HomeMy WebLinkAbout20181608 Ver 1_Construction Drawings_11x17_20181121PIEDMONT CONCORD LAKEPREPARED FORCAROLINA DEVELOPMENT SERVICESCOVER SHEETC0-1
VICINITY MAP
NTS LOCATION MAP
SCALE: 1" = 200'
11/16/2018
PROJECT
AREA
PIEDMONT CONCORD LAKE
MULTI-USE DEVELOPMENT
CONCORD LAKE ROAD KANNAPOILS, NC
KIMLEY-HORN AND ASSOCIATES, INC.
200 N. TRYON STREET
SUITE 200
CHARLOTTE, NORTH CAROLINA 28202
(704) 333-5131 TEL
LICENSE NO. F-0102
CONTACT: ADAM ESSINK, P.E.
SURVEYOR:ENGINEER:
NOTES:
ALL NECESSARY INSPECTIONS AND/OR CERTIFICATIONS REQUIRED BY CODES AND/OR
UTILITY SERVICE COMPANIES SHALL BE PERFORMED PRIOR TO THE FINAL
CONNECTIONS OF SERVICES.
THIS DOCUMENT, TOGETHER WITH THE CONCEPTS AND DESIGNS PRESENTED HEREIN,
AS AN INSTRUMENT OF SERVICE, IS INTENDED ONLY FOR THE SPECIFIC PURPOSE AND
CLIENT FOR WHICH IT WAS PREPARED. REUSE OF AND IMPROPER RELIANCE ON THIS
DOCUMENT WITHOUT WRITTEN AUTHORIZATION AND ADAPTATION BY KIMLEY-HORN
AND ASSOCIATES, INC. SHALL BE WITHOUT LIABILITY TO KIMLEY-HORN AND
ASSOCIATES, INC.
GROUNDWATER NOTE:
THE PRESENCE OF GROUNDWATER SHOULD BE ANTICIPATED ON THIS PROJECT.
CONTRACTOR'S BID SHALL INCLUDE CONSIDERATION FOR ADDRESSING THIS ISSUE.
R.B. PHARR & ASSOCIATES, P.A.
420 HAWTHORNE LANE
CHARLOTTE, NORTH CAROLINA 28204
(704) 376-2186 TEL
CONTACT: JUSTIN CLONINGER, PLS
PROJECT CONTACT LIST:
GEOTECH:
SUMMIT ENGINEERING AND LABORATORY TESTING P.C.
3575 CENTRE CIRCLE DRIVE
FORT MILL, SOUTH CAROLINA 29715
(704) 540-1717 TEL
CONTACT: KERRY C. COOPER, P.E.
CAROLINA DEVELOPMENT SERVICES
2649 BREKONRIDGE ROAD
MONROE, NORTH CAROLINA 28110
(980) 238-1229 TEL
CONTACT: JOHNATHAN MCCALL
OWNER:
85
29
Know what's
R
EROSION CONTROL NOTESGENERAL CONSTRUCTION NOTES
GROUND STABILIZATION
GRADING NOTES:
ALL WORK AND MATERIALS SHALL COMPLY WITH ALL CITY, COUNTY AND STATE REGULATIONS AND
CODES AND O.S.H.A. STANDARDS.
NO WORK WITHIN NCDOT RIGHT OF WAY SHALL TAKE PLACE WITHOUT ALL PERMITS.
EXISTING STRUCTURES WITHIN THE CONSTRUCTION LIMITS ARE TO BE ABANDONED, REMOVED OR
RELOCATED AS NECESSARY. ALL COST SHALL BE INCLUDED IN BASE BID.
CONTRACTOR SHALL BE RESPONSIBLE FOR ALL RELOCATIONS, INCLUDING BUT NOT LIMITED TO, ALL
UTILITIES, STORM DRAINAGE, SIGNS, ETC. AS REQUIRED. ALL WORK SHALL BE IN ACCORDANCE WITH
GOVERNING AUTHORITIES SPECIFICATIONS AND SHALL BE APPROVED BY SUCH. ALL COST SHALL BE
INCLUDED IN BASE BID. AREAS TO BE DISTURBED SHALL BE IMPROVED PER THE CIVIL PLANS OR
RESTORED TO THEIR ORIGINAL OR BETTER CONDITION. CONTRACTOR SHALL REPAIR ANY EXISTING
FEATURES THAT ARE DAMAGED DURING CONSTRUCTION TO THE EXISTING OR BETTER CONDITION.
SITE BOUNDARY, TOPOGRAPHY, UTILITY AND ROAD INFORMATION TAKEN FROM SIGNED ALTA/NSPS
SURVEY PERFORMED BY R.B. PHARR & ASSOCIATES, P.A. ON JANUARY 30, 2007. ALL INFORMATION IS
TO BE FIELD VERIFIED BY THE CONTRACTOR PRIOR TO CONSTRUCTION.
THE CONTRACTOR SHALL EMPLOY ALL NECESSARY BARRICADES, SIGNS, FENCES, FLASHING LIGHTS,
TRAFFIC MEN, ETC. FOR MAINTENANCE AND PROTECTION OF TRAFFIC AS REQUIRED BY THE NORTH
CAROLINA DEPT. OF TRANSPORTATION (NCDOT).
THE CONTRACTOR SHALL PROTECT ALL MONUMENTS, IRON PINS, AND PROPERTY CORNERS DURING
CONSTRUCTION.
APPROVAL OF THIS PLAN IS NOT AN AUTHORIZATION TO GRADE ADJACENT PROPERTIES. ANY
GRADING BEYOND THE LIMITS OF CONSTRUCTION AS SHOWN ON THE GRADING AND DRAINAGE PLAN
WITHOUT AUTHORIZATION IS SUBJECT TO A FINE. WHEN FIELD CONDITIONS WARRANT OFF-SITE
GRADING, PERMISSION MUST BE OBTAINED FROM THE AFFECTED PROPERTY OWNERS AND CITY OF
KANNAPOILS.
CONTRACTOR AGREES TO REPAIR ANY DAMAGE TO THE PUBLIC RIGHT-OF-WAY IN ACCORDANCE
WITH THE STANDARDS OF THE NCDOT AND CITY OF KANNAPOLIS.
THE CONTRACTOR SHALL IMMEDIATELY REPORT TO THE OWNER ANY DISCREPANCIES FOUND
BETWEEN THE ACTUAL FIELD CONDITIONS AND THE CONSTRUCTION DOCUMENTS AND SHALL WAIT
FOR INSTRUCTION PRIOR TO PROCEEDING.
THE CONTRACTOR SHALL MAINTAIN EACH STREAM, CREEK, OR BACKWASH CHANNEL IN A
UNOBSTRUCTED STATE AND SHALL REMOVE FROM THE CHANNEL AND BANKS OF THE STREAM ALL
DEBRIS, LOGS, TIMBER, JUNK AND OTHER ACCUMULATIONS.
CONTRACTOR SHALL ADJUST AND/OR CUT EXISTING PAVEMENT AS NECESSARY TO ASSURE A
SMOOTH FIT AND CONTINUOUS GRADE.
CONTRACTOR SHALL POST ASSIGNED BUILDING PERMIT NUMBER AND ADDRESS ON BUILDING.
IN ROLLING OR HILLY TERRAINS, SWEEPING OF THE STONE BASE AND/OR APPLICATION OF A TACK
COAT MAY BE REQUIRED NEAR INTERSECTIONS. THESE REQUIREMENTS WILL BE ESTABLISHED BY
THE INSPECTOR AND BASED ON FIELD CONDITIONS.
CONTACT THE UTILITY COMPANY TO RELOCATE ANY EXISTING UTILITY AND/OR LIGHT POLES. ALL
EXISTING FACILITIES WHICH CONFLICT WITH THE IMPROVEMENTS UNDER THE SCOPE OF THIS
PROJECT MUST BE RELOCATED AT THE EXPENSE OF THE CONTRACTOR.
THE CONTRACTOR MUST CALL THE APPROPRIATE UTILITY COMPANIES AT LEAST (3) THREE WORKING
DAYS BEFORE ANY EXCAVATION TO REQUEST EXACT FIELD LOCATION OF UTILITIES. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO RELOCATE ALL EXISTING UTILITIES WHICH CONFLICT WITH
THE PROPOSED IMPROVEMENTS SHOWN ON THE PLANS.
