanta, Georgia 30303-8801 Phone: (404) 562-5137 In order for an RFA to be accepted by the Corps, the Corps must determine that it is complete, that it meets the criteria for appeal under 33 CFR part 331.5, and that it has been received by the Division Office within 60 days of the date of the NAP. Should you decide to submit an RFA form, it must be received at the above address by **It is not necessary to submit an RFA form to the Division Office if you do not object to the determination in this correspondence. bY FUEMMELER.AMANDA.J D19iUEMIMELER.AMANDAJONE5.1242835090 DN: -US, -U.S. Government u=DOD, -=PKI, —USA, ONES.] 242835090—FUEMMELERAMANDAJONES. 1242835090 Corps Regulatory Official: Date: 2019M.2414'29:34-°5'00' Amanda Jones Issue Date of JD: January 24, 2019 Expiration Date of JD: N/A Preliminary JD The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to do so, please complete our Customer Satisfaction Survey, located online at http://corpsmgpu.usace.g,M.mil/cm_apex/f?p=136:4:0. Copy furnished: McGill Engineers, Attn: Jon Swaim (via email) NCDWR, Attn: Zan Price (via email) NCDMS, Attn: Kelly Williams (via email) Action ID Number: SAW -2018-01879 County: Buncombe Permittee: City of Asheville Water Resources Dept. / Attn: William Pierce Project Name: North Fork Water Line Project / NAT 12 Date Verification Issued: January 24, 2019 Project Manager: Amanda Jones Upon completion of the activity authorized by this permit and any mitigation required by the permit, sign this certification and return it to the following address: US ARMY CORPS OF ENGINEERS WILMINGTON DISTRICT Attn.: Amanda Jones 151 Patton Avenue, Room 208 Asheville, North Carolina 28801-5006 Please note that your permitted activity is subject to a compliance inspection by a U. S. Army Corps of Engineers representative. Failure to comply with any terms or conditions of this authorization may result in the Corps suspending, modifying or revoking the authorization and/or issuing a Class I administrative penalty, or initiating other appropriate legal action. I hereby certify that the work authorized by the above referenced permit has been completed in accordance with the terms and condition of the said permit, and required mitigation was completed in accordance with the permit conditions. Signature of Permittee Date SECTION I - The following identifies your rights and options regarding an administrative appeal of the above decision. Additional information may be found at htip://www.usace.army.mil/Missions/CivilWorks/Re _ug latoryProgramandPermits.aspx or Corps regulations at 33 CFR Part 331. A: INITIAL PROFFERED PERMIT: You may accept or object to the permit. • ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit. • OBJECT: If you object to the permit (Standard or LOP) because of certain terms and conditions therein, you may request that the permit be modified accordingly. You must complete Section II of this form and return the form to the district engineer. Your objections must be received by the district engineer within 60 days of the date of this notice, or you will forfeit your right to appeal the permit in the future. Upon receipt of your letter, the district engineer will evaluate your objections and may: (a) modify the permit to address all of your concerns, (b) modify the permit to address some of your objections, or (c) not modify the permit having determined that the permit should be issued as previously written. After evaluating your objections, the district engineer will send you a proffered permit for your reconsideration, as indicated in Section B below. B: PROFFERED PERMIT: You may accept or appeal the permit • ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit. • APPEAL: If you choose to decline the proffered permit (Standard or LOP) because of certain terms and conditions therein, you may appeal the declined permit under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice. C: PERMIT DENIAL: You may appeal the denial of a permit under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice. D: APPROVED JURISDICTIONAL DETERMINATION: You may accept or appeal the approved JD or provide new information. • ACCEPT: You do not need to notify the Corps to accept an approved JD. Failure to notify the Corps within 60 days of the date of this notice, means that you accept the approved JD in its entirety, and waive all rights to appeal the approved JD. • APPEAL: If you disagree with the approved JD, you may appeal the approved JD under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the district engineer. This form must be received by the division engineer within 60 days of the date of this notice. NOTIFICATION OF ADMINISTRATIVE APPEAL OPTIONS AND PROCESS AND REQUEST FOR APPEAL Applicant: City of Asheville Water Resources Dept. / Attn: William Pierce File Number: SAW -SAW -2018-01879 Date: January 24, 2019 Attached is: See Section below ❑ INITIAL PROFFERED PERMIT Standard Permit or Letter ofpermission) A ❑ PROFFERED PERMIT Standard Permit or Letter ofpermission) B ❑ PERMIT DENIAL C ❑ APPROVED JURISDICTIONAL DETERMINATION D ® PRELIMINARY JURISDICTIONAL DETERMINATION E SECTION I - The following identifies your rights and options regarding an administrative appeal of the above decision. Additional information may be found at htip://www.usace.army.mil/Missions/CivilWorks/Re _ug latoryProgramandPermits.aspx or Corps regulations at 33 CFR Part 331. A: INITIAL PROFFERED PERMIT: You may accept or object to the permit. • ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit. • OBJECT: If you object to the permit (Standard or LOP) because of certain terms and conditions therein, you may request that the permit be modified accordingly. You must complete Section II of this form and return the form to the district engineer. Your objections must be received by the district engineer within 60 days of the date of this notice, or you will forfeit your right to appeal the permit in the future. Upon receipt of your letter, the district engineer will evaluate your objections and may: (a) modify the permit to address all of your concerns, (b) modify the permit to address some of your objections, or (c) not modify the permit having determined that the permit should be issued as previously written. After evaluating your objections, the district engineer will send you a proffered permit for your reconsideration, as indicated in Section B below. B: PROFFERED PERMIT: You may accept or appeal the permit • ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit. • APPEAL: If you choose to decline the proffered permit (Standard or LOP) because of certain terms and conditions therein, you may appeal the declined permit under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice. C: PERMIT DENIAL: You may appeal the denial of a permit under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice. D: APPROVED JURISDICTIONAL DETERMINATION: You may accept or appeal the approved JD or provide new information. • ACCEPT: You do not need to notify the Corps to accept an approved JD. Failure to notify the Corps within 60 days of the date of this notice, means that you accept the approved JD in its entirety, and waive all rights to appeal the approved JD. • APPEAL: If you disagree with the approved JD, you may appeal the approved JD under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the district engineer. This form must be received by the division engineer within 60 days of the date of this notice. E: PRELIMINARY JURISDICTIONAL DETERMINATION: You do not need to respond to the Corps regarding the preliminary JD. The Preliminary JD is not appealable. If you wish, you may request an approved JD (which may be appealed), by contacting the Corps district for further instruction. Also you may provide new information for further consideration by the Corps to reevaluate the JD. SECTION II - REQUEST FOR APPEAL or OBJECTIONS TO AN INITIAL PROFFERED PERMIT I REASONS FOR APPEAL OR OBJECTIONS: (Describe your reasons for appealing the decision or your objections to an initial proffered permit in clear concise statements. You may attach additional information to this form to clarify where your reasons or objections are addressed in the administrative record.) ADDITIONAL INFORMATION: The appeal is limited to a review of the administrative record, the Corps memorandum for the record of the appeal conference or meeting, and any supplemental information that the review officer has determined is needed to clarify the administrative record. Neither the appellant nor the Corps may add new information or analyses to the record. However, you may provide additional information to clarify the location of information that is already in the administrative record. POINT OF CONTACT FOR QUESTIONS OR INFORMATION: If you have questions regarding this decision and/or the If you only have questions regarding the appeal process you may appeal process you may contact: also contact: District Engineer, Wilmington Regulatory Division, Attn.: Mr. Jason Steele, Administrative Appeal Review Officer Amanda Jones CESAD-PDO 151 Patton Avenue, Room 208 U.S. Army Corps of Engineers, South Atlantic Division Asheville, North Carolina 28801-5006 60 Forsyth Street, Room 10M 15 828-271-7980, ext. 4232 Atlanta, Georgia 30303-8801 Phone: 404 562-5137 RIGHT OF ENTRY: Your signature below grants the right of entry to Corps of Engineers personnel, and any government consultants, to conduct investigations of the project site during the course of the appeal process. You will be provided a 15 day notice of any site investigation, and will have the opportuni to participate in all site investigations. Date: Telephone number: Signature of appellant oragent. For appeals on Initial Proffered Permits send this form to: District Engineer, Wilmington Regulatory Division, Attn.: Amanda Jones, 69 Darlington Avenue, Wilmington, North Carolina 28403 For Permit denials, Proffered Permits and approved Jurisdictional Determinations send this form to: Division Engineer, Commander, U.S. Army Engineer Division, South Atlantic, Attn: Mr. Jason Steele, Administrative Appeal Officer, CESAD-PDO, 60 Forsyth Street, Room 1OM15, Atlanta, Georgia 30303-8801 Phone: (404) 562-5137 U.S. ARMY CORPS OF ENGINEERS Wilmington District Compensatory Mitigation Responsibility Transfer Form Permittee: City of Asheville Water Resources Dept. / Attn: William Pierce Action ID: 2018-01879 Project Name: North Fork Water Line County: Buncombe Instructions to Permittee: The Permittee must provide a copy of this form to the Mitigation Sponsor, either an approved Mitigation Bank or the North Carolina Division of Mitigation Services (NCDMS), who will then sign the form to verify the transfer of the mitigation responsibility. Once the Sponsor has signed this form, it is the Permittee's responsibility to ensure that to the U.S. Army Corps of Engineers (USACE) Project Manager identified on page two is in receipt of a signed copy of this form before conducting authorized impacts, unless otherwise specified below. If more than one mitigation Sponsor will be used to provide the mitigation associated with the permit, or if the impacts and/or the mitigation will occur in more than one 8 -digit Hydrologic Unit Code (HUC), multiple forms will be attached to the permit, and the separate forms for each Sponsor and/or HUC must be provided to the appropriate mitigation Sponsors. Instructions to Sponsor: The Sponsor must verify that the mitigation requirements (credits) shown below are available at the identified site. By signing below, the Sponsor is accepting full responsibility for the identified mitigation, regardless of whether or not they have received payment from the Permittee. Once the form is signed, the Sponsor must update the bank ledger and provide a copy of the signed form and the updated bank ledger to the Permittee, the USACE Project Manager, and the Wilmington District Mitigation Office (see contact information on page 2). The Sponsor must also comply with all reporting requirements established in their authorizing instrument. Permitted Impacts and Compensatory Mitigation Requirements Permitted Impacts Requiring Mitigation*: 8 -digit HUC and Basin: 06010105, French Broad River Basin Stream Impacts (linear feet) Wetland Impacts (acres) Warm Cool Cold Riparian Riverine FRiparian Non-Riverine Non Riparian Coastal 0.17 *If more than one mitigation sponsor will be used for the permit, only include impacts to be mitigated by this sponsor. Compensatory Mitigation Requirements: 8 -digit HUC and Basin: 06010105, French Broad River Basin Stream Mitigation (credits) Wetland Mitigation (credits) Warm Cool Cold Riparian Riverine Riparian Non-Riverine Non -Riparian Coastal 0.34 Mitigation Site Debited: (List the name of the bank to be debited. For umbrella banks, also list the specific site. acceptance letter identifies a specific site, also list the specific site to be debited). For NCDMS, list NCDMS. If the NCDMS Section to be completed by the Mitigation Sponsor Statement of Mitigation Liability Acceptance: I, the undersigned, verify that I am authorized to approve mitigation transactions for the Mitigation Sponsor shown below, and I certify that the Sponsor agrees to accept full responsibility for providing the mitigation identified in this document (see the table above), associated with the USACE Permittee and Action ID number shown. I also verify that released credits (and/or advance credits for NCDMS), as approved by the USACE, are currently available at the mitigation site identified above. Further, I understand that if the Sponsor fails to provide the required compensatory mitigation, the USACE Wilmington District Engineer may pursue measures against the Sponsor to ensure compliance associated with the mitigation requirements. Mitigation Sponsor Name: Name of Sponsor's Authorized Representative: Signature of Sponsor's Authorized Representative Date of Signature Page 1 of 2 Form Updated 14 September, 2017 USACE Wilmington District Compensatory Mitigation Responsibility Transfer Form, Page 2 Conditions for Transfer of Compensatory Mitigation Credit: • Once this document has been signed by the Mitigation Sponsor and the USACE is in receipt of the signed form, the Permittee is no longer responsible for providing the mitigation identified in this form, though the Permittee remains responsible for any other mitigation requirements stated in the permit conditions. • Construction within jurisdictional areas authorized by the permit identified on page one of this form can begin only after the USACE is in receipt of a copy of this document signed by the Sponsor, confirming that the Sponsor has accepted responsibility for providing the mitigation requirements listed herein. For authorized impacts conducted by the North Carolina Department of Transportation (NCDOT), construction within jurisdictional areas may proceed upon permit issuance; however, a copy of this form signed by the Sponsor must be provided to the USACE within 30 days of permit issuance. NCDOT remains fully responsible for the mitigation until the USACE has received this form, confirming that the Sponsor has accepted responsibility for providing the mitigation requirements listed herein. • Signed copies of this document must be retained by the Permittee, Mitigation Sponsor, and in the USACE administrative records for both the permit and the Bank/ILF Instrument. It is the Permittee's responsibility to ensure that the USACE Project Manager (address below) is provided with a signed copy of this form. • If changes are proposed to the type, amount, or location of mitigation after this form has been signed and returned to the USACE, the Sponsor must obtain case-by-case approval from the USACE Project Manager and/or North Carolina Interagency Review Team (NCIRT). If approved, higher mitigation ratios may be applied, as per current District guidance and a new version of this form must be completed and included in the USACE administrative records for both the permit and the Bank/ILF Instrument. Comments/Additional Conditions: This form is not valid unless signed below by the USACE Project Manager and by the Mitigation Sponsor on Page 1. Once signed, the Sponsor should provide copies of this form along with an updated bank ledger to: 1) the Permittee, 2) the USACE Project Manager at the address below, and 3) the Wilmington District Mitigation Office, Attn: Todd Tugwell, 3331 Heritage Trade Drive, Suite 105, Wake Forest, NC 27587 (email: todd. tugwell@usace. army. mil). Questions regarding this form or any of the permit conditions may be directed to the USACE Project Manager below. USACE Project Manager: USACE Field Office: Email: Amanda Jones Asheville Regulatory Field Office US Army Corps of Engineers 151 Patton Avenue, Room 208 Asheville, NC 28801-5006 amanda.iones@usace.army.mil FUEMMELER.AMAND EDUEMMEsigned by LERAMANDA.JONES.1242835090 DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, A.JONES.1242835090 Date: 2019.