Loading...
HomeMy WebLinkAbout19920652 Ver 1_COMPLETE FILE_19920116 DEPARTMENT OF THE ARMY WILMINGTON DISTRICT, CORPS OF ENGINEERS P.O. BOX 1890 WILMINGTON, NORTH CAROLINA 28402-1890 IN REPLY REFER TO December 22, 1992 Regulatory Branch Action ID. 199300754 and Nationwide Permit Numbers 14 (Road Crossing) and 26 (Headwaters. and Isolated Waters) City of Raleigh Attn.: Mr. Dempsey E. Benton City Manager Department of Public Utilities 222 West Hargett Street Raleigh, North Carolina 27602 Dear Mr. Benton: JAN -- 719W Reference the application of October 29, 1992, submitted on your behalf by Hazen and Sawyer, for Department of the Army authorization to discharge fill material within waters of the United States, in association with the construction of the Neuse River Wastewater Treatment Plant, Expansion and Upgrade, Phase 3, east of Raleigh, Wake County, North Carolina. You propose to construct a spill containment area causing the loss of less than 1/3 acre of an unnamed tributary to the Neuse River, and to construct a structural terra-gator bridge crossing of the Neuse River requiring bank stabilization. For the purposes of the U.S. Army Corps of Engineers' Regulatory Program, Title 33, Code of Federal Regulations (CFR), Part 330.6, published in the Federal Register on November 22, 1991, lists nationwide permits (NWP). Authorization was provided, pursuant to Section 404 of the Clean Water Act, for discharges of dredged or fill material into headwaters and isolated waters provided: a. The discharge does not cause the loss of more than 10 acres of waters of the United States; b. The permittee notifies the District Engineer if the discharge would cause the loss of waters of the United States greater than one acre in accordance with the "Notification" general condition. For discharges in special aquatic sites, including wetlands, the notification must also include a delineation of affected specific aquatic sites, including wetlands; and c. The discharge, including all attendant features, both temporary and permanent, is part of a single and complete project. Authorization, pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act, was also provided for bank stabilization activities provided: AF')? -2- a. No material is placed in excess of the minimum needed for erosion protection; b. The bank stabilization activity is less than 500 feet in length; c. The activity will not exceed an average of one cubic yard per running foot placed along the bank below the plane of the ordinary high water mark or the high tide line; d. No material is placed in any special aquatic site, including wetlands; e. No material is of the type or is placed in any location or in any manner so as to impair surface water flow into or out of any wetlands area; f. No material is placed in a manner that will be eroded by normal or expected high flows; and g. The activity is part of a single and complete project. Your work is authorized by these NWP provided it is accomplished in strict accordance with the enclosed conditions. These NWP do not relieve you of the responsibility to obtain any required State or local approval. This verification will be valid for 2 years from the date of this letter unless the NWP authorization is modified, reissued, or revoked. Also, this verification will remain valid for the 2 years if, during that period, the NWP authorization is reissued without modification or the activity complies with any subsequent modification of the NWP authorization. If during the 2 years, the NWP authorization expires or is suspended or revoked, or is modified, such that the activity would no longer comply with the terms and conditions of the NWP, activities which have commenced (i.e., are under construction) or are under contract to commence in reliance upon the NWP will remain authorized provided the activity is completed within 12 months of the date of the NWP's expiration, modification or revocation, unless