THE CONTRACTOR SHALL COORDINATE WITH THE GEOTECHNICAL ENGINEER FOR APPROPRIATE
SLOPE STABILIZATION ON ALL SLOPES STEEPER THAN 3:1.
THE CONTRACTOR SHALL OBTAIN ALL PERMITS REQUIRED FOR BLASTING ROCK IF BLAST ROCK IS
ENCOUNTERED. CONTRACTOR SHALL BE SOLEY RESPONSIBLE FOR COMPLYING WITH ALL BLASTING
AND SAFETY REQUIREMENTS
ALL CUT OR FILL SLOPES SHALL BE 2:1 OR FLATTER UNLESS OTHERWISE NOTED.
CONSTRUCTION SHALL COMPLY WITH ALL APPLICABLE GOVERNING CODES AND BE CONSTRUCTED
TO SAME.
ALL PROPOSED CONTOURS AND SPOT ELEVATIONS REFLECT FINISHED GRADES.
THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING AND PROTECTING EXISTING UTILITIES,
AND SHALL REPAIR ALL DAMAGE TO EXISTING UTILITIES THAT OCCUR DURING CONSTRUCTION.
CONTRACTOR SHALL BLEND NEW EARTHWORK SMOOTHLY TO TRANSITION BACK TO EXISTING GRADE.
LIMITS OF CLEARING SHOWN ON GRADING AND DRAINAGE PLAN ARE BASED UPON THE APPROXIMATE
CUT AND FILL SLOPE LIMITS, OR OTHER GRADING REQUIREMENTS.
THE CONTRACTOR IS RESPONSIBLE FOR THE DESIGN AND IMPLEMENTATION OF ALL SHEETING,
SHORING, BRACING AND SPECIAL EXCAVATION MEASURES REQUIRED TO MEET OSHA, FEDERAL,
STATE AND LOCAL REGULATIONS PURSUANT TO THE INSTALLATION OF THE WORK INDICATED ON
THESE DRAWINGS. THE DESIGN ENGINEER ACCEPTS NO RESPONSIBILITY FOR THE DESIGN(S) TO
INSTALL SAID ITEMS.
THE CONTRACTOR SHALL INCLUDE IN THE CONTRACT PRICE ANY DEWATERING AND MOISTURE
CONDITIONING NECESSARY TO CONSTRUCT THE PROJECT AS SHOWN ON THE PLANS.
GRADES, ELEVATIONS AND LOCATIONS SHOWN ARE APPROXIMATE. AS DIRECTED BY THE ENGINEER,
THEY MAY BE ADJUSTED TO ACCOMMODATE UNFORESEEN CONDITIONS. STATIONS, OFFSETS AND
ELEVATIONS REFER TO THE CENTER OF DROP INLETS, MANHOLES AND JUNCTION BOXES, AND THE
MIDPOINT OF THE LIP FOR CATCH BASINS.
ANY CONSTRUCTION OR USE WITHIN THE AREAS DELINEATED AS FLOODWAY DISTRICT FRINGE
BOUNDARY LINE OR FLOODWAY DISTRICT ENCROACHMENT BOUNDARY LINE IS SUBJECT TO THE
RESTRICTIONS IMPOSED BY THE FLOODWAY REGULATIONS OF MECKLENBURG COUNTY.
1) SOIL STABILIZATION SHALL BE ACHIEVED ON ANY AREA OF A SITE WHERE LAND-DISTURBING
ACTIVITIES HAVE TEMPORARILY OR PERMANENTLY CEASED ACCORDING TO THE FOLLOWING
SCHEDULE:
i) ALL PERIMETER DIKES, SWALES, DITCHES, PERIMETER SLOPES AND ALL SLOPES STEEPER THAN
3 HORIZONTAL TO 1 VERTICAL (3:1) SHALL BE PROVIDED TEMPORARY OR PERMANENT
STABILIZATION WITH GROUND COVER AS SOON AS PRACTICABLE BUT IN ANY EVENT WITHIN 7
CALENDAR DAYS FROM THE LAST LAND-DISTURBING ACTIVITY.
ii) ALL OTHER DISTURBED AREAS SHALL BE PROVIDED TEMPORARY OR PERMANENT STABILIZATION
WITH GROUND COVER AS SOON AS PRACTICABLE BUT IN ANY EVENT WITHIN 14 CALENDAR DAYS
FROM THE LAST LAND-DISTURBING ACTIVITY.
2) CONDITIONS - IN MEETING THE STABILIZATION REQUIREMENTS ABOVE, THE FOLLOWING
CONDITIONS OR EXEMPTIONS SHALL APPLY:
i) EXTENSIONS OF TIME MAY BE APPROVED BY THE PERMITTING AUTHORITY BASED ON WEATHER
OR OTHER SITE-SPECIFIC CONDITIONS THAT MAKE COMPLIANCE IMPRACTICABLE.
ii) ALL SLOPES 50' IN LENGTH OR GREATER SHALL APPLY THE GROUND COVER WITHIN 7 DAYS
EXCEPT WHEN THE SLOPE IS FLATTER THAN 4:1. SLOPES LESS THAN 50' SHALL APPLY
GROUNDCOVER WITHIN 14 DAYS EXCEPT WHEN SLOPES ARE STEEPER THAN 3:1, THE 7
DAY-REQUIREMENT APPLIES.
iii) ANY SLOPED AREA FLATTER THAN 4:1 SHALL BE EXEMPT FROM THE 7-DAY GROUND COVER
REQUIREMENT.
iv) ALTHOUGH STABILIZATION IS USUALLY SPECIFIED AS GROUND COVER, OTHER METHODS, SUCH
AS CHEMICAL STABILIZATION, MAY BE ALLOWED ON A CASE-BY-CASE BASIS.
v) FOR PORTIONS OF PROJECTS WITHIN THE SEDIMENT CONTROL COMMISSION-DEFINED "HIGH
QUALITY WATER ZONE" (I5A NCAC 04A. 0105) , STABILIZATION WITH GROUND COVER SHALL BE
ACHIEVED AS SOON AS PRACTICABLE BUT IN ANY EVENT ON ALL AREAS OF THE SITE WITHIN 7
CALENDAR DAYS FROM THE LAST LAND DISTURBING ACT.
vi) PORTIONS OF A SITE THAT ARE LOWER IN ELEVATION THAN ADJACENT DISCHARGE LOCATIONS
AND ARE NOT EXPECTED TO DISCHARGE DURING CONSTRUCTION MAY BE EXEMPT FROM THE
TEMPORARY GROUND COVER REQUIREMENTS IF IDENTIFIED ON THE APPROVED E&SC PLAN OR
ADDED BY THE PERMITTING AUTHORITY.
3) ALL DIVERSION DITCHES SHALL BE PERMANENTLY MATTED WITH NAG SC-150 OR APPROVED EQUAL.
TOTAL AREA DISTURBED = 41 ACRES
LIMITS OF GRADING SHOWN ON THE PLAN ARE MAXIMUM LIMITS FOR EROSION CONTROL PURPOSES
ONLY. SURVEYOR TO DETERMINE ACTUAL LIMIT.
CONTRACTOR SHALL COORDINATE ALL WORK WITH NCDEQ.
ON-SITE BURIAL PITS REQUIRE AN ON-SITE DEMOLITION LANDFILL PERMIT FROM THE ZONING
ADMINISTRATOR.
ANY GRADING BEYOND THE DENUDED LIMITS SHOWN ON THE PLAN IS A VIOLATION OF NCDEQ AND IS
SUBJECT TO A FINE.
GRADING MORE THAN ONE ACRE WITHOUT AN APPROVED EROSION CONTROL PLAN IS A VIOLATION
OF NCDEQ AND IS SUBJECT TO A FINE.