=FUEMMELE2AMANDA.JONE5.1242835090 .24 USACE Project Manager Signature January 24, 2019 Date of Signature Current Wilmington District mitigation guidance, including information on mitigation ratios, functional assessments, and mitigation bank location and availability, and credit classifications (including stream temperature and wetland groupings) is available at http://ribits.usace.army.mi1. Page 2 of 2 The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to do so, please complete the Customer Satisfaction Survey located at our website at http://regulatorV.usacesurveV.com/ to complete the survey online. PRELIMINARY JURISDICTIONAL DETERMINATION (PJD) FORM BACKGROUND INFORMATION A. REPORT COMPLETION DATE FOR PJD: 8/31/2018 B. NAME AND ADDRESS OF PERSON REQUESTING PJD: Jon Swaim McGill Associates, P.A. 1013 State Farm Road, Boone, NC, 28607 C. DISTRICT OFFICE, FILE NAME, AND NUMBER: Wilmington, #FOLDER NAME#, #FOLDER DA NUMBER# D. PROJECT LOCATION(S) AND BACKGROUND INFORMATION: Study Area located north of Black Mountain, on North Fork Left Fork Road just south of Burnett Reservoir. (USE THE TABLE BELOW TO DOCUMENT MULTIPLE AQUATIC RESOURCES AND/OR AQUATIC RESOURCES AT DIFFERENT SITES) State: NC County/parish/borough: Buncombe City: Black Mountain Center coordinates of site (lat/long in degree decimal format): Lat.: 35.6546470 Long.: -82.349886° Universal Transverse Mercator: 622193.9, 3946484.0 Name of nearest waterbody: Swannanoa River E. REVIEW PERFORMED FOR SITE EVALUATION (CHECK ALL THAT APPLY): ❑ Office (Desk) Determination. Date: ® Field Determination. Date(s):9/22/17 TABLE OF AQUATIC RESOURCES INREVIEW AREA WHICH "MAY BE" SUBJECT TO REGULATORY JURISDICTION. Site Latitude (decimal Longitude Estimated amount of Type of aquatic Geographic authority to Number degrees) (decimal degrees) aquatic resources in resources (i.e., which the aquatic resource review area (acreage wetland vs. non- "maybe" subject (i.e., and linear feet, if wetland waters) Section 404 or Section a licable 10/404 Swannanoa 35.654089 -82.350319 2521f River 404 River UT -1 35.654302 -82.350020 181 if Stream 404 Swannanoa River WA 35.654710 -82.350191 1.23 -acres Wetland 404 WB 35.653587 -82.350798 0.005 -acres Wetland 404 WC 35.654103 -82.350079 0.0005 -acres Wctland 404 WD 35.654103 -82.350079 0.005 -acres Wetland 404 WE 35.654519 -82.349633 0.01 -acres Wetland 404 WF 35.655205 -82.349133 0.13 -acres Wetland 404 WG 35.655205 -82.349133 0.002 -acres Wetland 404 1) The Corps of Engineers believes that there may be jurisdictional aquatic resources in the review area, and the requestor of this PJD is hereby advised of his or her option to request and obtain an approved JD (AJD) for that review area based on an informed decision after having discussed the various types of JDs and their characteristics and circumstances when they may be appropriate. 2) In any circumstance where a permit applicant obtains an individual permit, or a Nationwide General Permit (NWP) or other general permit verification requiring "pre- construction notification" (PCN), or requests verification for a non -reporting NWP or other general permit, and the permit applicant has not requested an AJD for the activity, the permit applicant is hereby made aware that: (1) the permit applicant has elected to seek a permit authorization based on a PJD, which does not make an official determination of jurisdictional aquatic resources; (2) the applicant has the option to request an AJD before accepting the terms and conditions of the permit authorization, and that basing a permit authorization on an AID could possibly result in less compensatory mitigation being required or different special conditions; (3) the applicant has the right to request an individual permit rather than accepting the terms and conditions of the NWP or other general permit authorization; (4) the applicant can accept a permit authorization and thereby agree to comply with all the terms and conditions of that permit, including whatever mitigation requirements the Corps has determined to be necessary; (5) undertaking any activity in reliance upon the subject permit authorization without requesting an AID constitutes the applicant's acceptance of the use of the PJD; (6) accepting a permit authorization (e.g., signing a proffered individual permit) or undertaking any activity in reliance on any form of Corps permit authorization based on a PJD constitutes agreement that all aquatic resources in the review area affected in any way by that activity will be treated as jurisdictional, and waives any challenge to such jurisdiction in any administrative or judicial compliance or enforcement action, or in any administrative appeal or in any Federal court; and (7) whether the applicant elects to use either an AID or a PJD, the JD will be processed as soon as practicable. Further, an AID, a proffered individual permit (and all terms and conditions contained therein), or individual permit denial can be administratively appealed pursuant to 33 C.F.R. Part 331. If, during an administrative appeal, it becomes appropriate to make an official determination whether geographic jurisdiction exists over aquatic resources in the review area, or to provide an official delineation of jurisdictional aquatic resources in the review area, the Corps will provide an AJD to accomplish that result, as soon as is practicable. This PJD finds that there "may be" waters of the U.S. and/or that there "may be" navigable waters of the U.S. on the subject review area, and identifies all aquatic features in the review area that could be affected by the proposed activity, based on the following information: SUPPORTING DATA. Data reviewed for PJD (check all that apply) Checked items should be included in subject file. Appropriately reference sources below where indicated for all checked items: ® Maps, plans, plots or plat submitted by or on behalf of the PJD requestor: Map: Delineation, Location, USGS, Soil ® Data sheets prepared/submitted by or on behalf of the PJD requestor. ❑ Office concurs with data sheets/delineation report. ❑ Office does not concur with data sheets/delineation report. Rationale: ❑ Data sheets prepared by the Corps: ❑ Corps navigable waters' study: ❑ U.S. Geological Survey Hydrologic Atlas: ❑ USGS NHD data. ❑ USGS 8 and 12 digit HUC maps. ® U.S. Geological Survey map(s). Cite scale & quad name: Montreat 1"=300' ❑ Natural Resources Conservation Service Soil Survey. Citation: ® National wetlands inventory map(s). Cite name:NWI Map ❑ State/local wetland inventory map(s): ❑ FEMA/FIRM maps: ® 100 -year Floodplain Elevation is: 2,423.2' (National Geodetic Vertical Datum of 1929) ® Photographs: ❑Aerial (Name & Date): or ®Other (Name & Date):Photo Sheets - 8/28/18 ❑ Previous determination(s). File no. and date of response letter: ❑ Other information (please specify): IMPORTANT NOTE: The information recorded on this form has not necessarily been verified by the Corps and should not be relied upon for later jurisdictional determinations. FUEMMELER.A MANDA.JONES. 1242835090 Digitally signed by FU EMMELER.AMANDAJONES.1242835090 DN: _US, —U.S. Government, ou=DoD, ou=PKI, ou=USA, c—FUEMMELER.AMAN DAJON ES.124283509 0 Date: 2019.01.24 15:06:17-05'00' Signature and date of Regulatory staff member completing PJD 9/6/18 Signature and date of person requesting PJD (REQUIRED, unless obtaining the signature is impracticable)1 1 Districts may establish timeframes for requester to return signed PJD forms. If the requester does not respond within the established time frame, the district may presume concurrence and no additional follow up is necessary prior to finalizing an action. 04. aha 9111 MPA(T W1 TEMPORARY ACCESS ROA ERMANENTLY STREAM TEMPORARY IMPACT TABLE MAINTAINED I CORRIDOR - 20' WIDE S1 NORTH FORK SWANNANOA RIVER 65 L.F. I WITHIN WETLANDS AND STREAMS i S2 UT -1 NORTH FORK SWANNANOA RIVER 40-L.F. TOTAL 105-L.F. TEMPORARY CONSTRUCTION + WETLAND IMPACT TABLE LIMITS O CORRIDOR - 45' WIDE DISTURBANCE TEMPORARY PERMANENT IMPACT W1 WETLAND A 0.27 - ACRES 0.16 -ACRES IMPACT W2 WETLAND B 0.003 - ACRES 0.002 - ACRES WETLAND A `' MPACT S1 IMPACT W3 WETLAND E 0.0007 - ACRES 0.0005 - ACRES IMPACT W4 WETLAND F 0.02 - ACRES 0.01 -ACRES 1 IMPACT W5 WETLAND G 0.00 - ACRES 0.002 -ACRES ` y TOTALS 0.29 ACRES 0.17 -ACRES - SWANNANOA RIVER TOB N FOR \ ` a p \\ 1 j - p i_ IMPACT W / TEMPORARY IMPACTS P't L LL PERMANENTIMPACTS Y 5�P MPACT Z W4 • WETLAND Y _ � O LL '� IMPACT S2' / - T-1 N FORK Z SWANNANOA RIVER a'' 'a;, ,� J .► /J,� MPACT W3 At +.►- / WETLAND WETLAND C \ �� • " PERMANENTLY MAINTAINE' '1 CORRIDOR - 24' WIDE o IMPACT W WETLAND B TEMPORARY CONSTRUCTIO/ CORRIDOR - 45' WIDE GRAPHIC SCALE -100 0 50 100 { -- 1 INCH = 100 FEET JURISDICTIONAL WETLANDS AND WATERS IDENTIFIED ON THIS MAP HAVE BEEN LOCATED WITHIN SUB -METER ACCURACY UTILIZING A THALES MAPPING GRADE GLOBAL POSITIONAING SYSTEM (GPS) AND THE SUBSEQUENT DIFFERENTIAL CORRECTION OF THAT _ DATA. GPS POINTS MAY DEMONSTRATE UNCORRECTABLE ERRORS DUE TO TOPOGRAPHY, VEGETATIVE COVER, AND/OR MULTIPATH SIGNAL ERROR. LIMITS` O t..t_ NOTE: THE ILLUSTRATED WETLAND AND STREAM LOCATIONS ARE APPROXIMATE. THESE AREAS HAVE BEEN FLAGGED IN THE FIELD; HOWEVER, THEY HAVE NOT BEEN SURVEYED. ALTHOUGH MCGILL ASSOCIATES, P.A. (MCGILL) IS CONFIDENT IN OUR ASSESSMENT, DISTURBANCE THE US ARMY CORPS OF ENGINEERS IS THE ONLY AGENCY THAT CAN MAKE FINAL DECISIONS REGARDING JURISDICTIONAL WETLAND AND WATERS OF THE US DELINEATIONS. THIS MAP WAS PREPARED BY MCGILL USING THE BEST INFORMATION AVAILABLE TO MCGILL AT THE TIME OF PRODUCTION. THIS MAP ..1 IS FOR INFORMATIONAL PURPOSES ONLY AND SHOULD NOT BE USED TO DETERMINE PRECISE BOUNDARIES, ROADWAYS, PROPERTY BOUNDARY LINES, NOR LEGAL DESCRIPTIONS. THIS MAP SHALL NOT BE CONSTRUED TO BEAN OFFICIAL SURVEY OF ANY DATA DEPICTED. BUNCOMBE COUNTY GIS. CITY OF ASHEVILLE NORTH FORK McGifl IMPACT MAP PROJECT # WATER LINE PROJECT 17.00346 BLACK MOUNTAIN, NC A S S O C I A T E S OCTOBER 2018 BUNCOMBE COUNTY, ENVIRONMENTAL FINANCE NORTH CAROLINA 1013 STATE FARM ROAD BOONE,NC28607 PH.(828)386-1920 3 M N O a) 0 LL v M O O a 0 LL `o z Q O U v co 0 O Q 0 Ne 0 co 0 N N U � W 0, 0 GENERAL CONSTRUCTION NOTES SPECIAL CONDITIONS EXISTING CONDITIONS LEGENDTEL W z W REVISION DATE -JUNE 16, 2009 SPED TELEPHONE PEDESTAL p CALCULATED POINT = - - - - - - - - - - - - - - - CULVERT • `� w U 1. INSURANCE SUBMITTALS FOR CONTRACTOR REQUIRED TO EXECUTE CONTRACT: DELEC PED CATV ELECTRIC PEDESTAL O IPS 1/2" REBAR SET WITH CAP x x x FENCE PED CABLE TV PEDESTAL 0 ElI� CONCRETE MONUMENT SILT FENCE 1. FINISH GRADE TOLERANCES SHALL BE AS NOTED IN THE SPECIFICATIONS. THE ENGINEER MAY MAKE GRADE a. SUBMIT A COI LISTING THE CITY AS CERTIFICATE HOLDER (COA, PO BOX 7148, ASHEVILLE, NC 28802) ANDSIGN SIGN SCM-R/W RIGHT-OF-WAY MONUMENT -o -o -o -o -o -o -o -o -o -o -o -o -o -o- GUARD RAIL �I CHANGES AS REQUIRED IN THE FIELD WITHOUT EFFECTING THE UNIT BID PRICE FOR UNCLASSIFIED EXCAVATION. LIST THE CITY AS ADDITIONAL INSURED ON THEIR GENERAL LIABILITY AND AUTO LIABILITY POLICIES. IN ADDITION, CATV 0- DOT MON - - - _ _ _ _ APPROXIMATE LOCATION OF s -s ' SUBMIT A WAIVER OF SUBROGATION FOR THE CITY ON CONTRACTOR'S WORKERS' COMPENSATION POLICY. UNDERGROUND CABLE TV SIGN D.O.T. CONTROL POINT EXISTING SEWER LINES 2. UNLESS OTHERWISE STATED, ALL FILL AREAS SHALL BE CONSTRUCTED IN LAYERS OF 8" MAXIMUM THICKNESS, FOC UNDERGROUND FIBER OPTIC CABLE SIGNUG • RBF REBAR FOUND - - - - _ W- - - - - W APPROXIMATE LOCATION OF o WITH WATER ADDED OR SOIL CONDITIONED TO THE OPTIMUM MOISTURE CONTENT AS DETERMINED BY THE b. COI LIMITS NEED TO REFLECT HIGH RISK PROFILE COLUMN ON CITY INSURANCE MATRIX, TITLED CITY OF UG TCS UNDERGROUND TELEPHONE CABLE SIGN •RRSPIKE RAILROAD SPIKE EXISTING WATER LINES cv ENGINEER AND COMPACTED WITH A SHEEP'S FOOT ROLLER TO A COMPACTION EQUAL TO OR GREATER THAN ASHEVILLE MINIMUM INSURANCE COVERAGE AND REQUIREMENTS 1/19/2010 (3 PAGES). UG cas 0 PK NL -----c-----c APPROXIMATE LOCATION OF N 95% (100% IN THE TOP 2' OF THE SUB GRADE BELOW ROADWAYS AND PARKING LOTS) OF THE DENSITY UNDERGROUND GAS LINE SIGN 'SPINDLE PK NAIL FOUND /SETEXISTING GAS LINES ) Z OBTAINED BY COMPACTING A SAMPLE OF THE MATERIAL IN ACCORDANCE WITH THE STANDARD PROCTOR 2. CONTRACTOR TO CALL NC ONE CALL (811) FOR KNOWN LOCATIONS OF BURIED UTILITIES. NATURAL GAS �UG ELEC UNDERGROUND ELECTRIC LINE SIGN SPINDLE FOUND /SET METHOD OF MOISTURE -DENSITY RELATIONSHIP TEST, ASTM D698 OR AASHTO-99 UNLESS SPECIFIED IN OTHER PIPELINES EXIST ON CERTAIN STREETS. LP ®CPHUB I I I I I I I I I I I I TOP & TOE LINES HUB &TACK SET z SPECIFICATIONS.a. 3. PROPOSED WATERLINE ALIGNMENT IS APPROXIMATE. ACTUAL INSTALLATION TO VARY IN ORDER TO MAINTAIN • uP LIGHT POLE UTILITY POLE ®P/NL -- CONTROL POINT NAIL SET /FOUNDDL-----DL-----DL- DITCH LINES GPS 3. 