discretionary authority has been exercised on a case-by-case basis to modify, suspend, or revoke the authorization. Questions or comments may be addressed to Mr. Eric Alsmeyer, Raleigh Regulatory Field office, at telephone (919) 876-8441, extension 23. Sincerely, G. Wayne Wright Chief, Regulatory Branch Enclosure -3- Copy Furnished (with enclosure): Hazen and Sawyer Attn.: Mr. Benjamin L. Roach, P.E., Associate 4011 Westchase Boulevard, Suite 500 Raleigh, North Carolina 27607 Copies Furnished (without enclosure): Mr. Mike Coughlin Environmental Engineer Wake County Community Development Services Post Office Box 550 Raleigh, North Carolina 27602 Mr. John Parker North Carolina Department of Environment, Health and Natural Resources Post Office Box 27687 Raleigh, North Carolina 27611-7687 Mr. John Dorney Water Quality Section Div sion of Environmental Management N th Carolina Department of Environment, Health and Natural Resources Post Office Box 27687 Raleigh, North Carolina 27611-7687 ,,«.. 'e ST State of North Carolina Department of Environment, Health, and Natural Resources Division of Environmental Management 512 North Salisbury Street • Raleigh, North Carolina 27604 James G. Martin, Governor A. Preston Howard, Jr., P.E. William W. Cobey, Jr., Secretary November 9, 1992 Acting Director Dale Crisp City of Raleigh 222 West Hargett St. Raleigh, NC 27602 Dear Mr. Crisp: Subject: Proposed Fill in Wetlands or Waters Spill containment facility Wake County DEM Project #92652 Upon review of your request for Water Quality Certification to place fill material in less than one-third acre of wetlands or waters for spill containment facility located at Raleigh wastewater treatment plant in Wake County, we have determined that the proposed fill can be covered by General Water Quality Certification No. 2671 and 2745 issued January 21, 1992. A copy of the General Certification is attached. This Certification may be used in qualifying for coverage under Corps of Engineers' Nationwide Permit No. 25 and 26. If you have any questions, please contact John Dorney at 919/733-1786 or 919/733-1787. Sincerely, f 1 IJ Preston Howard Jr. P.E. APH:JD U Attachment cc: Wilmington District Corps of Engineers Corps of Engineers Raleigh Field Office Raleigh DEM Regional Office Mr. John Dorney Central Files Benjamin Roach, Hazen and Sawyer REGIONAL OFFICES Asheville Fayetteville Mooresville Raleigh Washington Wilmington Winston-Salem 704/251-6208 919/486-1541 704/663-1699 919/571-4700 919/946-6481 919/395-3900 919/896-7007 Pollution Prevention Pays P.O. Box 29535, Raleigh, North Carolina 27626-0535 Telephone 919-733-7015 An Equal Opportunity Affirmative Action Employer RAZEN AND SAWYER Environmental Engineers & Scientists October 29, 1992 Mr. Eric Alsmeyer, Area Coordinator U.S. Army Corps of Engineers Regulatory Field Office 6512 Falls of Neuse, Suite 105 Raleigh, NC 27615-6846 Hazen and Sawyer, P. C. 4011 WestChase Blvd. Raleigh, NC 27607 919 833-7152 Fax: 919 833-1828 C LL9 z NOV - 5 g;,.. Re: Neuse River Wastewater Treatment Plant Proposed Spill Containment Area and Proposed Terra-Gator Bridge Over Neuse River H&S No. 3971 Dear Mr. Alsmeyer: Attached for your review are preliminary Drawings and construction procedures for the above referenced projects. We request construction approval of these projects based on satisfaction of the permit requirements of Section 404 of the Clean Water Act. As you discussed with Mr. Chris Phillips and Mr. Alan Stone of Hazen and Sawyer on Wednesday, October 21, 1992 at the job site, we request approval under nationwide permit No. 26 for the proposed spill containment area and nationwide permit No. 25 for the proposed Terra-Gator bridge to satisfy the Section 404 permit requirements. The spill containment area is being built to help prevent any harmful waste from being discharged into the Neuse River. If any kind of waste or chemical were spilled into the plant's storm