ALL PERIMETER DIKES, SWALES, PERIMETER SLOPES, AND ALL SLOPES GREATER STEEPER THAN 3
HORIZONTAL TO 1 VERTICAL (3:1) SHALL BE PROVIDED TEMPORARY OR PERMANENT STABILIZATION
WITH GROUND COVER AS SOON AS PRACTICABLE BUT IN ANY EVENT WITHIN 7 CALENDAR DAYS FROM
THE LAST LAND DISTURBING ACTIVITY. ALL OTHER DISTURBED AREAS SHALL BE PROVIDED
TEMPORARY OR PERMANENT STABILIZATION WITH GROUND COVER AS SOON AS PRACTICABLE BUT IN
ANY EVENT WITHIN 14 CALENDAR DAYS FROM THE LAST LAND-DISTURBING ACTIVITY.
ADDITIONAL MEASURES TO CONTROL EROSION AND SEDIMENT MAY BE REQUIRED BY A
REPRESENTATIVE OF NCDEQ.
SLOPES SHALL BE GRADED NO STEEPER THAN 2:1.
A GRADING PLAN MUST BE SUBMITTED FOR ANY GRADING THAT WAS NOT PREVIOUSLY APPROVED.
DEVIATION FROM THESE PLANS AND NOTES WITHOUT THE PRIOR CONSENT OF THE OWNER, HIS
REPRESENTATIVE, OR THE ENGINEER MAY BE CAUSE FOR THE WORK TO BE UNACCEPTABLE.
EROSION CONTROL MEASURES SHALL BE INSTALLED PRIOR TO CONSTRUCTION IN ACCORDANCE
WITH THE REQUIREMENTS OF THE NORTH CAROLINA SEDIMENTATION POLLUTION CONTROL ACT OF
1973, THE LOCAL JURISDICTIONAL AGENCY, THE APPROVED EROSION CONTROL PERMIT, AND THESE
PLANS AND SPECIFICATIONS.
SUFFICIENT EROSION CONTROL PRACTICES MUST BE INSTALLED AND MAINTAINED TO RETAIN
SEDIMENT WITHIN THE BOUNDARIES OF THE SITE AS SOON AS PRACTICABLE BUT IN ANY EVENT
WITHIN 7 CALENDAR DAYS FROM THE LAST LAND DISTURBING ACTIVITY. ALL OTHER DISTURBED
AREAS SHALL BE PROVIDED TEMPORARY OR PERMANENT STABILIZATION WITH GROUND COVER AS
SOON AS PRACTICABLE BUT IN ANY EVENT WITHIN 14 CALENDAR DAYS FROM THE LAST
LAND-DISTURBING ACTIVITY.
THE SEDIMENT BASINS AND DIVERSION DITCHES SHALL BE CLEANED OUT WHEN THE STORAGE
CAPACITY HAS BEEN APPROXIMATELY 50% FILLED. GRAVEL SHALL BE CLEANED OR REPLACED WHEN
THE SEDIMENT POOL NO LONGER DRAINS PROPERLY.
ALL EROSION AND SEDIMENT CONTROL PRACTICES SHALL BE INSPECTED BY A CERTIFIED INSPECTOR
TWICE A WEEK AND AFTER EVERY 0.5 INCH RAINFALL EVENT, BUT IN NO CASE LESS THAN TWICE
EVERY WEEK. NEEDED REPAIRS SHALL BE INITIATED WITHIN 24 HOURS OF INSPECTION. SUBMIT
WRITTEN REPORT WITH EACH INSPECTION TO THE OWNER.
SEDIMENT WILL BE REMOVED FROM BEHIND THE SILT FENCING WHEN IT BECOMES 6-INCHES DEEP AT
THE FENCE. THE FENCING WILL BE REPAIRED AS NECESSARY TO MAINTAIN SUFFICIENT BARRIER.
ALL SEEDED AREAS WILL BE FERTILIZED, RESEEDED AS NECESSARY, AND MULCHED ACCORDING TO
THE PLANS AND SPECIFICATIONS TO MAINTAIN A VIGOROUS, DENSE VEGETATIVE COVER.
ALL DRAINAGE SWALES MUST BE GRASSED AND RIP-RAP MUST BE REPLACED AS REQUIRED TO
CONTROL EROSION. RIP-RAP WILL CONSIST OF 50 TO 125 POUND STONES PLACED AT ALL
HEADWALLS, AND WHERE NOTED ON CONSTRUCTION DRAWINGS. (SEE DETAIL SHEET FOR OUTFALL
PIPE SIZE CHART)
ADDITIONAL EROSION CONTROL MEASURES OR SILT BARRIERS TO BE PLACED AS DIRECTED BY THE
LOCAL JURISDICTIONAL INSPECTOR.
WHEN ANY CONSTRUCTION BORDERS A DRAINAGE COURSE:
A. THE CONTRACTOR IS RESPONSIBLE FOR REMOVING ANY BUILDING OR OTHER
EXCAVATION SPOIL DIRT, CONSTRUCTION TRASH OR DEBRIS, ETC., FROM THE
DRAINAGE AREA SHOWN HEREON IN A EXPEDITIOUS MANNER AS
CONSTRUCTION PROGRESSES.
B. THE CONTRACTOR HEREBY AGREES TO STOP ALL WORK AND RESTORE THESE
IMMEDIATELY UPON NOTIFICATION BY THE LOCAL JURISDICTIONAL INSPECTOR
AND/OR THE OWNER.
FOR ALL CONSTRUCTION ALONG AND/OR ACROSS WATERWAYS, BANK PROTECTION AND
STABILIZATION SHALL BE REQUIRED AS PER LOCAL JURISDICTIONAL EROSION CONTROL LAWS.
ALL TREE PROTECTION AND EROSION CONTROL MEASURES SHALL BE IN PLACE PRIOR TO
COMMENCING CONSTRUCTION AND SHALL BE MAINTAINED IN PROPER WORKING ORDER UNTIL ALL
DISTURBED AREAS ARE STABILIZED AND GROUND COVER IS ESTABLISHED. CONSTRUCTION
ENTRANCE PADS SHALL BE INSTALLED BY THE CONTRACTOR AT CONSTRUCTION ACCESS POINTS
PRIOR TO LAND DISTURBANCE.
THE CONTRACTOR SHALL KEEP A COPY OF THE APPROVED LAND DISTURBANCE PLAN AND PERMIT ON
SITE WHENEVER LAND DISTURBING ACTIVITY IS IN PROGRESS.
INSTALL SILT FENCE ALONG THE DOWNSTREAM SIDE OF ALL PROPOSED CUT AND FILL
CONSTRUCTION AND AS INDICATED ON PLANS.
A TEMPORARY DIVERSION SWALE MAY BE USED IN LIEU OF SILT FENCE WHERE RUNOFF CAN BE
DIRECTED TO A TEMPORARY SEDIMENT BASIN.
IT IS THE CONTRACTOR'S RESPONSIBILITY TO PERFORM REQUIRED MAINTENANCE OF ALL EROSION
AND SEDIMENT CONTROL DEVICES TO ENSURE THEIR FUNCTION AT ALL TIMES.
CONTRACTOR SHALL MAINTAIN ALL EROSION CONTROL MEASURES UNTIL PERMANENT VEGETATION
HAS BEEN ESTABLISHED.
WHERE SEDIMENT IS TRANSPORTED ONTO A PAVED OR PUBLIC ROAD SURFACE, THE ROAD SURFACE
SHALL BE CLEANED THOROUGHLY AT THE END OF EACH DAY. SEDIMENT SHALL BE REMOVED FROM
THE ROADS BY SHOVELING OR SWEEPING AND TRANSPORTED TO A SEDIMENT CONTROL DISPOSAL
AREA. STREET WASHING SHALL BE ALLOWED ONLY AFTER SEDIMENT IS REMOVED IN THIS MANNER.
WHEN A CRUSHED STONE CONSTRUCTION ENTRANCE HAS BEEN COVERED WITH SOIL OR OR HAS
BEEN PUSHED INTO THE SOIL BY CONSTRUCTION TRAFFIC, IT SHALL BE REPLACED WITH A DEPTH OF
STONE EQUAL TO THAT OF THE ORIGINAL APPLICATION.
CONTRACTOR TO PROTECT THE EXISTING EXPOSED SANITARY SEWER MANHOLES AT ALL TIMES
DURING THE CONSTRUCTION.
PERFORM A FINAL DEMUCKING OF ALL SEDIMENT CONTROL DEVICES BEFORE DEMOBILIZATION.