20' PERMANENT MAINTENANCE CORRIDOR AREA SHALL BE CLEARED AND GRUBBED. NO PERMANENT FILL 3 -FT HORIZONTAL SEPARATION FROM OTHER UTILITIES EXCEPT EXISTING WATERLINES. WHERE A 3 -FT SEPARATION E GUY WIRE ANCHOR p CONTROL POINT/NAIL SET GPS - - - - -CTV- - - - -CTV- APPROXIMATE LOCATION OF o SHALL BE PLACED ON ANY AREA NOT CLEARED AND GRUBBED. AREAS OUTSIDE OF 20' PERMANENT CANNOT BE MAINTAINED, THE ASSIGNED CITY CONSTRUCTION OBSERVER MAY AUTHORIZE LESS SEPARATION FOR ®TSP TRAFFIC SIGNAL POLE CP/NL UNDERGROUND CABLE TV LINE CONTROL POINT TEMPORARY MARK o0 � MAINTENANCE CORRIDOR AND WITHIN 40' CONSTRUCTION CORRIDOR MAY BE CLEARED BUT NOT GRUBBED. NON -SEWER UTILITIES. REPAIR OF DAMAGE TO EXISTING UTILITIES DURING CONSTRUCTION IS INCIDENTAL TO WATERLINE CP/TEMP CTv APPROXIMATE LOCATION OF INSTALLATION AND SHOULD BE INCLUDED IN THE UNIT COSTS PER LINEAR FOOT. RXR RAILROAD CROSSING SIGNAL OVERHEAD CABLE TV LINE iV°�"S NGS METAL ROD NATIONAL GEODETIC SURVEY METAL ROD Z 4. ALL SOIL EROSION CONTROL MEASURES REQUIRED BY THE GRADING PLAN SHALL BE PERFORMED PRIOR TO 4. PROJECT AREA IS TRAVERSED BY BUNDLES OF UNDERGROUND TELECOMMUNICATIONS CABLES WHICH MAY BE QMH MANHOLE NGS CM -----FOC-----FOC- APPROXIMATE LOCATION OF NATIONAL GEODETIC SURVEY CONCRETE MONUMENT UNDERGROUND FIBER OPTIC CABLE LINE GRADING, CLEARING OR GRUBBING. ALL EROSION CONTROL DEVICES SUCH AS SILT FENCES, ETC., SHALL BE CROSSED AT MULTIPLE LOCATIONS. MAINTAIN 12 INCHES OF CLEARANCE FROM ALL TELECOMMUNICATIONS CABLES. Q SSMH SANITARY SEWER MANHOLE MAINTAINED IN WORKABLE CONDITION FOR THE LIFE OF THE PROJECT AND SHALL BE REMOVED AT THE WHERE WATERLINES MUST CROSS BENEATH CABLES TO MAINTAIN CLEARANCE AND COVER, ADDITIONAL COSTS ARE Q SDMH TEMPORARY CONTROL POINT SET APPROXIMATE LOCATION OF COMPLETION OF THE PROJECT ONLY ON THE ENGINEER'S APPROVAL. PAYMENT SHALL BE CONSIDERED INCIDENTAL TO PRICE PER LINEAR FOOT. STORM DRAIN MANHOLE ® - - - -E- - - - -E NETWORK TRIANGULATION POINT UNDERGROUND ELECTRIC LINE I --I > w INCIDENTAL TO CLEARING AND GRUBBING. IF DURING THE LIFE OF THE PROJECT, A STORM CAUSES SOIL Q COMMH COMMUNICATION MANHOLE APPROXIMATE LOCATION OF EROSION WHICH CHANGES FINISH GRADES OR CREATES "GULLIES" AND "WASHED AREAS", THESE SHALL BE 5. THE INFORMATION RELATIVE TO EXISTING STRUCTURES, APPARENT AND LATENT CONDITIONS, AND NATURAL Q ELMH ELECTRICAL MANHOLE STAKE E E STAKE FOUND OVERHEAD ELECTRIC LINE U, W Q REPAIRED AT NO EXTRA COST, AND ALL SILT WASHED OFF OF THE PROJECT SITE ONTO ADJACENT PROPERTY PHENOMENA, AS FURNISHED TO THE CONTRACTOR ON THE DRAWINGS, IN THE CONTRACT DOCUMENTS, OR BY THE Q J B 40 SHALL BE REMOVED AS DIRECTED BY THE ENGINEER AT NO EXTRA COST. THE CONTRACTOR SHALL ADHERE OWNER OR THE ENGINEER, CARRIES NO GUARANTEE EXPRESSED OR IMPLIED AS TO ITS COMPLETENESS OR ACCURACY, JUNCTION BOX 66 INTERSTATE HIGHWAY APPROXIMATE LOCATION OF - - - - T- - - - - T UNDERGROUND TELEPHONE LINES W F. TO ANY APPROVED EROSION CONTROL PLANS WHETHER INDICATED IN THE CONSTRUCTION PLANS OR UNDERAND SEPARATE COVER.FFE HE HAS MADE DUE ALLOWANCE THEREFORE. INFORMATION FROM ARCHIVAL DOCUMENTS IS AVAILABLE BUT NO SPIGOT SPIGOT YARD HYDRANT U.S. HIGHWAY w GUARANTEE IS EXPRESSED OR IMPLIED AS TO THEIR COMPLETENESS OR ACCURACY AT THE TIME OF PREPARATION OR O C.O. *ELEVATION FINISHED FLOOR ELEVATIONAPPROXIMATE LOCATION OF 5. DISPOSABLE MATERIAL CURRENTLY. 0 E.SS SEWER CLEAN-OUT ELECTRIC SERVICE STUB -OUT Q5 MW T T OVERHEAD TELEPHONE LINES MONITORING WELL ~ INFORMATION SHOWN IN PLAN VIEW IS NOT COMPLETE. ALL UNDERGROUND UTILITIES AND STORM DRAINAGE PIPES O c.ss • Pz ---- PIEZOMETER -ROW-----ROW- RIGHT-OF-WAY `.J O A. CLEARING AND GRUBBING WASTES SHALL BE REMOVED FROM THE SITE AND PROPERLY DISPOSED OF BY ARE NOT SHOWN IN THE PLAN VIEWS. NO GUARANTEE IS EXPRESSED OR IMPLIED AS TO THE ACCURACY OF THE GAS SERVICE STUB -OUT ® TREELINE Z THE CONTRACTOR AT HIS EXPENSE, UNLESS SPECIFIED OTHERWISE. INFORMATION SHOWN IN THE PLAN VIEWS. ® CB CATCH BASIN LANDFILL GAS MONITORING PROBE m ®cI ® () 0 0 () 0 0 0 0 0 C) SHRUBLINE W B. SOLID WASTES TO BE REMOVED, SUCH AS SIDEWALKS, CURBS, PAVEMENT, ETC., MAY BE PLACED IN 6. CONTRACTOR WILL FURNISH ALL OF THE MATERIALS, SUPPLIES, TOOLS, EQUIPMENT, LABOR, AND OTHER SERVICES CURB INLET SURFACE WATER SAMPLING LOCATION SPECIFIC DISPOSAL AREAS DELINEATED ON THE PLANS OR REMOVED FROM THE SITE AS REQUIRED BY NECESSARY FOR THE CONSTRUCTION AND COMPLETION OF THE PROJECT DESCRIBED HEREIN. THE UNIT PRICES SHALL OWM LANDFILL GAS VENT WATER METER PROPERTY LINE NOT SURVEYED THE SPECIFICATIONS. THIS MATERIAL SHALL HAVE A MINIMUM COVER OF 2'. THE CONTRACTOR SHALL INCLUDE ALL LABOR, MATERIALS, DEWATERING, SHORING, REMOVAL, OVERHEAD, PROFIT, INSURANCE, TAXES, FEES, AFHO FIRE HYDRANT LANDFILL GAS COLLECTION WELLHEAD MAINTAIN SPECIFIED COMPACTION REQUIREMENTS IN THESE AREAS. WHEN DISPOSAL SITES ARE NOT ETC., TO COVER THE FINISHED WORK OF THE SEVERAL KINDS CALLED FOR: � 000000000000000000000000 R O C K LI N E PROVIDED, THE CONTRACTOR SHALL REMOVE THIS WASTE FROM THE SITE AND PROPERLY DISPOSE OF IT � WV WATER VALVE POTABLE WATER WELL I AT HIS EXPENSE. CONTRACTOR SHALL FURNISH AND ASSUME FULL RESPONSIBILITY FOR ALL MATERIALS, EQUIPMENT, LABOR I>< BLOW OFF VALV. BLOW OFF VALVE OMB MAILBOX OR PAPER BOX - STREAM LINE C. ABANDONED UTILITIES SUCH AS CULVERTS, WATER PIPE, HYDRANTS, CASTINGS, PIPE APPURTENANCES, TRANSPORTATION,TR TI IP T N MACHINERY, T PPI F TRI POWER, LIGHT, CONSTRUCTION ON EQU MEN ANDTOOLS, APPLIANCES, FUEL, ELECTRIC OWE L G HEAT, TELEPHONE, WATER, SANITARY FACILITIES, TEMPORARY FACILITIES AND ALL OTHER FACILITIES AND INCIDENTALS b G/M GAS METER 1:1 PB POSTAL DROP BOX CENTERLINE ROADS UTILITY POLES, ETC., SHALL BE THE PROPERTY OF THE SPECIFIC UTILITY AGENCY, OR COMPANY HAVING NECESSARY FOR THE FURNISHING, PERFORMANCE, TESTINGS, START-UP, PROTECTION AND COMPLETION OF THE WORK. b G/v GAS VALVE .4 SAT DISH SATELLITE DISH CENTERLINE OTHER THAN ROADS Jam` �`` JURISDICTION. BEFORE THE CONTRACTOR CAN REMOVE, DESTROY, SALVAGE, REUSE, SELL OR STORE FOR >4IcV OYARD ORNAMENT STATUE, BIRD BATHS, ETC. HIS OWN USE ANY ABANDONED UTILITY, HE MUST PRESENT TO THE OWNER WRITTEN PERMISSION FROM THE UTILITY INVOLVED. 7. WHEREVER SANITARY SEWER CROSSINGS ARE NECESSARY AND DO NOT MEET THE 18" MINIMUM CLEARANCE OR °° PIV IRRIGATION CONTROL VALVE TREES SWAMPLINE/WETLANDS 2 THE SEWER IS OVER THE WATERLINE, THE CONTRACTOR WILL REPLACE THE SEWER PIPE (ALL SIZES INCLUDING POST INDICATOR VALVE SERVICES) FOR 10 LF ON EITHER SIDE OF NEW WATERLINE WITH FERROUS PIPE WITH JOINTS EQUIVALENT TO POTABLE ® E.JUNC ELECTRIC JUNCTION BOX OR OUTLET 0 SHRUBS /BUSHES u u APPROXIMATE LOCATION OF D. ON SITE BURNING IS AN ACCEPTABLE METHOD OF DISPOSING OF FLAMMABLE WASTES. WHEN BURNING IS WATERLINE CONSTRUCTION STANDARDS. NO SEWER REPLACEMENT IS NECESSARY WHERE A VERTICAL SEPARATION OF o SIG OVERHEAD UTILITY LINE ANTICIPATED, THE CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING ALL NECESSARY PERMITS AND 18 INCHES IS MAINTAINED WITH THE WATER MAIN ABOVE THE SANITARY SEWER. THERE IS A PAY ITEM FOR THE Box TRAFFIC SIGNAL BOX (H) HORIZONTAL GROUND DISTANCE MEETING GOVERNING CODES. THE CONTRACTOR SHALL NOTIFY THE ENGINEER OR HIS REPRESENTATIVE AS REPLACEMENT OF SEWER PIPE AT THE CROSSINGS BY THE WATER MAIN. (G) NC STATE PLANE GRID DISTANCE TO THE SPECIFIC LOCATION OF BURNING. Q Q AFTER BURNING IS COMPLETED, PURE ASH MAY BE DISPOSED OF BY MIXING WITH FILL DIRT. ALL 8. CONTRACTOR TO IMMEDIATELY REPAIR ANY BREAKS IN EXISTING WATER AND SEWER LINES ENCOUNTERED DURING CONSTRUCTION. FULL UTILITY SERVICES TO BE MAINTAINED TO ALL RESIDENCES DURING CONSTRUCTION EXCEPT IPS IRON PIN SET � Z MATERIAL NOT TOTALLY BURNED SHALL BE DISPOSED OF AS SPECIFIED IN "B" ABOVE. THE CONTRACTOR DURING REPAIR OF BREAKS, TIE-IN CONNECTIONS, AND FINAL RECONNECTION OF CITY WATER METERS. RBF REBAR FOUND � SHALL NOT HOLD UP WORK PROGRESS FOR THE PURPOSE OF WAITING FORA "BURNING DAY". � J 9. ACCESS TO RESIDENCES TO BE MAINTAINED AT ALL TIMES EXCEPT WITH PERMISSION OF THE ASSIGNED CITY OTIPF OPEN TOP IRON PIN FOUND Q O 6. IN THE EVENT EXCESSIVE GROUNDWATER OR SPRINGS ARE ENCOUNTERED WITHIN THE LIMITS OF CONSTRUCTION, THE CONTRACTOR SHALL INSTALL NECESSARY DEWATERING DEVICE AS DIRECTED BY THE CONSTRUCTION OBSERVER. CONTRACTOR TO NOTIFY AFFECTED RESIDENTS IN ADVANCE OF ANY BLOCKAGES TO ACCESS SO VEHICLES CAN BE MOVED OUTSIDE THE BLOCKED AREA. DETOUR SIGNS TO BE ERECTED FOR ANY STREET CTIPF CRIMPED TOP IRON PIN FOUND 3:: N L.1_ ENGINEER. ALL WORK SHALL BE PAID BASED UPON UNIT BIDS, UNLESS SPECIFIED OTHERWISE. UNDER DRAINS CLOSURES. ALL EXCAVATIONS TO BE FILLED OR COVERED AT THE END OF EACH DAY FOR SAFETY AND SO THAT CMU CONCRETE MASONRY UNIT CITY OF ASHEVILLE Q AND STONE ARE NOT ALLOWED UNDER THE PROPOSED US ARMY CORPS PERMITTING. VEHICULAR ACCESS IS RESTORED. R/W RIGHT OF WAY w (n L1 U 7. THE CONTRACTOR IS RESPONSIBLE FOR THE COORDINATION OF ADJUSTMENT OF ALL UTILITY SURFACE10. AWARDED CONTRACTOR TO PROVIDE SCHEDULE OF ANTICIPATED STREETS WHERE CONTRACTOR WILL BE WORKING q_ CENTERLINE WATER LINE CONSTRUCTION NOTES o J = ACCESSES WHETHER HE PERFORMS THE WORK OR A UTILITY COMPANY PERFORMS THE WORK. FOR EACH OF NEXT FOUR WEEKS AND THEN SUBSEQUENT MONTHS REMAINING IN CONTRACT. WORK SCHEDULE TO BE C CURVE (SEE CURVE TABLE) Q 8. THE CONTRACTOR SHALL CONTROL ALL "DUST" BY PERIODIC WATERING AND SHALL PROVIDE ACCESS AT ALL MAINTAINED IN ELECTRONIC DOCUMENT (WORD, EXCEL, OR EQUIVALENT) SUCH THAT CITY CAN COMMUNICATE POB POINT OF BEGINNING NN SCHEDULE INFORMATION TO WEBSITE OR OTHER MEANS. L.L TIMES FOR PROPERTY OWNERS WITHIN THE PROJECT AREA AND FOR EMERGENCY VEHICLES. ALL OPEN DITCHES CP CALCULATED POINT 1. WATER LINE CONSTRUCTION IS AUTHORIZED BY PERMITS ISSUED BY THE NORTH CAROLINA AND HAZARDOUS AREAS SHALL BE CLEARLY MARKED IN ACCORDANCE WITH THE SPECIFICATIONS. 11. OWNER WILL PROVIDE SURVEY CONTROL POINTS WITHIN OR ADJACENT TO PROJECT AREA BUT CONTRACTOR IS PB PLAT BOOK DEPARTMENT OF ENVIRONMENTAL QUALITY (NCDEQ) AND THE CITY OF ASHEVILLE (COA). m m 9. ALL AREAS WHERE THERE IS EXPOSED DIRT SHALL BE SEEDED, FERTILIZED AND MULCHED ACCORDING TO THE RESPONSIBLE FOR CONSTRUCTION STAKEOUT AND ANY ADDITIONAL SURVEY REQUIREMENTS FOR CONSTRUCTION OFTHE DB DEED BOOK THE WORK IS SUBJECT TO INSPECTIONS AT ALL TIMES BY REPRESENTATIVES OF NCDEQ, � PROJECT. OWNER WILL PROVIDE 2015 CIVIL 3D DIGITAL COPIES OF CONSTRUCTION DRAWINGS IF DESIRED BY THE w SPECIFICATIONS. THE FINISHED SURFACE SHALL BE TO GRADE AND SMOOTH, FREE OF ALL ROCKS LARGER CONTRACTOR FOR CONSTRUCTION LAYOUT. ANY SURVEYING BY THE CONTRACTOR ARE INCIDENTAL TO THE UNIT COSTS L LINE (SEE LINE TABLE) CITY OF ASHEVILLE, AND THE ENGINEER. THE PERMITS REQUIRE CERTIFICATION OF z THAN 3", EQUIPMENT TRACKS, DIRT CLODS, BUMPS, RIDGES AND GOUGES PRIOR TO SEEDING; THE SURFACE IN THE BID SCHEDULE PAY ITEMS. THE CONTRACTOR WILL NOT BE RESPONSIBLE TO PROVIDE THE SURVEYING COMPLETION BY THE ENGINEER OF RECORD PRIOR TO ISSUANCE OF FINAL APPROVAL BY 0 >- SHALL BE LOOSENED TO A DEPTH OF t4"-6" TO ACCEPT SEED. THE CONTRACTOR SHALL NOT PROCEED WITH NECESSARY FOR THE AS -BUILT DOCUMENTS, BUT WILL BE RESPONSIBLE FOR CONSTRUCTION DRAWING MARK-UPS AND BLDG BUILDING NCDEQ. 0J SEEDING OPERATIONS WITHOUT FIRST OBTAINING THE ENGINEER'S APPROVAL OF THE GRADED SURFACE. ALL SEEDING SHALL BE PERFORMED BY A MECHANICAL "HYDRO HAND SEEDING SHALL BE AUTHORIZED UNDERGROUND DIMENSIONS WHERE THERE ARE NO SURFACE FEATURES. CIP CAST IRON PIPE z -SEEDER". CMP CORRUGATED METAL PIPE 2. CONTRACTOR SHALL VERIFY THE EXACT LOCATION AND ELEVATION FOR ALL UTILITIES z ON AN AREA BY AREA APPROVAL BY THE ENGINEER. DISTURBED AREAS SHOULD THEN BE MATTED WITH 12. IN AREAS WHERE CONNECTIONS TO EXISTING WATERLINES ARE DESIGNATED (EITHER BY TAPPING SLEEVE OR CONC CONCRETE DRAINAGE & OTHER UNDERGROUND FACILITIES BOTH EXISTING & PROPOSED, & SHALL = O SHORT-TERM PHOTODEGRADABLE EROSION CONTROL MATTING. CUT -INS), THE CONNECTION FITTING DETAILS ARE NOT SHOWN ON THE PLAN. THE CONTRACTOR IS RESPONSIBLE FOR THE DETAILS OF THE FITTINGS AND CONNECTIONS. THE CONNECTION SPECIFICS ARE SUBJECT TO APPROVAL BY THE CMU CONCRETE MASONRY UNIT NOTIFY THE ENGINEER OF ANY DISCREPANCIES OR CONFLICTS PRIOR TO CONSTRUCTION. N U 10. WHERE SPECIFIED, STORM DRAIN PIPE SHALL BE CORRUGATED METAL PIPE (CMP) CONFORMING TO AASHTO ASSIGNED CITY CONSTRUCTION OBSERVER AND MUST BE IN IN ACCORDANCE WITH CITY STANDARDS. THE CONTRACTOR CPP CORRUGATED PLASTIC PIPE 13L 0 M-36, WITH REROLLED ENDS TO ACCOMMODATE CORRUGATED COUPLING BANDS. 18" PIPE SHALL BE 16 IS RESPONSIBLE FOR INVESTIGATING EXISTING UNDERGROUND CONDITIONS PRIOR TO BIDDING AND THE COSTS OF ANY 3. ALL PROPOSED WATER LINES SHALL HAVE 3'-0"MINIMUM COVER & BE CONSTRUCTED OF O W GAUGE, 24" AND 30" PIPE SHALL BE 14 GAUGE AND 36" PIPE AND OVER SHALL BE 12 GAUGE AS SPECIFIED ACCOMMODATIONS FOR ANY UNDERGROUND CONFLICTS ARE INCIDENTAL TO THE UNIT PRICES FOR THE TIE-INS, DIP DUCTILE IRON PIPE _ ON THE PLANS, PIPE AND COUPLING BANDS SHALL CONFORM TO NCDOT 1032-3 FOR PLAIN PIPE OR 1032-4 TAPPING SLEEVES, FITTINGS, OR OTHERS. E&T ELECTRIC & TELEPHONE FERROUS MATERIAL. z 2i O m (A) FOR BITUMINOUS COATED AND PARTIALLY PAVED PIPE. DIMPLE BANDS SHALL NOT BE USED. 13. CONTRACTOR TO STAKE PROPOSED FIRE HYDRANT LOCATIONS AS SHOWN ON THE CONSTRUCTION DRAWINGS. IN FOC FIBER OPTIC CABLE 4. MATERIALS FOR & INSTALLATION OF PROPOSED WATER LINES SHALL CONFORM TO ALL U) WHERE SPECIFIED, STORM DRAIN PIPE SHALL BE REINFORCED CONCRETE PIPE (RCP) CONFORMING TO AASHTO CONSULTATION WITH THE CONTRACTOR, AND THE ASSIGNED CITY CONSTRUCTION OBSERVER, THE ENGINEER WILL GIP GALVANIZED IRON PIPE APPLICABLE COA STANDARD SPECIFICATIONS &MOST RECENT DESIGN GUIDELINES, & z Q M-170, AS CONTAINED IN NCDOT STANDARD SPECIFICATION 1032-9 FOR WALL "B" TYPE. REVIEW THE STAKED PROPOSED FIRE HYDRANT LOCATIONS AND MANUALLY ADJUST THEM IN THE FIELD. HOWEVER, CHANGES IN FOOTAGE OF 6" DIP RESULTING FROM CHANGES IN THE PROPOSED LOCATIONS OF THE FIRE HYDRANTS 0/H OVERHEAD SHALL BE PERFORMED BY A NORTH CAROLINA LICENSED UTILITY CONTRACTOR UNDER THE � � V z WILL ADJUST THE PRICE ACCORDING TO THE UNIT PRICE PER LINEAR FOOT. DOT DEPARTMENT OF TRANSPORTATION INSPECTION OF THE CITY OF ASHEVILLE. WHERE SPECIFIED, ALL STORM DRAIN PIPE SHALL BE HIGH DENSITY POLYETHYLENE (HDPE). SMOOTH WALL NGS NATIONAL GEODETIC SYRVEY ~ INTERIOR, WITH WATER TIGHT JOINTS, BACKFILLED WITH # 57 WASHED STONE UP TO MIN. 6" OVER THE TOP NCSP NORTH CAROLINA STATE PLANE 5. CONTRACTOR SHALL PROTECT EXISTING UTILITIES DURING CONSTRUCTION. REPAIRS SHALL V m OF THE PIPE. HDPE PIPE USED FOR STORM DRAINAGE DETENTION SYSTEMS SHALL BE ADS N12 WT 14. THE CONTRACTOR IS RESPONSIBLE FOR THE ABANDONMENT OF AND ABANDONMENT PROCEDURES FOR THE MTR BOX METER BOX OR APPROVED EQUAL. EXISTING WATER LINES BEING REPLACED AND, IN FACT, MUST MAINTAIN THEM IN SERVICE THROUGHOUT UNTILBE MADE IN ACCORDANCE WITH APPLICABLE STANDARDS OF APPROPRIATE AGENCIES AT CERTIFICATION BY THE ENGINEER AND CONNECTION OF THE NEW WATERLINE TO THE CITY WATER METERS SERVED BY RCP REINFORCED CONCRETE PIPE THE CONTRACTOR'S EXPENSE. WHERE SPECIFIED, ALL CORRUGATED METAL STORM DRAIN PIPE (CMP) SHALL BE ALUMINIZED TYPE 2 THE LINE TO BE ABANDONED. THE CONTRACTOR MAY REQUEST FROM THE OWNER THAT CERTIFICATION, SWITCHOVER, U/G UNDERGROUND CORRUGATED STEEL MANUFACTURED IN ACCORDANCE WITH THE REQUIREMENTS OF AASHTO M-36. THE PIPE AND ABANDONMENT BE CONDUCTED IN PHASES SUBJECT TO THE OWNER'S APPROVAL. THE ABANDONED WATERLINES VCP VITRIFIED CLAY PIPE SHALL BE MANUFACTURED FROM ALUMINIZED STEEL TYPE 2 MATERIAL CONFORMING TO THE REQUIREMENTS OF WILL BE CAPPED/PLUGGED AT MAXIMUM 1000 LF INTERVALS AND THE VALVE BOXES REMOVED AFTER THE 6. CONTRACTOR SHALL NOTIFY NC ONE -CALL CENTER & APPROPRIATE UTILITY AGENCY PRIOR = AASHTO M-274. ALL PIPE SHALL BE FURNISHED WITH REROLLED ENDS AND SHALL BE JOINED WITH HUGGER ABANDONED VALVES ARE PERMANENTLY CLOSED. EXISTING FIRE HYDRANTS ARE TO BE REMOVED AFTER NEW PVC POLYVINYL CHLORIDE PIPE TO PERFORMING ANY WORK. CO 00 It J BANDS. THE USE OF DIMPLE BANDS WILL NOT BE ALLOWED. PIPE THROUGH 24" DIAMETER SHALL BE 16 HYDRANTS ARE FULLY OPERATIONAL AND THEN TRANSPORTED AND UNLOADED AT LOCATION DESIGNATED BY CITY NOT FFE FINISHED FLOOR ELEVATION o C) GAUGE, PIPE THROUGH 42" DIAMETER SHALL BE 14 GAUGE, PIPE THROUGH 54" DIAMETER SHALL BE 12 TO EXCEED 10 MILES IN DISTANCE FROM PROJECT. PG PAGE 7. THE CITY OF ASHEVILLE REQUIRES A 3 -0 MINIMUM SEPARATION BETWEEN THE o N w w m > > o W GAUGE. 