Loading...
HomeMy WebLinkAboutVer _COMPLETE FILE_19990901d INV o? 3 ?u J 0 J 3 ? z g? A z v ?r a. N z im Z C. E ap a , ohs oc g L 8 q r t? v Q Ol W 49 Z1 O V O O v 8 CESAW-PD-E 1 Sep 94 MEMORANDUM FOR: All Participants SUBJECT: FY 94 Dredging Coordination Meeting 1. The FY 94 Dredging Coordination Meeting was held in Wilmington, North Carolina on 18 August 1994. The agenda for this meeting is included as attachment 1, dredging projects for FY 95 are included as attachment 2, and attendees are listed as attachment 3. Following is a synopsis of the meeting and required follow-up actions. 2. Review of FY 95 Operation & Maintenance (O & M) Protects. i? Eleven (11) O & M dredging projects are scheduled for FY 95 and are listed ? in attachment 2. Discussion on this topic was limited as most of the areas to be dredged in FY 95 are dredged on an annual basis and no changes to past dredging practices are anticipated. The projects discussed included: a. Alligator Pungo Land Cut (AIWW). In the past, dredged material from this channel was placed, on the toe of the bank, however, in FY 95 the dredged material will be placed in upland diked disposal sites along the north bank of the channel. An EA/FONSI for this work was completed in November 1993. b. AIWW Inlet Crossings. The AIWW inlet crossings will be dredged as usual. Material from Lockwoods Folly Inlet Crossing will be pumped to Long Beach. During the discussion of inlet crossings 2 questions regarding dredging of other areas were raised: 1) A question was asked regarding the status of dredging in the AIWW between Surf City and New River Inlet (Section III, Tangents 2-6). The EA for this project is currently out for 30-day review. Assuming no unresolved issues arise during the comment period, it is anticipated that a FONSI will be signed. A Public Notice will be circulated and dredging should take place in FY 95. 2) A DEM representative asked why material from Shinn Creek and Bogue Inlet Crossing was placed in upland diked disposal sites rather than being pumped to the beach. It was stated that due to the pumping distance and small amount of material from these areas, it was infeasible to pump the material to the beach. This led to a discussion of the recent amendments to the Dredge and Fill Law. The implications of the new legislation are not fully understood at this time. The Corps is in the process of putting together a coordinated response to the Division of Water Resources with regard to the new legislation in an effort to determine the implications of the amendments. C. Wilmington Harbor - Anchorage Basin and 38-Foot Project. These projects will go out on two separate contracts. Material from the Anchorage Basin will go to Eagle Island and dredging is scheduled to take place in September or October 1994. The 38-Foot Project will be dredged in October 1994 and material will go to the Ocean Dredged Material Disposal Site (ODMDS). d. Channel from Back Sound to Lookout Bight. A concern was raised regarding the deterioration of sandbags at the Harkers Island disposal site. The Corps will investigate this problem the next time material is placed on Harkers Island. e. Wainwright Slough. Dredged material from Wainwright Slough is usually placed on the channel-side toe of Wainwright Island. However, this material is being washed back into the channel at an undesirably fast rate. The Corps will investigate alternative disposal sites, one of which would be the back side of the island. It is thought that resources of concern (SAV)-might be present on the back side of the island, therefore, any changes to the current method of disposal would be looked at carefully and coordinated with all appropriate agencies. Walker Golder of the National Audubon Society stated that Wainwright Island desperately needs more dredged material for bird habitat. Mr. Golder provided attendees with the numbers of nesting terns on Wainwright Island for the past few years. Just a few years ago, 6000 to 8000 pairs of terns were nesting on Wainwright Island, last year 2000 pairs nested, and this year 0 pairs nested. The Corps indicated that a decision regarding dredged material disposal for this project would be forthcoming. f. Cape Fear River Above Wilmington. This project is done routinely with a pipeline dredge and toe-of-the-bank disposal. However, the Corps is investigating the possibility of using a sidecast dredge for upcoming. work. This will be coordinated with all interested agencies. g. Wilmington Harbor - Ocean Bar Channel. This project will entail the deepening of the channel to its authorized depth of 401. This dredging is scheduled to start in September 1994 and will require the removal of rock; disposal of the rock is discussed in paragraph 3.j.. h. Morehead City Harbor - Outer Harbor (Ocean Bar Channel). This will be dredged in FY 95. Hydrographic surveys have not yet been completed. The nearshore berm associated with this project is discussed in paragraph 3.i. 3. Project/Study Updates. a. AIWW Longterm Study - The purpose of this study is to develop a 50-year maintenance and management plan for the AIWW. This will be accomplished in three (3) phases: Phase I - Acquisition of aerial photography, Phase II - A plan of action, and Phase III - Data collection and analysis leading to a management plan (to cover the next 50 years). Funding for this project has been sporadic over the past few years. However, Construction-Operations (Corps) has stated that they are committed to funding this study for the next 3 years in order that it may be completed. During this discussion three (3) questions were raised: 1) What changes for the AIWW, if any, are envisioned? Will there be changes in uses of the AIWW, maintenance, management, etc.? No major changes to current practices are envisioned. The purpose of the long-term study is to compile all available data in an attempt to project future maintenance needs of the AIWW. Two significant portions of the study will involve investigation of areas for future disposal and investigation of encroaching development on the AIWW. 7, 2) Will it be feasible to include analyses of dredged material as part of this study? Yes, sediment analyses will be conducted for the main purpose of determining the availability and location Qf beach quality material. These analyses will be a significant part of Phase IT of the study. Also, in Phase III of the study, the Corps will investigate the possibility of pumping dredged material from previously used disposal sites to the beach. 3) Is the Corps surveying disposal sites to determine their availability for future use? Yes. Numerous sites have already been surveyed and sites that could prove to be useful in the future will be surveyed during Phase III of the long-term study. As part of this process the Corps will be looking closely at easements, piers, etc. that may affect the accessibility of potential disposal sites. b. Morehead City Harbor. This project was completed last year. There was some concern about the impacts of the project on nearshore fisheries and a study regarding those impacts has been completed by North Carolina Division of Marine Fisheries (NCDMF). Generally, the study, referred to as the "Mullet Project Report," found that impacts were insignificant. Copies are available in Morehead City office of NCDMF. c. Sandbagged Disposal island - Old House Channel. During the FY 94 dredging coordination meeting the possibility of changing the current method of sandbagging on this island was discussed. The suggestion was made by the Corps to pump material onto the island and then sandbag it, rather that sandbagging the island.prior to pumping material. However, due to the timing of dredging it was decided to revert to the previously used method of placing the sandbags then pumping material. Work on this project is ongoing. At this time approximately 1/4 of the sandbags have been placed on the island. Mitigation for this is discussed in paragraph 3.f. d. Colonial Nesting Waterbird Islands. The two islands in the Cape Fear River, Ferry Slip and South Pelican Islands were considered for placement of material from the Wilmington Harbor 38-foot project in FY 95. Ferry Slip Island was surveyed and is right at 7 acres, the allowed size. South Pelican Island was not surveyed but is believed to also be about 7 acres. Therefore, no material will be disposed of on either island in FY 95. We will continue to monitor the two islands and hopefully place material on them, as needed. The need to try to maintain the nesting habitat at Big Foot Slough was discussed. Big Foot Slough is a sandbagged disposal site which after disposal is at or above mean high water. However, the material washes away within a year's time and habitat is lost. The Corps agreed to investigate possible solutions. A question was raised regarding the initiation of this investigation and it was decided that Tom Henson, NCWRC, would head up the investigation through the Colonial Waterbird Comittee and report back to the Corps. The majority of the agencies present are partners to the Colonial Waterbird Cooperative Agreement and a meeting will be called soon to discuss the concerns. Trudy Wilder, is the Corps colonial Waterbird representative. Walker Golder gave statistics on numbers of colonial nesting waterbirds in North Carolina and stated that 66%- of all waterbirds in North Carolina nest on undiked dredged material disposal islands. The erosion of Battery Island was also brought to everyone's attention. Battery Island has the largest population of wading birds in North Carolina and erosion is causing trees to fall into the water. The Corps was asked to help with this situation if possible. e. SAV Impact Assessment, Walter Slough Channel. The 1990 emergency dredging of Walter Slough channel was conducted with a sidecast dredge. To do the work in this manner, the Corps made the commitment to determine the impacts on SAV. The Corps has been working with NMFS to assess impacts on SAV. This study has been complicated by difficulty in obtaining good quality maps on which to overlay aerial photography. However, recently the NMFS obtained maps from the Department of Commerce and analysis of the photos should be completed by the end of August 1994. f. Oyster Reef Construction - Manteo (Shallowbag Bay) Project. Islands along the Oregon Inlet Channel are used by the Corps for dredged material disposal. As mitigation - for every acre of shallow water bottom covered by dredged material, 0.66 acres of oyster reef will be created by the Corps. Sixty- seven (67) acres of oyster reefs will be constructed. The North Carolina Division of Marine Fisheries is responsible for identifying suitable sites for oyster reefs. However, due to an oyster disease that is affecting some areas, sites are limited. A question was raised regarding the limitations/boundaries of the oyster reefs and whether or not they had to be located near the project site. The Corps' response was that it is required that the oyster reefs be located in the vicinity of the project. This would include Roanoke Sound or the northern portion of Pamlico Sound. Ongoing research of the production of oyster reefs is being used by NCDMF. g. Biological Study, Beach Disposal Projects. Although monitoring of the impacts of beach disposal on various organisms has been carried out by several individuals and agencies, there are gaps in the data as well as duplication of data in some cases. The Corps has contracted with UNCW to do a detailed literature search on impacts of beach disposal on various organisms. Three areas will be looked at: the dry beach, the intertidal zone, and the surf zone. The schedule is for work to begin in August with a final report due in June of 1995. The goals of the literature search are to identify gaps in available data, to identify additional research needed, and