HomeMy WebLinkAbout20061581 Ver 1_Emails_20061106Re: WiRO Tracking and Tardy Projects
Subject: Re: WiRO Tracking and Tardy Projects
From: Noelle Lutheran <Noe1le.Lutheran@ncmail.net>
Date: Mon, 06 Nov 2006 10:35:07 -0500
To: Ian McMillan <ian.mcmillan@ncmail.net>
Yes, it was concerning whether or not you (Raleigh Office) needs complete CAMA
applications? Question came up because I realized that DCM has not been providing
your office with revised CAMA Major applications. Sometimes, due to multiply
agency concerns, the applicant makes revisions and DCM circulates them to the
agencies, but not you. I became aware when some projects were not appearing on my
tracking list but were close to the deadline. I asked DCM to provide you with
copies also. Morehead City does not seem to have an issue with this, but our DCM
office does. They do not see the need to provide two copies to one agency. They
already have to provide many copies.....
I can copy it and send it to you, but sometimes full plan sheets are involved. My
supervisor wants to know if you really need a full copy of the revisions. I say
"yes".
Ian McMillan wrote:
Hey! You left me a message Friday and I forgot what it pertained to... do you
remember? Thanks, Ian
Noelle Lutheran wrote:
Listed below are status reports on the listed projects. For some projects, we
have been entering "no 401, deemed issued" which, we have learned does not
close out a project on BIMS. So, I plan to discuss with Reeder and Beverly to
find out the preferred way of entering the data, but for now...it is not as
bad as it looks!
*
*
*Wilmington **
_Tracking: _
_*06-1699, *St. James By The Sea, Brunswick Co, CAMA EXP 10/30/06 11/28/06
No 401 Required, entered BIMS 11/1/06
*06-1581, *New Hanover County Well Field & Water Tx Plant, New Hanover Co,
LAMA 9/29/06 11/27/06
USACE IP, No Public Notice yet as far as I know.
*06-1568, *Live Oak Community Docks, Onslow Co, CAMA 9/27/06 11/25/06
Issued...Deemed issued under 3402 and 3494, copy GC sent.
*99-1035, Ver. 2, *Forest Sound Breakwater, Pender Co, CAMA 9/20/06 11/18/06
*06-1274, *The Villages At Turtle Creek - Phase I, PPender Co, NW39 9/18/06
11/16/06
Issued 11/3/06.
_Tardy:_
*06-1571, *Yopp:* *7510 River Road, Tract* *3, New Hanover Co, NW18 9/28/06
10/26/06
Deemed issued after 30 days 10/26/06. Copy GC sent 11/1/06.
*06-1402, *CHC Excavation Site, Brunswick Co, NW44 9/0806 11/06/06
Issued 11/1/06.
*06-1510, *TOPine Knoll Shores, Carteret Co, LAMA 9/15/06 11/13/06
1 oft 11/]4/200610:30AM
Re: WiRO Tracking and Tardy Projects
No 401 required, entered BIMS 10/18/06.
*06-1129, *Willow Woods SD,* *Brunswick Co, NW39 9/15/06 11/13/06
Issued 11/1/06.
*06-0197, *Helmsdale At Landfall,* *New Hanover Co, IP Due 11/13/06 **
*06-1488, *H. Johnson Sifly, New Hanover Co, LAMA 9/1306 11/11/06
No 401 required, entered BIMS 10/18/06.
*OS-0813, Ver. 2, *Mimosa Bay SD, Onslow Co, NW39 9/13/06 11/11/06
Additional information receivedll/1/06.