15. THE CONTRACTOR IS RESPONSIBLE TO PROVIDE THE OWNER WITH NOTICE OF THREE BUSINESS DAYS IN ADVANCE REF REFERENCE BACK-OF-CURB/EDGE-OF-PAVEMENT AND PROPOSED WATER LINE. > m Uj 2E w .0 ro 11. CONTRACTOR SHALL VERIFY ALL ELEVATIONS BEFORE INSTALLATION OF FACILITIES. OF ANY SCHEDULED WATER SERVICE INTERRUPTIONS INCLUDING TIE-INS. p z m z Q I , 8. ALL BRASS FITTINGS INSTALLED IN CONJUNCTION WITH THE PROPOSED WATER LINE MUST z w LD `" z z o 12. CATCH BASINS CAST -IN-PLACE SHALL CONFORM TO THE REQUIREMENTS OF NCDOT STANDARD SPECIFICATIONS 16. EXCEPT WHERE NOTED ON THE PLANS OR DIRECTED BY OWNER, METER BOXES AND WATER METERS ARE TO BE m Q co o co w w Q w O _j o c� FOR ROADS AND STRUCTURES (LATEST EDITION) ARTICLES 840-1 THROUGH 840-3. CURB INLET CATCH BASIN REPLACED AND INSTALLED ADJACENT TO THE EXISTING METER AT ALL LOCATIONS. PROVIDE NEW WATER METERS AND BE LEAD FREE PER CURRENT COA STANDARDS. O 0 0 0 0 U IL SHALL CONFORM TO NCDOT STANDARD DETAILS 840.02 THROUGH 840.04. DROP INLETS SHALL CONFORM TO BOXES BUT USE THE SAME RADIO READING DEVICE AS IN THE EXISTING BOX. THE CONTRACTOR HAS THE OPTION OF STANDARD DETAIL 840.14. JUNCTION BOXES SHALL CONFORM TO STANDARD DETAIL 840.31. MOVING EXISTING WATER METERS TO FACILITATE INSTALLATION OF THE NEW WATER LINES, SUBJECT TO THE 9. CONTRACTOR SHALL COORDINATE & SCHEDULE ALL TIE-INS WITH THE CITY OF ASHEVILLE AUTHORIZATION BY THE ASSIGNED CITY CONSTRUCTION OBSERVER, BUT ALL COSTS ARE INCIDENTAL TO WATERLINE ENGINEERING DEPARTMENT. 13. CURB INLET FRAME, GRATE AND HOOD SHALL BE NEENAH R -3233D, PRODUCTS BY DEWEY BROS., U.S. INSTALLATION AND SHOULD BE INCLUDED IN THE UNIT COSTS PER LINEAR FOOT. PROJECT COMPLETION REQUIRES FOUNDRY OR EQUAL. DROP INLET FRAME AND GRATE SHALL BE NEENAH R -3339A OR EQUAL. FIELD INLET RECONNECTION OF ALL WATER METERS BUT ALL EXISTING WATER METERS MAY NOT BE SHOWN ON PLANS. THE OWNER COVER SHALL CONFORM TO NCDOT STANDARD DETAIL 840.04, OPENING FACING UPSTREAM. WILL FIELD LOCATE, PRIOR TO SWITCHOVER, ANY METERS NOT SHOWN ON THE PLANS. 10. WATER & SEWER LINES SHALL HAVE A 10' MINIMUM HORIZONTAL SEPARATION OR 18" VERTICAL SEPARATION WITH WATER OVER SEWER OR BOTH MUST BE CONSTRUCTED OF J 14. CONCRETE AND MASONRY SHALL MEET THE REQUIREMENTS OF APPROPRIATE SECTION OF NCDOT STANDARD 17. WATER METER RELOCATIONS ARE DESIGNATED WHERE THE EXISTING WATER METERS ARE OFF-SITE OR NOT FERROUS MATERIAL FOR A DISTANCE OF 10 EACH SIDE OF CROSSING. Q U) SPECIFICATIONS FOR ROAD AND STRUCTURES (LATEST EDITION). CONCRETE SHALL BE CLASS A OR B, 4000 ALONG THE PROPOSED WATERLINE ALIGNMENTS. WHERE METER RELOCATIONS ARE DESIGNATED, THE CONTRACTOR WILL ~ PSI MINIMUM, MEETING THE REQUIREMENTS OF SECTION 1000, CONSTRUCTED IN ACCORDANCE WITH SECTION PROVIDE NEW WATER METERS AND BOXES BUT USE THE SAME RADIO READING DEVICE AS IN THE EXISTING BOX. W 825. MASONRY SHALL MEET THE REQUIREMENTS OF SECTION 1040, CONSTRUCTED IN ACCORDANCE WITH WATER SERVICE LINE LENGTH WILL BE PAID IN THE SAME MANNER AS THE CONNECTION OF THE OTHER WATER 11. ALL FIRE HYDRANTS AND WATER METERS ARE TO BE LOCATED IN RELATIVELY FLAT AREAS Ill U l__ SECTION 830 AND/OR 834. METERS. THE CONTRACTOR MUST LOCATE THE EXISTING SERVICE LINE TO MAKE THE DOWNSTREAM CONNECTION FOR AND OUTSIDE OF PAVEMENT OR DRIVEWAYS. z Ill O THE RELOCATED METERS. --) 15. TOPS OF PROPOSED FRAMES AND GRATES SHALL BE FLUSH WITH FINISHED GRADE. Ill z 18. THE CONTRACTOR'S RESPONSIBILITY AND STANDARD OF PERFORMANCE WILL BE: NO SEDIMENT MAY LEAVE THE 12. ALL WATER METERS ARE TO BE LOCATED WITHIN 5 FEET OF THE EDGE OF PAVEMENT. Ur O 16. PRE CAST CONCRETE BOXES ARE ACCEPTABLE ALTERNATIVES FOR PROPOSED CATCH BASINS. PROJECT OR ENTER THE WATERS OF THE STATE. FOR THIS PROJECT THE WATERS OF THE STATE WILL BE DEFINED AS J INCLUDING ANY STORM DRAINAGE INLETS. 13. THE PROPOSED WATER LINE SHALL MAINTAIN 10' SEPARATION FROM ALL TREES. Q Q a. THE CONDITION OF EXISTING STORM DRAINAGE INLETS VARIES WIDELY. ALTHOUGH, THE CITY OF ASHEVILLE NOT APPLICABLE. z D • Know below. HAS STANDARD DETAILS FOR THE PROTECTION OF PIPE AND DROP INLETS, IT IS ACKNOWLEDGED THAT THE Ill what's CONTRACTOR WILL HAVE TO ADAPT THESE DETAILS FOR THE EXISTING CONDITIONS, AND THAT SILT SOCKS ARE W z 00 Call before dig. AN ACCEPTABLE EQUIVALENT FOR INLETS IN THE PAVEMENT AREAS. REGARDLESS OF THE MEASURES you UNDERTAKEN, THE CONTRACTOR'S RESPONSIBILITY WILL BE PERFORMANCE-BASED. W U) N.C. One -Call Center 19. WATER LINE TO BE INSTALLED UNDERNEATH STORM WATER CULVERTS WITH SPECIFIED VERTICAL SEPARATION, IF J Dial 811 or 1-800-632-4949 SPECIFIED COVER AND VERTICAL SEPARATIONS CANNOT BE ATTAINED WITH INSTALLATION ABOVE CULVERT UNLESS OTHERWISE STATED OR DIRECTED BY OWNER'S REPRESENTATIVE. 20. THE CONTRACTOR IS RESPONSIBLE TO MATCH RESTORED SHOULDER ELEVATIONS TO FINAL ASPHALT ELEVATIONS. SURVEY INFORMATION PROVIDED BY: SHEET OMcG • A S S O C I A T E S 55 BROAD STREET ASHEVILLE, NC 28806 PH. (828) 252-0575 NC BOARD OF EXAMINERS CORPORATE LICENSE NO. C-0459 G=002 NOTE: R/W AND PARCEL LINES & INFO FROM GIS NO. DATE BY REVISION DESCRIPTION rVfl A\/A Trn \I ATrr7)I AI nl Arlr'n TEC ,34, JL 7TL1\ VI\ I7ll ILI\II L (SEE TRENCHING DETAIL) NOTES: 1. THIS DETAIL SHALL BE USED WHERE NOTED ON THE PLANS OR ANYWHERE SEPARATION BETWEEN THE SEWER OR WATER LINE AND STREAM IS LESS THAN 30 FEET. 2. SILT FENCE IN THESE AREAS SHALL BE INSTALLED PRIOR TO BEGINNING EXCAVATION FOR THE PROPOSED LINE. 3. EXCAVATED MATERIAL SHALL BE PLACED ON SIDE OF TRENCH AWAY FROM STREAM. 4. STREAM PROTECTION AREA SHALL BE SEEDED IMMEDIATELY AFTER INSTALLATION OF PROPOSED LINE. 5. SILT FENCE SHALL BE MAINTAINED UNTIL VEGETATIVE COVER IS ESTABLISHED. STREAM BANK PROTECTION - EXCAVATION UPDATED MARCH, 2017 NOT TO SCALE NCDOT RIGHT—OF—WAY NOTES: 1. NCDOT REQUIRES ALL WATERLINES TO BE THREE (3) FEET OUTSIDE OR INSIDE OF EDGE OF PAVEMENT EXCEPT IN DESIGNATED TRANSITIONAL SECTIONS OF ALIGNMENT. a. ALL VALVES, HYDRANTS, ETC. SHALL BE PLACED BEHIND THE DITCH LINE OR AS CLOSE TO THE RIGHT OF WAY LINE AS POSSIBLE. b. ALL TRENCH REPAIRS ACROSS NCDOT ROADS SHALL BE RESURFACED TWENTY—FIVE FEET EACH SIDE OF THE TRENCH. TRENCH REPAIR AND RESURFACING SHALL BE GUARANTEED FOR A PERIOD OF ONE YEAR AFTER COMPLETION OF PROJECT. C. ALL SERVICE CONNECTIONS ACROSS NCDOT ROADS SHALL BE DONE BY DIRECTIONAL BORE METHOD ONLY. d. IN AREAS WHERE PARALLEL INSTALLATION IS REQUIRED IN ROADWAY, ROAD SHALL BE RESURFACED FULL WIDTH PER NCDOT SPECIFICATIONS e. ALL ASPHALT WORK SHALL BE IN ACCORDANCE WITH NCDOT SPECIFICATIONS AND PERFORMED BY A QMS CERTIFIED ASPHALT CONTRACTOR. LINEAR FEET OF ENCROACHMENT NCDOT ASPHALT ROADS PRIVATE GRAVEL ROADS NORTH FORK LEFT FORK #1 (SR 2469) - 120 LF PRMI - 240 LF NORTH FORK LEFT FORK #2 (SR 2469) - 30 LF 92.0 TOTAL = 150 LF TOTAL = 240 LF • � '� u' .�IIAI�. �? .+. II�iY ,!t mY 4w I�i2 � IavIit-w ��I 6" CABC COMPACTED SUBGRADE 4:1 TYPICAL GRAVEL ROAD CROSS-SECTION UPDATED MARCH, 2017 NOT TO SCALE N.C.D.O.T. STANDARD SPECIFICATION TABLE 610-5 SUPERPAVE DENSITY REQUIREMENTS SUPERPAVE MIX TYPE MINIMUM % Gmm (MAX. SPECIFIC GRAVITY) SF9.5A 90.0 S9.5X, S12.5X, 119.X, 325.OX 92.0 • DRY UNDISTURB EARTH 1 5'� NOTE: 1. STANDARD DETAIL SHOWN HEREIN AND SPECIFIED IN SECTION 61C OF THE SPECIFICATIONS ARE THE MINIMUM REQUIREMENTS SET BY N.C.D.O.T. IF EXISTING PAVEMENT IS FOUND TO EXCEED MINIMUM REQUIREMENTS, REPLACE TO MATCH EXISTING. 2. EDGES TO BE SAWED WITH A CONCRETE SAW TO A NEAT SQUARED EDGE GROOMED CLEAN OF DUST BEFORE TACK COAT IS APPLIED. 3. ALL O.S.H.A. REQUIREMENTS SHALL BE ADHERED TO FOR TRENCHING OPERATIONS. 3" SURFACE COURSE TYPE S9.53 OR S9.5C PER N.C.D.O.T. STANDARD SPECIFICATIONS STANDARD PROCTOR USE APPROPRIATE BEDDING FOR TYPE OF PIPE BEING INSTALLED 1,-0„ PIPE 1,-0„ DIAMETER 3'-0" MIN. COVER 6" LIFTS OF COMPACTED SOIL. IF EXCAVATED MATERIAL IS TO WET OR UNSUITABLE. A PROPER FILL MATERIAL WILL BE SUBSTITUTED. FILL MATERIAL WILL BE PLACED IN 6" LIFTS AT OPTIMUM MOISTURE AND COMPACTED 957 STATE OF NORTH CAROLINA DATE DESCRIPTION DEPT. OF TRANSPORTATION ROAD PAVEMENT 12/2016 N.C.D.O.T. STANDARDS DIVISION OF HIGHWAYS N.C.D.O.T. REPAIR UTILITY RALEIGH, N.C. NO DATE I BY REVISION DESCRIPTION D Q z Lu U) W v (DJ z mm >0 o �z W of Z� "z � j - Oct o o� � w zgc)� Q >= O � H z ~Vm � pp � W c7. U� > m 0 Z i W i W LL .L LLI Z N �z w z w U O Z 00 Z � Q � Z LLI (D W o U' W U) I� 0 Q 0 o Q U C) cv U4c1l o � U z w w w ~ w W¢ W w Zw x F- Z o m D Q z Lu U) W v (DJ z mm >0 o �z W of Z� "z � j - Oct o o� � w zgc)� Q >= O � H z ~Vm � pp = J I > m 0 m i W i W LL .L LLI Z N j LLJ O Z 00 Z � Q � Z LLI (D W o U' W U) Z cl) - CD w m 0 Q 0 C) Q U C) O U Li �: z w () 2 Q U � Qw 00 U Q z0 wry O� 0 Q U z SHEET G-003 ^X ' ' ' 'MAPS) SEE FEMA FIRM � B Y. Bedrick Cravel and Sand Company /' . .\ 3710070000J DATED BB. 9'9'4, P. 25-e . . . . . . . . . . /. . � 01.06.2010 . . . . . . . . . . . . . . . . . . . . . . . . . � . . o.. ............. PERMANENT MAINTENANCE \ CONSTRUCT TEMPORARY ......... ... ACCESS RAMP ONTO CORRIDOR 20' WIDE WITHIN - -_ _ _ _ _ _ _ _ _' _ _ _ � _ _ _ _ _ FLOOD PLAIN WETLAND AREAS � � - - - � - - - - - - - - � - - - - - - - - - - - \ WETLAND A�(. .� . . v. \ . CONSTRUCT PORTABLE, \ TEMPORARY ACCESS ACROSS. 24+00 RIVER CHANNEL FOR Robert2: Burnett M CONSTRUCTION TRAFFIC AB. 122e, P. 99 / O (CHANNEL FLOW PRIMARILY CONTROLLED BY RESERVOIR DISCHARGE) .... ..� RY / PRIMA APPROX. LIMITS OF 10 1• • • • YEAR FLOOD (AS SHO BY FLOOD RATE INSURAN t ' 23+00 MAPS) SEE FEMA FIR CONf \ \ 24 /Fork \ \� North B. V. Hedrick Gravel and Sand Company D.B. 774, P. 256 CONNECTION TO EXISTING 36" STEEL WATER LINE _ 4 _ _ ' �E �0 UP GVH 10+00 TO NORTH ROARK D AND BLACK MOUNTAIN EXPAND WIDTH OF ------------------------------------ P R M I PRIMARY ------ ----------------------- ENTRANCE Presbyterian Reformed Ministries Int., Inc. D.B. 3321, P. 716 0 371 0070000JDATED 1 01.06.2010 INSTALL WATER LINE BELOW CHANNEL BOTTOM PROPOSED WETLAND \ \, TRANSMISSION MAIN 5 �,kPERMANENT MAINTENANCE �oCORRIDOR 24' WIDE �� \%o��% /CONSTRUCT TEMPORARY ACCESS \ C -A 02 , V \ ..... ACROSS SIDE CHANNEL FOR / . ; % ,� CONSTRUCTION TRAFFIC + O� WETLAND E / �% 0 \ PERMANENT EASEMENT i o CTI ON TO EXISTING � / Presbyterian Reformed \ i — X11 WETLAND F P WATER LINE \ �� / 0 Di B.t3321,I P. Inc. _ _ _ _ _ _ — — \ 0,� 1 , ` CITY OF ASHEVILLE PROPERTY v / WETLAND D, C-101 - �` o\\\ � / ' � \' UT -1 N FORK SWANNANOA WETLAND C I , , , / PERMANENT MAINTENANCE RIVER L /S UP 00 READ / // �'' �' �' .\ - , / \ \ \ ` \ CORRIDOR 24' WIDE � NOg'f11 f0ft / WETLAND B } \ \ , PROPOSED PRMI IMPROVEMENTS �, / N (BY OTHERS OUTSIDE EASEMENTS) G , - \ — G P , , / F101 i / Presbyterian Reformed Ministries Int., Inc. 71 I I I I J J \\ D.B. 3321, P. 716 �=- REPLACE ENTRANCE GATE - �% \ \ , - 1 ' ' ' -'- ' - II '00 / i '1 I I NEW METER VAULT - TEMPORARY EASEMENT 4FOR ROADWORK Presbyterian Reformed Ministries Int., Inc. D.B. 3321, P. 716 MAINTAIN RIVER GAUGING STATION (ABANDONED) ---------------------- \ PERMANENT MAINTENANCE \ CORRIDOR 20' WIDE ----- ---- P WITHIN WETLAND AREAS I� ----------- o — i "MO Presbyterian Reformed Ministries Int., Inc. D.B. 3321, P. 716 i NOTE: 100 -YEAR FLOOD LINE FROM HIGH COUNTRY SURVEYING NO. I DATE I BY I REVISION DESCRIPTION NOR \ / �w°l� TO NORTH FORK / PLAN WATER TREATMENT 0 Wz� PLANT ENTRANCE / L Q) 0) i � / z w 50 0 25 50 100 150 / U w o / r, H GRAPHIC SCALE i INCH - 50 FEET CONNECTION TO EXISTING N Uz00cv > W 36" STEEL WATER LINE L �o /• : - W ^X 0Y W -SZ OZ o / 00 00 N CONNECTION TO EXISTING � U z p 24" DIP WATER LINE ...........\ .. %' Z co (1) w APPROX. LIMITS OF 100 �W _ p . . . . _/ . . . . . . .. \ YEAR FLOOD (AS SHOWN BY O O� • • • • . • • . • • •I'/'• FLOOD RATE INSURANCE ^X ' ' ' 'MAPS) SEE FEMA FIRM � B Y. Bedrick Cravel and Sand Company /' . .\ 3710070000J DATED BB. 9'9'4, P. 25-e . . . . . . . . . . /. . � 01.06.2010 . . . . . . . . . . . . . . . . . . . . . . . . . � . . o.. ............. PERMANENT MAINTENANCE \ CONSTRUCT TEMPORARY ......... ... ACCESS RAMP ONTO CORRIDOR 20' WIDE WITHIN - -_ _ _ _ _ _ _ _ _' _ _ _ � _ _ _ _ _ FLOOD PLAIN WETLAND AREAS � � - - - � - - - - - - - - � - - - - - - - - - - - \ WETLAND A�(. .� . . v. \ . CONSTRUCT PORTABLE, \ TEMPORARY ACCESS ACROSS. 24+00 RIVER CHANNEL FOR Robert2: Burnett M CONSTRUCTION TRAFFIC AB. 122e, P. 99 / O (CHANNEL FLOW PRIMARILY CONTROLLED BY RESERVOIR DISCHARGE) .... ..� RY / PRIMA APPROX. LIMITS OF 10 1• • • • YEAR FLOOD (AS SHO BY FLOOD RATE INSURAN t ' 23+00 MAPS) SEE FEMA FIR CONf \ \ 24 /Fork \ \� North B. V. Hedrick Gravel and Sand Company D.B. 774, P. 256 CONNECTION TO EXISTING 36" STEEL WATER LINE _ 4 _ _ ' �E �0 UP GVH 10+00 TO NORTH ROARK D AND BLACK MOUNTAIN EXPAND WIDTH OF ------------------------------------ P R M I PRIMARY ------ ----------------------- ENTRANCE Presbyterian Reformed Ministries Int., Inc. D.B. 3321, P. 716 0 371 0070000JDATED 1 01.06.2010 INSTALL WATER LINE BELOW CHANNEL BOTTOM PROPOSED WETLAND \ \, TRANSMISSION MAIN 5 �,kPERMANENT MAINTENANCE �oCORRIDOR 24' WIDE �� \%o��% /CONSTRUCT TEMPORARY ACCESS \ C -A 02 , V \ ..... ACROSS SIDE CHANNEL FOR / . ; % ,� CONSTRUCTION TRAFFIC + O� WETLAND E / �% 0 \ PERMANENT EASEMENT i o CTI ON TO EXISTING � / Presbyterian Reformed \ i — X11 WETLAND F P WATER LINE \ �� / 0 Di B.t3321,I P. Inc. _ _ _ _ _ _ — — \ 0,� 1 , ` CITY OF ASHEVILLE PROPERTY v / WETLAND D, C-101 - �` o\\\ � / ' � \' UT -1 N FORK SWANNANOA WETLAND C I , , , / PERMANENT MAINTENANCE RIVER L /S UP 00 READ / // �'' �' �' .