to identify management implications of the findings. For copies of the proposal, see Frank Yelverton. h. Dredging Window. The Corps has multiple dredging windows for various areas and types of dredging, such as Primary Nursery Areas, beach disposal, hopper dredging, etc., all of which were set up to avoid dredging during biologically sensitive times of the year. However, dealing with these different windows often causes management problems. It was suggested that a small working group of interested agencies be formulated to address this issue. The main goal of this committee would be to look at all available data and based on that data, determine which dredging windows are the most beneficial. It was the general consensus that this was a good idea and the committee to address this issue should be kept as small as possible. The following representatives agreed to be points of contact for this project: Mike Street (NCDMF), Howard Hall (USFWS), Larry Hardy or Ron Sechler (NMFS), Tom Henson (NCWRC), Howard Varnam (COE-Con- Ops), and Bill Adams (COE - Environmental). It was sug%ested that an academic- type might be helpful to this committee, however, the general feeling was that the group should be kept very small and academic-types could be consulted during the process of analyzing available data or could be contacted for input after solutions are reached. The schedule for this work is not known at this time'. i. Nearshore Berm Project, Morehead City, Beaufort Inlet. The Corps proposes to construct a nearshore berm on the west side of Beaufort Inlet as a means of keeping the dredged material in the ebb tide delta system. The berm would be located on.the 25' to 30' contour, which is on the outer edge of the ebb tide delta. The berm will rise approximately 6' above the current bottom contour (slope of 1V:30H). The natural movement of the material should be back toward the delta, thus keeping the material in the system. There has been some concern about impacts to larval fish. Baseline data has been gathered and NMFS (Beaufort Lab) will be doing a study to monitor impacts of the berm on larval fish. Berm migration will be monitored by the Corps over the next 2 to 3 years. An EA for this project is in the process of being finalized at this time. Assuming all clearances are gbtained, work would begin in the fall of 1994. A question was asked regarding the plans for future additions to the berm should impacts be found to be insignificant. The Corps stated that the berm may be extended, moved, etc. depending on its migration. As stated previously, the Corps will monitor berm movement to determine what future actions, if any, will be necessary. j; Beneficial Uses - Rock Dredging, Cape Fear River Bar Channel. The Corps has a unique opportunity to make beneficial use of the rock that will have to be dredged in order to deepen the bar channel to its authorized depth. Plans are to use the dredged rock to construct on offshore structure, known as the Wilmington Offshore Fish Enhancement Structure (WOFES). The WOFES will be located east of the ocean Dredged Material Disposal Site .(ODMDS), will be 8000 linear feet (in the shape of the Greek letter "pi" (H)),, and will extend from 12' to 21' off of the bottom. A clearance of at least 25 (water depth) at mean lower low water will remain for navigational purposes. The Corps has committed to pre- and post-monitoring of the structure. A concern was raised regarding the need for blasting to remove the rock. It was stated that the contractor thinks he can dig the rock out without blasting and there are very tight environmental constraints on blasting so that it is discouraged. A question was raised regarding the placement of buoys at the WOFES. The Corps stated that river pilots would most likely be opposed to the placement of buoys at the site as they may cause confusion to boat pilots (marker buoys may be mistaken for navigational buoys). It was decided that the Corps would work this problem out with all concerned parties, including the Coast Guard and river pilots to come up with an agreeable solution. k. Habitat Creation/Restoration/Coastal America Program. The Corps is involved in habitat creation and restoration under the following innitatives or authorities. 1) The Co s National Mar3.ne riatsaa?? -- MOA - The Corps has made a commitment to investigate opportunities with the NNFS to create/restore fisheries habitat in conjunction with ongong O&M activities. We have several ideas for projects and are currently working on a 5 year marsh creation project at Island "H," a dredge material disposal island near Wanchese, North Carolina. This project is a cooperative effort between the Wilmington District, the Waterways Experiment Station (WES) and NMFS and involves annual planting of Spartina alterniflora and ST) rtina patens for eductional demonstration, shoreline erosion control and enhancement of fish habitat. Although the first planting in 1992 was severely damaged by the March 13 Storm, the second year's planting appeared to be surviving well this spring, and we are optimistic about this year's work. The Corps and NMFS are scheduled to monitor this site this October. 2) Coastal America - This is an interagency initiative to implement projects to restore or enhance the coastal environment. The Corps has contributed hydrologic analysis, planning and design assistance, for a Coastal America project, funded by EPA, to remove obstructions to anadromous fish. The project involves the removal of 2 dams. One is on the Neuse River near Goldsboro N. C. and one is on a tributary and located near Cherry Hospital. Work is scheduled for the near future. 3) Section 1135 of the Water Resources Development Act of 1986 - This authority allows the Corps to modify existing projects for the improvement of the environment. These projects require a nonfederal cost share partner. The Corps are investigating three potential Section 1135 projects. These projects are all in reconnaissance phase and include: Cape Fear River Locks and Dams - a project to improve the passage of anadromous fish at Lock and Dam 1; Snows Cut - a shoreline protection project on an AIWW land cut near Carolina Beach N.C.; and Restoration of Tidal Creeks - projects to improve tidal flushing on three creeks near Wilmington N.C.. 4. Other Topics/Open Discussion. The only item discussed during this time was with regard to the Colonial Waterbird Committee. It was suggested that the Colonial Waterbird Committee hold their annual meeting next year immediately after the dredging coordination meeting (and in the same location) since most committee members would be in attendance for the dredging meeting. All interested parties agreed that this was a good idea. 5. Actions Required. As a result of issues and questions raised during this meeting the following actions are required: a. Continued coordination between the Corps (Dan Small - POC) and the Division of Water Resources and the North Carolina Division of Coastal Management with regard to the new amendments to the Dredge and Fill Law and its implications for the Corps. i b. The Corps (Howard Varnam - POC) will investigate possible solutions to the deterioration of sandbags (and associated erosion) at the Harkers island disposal site. C. The Corps (Trudy Wilder - POC) will make a decision regarding the disposal of material at Wainwright Slough. d. Coordination between the Corps (Trudy Wilder - POC) and the Colonial Waterbird Committee regarding potential solutions to the erosion of Big Foot Island. e. The report on the impacts of dredged material disposal into SAV at Walter Slough will be completed (Corps and NMFS) and shared with interested agencies. f. Continued construction of oyster reefs at Manteo (Shallowbag Bay) by the Corps and NC Division of Marine Fisheries and continued monitoring of oyster reef production. g. Bill Adams (Corps POC) and the POCs listed in paragraph 2.h. will begin work on determining better/more beneficial dredging windows. h. Dan Small (Corps POC) will complete the EA on the nearshore berm project at Morehead City. i. The Corps (Carmine Forcinito and Phil Payonk - POCs) will coordinate with appropriate agencies/ individuals on possible placement of buoys at the WOFES. j. The Corps will complete environmental work (FONSI and Public Notice) for the AIWW, Section III, Tangents 2-6 (Trudy Wilder - POC). k. Cape Fear River Above Wilmington - The Corps (Howard Varnam - POC) will investigate the use of a sidecast dredge on this project and the Environmental Resources Branch (Corps) will coordinate this with appropriate agencies. 6. Update. Two projects that were discussed during the dredging coordination meeting will not be dredged in FY 95. They are the Alligator Pungo Land Cut and the Channel from Back Sound to Lookout Bight. Recent hydrographic surveys indicate that these two projects do not need to be dredged. Coleman Long Chief, Environmental Resources Branch FY 95 DREDGING COORDINATION MEETING TIM : 18 August 1994 - 10 a.m. to 12 noon PLACE: U.S. Army Corps of Engineers, Wilmington District, 69 Darlington Avenue (main conference room), Wilmington, North Carolina WELCOME: Colonel Robert J. Sperberg, District Engineer OPENING REMARKS: Carmine Forcinito, Corps of Engineers; Preston Pate, NC Division of Coastal Management; and Daniel Small, Corps of Engineers TOPICS TO BE DISCUSSED 1. Review of FY 95 O&M Projects (Forcinito/Wells) 2. Pro.-ject/Study Updates - AIWW Long-Term Study (Meshaw) - Morehead City Harbor-Combined Action (Small) - Sandbagged Disposal Island-Old House Channel (Forcinito/Wells) - Colonial Nesting Waterbird Islands (Wilder) - SAV Impact Assessment, Walter Slough Channel (Small) - Oyster Reef Construction - Manteo (Shallowbag Bay) Project (Small) BREAK (10 minutes) \1 - Biological Study, Beach Disposal Projects (Yelverton) - Dredging Window, Lower Cape Fear River (Adams) - Nearshore Berm Project, Morehead City, Beaufort Inlet (Small) - Beneficial Uses - Rock Dredging, Cape Fear River Bar Channel (Payonk) - Habitat Creation/Restoration/Coastal America Program (WIson) 3. OTHER TOPICS/OPEN DISCUSSION 4. CLOSING REMARKS: Carmine Forcinito, Corps of Engineers Preston Pate, NC Division of Coastal Management; and Daniel Small, Corps of Engineers a-Ma. ,ey'd r+ l FY 95 COORDINATION MEETING PROJECT INFORMATION FY 95 DREDGING PROJECTS * 1. ATLANTIC INTRACOASTAL WATERWAY (ALLIGATOR PUNGO LAND CUT) 2. ATLANTIC INTRACOASTAL WATERWAY (AIWW) INLET CROSSING 3. WILMINGTON HARBOR ANCHORAGE BASIN AND 38-FOOT PROJECT * 4. WATERWAY CONNECTING PAMLICO SOUND AND BEAUFORT HARBOR, CHANNEL FROM BACK SOUND TO LOOKOUT BIGHT, AND WAINWRIGHT SLOUGH * 5. CAPE FEAR RIVER ABOVE WILMINGTON 6. WILMINGTON HARBOR - OCEAN BAR CHANNEL 7. MOREHEAD CITY HARBOR OUTER HARBOR (OCEAN BAR CHANNEL) 8. MANTEO OREGON INLET CHANNEL (INTERSECTION - MANTEO-OREGON INLET-OLD HOUSE CHANNEL) 9. ROLLINSON CHANNEL (HATTERAS INLET TO HATTERAS) 10. OREGON INLET (OCEAN BAR CHANNEL AND VICINITY OF BONNER BRIDGE) 11. U.S. MILITARY OCEAN TERMINAL SUNNY POINT (MOTSU) NOTE: Funds for this FY do not allow a complete survey of projects. Other projects may be scheduled as navigational surveys are performed or unexpected shoals occur which require immediate removal. Should funds become available and projects are scheduled, notices will be made available to Federal and State resource agencies and the interested public. 0.