HomeMy WebLinkAbout20181349 Ver 1_eApproval Letter_SAW-2016-01335_20181220Regulatory Division
DEPARTMENT OF THE ARMY
WILMINGTON DISTRICT, CORPS OF ENGINEERS
69 DARLINGTON AVENUE
WILMINGTON, NORTH CAROLINA 28403-1343
November 30, 2018
Re: NCIRT Review and USACE Approval of the Mill Dam Creek Mitigation Plan; SAW -2016-01335;
NCDMS Project # 97136
Mr. Tim Baumgartner
North Carolina Ecosystem Enhancement Program
1652 Mail Service Center
Raleigh, NC 27699-1652
Dear Mr. Baumgartner:
The purpose of this letter is to provide the North Carolina Division of Mitigation Services
(NCDMS) with all comments generated by the North Carolina Interagency Review Team (NCIRT) during
the 30 -day comment period for the Mill Dam Creek Mitigation Plan, which closed on November 5, 2018.
These comments are attached for your review.
Based on our review of these comments, we have determined that no major concerns have been
identified with the Draft Mitigation Plan, which is considered approved with this correspondence.
However, several minor issues were identified, as described in the attached comment memo, which must
be addressed in the Final Mitigation Plan.
The Final Mitigation Plan is to be submitted with the Preconstruction Notification (PCN)
Application for Nationwide permit approval of the project along with a copy of this letter. Issues identified
above must be addressed in the Final Mitigation Plan. All changes made to the Final Mitigation Plan
should be summarized in an errata sheet included at the beginning of the document. If it is determined
that the project does not require a Department of the Army permit, you must still provide a copy of the
Final Mitigation Plan, along with a copy of this letter, to the appropriate USACE field office at least 30
days in advance of beginning construction of the project. Please note that this approval does not preclude
the inclusion of permit conditions in the permit authorization for the project, particularly if issues
mentioned above are not satisfactorily addressed. Additionally, this letter provides initial approval for the
Mitigation Plan, but this does not guarantee that the project will generate the requested amount of
mitigation credit. As you are aware, unforeseen issues may arise during construction or monitoring of the
project that may require maintenance or reconstruction that may lead to reduced credit.
Thank you for your prompt attention to this matter, and if you have any questions regarding this
letter, the mitigation plan review process, or the requirements of the Mitigation Rule, please call me at
919-554-4884, ext 60.
Sincerely,
BROWNING.KIMBERLY.Digitally signed by
BROWNING.KIMBERLY.DANIELLE.1527683510
DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA,
DANIELLE.1527683510 Date:2018.11N301^243605'00'LLE.1527683510
Kim Browning
Mitigation Specialist
for Henry Wicker
Enclosures
Electronic Copies Furnished:
NCIRT Distribution List
Paul Wiesner — NCDMS
Matthew Reid — NCDMS