\ - , / \ \ \ ` \ CORRIDOR 24' WIDE � NOg'f11 f0ft / WETLAND B } \ \ , PROPOSED PRMI IMPROVEMENTS �, / N (BY OTHERS OUTSIDE EASEMENTS) G , - \ — G P , , / F101 i / Presbyterian Reformed Ministries Int., Inc. 71 I I I I J J \\ D.B. 3321, P. 716 �=- REPLACE ENTRANCE GATE - �% \ \ , - 1 ' ' ' -'- ' - II '00 / i '1 I I NEW METER VAULT - TEMPORARY EASEMENT 4FOR ROADWORK Presbyterian Reformed Ministries Int., Inc. D.B. 3321, P. 716 MAINTAIN RIVER GAUGING STATION (ABANDONED) ---------------------- \ PERMANENT MAINTENANCE \ CORRIDOR 20' WIDE ----- ---- P WITHIN WETLAND AREAS I� ----------- o — i "MO Presbyterian Reformed Ministries Int., Inc. D.B. 3321, P. 716 i NOTE: 100 -YEAR FLOOD LINE FROM HIGH COUNTRY SURVEYING NO. I DATE I BY I REVISION DESCRIPTION NOR \ / Q a z Lu cin W v U) J z mm�o �z W = z tn � Oct 0 oLL. w z Z O V m �w°l� U� 0 Wz� w L Q) 0) i � o z w U w r, H J N Uz00cv > W 00 N W o W } 0Y W -SZ OZ o ' w v1 00 00 N 0 � U z p C� co Z co (1) w �W W Q w¢ O w� w Z o x W� Q a z Lu cin W v U) J z mm�o �z W = z tn � Oct 0 oLL. w z Z O V m L -j X zLLL J00 Z L QL Z L �J (� 0 - SHEET L Q) 0) i � o -J >Y � M J > W >IL W N W o W } 0Y W -SZ OZ 0 LLI C� p C� co Z co (1) w Q W Q W O L -j X zLLL J00 Z L QL Z L �J (� 0 - SHEET 3 0 Y 0 LL M O O m Q PLAN \ \ / RBS 5/8 DIST i CA v 30 0 15 30 60 90 A i N:709 111.72 T � w E: 1004772.91 EL: 2430.13 1. PHASE I WATER LINE IMPROVEMENTS MUST BE COMPLETED AND PLACED INTO SERVICE PRIOR TO BEGINNING WORK ON PHASE II. W 1111111 GRAPHIC SCALE 1 INCH = 30 FEET C-104 \ ' /' � 2. FOR THE CONNECTION BETWEEN PHASE 1 AND PHASE 2 WATER LINE SECTIONS THE CONTRACTOR SHALL INSTALL THE PROPOSED • Z -- [� \ \ / 36"06"x6" TEE, A 36" BUTTERFLY VALVE, 6" GATE VALVE, 10 -FOOT LONG 36" SECTION OF PIPE, 36" MJ PLUG TAPPED 4" FOR FILLING i UP �' �W THE LINE AND APPROPRIATE RESTRAINT AND BLOCKING. ONCE THE ' / \ \gON j 36" LINE IS INSTALLED TO THIS LOCATION FROM THE DOWNSTREAM 100 \ / SECTION THE CONTRACTOR SHALL FILL THE 36" LINE DOWNSTREAM TO THE CONNECTION POINT TO THE EXISTING 36" WATER LINE AND o PROPOSED CONNECT TO �' / // SIGN ice/ yEFT PROPOSED SILT FENCE \ \ \ / \ K PRESSURE TEST THE LINE. THE LINE SHALL BE PRESSURE TESTED ~ EXISTING 24" WATER _ LINE WITH V/ \ �Oy �� PVC STUB 1 1/4 /NOILTO FOR #5 RBF (DOUBLE ROW) 0 v AGAINST THE BUTTERFLY VALVES PRIOR TO MAKING ANY FINAL U 24"X24"X24" TEE, 2-24" // ,' l%w / �_ o CONNECTIONS. UPON COMPLETION OF THE PRESSURE TEST THE LINE SHALL BE DISINFECTED AND A CLEAR WATER SAMPLE OBTAINED PRIOR 00 BUTTERFLY VALVES AND BOXES _ / TO MAKING THE FINAL CONNECTIONS TO THE EXISTING 36" AND 24" x °" / P�Cp Gp /' WETLAND B _� � 2 �`i WATER LINES AND THE PRMI MASTER METER CONNECTION. O PROPOSED CONNECT TO s / A 2g \ /\NE ��W R TOP 6" DIP , - / /\ 2S� WP�ER EL: 2430.41' TOP 6" DIP / / / \ 3. ALL PIPE AND FITTINGS SHALL BE RESTRAINED PER COA STANDARD DETAILS AND APPROVED MANUFACTURER'S PARTS LIST. o 00 EXISTING 36" WATER LINE WITH / �/ a �. s,,eMERw��� ,-� ® UNDERGROUND EL: 2429.65' / I N FIBER OPTIC SIGN C-105 p i� a U Z " f0 ff f0 36 x36 x36 TEE, 2-36 36" W/L MH 'g6 (ER / �� WP PROPOSED LIMITS A-_ - \ TW -6 DIP BUTTERFLY VALVES AND BOXES TOP EL: 2432.75' �'' Jp(EG/� _ UnL1 x -- - EL: 2429.9 �to _ r ,- E`�� OF DISTURBANCE er -� l -�' -= '-'�'\ �'' 243 Z a -_ %, - - - _ _ / MAX WIDTH 45' Rtiv ;- , �,=�%, �— SIGN roa i — / ii''� i o� - NF /��_ �� '\� �� W # F / SU�p'I'°a A ��GF +� � kO��/ UP GV �T�� 2" OTIPF -' PROPOSED 36" — — — — BLUE PAINT / X N: 709420. z' y\ _ _ E 10443.4 TRANSMISSION MAINS SIG /0010 STACKED // I BOULDER /__� i BOULDER WALL � i \'r O _ _ /� / / �� y�S I i � \ O wa "I — » /� iC N ���� -' PROPOSED IN–LINE 36 �` –oe\� ;;=_ — — — — PrAaiJT \\ BOREAPPR/ \ ` \ _ _ '� %' — // NF1-I+L ° q BUTTERFLY VALVE (TIE \ `_ ;;– /", / , I-i�- 4-1 I I F 1 I I % BT� � C \�\�� �. • no _ kiEM con vZ SIGI11�__ (-12435 CONNECTION PHASE 1��r/�} \ / �l 1 / i / UNDERGROUND I FIBER OPTIC SIGN PROPOSED LIMITS OF NCDOT OVERALAY PROPOSED 36 _ _ -- 1\ ?' \ / \ / �J i� / rC2440rI� I�rt 11 TC C' R\ & PHASE 2, SEE NOTE MAP ��F o 12" HEM _________ __ - x Ropy \ °L 81A ��R�`\\S\\\ __ ) – ���_ 16" = �/' 10�D� �/ PROPOSED LIMITS ! �� .. �o� \\ \\ _' = I _ _ C' /'� ' eH ` %OF DISTURBANCE / y �ff�a.f., SRI ti TRANSMISSION MAIN _-- i i R /'/ 1 li �� 12 MAP 40" BCH �FrEMLQC�" B \ �� / _ / 1 �/, 1�// �� / 2x2 SEPTIC ;� op\ ` J B2 = - "'�'� ;, �„ 1 �,', , , /��/ J TANK p p 14" POPA eef�eM� e , s. • ., w s \ \ \ PROPOSED3/�efEc�4%GRPv BS\\ // � / j r-�c----rX__x— �- ",',`1 �T� -`---- \ p „\ " » »�V_ / // 7 36 x36 x24 TEE �;\\ �` `\ -----------,6" R P G ZA ., 11+ SG POP MAP \ �\ \� / _ \ / �16'i8� BORA/ { p / / / /12" BIR' '100' HHM\ 2450.1' HEM 8 % `/ I v r-• 4a r .'.� 4 II I 4 / CONTRACTOR AR / R / s \\ NOTES: s"; ,- -- • '�" ` __ ,, \ HEMLOCK 28" 1 °W /i �i 11 = — / / O ��-' ------�-' PROPOSED l ,yam 24" MAP o k 1. 1 I \ + en 12" CMP ��� ,: BENDS SHOWN ARE REPRESENTATIVE BASED ON SURFACE CAD MODELING OF GROUND. ACTUAL BENDS REQUIRED DEGREE MAXIMUM) MAY t{.� i "� •��,Y`'►rA 4Y 2452.1' i BLASTED EXCAVATED \\ LUE P 243.63 `- / �� � — ,— — ® \ — �'��------ EXISTING (45 DIFFER IN ANGLES OR NUMBERS. uw' ,s" MAP ROCK SLOPE (SEE \\\` R P�1i/�, i I �,� K C.O. �c' 1\) IIII PRE B3A N I 24" HEM O 2. RESTORE TOPOGRAPHY WITHIN 100 -YEAR FLOOD LINES TO MATCH EXISTING s �\ DRAWING C-104) `�\���\� _ ® –' X /POPLAR/12" / ' - ��� _ _ „s" CHR WM O SURFACE. f ORE 3eODUMPSTER / �/ /" �.--- -MARK 5 BUFFER AROUND 3. RESTORE TOPOGRAPHY OUTSIDE 100 -YEAR FLOOD TO NATURAL APPEARANCE <��` \\��\ _! �, " GAUGING STATION W/ 2FRi �___� PROPOSED 6 4. AND SLOPES. RETURN RELOCATED SURFACE BOULDERS TO WORK AREA BUT NOT DIRECTLY z — 46 _� _ — `�\ ORANGE CONSTRUCTION OVER PIPE. EXCAVATED BOULDERS TO BE REMOVED FROM SITE. FINAL J WATER CONNECTION i i i FENCING AND HAY BALES PLACEMENT AND ORIENTATION TO BE APPROVED BY ENGINEER. O Q Presbyterian Reformed ��I i I 5. I P EXCESS CUT TO BE REMOVED AND DISPOSED OF OFF-SITE. CONTRACTOR Ministries Int., Inc. -''� POR H i D.B. 3321, P. 718 I R cF SHALL NOT PLACE STOCKPILE ON-SITE. 12" HEM � v , V 12 U (D GL � \\ 1 STORY FRAME WITH �y'� LJJ m O 00)BASEMENT z NO. DATE BY REVISION DESCRIPTION Lu Oz=� 2472 PROFILE 2472 LL z cn z 2469 SCALE: HORIZ. 1 "= 30' 2469 0 O 2466 VERT. 1"= 10' 2466 O Lo L` Lu 2463 PHASE 1 SHALL BE COMPLETED BEFORE MAY 15, 2019 2463 z U) O 2460 (SEE SPECIAL CONDITIONS OF PRMI EASEMENT) 2460 2 Cn 2457 2457 z O PROPOSED () 2454 PROPOSED VERTICAL 2454 z 2451 2451 PROPOSED 36" HORIZONTAL 11.25 BEND D PROPOSED TRANSMISSION MAIN 11.25° BEND BOORER134A, AL PROPOSED 2448 2448 HORIZONTAL FINISH GRADE 5.5' PROPOSED 2445 2445 22.50° BEND ANGLED PROPOSED STORM DRAIN PROPOSED 36"x36"x6" TEE, (0 o = 2442 2442 PROPOSED 22.50° BEND 6" GATE VALVE AND BOX, BORE B2A, APPROXIMATE 100–YEAR o } Lu w o o 2439 2439 HORIZONTAL TAUGER REFUSAL 8.3' 6" WATER CONNECTION FLOOD ELEVATION Q z o In w w z 2436 2436 Q z m 2433 45° BEND EXISTING GROUND PROPOSED ^2" 2433 z iii c� o 0z o mp Q w Q w o 1CP VERTICAL 15" HDPE 2430 2430 D U U 11.250 BEND 2427 Re 2424 2424 –� 2421 2421 2418 2418 W J PROPOSED PROPOSED W 2415 PROPOSED ANGLED HORIZONTAL 2415 z LL 1-1 2412 2412 36"x36"x24" TEE 45° BEND 11.25° BEND J 2409 APPROXIMATE LOCATION OF 2409 W EXISTING 24" DIP BELOW EXISTING PROPOSED 36" ff PROPOSED IN–LINE 36 , 0 ~ 2406 2406 cn 36" STEEL PIPE (NO CONNECTION TRANSMISSION MAIN BUTTERFLY VALVE (TIE z (n Q z 2403 X TO 24" AT THIS POINT) CONNECTION PHASE 1 2403 2400 O W w m & PHASE 2, SEE NOTE) 2400 > J 2397 "win OII­_ J M 2394 U w N 2391 2394 2391 Z � J 2388OU w 2388 - j w 2385 2385 SHEET p n M J 2382 2382 NO z (0 w FOR BID PURPOSES] C=l 01 2379 2379 p Ln X � ofX(o=) 0-WMm 10+00 10+20 10+80 11+40 12+00 12+60 13+20 13+80 14+40 15+00 15+60 16+00 m U PLAN 30 0 15 30 60 90 �� / \ 100 YEAR CITY OF ASHEVILLE FLOODPLAIN PROPERTY GRAPHIC SCALE 1 INCH = 30 FEET � � PROPOSED LIMITS PROPOSED SILT FENCE OF DISTURBANCE \'oBF ��+i (DOUBLE ROW) MAX WIDTH 45 '. \ jy>J _; ,� y Prul., rlen Reformed — — — — — Wnietrlee Int, Inc. — D. B. 3921, P. 718 :^ i i — Z / WETLAND E�2� j,� i oo - WETLAND D 2425 — - \/ \\� DL= WETLAND C /� / / / __ k y r� - 1 —PROPOSED 42 �j - TRANSMISSION MAIN moi% � �1, \ / ,, + // /�-_ --_ - _ J�_, �_� _�� � \ \\\ 00 c) r� �4-` / '\�USE TEMPORARY PERMANENT MAINTENANCE z \__�/ \ \--- ,- _ ?___= STREAM BYPASS IF T ^ ��� 6" NECESSARY. SEE CORRIDOR 24 WIDE I11 � 1 I%�/�� // — —� _-- _ �/ �� ���//// ���5' ��/ �� 12" HEM \ r �' / �/ k\� / - --"-SHEET C-106 oir ,D // _ / N 6" HDPE ,� ,,=% �, M, ��P-__ p 12" "PERMANENT MAINTENANCE L---���_----/I �' ' (BY OTHERS )X '� / _ j� 4" PERF. HDPE ,/ CORRIDOR 20 WIDE UNDERDRAIN a (BY OTHERS) WITHIN WETLAND AREAS 6'x6'x5' 12" HEM / p 12 /) M_ STORMWATER RETENTION / / UNUtKUKHIN ULTIPLE / // — — �_ 1 BOX FOR BASIN Bt -10" SWD V — / / / /� — — — °� �- 4 a — ) ````` 10" HEM f-� Z 15X10- — / // / _ _ (BY OTHERS 14" HEM (BY OTHERS) 4'v� 18" HEM � — 9.�p. L s'o 20' HEM p — 14" HEM �? 9s� 12� Fil`M� 4 18' M p 1 'HEM N( 09868.97 24' HIK�24" HEMrm S 14" HEM '1 i / 14" HEM E:1005185.47 ai -�—� PROPOSED LIMITS p 16" BGM� T __ EL: 2447.69 ' — —32" HE —L2 A� p 36' MAP I 16" HE�fvl'-_�` W p 10" BGM 24" HEM + Y t-I�_ G' 28" LCT DECK -18" HDPE 12� Pl�fd� n /� \ / 18" POP ., \\ - — _ — I I �' SHELTER G.I. B-1 / _ 1 /-/ OF DISTURBANCE 2g" LCT / t (BY OTHERS) 12" HEM Zi MAX WIDTH 45 ) �,2 HEM �� 12 CHR \ (BY OTHERS 12" HEM / / 18" HEM p 14" MAP CONTRACTOR NOTES: \\ 1. BENDS SHOWN ARE REPRESENTATIVE BASED ON SURFACE CAD MODELING OF elm 24" HEM 12" HEM 10" HEM 20" BIR q�\ C? 12" HEM �� - 28" HEM A-np * �\ EXISTING GROUND. ACTUAL BENDS REQUIRED (45 DEGREE MAXIMUM) MAY p 18" WHO 36" BCH 10" CHO 14' HEM 12 HEM ---____ ""��,,�- ® 14" BIR p 24� HEM 10' SWD 12' MAP , DIFFER IN ANGLES OR NUMBERS. / 4�------ 14" ASH/ 7, j I 24" MAP p 14" HEM p % i \\`\? �� ___ , ,, . _„ ... _ 2. RESTORE TOPOGRAPHY WITHIN 100 -YEAR FLOOD LINES TO MATCH EXISTING ""'" SURFACE. 1. NOTES:3.OF EXISTING UTILITIES AS SHOWN ARE APPROXIMATE ONLY. EXACT LOCATIONS ARE TO BE VERIFIED IN THE 3. RESTORE TOPOGRAPHY OUTSIDE 100 -YEAR FLOOD TO NATURAL APPEARANCE FIELD BY THE CONTRACTOR. AND SLOPES. 2. CONTRACTOR SHALL REMOVE AND REPLACE ROADWAY SIGNS AND MAILBOXES AS NECESSARY TO INSTALL PROPOSED 4. RETURN RELOCATED BOULDERS TO WORK AREA BUT NOT DIRECTLY OVER PIPE. UTILITY LINE. CONTRACTOR SHALL COORDINATE SIGN REMOVAL AND REPLACEMENT WITH THE NCDOT. FINAL PLACEMENT AND ORIENTATION MAY VARY. 3. CONTRACTOR SHALL COORDINATE WORK IN THE PROXIMITY OF UTILITY POLES WITH APPROPRIATE UTILITY COMPANIES. 4. CONTRACTOR SHALL PLACE A 2" LAYER OF SAND ON ALL ASPHALT OR CONCRETE SURFACES PRIOR TO PLACING EXCAVATED MATERIAL. 5. CONTRACTOR SHALL CONTACT ALL UTILITY PROVIDERS CONCERNING EXACT LOCATION OF EXISTING LINES PRIOR TO CONSTRUCTION. IF EXISTING UTILITY CABLES ARE ENCOUNTERED IN CONFLICT WITH PROPOSED UTILITY LINE, CONTRACTOR SHALL STRIP OUT EXISTING CABLES, INSTALL PROPOSED UTILITY LINE, & RE -INSTALL EXISTING UTILITY CABLES. 6. ALL RIGHT OF WAY INFORMATION PROVIDED BY THE NORTH CAROLINA DEPARTMENT OF TRANSPORTATION. 7. ALL UTILITY LINE INSTALLATIONS SHALL BE A MINIMUM OF 3' OFF THE EDGE OF PAVEMENT UNLESS SHORING MEASURES APPROVED BY NCDOT AND THE ENGINEER ARE UTILIZED. NO. DATE BY REVISION DESCRIPTION w U w H Z o 00 00 00 CIA w Z Q Z pa �►� V Q r Q w UJ 0 Q LL m m � z z J Q L.L U O z O- Z 2472 PROFILE SCALE: HORIZ. 1 "= 30' VERT. 1 "= 10' 2472 LL z cn Q o< co 0o L - 2 O Cn z O W � O z D 2469 2469 2466 2466 2463 2463 2460 2460 2457 2457 2454 2454 2451 2451 2448 PROPOSED ANGLED 2448 L 2445 11.25 ELBOW 2445 2442 2442 � o � °O CD � N }> W W O co w >} Z o o z m z z ui o o to m o Fn z o > p Q w Q w 2439 EXISTING GROUND -\ PROPOSED 2439 2436 PROPOSED PROPOSED VERTICAL VERTICAL 11.25 ELBOW 11.25 ELBOW VERTICAL 11.25 ELBOW PROPOSED VERTICAL 11.25 ELBOW 2436 2433 2433 2430 2430 2427 2427 2424 2424 2421 2421 PROPOSED VERTICAL LLJ LLI J 2418 2418 2415 11.25 ELBOW PROPOSED 2415 z LL O J2412 D LLI 0 ' >Q z J PROPOSED VERTICAL 11.25 ELBOW 2409 PROPOSED 42" TRANSMISSION MAIN VERTICAL 11.25 ELBOW 2409 2406 2406 2403 2403 2400 2400 2397 2397 2394 2394 2391 2391 2388 2388 2385 23$5 SHEET 2382 2382 2379 2379 2 16+00 16+20 16+80 17+40 18+00 18+60 19+20 19+80 20+4 -?0+50 0 0 0 Q 0 Y Q) N 0 Z) PLAN � � W o 30 o is 30 60 yo _ PROPOSED CONNECT TO W Z 70 'AFF EXISTING 24" WATER LINE WITH ��ti� GRAPHIC SCALE I INCH = 30 FEET `� 24"X24"X24" TEE, 2-24" I Z 100 YEAR � `� , \ -- BUTTERFLY VALVES AND BOXES I � \� \ \ \ I x � w FLOODPLAIN \ . \ \ � ` T__ _ `\`\�\` PROPOSED �� \. s \ �� PROPOSED \\\ CONNECT TO I� TEMPORARY CULVERT'.-. . `s �•\\ �\ X�3 I " 36 E WITH 00 U USE TEMPORARY x ` ��� `� 361 x316 x36 \\� I EE, 2 STREAM BYPASS. P,� ��� ` BUTTERFLY VALVES AND BOXES a O SEE SHEET C-106 I /�_ CONSTRUCT TEMPORARY �';• ACCESS RAMP --• ; � � ONTO FLOOD , �� PROPOSED 36 ,� o tl� OF ASHEVILLE PLAIN (REMOVE TRANSMISSION MAINNCITY AND RESTORE)PROPERTY�510 j.. .\._.�. I".°o'er:`. " �" ...., `\ P. ;xoo �� WETLAND A PROPOSED LIMITS ........ �. OF DISTURBANCE :.:.:.....:.:.:.:.:.:.:..... I- �" 24��` I� . . . . . . . . � � \ . r. . . . 3n .. �_ PROPOSED �y w v] a / \ \ �. MAX WIDTH 45 ..... .. . . . . . . . . . . . . . . ...... /. o I. I TO NORTH FORK ���. I. . . . WATER TREATMENT ........... '�' 42"x36" REDUCER ,I" \ \ ��\�► » » ' I PLANT ENTRANCE W W w -�i PROPOSED SILT FENCE 36 x36 x24 TEE ".".".". / PERMANENT MAINTENANCE /C. �� (DOUBLE ROW), TYP. �`....... PROPOSED 42" ..... ....." `�." .". ."."l If ............. .. . \ , \✓A°: .. 1 CORRIDOR 20' WIDE I \ TRANSMISSION MAIN ..... ..... ..... ..... ... SEEP COLLARS �....� . �o .. .. WITHIN WETLAND AREAS i;: I . . . . .ANTI REQUIRED THROUGH `� - ............ •.••" PROPOSED Z /�i W I i \ !........... PROPOSED FIRE WETLAND AREA s.. xo = TE MPORARY CULVERT'.'.'.'. ." Jl �....... .. .... . . . .. .. . .. ... ... . :I. UT -1 N FORK \\I a \ \ I v_\ SWANNANOA I ,1 1. �� I \ �\ HYDRANT ASSEMBLY . . . . . . . . . . . . ......................... SEE SHEET C-108 0 . . . . . . . . . . .�i". �� 11 �� == 242 ... ..... .ter 'ri • �ire •��ir- • �r i� •��• it it- \ ?6. .. • .............. .... .... . �\I.".". . . �; I \. ;tik�1 �� \� R RIVER 1\�I �`� ." \` ,�� . .\ N'� - N�Sr� ��?6 \. . . . . . . . . . . . . . . . . �a� ............... C-109 `: :� P �...... — - - T .T. Tt fr. `2427:-;�- ,.;. Tr .�. . ". •.". �' �j� � �� '�/ '–' SEE SHEET C-109 FOR \. x O �, __ \\ \ �\ // . V . . . . N". % c► 1 ................ /. 100 YEAR ADDITIONAL E 8c S MEASURES PROPOSED LIMITS \......"... \\ ��\II \\ �........"�\\"'' . ".".� ���rFLOODPLAIN OF DISTURBANCE \...... WE AND G \ \,\\ ......".... \ \.� �I. 2g ".". ..."."."."."."."."."."."..."."."."....".. " Q \� o \ _ _ _ \ .. ..."......"." ' ."."."."."... .. . .. ... . . . . . . . .. CONTRACTOR NOTES: 1. BENDS SHOWN ARE REPRESENTATIVE BASED ON SURFACE CAD MODELING OF - , EXISTING GROUND. ACTUAL BENDS REQUIRED (45 DEGREE MAXIMUM) MAY . . . . . . . . . . . . / - . . . . . . DIFFER IN ANGLES OR NUMBERS. Q Q _ \ \ �. •.•... . . . . . . . . . . . . . . WETLAND F ,� •��. \ �" io. .. �.\. ..I 1. ..%�. 2. RESTORE TOPOGRAPHY WITHIN 100 -YEAR FLOOD LINES TO MATCH EXISTING .. ............. SURFACE. r i z NOTES: 1. LOCATIONS OF EXISTING UTILITIES AS SHOWN ARE APPROXIMATE ONLY. EXACT LOCATIONS ARE TO BE VERIFIED IN THE \ !\\\�� FIELD BY THE CONTRACTOR. \\�--' \ ��:�� �I r-- '� ; h PERMANENT MAINTENANCE 3. RESTORE TOPOGRAPHY OUTSIDE 100 -YEAR FLOOD TO NATURAL APPEARANCE PROPOSED TEMPORARY STREAM AND SLOPES. Q J 2. CONTRACTOR SHALL REMOVE AND REPLACE ROADWAY SIGNS AND MAILBOXES AS NECESSARY TO INSTALL PROPOSED \- • • •� \ �` \\ \/ . . . . . • - . CORRIDOR 20' WIDE ' ' ' ' CROSSING WITH REMOVABLE MATS 4. RETURN RELOCATED BOULDERS TO WORK AREA BUT NOT DIRECTLY OVER PIPE. nQ// LL UTILITY LINE. CONTRACTOR SHALL COORDINATE • � SIGN REMOVAL AND REPLACEMENT WITH THE NCDOT. " ?\ _ -' •� _ • _ _ • _ • - _ - - . . ............... WITHIN WETLAND AREAS (TYP.). MATS MAY BE NEEDED FINAL PLACEMENT AND ORIENTATION MAY VARY. Q 3. CONTRACTOR SHALL COORDINATE WORK IN 4. CONTRACTOR SHALL PLACE A 2" LAYER THE PROXIMITY OF UTILITY POLES WITH APPROPRIATE UTILITY COMPANIES OF SAND ON ALL ASPHALT OR CONCRETE SURFACES PRIOR TO PLACING I �� �. THROUGHOUT WETLAND AREA WHEN Lu u) U • " �Y \ 2R3 EXCAVATED MATERIAL. \ �� \ ° — I•"- . . i PROPOSED CHANNEL CROSSING WET AND SOFT SOILS ARE (� J _ 5. CONTRACTOR SHALL CONTACT ALL UTILITY PROVIDERS CONCERNING EXACT LOCATION OF EXISTING LINES PRIOR TO " . ENCOUNTERED. SEE NOTES AND � Q CONSTRUCTION. IF EXISTING UTILITY CABLES ARE ENCOUNTERED IN CONFLICT WITH PROPOSED UTILITY LINE, CONTRACTOR L WITH ENCASEMENT SEE SHEET ( J SHALL STRIP OUT EXISTING CABLES, INSTALL PROPOSED UTILITY LINE, & RE -INSTALL EXISTING UTILITY CABLES. — — — 6. ALL RIGHT OF WAY INFORMATION PROVIDED BY THE NORTH CAROLINA DEPARTMENT OF TRANSPORTATION. — — — — — — — — — C-106 FOR DETAILS) DETAILS SHEETS C-106 & C-107. 