-H"ac?nrV?e-v?? 2 ATTENDEES NAME AGENCY PHONE Bill Adams COE, Environmental Branch 910-251-4748 Alice L. Anderson NCDEHNR, Public Health Pest Mgmt. 919-726-8970 Caroline Bellis NCDCM 919-733-2293 Steve Benton NCDCM 919-733-2293 Zoe Bruner NCDCM 910-395-3900 Rich Carpenter NC Division of Marine Fisheries 910-395-3900 Therese Conant NC Wildlife Resources Commission 919-726-7157 Carmine Forcinito COE, Navigation Branch 910-251-4823 Walker Golder National Audubon Society 910-256-3779 Curtis Gregg NC Division of Marine Fisheries 919-726-7021 Jim Gregson NCDEM 910-395-3900 David Griffin NCDCM 919-264-3901 Howard F. Hall USFWS 919-856-4520 Larry Hardy NMFS 919-728-5090 Tom Henson NC Wildlife Resources Commission 919-946-1969 Charles Jones NCDCM 919-726-7021 John Meshaw COE, Environmental Branch 910-251-4175 Steve Murphey NC Division of Marine Fisheries 919-726-7021 Jenny Owens COE, Environmental Branch 910-251-4757 Preston Pate NCDCM 919-726-7021 Phil Payonk COE, Environmental Branch 910-251-4589 Janet Russell NCDCM 910-395-3900 Deborah Sawyer NCDEM 919-946-6481 Ron Sechler NMFS 919-728-5090 Rick Shiver NCDEM 910-395-3900 Daniel Small COE, Environmental Branch 910-251-4730 Frank Snipes COE, Plan Formulation Branch 910-251-4774 Colonel Sperberg COE, District Engineer 910-251-4501 Charlie Stehman NCDLM 910-395-3900 Mike Street NC Division '?of Marine Fisheries 919-726-7021 Bob Stroud NCDCM 910-395-3900 Joseph F. Wade COE, Navigation Branch 910-251-4824 James Wells COE, Navigation Branch 910-251-4824 Trudy Wilder COE, Environmental Branch's 910-251-4581 Chuck Wilson COE, Environmental Branch 910-251-4746 Frank Yelverton COE, Environmental Branch 910-251-4640 ai ack vv a4 3 FY 95 DREDGING COORDINATION MEETING TIM : 18 August 1994 - 10 a.m. to 12 noon PLACE: U.S. Army Corps of Engineers, Wilmington District, 69 Darlington Avenue (main conference room), Wilmington, North Carolina WELCOME: Colonel Robert J. Sperberg, District Engineer OPENING REMARKS: Carmine Forcinito, Corps of Engineers; Preston Pate, NC Division of Coastal Management; and Daniel Small, Corps of Engineers TOPICS TO BE DISCUSSED 1. Review of FY 95 O&M Projects (Forcinito/Wells) 2. Project/Study Updates - AIVWV Long-Term Study (Meshaw) - Morehead City Harbor-Combined Action (Small) - Sandbagged Disposal Island-Old House Channel (Forcinito/Wells) - Colonial Nesting Waterbird Islands (Wider) - SAV Impact Assessment, Walter Slough Channel (Small) - Oyster Reef Construction - Manteo (Shallowbag Bay) Project (Small) BREAK (10 minutes) - Biological Study, Beach Disposal Projects (Yelverton) - Dredging Window, Lower Cape Fear River (Adams) - Nearshore Berm Project, Morehead City, Beaufort Inlet (Small) - Beneficial Uses - Rock Dredging, Cape Fear River Bar Channel (Payonk) - Habitat Creation/Restoration/Coastal America Program (WIson) 3. OTHER TOPICS/OPEN DISCUSSION 4. CLOSING REMARKS: Carmine Forcinito, Corps of Engineers Preston Pate, NC Division of Coastal Management; and Daniel Small, Corps of Engineers FY 95 COORDINATION MEETING PROJECT INFORMATION FY 95 DREDGING PROJECTS - * 1. ATLANTIC INTRACOASTAL WATERWAY (ALLIGATOR PUNGO LAND CUT) 2. ATLANTIC INTRACOASTAL WATERWAY (AIWW) INLET CROSSING 3. WILMINGTON HARBOR ANCHORAGE BASIN AND 38-FOOT PROJECT * 4. WATERWAY CONNECTING PAMLICO SOUND AND BEAUFORT HARBOR, CHANNEL FROM BACK SOUND TO LOOKOUT BIGHT, AND WAINWRIGHT SLOUGH * 5. CAPE FEAR RIVER ABOVE WILMINGTON 6. WILMINGTON HARBOR - OCEAN BAR CHANNEL 7. MOREHEAD CITY HARBOR OUTER HARBOR (OCEAN BAR CHANNEL) 8. MANTEO OREGON INLET CHANNEL (INTERSECTION - MANTEO-OREGON INLET-OLD HOUSE CHANNEL) 9. ROLLINSON CHANNEL (HATTERAS INLET TO HATTERAS) 10. OREGON INLET (OCEAN BAR CHANNEL AND VICINITY OF B.ONNER BRIDGE) 11. U.S. MILITARY OCEAN TERMINAL SUNNY POINT (MOTSU) NOTE: Funds for this FY do not allow a complete survey of projects. Other projects may be scheduled as navigational surveys are performed or unexpected shoals occur which require immediate. removal. Should funds become available and projects are scheduled, notices will be made available to Federal and State resource agencies and the interested public. FY 95 DREDGING PROJECTS * 1. ATLANTIC INTRACO STAL WATERWAY (ALLIGATOR PUNGO LAND CUTI. (Plate 1) Project Description. This maintenance work involves removal of material lying above the plane of 14 feet mean low water (m.l.w.) along designated limits of the AIWW. Routinely, the material has been placed along the toe-of-the-bank adjacent to the channel. FY 95 maintenance will involve placing the material in upland diked disposal sites. Dredging will be performed with a hydraulic pipeline dredge. 2. ATLANTIC INTRACOASTAL WATERWAY (AM INLET CROSSING. (Plate 2) Project Description. This routine maintenance dredging involves removal of all material lying above the plane of 14 feet below m.l.w. within the designated limits of the channel at various inlet crossings. The estimated quantity of material to be removed varies, depending upon the areas to be dredged during the dredging cycle.. Dredging is to be accomplished by a hydraulic pipeline dredge with disposal in upland disposal sites or along the ocean beaches adjacent to the inlet crossings. Maintenance is scheduled to start in early January 1995 and will require approximately 6 months to complete. Every effort will be made to complete all beach disposal prior to 1 May or soon thereafter. The areas known to require dredging at this time are: Area To Be Dredged Estimated Quantities Disposal Area (Cubic Yards) CAPE FEAR - LITTLE RIVER REACH - Shallotte Inlet Crossing 69,400 Ocean Isle Beach - Lockwood Folly Inlet Crossing 42,000 Holden Beach - Carolina Beach Inlet Crossing - Mason Inlet Crossing - Shinn Creek Crossing - Bogue Inlet Crossing - Topsail Inlet Crossing - New River Inlet Crossing - Bear Inlet to Brown Inlet 18,000 Carolina Beach 13,000 Wrightsville Beach 25,000 Upland Dike 30,000 Upland Dike 14,000 Topsail Beach 56,000 North Topsail 150,000 Onslow Beach 3. WILMINGTON HARBOR ANCHORAGE BASIN AND 38-FOOT PROJECT. (Plate 3) This routine maintenance dredging is scheduled to begin October 1994 and will take approximately 4 months. The work consists of the removal of all material lying above the plane of 40 feet below m.l.w. within the limits of the channels. The estimated quantity of material to be removed from the Anchorage Basin, Between Channel, and Fourth East Jetty is approximately 800,000 cubic yards. The type of material is predominately silt with lesser amounts of sand. The frequency of dredging is once every year. The dredged material will be placed in the Eagle Island upland disposal site. For the 38-foot project, approximately 742,000 cubic yards of material will be removed from Upper and Lower Midnight Channels, Lower Lilliput, Keg Island, Lower Big Island, and Snows Marsh Channel. Dredged material will be placed in the Wilmington Ocean Dredged Material Disposal Site offshore. This work will be accomplished by a bucket and barge dredge. * 4. Waterway Connecting Pamlico Sound and Beaufort Harbor-, Channel From Back Sound to Lookout Bight, and Wainwright Slough. (Plates 4 and 5) This routine maintenance dredging involves removal of all material lying above the plane of 9 feet below m.l.w. within the designated limits of the channel. The estimated quantity of material to be removed is approximately 200,000 cubic yards of predominately medium-to-fine sand. Material will be placed on the 12-acre sandbagged disposal site within Back Sound. Routinely, the material dredged from Wainwright Channel has been placed at or near the toe-of-the-bank on the channel side of Wainwright Island. However, this disposal activity results in the material running back into the channel resulting in channel shoaling. Therefore, in FY 95 the placement of material on the back side of the island will be investigated along with other disposal alternatives. This work will be coordinated with the other agencies in FY 95. * 5. CAPE FEAR RIVER ABOVE WILMINGTON. (Plate 5) Project Description. The work involves removal of shoals along the navigation channel in the Cape Fear River from Wilmington upstream to Fayetteville, approximately 111 miles. The total estimated quantity of material to be removed from all reaches is approximately 87,500 cubic yards. Dredging is performed by hydraulic pipeline dredge with material being placed along the toe-of -the-bank annually and in upland diked disposal areas once every 5 to 6 years. In FY 95 we will be investigating the possibility of performing the work using a sidecast dredge with toe-of-the-bank disposal. 2 6. WILMINGTON HARBOR - OCEAN BAR CHANNEL. (Plate 6) Project Description. This work involves providing the authorized project depth of 40 feet at m.l.w. for the Wilmington Harbor Ocean Bar Channel (Baldhead Shoal Channel). Rock obstructions will be removed from the channel bottom seaward of the channel's intersection with Smith Island Channel and proceeding seaward to the end of the channel (about 5.8 miles at sea). . 7. MO EHEAD CITY HARBOR OUTER HARBOR (OCEAN BAR CHANNEL) (Plate 7) Project Description. The Outer Harbor maintenance consists of maintenance of the -45 foot outer bar channel (Range A). The total quantity of material to be dredged is estimated to be approximately 2 million cubic yards. Dredged material from the Outer Harbor maintenance deepening will be discharged in a placement site for an underwater nearshore berm. The work is scheduled to be performed between December 1994 and March 1995 by hopper dredge. 8. M-ANTED OREGON INLET CHANNEL WMRSEC ION - MANTEO- OREGON INLET-OLD HOUSE CHANNEL. (Plate 8) Project Description. This routine maintenance dredging is scheduled to begin on or around 15 January 1995 and will require approximately 90 days to complete. The quantity of material to be removed is approximately 100,000 cubic yards of coarse-to-fine sand. The work requires the removal of all material lying above the plane of 14 feet below m.l.w. The work is performed annually. the work will be accomplished by hydraulic pipeline dredge with disposal of dredged material on adjacent disposal islands using the control-of-effluent method of disposal. 9, RO T INSON CHANNEL (HATTERAS INLET TO HATTERAS). (Plate 9) Project Description. Maintenance dredging will be accomplished by hydraulic pipeline dredge with disposal of approximately 20,000 yards of dredged material on the ocean beach (Hatteras Island). 10. OREGON INLET (QCEAN BAR CHANNEL AND VICI MTY OF BONNER BRIDGE). (Plate 10) Project Description. This routine maintenance dredging involves the removal of all material in the authorized channel to a depth of 14 feet below m.l.w. in miles 0 to 1.5 of the channel from Manteo to Oregon Inlet, and 17 feet below m.l.w. along the ocean bar channel. Environmental clearances have been received to perform routine maintenance dredging of the 3 ocean bar channel by an ocean-certified hydraulic pipeline dredge or hopper dredge with direct pumpout of dredged material with discharge of dredged material on the Pea Island National Wildlife Refuge or disposal offshore. 11. U.S. MILITARY OCEAN TERMINAL SUNNY POINT (MOT SUI. (Plate 11) Project Description. This routine maintenance dredging which is ongoing involves dredging of the facility's access channels, connecting channels, and navigation basins on the Cape Fear River in Brunswick County, North Carolina, to an overall depth of 36 feet below m.l.w. Dredging will be accomplished by a large volume clam bucket dredge. Materials excavated by clam bucket dredge will be transported by scow or split hull barge and dumped in the EPA approved Wilmington Harbor Ocean Dredged Material Disposal Site. Dredging schedule is contingent on shoaling conditions which is expected to occur around May-June 1995. 4 :yA .. _ VIRGINIA ------------ ------- .\ ._C -- ?, c- "_"-? NORTH CAROLINA ?? • \ . ? d ' \ y 4rO ? 9 10 ?,Ebmtetm v Spend ALLtGAToQ- PtUAGO `°°?., Alpenl°•k ?AtJD CUT - /T-f RRELL 1 ` ' ? ? Y E 1WosMngtor. c ?.: • t ? News* i 1 r fir. 1?Go New Bern A 1 7A N 1 ? I t o N S L O W ?4, t a E Jacksonville a CeOO , / I ? 