BE ADVISED DIRECTLY PUMPING OUT A SEDIMENT BASIN IS CONSIDERED BYPASSING A STORMWATER
CONTROL FACILITY IN VIOLATION OF SECTION IV (3) OF NPDES PERMIT NCG0100000 STORMWATER
DISCHARGE PERMIT FOR CONSTRUCTION ACTIVITIES. IF ANY DRAINING OCCURS OF THE SEDIMENT
BASIN, SUCH AS FOR MAINTENANCE OF THE BASIN OR CONVERSION TO THE POST-CONSTRUCTION
STORMWATER MEASURE, THE DRAINAGE MUST OCCUR THROUGH A SILT BAG AND DISCHARGED IN A
NON EROSIVE MANNER. [15A NCAC 4B 0105]
ADDITIONAL SEDIMENT AND EROSION CONTROL NOTES:
1. SILT FENCE SHALL BE MAINTAINED AROUND THE PERIMETER OF ALL EARTHWORK AREAS TO
PREVENT SEDIMENT TRANSPORT ONTO ADJACENT PROPERTIES OR OFFSITE ROADWAYS, AS
APPLICABLE.
2.SILT FENCE FILTER BARRIERS SHALL BE INSTALLED AND MAINTAINED UNTIL CONSTRUCTION IS
COMPLETE AND LANDSCAPING IS INSTALLED.
3.THE CONTRACTOR SHALL IMMEDIATELY CLEANUP AND REPAIR ALL EROSION DAMAGE AFTER
DISCOVERY AND REINSTALL ADEQUATE CONTROL MEASURES AS NECESSARY TO PREVENT
REOCCURRENCE OF DAMAGE.
4. CONSTRUCTION POINT OF ACCESS TO LIMIT DEPOSITS OF EARTH AND OTHER HAULED
MATERIALS ONTO THE ADJACENT LOT. THE CONTRACTOR SHALL ROUTINELY CLEAN ALL
SEDIMENT DEPOSITS AND DEBRIS FROM ROADWAY AS THEY OCCUR.
SEEDING SCHEDULE AND SEEDBED PREPARATION
SEEDING SCHEDULE
1.SEED, MULCH, AND FERTILIZE AS SHOWN ON THE PHASED EROSION CONTROL PLANS.
2.PROTECTIVE COVER MUST BE ESTABLISHED ON ALL DISTURBED AREAS, GRADED SLOPES AND
FILLS.
SEEDBED PREPARATION
1. GRADED SLOPES AND FILL - THE ANGLE FOR GRADED SLOPES AND FILLS SHALL BE NO GREATER
THAN THE ANGLE WHICH CAN BE RETAINED BY VEGETATIVE COVER OR OTHER ADEQUATE
EROSION CONTROL DEVICES OR STRUCTURES.
2.SURFACE WATER CONTROL MEASURES TO BE INSTALLED ACCORDING TO THE PLANS.
3.AREAS TO BE SEEDED SHALL BE RIPPED AND SPREAD WITH AVAILABLE TOPSOIL 3" DEEP. TOTAL
SEEDBED PREPARED DEPTH SHALL BE 4" TO 8" DEEP.
4.LOOSE ROCKS, ROOTS, AND OTHER OBSTRUCTIONS SHALL BE REMOVED FROM THE SURFACE SO
THAT THEY WILL NOT INTERFERE WITH ESTABLISHMENT AND MAINTENANCE OF VEGETATION.
SURFACE FOR FINAL SEEDBED PREPARATION, AT FINISH GRADES SHOWN, SHALL BE
REASONABLY SMOOTH AND UNIFORM.
5.IF NO SOIL TEST IS TAKEN, FERTILIZER AND LIME SHALL BE ACCORDING TO SEEDING
SPECIFICATIONS.
6.IF SOIL TEST IS TAKEN, PROVIDE LIME AND FERTILIZER ACCORDING TO THE SOIL TEST REPORT.
7.LIME AND FERTILIZER SHALL BE APPLIED UNIFORMLY AND MIXED WITH THE SOIL DURING
SEEDBED PREPARATION.
RIP RAP
CONSTRUCTION SPECIFICATIONS
1. SUBGRADE PREPARATION - PREPARE THE SUBGRADE FOR RIP RAP AND FILTER TO THE
REQUIRED LINES AND GRADES SHOWN ON THE PLANS. COMPACT ANY FILL REQUIRED IN THE
SUBGRADE TO A DENSITY APPROXIMATING THAT OF THE SURROUNDING UNDISTURBED MATERIAL
OR OVERFILL DEPRESSIONS WITH RIPRAP. REMOVE BRUSH, TREES, STUMPS AND OTHER
OBJECTIONABLE MATERIAL. CUT THE SUBGRADE SUFFICIENTLY DEEP THAT THE FINISHED GRADE
OF THE RIPRAP WILL BE AT THE ELEVATION OF THE SURROUNDING AREA. CHANNELS SHOULD BE
EXCAVATED SUFFICIENTLY TO ALLOW PLACEMENT OF THE RIPRAP IN A MANNER SUCH THAT THE
FINISHED INSIDE DIMENSIONS AND GRADE OF THE RIPRAP MEET DESIGN SPECIFICATIONS.
2. SAND AND GRAVEL FILTER BLANKET - PLACE THE FILTER BLANKET IMMEDIATELY AFTER THE
GROUND FOUNDATION IS PREPARED. FOR GRAVEL, SPREAD FILTER STONE IN A UNIFORM LAYER
TO THE SPECIFIED DEPTH. WHERE MORE THAN ONE LAYER OF FILTER MATERIAL IS USED,
SPREAD THE LAYERS WITH MINIMAL MIXING.
3.SYNTHETIC FILTER FABRIC - PLACE THE CLOTH FILTER DIRECTLY ON THE PREPARED
FOUNDATION. OVERLAP THE EDGES BY AT LEAST 12 INCHES, AND SPACE ANCHOR PINS EVERY 3
FT ALONG THE OVERLAP. BURY THE UPSTREAM END OF THE CLOTH A MINIMUM OF 12 INCHES
BELOW GROUND AND WHERE NECESSARY, BURY THE LOWER END OF THE CLOTH OR OVERLAP
WITH THE NEXT SECTION AS REQUIRED. TAKE CARE NOT TO DAMAGE THE CLOTH WHEN PLACING
RIPRAP. IF DAMAGE OCCURS REMOVE THE RIPRAP AND REPAIR THE SHEET BY ADDING ANOTHER
LAYER OF FILTER MATERIALS WITH A MINIMUM OVERLAP OF 12 INCHES AROUND THE DAMAGE
AREA. IF EXTENSIVE DAMAGE IS SUSPECTED, REMOVE AND REPLACE THE ENTIRE SHEET.
4.WHERE LARGE STONES ARE USED OR MACHINE PLACEMENT IS DIFFICULT, A 4-INCH LAYER OF
FINE GRAVEL OR SAND MAY BE NEEDED TO PROTECT THE FILTER CLOTH.
5. STONE PLACEMENT - PLACEMENT OF RIPRAP SHOULD FOLLOW IMMEDIATELY AFTER PLACEMENT
OF THE FILTER. PLACE RIPRAP SO THAT IT FORMS A DENSE, WELL-GRADED MASS OF STONE
WITH A MINIMUM OF VOIDS. THE DESIGNED DISTRIBUTION OF STONES THROUGHOUT THE MASS
MAY BE OBTAINED BY SELECTIVE LOADING AT THE QUARRY AND CONTROLLED DUMPING DURING
FINAL PLACEMENT. PLACE RIPRAP TO ITS FULL THICKNESS IN ONE OPERATION. DO NOT PLACE
RIPRAP BY DUMPING THE THROUGH CHUTES OR OTHER METHODS THAT CAUSE SEGREGATION
OF STONE SIZES. TAKE CARE NOT TO DISLODGE THE UNDERLYING BASE OR FILTER WHEN
PLACING THE STONES.
6. THE FINISHED SLOPE SHOULD BE FREE OF POCKETS OF SMALL STONE OR CLUSTERS OF LARGE
STONES. HAND PLACING MAY BE NECESSARY TO ACHIEVE THE PROPER DISTRIBUTION OF STONE
SIZES TO PRODUCE A RELATIVELY SMOOTH, UNIFORM SURFACE. THE FINISHED GRADE OF
RIPRAP SHOULD BLEND WITH THE SURROUNDING AREA. NO OVERFALL OR PROTRUSION OF
RIPRAP SHOULD BE APPARENT.