7. ALL UTILITY LINE INSTALLATIONS SHALL BE A MINIMUM OF 3' OFF THE EDGE OF PAVEMENT UNLESS SHORING MEASURES SEE SHEET C-1 O6 FOR m O APPROVED BY NCDOT AND THE ENGINEER ARE UTILIZED. m z ADDITIONAL E & S MEASURES NO. DATE BY REVISION DESCRIPTION W L.L O z -:j � 2472 PROFILE 2472 '� z Cn z 2469 SCALE: HORIZ. 1 "= 30' 2469 Q a< O 2466 VERT. 1 "= 10' 2466 (n LL W 2463 2463 � — 2i O � 2460 2460 C� 2457 2457 z O 2454 PROPOSED CONNECT TO 2454 Q U z 2451 2451 EXISTING 24" WATER LINE WITH D 24"x24"x24" TEE, 2-24" V m 2448 BUTTERFLY VALVES AND BOXES NORTH FORK 2448 LEFT FORK ROAD 2445 2445 PROPOSED FIRE 2442 HYDRANT ASSEMBLY PROPOSED PROPOSED PROPOSED PROPOSED 2442 co o 2439 2439 `_ HORIZONTAL VERTICAL ANGLED VERTICAL o A PROPOSED 22.50 ELBOW 22.50 ELBOW 22.50 ELBOW 22.50 ELBOW 773 n 0 } m m > > �° 2436 VERTICAL 2436 D } 0 Z o 2433 11.25 ELBOW PROPOSED EXISTING GROUND 2433 w o o VERTICAL _ 18" MIN. _ PROPOSED 0 < < o 2430 22.50 ELBOW CLEARANCE VERTICAL 2430 2427 22.50 ELBOW 2427 2424 PROPOSED 36" 2424 2421 TRANSMISSION MAIN 2421 2418 401A M/11 PROPOSED 2418 J AA PROPOSED 36x36x24 TEE W — 2415 PROPOSEDX11 ANGLED 2415 z 2412 2412 HORIZONTAL 22.50 ELBOW PROPOSED J O � 45 ELBOW PROPOSED 42" 42"x36" REDUCER 2409 PROPOSED TRANSMISSION MAIN 2409 PROPOSED VERTICAL O 2406 2406 VERTICAL 22.50 ELBOW V) z Q 2403 22.50 ELBOW X 2403 Q 2400 2400 � m w„ J PROPOSED CHANNEL CROSSING z p 2397 WITH ENCASEMENT (SEE SHEET n 2397 2394 C-103 FOR DETAILS Of N Q w 2394 2391 2391 cn z� w -i 2388 2388 O ~ < w ft 2385 p tn � }- 2385 SHEET 2382 w x� p Z co 2382 2379 Xw- p (n 2379 _ �XC0D EL w nm 20+50 21+00 21+60 22+20 22+80 23+40 24+00 24+60 25+20 25+80 26+40 27+00 27+60 PLAN / 10 0 5 10 20 30 GRAPHIC SCALE 1 INCH = 10 FEET w fop / \ / � LEFT FpR Fogg 6" GATE VALVE / /' \ / (TO BE ABANDONED) / / ' • \ / , SIGN PROPOSED LIMITS PROPOSED OF DISTURBANCE SILT FENCE MAX WIDTH 45' \- /,'� Zj`j PROPOSED CONNECT TO CONCRETE—U—___—u-- EXISTING 36" WATER LINE WITH - 36"x36"x36" TEE, 2-36" - -- - -- - �� ;\/-u- / PROPOSED CONNECT TO BUTTERFLY VALVES AND BOXES TOP EL: 2 32.75 // / ' ' I I I I u -----u-- —� ° / \ EXISTING 24 WATER LINE WITH - - ° o ° SIG" _ 24"x24"x24" TEE, 2-24" °%' 11-1 IIIIIIIIIIM _U_24 u BUTTERFLY VALVES AND BOXES % / MNF A / 0 ° UP `� / - - - - �w W— PROPOSED TEMPORARY — — �o+oo J// // 6•• GV \ / CONSTRUCTION ENTRANCE ---- ___---- BLUE PAINT / PROPOSED 36" / \ MAINTAIN 'OR REPLACE 100 -YEAR FLOODPLAIN / TRANSMISSION MAIN , \ � STACKED BOULDER WALL + STACKEDe r / BOULDER WALL \ �� / gav Oct MAINTAIN NORTH COLUMN AND REPLACE APPROXIMATE \ \ , GATE. INSTALL NEW ELECTRICAL W BLUE PAINT - _� / / BORE LOCATION __ SERVICE TO COLUMN LIGHTS / N 61'04'09" E 121.58 /- OW an// �� 6" WATER LINE H _--------___ -- _ --_ TO BE REMOVED I I 1,� _L � _L ,� -L " � �1-k 1-I 4- �--I � � - I- �-I -r t -I I _ 1 1 1 I / o 1 -- -- ------------------ - ---2435— — --- SIGN = —----------- ��� PROPOSED EDGE OF --- — — — ---------------- 4%* 20' GRAVEL ENTRANCE -- --- --------------------------------------- -tet -\ \\�\ �\ \'�,� \ r I I I I I - 2435 — 2440 - IIIII-r-rTl I I fi>-i i i I i I-rrl iiI — - -I ------------I -I I -I -I I -I -I I -I -I -- __________I I 124401 __-----I I I I - �--�- �- -OU oA,Nc� 'CO-LUMN � ` \\\ \\• PROPOSED SILT FENCE BORE -I- -I 1- \� \BlA \\ \ \ (DOUBLE ROW), TYP. ♦s PROPOSED CONNECT TEMPORARY EXPAND WIDTH OF �� �- �\ PROPOSED LIMIT OF R v \ » � �\ \ �\� I � \ , � < ABANDON 6 WATER LINE NCDOT OVERLAY WATER LINE TO 6 EXISTING DIP PRMI PRIMARY ENTRANCE s410 PROPOSED 42 _ - \�\ TRANSMISSION MAIN _ _ - / ) \ \ \ \ Qp BORE PROPOSED TEMPORARY -,�� `o�. y \\ \ �P 62 6 0 HDPE WATER SERVICE (ABOVE GROUND) _ ' \ \ r ,2 POP REMOVE EXISTING SOUTH COLUMN ` ` -`� ` \ ' X111 , I \\\\\ 132 I MAINTAIN OR PROPOSED NEW SOUTH COLUMN\��\` �\ ?'� \\ SIGN LOCATION. REPLACE GATE, ELECTRICAL\\\ \` \\ '��,I h REPLACE SIGN SERVICE AND COLUMN LIGHTS Cj PROPOSED ROCK FACE PROPOSED LIMITS A OF DISTURBANCE �� �� \\ \ \ \\\ UTILITY MAX WIDTH 45 \_-OPRV TO BE REMOVED AND REPLACED AT NEW LOCATION ��\�\\� �\\� \� �_ G.I. G-' PROPOSED INLET \\\\�\� \\\ \, \\ ♦ PROTECTION PROPOSED EDGE OF 20 \\ GRAVEL ENTRANCE ROAD I REVISION DESCRIPTION 1 z J >D 0 Q Lu co LU v D � J � O z �Lu W �z=> � J Z cn Z z �oQo �U O_ Lu z 0 m U Z � O Q z �Vm Q)0) o� ce) o Y� Oo N } > Lu Lu O M f.- } m m > > � N J 0 LLI LLl Lu Z w LD CO 2 co zo a p Q w Q w O w� --) o U U 1 - SHEET C-104 O (n Z W i_ 0 Z U Z Lu Lu QwO� Lu L.L W 0- > w Q J � Z — W SHEET C-104 NI!\\ GRAPHIC SCALE I INCH= 10 FEET PROPOSED SILT FENCE (DOUBLE ROW), TYP. \ Rti�er REPLACE a11oa �// awn SIGN PROPOSED 42" TRANSMISSION MAIN REPLACEMENT OF METER"-- / \ VAULT AND RPZD / \ \ RIVER GAUGING STATION (ABANDONED) _ — �� \ PROPOSED IN-LINE PROPOSED 6" VAULT - \�\� 42 BUTTERFLY VALVE _ - DRAIN WITH FLAP VALVE fBOU�LDERS__ i 10" RDO AP - - PROPOSED 6" CONNECTION AND GATE VALVE WITH BOX PROPOSED AIR - 6921`B6 \�� �o HEM 6" POP / / \ \ 40P RELIEF VALVE - , , _ _ - �� / //''' �''' I I ' ' �' ' 1 ' ' 10" WHO/ 40*# PROPOSED FILL SLOPE 10, EE 12" X Vv 00 / / 10* PROPOSED EDGE OF 20' GRAVEL ENTRANCE ROAD 00`,' PROPOSED TEMPORARY CONNECTION OF 6" HDPE WATER LINE TO EXISTING FIRE \ ---- HYDRANT (REMOVE AND RELOCATE TO VAULT AREA AT PROJECT COMPLETION) \ PROPOSED LIMITS OF 40P \ 'DISTURBANCE FOLLOWS / \\ PERMANENT AND TEMPORARY EASEMENT LINES ON UPHILL SIDE \ \ \\ \\ \\\"RRo \' 11 V VI 14 VLV 1 1 1\VI \/liL_LJ 6" DIP TO EXISTING WATER LINE Presbyterian Reformed Ministries Int., Inc. D.B. 3321, P. 716 1 1\VI WIJL-LJ INLET PROTECTION UP_-/ PROPOSED LIMITS // OF DISTURBANCE / �� r� �� MAX 45' WIDTH PROPOSED FIRE HYDRANT ASSEMBLY (USING RELOCATED FIRE HYDRANT) _A/6 ELEC f I" -PROPOSED 6'x6'x5' STORMWATER RETENTION BOX FOR BASIN A "N- - PROPOSED HDPE STORM DRAIN (TYP.) V ��/ IMPROVEMENTS OUTSIDE EASEMENT (BY OTHERS) L_— NO. I DATE I BY PORCH REVISION DESCRIPTION Q a z Lu cin W v w J z mm�o �z W = z tn � Oct 0 0 c LLM w z g (:) � Z O V m �WCl� U� U Wz� W LLJ0 Q) 1) ce)o Z Ln z w z w w U O0 w 5 O Lu f� } J o cv Uz0000 > W N N W � W �x � W -S OZ n Wo J P�o0 N 0Qwawowo� � U z p C� w Z a� -3 � w Ln U W¢ U 1— Of W� w V O wAl Wtn Q a z Lu cin W v w J z mm�o �z W = z tn � Oct 0 0 c LLM w z g (:) � Z O V m SHEET N � o� LLJ0 Q) 1) ce)o Z U z w w Y� O0 5 O Lu f� } J m p Lb > W >LL LL, N W � W } � W -S OZ n J 2 M 0Qwawowo� 111 C� p C� Z a� -3 p p U p U 1— Of SHEET N � Z LLJ0 Z U z w w 5 O Lu I..L G 0— > (DOp � W 0-�^ n J 2 Z LLJ SHEET NOTES: CONSTRUCTION MATTING BEST MANAGEMENT PRACTICES INSTALLATION: 1. MATS SHOULD BE IN GOOD CONDITION TO ENSURE PROPER INSTALLATION, USE AND REMOVAL. OPERATING HEAVY EQUIPMENT IN WETLANDS SHALL BE MINIMIZED, AND SUCH EQUIPMENT OTHER THAN FIXED EQUIPMENT (DRILL RIGS, FIXED CRANES, ETC.) SHALL NOT BE STORED, MAINTAINED, FUELED OR REPAIRED IN WETLANDS UNLESS THE EQUIPMENT IS BROKEN DOWN AND CANNOT BE EASILY REMOVED. 2. WOODY VEGETATION (TREES, SHRUBS, ETC.) SHALL BE CUT AT OR ABOVE GROUND LEVEL AND NOT UPROOTED IN ORDER TO PREVENT DISRUPTION TO THE WETLAND SOIL STRUCTURE AND TO ALLOW STUMP SPROUTS TO REVEGETATE THE WORK AREA. 3. WHERE FEASIBLE, PLACE MATS IN A LOCATION THAT WOULD MINIMIZE THE AMOUNT NEEDED FOR THE WETLANDS CROSSING: 4. MINIMIZE IMPACTS TO WETLAND AREAS DURING INSTALLATION, USE, AND REMOVAL. 5. INSTALL ADEQUATE EROSION AND SEDIMENT CONTROLS AT APPROACHES TO MATS TO PROMOTE A SMOOTH TRANSITION TO, AND MINIMIZE SEDIMENT TRACKING ONTO, SWAMP MATS. 6. IN MOST CASES, CONSTRUCTION MATS SHOULD BE PLACED ALONG THE TRAVEL AREA SO THAT THE INDIVIDUAL BOARDS ARE RESTING PERPENDICULAR TO THE DIRECTION OF TRAFFIC. NO GAPS SHOULD EXIST BETWEEN MATS. PLACE MATS FAR ENOUGH ON EITHER SIDE OF THE RESOURCE AREA TO REST ON FIRM GROUND. WETLAND/STREAM CHANNEL CROSSING: 1. AT 'DRY"CROSSINGS WHERE NO FLOW IS PRESENT OR ANTICIPATED DURING PROJECT CONSTRUCTION, THE MATS MAY BE PLACED DIRECTLY ONTO THE GROUND IN ORDER TO PREVENT EXCESSIVE RUTTING, PROVIDED STREAM BANKS AND BOTTOMS ARE NOT ADVERSELY ALTERED. 2. CONSTRUCTION MATS MAY BE USED AS A TEMPORARY BRIDGE OVER A STREAM TO ALLOW VEHICLES ACCESS TO THE WORK SITE. SMALL SECTIONS OF MAT ARE PLACED WITHIN AND ALONG THE STREAM PARALLEL TO THE FLOW OF WATER. MATS MAY THEN BE PLACED PERPENDICULAR TO THE STREAM, RESTING ON TOP OF THE INITIAL CONSTRUCTION MAT SUPPORTS. IT MAY BE NECESSARY TO PLACE ADDITIONAL REINFORCEMENT FOR EXTRA STABILITY AND TO MINIMIZE THE AMOUNT OF SEDIMENT THAT COULD FALL BETWEEN THE SPACES OF EACH TIMBER. 3. MATS SHOULD NOT BE PLACED SO THAT THEY RESTRICT THE NATURAL FLOW OF THE STREAM. 4. MINIMIZE NUMBER OF STREAM/WETLAND CROSSINGS. WHERE FEASIBLE, LOCATE CROSSING SITE WHERE STREAM CHANNEL IS NARROW FOR THE SHORTEST POSSIBLE CLEAR SPAN AND WHERE STREAM BANKS ARE STABLE AND WELL DEFINED. FOR LARGE WETLAND COMPLEXES, CONSIDER ACCESSING STRUCTURES FROM OPPOSITE SIDES WHERE POSSIBLE TO AVOID CROSSING THE ENTIRE WETLAND. 5. MORE THAN ONE LAYER OF MATS MAY BE NECESSARY IN AREAS WHICH ARE INUNDATED OR HAVE DEEP ORGANIC WETLAND SOILS. REMOVAL/RESTORATION: 1. MATTING SHOULD BE REMOVED BY "BACKING" OUT OF THE SITE, REMOVING MATS ONE AT A TIME. ANY RUTTING OR SIGNIFICANT INDENTATIONS IDENTIFIED DURING MAT REMOVAL SHOULD BE REGRADED IMMEDIATELY, TAKING CARE NOT TO COMPACT SOILS. 2. MATS SHOULD BE CLEANED BEFORE TRANSPORT TO ANOTHER WETLAND LOCATION TO REMOVE SOIL AND ANY INVASIVE PLANT SPECIES SEED STOCK OR PLANT MATERIAL. 3. MATS SHALL BE CLEANED OF SOIL AND ANY INVASIVE PLANT SPECIES SEED STOCK OR PLANT MATERIAL FROM BEFORE INSTALLATION. 4. CROSSINGS SHOULD BE INSPECTED FOLLOWING MAT REMOVAL TO DETERMINE THE LEVEL OF RESTORATION REQUIRED. SPECIAL PRECAUTIONS SHOULD BE TAKEN TO PROMPTLY STABILIZE AREAS OF DISTURBED SOIL LOCATED NEAR WETLANDS AND STREAMS. MATTED AREAS WITHIN WETLANDS SHALL BE RESTORED TO THEIR ORIGINAL CONDITION AND ELEVATION. THIS MAY INVOLVE NATURAL REVEGETATION FROM EXISTING ROOT AND SEED STOCK OF NATIVE PLANT SPECIES. CONDITIONS MAY WARRANT PLANTING AND THE BROADCAST OF A WETLAND SEED MIX OVER THE MATTED AREA TO SUPPLEMENT THE EXISTING SEED AND ROOTSTOCK. SEED MIXES AND VEGETATION SHALL CONTAIN ONLY PLANT SPECIES NATIVE TO NORTH CAROLINA. WETLAND G //1\ 1\\ \x� 1< �. . . . . . . . . . .� . . . . . . . . . . . .Y�\ WETLAND F �. '. . . .', ..... .� TEMPORARY BYPASS NOTES 1. INSTALL ALL EROSION CONTROL MEASURES AS SHOWN ON EROSION CONTROL PLAN AND IN THIS DETAIL. 2. CONSTRUCT IMPERVIOUS DIKE (RECOMMEND SAND BAGS OR OTHER EASILY REMOVABLE MATERIAL) ON UPSTREAM SIDE OF EXISTING CHANNEL AND INSTALL TEMPORARY BYPASS PUMP TO DIVERT WATER AROUND CONSTRUCTION AREA. ALL MATERIAL MUST BE COMPLETELY REMOVED FOLLOWING CONSTRUCTION. 3. CONSTRUCT IMPERVIOUS DIKE (RECOMMEND SAND BAGS OR OTHER EASILY REMOVABLE MATERIAL) ON DOWNSTREAM SIDE OF EXISTING CHANNEL TO PREVENT BACKING UP OF STREAM WATER INTO THE CONSTRUCTION AREA. 4. DEWATER THE CONSTRUCTION AREA USING ANOTHER TEMPORARY PUMP AND DISCHARGE WATER INTO A DEWATERING BASIN UNTIL SEDIMENT HAS SETTLED AND WATER CAN BE DISCHARGED BACK INTO STREAM. DEWATERING BASIN MUST BE OUTSIDE OF ANY RESTRICTED BUFFER AREAS, USE WATTLES INSTEAD OF EARTH BERM IF REASONABLE. WETLAND A-\ 5. BEGIN CONSTRUCTION OF WATER LINE. CONTRACTOR SHALL INSPECT SYSTEM DAILY BEFORE BEGINNING ANY CONSTRUCTION. NO CONSTRUCTION SHALL CONTINUE IF SYSTEM IS NOT FULLY OPERATIONAL. 6. ANY WASH MATERIAL REMOVED FROM BYPASS AREA SHOULD BE STORED OUTSIDE THE FLOOD ZONE OR REGULATED BUFFER AREA UNTIL CONSTRUCTION IS COMPLETE. 7. UPON COMPLETION OF WATER LINE CONSTRUCTION, REMOVE BYPASS SYSTEM WITHIN (2) TWO CALENDAR DAYS. 8. STABILIZE ALL AREAS DISTURBED DURING CONSTRUCTION. STREAM BED AND BANKS MUST BE RETURNED TO PRE -CONSTRUCTION CONDITIONS. 9. CONTRACTOR SHALL RECEIVE PRIOR APPROVAL FROM ENGINEER IF CHOOSING TO USE ANOTHER METHOD IN LIEU OF BYPASS CHANNEL. PROPOSED PIPE ENCASEMENT . . . . � -BENEATH CHANNEL, MIN. 5' INTO • . . . _\BANK (APPROXIMATELY 40 LF) \ .nnnnnrrn niin. GRAPHIC SCALE I INCH = 10 FEET NOTES: STATEMENT OF PERMIT AND CONTRACTOR RESPONSIBILITIES 1. PROJECT SITE CONTAINS JURISDICTIOANL WATERS OF THE U.S (WOTUS). 2. PROJECT INVOLVES IMPACTS TO WOTUS IN SEVERAL LOCATIONS. 3. PROPOSED IMPACTS TO WOTUS ARE REGULATED BY THE CLEAN WATER ACT SECTIONS 404 AND 401. 4. PERMITS HAVE BEEN OBTAINED BY THE CITY OF HENDERSON, NC TO AUTHORIZE THE PROPOSED IMPACTS TO WOTUS AND ARE SUBJECT TO THE TERMS AND CONDITIONS OF THE PERMITS. 5. CWA 404/401 PERMIT REQUIREMENTS, TERMS, AND CONDITIONS ARE SUMMARIZED ON THIS SHEET ALONG WITH VARIOUS ASSOCIATED DETAILS AND SPECIFICATIONS. 6. A COPY OF THE PERMITS HAVE BEEN PROVIDED TO THE CONTRACTOR AT THE PRE -CONSTRUCTION MEETING. THE CONTRACTOR IS RESPONSIBLE FOR READING THE PERMITS, PLANS AND SPECIFICATIONS, AND UNDERSTANDING HIS/HER RESPONSIBILITIES UNDER THE PERMITS, WHICH INCLUDE BUT ARE NOT LIMITED TO: A) COMPLIANCE WITH ALL PERMIT CONDITIONS RELATING TO CONTRACTED CONSTRUCTION ACTIVITIES BOTH ON-SITE AND OFF-SITE, IF OFF-SITE AREAS ARE USED FOR PROJECT RELATED PURPOSES (EG: ACCESS, LAYDOWN, STAGING, BORROW, WASTE, ETC.) B) COMMUNICATION OF PERMIT COMPLIANCE RESPONSIBILITIES TO SUBCONTRACTORS WORKING ON THE PROJECT. C) COORDINATION WITH PROJECT ENGINEER REGARDING PERMIT COMPLIANCE RELATED ISSUES AND QUESTIONS. D) IMMEDIATE REPORTING TO PROJECT ENGINEER OR OWNER OF ANY VIOLATION OR SUSPECTED VIOLATION OF PERMIT CONDITIONS. E) A COPY OF ALL PERMITS AND CONDITIONS SHOULD BE MADE AVAILABLE AT THE PROJECT SITE DURING CONSTRUCTION AND MAINTENANCE ACTIVITIES. TOP OF BANK f ' PROPOSED SILT I IPEXISTINGI STREAM FENCE I PROPOSED TEMPORARY X WORK AREA I I PUMP AROUND x IIMPERVIOUS DIKE P X TO BE INSTALLED\ IN CHANNEL X i X X PROPOSED SILT ....... -X--X X X �J _ FENCE .'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.... .'.'.'.'.'.'.'.'.'.'.'.'.'.��.'..'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'..'...'.'.'.'.'.'......... . '.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'. .:.:.:.:.:.:.:.'.'.'.'.'� ��.:.:.:.:.:.:.;.:.:.:.:.:.:.:.:.;.:.:.:.:.:.;.:.:.:.:.:.:.:.:. ..:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:. ::':':':'....:: 1:... '.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.':":'.:::'.'.'.'.'.'.'.'.'.':':':'a�:':':':'l.'.'.'.'.'.'.'.'.':'.'.'.'.'.'.':'.'.'.'.'.'.':'.'.'.'.'.'.':'.'.'.'.'.':'.'.'.'.'.'.....': ...................... .. ........ �............ .:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:. r....'��.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:..:.:.:.:.:.:.:.:.:. ':'.......::::.:. i.... . ........... .... ..................................... ........ X. ............................................ 1 X I I PROPOSED PIPE PUMP X X I DEWATE DEVICE RING X X ENERGY X IMPERVIOUS DIKE DISSIPATOR i X 0� PROPOSED SILT I I FENCE PROPOSED SILT FENCE TEMPORARY BYPASS NOTES 1. Install all erosion control measures as shown on Erosion Control Plan and in this detail. 