9 J t v E H o? E R n t Wilnungfor, MOfonDoro Intel RA HSwICK GAPE LOOKOUT P? C?JJ 11 111 /I/ V1 411 1111 .:AI./ 1 I All [NO A I W W Mil l WILMINGTON DESTRICT NI wr4 A 1 -G" w. N IL M1NC-!t,N DISTRICT i t nXEw so A ,rf CAPE i HATTERAS *to$ Intel Ocrocohe Intel G1' a General Location Map Atlantic Intracoastal Waterway Virlj i n j a :.Late Lino Lo 1.iI LI/? It iver 11111•L, Soul.h Ca Iol itl.l Plate 1 U.S. ARI' CORPS OF ENGINEERS NORFOLK O &SSB SUFFOL! v USSR b° v BEGIN A.I.W.W. e DISTRICT. VIRGINIA ? ? ? JAL N NORTH CAROLINA ?r OINJOCK BRIDGE ELI - ` \ I C .I- •. WINDSOR Yl ?`•i P µ? WIU.IAMSTON 2 AI(iOM ?6A .T'o a irte-r WILSON FAIRFIELD BRIDC 10 0 spl REEW41LLE WILKERSON CIL A FIELD MPIN6 ?. 115 f11NL;PON BRIDGE LANT ` uT? a i1T1? Y us c'?v 5 0 Q"S8OR " KIN OBUCKEl EN BRIDGE G 0 1 + L 1 CAVC NAT RAS }P Us AW 4 NEWBERN /CORE C K BRIDGE SIDE CKANNE / I c S 6 BASIN A :y:'?ApgoNVt ANSBORO " CHANNELS TO = t t j . JACKSONVILLE a••:• ?. tro NEW RIVER INLET. # CAPI: LOORavr OGU `PELTIER CREEK INLET to 1 b tl HANNEL TO ROGUE INLET 7I Q : y( T 2SAjLjNU-ET AND la CONNECTING CHANNELS G WILHIN87'ON MASONSORO INLET •t ' BOAT BASIN AT? t9o AND CONNECTING CHANNELS P a sou R la V ?,? T? RGI INA BEACH INLET I• P 1 ^ ` i/ (?I?S `Y4. !C! t t L ` CAROLINA BEACH HARBOR 1b alt CAK RAA END A.I.W.W. SOUTHPORT HARBOR tb WILMINGTON Ic - DETAIL SHEET NUMBER. DISTRICT /30 -MILEAGE. MEASURED FROM FOOT OF WEST MAIN STREET. NORFOLK. VA. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK.VA. AND THE ST JOHNS RIVER, FLA. (WILMINGTON DISTRICT) VARYING SCALE OF MILES 0 p p 40 3 ?VA I ---i - VARYING CORPS OF ENGINEERS WILMINGTON.N.C. TYPICAL SECTION MAP REVISED SEPTEMBER 1983 7iool i I ?a Qi y ? l 'w- I , 1 ? u a SOUTHPORT ar `e1E0NEA0•CAS.6ELL [r rj??a 10•f Soo', f ry` ` I ? /moo`: ? j ?ti:? 1 Is. t I?IN`(??? MILITARY OCEAN TERMINAL BRUNSWICK COUNTY //t1//° /Ar SUNNY POINT f N't ©Q' eta `°» `i' - C A P E E F A R °'• a = / +i euv[a n: ex. ` rte, i rmf 'V'??..••?.,,((?[ /Jf/x i MIOM - J?? N100_-____?•? •? i ?„?, '}'tV([?J Cx?"' - V[IE? ??.MIONIGXT CM p FEOE AL © `lDM[o llE(,??T ?r ?_ -GM -KEG IfLANa CE P01 NT q cx. •-.61%f? lilUW _,y^^""? i` K`•?• ---v _? .?\ ?? aDNNt CTINi Cx., 1 ?' I 1 V FORT FISHER NEW HANOVER COUNTY t r KURE BEACH CAROLINA GEAC C O C E A N RIVER M BRUNS j0A I?ER R o O q n EAGLE ISLAND _ -ANCMONA Oi?3 d ? .:dGe • F u 'EAST Jerry W M.L.W. --------- -------- VARYING Ip vARTdc VARYING TYPICAL SECTION Mileages, are measures ,rum me ..?•••- •-•• -• Boldhead Shoal and Smith Island Channels. ?L 0,o- / +A?tl .A mot. 00" 10'00...6 SEa a.O NK TNEAM ERECT OF ERAL PMJECT 30.eMi. Toolval ENr. OA11N o' awwn I NAG T'0 N WILMINGTON HARBOR, NORTH CAROLINA SCALE OF MILES 0 I 2 3 1 CORPS OF ENGINEERS WILMINGTON,N.C. MAP REVISED SEPTEMBER 1990 Plate 3 GI /'R11 W"AL ' HE SrRA/ S_.....»•' WESrMourH ; BAY BROWNS ISLAND HARKERS •,, ?'•:;:, £ASTMOUTN J,, ``? :?• • a .. _ I S L A N D BA r /? OJ .. ?/ ...., 4 I/ n PROJECT 36 /•M 1 NC % r O`L Pty oN1?G t?P P LOCALITY MAP 0 t SCA1: IN MII FS COP '••7r...tl+ CARTERET COUNTY ?n q 2 ?Q •4 C ?" SANDS G!,'A L P DISPOSAL ?? ild-L Q! S AREA It O b ?? CHANNEL 7' DEEP O li W/DE t1 Sy9 it ? C''? <F Q ? o '• a• ? O ,Q IllyllU. ? 4 y4. 6 .44, a °J X10' U Mi. Loor.our BIGHT BAO gT CAPE LOOKOUT M.L.W _-_--------- F -------------- 7• 1p 3 r 100• I TYPICAL SECTION Mileage is measured from a point N5T°W & 4500' from Cape Lookout Liahthouse. CAPE LOOKOUT LIGHTHOUSE V P v P P V M CHANNEL FROM BACK SOUND TO LOOKOUT BIGHT, NORTH CAROLINA SCALE OF FEET 2000 O 4000 8000 12000 CORPS OF ENGINEERS WILMINGTON, N.C. MAP REVISED SEP 1980 Plate 4(a) dYJ Vf r-&14v 4GGftJ ? - ?- NltM 1 Plate 4 (b) COKF'S Vr tlvvllvttrcJ PAC y 1 S`y ?o e - y e' UPSTREAM LIMIT OF FAYETTEVIL' FEDERAL PROJECT u.: Pol I MI- III ML { C V. J. Htt M i ?38 VA -T?• ?I L I ti0 1 ` N.C PRO E ? ?OCEAN ATLANTIC \ 3.L'414. LOCALITY MAP lROSEBORO SCAL[ Of N1Les COUNTY o SO w SAMPSON COUNTY -- Q NUSKE-' ti i - OAM 9?ae ` \\ .ems l? ? 1 rG1? ? s9' CVm \ - o V ? \ ,S,a WHITE FIXED 9RIDGE Noll. CL 90' + OAK. VCRT.CL•9' ???QloI?G N MI ROBESON CO. POOL LCV C L '? raco L. Sw ,\ I P; NOR CL. 3.&V ? vicer.c ao' 1 POOL LCVCL 1 i f A ( F , ;LUMBERTON ) BLOCK a DAM NO.2 / ELIZABETHTOWN \ B L A D E N CO -9 y? 1 60 1. 1 'P °A ? Ness S IL 50 MI. . •.?r EL-ELLS rCRNr CLARKTON • w PENOER COUNTY LOCK DAM NQ I ' - FIXED DRIDGE VE OOML 140R.CL.219' V[RT,CL. •2 21' M. "t N. W. Cu T COLUMBUS COUNTY 30 M1. r u:T9_ra RIEGELW00 A MEN 20 MI. WHITEVILLE uTOFF / _ O M1. NAVASSA WILMINGTON BR UNSWICK CO. NEW / HANOVER CO. BLC R N. BRIDGE MO-ON. . CL. 102' VERTCL.S w, DIAW CLOSED • DASCOLE HwX ORIDGE NON,CL. 120' VE RT,CL. 30' M. L.w. OR Aw CI.OSCO MILEAGE IS MEASURED FROM THE CONFLUENCE OF THE CAPE FEAR 86 NORTHEAST CAPE FEAR RIVER CAPE FEAR RIVER, N.C. • ----_----- ABOVE WILMINGTON ` ----------"IN' VARYING I? SCALE OF MILES 3 5 O 5 10 15 I VARYING TYPICAL SECTION CORPS OF ENGINEERS WILMINGTON,N.C. MAP REVISED SEPTEMBER 1983 Plate 5 P. i TAM q``` ?r_ I r2 , 1 .,B At ? ? -:' ?51011d { S ? 1 -tt p/ Y° po,: B9octi \ Oa t 1 ? ? M1 p i :UT-0 9/ye? ?I n.Yr \ 2: ._+ ::-•oo la .'1• a Is i 1 r 72 d °r V _ la ; a o •C a to 16 TANK 9 \ d iG F y,:'G i ' ?r •I,T} ;ii w'?' -2 \ w or a o i ? 's 1 is 17 13- 1 , l? ? S !;.. .? _ I .y '' 11 a GA¦R¦• It a • e?! i t 6°. 11 ' t X"•'? 03 19 is • ?r 84 ? 4 N ??ti ra`y'. ••? Is t f j ao al T TIT ?-: s.?'y?!M T ar to 21 at Is • ? Bald H a' t .? • Z ad r4 ;s;? '? • It n ? // • two ® •n 'a s.r..... x 19 u 20 It i ? k.I?t„4 t' . Cf: '? d H I x t \ 19 \ la It t t 7 • s a ead sland \ It BALI}HEAD SHOAL CHANNEL It l/ 17 of 7 to t- R=s• 'a la 11 to / 14. 16 . ?x Gy / pG23. 19 K la - 7 \` p Is 17 x / Is 77 \ / _ 19 Is 7 1? 17 .2. 20 Z, w .,? /9 14 s,RO 25 1° 1? ? 27 19 17 21 72 30 A 3) nG? // \ n 16 76 ? 21 37 77 D / 19 39 25 23 u ?j / ? n 20 / ? ? » / /, 11 ?\? ? y 25 /? / ? u ]s 27 ,' `? 71 1 » 72 OCEAN 7s ' • ? DREDGED 77 ` ' MATERIAL ? sooo 0 300 `6000 9ooet u ??? DISPOSAL Z?o?. SCALE IN FEET SITE 27 " u /47 q . I 2t DISPOSAL 17 N ,6 ZONE .4 WILMINGTON HARBOR, NORTH CAROLINA ?7 u OCEAN BAR CHANNELS t2 I 1 .. •? U. Dl oI- Fi tom' 383 TYPICAL SECTION 2? \a :a `?O• 1 its M BEAUFORT N elAO S NOA t 00- '?J? •1s .r ` c. C.. ?c Ill Q?\P .O?t [ r-1-d O. W. SNACKI EFOAD rot NT Gi ?.T O =^ \ ?. - . x l=) ' C7 . r C7 J9 C r r LEGEND a T L a N! / C O C A Al I - DREDGED MATERIALS. FROM THESE AREAS ARE PROPOSED FOR OCEAN DUMPING ® - BEACH AREAS USED FOR DREDGED MATERIAL DISPOSAL MOREHEAD CITY HARBOR, NORTH CAROLINA - BRANDT ISLAND, UPLAND DREDGED MATERIAL DISPOSAL SITE i SCALE OF MILES F CORPS OF ENGINEERS WILMINGTON. N C MAP REVISED SEPTEMBER Ica? ?,•, .[•?c arr... 1, vr• c. a3rar / •ascrat •w •• -.) .WC. •o Q v[wrca••rrr o•A. caolte / HEAD ITY ?`'" • • U V ! 10 ?• was .C .? 2 3u. ro It Sw: l W 0.3Y. ?V•r .• RADIO ISLAND _ ' •.! r I to y a, BRANDT ISLAND` 2Y. \` as y so,*" E M? - V• T• \\ .c N M C 5 C? CC+N 0 \ AtaANt.C PROJECT LOCALITY 4AP SC-Lit or ..at! e 30 so Plate 7 a O a n 4?p, irq rwNp("? qr, M? ?J O a 003-04 v H .n O 7D ? G O 4A ))p D h Z w Z ZO N o or h M M 003-09 • G ? a e? 03-05 rL t f E '11br 003-07 0 O O i ?-A. r - n s 9 Z O O m Z c 44A M w .uA w1u tw ai ?s /005-06 „ -OS A KNo 006-02? SOVNO PA41CO 006-08 M )411 y If i I N N rN N N M ti v y/ 4 PROPOSED DISPOSAL ISLAND (1993) DIKED UNDERWATER DISPOSAL AREAS 005-03 ?d a A? 9 \ :r ?O YS COAST Otomm- SIA100+ MIANIEO ISHALLOWSAG) 6AY NORIH CAROLINA ISLAND f/Ap CONSTRUCTED 1988 (NCIN DR-006-35) DISPOSAL ISLANDS 3M . r«n «» .ees SCALE IN FEET 28 JANUARY 1993 Plate 8 o Q 0, 10 a n 003-04 v H Y q js :. ,? Z O 30 C. 4 Z y Z" Z Zo N v O e a a r 003 -09 ?G c e 03-05 • e ff ? ?. '2 E w.wc p `' O tc was r?r C? y? r 003-07 D IN N ' w 005- K?"o 4 cc- 006-02V , SOUND 1 R ICO 006-08 M Alf P „I ((R a y A .If M M -OS 005 tb a .o ?A v 005-03 US Cost cww_ SlAt1ON ;• r PROPOSED DISPOSAL ISLAND (1993) J y DIKED UNDERWATER yy DISPOSAL AREAS N ISLAND CONSTRUCTED 41 IN 1988 (NC-DR-006-35) .¦ MANIEO ISHAUAWWKj GAT NORM CAROUNA DISPOSAL ISLANDS 3M . ..? .,. .«. SCALE IN FEET 28 JANUARY 1993 Plate 8 CORPS OF ENGINEERS ?o \r o.2 w?OJ \G0 \ \ Q P`" RUBBLE MOVN BREAKWATER I MY. SUL- DETAIL OF BASIN ?ML, AT HATTERAS \\\ `• s > sOALE of FEET • \ \ j O !DO _ 400 eo0 • I \\ ?•_ rROLLINSON CHANNEL 3ML12, X IOO' 2IAI- \ 5 U U \\?\ L V - '?•-.? ••?. `•?` IML \7, DURANT PT. A • `•~• , - ``.\\ \\ SANDY LAY ' ;CHANNEL FROM HATTERAS \\ g '- : INLET TO HATTERAS 10' X 100' t •• IML • ??'OMI -.- -? ZML t 3ML ?. . = i .....,..... Ray/ U vac ?• A N AGE A c?Mt c 9s A T M.LW. Ip Ice s TYPICAL SECTION HATTERAS Distances are measured from basin at Hatteras. ROLLINSON CHANNEL, NORTH CAROLINA SCALE OF MILES O 1 2 CORPS OF ENGINEERS WILMINGTON, N.C. MAP REVISED SEPT. 1977 Plate 9 71 ` `? ?' ` A-- 60DIE ISLAND ? GO N. C. CAPE HATTERAS \ LocAunr MAP E NATIONAL S SCALE OF MIL o 30 60 SEASHORE Ell v -yA OREGON /NL ET BAR CHANNEL /-?--APPROX. LOCATION OF PIPELINE ROUTE 8ONNER BRIDGE x-APPROX. LOCATION OF MOORING \N FOR HOPPER PUMPOUT TERMINAL GROIN C oo st ? i Q 4, p P 1• DISPOSAL AREA 1 EXTENDS 15,000 FEET SOUTH USCGS OF NORTHERN LIMIT 0 1000 2000 1 1 1 SCALE IN FEET r 'PEA ISLAND j NATIONAL WILDLIFE REFUGE N Plate 10 e z a IZ v ;l At _ Q f g E o Y p? = a V 0 i ' ip rc: t i ? Plate 11 CESAW-PD-E MEMORANDUM FOR: All Participants SUBJECT: FY 94 Dredging Coordination Meeting 10 Nov 93 1. The FY 94 Dredging Coordination Meeting was held in Wilmington, North Carolina on 4 November 1993. The agenda for this meeting is included as attachment 1, attendees are listed as attachment 2. Following is a synopsis of topics discussed during the meeting and any follow-up actions which will be required as a result of questions and discussion on the various topics. 2. Review of FY 94 O & M Projects. Discussion on this topic was limited as most O & M dredging projects for FY 94 are performed annually. The only exception to this, for FY 94, is the renourishment of Wrightsville Beach and Masonboro Island, which are scheduled to be performed every 4 years. 3. Proiect/Study Updates. a. Morehead City Harbor, Brandt Island Pump-out. Construction on this project began on October 19, 1993. Currently, dredged material is being pumped out of the Brandt Island disposal site and is being placed on Atlantic Beach. Two items of concern were discussed regarding this topic: 1) Plastic - some of the plastic material, which lines the diked disposal site was inadvertently pumped to the beach, however, the plastic was seen as it was coming out of the pipe on the beach and was cleaned up immediately. A representative of the Corps stated that in the future some material other than plastic may be used, if possible, so this situatuation could be avoided. 