7. INSPECT CHANNELS AT REGULAR INTERVALS AS WELL AS AFTER MAJOR RAINS, AND MAKE
REPAIRS PROMPTLY. GIVE SPECIAL ATTENTION TO THE OUTLET AND INLET SECTIONS AND
OTHER POINTS WHERE CONCENTRATED FLOW ENTERS. CAREFULLY CHECK STABILITY AT ROAD
CROSSINGS AND LOOK FOR INDICATIONS OF PIPING, SCOUR HOLES, OR BANK FAILURES. MAKE
REPAIRS IMMEDIATELY. MAINTAIN ALL VEGETATION ADJACENT TO THE CHANNEL IN A HEALTHY
VIGOROUS CONDITION TO PROTECT THE AREA FROM EROSION AND SCOUR DURING OUT-OF-BAN
FLOW. CONTROL OF WEED AND BRUSH GROWTH MAY BE NEEDED IN SOME LOCATIONS
MAINTENANCE PLAN
1.THE CONTRACTOR IS RESPONSIBLE FOR MAINTENANCE OF EROSION AND SEDIMENT CONTROL
DEVICES.
2. THE CONTRACTOR SHALL CHECK ALL EROSION AND SEDIMENT CONTROL PRACTICES FOR
STABILITY AND OPERATION FOLLOWING EVERY RUNOFF PRODUCING RAINFALL BUT IN NO CASE
LESS THAN ONCE E VERY WEEK. ANY NEEDED REPAIRS WILL BE MADE IMMEDIATELY BY THE
CONTRACTOR TO MAINTAIN ALL PRACTICES AS DESIGNED. ALSO PER NATIONAL POLLUTANT
DISCHARGE ELIMINATION SYSTEM (NPDES) GENERAL STORMWATER PERMIT, A RAIN GAUGE MUST
BE INSTALLED ON SITE. THE RAIN GAUGE MUST BE KEPT ONSITE AND INSPECTIONS BY THE
CONTRACTOR MUST BE MADE AND LOGGED AFTER EVERY HALF INCH OF RAINFALL AND ONCE A
WEEK.
3. THE CONTRACTOR SHALL REMOVE SEDIMENT FROM SEDIMENT BASIN WHEN STORAGE CAPACITY
HAS BEEN APPROXIMATELY 50% FILLED. GRAVEL WILL BE CLEANED OR REPLACED WHEN THE
SEDIMENT POOL NO LONGER DRAINS PROPERLY.
4.THE CONTRACTOR SHALL REMOVE SEDIMENT FROM BEHIND SLIT FENCE WHEN IT BECOMES 0.5
FEET DEEP AT THE FENCE. SLIT FENCE WILL BE REPAIRED AS NECESSARY TO MAINTAIN A
BARRIER.
5.THE CONTRACTOR SHALL FERTILIZE, RESEED AS NECESSARY, AND MULCH ALL SEEDED AREAS
ACCORDING TO SPECIFICATIONS IN THE VEGETATIVE PLAN TO MAINTAIN A VIGOROUS, DENSE
VEGETATIVE COVER.
.
UTILITY NOTES
1.THE CONTRACTOR IS RESPONSIBLE FOR HORIZONTALLY AND VERTICALLY LOCATING AND
PROTECTING ALL PUBLIC OR PRIVATE UTILITIES (SHOWN OR NOT SHOWN) WHICH LIE IN OR
ADJACENT TO THE CONSTRUCTION SITE. AT LEAST (3) WORKING DAYS PRIOR TO ANY
DEMOLITION, GRADING, OR CONSTRUCTION ACTIVITY, THE CONTRACTOR SHALL NOTIFY THE
NORTH CAROLINA ONE-CALL UTILITIES LOCATION SERVICE (ULOCO) AT (800)632-4949 FOR
PROPER IDENTIFICATION OF EXISTING UTILITIES WITHIN THE SITE.
2.SHOULD ANY UNCHARTED OR INCORRECTLY CHARTED UTILITIES BE ENCOUNTERED, THE
CONTRACTOR SHALL CONTACT THE OWNER IMMEDIATELY FOR DIRECTIONS.
3.CONTRACTOR SHALL COORDINATE ANY INTERRUPTION OF UTILITY SERVICE WITH OWNER AND
RESPECTIVE UTILITY COMPANY REPRESENTATIVE.
4. ANY PLANNED INTERRUPTION OF UTILITY SERVICE SHALL BE GIVEN A 48 HOUR NOTICE TO THE
UTILITY COMPANY AND THE OWNER.
5.CONTRACTOR SHALL SAW CUT, REMOVE, AND REPLACE ASPHALT PAVEMENT AS NECESSARY TO
INSTALL UNDERGROUND ELECTRIC,TELEPHONE, SEWER, WATER, AND COMMUNICATION
CONDUITS.
6.ALL ELECTRICAL WORK SHALL BE DONE IN ACCORDANCE WITH LOCAL POWER COMPANY
STANDARDS.
INSPECTION NOTES
EFFECTIVE OCTOBER 1, 2010, PERSONS RESPONSIBLE FOR LAND DISTURBING ACTIVITIES MUST
INSPECT THE SEDIMENT AND EROSION CONTROL MEASURES ON A PROJECT AFTER EACH PHASE
OF THE PROJECT TO MAKE SURE THAT THE APPROVED EROSION AND SEDIMENTATION CONTROL
PLAN IS BEING FOLLOWED. SELF-INSPECTION REPORTS ARE REQUIRED. A SAMPLE
SELF-INSPECTION REPORT, AS WELL AS DETAILS OF THE SELF-INSPECTION PROGRAM, CAN BE
FOUND ON THE LAND QUALITY WEBSITE:
http://deq.nc.gov/about/divisions/energy-mineral-land-resources/erosion-sediment-control/forms
AS A MINIMUM, THE INSPECTIONS SHALL BE PERFORMED AFTER EACH OF THE FOLLOWING
PHASES OF A PLAN:
1.INSTALLATION OF PERIMETER EROSION AND SEDIMENT CONTROL MEASURES.
2.INSTALLATION OF SEDIMENT TRAPS/BASINS.
3. CLEARING AND GRUBBING OF EXISTING GROUND COVER.
4. COMPLETION OF ANY PHASE OF GRADING THAT REQUIRES PROVISION OF STABILIZATION.
5. INSTALLATION OF MEASURES DURING ANY PHASE OF THE PROJECT.
6. COMPLETION OF CONSTRUCTION OR DEVELOPMENT.
7. INSTALLATION OF STORMWATER RETENTION MEASURES.
8.QUARTERLY UNTIL THE ESTABLISHMENT OF PERMANENT GROUND COVER IS FULLY
ESTABLISHED.
HYDROSEED MULCH WITH PAM APPLICATION GUIDELINES
ALL HYDROSEEDING SPECIFIED FOR THIS SITE SHALL INCLUDE PAM ADDITIVE MEETING THE
REQUIREMENTS OF THESE PLANS AND GUIDELINES BELOW. HYDROSEEDING SHALL BE INSTALLED
AS THE FIRST MEASURE OF SLOPE STABILIZATION WITH EROSION CONTROL MATTING BEING
PLACED OVER THE APPLICATION.
1.MANUFACTURER RECOMMENDED APPLICATION RATE (PER ACRE COVERAGE): SITE
APPLICATION RATES VARY BY SOIL CONTENT AND GRADE OF SLOPE AND SHALL BE VERIFIED
BY SITE SPECIFIC SOIL TESTING AS OUTLINED IN THE FLOCCULANT/POLYACRYLAMIDE (PAM)
APPLICATION NOTES.
a. GENTLE TO MODERATE SLOPES (0 TO 4H:1V)
i.HIGH CLAY CONTENT: 10-20 # POWDER OR 1.0-2.0 GALLONS EMULSION
ii. HIGH SAND CONTENT: 25-50 # POWDER OR 2.0-3.0 GALLONS EMULSION
b.STEEP SLOPES (3H:1V TO 1H:1V)
i. HIGH CLAY CONTENT: 20-35 # POWDER OR 1.0-2.5 GALLONS EMULSION
ii.HIGH SAND CONTENT: 40-50 # POWDER OR 2.5-3.0 GALLONS EMULSION
2. ADD PAM EMULSION OR POWDER TO ALL HYDROSEEDING MIXES AT THE ABOVE
APPLICATION RATES OF NO MORE THAN 30 POUNDS OF POWDER AND NOR MORE THAN 2.5
GALLONS PER 3000 GALLONS OF WATER, AND THEN APPLIED AT THE RATE OF 3000 GALLONS
OF HYDROSEED MIX/ ACRE (NOTE: POLYMER ADDITIONS ARE LIMITED BY EXTREMELY HIGH
VISCOSITY, DO NOT EXCEED THE RECOMMENDED DOSAGE RATES.) SITE TESTING SHALL
DETERMINE THE CORRECT POLYMER TYPE.