2. Construct impervious dike (recommend sand bags or other easily removable material) on upstream side of existing channel and install temporary bypass pump to divert water around construction area. All material must be completely removed following construction. 3. Construct impervious dike (recommend sand bags or other easily removable material) on downstream side of existing channel to prevent backing up of stream water into the construction area. 4. Dewater the construction area using another temporary pump and discharge water into a dewatering basin until sediment has settled and water can be discharged back into stream. Dewatering basin must be outside of any restricted buffer areas, use wattles instead of earth berm if reasonable. 5. Begin construction of cross -culvert. Contractor shall inspect system daily before beginning any construction. No construction shall continue if system is not fully operational. 6. Any wash material removed from bypass area should be stoned outside the flood zone or regulated buffer area until construction is complete. 7. Upon completion of culvert construction, remove bypass system within (2) two calendar days. 8. Stabilize all areas disturbed during construction. Stream bed and banks must be returned to pre -construction conditions. 9. Contractor shall receive prior approval from engineer if choosing to use another method in lieu of bypass channel. PROPOSED ROADWAY M TEMPORARY STREAM BYPASS 7")UPDATED MARCH, 2017 NOT TO SCALE NO. I DATE I BY REVISION DESCRIPTION �w D Q U \ . ..................... Z co o 0O N 20 w z 30 . . GRAPHIC SCALE I INCH = 10 FEET NOTES: STATEMENT OF PERMIT AND CONTRACTOR RESPONSIBILITIES 1. PROJECT SITE CONTAINS JURISDICTIOANL WATERS OF THE U.S (WOTUS). 2. PROJECT INVOLVES IMPACTS TO WOTUS IN SEVERAL LOCATIONS. 3. PROPOSED IMPACTS TO WOTUS ARE REGULATED BY THE CLEAN WATER ACT SECTIONS 404 AND 401. 4. PERMITS HAVE BEEN OBTAINED BY THE CITY OF HENDERSON, NC TO AUTHORIZE THE PROPOSED IMPACTS TO WOTUS AND ARE SUBJECT TO THE TERMS AND CONDITIONS OF THE PERMITS. 5. CWA 404/401 PERMIT REQUIREMENTS, TERMS, AND CONDITIONS ARE SUMMARIZED ON THIS SHEET ALONG WITH VARIOUS ASSOCIATED DETAILS AND SPECIFICATIONS. 6. A COPY OF THE PERMITS HAVE BEEN PROVIDED TO THE CONTRACTOR AT THE PRE -CONSTRUCTION MEETING. THE CONTRACTOR IS RESPONSIBLE FOR READING THE PERMITS, PLANS AND SPECIFICATIONS, AND UNDERSTANDING HIS/HER RESPONSIBILITIES UNDER THE PERMITS, WHICH INCLUDE BUT ARE NOT LIMITED TO: A) COMPLIANCE WITH ALL PERMIT CONDITIONS RELATING TO CONTRACTED CONSTRUCTION ACTIVITIES BOTH ON-SITE AND OFF-SITE, IF OFF-SITE AREAS ARE USED FOR PROJECT RELATED PURPOSES (EG: ACCESS, LAYDOWN, STAGING, BORROW, WASTE, ETC.) B) COMMUNICATION OF PERMIT COMPLIANCE RESPONSIBILITIES TO SUBCONTRACTORS WORKING ON THE PROJECT. C) COORDINATION WITH PROJECT ENGINEER REGARDING PERMIT COMPLIANCE RELATED ISSUES AND QUESTIONS. D) IMMEDIATE REPORTING TO PROJECT ENGINEER OR OWNER OF ANY VIOLATION OR SUSPECTED VIOLATION OF PERMIT CONDITIONS. E) A COPY OF ALL PERMITS AND CONDITIONS SHOULD BE MADE AVAILABLE AT THE PROJECT SITE DURING CONSTRUCTION AND MAINTENANCE ACTIVITIES. TOP OF BANK f ' PROPOSED SILT I IPEXISTINGI STREAM FENCE I PROPOSED TEMPORARY X WORK AREA I I PUMP AROUND x IIMPERVIOUS DIKE P X TO BE INSTALLED\ IN CHANNEL X i X X PROPOSED SILT ....... -X--X X X �J _ FENCE .'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.... .'.'.'.'.'.'.'.'.'.'.'.'.'.��.'..'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'..'...'.'.'.'.'.'......... . '.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'. .:.:.:.:.:.:.:.'.'.'.'.'� ��.:.:.:.:.:.:.;.:.:.:.:.:.:.:.:.;.:.:.:.:.:.;.:.:.:.:.:.:.:.:. ..:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:. ::':':':'....:: 1:... '.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.'.':":'.:::'.'.'.'.'.'.'.'.'.':':':'a�:':':':'l.'.'.'.'.'.'.'.'.':'.'.'.'.'.'.':'.'.'.'.'.'.':'.'.'.'.'.'.':'.'.'.'.'.':'.'.'.'.'.'.....': ...................... .. ........ �............ .:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:. r....'��.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:.:..:.:.:.:.:.:.:.:.:. ':'.......::::.:. i.... . ........... .... ..................................... ........ X. ............................................ 1 X I I PROPOSED PIPE PUMP X X I DEWATE DEVICE RING X X ENERGY X IMPERVIOUS DIKE DISSIPATOR i X 0� PROPOSED SILT I I FENCE PROPOSED SILT FENCE TEMPORARY BYPASS NOTES 1. Install all erosion control measures as shown on Erosion Control Plan and in this detail. 2. Construct impervious dike (recommend sand bags or other easily removable material) on upstream side of existing channel and install temporary bypass pump to divert water around construction area. All material must be completely removed following construction. 3. Construct impervious dike (recommend sand bags or other easily removable material) on downstream side of existing channel to prevent backing up of stream water into the construction area. 4. Dewater the construction area using another temporary pump and discharge water into a dewatering basin until sediment has settled and water can be discharged back into stream. Dewatering basin must be outside of any restricted buffer areas, use wattles instead of earth berm if reasonable. 5. Begin construction of cross -culvert. Contractor shall inspect system daily before beginning any construction. No construction shall continue if system is not fully operational. 6. Any wash material removed from bypass area should be stoned outside the flood zone or regulated buffer area until construction is complete. 7. Upon completion of culvert construction, remove bypass system within (2) two calendar days. 8. Stabilize all areas disturbed during construction. Stream bed and banks must be returned to pre -construction conditions. 9. Contractor shall receive prior approval from engineer if choosing to use another method in lieu of bypass channel. PROPOSED ROADWAY M TEMPORARY STREAM BYPASS 7")UPDATED MARCH, 2017 NOT TO SCALE NO. I DATE I BY REVISION DESCRIPTION �w D Q U t oo Z co o 0O N w z W LU m U W v (DJ i i z J 0 � � o � cv N W N OJZ� Z z Cos) O = a Z � o tJl OctO Z CY) � O � U z W z� w� 0 Q w i --i > w w o w � H z m ~ V m AFilO m w � 0 z z Q Z 0 Z 0. w U2_j LLI� w Z L.L LL 0 Z Q Z Q J - U w SHEET C-1 06 D Q oo Z `6 co o 0O N W LU U) W v (DJ i i z J 0 LU CO CO �z W OJZ� Z m Z = Z� Z � O OctO Z CY) � O u) LL. W z� w� 0 Q m Q o � H z ~ V m 0 z z Q Z 0 Z 0. w U2_j LLI� w Z L.L LL 0 Z Q Z Q J - U w SHEET C-1 06 oo = `6 co o 0O N W LU 00 L r > M m i i LL N J 0 LU LLJ LU O Z m Z Q t 70 Z v, Z CY) w Q w O w� 0 Q m 0 z z Q Z 0 Z 0. w U2_j LLI� w Z L.L LL 0 Z Q Z Q J - U w SHEET C-1 06 Best Management Practices Manual for Utility Maintenance In and Adjacent to Wetlands and Waterbodies Interim January 2010. T 16'-0" 12'-0" i I 16'-0" 12" x 12" TIMBERS (TYP) TRANSITION AS 4" RAIL REQUIRED GROUND AND/OR VEGETATION SURFACE TYPICAL STREAM CROSSING WITH TIMBER MATS * NOT TO SCALE Best Management Practices Manual for Utility Maintenance In and Adjacent to Wetlands and Waterbodies Interim January 2010. 4'-0" 4" RAIL 16'-0" 12'-0" ROADWAY 4" RAIL 7121" x 12" TIMBERS (TYP) TYPICAL PLAN VIEW 4" RAIL 1'-0" 1'-0" SECTION A -A TYPICAL MAT SECTION TRANSITION AS 4" RAIL REQUIRED GROUND AND/OR VEGETATION SURFACE TYPICAL SECTION VIEW TYPICAL WETLAND CROSSING WITH TIMBER MATS * NOT TO SCALE NOTE: 1. TO BE INSTALLED IF NECESSARY TO PREVENT RUTTING DURING CONSTRUCTION. 2. THIS DETAIL SHOWS TYPICAL DIMENSIONS. SOME CONTRACTORS TIMBER MATS ARE DIMENSIONALLY DIFFERENT FROM WHAT IS SHOWN HERE. 3. DEPENDENT ON SITE CONDITIONS MULTIPLE LAYERS OF TIMBER MATS MAY BE INSTALLED. GEOTEXTILE FILTER FABRIC 6" #57 WATER IN TRENCH DISCHARGE VT kRGE SUCTION HOSE YW� W W W W INSERT DISCHARGE HOSE INTO DEWATERING FILTER TUBE/ SOCK CLOSED END DEWATERING FILTER TUBE/SOCK SECTIONZISOMETRIC ATTACHMENT POINT GEOTEXTILE FILTER BAG SIZED SEWN -IN PIPE FOR PUMP DISCHARGE FOR PUMP DISCHARGE DISCHARGE SLEEVE PUMP DISCHARGE NOTES: (MIN. 10'X15') HOSE GEOTEXTILE 1. CONSTRUCT A STABILIZED EARTHEN BERM BETWEEN THE DEWATERING DEVICE AND THE TRENCH FILTER FABRIC TO PROTECT THE TRENCH IN THE EVENT OF A FAILURE. 2. PLACE DEWATERING FILTER TUBE/ SOCK ON THE GROUND OR ON A TRAILER OVER A RELATIVELY LEVEL, STABILIZED AREA. 3 AND INSERT EC SECUREARGE WITH A IPE FROM PUMP ROPE WRAPPED AROUND DNTLY FAR THE SNOUT TOFDIEWATERING TH E BAG, ORLTER TUBE/ SOCK PER INSTALL ON LESS MANUFACTURER INSTRUCTIONS. SECURE THE OTHER END OF THE TUBE BY FOLDING THE OPEN 6" #57 STONE THAN 5% SLOPE END BACK ON ITSELF, AND THEN WRAPPING THAT END WITH A ROPE, OR PER MANUFACTURER UNDISTURBED EARTH INSTRUCTIONS. NOTES: SECTION 1. FILTER BAG SHALL BE CONSTRUCTED OF NON—WOVEN FILTER FABRIC WITH A MIN. 8 OZ/SQUARE YARD WEIGHT 2. FILTER BAG FABRIC SHALL HAVE A FLOW RATE OF 80 GPM/S.F. OR SIZED FOR PUMP DISCHARGE 3. SILT BAG SHALL HAVE SLEEVE SEWN—IN SLEEVE FOR RECEIVING THE PUMP DISCHARGE AND PUMP HOSE SHALL BE SECURELY ATTACHED TO SILT BAG 4. SILT BAG SHALL BE REPLACED WHEN HALF FULL OR PUMP DISCHARGE RATE IS REDUCED ENOUGH TO CAUSE OVERFLOW. CONTRACTOR SHALL PROVIDE ADDITIONAL BAGS AS REQUIRED. 5. BOTH FILTER BAG AND SILT WITHIN SHALL BE DISPOSED OF IN A PROPER MANNER AFTER MATERIAL INSIDE IS DRY, RESULTING IN NO DISCHARGE TO THE STREAM HAY BALES MAY BE PLACED ALONG EDGE OF TIRAI-lrr-) RAATC+ T!'l %A/rTl AAIr1C% r1f-knA 4. EMPTY DEWATERING FILTER TUBE/ SOCK WHEN: (1) HALF FULL OF SEDIMENT; (2) WHEN THE SEDIMENT HAS REDUCED THE FLOW RATE OF THE PUMP DISCHARGE TO AN IMPRACTICAL AMOUNT; OR (3) PER MANUFACTURER INSTRUCTIONS. MAINTENANCE AND DISPOSAL: 1. REMOVE AND DISPOSE OF ACCUMULATED SEDIMENT IN A PRE—APPROVED LOCATION AWAY FROM WATERWAYS OR ENVIRONMENTALLY SENSITIVE AREAS. OPEN BOTH ENDS OF THE DEWATERING FILTER TUBE/ SOCK, PICK IT UP IN THE CENTER AND DUMP ACCUMULATED SEDIMENT OUT OF BOTH ENDS, OR PER MANUFACTURER INSTRUCTIONS. 2. ALLOW TO DRY AND STORE FOR RE—USE OR; AS DIRECTED BY ENGINEER OR INSPECTOR. CONTRACTOR SHALL INSPECT DISCHARGE FROM SILT BAG AND/OR SOCK TO PREVENT SEDIMENT OR TURBIDITY IN RECEIVING WATERS. TYPICAL SILT BAG TYPICAL SILT SOCK EC TRENCH DEWATERING DETAIL 29UPDATED FEBRUARY, 2018 NOT TO SCALE V I VI VL r-%1 1\VIY I I A\/ M A I r PLAN VIEW PLAN VIEW ""` I L/1114L-1 /11, NOT TO SCALE TYPICAL TIMBER MAT USE WETLAND RESTORATION NOTES 1. WETLAND SOILS SHOULD BE SIDECAST SEPARATELY FROM SUBSOILS AND RETURNED BACK INTO THE TOP OF BACKFILLED TRENCHES POST CONSTRUCTION. 2. DISTURBED WETLAND AREAS SHOULD BE RETURNED TO ORIGINAL CONTOURS AND ELEVATIONS. 3. SEED MIX SHALL CONSIST OF NATIVE NORTH CAROLINA WETLAND SPECIES. SEE SHEET G-004 WETLAND RESTORATION SEED MIX. 4. STRAW MULCH — STRAW MULCH SHALL CONSIST OF UN—ROTTEN SMALL GRAIN STRAW. ALL MULCH SHALL BE FREE FROM STATE AND FEDERAL PROHIBITED NOXIOUS WEED SEEDS LISTED AS ALIEN INVASIVE SPECIES BY THE VIRGINIA DEPARTMENT OF CONSERVATION AND RECREATION NATURAL HERITAGE PROGRAM, THE US DEPARTMENT OF AGRICULTURE AND THE MID—ATLANTIC EXOTIC PEST PLANT COUNCIL. 5. ALL AREAS DISTURBED BY CONSTRUCTION SHALL BE SEEDED IN ACCORDANCE WITH THE SEEDING SCHEDULE. 6. NO SEEDING SHALL BE PERFORMED ON FROZEN GROUND OR WHEN THE TEMPERATURE IS 32F/OC OR LOWER. NOIDATEIBY REVISION DESCRIPTION J � w o Z Z Z Q co = J_ U Q Z LLJ Q 0 D � Z Z Q U) J C) � Q W 3:(.) SHEET C-1 07 �WC� M< 1 U _ L �: -C� C) 0 N ww25 Lu cin W v m U) J z � H o N UzN �N 00 m z Wolf Q � -= ❑ (D ^x z Cn z Q U W ❑ Oct /11W� 00 00 N LLMw � U z � Z w �—, � > w z W¢ O W �- W W I—I h zi Q AFilW O J � w o Z Z Z Q co = J_ U Q Z LLJ Q 0 D � Z Z Q U) J C) � Q W 3:(.) SHEET C-1 07 M< 1 �,o _ L �: -C� C) 0 N W Lu cin W v m U) J z W mm � o m z Wolf Q 0- -= ❑ (D LL z Cn z Q U W ❑ Oct 0 oU) LLMw z g 11110 � Z O V m J � w o Z Z Z Q co = J_ U Q Z LLJ Q 0 D � Z Z Q U) J C) � Q W 3:(.) SHEET C-1 07 1 �,o _ L �: -C� C) 0 N W W P'_ > J❑ m m i W i W LL N W 1 W p z m z Q Z �j (D ❑ (D C/) z M aD p Q ❑ W ❑ Q U W ❑ 0 U _J m LL — 0f J � w o Z Z Z Q co = J_ U Q Z LLJ Q 0 D � Z Z Q U) J C) � Q W 3:(.) SHEET C-1 07 NOTES: NCDEQ GENERAL CONSTRUCTION CONDITIONS 1. THE CONTRACTOR SHALL MINIMIZE CLEARING WITHIN WETLANDS AND ACROSS STREAMS TO THE GREATEST EXTENT PRACTICABLE AND SHALL NOT EXCEED 50' WIDE FOR GAS UTILITY LINES AND 40' WIDE FOR ALL OTHER UTILITY LINES. EXCEPTIONS TO THIS CONDITION WILL REQUIRE WRITTEN APPROVAL FROM THE PROJECT ENGINEER. FOR CONSTRUCTION CORRIDORS IN WETLANDS AND ACROSS STREAM CHANNELS, STUMPS SHALL BE GRUBBED ONLY AS NEEDED TO INSTALL THE UTILITY AND REMAINING STUMPS SHALL BE CUT OFF AT GRADE LEVEL. THE GENERAL STRIPPING OF TOPSOIL WITHIN WETLANDS ALONG THE CONSTRUCTION CORRIDOR IS NOT PERMITTED. 2. PERMANENT MAINTAINED ACCESS CORRIDORS IN WETLANDS AND ACROSS STREAM CHANNELS SHALL BE RESTRICTED TO THE MINIMUM WIDTH PRACTICABLE AND SHALL NOT EXCEED 30' WIDE FOR GAS UTILITY LINES AND 20' WIDE FOR ALL OTHER UTILITY LINES EXCEPT AT MANHOLE LOCATIONS. 15' X 15' PERPENDICULAR VEHICLE TURN-AROUNDS ARE ALLOWED IN ACCESS CORRIDORS BUT MUST BE SPACED AT LEAST 500' APART. EXCEPTIONS TO THIS CONDITION REQUIRE WRITTEN APPROVAL FROM THE PROJECT ENGINEER. 3. THE CONTRACTOR SHALL HAVE A SPECIFIC PLAN FOR RESTORING WETLAND CONTOURS. ANY EXCESS MATERIAL SHALL BE REMOVED TO A HIGH GROUND DISPOSAL AREA. THE MIXING OF TOPSOIL AND SUBSOILS WITHIN WETLANDS ALONG UTILITY CORRIDORS SHALL BE MINIMIZED TO THE GREATEST EXTENT PRACTICABLE DURING EXCAVATION. THE SOILS SHALL BE PLACED ON FABRIC TO MINIMIZE IMPACTS WHENEVER POSSIBLE. TOPSOIL EXCAVATED FROM UTILITY TRENCHES SHALL BE PILED SEPARATELY FROM SUBSOILS AND BACKFILLED INTO THE TRENCH ONLY AFTER THE SUBSOILS HAVE BEEN PLACED AND COMPACTED. 4. NO WASTE, SPOIL, SOLIDS, OR FILL OF ANY KIND CAN OCCUR IN WETLANDS OR WATERS BEYOND THE FOOTPRINT OF THE IMPACT AREA (INCLUDING TEMPORARY IMPACTS) OR BEYOND THE PERMITTED THRESHOLDS WITHOUT WRITTEN AUTHORIZATION FROM THE PROJECT ENGINEER. NO REMOVAL OF VEGETATION OR OTHER IMPACTS OF ANY KIND CAN OCCUR TO STATE REGULATED RIPARIAN BUFFERS BEYOND THE FOOTPRINT OF IMPACTS APPROVED IN A BUFFER AUTHORIZATION OR VARIANCE OR AS LISTED AS AN EXEMPT ACTIVITY IN THE APPLICABLE RIPARIAN BUFFER RULES. 5. ALL EROSION CONTROL DEVICES SHALL BE MAINTAINED ON ALL CONSTRUCTION SITES, BORROW SITES, AND WASTE PILE (SPOIL) SITES, INCLUDING CONTRACTOR OWNED OR LEASED BORROW PITS ASSOCIATED WITH THE PROJECT. SUFFICIENT MATERIALS REQUIRED FOR STABILIZATION AND/OR REPAIR OF EROSION CONTROL MEASURES AND STORMWATER ROUTING AND TREATMENT SHALL BE ON-SITE AT ALL TIMES. 6. SEDIMENT AND EROSION CONTROL MEASURES SHALL NOT BE PLACED IN WETLANDS OR WATERS EXCEPT WITHIN THE FOOTPRINT OF TEMPORARY OR PERMANENT IMPACTS AUTHORIZED UNDER THE PERMITS. EXCEPTIONS TO THIS CONDITION REQUIRE WRITTEN APPROVAL FROM THE PROJECT ENGINEER. 7. EROSION CONTROL MATTING THAT INCORPORATES PLASTIC MESH AND/OR PLASTIC TWINE SHALL NOT BE USED ALONG STREAMBANKS OR WITHIN WETLANDS. EXCEPTIONS TO THIS CONDITION REQUIRE WRITTEN APPROVAL FROM THE PROJECT ENGINEER. 8. AN NPDES CONSTRUCTION STORMWATER PERMIT (NCGO10000) IS REQUIRED FOR CONSTRUCTION PROJECTS THAT DISTURB ONE OR MORE ACRES OF LAND. THE NCGO10000 PERMIT ALLOWS STORMWATER TO BE DISCHARGED DURING LAND DISTURBING CONSTRUCTION ACTIVITIES AS STIPULATED IN THE CONDITIONS OF THE PERMIT. IF THE PROJECT IS COVERED BY THE PERMITS, FULL COMPLIANCE WITH PERMIT CONDITIONS INCLUDING THE EROSION AND SEDIMENTATION CONTROL PLAN, INSPECTIONS AND MAINTENANCE, SELF-MONITORING, RECORD KEEPING AND REPORTING REQUIREMENTS IS REQUIRED. 