2) Fine sediments - because of the location of the spillway and the area where the dredge must enter the Brandt Island disposal site, fine sediments, which accumulate near the spillway, were picked up by the dredge and pumped to the beach. As the dredge moves further into the island the amount of fine material should decrease and coarser material should be encountered. Discussion followed regarding the possibility of managing the disposal area so that fine sediments are avoided, however, it was stated that this would involve moving the spillway to the back side of the island and this was proposed previously but opposed by several State agencias. b. Morehead City Harbor Deepening/Maintenance. Questions regarding the quality of material from the harbor deepening, the method of disposal, and the anticipated quantity of material from maintenance dredging of the deepened harbor were raised. It was noted that the material, based on borings, is medium to coarse sand and the material will be placed on the beach; some material will go to Pine Knoll Shores and some to Fort Macon. Also, it is estimated that the volume of maintenance material dredged from the deepened channel will be equal to the volume dredged during maintenance of the harbor at its current dimensions. C. Sandbagged Disposal Islands. The Corps is in the process of replacing some of the sandbags on Island "H.", which were destroyed during the March 1993 storm. In addition, the Corps is sandbagging the island near old House Channel. Although attendees were not asked for an immediate answer, they were asked to think about the possibility of changing the current method of sandbagging. The suggestion was made by the Corps to pump material onto the islands and then sandbag them, rather that the current practice of sandbagging the island prior to pumping material on the island. This method would contain the dredged material more efficiently than the currently used method. d. Island "H" Mitigation, Oyster Reef Construction and Manteo (Shallowbag Bay) Project, O & M Mitigation, Disposal Islands. Construction of the Island "H" mitigation oyster reef is complete. In addition to the Island "H" mitigation site, there are 7 islands along the Oregon Inlet Channel which are used for dredged material disposal and for every acre of shallow water bottom covered by dredged material, 0.66 acres of oyster reef will be created by the Corps as a means of mitigation. The North Carolina Division of Marine Fisheries will monitor the oyster reef sites for 4 years and then the sites will be turned over to them for management. Discussion followed regarding the lack of information on the long-term productivity of these oyster reefs. Several agencies agreed that a lack of data does exist, but stated that they did not have the resources to do long-term monitoring of the reef sites. A suggestion was made to get local university students to do reef studies as part of their graduate studies. The Corps of Engineers and the NC Division of Marine Fisheries will follow-up by coordinating on exploring the feasibility of initiating studies on this subject. 4. FY 93 Emergency-Dredging Activities. a. Cape Fear River. The Corps removed a shoal in the Upper Midnight Channel by renting equipment from a contractor who was in the area. Approximately 3000 to 4000 cubic yards of material were removed at total cost of $3000. b. Oregon Inlet Dredging. The Corps just completed some dredging west of the Oregon Inlet Bridge. 5. Other Topics/Open Discussion. a. SAV Impact Assessment, Walter Slough Channel. Conclusions on the covering of grass beds are forthcoming. b. AIWW Long-term Study. The Corps is currently working on Phase I of this study and the study will continue as funded. Phase I is an in-house document, but will be available to. anyone interested in its content. A few questions were raised regarding the long-term maintenance of the AIWW and topics which would be included in the long-term study. It was stated that all issues in question would be addressed in the long-term study. C. Cape Fear River Colonial Nesting Waterbird Islands, and Others. The technique of placing dredged material on these islands in the Cape Fear River was very successful. Immediately following placement of dredged material, 3648 pairs of royal terns nested on Ferry Slip Island. South Pelican Island was successful as well. A few islands which are in need of material were discussed. These include Wells Island, the island near Drum Inlet, Wainwright Island and Battery Island. A representative of the Corps stated that placing material on some of these islands was a possibility and would be considered. d. Habitat Creation/Restoration/Coastal America Program. The Corps is investigating possibilities for beneficial uses of the dredged material (rock) that will be dredged from the Ocean Bar channel during the upcoming dredging, which will attempt to deepen the channel to its authorized dimensions. Several alternatives were discussed and numerous questions were raised regarding the various alternatives. The majority of questions could not be answered without further investigation, and it was decided that this subject should be discussed in another forum where all interested parties, including commercial and recreational fishermen, could be represented and questions raised could be answered. The Corps will contact the resource agencies and arrange for the necessary meetings regarding this subject. e. Biological Studies of Beach Disposal Projects. Although some beach monitoring is performed on beach disposal projects, detailed monitoring is not done. There is a serious lack of information in the area of beach monitoring, i.e. there are no established thresholds for monitoring. It was suggested that a detailed literature search needs to be done to determine the "gaps" in the data and then research needs to be carried out to fill these "gaps." It was also suggested that any information gained regarding impacts of beach disposal should be conveyed to the public. Questions were raised regarding funding and personnel for the necessary research. It was again suggested that local university students could perform some of the necessary work. This is a topic which will require further coordination between all interested parties. The Corps will follow-up by contacting the resource agencies and initiating plans to study the impacts of beach disposal projects. f. Report on Shortnose Sturgeon and Other Anadromous Fishes, Lower Cape Fear River. The long-term study results are in regarding this topic and based on the data it would be beneficial to change the dredging window for the Lower Cape Fear River. The suggested change for the dreging window is from October 1 -March 31 to a new window of August 1 - January 31. Several agencies agreed with this change, however, an official position has not yet been received from the National Marine Fisheries Service. Further coordination on this subject will be required and the Corps will initiate this coordination. g. Project Modifications After Award of Dredging Contracts. Attendees were informed that if a contractor proposes any changes to a project after award of a contract, the contractor is generally required to acquire any clearances which are necessary as a result of those changes. This procedure always applies to those changes that are only to the benefit of the contractor (i.e. different borrow area, new pipeline route, etc.). Changes that are made at the Corps request or that have to be made because of changed conditions will be addressed by the Corps. h. Sea Turtle Nesting. Tom Henson, Wildlife Resources Commission, suggested that sea turtle nesting data be looked at to determine if a change in the dredging window (beach disposal) is warranted. If a change is warranted, the Wildlife Resources Commission will initiate coordination between the Corps and resource agencies to discuss possible changes. h. Drum Inlet. The Corps is looking at the possibility of re-initiating dredging in Drum Inlet. An Environmental Assessment will be circulated for public review in FY 94. 6. As a result of issues and questions raised during this meeting the following actions are required: a. Further investigation by the Corps and interested agencies regarding the method of sandbagging dredged material disposal islands. Howard Varnam (CESAW- CO-N) will initiate this investigation if it is to be pursued. b. Initiation by the Corps (Dan Small, PD-E) and the NC Division of Marine Fisheries (Mike Marshall and Mike Street) of the feasibility of studies on long- term productivity of oyster reefs. C. Coordination between the Corps (Trudy Wilder, PD-E) and other agencies regarding placement of dredged material on bird islands which are in need of material. d. Further research into the beneficial uses of rock which will be dredged from the Cape Fear River Ocean Bar channel and coordination between the Corps, interested agencies, and the public regarding possible alternatives. John Meshaw (CESAW-PD-E) will initiate this research and coordination. e. Frank Yelverton (CESAW-PD-E) will initiate coordination on the biological studies of impacts of beach disposal. f. Bill Adams (CESAW-PD-E) will continue to coordinate with resource agencies on the change in the dredging window for the Lower Cape Fear River. g. Study of sea turtle nesting data by Tom Henson a..d coordination regarding a possible change in the dredging window for beach disposal. Coleman Long 0 ? Chief, Environmenta Resources Branch a FY 94 DREDGING COORDINATION MEETING Time: November 4, 1993 - 10:00 a.m. to 12 noon Place: U.S. Army Corps of Engineers, Wilmington District, 69 Darlington Avenue (main conference room), Wilmington, North Carolina Welcome and Opening Comments: Carmine Forcinito, COE, Preston Pate, NCDCM, and Coleman Long, COE TOPICS TO BE DISCUSSED 1. Review of FY 94 O&M Projects (Forcinito/Wells/Varnam) 2. Protect/Study Updates - Morehead City Harbor, inner harbor maintenance/deepening(Wells) - Sandbagged disposal island - Old House Channel, Dare County (Varnam) - Island H mitigation, oyster reef construction, Dare County (Small) - Manteo (Shallowbag'Bay) project, 0&M mitigation, disposal islands (Small) BREAK (10 minutes) 3. FY 93 Emergency Dredging Activities - Cape Fear River (Upper Midnight Channel), removal of isolated shoal (Wells) - Oregon Inlet Dredging and Dredged Material Management Plan (Butler) 5. Other Topics/Open Discussion - SAV impact assessment, Walter Slough Channel (Small) - AIWW long-term study (Wilder) - Cape Fear River colonial nesting waterbird islands, and others (Henson) -*Habitat creation/restoration/Coastal America Program (Meshaw) - Biological studies of beach disposal projects (Yelverton) - Report on Shortnose Sturgeon and other anadromous fishes, Lower Cape Fear River, North Carolina (Adams/Moser) - Project modifications after award of dredging contracts (Small) Closing Remarks: Carmine Forcinito, COE; Preston Pate, DCM; Coleman Long, COE Att-ak _k v„4 e -?4 t L ATTENDEES NAME AGENCY Carmine Forcinito Corps of Engineers James Wells Corps of Engineers Jim Butler Corps of Engineers Howard Varnam Corps of Engineers Coleman Long Corps of NC Divisi Engineers on of Marine Fisheries Mike Street Daniel Small Corps of Engineers Mary Moser NC State Univ./UNCW Bill Adams Corps of Engineers Walker Golder National Audobon Society Tom Henson NC Wildlife Resources Commission Charles Jones NCDCM Rick Shiver NCDEM Preston Pate NCDCM Bob Stroud NCDCM Peter Campbell USFWS Eric Galamb NCDCM Caroline Bellis NCDCM Charlie Stehman NCDLM Jim Gregson NCDEM Jim Bushardt NCDEM Fritz Rohde Therese Conant NCDMF NC Wildlife Resources Commission John Mesraw Corps of Engineers Frank Yelverton Corps of Engineers Howard F. Hall USFWS Ron Sechler NMFS Larry Hardy NMFS Trudy Wilder Corps of Engineers Jenny Owens Corps of Engineers PHONE 919-251-4823 919-251-4824 919-251-4819 919-251-4411 919-251-4745 919-726-7021 919-251-4730 919-395-3905 919-251-4748 919-256-3779 919-946-1969 919-726-7021 919-395-3906 919-726-7021 919-395-3900 919-856-4520 919-733-2293 919-733-2293 919-395-3900 919-395-3900 919-395-3900 919-395-3900 919-726-7157 919-251-4175 919-251-4640 919-856-4520 919-728-5090 919-728-5090 919-251-4581 919-251-4757 A-1Cn??wi?rr? Z V/ I * 415? : d ?? a i /. .4- ------------ i r- ---------- i --- J O FY 94 DREDGING COORDINATION MEETING Time: November 4, 1993 - 10:00 a.m. to 12 noon Place: U.S. Army Corps of Engineers, Wilmington District, 69 Darlington Avenue (main conference room), Wilmington, North Carolina Welcome and Opening Comments: Carmine Forcinito, COE, Preston Pate, NCDCM, and Coleman Long, COE TOPICS TO BE DISCUSSED 1. Review of FY 94 O&M Projects (Forcinito/Wells/Varnam) 2. Project/Study Updates - Morehead City Harbor, inner harbor maintenance/deepening(Wells) - Sandbagged disposal island - Old House Channel, Dare County (Varnam) - Island H mitigation, oyster reef construction, Dare County (Small) - Manteo (Shallowbag Bay) project, 0&M mitigation, disposal islands (Small) BREAK (10 minutes) 3• FY 93 Emergency Dredging Activities - Cape Fear River (Upper Midnight Channel), removal of isolated shoal (Wells) - Oregon Inlet Dredging and Dredged Material Management Plan (Butler) 5. Other Topics/Open Discussion - SAV impact assessment, Walter Slough Channel (Small) - AIWW long-term study (Wilder) - Cape Fear River colonial nesting waterbird islands, and others (Henson) - Habitat creation/restoration/Coastal America Program (Meshaw) Jo?n - Biological studies of beach disposal projects (Yelverton) - Report on Shortnose Sturgeon and other anadromous fishes, Lower Cape Fear River, North Carolina (Adams/Moser) - Project modifications after award of dredging contracts (Small) Closing Remarksi , Carmine Forcinito, COE; Preston Pate, D/,CM;t Coleman jLong, COE `.. C/rt^?' aG(6Z yurxr'S (v j1 L7 /?,- ?, ??,pyW 1 y "rvt ,J i ae tr' 4 ry FISCAL YEAR 1994 0 & N DREDGING CONTRACTS PROJECT,' IIFB%CONTRACTICONTRACT 1ADVERTIS.IBID OPEN !AWARD ICOMP. IPERF. 