drainage system, the waste could be captured in the spill containment area. A preliminary construction plan of the spill containment area is included as Attachment No. 1. The total area disturbed is less than 1 /3 acre. The Terra-Gator bridge is proposed to gain access to sludge application fields located across the Neuse River from the wastewater treatment plant without using public roads. The proposed bridge is as a low-water bridge designed to be inundated during a 10-year plus storm event. Recent HEC-2 analyses by Hazen and Sawyer indicate that the bridge will not cause a rise in flood elevation at the bridge for the 100-year event. A preliminary General Drawing of the bridge is included as Attachment No. 2 and the construction sequence for the bridge is included as Attachment No. 3. The proposed construction sequence is based on a New York, NY - Armonk, NY - Upper Saddle River, NJ - Raleigh, NC - Charlotte, NC - Richmond, VA - Hollywood, FL - Boca Raton, FL - Fort Pierce, FL - Jupiter, FL - Miami, FL - Bogota, D.E. Colombia T HAZEN AND SAWYER Mr. Eric Alsmeyer, Area Coordinator October 29, 1992 Page 2 substructure using HP12X53 piles encased in concrete to a depth of 18" below the river bed. A subsurface investigation is currently in progress to determine if bedrock is at a sufficient depth below the riverbed to allow sufficient penetration of the HP12X53 piles to develop adequate lateral stability. If bedrock is too shallow, the interior support piers will be supported on concrete piles battered as necessary to resist the lateral loads. This alternative will not require construction of a pile encasement. Therefore, a coffercell will not be constructed, and nationwide permit No. 25 will probably not be applicable. We will advise when this decision is reached. By copy of this letter I am transmitting the referenced attachments to Mr. John Dorney of DEM requesting a 401 Water Quality Certification. We understand that the general 401 certification to be issued by DEM is for work required under nationwide permits 26, 25 and 13. The total length of stream bank stabilization is less than 500 linear feet. We further understand that written application to DEM is not required but we are providing them this information for their records. Please advise if further information is needed or if additional permits are required. Very truly yours, HAZEN AND SAWYER, P.C. B n L. Roach, P.E. Associate BLR/wp Enclosure cc: Mr. Dale Crisp, P.E., City of Raleigh Mr. John Dorney, DEM w/attachments Mr.' Bob DiFiore Mr. Bennie Meeks .. ......... ./ J4 ''. ........ /' .. ....... ...... :............. ta a z 0 N .........I., Z z I-I M 0 .. ,f II Z r m z O N P$ zimR ilt 2A.Z n C Nci Dm> ?? m ?y $ ED zn W bmz J _ un ? z - --- - --- --- - --- Nf II N= ?N? ? II 4T N I 1 1 1 1? 1 1 1 v = -Z-?` 000 ZAa;Z?l 'v=w i ATTACHMENT NO. 3 Terra-Gator Bridge Over Neuse River Construction Procedure 1. Install and maintain specified erosion control measures. 2. Clear area, excavate and stabilize banks as shown on Drawings. 3. Drive piles for end bents and interior piers, using barge if necessary. 4. Construct temporary coffer cells around piles for interior piers using sandbags. Pump water out of coffercells. 5. Excavate 18" minimum below river bed and construct pile encasement using watertight formwork. (Specifications will require this.) 6. Strip formwork and backfill with graded stone around encasements 18" minimum into riverbed. 7. Remove sand bag coffercells: 8. Construct pile caps for end bents and interior piers. Construct wing walls at end bents. 9. Place rip-rap slope protection at end bents and complete excavation, embankments, and subgrade preparation for roadway and approach slabs at end bents. 10. Set precast slab sections on all spans and post tension transverse strands. 11. Place concrete for bridge topping, curbs, and approach slabs. 