3.PAM SHALL BE ADDED SLOWLY AS THE FINAL ADDITIVE TO THE HYDROSEEDING MIX TO HELP
AVOID POLYMER CLUMPING THAT COULD RESULT IN CLOGGING OF THE SPRAYING
EQUIPMENT.
4.THE HYDROSEED MIX SHALL BE APPLIED IMMEDIATELY AFTER MIXING DUE TO THE VISCOUS
NATURE OF THE PAM POLYMER.
5.THE STRAW, MULCH, AND/OR EROSION CONTROL MATTING SHALL BE APPLIED OVER THE
HYDROSEEDED APPLICATION AS SPECIFIED IN THE DRAWINGS.PIEDMONT CONCORD LAKEPREPARED FORCAROLINA DEVELOPMENT SERVICESGENERAL NOTESC0-2
SOILS TYPE LEGEND
EROSION CONTROL LEGEND
XxX
CcB2 CECIL SANDY CLAY LOAM, 2 TO 8 PERCENT SLOPES, MODERATELY ERODED
CcD2 CECIL SANDY CLAY LOAM, 8 TO 15 PERCENT SLOPES, MODERATELY ERODED
CeB CECIL-URBAN LAND COMPLEX, 2 TO 10 PERCENT SLOPES
ChA CHEWACLA SANDY LOAM, 0 TO 2 PERCENT SLOPES
ENB ENON SANDY LOAM, 2 TO 8 PERCENT SLOPES
EnD ENON SANDY LOAM, 8 TO 15 PERCENT SLOPES
EoB ENON-URBAN LAND COMPLEX, 2 TO 10 PERCENT SLOPES
IdB IREDELL LOAM, 2 TO 6 PERCENT SLOPES
PoB POINDEXTER LOAM, 2 TO 8 PERCENT SLOPES
PoD POINDEXTER LOAM, 8 TO 15 PERCENT SLOPES
TOTAL DISTURBED AREA:
41
SOIL TYPE
LIMITS OF DISTURBANCE
EXISTING MAJOR CONTOUR
EXISTING MINOR CONTOUR
PROPOSED MAJOR CONTOUR
PROPOSED MINOR CONTOUR
SLOPE ARROW
LIMITS OF DRAINAGE SUB-BASIN
TEMPORARY/PERMANENT DIVERSION
DITCH OR BERM, SEE DETAIL SHEET
SWPPP INFORMATION SIGN
PROPERTY LINE
RIP RAP APRON , RIP-RAP SHALL
BE GRADED AT 0.0% SLOPE
TEMPORARY SILT FENCE
SOIL TYPE BOUNDARY
SLOPE MATTING
(SC150 UNLESS OTHERWISE SPECIFIED)
TEMPORARY PROTECTION FENCE/
HIGH HAZARD SILT FENCE
TEMPORARY SLOPE DRAIN
SEE DETAIL SHEET
STONE FILTER RING
COIR WATTLE CHECK DAM, SEE DETAIL
SHEET
CONSTRUCTION EXIT
EE DETAIL SHEET
TEMPORARY RISER SKIMMER, SEE
DETAIL SHEET
TEMPORARY JUTE NET BAFFLES
12" COIR WATTLE/FILTREX FILTER
SOX, SEE DETAIL SHEET.
LOD
SIS
CE
CD
JN
DD#
ECB
SF
PF
RR
SD #
SFR
CW
SK
(SEE DETAIL SHEETS FOR TYPICAL DETAILS AND GENERAL NOTES. THIS SHEET FOR
ADDITIONAL NOTES.
EROSION CONTROL NOTES:
1. CONTRACTOR SHALL PROTECT EXISTING PLANT MATERIAL NOT DESIGNATED
FOR REMOVAL OR RELOCATION FROM DAMAGE DURING CONSTRUCTION.
2. CONTRACTOR SHALL KEEP ALL SURROUNDING PUBLIC ROADWAYS AND
DRAINAGE SYSTEMS FREE FROM DIRT, MUD, AND CONSTRUCTION DEBRIS AT
ALL TIMES.
3. LIMITS OF CONSTRUCTION AND CONTRACTOR STAGING AREAS SHALL BE
LIMITED TO THE PROPERTY BOUNDARY, UNLESS NOTED OTHERWISE ON THESE
PLANS.
4. LIMITS OF DEMOLITION INDICATED ON PLAN ARE MINIMUM. CONTRACTOR SHALL
REMOVE AND REPLACE ASPHALT PAVEMENT AS NECESSARY TO FACILITATE
CONSTRUCTION IN ACCORDANCE WITH STATE AND LOCAL REGULATIONS.
5. CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR AND/OR REPLACEMENT
OF ANY ITEMS OR EXISTING IMPROVEMENTS (NOT SCHEDULED FOR
DEMOLITION) DAMAGED DURING THE CONSTRUCTION INCLUDING PROPERTY
CORNERS, MONUMENTS, ETC.
6. CONTRACTOR SHALL COORDINATE WITH THE CITY OF KANNAPOLIS TO OBTAIN
ALL NECESSARY DEMOLITION PERMITS PRIOR TO THE START OF ANY
DEMOLITION WORK.
7. REMOVE VEGETATION AND GRASS IN AREAS TO RECEIVE NEW ASPHALT AND
CONCRETE PAVEMENTS.
8. THE CONTRACTOR SHALL DEMOLISH AND REMOVE OFF-SITE FACILITIES WITHIN
THE PROJECT SITE TO INCLUDE BUILDINGS, CONCRETE STRUCTURES (ABOVE
GROUND AND FOUNDATION), SITE LIGHTING STRUCTURES, PAVEMENTS AND
SECONDARY UTILITIES. ALL MATERIALS SHALL BE PROPERLY DISPOSED OF PER
LOCAL AND STATE REGULATIONS.
9. ALL PRIMARY UTILITIES DISCOVERED DURING DEMOLITION OPERATIONS THAT
SERVE ACTIVITIES OTHER THAN THE EXISTING STRUCTURE SHALL BE
PROPERLY PRESERVED AND PROTECTED.
10. THE CONTRACTOR SHALL IMMEDIATELY REPORT TO THE OWNER AND
ENGINEER ANY UNFORESEEN OR ADVERSE CONDITIONS, INCLUDING
UNCHARTED UTILITIES, DISCOVERED DURING DEMOLITION OPERATIONS.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR AND/OR
REPLACEMENT OF ANY ITEMS OR EXISTING IMPROVEMENTS (NOT SCHEDULED
FOR DEMOLITION) WHICH ARE DAMAGED DURING CONSTRUCTION, INCLUDING
PROPERTY CORNERS, MONUMENTS, VEGETATION, ETC.