1AVAIL.IDRED. DESCRIPTION ----------------=- INUMBER !AMOUNT -- I------------ j---------- IDATE -- I------- IDATE ---------- IDATE -- ---- IDATE t IPERIOD ;BW ; ITYPE AIWW (Norfolk- I I I 1 --- --, ----- I -- j----- ! .... --, I -- I----- ! SC line) i5 191-3-0000 ( I IDec 1 iJan IFeb ! lzont INo IF AIWW Inlet kings 4 194-8-0000 ! 119 Nov 113 Dec !!DEC 93 1June 16 nos INo 1P AIWW A/P 8 194-B-0000 ! IDec 93 !Jan 94 1 !Mar 1 12 mcs IYES IP Wilmington Harbor ! ! I I i ! I I I I ! i ? I ? ! Anchorage Basin/ j I I i i I I I I 3S Ft project 1 193-C-01VO3 13,394,960 13 Sept 11 Oct 18 Oct (Apr 3 Mcs INC IP Ocean Bar 1 194-8-0000 1 115 Oct 118 Nov INoV IMar 94 ;3 HOS INC IH Ocean Bar Rack 194-8-0000 I IJune !July !Aug 1 1995 1 1 1 Ditch Eaale is 194-B-0000 I INOV IDEC ?Jan (APP, 13 Mos I I I I I I I I I I IF Wrightsville/ 2 194-B-0000 IDec 1Jan (Feb 1May 13 Hos INC IP Ma.cnbaro I ! ! I I ! I ? ! Morehead City 3 l93-C-0043 1 10,802,345 19 June IS July 119 July 131 Mar Ocean Bar 1933-C-0005 I 14,880.276 19 Sept I ! 112 Oct I 11 Nov ! 131 Mar i 12 MOS 1-No I I IH Manteo(Old House- I94-B-0000 ! I 1 119 Nov I 117 Dec I 13 Jan ! 131 mar I I 2 mcs I Wanchese) 6 ! 1 1 1 ! ! 1 1 1 Oregon Inlet Bar 6 I 194-B-0000 I I I 1 115 Apr I ! 119 May 1June I 1 I I 13 NOS INC I IP :ape Fear Above 94-B-0000 I Dec I Jan I Feb I Apr I I 2 MOS I IP SUNNY POINT 194-B-0000 I 1 14 Apr I 17 May IMay IJUN 92 13 NOS INO IB I I +?+++++++t++ I ++++++++++++ I ++++++++ I ++T++++++++ I I ! +++++++++ I +++++++ I I I 1+4+4++41 ++++++ 1+++++ 3 NOV fy94 FY 94 COORDINATION MEETING PROJECT INFORMATION FY 94 DREDGING PROJECTS 1. ATLANTIC INTRACOASTAL WATERWAY NORFOLK (AIWW) TO SC LINE. (Plate 1) Project Description. This routine maintenance work involves removal of material lying above the plane of 14 feet mean low water (mlw) along designated limits of the AIWW. Dredging is performed with a hydraulic pipeline dredge with disposal of dredged material in diked upland disposal sites along the channel. Dredging of the AIWW between Bear to Brown Inlet is scheduled for this coming fall. Dredging will be performed under the dredging contract for AIWW inlet crossings. 2. ATLANTIC INTRACOASTAL WATERWAY (AIWW) INLET CROSSINGS. (Plate 2) Project Description. This routine maintenance dredging involves removal of all material lying above the plane of 14 feet below mlw within the designated limits of the channel at various inlet crossings. The estimated quantity of material to be removed varies, depending upon the areas to be dredged during the dredging cycle. Dredging is to be accomplished by a hydraulic pipeline dredge with disposal in upland disposal sites or along the ocean beaches adjacent to the inlet crossings. Maintenance is scheduled to start in early January 1994 and will require --approximately 6 months to-complete. Area to Dredged Estimated Quantities Disposal Area (Cubic yards) Cape Fear- Little River Reach - Shallotte Inlet Crossing 69,400 Ocean Isle Beach - Lockwood Folly Inlet crossing 42,000 Holden Beach Beaufort - Cane Fear Reach - Carolina Beach Inlet crossing 18,000 Masonboro Island - Mason Inlet Crossing 13,000 Wrightsville Beach - Shinn Creek Crossing 25,000 Upland Dike - Bogue Inlet Crossing 30,000 Upland Dike - Entrance Channel to Oak Island 60,000 Upland Dike Coast Guard Station - Southport Municipal Boat Basin 80,000 Upland Dike - Topsail Inlet Crossing 14,000 Topsail Beach - New River Inlet Crossing 56,000 North Topsail - Bear Inlet to Brown Inlet 150,000 Onlsow Beach - New River(Channel to Jacksonville) 75,000 North Topsail Beach 3. WILMINGTON HARBOR ANCHORAGE BASIN, 25-FOOT AND 38-FOOT PROJECT. (Plate 3) Project Description. This routine maintenance dredging is scheduled to begin November 1993 and will be completed prior to March 31, 1994. The work consists of the removal of all material lying above the plane of 40 feet below mean low water (mlw) within the limits of the channels. The estimated quantity of material to be removed from the Anchorage Basin, Between Channel and Fourth East Jetty is approximately 800,000 cubic yards. The type of material is predominately silt with lesser amounts of sand. The frequency of dredging is once every year. The dredged material will be placed in the Eagle Island Upland disposal site. Also to be dredged.at this time is approximately 30,000 cubic yards of material from the 25-foot project turning Basin which is predominately fine sand. This material will be placed in the Ideal Cement disposal area. For the 38-foot project, approximately 370,000 cubic yards of material will be removed from Upper Midnight Channel, Upper Lilliput, Keg Island, Lower Brunswick, Upper Brunswick, and Lower Big Island. The material consists mostly of fine sand and silt with lesser amounts of shell fragments. The location of the upland disposal sites are shown on Plate plate 4. This work will be accomplished by hydraulic pipeline dredge 4. WILMINGTON HARBOR - OCEAN BAR CHANNEL. (Plate 4) . °-"PraJect-'Descript on. This routine mai-ntenance--&edg•ing- involves removal of -all material lying above ,the- -plane-.of_.40..feet..below mlw . in. Bald__.__.___ Head`"S?ioal'Channel: "lpproximately-700 `000-cubic`-yards--af.-ma-ue4--ial -is °> -- - ? - dredged annually from the channel. Dredging is expected to occur during the winter of 1994. The material will be removed and transported to the. Wilmington Harbor Ocean Dredged Material Disposal Site (ODMDS) by hopper dredge. 5. WILMINGTON HARBOR OCEAN BAR CHANNEL (ROCK DREDGING). (Plate 4) Project Description. This work involves providing the authorized project depth of 40 feet at mlw for the Wilmington Harbor ocean bar channel (Baldhead Shoal Channel). Rock obstructions will be removed from the channel bottom beginning at station 125+00 (12,500 seaward of the channel's intersection with Smith Island Channel) and proceeding seaward to the end of the channel at station 305+00 (about 5.8 miles at sea. Dredging is expected to _q.ae?rr? during the summer of 1994. S-?S L l 830 000 ?v1oVo --, /00/9 n?qt? I "706/t ? " a /4?r -?j0 ?tGXX ?IoC?C 6. WRIGHTSVILLE BEACH/MASONBORO ISLAND. (Plates 5A, 5B) Project Description. The proposed action involves the renourishment of Wrightsville Beach and performing sand bypassing of material to Masonboro Island. Material will be obtained from existing sediment traps/borrow sites in Masonboro Inlet and Banks Channel. The material is naturally occurring coarse to fine sands. Due to limited availability of sand in existing sediment traps, in 1994 Wrightsville beach will receive an estimated volume of 594,000 cubic yards and Masonboro Island will receive about 343,000 cubic yards. Renourishment of Wrightsville Beach is scheduled to begin in mid-January 1994 and be completed by late April 1994, bypassing of material to Masonboro Island is scheduled to begin in late April 1994 and be completed by mid-July 1994. 7. MOREHEAD CITY (INNER HARBOR PROJECT). (Plate 6) The proposed action involves disposal of dredged material on Bogue Banks from maintenance dredging of Bulkhead Channel, the combined maintenance dredging and deepening of the Morehead City inner harbor navigation channels, and pumpout of the Brandt Island upland diked disposal site. Dredging started October 18, 1993 and is scheduled completion date is March 15, 1994. This is a one-time action. An additional three months (September - November) is needed beyond the regular disposal window in order to have sufficient time to perform the different aspects of the work. 8. MOREHEAD CITY HARBOR OUTER HARBOR (OCEAN BAR CHANNEL). (Plate 7) . Project--,Description. The Outer. harbor Deepening: _and. Outer harbor a_ maintenance consists of: deepening the..outer harbor_,(Cutoff Channel) to -45 feet cl Epen^in?'-the -6hter,-bar charnel.(Range- A-)-.xto.,i-47,cifee-t--mlw from?::,42 feet mlw, and.adding wideners along the outer harbor range A channnel. The outer harbor maintenance consists of removing the maintenance material in the outer harbor to -40 feet mlw and in Range A to -42 feet mlw. The total quantity of material to be dredged is estimated to be approximately 2,775,100 cubic yards. All dredged material from the outer harbor maintenance deepening will be deposited in the designated Morehead City Harbor Ocean Dredged Material Disposal Site. The work is scheduled to be performed between December 1993 and March 1994 by hopper dredge. 9. MANTEO OREGON INLET CHANNEL (INTERSECTION - MANTEO-OREGON INLET-OLD HOUSE CHANNEL) (Plate 8) Project Description. This routine maintenance dredging is scheduled to begin or or around January 15, 1994 and will require approximatley 90 days to complete. The quantity of material to be removed is approximately 100,000 cubic yards of coarse to fine sand. The work requires the removal of all material lying above the plane of 14 feet below mlw. The work is performed annually. The work will be accomplished by hydraulic pipeline dredge with disposal of dredged material on adjacent disposal islands using the control of effluent method of disposal. 10. OREGON INLET (OCEAN BAR CHANNEL). (Plate 9) Project Description. This routine maintenance dredging which is currently being performed involves the removal of all material in the authorized channel to a depth of 14 feet below mlw in miles 0 to 1.5 of the channel from Manteo to Oregon Inlet, and 17 feet below mlw along the ocean bar channel. Environmental clearances have been received to perform routine maintenance dredging of the ocean bar channel by an ocean-certified hydraulic pipeline dredge or hopper dredge with direct pumpout of dredged material with discharge of dredged material on the Pea Island National Wildlife Refuge. Work is currently performed with an ocean-certified pipeline dredge. 11. CAPE FEAR ABOVE WILMINGTON. (Plate 10) Project Description. The work involves removal of shoals along the navigation channel in the Cape Fear River from Wilmington upstream to Fayetteville,'approximately 111 miles. The total estimated quantity of material to be removed from all reaches is approximately 87,500 cubic yards. Dredging is performed by hydraulic pipeline dredge with material being placed along the toe-of-the-bank annually and in upland diked disposal areas once every 5 to 6 years. Dredging in FY 94 is contingent on the availability of funds. 12. U.S. MILITARY OCEAN TERMINAL SUNNY POINT (MOTSU). (Plate 11) Project Description. This routine maintenance involves dredging of the facility s a-c-aes" =channels, connecting c}iannels;-and-navigation. basins on - f - -? r the Cape Fear River in Brunswick County, NC, to an overall depth of 36 feet below mlw. Dredging will be accomplished by a large volume clam bucket dredge. Materials excavated by clam bucket dredge will be transported by scow or split hull barge and dumped in the EPA approved Wilmington Harbor Ocean Dredged Material Disposal Site. Dredging schedule is contingent on shoaling conditions which is expected to occur around May-June. NOTE: Funds for this FY do not allow a complete survey of projects. Other projects may be scheduled as navigational surveys are performed or unexpected shoals occur which require immediate removal. Should funds become avaiable and projects are scheduled, notices will be made avaiable to Federal and State resource agencies and the interested public. f 14f 1:111 A 1 Y.' w. VIRGINIA -- - c ` -- V 1LA14.C:1t:N --- - I• a ` ct? `l WSTRICT NORTH CAROLINA 4, v l(, \ J0 v \ ' 1 • G ??Lf^•1:?In ? Sound 3 ALLIGATOQ- PU.T16? ?COk/?