12. Remove all construction debris from site and stabilize all disturbed areas by seeding and mulching. C - / PRINTED IN U.S.A. ? RX "_ _1G I I I ATTENTION (919) 833-7152 FAX(919)833-1828 TO ?V. OF Q.)VIP?ti11uTCD? ?'1 G? ? l2. N . S?t.1 SOU ? STET > WE ARE SENDING YOU A Attached ? Under separate cover via DATE ? /? JOB NO. A . 1 W G? RE: N 1, 7g Q)A5Te7W A?a_P- - r2 _rwte rr P _4dlrr P12onosf?v C?o?rT,at N A"IC) 'P?2oPasem -rea"- AkTbt2 -62lr-C1F Ov?1Z N?usc ?vE?2? the following items: ? Shop drawings ? Prints ? Plans ? Samples ? Specifications ? Copy of letter ? Change-order ? COPIES DATE NO, DESCRIPTION N ?e P_A 12. S 1 u, CQNT&4NMtQKrr A-NJ rD -T Ca - A-Tb M I A NOV 30 1992 _ - ,. t1 DEC f t, THESE ARE TRANSMITTED as checked below: X For approval _' Approved as submitted J Resubmit copies for approval ? For your use C Approved as noted Submit copies for distribution ? As requested Returned for corrections L_ Return corrected prints IL For review and comment f2 \ 1 12. 95C.( Il2_QJ E FOR BIDS DUE 19 J PRINTS RETURNED AFTER LOAN TO US REMARKS 6NCA 02 V-_01Z Y 0 O KZ A40191ZOVArt, keNYD I2eZ_,QaLs IS A, CA(2?1 OP Al t?_Te1z I,,s? CAA i)OAtS Syf;M127DM -No 7H'P,;? C,00r-r> ov ' ?T1 G I N ?E125 r?o rZ ?n 120?? YLP,G ?"?[ N G -C I-?E prLp noS? SP ILA_ 'CO ?sTbe1 N Me-NR AA1-? A-N>] -rihri,_weus V QJ tA'"12 v? D-s??Lv,0?2. -tfQ t rvt lsf P L-A r ' I ?(a V ('11V COPY TO SIGNED: IA_ If enclosures are not as noted, kindly notify u at one MINNW SAWYER Environmental Engineers & Scientists 4011 Westchase Boulevard, Suite 500 Raleigh, NC 27607 ?. -xG wYe_l - HAZEN S.MWE Environmental Engineers & Scientists 4011 Westchase Boulevard, Suite 500 Raleigh, NC 27607 (919) 833-7152 FAX(919)833-1828 C PRINTED IN U.S.A. TO 'iV. LFJ'?lt. DATE 2,0- 0 JOB NCO" - _41 ATTENTION RE: rJ USE >4=-r +,i< (? i.:' ?;1-?c;St:-L -r r? ti? K'??- Cl`?. + urz !'? 1 !>Gi>=. L ?G k N --USE k l vt _. > WE ARE SENDING YOU ;, Attached ? Under separate cover via the following items: ? Shop drawings ? Prints ? Plans ? Samples ? Specifications ? Copy of letter ? Change order ? COPIES DATE NO. DESCRIPTION i? 1 -LA 6, 1,1 THESE ARE TRANSMITTED as checked below: YZ, For approval Approved as submitted ? Resubmit copies for approval ? For your use E As requested E For review and comment O FOR BIDS DUE ? Approved as noted ? Submit-copies for distribution ? Returned for corrections ? Return corrected prints 19 ? PRINTS RETURNED AFTER LOAN TO US REMARKS ( L)rl ('IL1) QL' ( y L) YG A 4Y V t)VAt_ A 1"JY) Il E-C-Ap ?_'_ 1?? I S '& C_z)i iii= A Lt,` i E 1L lk) I-L1 LP AS S I, Iii LA I ?'?l -.3 I Ltt, LID( 1-?_ 0?7-Z l,_l rI I H L2 iC_ C * r) CZ t_?VL\ L Y L_ ?r1 'PG l r N C i i '(_: P 1C U V-`0S?' yJIL,-_"t,UJI?- t_ -k r? E -4,7 "i?'l c-MT }>L'4?t') ( I 0 t 1/ (?N y f l f1?1 I="YSTS t?? i) F S 1 I C i?J S ?I ' i;= Z\ C ,k? T C_T i i Y zpjE \ COPY TO SIGNED: If enclosures are not as noted, kindly notify u at oncl6l ("%SU-7M FAX (919) 833 IM TO`?if.? i.1 t1 ;A L 12 cc T DATE iF L JOB NO,_ ?? .? (F ATTENTION RE: ? . 3 6X ... ATTACHMENT NO. 3 Terra-Gator Bridge Over Neuse River Construction Procedure 1. Install and maintain specified erosion control measures. 2. Clear area, excavate and stabilize banks as shown on Drawings. 3. Drive piles for end bents and interior piers, using barge if necessary. 4. Construct temporary coffer cells around piles for interior piers using sandbags. Pump water out of coffercells. 5. Excavate 18" minimum below river bed and construct pile encasement using watertight formwork. (Specifications will require this.) 6. Strip formwork and backfill with graded stone around encasements 18" minimum into riverbed. 7. Remove sand bag coffercells. 8. Construct pile caps for end bents and interior piers. Construct wing walls at end bents. 9. Place rip-rap slope protection at end bents and complete excavation, embankments, and subgrade preparation for roadway and approach slabs at end bents. 10. Set precast slab sections on all spans and post tension transverse strands. 