DB#
IP INLET PROTECTION
EoB
ChA
EnB
EnB
DD2
CW
PF
PF
LOD
LOD
LOD
LOD
LOD
LOD
LOD
SF
RR1A RR 1B
ECB
ECB
ECB
SF
SD1B
SD1A
DB1
CONSTRUCTION SEQUENCE
PIEDMONT CONCORD LAKEPREPARED FORCAROLINA DEVELOPMENT SERVICESEROSION CONTROLPHASE 1C2-1Know what's
R
NORTH
IdB
DD4
SD 2B
LOD
LOD
LOD
LOD LOD
LOD
LOD
SFR
SFR
SFR
IP
RR 2B
RR
JN
JN
SD 3A
RR3A
RR 3B
ECB
ECBECB
ECB
ECB
SD 2A
RR2A
RR 2C
SD 3B
SOILS TYPE LEGEND
EROSION CONTROL LEGEND
XxX
CcB2 CECIL SANDY CLAY LOAM, 2 TO 8 PERCENT SLOPES, MODERATELY ERODED
CcD2 CECIL SANDY CLAY LOAM, 8 TO 15 PERCENT SLOPES, MODERATELY ERODED
CeB CECIL-URBAN LAND COMPLEX, 2 TO 10 PERCENT SLOPES
ChA CHEWACLA SANDY LOAM, 0 TO 2 PERCENT SLOPES
ENB ENON SANDY LOAM, 2 TO 8 PERCENT SLOPES
EnD ENON SANDY LOAM, 8 TO 15 PERCENT SLOPES
EoB ENON-URBAN LAND COMPLEX, 2 TO 10 PERCENT SLOPES
IdB IREDELL LOAM, 2 TO 6 PERCENT SLOPES
PoB POINDEXTER LOAM, 2 TO 8 PERCENT SLOPES
PoD POINDEXTER LOAM, 8 TO 15 PERCENT SLOPES
TOTAL DISTURBED AREA:
41
SOIL TYPE
LIMITS OF DISTURBANCE
EXISTING MAJOR CONTOUR
EXISTING MINOR CONTOUR
PROPOSED MAJOR CONTOUR
PROPOSED MINOR CONTOUR
SLOPE ARROW
LIMITS OF DRAINAGE SUB-BASIN
TEMPORARY/PERMANENT DIVERSION
DITCH OR BERM, SEE DETAIL SHEET
SWPPP INFORMATION SIGN
PROPERTY LINE
RIP RAP APRON , RIP-RAP SHALL
BE GRADED AT 0.0% SLOPE
TEMPORARY SILT FENCE
SOIL TYPE BOUNDARY
SLOPE MATTING
(SC150 UNLESS OTHERWISE SPECIFIED)
TEMPORARY PROTECTION FENCE/
HIGH HAZARD SILT FENCE
TEMPORARY SLOPE DRAIN
SEE DETAIL SHEET
STONE FILTER RING
COIR WATTLE CHECK DAM, SEE DETAIL
SHEET
CONSTRUCTION EXIT
EE DETAIL SHEET
TEMPORARY RISER SKIMMER, SEE
DETAIL SHEET
TEMPORARY JUTE NET BAFFLES
12" COIR WATTLE/FILTREX FILTER
SOX, SEE DETAIL SHEET.
LOD
SIS
CE
CD
JN
DD#
ECB
SF
PF
RR
SD #
SFR
CW
SK
(SEE DETAIL SHEETS FOR TYPICAL DETAILS AND GENERAL NOTES. THIS SHEET FOR
ADDITIONAL NOTES.
EROSION CONTROL NOTES:
1. CONTRACTOR SHALL PROTECT EXISTING PLANT MATERIAL NOT DESIGNATED
FOR REMOVAL OR RELOCATION FROM DAMAGE DURING CONSTRUCTION.
2. CONTRACTOR SHALL KEEP ALL SURROUNDING PUBLIC ROADWAYS AND
DRAINAGE SYSTEMS FREE FROM DIRT, MUD, AND CONSTRUCTION DEBRIS AT
ALL TIMES.
3. LIMITS OF CONSTRUCTION AND CONTRACTOR STAGING AREAS SHALL BE
LIMITED TO THE PROPERTY BOUNDARY, UNLESS NOTED OTHERWISE ON THESE
PLANS.
4. LIMITS OF DEMOLITION INDICATED ON PLAN ARE MINIMUM. CONTRACTOR SHALL
REMOVE AND REPLACE ASPHALT PAVEMENT AS NECESSARY TO FACILITATE
CONSTRUCTION IN ACCORDANCE WITH STATE AND LOCAL REGULATIONS.
5. CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR AND/OR REPLACEMENT
OF ANY ITEMS OR EXISTING IMPROVEMENTS (NOT SCHEDULED FOR
DEMOLITION) DAMAGED DURING THE CONSTRUCTION INCLUDING PROPERTY
CORNERS, MONUMENTS, ETC.
6. CONTRACTOR SHALL COORDINATE WITH THE CITY OF KANNAPOLIS TO OBTAIN
ALL NECESSARY DEMOLITION PERMITS PRIOR TO THE START OF ANY
DEMOLITION WORK.
7. REMOVE VEGETATION AND GRASS IN AREAS TO RECEIVE NEW ASPHALT AND
CONCRETE PAVEMENTS.
8. THE CONTRACTOR SHALL DEMOLISH AND REMOVE OFF-SITE FACILITIES WITHIN
THE PROJECT SITE TO INCLUDE BUILDINGS, CONCRETE STRUCTURES (ABOVE
GROUND AND FOUNDATION), SITE LIGHTING STRUCTURES, PAVEMENTS AND
SECONDARY UTILITIES. ALL MATERIALS SHALL BE PROPERLY DISPOSED OF PER
LOCAL AND STATE REGULATIONS.
9. ALL PRIMARY UTILITIES DISCOVERED DURING DEMOLITION OPERATIONS THAT
SERVE ACTIVITIES OTHER THAN THE EXISTING STRUCTURE SHALL BE
PROPERLY PRESERVED AND PROTECTED.
10. THE CONTRACTOR SHALL IMMEDIATELY REPORT TO THE OWNER AND
ENGINEER ANY UNFORESEEN OR ADVERSE CONDITIONS, INCLUDING
UNCHARTED UTILITIES, DISCOVERED DURING DEMOLITION OPERATIONS.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR AND/OR
REPLACEMENT OF ANY ITEMS OR EXISTING IMPROVEMENTS (NOT SCHEDULED
FOR DEMOLITION) WHICH ARE DAMAGED DURING CONSTRUCTION, INCLUDING
PROPERTY CORNERS, MONUMENTS, VEGETATION, ETC.
DB#
IP INLET PROTECTION
CONSTRUCTION SEQUENCE
PIEDMONT CONCORD LAKEPREPARED FORCAROLINA DEVELOPMENT SERVICESEROSION CONTROLPHASE 1C2-2Know what's
R
NORTH
SOILS TYPE LEGEND
EROSION CONTROL LEGEND
XxXXxX
EROSION CONTROL NOTES:
CcB2 CECIL SANDY CLAY LOAM, 2 TO 8 PERCENT SLOPES, MODERATELY ERODED
CcD2 CECIL SANDY CLAY LOAM, 8 TO 15 PERCENT SLOPES, MODERATELY ERODED
CeB CECIL-URBAN LAND COMPLEX, 2 TO 10 PERCENT SLOPES
ChA CHEWACLA SANDY LOAM, 0 TO 2 PERCENT SLOPES
ENB ENON SANDY LOAM, 2 TO 8 PERCENT SLOPES
EnD ENON SANDY LOAM, 8 TO 15 PERCENT SLOPES
EoB ENON-URBAN LAND COMPLEX, 2 TO 10 PERCENT SLOPES
IdB IREDELL LOAM, 2 TO 6 PERCENT SLOPES
PoB POINDEXTER LOAM, 2 TO 8 PERCENT SLOPES
PoD POINDEXTER LOAM, 8 TO 15 PERCENT SLOPES
(SEE DETAIL SHEETS FOR TYPICAL DETAILS AND GENERAL NOTES. THIS SHEET FOR
ADDITIONAL NOTES.
SLOPE ARROW
SWPPP INFORMATION SIGN
RIP RAP APRON , RIP-RAP SHALL
BE GRADED AT 0.0% SLOPE
TEMPORARY SILT FENCE
TOTAL DISTURBED AREA:
41
1. CONTRACTOR SHALL PROTECT EXISTING PLANT MATERIAL NOT DESIGNATED
FOR REMOVAL OR RELOCATION FROM DAMAGE DURING CONSTRUCTION.
2. CONTRACTOR SHALL KEEP ALL SURROUNDING PUBLIC ROADWAYS AND
DRAINAGE SYSTEMS FREE FROM DIRT, MUD, AND CONSTRUCTION DEBRIS AT
ALL TIMES.