° AtOO.w°'ic Q ?? Winteo P"wD CLT-- /T Y R 11 E L l •OanE - r ' At r E 1Woshingtor. C ?V1 ?` ? l ae rCaPE No/b0'of Antos New Bern ? i Ocrocoho In1*1 \ P w M 1 ONSLOW C A R etetatt r Jacksonville • y P E N 0E a O i 1 Wdnwnglon S yafeM°.o MNt p.'t f •aUNSWICK ti. Al W J /1/t ?J'1 It If/ %0 :/l 411 •.1? .:AI'1 J 1 Aft (NI1 A 1 W W MIS MIL utNG I ON DES i RICT General Location Map Atlantic Intracoastal Waterway Vir(jini.i Suite Line Lo l.il LI•? River Inll•L, .1;0ul.h (:ot ol il?.? ? \ aTe I U.S. ARMY CORPS OF ENGINEERS NORFOLK O USSR SUFFOL e - us36 ? b h BEGIN A.I.W.VK DISTRI+CTON VIRGINIA - N NORTH CAROLINA J OINJOCK BRIDGE E.UZAd CITY b T 70 vs 11 rARL( JurrO • ?`(( P ?wrE WINDSOR WILLUMSTON Z ! ORlfOM X64 .e !O o ircEr WILSON f FAIRFIELD BRIDGE is x5301 Src+ REE:NVILLE MfILKERSON CR A FIELOLNT PING, A INGroN BRIDGE . V us'O us rs ?,,. 013 x Q"S80R » ° 5 KIN ON OBUCKKEEN BRIDGE `0 Ie V i tAK XAT CPAS 1 Us KG S * L' p It --/70 NEWBERN o • SLOE CH ANNE CORE C le K BRIDGE a BASIN AT ': ;;;:'lAC+csoNV ANSBORO ..:.... - -•=r•- - "'CNANNECS TO ?_:?- ?'i .:y..,-' '- ?._- ------ _. ._._._ _r - _ JACKSONVILLE 8 • . ' # s/° d HEW RIVER INLET eA?c Ic _:- - OGUF? PELTtER CREEK :! tC iNLET la 1 b tl ?' - P 50 !er HANNEL TO 80GUE INLET G R 0 0 • 74 •• TOocell INI FT AND `CONNECTING CHANNELS lO G ` WIU11NiTaN MASON80R0 INLET , BASIN AT? t9o AND CONNECTING CHANNELS BOAT A Ia V SOUTHPORT ©? MUNA 6EJ?CI+ INLET 1. P 7k F+cl 1f?1 `? {J (t3-1 CAROLINA BEACH HARBOR Ib * s Stl CAM rtAA END A.I.W.W. SOUTHPORT HARBOR fib WILMINGTON 1c _ DETAIL SHEET NUMBER. DISTRICT /.T0 -MILEAGE. MEASURED FROM FOOT Of WEST MAIN STREET. NORFOLK. VA. ATLANTIC INTRACOASTAL WATERWAY BETWEEN NORFOLK.VA.AND THE ST JOHNS RIVER, FLA. (WILMINGTON DISTRICT) -77 r VARYING SCALE Of MILES L j C ap p t0 VARYING CORPS OF ENGINEERS WILMINGTON.N-C- TYPICAL SECTION MAP REVISED SEPTEMBER 1983 , 'p t ec a a 1 ? K J Z :r a Af r : t N ? .moo A Y s M 7 t t V J i 7 Ot i i? ri_ S? 3 ` / z Z 0 t7 ? 0 ac m Q a V? Q J 3 0Q a ~ u Z C O `may Z J ? y _ 1 / z 3 O Y i 1 1 1 1 1 Z 1 O 1 r 1 Y w_ J? 1 ? _Y 1 ? 1 - r ? I F P 7.ww A- - 1 ( .•Batl•r7 I ?? ?-a '?Y 1 1? 0 1°a bond S 1 s?uK •? / 7 °b•k''?o ? I 1 a s J z 1 ? Ye Pon 9:eeli ? •'r ' M Ta...•ey 9?ya? ?w 71a A? \ I i0`d'17 C1. 2 /J { l V 2? ?j -A QAK • Fart C-9 \? IS •1i_ :i4 :: 4..n 30 is ly 1) 7 to Gh•na• r 16 14 .0 21 © - 7 {1 ?•j. •-C 13 2 25 711 ? 71 10 . '?' • . . 26 + i 71 • \ ,• ?..?.. a ' is ? ? Bald H ad .•f ,?.' y `'`?"? 34 2 f 26 of 13 •t It 6 20 31 \ t+ to Ia,d {` 7 ald Head jsland la •?? 1] n 11 fla f 7 BAL]}lIEAI} SHOAL CHANNEL t{ RR?, ,• 17 11 1° / 14 10 \ 1{ la -? ncu.? n If IS x / 17 42 33 1) 28 35 Y. 1+ to 7 f Mf1A4 I 1{ >a / I / ' 7) 71 n 7e r )7 _ x % /IC a. / 11 )' x x )7 13 71 77 H ]? ,\ 7) tl " : \. 70 19 14 / \ P 1 43 10 Z4 OCEAN \` )1 )) I x _ 34 DREDGED ' MATERIAL 3000 0 3000 6000 goo-c" u " DISPOSAL .\ SCALE IN FEET \\\ SITE 1 j7 a3 n ? I-\ / Tti \ / lc WILMINGTON HARBOR. I4ORTH CAF.OLi2.' O /CEAN BAR CHANNELS 42! g Q Q v• ? 3 a Z Q z U 3 ? J z u s/?' Q y Q 0 _ V Q Z r _ci x x Np?? U z 2 CD U O w W E, J U V) O ZZ: z ?? Q 3 w t to O • U CD I o? O OW • HO Q I < J VV O-Jr W ' O z -C cc U oo w • o w M LL- z W x o W =CL L7 cr 7- V_ I o .a w r •,. J LL 1 ~ 0O 0O I 4 H w O Q' M x O Q LA- ID 9= z z a wa x = ,c -, w S°' a ~co VIX i LL z 0 I --w m wa ! oN •' N O O w I F- CL 4-77N/ If: - 'YOGiUOSD, y O X11 3r ?:___ ? Boa _..?, 47 3 J Q w =a w 0 z Ar2 • VA. NORFOLK N ' N 0 R T H • CURIUM O RALEIGH C A R O L I N A CAPE OOYNTERAS m Cm Atlantic Ocean •'? rttH?wcroN S • C.-\ SITE o so ao CN£ SCALE H YI.ES fEAN VICINITY MAP ??O ?O V O ATLANTIC OCEAN v C1 y? NOTE: SHORELINE DIGITIZED USING VISIBLE HIGH WATER MARK FROM 1990 ORTHOPHOTOS. .A-BYPASS " MASONBORO ISLAND. NORTH CAROLINA SAND BYPASSING 5000 2500 0 5000 10000 PROJECT LOCATION SCALE IN FEET ,` ..•.C' ; toot V p O 2 s b d1?? Q? Z Q . 7 j tF., c f t I.1 , m y t (C A ? V q .+. ??•? ?., . • O j = J W r C . ~'! r oygr i \ ?? y _d G? ,.. R,1 W O a i • +f ? r.e ,,tom t t A ?t s t..? ? r s s ? ?,• ?; ? 4' r :1 Via. •ti''??:?I• ? fly Imo` - Q r' s i as ,•• \ ? i?' ? ly C N I ,ar r•' 1 y0 . I Wo Q z N ' F•• W N W ... at Q 0° N - . O _o N . O M M Q F- N N Q1 a' O 2 v $ a ".r. 1 t~LI a F?-• Y M ? J Z ir Z Q ? O M J W W N d vvi 0 N o O co ? a. 0 -?-Z W r N r Q I I s z O I w•-• ? I O J I I 1 .tT"P i i I ----------.a::?? ------- TYPICAL SECTION -J ? e .... .. •....Qop a? (:o. 7-7. BEACM,DISPOSAL AREA VKr. ?G o at moo. C fp ? t'sl TM 6 ? OY: C \ a? ? s 2 ?m sD x= ?2• l a:: a? G a. 0 Cl C7 J9 C :a U I: ,A, ` pcc,N 0001 PROJECT LOCALITY YAP stuff( o. •.aas o So to I SNACKI EfOUO 1 . r r LEGEND a r I..o Ar r i c o c F A :r ® - DREDGED MATERIALS. FROM THESE AREAS ARE PROPOSED FOR OCEAN DUMPING MOREHEAD CITY HARBOR, ! ® - BEACH AREAS USED FOR DREDGED MATERIAL DISPOSAL NORTH CAROLINA ! 1 ` - BRANDT ISLAND. UPLAND DREDGED MATERIAL DISPOSAL SITE SCALE 0; 404LES 4,2 r '. CORPS OF ENGINEERS WIL1.*:INGTOU.N C YAP REI/ISEO SEPTEMBER VCV A aT ? `7 ', ?+ ?o •r+so • ? o y ? Z 0 w (?I R . r? H o . ? -sp a . - o` . K? 'P. r Z n O .n Th lip ?c ,?.wrto I?..ww?•ca .., NMI" CASOUNA DREDGED MATERIAL • DISPOSAL ISLANDS -' 600lE ISLAND C ,'? ,EGG & C. CAPE HATTERAS I '1 LOCAUTY MAP NATIONAL .1 SCA.E0 MILES o * SEASHORE W Al) O OREGON 11W ET BAR CHANNEL Off- /-.*-APPROX. LOCATION OF PIPELINE ROUTE '- f SONNER:BRIDGE ?-APPROX.. LOCATION _OF MOORING... Pt11ViPOUT: i TERMINAL GROIN Av a p P? 15 ?- DISPOSAL AREA EXTENDS 15,000 FEET SOUTH USCGS ?. OF NORTHERN LIMIT MAINTENANCE DREDGING OF OREGON INLET :j. PEA ISLAND OCEAN BAR CHANNEL NATIONAL BY WILDUFE OCEAN-CERTIFIED REFUGE HYDRAULIC PIPELINE DREDGE OR HOPPER DREDGE WITH DIRECT 0 1000 2000 2 PUMPOUT OF DREDGED MATERIAL t = U SCALE IN FEET .? JUNE 1991 . J.n U.S ARMY C ORPS Ut- tNUINttKS 7 4 1 JI UPSTREAM LIMIT OF I PRO E ? FAYETTEVIL " FEDERAL PROJECT L N ? s=c-1 f EsN UA 4*1 1 ML 111 M { OC > `, ANTIC " pTL J % sc.L4.4 LOCALITY MAP . lROSEBORO scALt Of Y.ats a 36 10 C SEA NO $0 COUNTY • '. ? SAMPSON COUNTY e ` i a \ J -' LLIAM O. NUSKE LACK B DAM 9 111 Fine ". ct- soo v[aLCL so' Qua=poi 1.1 \ v ?OOl lC [L. ?JJ i WHITE Hate Oaect o 43-6 WHITE 1 ROBESON CO. L„ POOL Levitt 'O 1131co tRlo4c ,\ Ca. 1 ,q .ooa LCVCL I ? .{'1t5 ,?t_.. TL7 ??? qc>r ll I ? , LACK B DAM NO 2 -LUMBERTON . ?i L•s ELIZABETHTOWN / / BLADEN CO 9 +c 60 1. r 1 \ iL S NC as O w. ry > - -? _.- CL.ARKTON L.CUS_nalr v c c` -• « y { • O - PENOE R COUNTY r ,'t ' / [ om c ? ? ' LDCKB DAA1 Not Lt c ?. 'r :to OAIocc A SO \ ? OOLK Hoo.CL.2H' YtoT:CL. •2 Y.lT1 NtCI. 1T COLUMBUS COUNTY 30ML / = o:T•_TC RIEGELW A ME 20w, - WHITEVILLE Trot OML NAVAS WILMINfTON .? y _... / BRUNSWICK CO NEW NANOV ER NIIOGC Co. OASCULC A N . Yp1. CL. $02- 1 vt11LCs'II.L,?. 041" cLo cwsto :&ScULC Mt GRUP" 0* AL, KO' vt RLCL W-La, on, CLOstO MILEAGE IS MEASURED FROM THE CONFLUENCE OF THE CAPE FEAR a NORTHEAST CAPE FEAR CAPE FEAR RIVER, N. C. ' ----- ------"" ----- ABOVE WILMINGTON I? VARYING SCALE OF MILES 3 S O S 10 Is VARYING CORPS OF ENGINEERS WILMINGTON,N.C. TYPICAL SECTION MAP REVISED SEPTEMBER 1933 v 11--T'P it _ r-- ?I i= I ? W i ? i <L _? E < 2 i? 0 o Y p itts 1, v t ALTERNATIVES ANALYIS CONSTRUCTION OF SANDBAG DISPOSAL ISLAND OLD HOUSE CHANNEL, DARE COUNTY, NORTH CAROLINA A. Project Description. The sandbag retention island will be located approximately 1.5 miles from the junction of Old House Channel and Oregon Inlet Channel (figure 1). Construction of the sandbag dredged material disposal island is needed in order to accommodate disposal of dredged material from maintenance dredging of Old House Channel between Island MN (006-08) to the north and the sandbag disposal island (Wells Island - 006-35) located approximately 2.0 miles south of the junction. Wells Island was constructed in 1988. Construction of the 12-acre sandbag retention dike is scheduled for the summer of 1993 and is expected to take approximately 1 to 2 months to construct. The project is being coordinated with the National Marine Fisheries Service, Beaufort Marine Laboratory, to further document whether submerged grassbeds are in the area. Based on initial review of aerial photography, there appears to be no submerged grassbeds located within the general area of the proposed construction site. Once the sandbag retention dike is constructed, dredged material from maintenance dredging of Old House Channel will be placed within the confines of the dike to construct the island. Dredged material from routine mainte- nance dredging will be placed on the island using the control of effluent method of disposal (i.e., allowing the effluent to flow back toward the channel being dredged). shows that water depth is approximately 2 to 3 on the east side of the channel. Depths on the range from 7 to 10 feet m.l.w. Therefore, the be constructed on the east side instead of the as described in the Final Environmental Impact A copy of the'hydrographic survey is available feet mean low water (m.l.w.) west side of the channel sandbag retention dike will west side of Old House Channel Statement. The site is remote. upon request. Approximately 4,000 cubic yards of predominantly fine to medium sand will be excavated from the bottom in the vicinity of the construction site for the filling of the nylon sandbags. The sand source is free from toxic material. B. Environmental Documentation. The use of sandbag dredged material disposal islands along Old House Channel is described in the Final Environmental Impact Statement and the Final Supplement to the Environmental Impact Statement for Manteo (Shallowbag) Bay Project, Dare County, North Carolina, filed with the U.S. Environmental Protection Agency on April 29, 1979, and November 7, 1980, respectively. State Consistency concurrence was received on September 19, 1980, for the Manteo (Shallowbag) Bay project, which includes Old House Channel. A Section 404(b)(1) Evaluation (Public Law 95-217), dated December 12, 1977, was prepared for underwater sand filled bag retention works associated with construction of disposal islands along Old House Channel. Use of sandbag dredged material disposal islands as part of the dredged material disposal plan for the Manteo (Shallowbag) Bay project was approved prior to passage of the Clean Water Act (December 7, 1977). A Section 401 Water Quality certification was requested from the North Carolina Division of Environmental Management on February 5, 1993, to cover construc- tion of the sandbag retention dike. A Public Notice describing the proposed project will be prepared and circulated to Federal and State agencies and the interested public prior to construction. C. Alternatives. Dredged material disposal islands along Oregon Inlet-Old House Channel are managed for colonially nesting waterbirds. Material is scheduled for placement on the islands when feasible in order to provide suitable habitat for pioneering bird species (i.e., birds pre- ferring mounded bare sand with little if any vegetation). Dredged material from maintenance dredging of Old House Channel is routinely placed on Islands L (006-02) and MN. Elevations on these islands have reached a point where wind borne sand is becoming a major problem for habitat management. For bird management purposes, normal elevation of these islands should not exceed 15 feet in height, since the higher the islands project upward into the coastal winds the .greater the likelihood of nesting failure due to nest covering by shifting winds. Islands L and MN have already reached elevations close to 15 feet. Disposal islands along the channel are expanding into the surrounding sound at a rapid rate along the nonchannel sides due to sand migration off of the island. Any increases in the size of the islands enhances the likelihood that predatory mammals can be sustained and become permanently established. Placing additional sand on the islands would only exacerbate the problems currently-being expefienced. a?