9. ALL WORK IN OR ADJACENT TO STREAMS SHALL BE CONDUCTED SO THAT THE FLOWING STREAM DOES NOT COME IN CONTACT WITH THE DISTURBED AREA. APPROVED BEST MANAGEMENT PRACTICES FROM THE MOST CURRENT VERSION OF THE NC SEDIMENT AND EROSION CONTROL MANUAL, OR THE NC DOT CONSTRUCTION FLOW TOP STREAM BANK UPON REMOVAL OF TEMPORARY DIVERSION IMMEDIATELY INSTALL BIODEGRADEABLE COIR MATTING (NO BACKING) ON DISTURBED AREAS OF CREEK SIDE SLOPES OUTSIDE OF TRENCH AREA, OVERLAP MATTING MIN. OF 2' TO ADJACENT NON -DISTURBED AREAS. DO NOT MAT CREEK BOTTOM NOTES: 1. STREAM BED SHALL BE RETURNED TO ORIGINAL CONTOURS AND ELEVATIONS USING ORIGINAL EXCAVATED STREAM BED MATERIAL. 2. STREAM BANKS SHALL BE RESTORED TO A MINIMUM 3:1 SLOPE, COVERED WITH FULLY BIODEGRADABLE MATTING, AND STABILIZED WITH NATIVE RIPARIAN SEED MIX. LIVE STAKES SHALL BE INSTALLED ALONG BOTH SIDES OF ANY DISTURBED STREAM CHANNEL OUTSIDE OF 20' PERMANENT MAINTENANCE CORRIDOR. SEE SHEET G-004 STREAM BANK RESTORATION SEED MIX. RIVER AND STREAM BANK RESTORATION DETAIL OUTSIDE OF TRENCH AREA NOT TO SCALE 1'-0" BELOW BOTTOM OF TRENCH AND MAINTENANCE ACTIVITIES MANUAL, SUCH AS SANDBAGS, ROCK BERMS, COFFERDAMS, AND OTHER DIVERSION STRUCTURES SHALL BE USED TO MINIMIZE EXCAVATION IN FLOWING WATER. EXCEPTIONS TO THIS CONDITION REQUIRE WRITTEN APPROVAL FROM THE PROJECT ENGINEER. 10. CULVERTS SHALL BE INSTALLED IN SUCH A MANNER THAT THE ORIGINAL STREAM PROFILES ARE NOT ALTERED AND ALLOW FOR AQUATIC LIFE MOVEMENT DURING LOW FLOWS. THE DIMENSION, PATTERN, AND PROFILE OF THE STREAM ABOVE AND BELOW A PIPE OR CULVERT SHALL NOT BE MODIFIED BY WIDENING THE STREAM CHANNEL OR BY REDUCING THE DEPTH OF THE STREAM IN CONNECTION WITH THE CONSTRUCTION ACTIVITY. 11. APPLICATION OF FERTILIZER TO ESTABLISH PLANTED/SEEDED VEGETATION WITHIN DISTURBED RIPARIAN AREAS SHALL COMPLY WITH ALL OTHER FEDERAL, STATE AND LOCAL REGULATIONS. FERTILIZER APPLICATION SHALL BE ACCOMPLISHED IN A MANNER THAT MINIMIZES THE RISK OF CONTACT BETWEEN THE FERTILIZER AND SURFACE WATERS. 12. IF CONCRETE IS USED DURING CONSTRUCTION, THEN ALL NECESSARY MEASURES SHALL BE TAKEN TO PREVENT DIRECT CONTACT BETWEEN UNCURED OR CURING CONCRETE AND WATERS OF THE US. WATER THAT INADVERTENTLY CONTACTS UNCURED CONCRETE SHALL NOT BE DISCHARGED TO WATERS OF THE US. 13. ALL PROPOSED AND APPROVED TEMPORARY FILL AND CULVERTS SHALL BE REMOVED AND THE IMPACTED AREA RETURNED TO NATURAL CONDITIONS WITHIN 60 CALENDAR DAYS AFTER THE TEMPORARY IMPACT IS NO LONGER NECESSARY. THE IMPACTED AREAS SHALL BE RETURNED TO ORIGINAL GRADE, INCLUDING EACH STREAM'S ORIGINAL CROSS SECTIONAL DIMENSIONS, PLANFORM PATTERN, AND LONGITUDINAL BED PROFILE. ALL TEMPORARY IMPACTS SHALL BE RESTORED AND STABILIZED WITH NATIVE VEGETATION. 14. ALL PROPOSED AND APPROVED TEMPORARY PIPES/CULVERTS/RIP-RAP PADS ETC. IN STREAMS SHALL BE INSTALLED AS OUTLINED IN THE MOST RECENT EDITION OF THE NC SEDIMENT AND EROSION CONTROL PLANNING AND DESIGN MANUAL OR THE NCDOT BEST MANAGEMENT PRACTICES FOR CONSTRUCTION AND MAINTENANCE ACTIVITIES SO AS NOT TO RESTRICT STREAM FLOW OR CAUSE DIS -EQUILIBRIUM DURING USE OF THIS CERTIFICATION. 15. ANY RIP -RAP REQUIRED FOR PROPER CULVERT PLACEMENT, STREAM STABILIZATION, OR RESTORATION OF TEMPORARILY DISTURBED AREAS SHALL BE RESTRICTED TO THE AREA DIRECTLY IMPACTED BY THE APPROVED CONSTRUCTION ACTIVITY. ALL RIP -RAP SHALL BE PLACED SUCH THAT THE ORIGINAL STREAM ELEVATION AND STREAM BANK CONTOURS ARE RESTORED AND MAINTAINED, NOT RESULT IN THE DE -STABILIZATION OF STREAM BED OR BANKS UPSTREAM OR DOWNSTREAM OF THE AREA, AND NOT RESTRICT AQUATIC LIFE PASSAGE. 16. ANY RIP -RAP USED FOR STREAM OR SHORELINE STABILIZATION SHALL BE OF SIZE AND DENSITY TO PREVENT MOVEMENT BY WAVE, CURRENT, OR STREAM FLOWS, AND WILL CONSIST OF CLEAN ROCK OR MASONRY MATERIAL. RIP -RAP SHALL NOT BE INSTALLED IN THE STREAMBED EXCEPT IN SPECIFIC AREAS REQUIRED FOR VELOCITY CONTROL AND TO ENSURE STRUCTURAL INTEGRITY OF BANK STABILIZATION MEASURES. 17. ALL MECHANIZED EQUIPMENT OPERATED NEAR SURFACE WATERS SHALL BE INSPECTED, FUELED, LUBRICATED, AND MAINTAINED REGULARLY AND MAINTENANCE PERFORMED IN A MANNER TO PREVENT CONTAMINATION OF STREAM WATER FROM FUELS, LUBRICANTS, HYDRAULIC FLUIDS, OR OTHER TOXIC MATERIALS. 18. HEAVY EQUIPMENT WORKING IN WETLANDS SHALL BE PLACED ON MATS OR OTHER MEASURES TAKEN TO MINIMIZE SOIL DISTURBANCE. 19. THE CONTRACTOR OR OTHER RESPONSIBLE ENTITY SHALL REPORT ANY PETROLEUM SPILL OF 25 GALLONS OR MORE; ANY SPILL REGARDLESS OF AMOUNT THAT CAUSES A SHEEN ON SURFACE WATERS; ANY PETROLEUM SPILL REGARDLESS OF SIZE THAT OCCURS WITHIN 100 -FEET OF SURFACE WATER; AND ANY PETROLEUM SPILL LESS THAN 25 GALLONS THAT CANNOT BE CLEANED UP WITHIN 24 HOURS. r\�\A�\r\�\i 6» TRENCH 6» WIDTH NOT TO EXCEED 40 FEET BETWEEN COLLARS PLAN UTILITY LINE (DIAMETER VARIES) I"ll— CLASS B CONCRETE OR COMPACTED CLAY SECTION ANTI -SEEP COLLAR DETAIL UPDATED MARCH, 2017 NOT TO SCALE Lit CLAY CHANNEL PRECAST CONCRETE SANDBAGS NOTE: ALL DISCHARGE FROM DE -WATERING THE WORK AREA SHALL BE PUMPED TO EITHER A TEMPORARY SEDIMENT TRAP OR DE -WATERING SILT BAG PER DETAILS WATER LEVEL (FIELD VERIFY SANDBAGS AT ANY OPENINGS PRFC;AST DAM PLAN CHANNEL SANDBAGS CLASS B CLASS B SANDBAGS A 11"11"1 A M .... .. SECTION AA NOTES: 1. MATERIAL FROM THE CHANNEL SHALL NOT BE USED FOR COFFER DAM 2. CHANNEL SHALL BE DISTURBED THE MINIMUM REQUIRED FOR CONSTRUCTION AND WILL BE RESTORED TO ORIGINAL CONTOURS WHEN WORK IS COMPLETE. COIR MATTING BASE FLOW WATER ELEVATION ELEVATION ATER LEVEL IELD VERIFY) 3. ALTERNATIVE COFFER DAM MATERIAL IS ACCEPTABLE BUT SHALL BE APPROVED BY THE ENGINEER. 4. CIRCULAR OR RECTANGULAR CONFIGURATION MAY BE USED FOR CONSTRUCTION. COFFER DAN NOT TO SCALE BANK OR BENCH • TRENCH TOP OF MATTING TO A DEPTH OF AT LEAST 12", STAKE OR STAPLE IN PLACE, & BACKFILL TO DESIGN GRADE • MINIMUM 24" ECO-STAKESo INSTALLED ALONG TOE OF MATTING (INTERCEPT BETWEEN WATER SURFACE AND BANK) • 0.75" X 0.75" OPENINGS 460 G/M WEIGHT 12" ECO -STAKE (TYP.) 24" ECO -STAKE (TYP. ) 24" ECO -STAKE (TYP. ) COIR MATTING DETAIL NOT TO SCALE NO. I DATE I BY ECO-STAKEA MINIMUM 2' CENTERS ALONG BOTTOM • MINIMUM 1" OVERLAP AT JOINING SECTIONS OF COIR MATTING • 12" ECO -STAKES® INSTALLED IN BANK FLUSH WITH COIR MATTING ABOVE BOTTOM ROW OF 24" ECO-STAKESo • ECO-STAKESo SPACED AT MAXIMUM 3' CENTERS (APPROX.) BOTH DIRECTIONS REVISION DESCRIPTION r C) fw U) V U) C L.L m m iw �z O J LL z O N� U) OU) v! z �Q ry �wC7� Uo U Wz� w L 3: � � S W oY N W W U ti >: J m O w i W i W LL N LLI ' O � � o cv Uzc� W' 2E Q p z m zF_� O � a w (D o o U) z r) p Q w Q U w 0 U _j m LL �--i W x w w F" w O w � r C) fw U) V U) C L.L m m iw �z O J LL z O N� U) OU) v! z �Q ry J N W O z z z Q v! r J_ U Q Z W Q 0 z Z Q U) J (n �O w r/ � U SHEET C-1 08 1 L 3: � � S W oY N 0 W o0 ti >: J m O m i W i W LL N LLI ' O D W}� W' 2E Q p z m zF_� Q 4 Z w (D o (D U) z r) p Q w Q U w 0 0 U _j m LL J N W O z z z Q v! r J_ U Q Z W Q 0 z Z Q U) J (n �O w r/ � U SHEET C-1 08 PLAN 10 0 5 10 20 30 GRAPHIC SCALE 1 INCH= 10 FEET TO SOUTH CONNECTIONS \— PROPOSED TEMPORARY CONSTRUCTION ENTRANCE T F �0 PROPOSED TEMPORARY CULVERT \ \ PROPOSED LIMIT OF NCDOT OVERLAY . \ x -- . .\ �\ 100–YEAR- \ti FLOODPLAIN ...... . .... . ` �` ` \ ... PROPOSED SILT FENCE'.'.' �__ s. . . (DOUBLE ROW), TYP. �0 ............. .. . ..... .................. .. . ......... –� . .. \ --------------------- .---\- --------- --------------------- -- . . i--- .....---- ----- . . . . . . . . . . . . . . . . . . . 1 ............................ �. .. .. ..... ........ �. .............................. ......... ... ... PROPOSED CONNECT TO EXISTING 24" WATER LINE WITH 24"x24"x24" TEE, 2-24" BUTTERFLY VALVES AND BOXES PROPOSED CONNECT TO _ EXISTING 36" WATER LINE WITH 36"x36"x36" TEE, 2-36" 1 BUTTERFLY VALVES AND BOXES 0 V PROPOSED SILT FENCE (TYP.) �`� PROPOSED 36" TRANSMISSION MAIN UNDER EXISTING 24" WATER LINE :.:.:.:.: CONSTRUCT TEMPORARY �.:600TV, �. • a<� .... ACCESS RAMP ONTO FLOOD . . ... ..... PLAIN (REMOVE AND RESTORE) . .".. �. �#*;..... �..� .... ................................; .R.. .. \---.-. .. ........\ \ \ .......................................'\ ..... :� ��. .... i. \ ��\ . . . . . . . . . . . . . .. .. . .. . .. . . . . . . .. . .. . ,�\. .. . . . . . . .� . �o \ .�� .\..\. �. \ \ \ \ 2 . . . . . . . . . . . . . . . . . .. . . . . . . • . . --^�� . . _ �\ \. y �� � . \ . \ �� \ \ \ \ \ % . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . :�. . . . . . . . . . ..� .� \. . . . . . . . .rr� . . . . . . . . .\\. .\. \ . . . . . . . . . . . . . . . . . . . . . . .� � . . . . . . . . . . . � \. . . . . . . . . . . . . � . .� \ . ,� . . . . . . . . . . . . . . . . . . ... . i. ` \ \ . . . . . . . . O<\ \ \ \ \ \ \ \ PROPOSED 42" : ... \ .. ........`�'� .. TRANSMISSION MAIN ........ �. .. �: ,\°�� `�``\���� R`�s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i . . / . . . . . \ \ �,� �� �,\ . a . . . TO NORTH FORK .I . . . . ��. 1 \bl\ ... . . . . . \ WATER TREATMENT j y `< . . . . . . . . . . . . . . . . a PLANT ENTRANCE . j . .. l . . .\. . 1 . . . . . . . . . . . . . . . . . _. . . .\�. . .......................--�-1.. .... -� .. . ........•..-- ..-- a�3o i.. x .... ........1".. ........ ..... .\ . . .""1/- °° ... \`� ...\...� .-------- I �.;.� .............................� ............... ....... �. f . . . . . . . . . . . � . .t. . . . . . . . . . ,�� . . --------•-• \�� �� i . -"- -- PROPOSED LIMITS ... .._.. �........ . �,�o...\.....�..�. ��.��\.....�.. .... OF DISTURBANCE i" i �� . . . . . . /ry . :�. ;. _.���., �� ". . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . �..\.l. �..... .. .... ...........�"...... ..,......:�\..,".\................................................ �' . .�\`��...............................................\ ........"\. ..........". ;..\�.......�o................................................. ....:.:........" .::..... .....� :.:.:.:.:.:.�.. ........ �.. PROPOSED . -"- . .......PERMANENT TEMPORARY CULVERT............................................... .......MAINTENANCE A................................................................... \ `..... Q�........... ................................................... CORRIDOR-" 0*-------•----------•--•-------•--•.................................. .. ...�........... ........ \ 20' MAX WIDTH ------- .................. � - -------------------------------------------------------------------- ...... ...................... ...... ......... .................. �. ...... ..........WETLAND A. ........... .................. . ............................... . ;..------------------------ *.....-----.100–YEAR............................................. ------------- LIMITS OF .-- ♦---------............................................. .................. DISTURBANCE ; FLOODPLAIN_._._._._._._._._._._....._._............................... . ---------------•45' MAX WIDTH .. .� ................................................................................................................ """"""""""""""""""""""""""".......-*+-------------------------- ........... """"""-"""""""""""""""""""----------.................................................... NO. I DATE I BY REVISION DESCRIPTION Q a z w cin W v w J z mm�o �z W = z tn � Oct 0 o� � w z g c) � Z >= O V m �WCl� U� U Wz� W L i ce)o z w U w M J o cv Uz00 M--� N N LL N W 00 W } Oda 2 � o ^� 0 000 N ZZ 0Qwawowo� � U z p LD U) Z a) � � w x Ln U W¢ U 1— W� w d W� V PROPOSED SILT FENCE (TYP.) �`� PROPOSED 36" TRANSMISSION MAIN UNDER EXISTING 24" WATER LINE :.:.:.:.: CONSTRUCT TEMPORARY �.:600TV, �. • a<� .... ACCESS RAMP ONTO FLOOD . . ... ..... PLAIN (REMOVE AND RESTORE) . .".. �. �#*;..... �..� .... ................................; .R.. .. \---.-. .. ........\ \ \ .......................................'\ ..... :� ��. .... i. \ ��\ . . . . . . . . . . . . . .. .. . .. . .. . . . . . . .. . .. . ,�\. .. . . . . . . .� . �o \ .�� .\..\. �. \ \ \ \ 2 . . . . . . . . . . . . . . . . . .. . . . . . . • . . --^�� . . _ �\ \. y �� � . \ . \ �� \ \ \ \ \ % . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . :�. . . . . . . . . . ..� .� \. . . . . . . . .rr� . . . . . . . . .\\. .\. \ . . . . . . . . . . . . . . . . . . . . . . .� � . . . . . . . . . . . � \. . . . . . . . . . . . . � . .� \ . ,� . . . . . . . . . . . . . . . . . . ... . i. ` \ \ . . . . . . . . O<\ \ \ \ \ \ \ \ PROPOSED 42" : ... \ .. ........`�'� .. TRANSMISSION MAIN ........ �. .. �: ,\°�� `�``\���� R`�s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i . . / . . . . . \ \ �,� �� �,\ . a . . . TO NORTH FORK .I . . . . ��. 1 \bl\ ... . . . . . \ WATER TREATMENT j y `< . . . . . . . . . . . . . . . . a PLANT ENTRANCE . j . .. l . . .\. . 1 . . . . . . . . . . . . . . . . . _. . . .\�. . .......................--�-1.. .... -� .. . ........•..-- ..-- a�3o i.. x .... ........1".. ........ ..... .\ . . .""1/- °° ... \`� ...\...� .-------- I �.;.� .............................� ............... ....... �. f . . . . . . . . . . . � . .t. . . . . . . . . . ,�� . . --------•-• \�� �� i . -"- -- PROPOSED LIMITS ... .._.. �........ . �,�o...\.....�..�. ��.��\.....�.. .... OF DISTURBANCE i" i �� . . . . . . /ry . :�. ;. _.���., �� ". . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . �..\.l. �..... .. .... ...........�"...... ..,......:�\..,".\................................................ �' . .�\`��...............................................\ ........"\. ..........". ;..\�.......�o................................................. ....:.:........" .::..... .....� :.:.:.:.:.:.�.. ........ �.. PROPOSED . -"- . .......PERMANENT TEMPORARY CULVERT............................................... .......MAINTENANCE A................................................................... \ `..... Q�........... ................................................... CORRIDOR-" 0*-------•----------•--•-------•--•.................................. .. ...�........... ........ \ 20' MAX WIDTH ------- .................. � - -------------------------------------------------------------------- ...... ...................... ...... ......... .................. �. ...... ..........WETLAND A. ........... .................. . ............................... . ;..------------------------ *.....-----.100–YEAR............................................. ------------- LIMITS OF .-- ♦---------............................................. .................. DISTURBANCE ; FLOODPLAIN_._._._._._._._._._._....._._............................... . ---------------•45' MAX WIDTH .. .� ................................................................................................................ """"""""""""""""""""""""""".......-*+-------------------------- ........... """"""-"""""""""""""""""""----------.................................................... NO. I DATE I BY REVISION DESCRIPTION Q a z w cin W v w J z mm�o �z W = z tn � Oct 0 o� � w z g c) � Z >= O V m Z O F--- r -- c) Z Lu w Z 2 Z W O(D U � I J W O Z SHEET L i ce)o Q >Y� M J p > W > W LL N W W } W 2 � M ZZ 0Qwawowo� LLI C� p LD U) Z a) � p p U p U 1— Z O F--- r -- c) Z Lu w Z 2 Z W O(D U � I J W O Z SHEET