11. Place concrete for bridge topping, curbs, and approach slabs. 12. Remove ail construction debris from site and stabilize all disturbed areas by seeding and mulching. ffim, IND SAWYER Mr. Eric Alsmeyer, Area Coordinator October 29, 1992 Page 2 substructure using HP12X53 piles encased in concrete to a depth of 18" below the river bed. A subsurface investigation is currently in progress to determine if bedrock is at a sufficient depth below the riverbed to allow sufficient penetration of the HP12X53 piles to develop adequate lateral stability. If bedrock is too shallow, the interior support piers will be supported on concrete piles battered as necessary to resist the lateral loads. This alternative will not require construction of a pile encasement. Therefore, a coffercell will not be constructed, and nationwide permit No. 25 will probably not be applicable. We will advise when this decision is reached. By copy of this letter I am transmitting the referenced attachments to Mr. John Dorney of DEM requesting a 401 Water Quality Certification. We understand that the general 401 certification to be issued by DEM is for work required under nationwide permits 26, 25 and 13. The total length of stream bank stabilization is less than 500 linear feet. We further understand that written application to DEM is not required but we are providing them this information for their records. Please advise if further information is needed or if additional permits are required. Very truly yours, HAZEN AND SAWYER, P.C. Benjamin L. Roach, P.E. Associate BLR/wp Enclosure cc: Mr. Dale Crisp, P.E., City of Raleigh Mr. John Dorney, DEM w/attachments Mr. Bob DiFiore Mr. Bennie Meeks HAZEN AND SAWYER Environmental Engineers & Scientists October 29, 1992 Mr. Eric Alsmeyer, Area Coordinator U.S. Army Corps of Engineers Regulatory Field Office 6512 Falls of Neuse, Suite 105 Raleigh, NC 27615-6846 Hazen and Sawyer. P. C. 4011 WestChase Blvd. Raleigh. NC 27607 919 833-7152 Fax: 919 833-1828 Re: Neuse River Wastewater Treatment Plant Proposed Spill Containment Area and Proposed Terra-Gator Bridge Over Neuse River H&S No. 3971 Dear Mr. Alsmeyer: Attached for your review are preliminary Drawings and construction procedures for the above referenced projects. We request construction approval of these projects based on satisfaction of the permit requirements of Section 404 of the Clean Water Act. As you discussed with Mr. Chris Phillips and Mr. Alan Stone of Hazen and Sawyer on Wednesday, October 21, 1992 at the job site, we request approval under nationwide permit No. 26 for the proposed spill containment area and nationwide permit No. 25 for the proposed Terra-Gator bridge to satisfy the Section 404 permit requirements. The spill containment area is being built to help prevent any harmful waste from being discharged into the Neuse River. If any kind of waste or chemical were spilled into the plant's storm drainage system, the waste could be captured in the spill containment area. A preliminary construction plan of the spill containment area is included as Attachment No. 1. The total area disturbed is less than 1 /3 acre. The Terra-Gator bridge is proposed to gain access to sludge application fields located across the Neuse River from the wastewater treatment plant without using public roads. The proposed bridge is as a low-water bridge designed to be inundated during a 10-year plus storm event. Recent HEC-2 analyses by Hazen and Sawyer indicate that the bridge will not cause a rise in flood elevation at the bridge for the 100-year event. A preliminary General Drawing of the bridge is included as Attachment No. 2 and the construction sequence for the bridge is included as Attachment No. 3. The proposed construction sequence is based on a mew Yon. NY . Armonk. NY - Upper Saadle River. NJ - Rakign, NC - CWti te. NC - Ricnmond. VA - Hol"Od. FL • Bow Raton. FL - Fort Pierce. FL - Jupiter. FL - Miami, FL - Bogota. O.E. Colomoia