=s?a- aty=of -=pumping,=mai-n-tenancA.-r.&,edg..ed=-mater a .ath J d; -- :. material disposal islands along Oregon Inlet-Old House Channel has been investigated as a possible alternative to construction of the sandbag island. The District has agreed not to dispose on Island MN unless prior approval has been obtained, because the island serves as a nesting area for brown pelicans. Operational constraints due to the pumping distance to Island L which is the nearest disposal island to'the section of channel to be dredged (3-4 miles maximum) limits the feasibility of this being a long-term management option for the disposal of dredged material from the channel. D. Mitigation Plan. Construction of the second sandbag island is part of the operation and maintenance plan of the existing Manteo (Shallowbag) Bay project. The sandbag retention dike will cover approximately 12 acres of estuarine bottom in Pamlico Sound. The raising of estuarine bottom and any associated mitigation is done in accordance with the U.S. Fish and Wildlife Service Mitigation and Enhancement Plan dated August 21, 1980, for the Manteo (Shallowbag) Bay project. The mitigation plan for the expansion and maintenance of the Manteo (Shallowbag) Bay project requires that 0.66 acres of oyster reefs be constructed for every acre of estuarine bottom raised above mean high water. Funding of any mitigation is a Federal responsibility. Site selection, construction, and maintenance of oyster reefs will be done through a Memorandum of Agreement between the U.S. Army Corps of Engineers, Wilmington District, and the North Carolina Division of Marine Fisheries, Shellfish Rehabilitation Program. The District has done a preliminary assessment of the total number of acres of estaurine bottom raised from maintenance dredging since 1977 as a result of the use of dredged material disposal islands along Old House Channel and Oregon Inlet Channel. Attachment 1 shows the total number of acres of estaurine bottom raised per island since 1977, based on planimetering work done by the District using aerial photography taken in 1990. Through a previous agreement with the State, only those acreages of estaurine bottom raised as a result of disposal of maintenance dredged material on these islands since 1977 will require mitigation. The acreages raised by the first sandbag island in 1988 (Wells Island) is shown on attachment 1. The acreages raised by the construction of the second sandbag island this summer will be included in the overall number of acres of estaurine bottom shown on attachment 1. Currently, the North Carolina Division of Marine Fisheries, Shellfish Rehabilitation Program, is implementing the mitgation plan for the recent expansion work associated with Island H. Construction of the oyster reefs near Wanchese should be completed by the end of this year. At this time, we recommend that this work be completed prior to any further mitigation work in order that any. experiences learned can be incorporated in future plans. 3 a o a 0 ' ?a .wwwp Z e ` t4 r M ? . er 003-04 H 7 ao ? ? ? y O C. Z 4A V. D Z w Z ZO o N Q m . M ti w w 003 -09 t ? . i 4 03-OS • t. F a? gQE wu?A e" O lNflf fW {S' ZZ` IU f6 003-07 <. ,Vb--? ~ 0 c ?_ = i?'ts bbd :r ,r :r ,r N N 005-Ob))) 005-05 K?tlr?.c ?A ?0?9• 006-02 SO?NO 005-03 ?O 006-06 M ?? vs coal ouMO_ swoN PAM ,• ? - - z 49 oij I. 40 N N N ti yy ?y N? M N If IF PROPOSED DISPOSAL ISLAND (1993) y DIKED UNDERWATER DISPOSAL AREAS .¦ MAMEO (SMAt,*W&A?1 SAY sMs" CAROUNA DIKED UNDERWATER DISPOSAL ISLANDS air a* . r? ISLAND CONSTRUCTED SCALE IN 1988 (NC- DR-006-35) cwt l& 2e JANUARY 1993 Figure -. MANTEO (SHALLOWBAG) BAY PROJECT Manteo/Oregon inlet-Old House Channel Disposal Islands Disposal 1977 1990 1977-1990 Island Acreage Acreage Change (+/-) "B" 23.0 acres 11.5 acres -11.5 acres "C" 60.3 acres 65.0 acres +04.7 acres "D" 31.1 acres 49.8 acres +18.7 acres "F" 43.9 acres 31.0 acres -12.9 acres "G'I 16.3 acres 14.6 acres -01.7 acres "H" 18.1 acres 18.0 acres -00.1 acres "L" 19.9 acres 57.4 acres +37.5 acres "M & N" 41.4 acres 58.5 acres +17.1 acres "Wells lsl." 00.0 acres 19.9 acres .+19.9 acres "Sandshoal" 00.0 acres 19.0 acres +19.0 acres Net Total = +90.7 acres Note: 1) Islands " A," "E," 111," and "J" have not been used since prior to 1977. 2) Island "K" has disappeared since 1977. 3) Islands "M" and "N" have merged since 1977. 4) Islands were planimetered using November 1977 aerial photography. and April 1990 aerial photography. Attachment 1 MEMORANDUM TO: Mike Marshall FROM: Jeff FrenchZ=-O? DATE: October 4, 1993 SUBJECT: NCDMF/US Army Corps. On September 2, 1993 the crew of the R/V SHELL POINT completed cultch planting operations for 1993 at Half Moon Rock, in Roanoke Sound, Dare County. A total of 30,050 bushels of cultch material were placed at Half Moon Rock during 1993 in response to your instructions concerning estuarine bottom mitigation relating to US Army Corps of Engineers activities in the area. The following table details the cultch material composition of each of the planting site established during this project. Planting Site No. 802 803 843 Planting Dates Aug - Sept 1992 Aug - Sept 1992 June - Sept 1993 'Bushels Cultch Tvae Planted surf clam 33,000 Surf Clam 6,000 Surf Clam 22,000 Calico Scallop 5,750 Marl 2,300 TOTAL 69,050 Planting site No. 843 was established to the south of site No. 802 in the Half Moon Rock area of Roanoke Sound. Calico scallop shells and marl (fossil stone) were used to complete the 1993 planting due to a shortage of available surf clam material. Both marl and calicos are regularly utilized as cultch material within our program and should prove as equally effective as surf clam ,, -shell in that area. The planting sites were established on flat r sandy bottom at an average depth of 5 feet. Page two Sampling of oyster larvae (or "Spat") found on cultch material planted during 1992 has,been completed by our staff. Both planting sites No. 802 and No. 803 were found to contain an average spatset of 0.67 oyster larvae per piece of cultch. This is generally considered a moderate level spatset with 1.0 or above considered as good. The locations of all three cultch planting sites discussed herein are made available to the public. Loran bearings are listed 'below for ends of the sites. Site No. Loran Bearings 802 26983.3/40599.4 26983.7/40600.7 803 26984.5/40596.7 26984.3/40595.8 843 26983.4/40599.1 26983.6/40597.2 /bj ,if O ¦ .? N Q. = 0 M Q) 0) o U U cV A 0) C -W v G 0 o m CA U. _ _ *" !a V z u cc i Ii; ? p O 0 O 0 O ? O I- m ? c1r) (1) co ca N ? N ? - M rn .- ? r- C)) o Z N N N 00 cY w W N CO c? Nt zz Oo ON M cu o z N Cf) CD N C O 00 C co O 0- z -Y- 0-0 (a ? co 0 0 Y O 0.O a_ z ca c Cc$ cc c co -O c O U VJ November 03, 9 993 SCHWEIZER, Oregon Inlet BAR CHANNEL: Schweizer presently working Bar Channel. Users are complaining that Contract Dredge tried to realign present channel and worked primarily outside of the red buoys. RECOMMEND: Beaufort survey channel and notify Coast Guard of need to relocate buoys. NO. 33: The area surrounding No. 33 is in fair shape at the present time. The fall fishing has not fully started, and have a minimum number of transits at this time. RECOMMEND: Extend necessary permits to allow for minimal dredging during the winter to insure channel dimensions are maintained. NO.45: It appears the fishing fleet is having problems in the area of No. 45. Several vessels have radioed the SCHWEIZER and stated the need for dredging in this area. RECOMMEND: Survey area, and determine need for dredging. If SCHWEIZER can be used in this area, pursue necessary permits. eo POTENTIAL DEEP WATER DISPOSAL AREAS FOR DREDGE CURRITUCK r r Y -1000 0 1000 2000 3000 SCALE IN FEET MANTEO (SHALLOWBAG) BAY, DARE COUNTY, NORTH CAROLINA OREGON INLET AND VICINITY U.S. ARMY CORPS OF ENGINEERS WILMINGTON DISTRICT, N.C. 17 JANUARY 1992 FIGURE :,l /r « ? 1 L??O VAjer-JAAA k ?%vvzc?? Loth ----?-roe..?.:_L--?-_S_e.?..?.5_L.-------------------__i'.._oa?r-----a_.? . ??±?.??_-------?-t`!''-?5.__I_- ?73cv --.__v p-?r' -- -- - ------- /_ etc- w--- ?' - -- 395 - _a YO s. -- -i !--r--, --- --- ------ - - -? ??? _ i--; Wig. _ 90 1d2 ( _.. - -- --- /? ???._ _ry ck.?o.-LC<<- - - ---- ??5. - aS G - 7 ?? - Ale --- ?GLrULtnZ 5'e-_lil tS _ 1JC e _ q - 733- zz j 3_ ---->Z? L.l? L: -fir- ? ? i.--_?d ? ?? e. --- -- - W-??mf - -(,?? _ ' .?-? ? t?_-- 3 °t s--- ? °? D ? 1;111!?5 Z O Z n Z J Q Q ?J L W U O LL, V z U ) w b W ~ W Q a ?_ C7 U ?® m I i = o O W J O O w U 0 N N W rc < Z O 0 O F- m d W J H Z m m 0 o a ~ V d a ` A a O O N + ? c co d 7 io Z c N c C ? - E c ?p 1 C W Z 10-??-93 03:17 PM FROM USACOE WD P PO 1/03 FACSIMILE TRANSMITTAL HEADER SHEET Fat un of im ImM we AA P_ 11. the M ?V to ObISCA NAME/ OFFICE TELEPHONE FAX NO. C'00 F OFFICE f NO. (AUTOVONICm m.) SYMBOL. IAurOVON/Camm. ) q yr i I? s ym a l l Josh dorney/ nC/Y1 qI?--733.1338 eric Gq Iamb ?a ler9 CLASM OAT04 PRECEDENCE NO. PAGES OATE•TIME MONTH YEAR RELEASER'S SIGNATURE A udkv Mre Wader) t REMARKS srmcs Aaww For communzadws ca"mr Use only ra ao%nA awt-Ka -it to on nArrwu'tata.A ALn 7219CORMOM *_ 10--16-93 03:17 PM FROM USACOE WD P - 11, October 26, 1993 CESAW-CO-N TO: Federal and State Review Agencies SUBJECT: FY 94 Dredging Coordination Meeting 1. Attached is the draft agenda for the annual Corps- State dredging coordination meeting. The meeting will be held in Wilmington, in the Wilmington Distriot plain Conference Room, on November 4, 1993, from 10:00 until 12:00. 2. Please review the tentative list of topics to be discussed. If you have topios or concerns that you would like to see discussed, let us know by November 2, 1993. 3. If you have any questions or need additional information, contact Daniel Small, Environmental Resources Branch, at (919) 251-4730. 1 c Carmin oinito Chief, vigation Sranoh P02/03 Attachment 10-96-93 0317 PM FROM USACOE WD P P03/03 uRAFT FY 94 MAINTENANCE DREDGING COORDINATION MEETING Time: November 4, 1993 - 10:00 a.m. to 12 noon Place: U.S. Army Corps of Engineers, Wilmington District, 69 Darlington Avenue (main conference room), Wilmington, North Carolina Welcome and Opening Comments: Carmine Forcinito, COE, Preston Pate, NCDCM, and Coleman Long, COE TOPICS TO BE DISCUSSED 1. Review of FY 94 O&M Projects 2. Project/Stud Updates - Morehead City Harbor, inner harbor maintenance/deepening - Sandbagged disposal island construction - Old House Channel, Dare Co. - Update - Island H mitigation, oyster reef construction, Dare County - Manteo (Shallowbag Bay) project, 0&M mitigation, disposal islands BREAK (10 minutes) 3. FY_93_Emergency_Uredging Activities - Cape Fear River (Upper Midnight Channel), New Hanover County - removal of isolated shoal - Oregon Inlet Dredging and Dredged Material Management Plan / ] ^G ?°??( fly /? 5. Other Topics/Open Discussion - SAV impact assessment, Walter Slough Channel - AIWW long-term study - Habitat creation/restoration - Coastal America Program/MOA with NMFS - Cape Fear River colonial nesting waterbird islands, and others - Biological monitoring, beach disposal projects - Report on distribution and movement of Shortnose Sturgeon and other Anadromous Fishes, Lower Cape Fear River, North Carolina - Project modifications after award of dredging contracts Closing Remarks: Carmine Forcinito, COE; Preston Pate, DCM; Coleman Long, COE rn 0 ? ? ? ? ? • • aw an ?w sn sw r O • M . r Ns ,Q; 6 ? o ? E k . t. imp. b Ya , x oil ? ? ? x F I R ? ? t ?? q g R oil ?1 R. l A/ / - _? . s l J ale t "RI LL BII, W = LLI 04. {? Q ,k < 2 LLJ ,x R ry R n I h . 6L. x . x • ?"' O a , r j J; i? # •• ? ? R » ii I 3 ?^ 1 a R•`t N ? R p ? ? II ? ?R t ? g d ? •3 g - + 'C ' : V _ _ rti -260 a r .? \l EhcAosttt't