3. LIMITS OF CONSTRUCTION AND CONTRACTOR STAGING AREAS SHALL BE
LIMITED TO THE PROPERTY BOUNDARY, UNLESS NOTED OTHERWISE ON THESE
PLANS.
4. LIMITS OF DEMOLITION INDICATED ON PLAN ARE MINIMUM. CONTRACTOR SHALL
REMOVE AND REPLACE ASPHALT PAVEMENT AS NECESSARY TO FACILITATE
CONSTRUCTION IN ACCORDANCE WITH STATE AND LOCAL REGULATIONS.
5. CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR AND/OR REPLACEMENT
OF ANY ITEMS OR EXISTING IMPROVEMENTS (NOT SCHEDULED FOR
DEMOLITION) DAMAGED DURING THE CONSTRUCTION INCLUDING PROPERTY
CORNERS, MONUMENTS, ETC.
6. CONTRACTOR SHALL COORDINATE WITH THE CITY OF KANNAPOLIS TO OBTAIN
ALL NECESSARY DEMOLITION PERMITS PRIOR TO THE START OF ANY
DEMOLITION WORK.
7. REMOVE VEGETATION AND GRASS IN AREAS TO RECEIVE NEW ASPHALT AND
CONCRETE PAVEMENTS.
8. THE CONTRACTOR SHALL DEMOLISH AND REMOVE OFF-SITE FACILITIES WITHIN
THE PROJECT SITE TO INCLUDE BUILDINGS, CONCRETE STRUCTURES (ABOVE
GROUND AND FOUNDATION), SITE LIGHTING STRUCTURES, PAVEMENTS AND
SECONDARY UTILITIES. ALL MATERIALS SHALL BE PROPERLY DISPOSED OF PER
LOCAL AND STATE REGULATIONS.
9. ALL PRIMARY UTILITIES DISCOVERED DURING DEMOLITION OPERATIONS THAT
SERVE ACTIVITIES OTHER THAN THE EXISTING STRUCTURE SHALL BE
PROPERLY PRESERVED AND PROTECTED.
10. THE CONTRACTOR SHALL IMMEDIATELY REPORT TO THE OWNER AND
ENGINEER ANY UNFORESEEN OR ADVERSE CONDITIONS, INCLUDING
UNCHARTED UTILITIES, DISCOVERED DURING DEMOLITION OPERATIONS.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR AND/OR
REPLACEMENT OF ANY ITEMS OR EXISTING IMPROVEMENTS (NOT SCHEDULED
FOR DEMOLITION) WHICH ARE DAMAGED DURING CONSTRUCTION, INCLUDING
PROPERTY CORNERS, MONUMENTS, VEGETATION, ETC.
SOIL TYPE BOUNDARY
SOIL TYPE
TEMPORARY PROTECTION FENCE/
HIGH HAZARD SILT FENCE
TEMPORARY SLOPE DRAIN
SEE DETAIL SHEET
LIMITS OF DISTURBANCE
EXISTING MAJOR CONTOUR
STONE FILTER RING
EXISTING MINOR CONTOUR
PROPOSED MAJOR CONTOUR
PROPOSED MINOR CONTOUR
TEMPORARY JUTE NET BAFFLES
LIMITS OF DRAINAGE SUB-BASIN
TEMPORARY/PERMANENT DIVERSION
DITCH OR BERM, SEE DETAIL SHEET
PERMANENT SEEDING
SEE DETAIL SHEET FOR SCHEDULE
PROPERTY LINE
CONSTRUCTION EXIT
SEE DETAIL SHEET
ROCK CHECK DAM
SEE DETAIL SHEET
12" COIR WATTLE/FILTREX FILTER
SOX, SEE DETAIL SHEET.
INLET PROTECTION
TEMPORARY RISER SKIMMER, SEE
DETAIL SHEET
SLOPE MATTING
(SC150 UNLESS OTHERWISE SPECIFIED)
LOD
SIS
CE
CD
JN
DD#
PS
SF
PF
RR
SD #
SFR
CW
SK
DB#
IP
ECB
EoB
ChA
EnB
EnB
DD2
CW
PF
PF
LOD
LOD
LOD
LOD
LOD
LOD
LOD
SF
RR1A RR 1B
ECB
ECB
ECB
SF
SD1A
DB1
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
CONSTRUCTION SEQUENCE
PIEDMONT CONCORD LAKEPREPARED FORCAROLINA DEVELOPMENT SERVICESEROSION CONTROLPHASE 2C2-3Know what's
R
NORTH
SOILS TYPE LEGEND
EROSION CONTROL LEGEND
XxXXxX
EROSION CONTROL NOTES:
CcB2 CECIL SANDY CLAY LOAM, 2 TO 8 PERCENT SLOPES, MODERATELY ERODED
CcD2 CECIL SANDY CLAY LOAM, 8 TO 15 PERCENT SLOPES, MODERATELY ERODED
CeB CECIL-URBAN LAND COMPLEX, 2 TO 10 PERCENT SLOPES
ChA CHEWACLA SANDY LOAM, 0 TO 2 PERCENT SLOPES
ENB ENON SANDY LOAM, 2 TO 8 PERCENT SLOPES
EnD ENON SANDY LOAM, 8 TO 15 PERCENT SLOPES
EoB ENON-URBAN LAND COMPLEX, 2 TO 10 PERCENT SLOPES
IdB IREDELL LOAM, 2 TO 6 PERCENT SLOPES
PoB POINDEXTER LOAM, 2 TO 8 PERCENT SLOPES
PoD POINDEXTER LOAM, 8 TO 15 PERCENT SLOPES
(SEE DETAIL SHEETS FOR TYPICAL DETAILS AND GENERAL NOTES. THIS SHEET FOR
ADDITIONAL NOTES.
SLOPE ARROW
SWPPP INFORMATION SIGN
RIP RAP APRON , RIP-RAP SHALL
BE GRADED AT 0.0% SLOPE
TEMPORARY SILT FENCE
TOTAL DISTURBED AREA:
41
1. CONTRACTOR SHALL PROTECT EXISTING PLANT MATERIAL NOT DESIGNATED
FOR REMOVAL OR RELOCATION FROM DAMAGE DURING CONSTRUCTION.
2. CONTRACTOR SHALL KEEP ALL SURROUNDING PUBLIC ROADWAYS AND
DRAINAGE SYSTEMS FREE FROM DIRT, MUD, AND CONSTRUCTION DEBRIS AT
ALL TIMES.
3. LIMITS OF CONSTRUCTION AND CONTRACTOR STAGING AREAS SHALL BE
LIMITED TO THE PROPERTY BOUNDARY, UNLESS NOTED OTHERWISE ON THESE
PLANS.
4. LIMITS OF DEMOLITION INDICATED ON PLAN ARE MINIMUM. CONTRACTOR SHALL
REMOVE AND REPLACE ASPHALT PAVEMENT AS NECESSARY TO FACILITATE
CONSTRUCTION IN ACCORDANCE WITH STATE AND LOCAL REGULATIONS.
5. CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR AND/OR REPLACEMENT
OF ANY ITEMS OR EXISTING IMPROVEMENTS (NOT SCHEDULED FOR
DEMOLITION) DAMAGED DURING THE CONSTRUCTION INCLUDING PROPERTY
CORNERS, MONUMENTS, ETC.
6. CONTRACTOR SHALL COORDINATE WITH THE CITY OF KANNAPOLIS TO OBTAIN
ALL NECESSARY DEMOLITION PERMITS PRIOR TO THE START OF ANY
DEMOLITION WORK.
7. REMOVE VEGETATION AND GRASS IN AREAS TO RECEIVE NEW ASPHALT AND
CONCRETE PAVEMENTS.
8. THE CONTRACTOR SHALL DEMOLISH AND REMOVE OFF-SITE FACILITIES WITHIN
THE PROJECT SITE TO INCLUDE BUILDINGS, CONCRETE STRUCTURES (ABOVE
GROUND AND FOUNDATION), SITE LIGHTING STRUCTURES, PAVEMENTS AND
SECONDARY UTILITIES. ALL MATERIALS SHALL BE PROPERLY DISPOSED OF PER
LOCAL AND STATE REGULATIONS.
9. ALL PRIMARY UTILITIES DISCOVERED DURING DEMOLITION OPERATIONS THAT
SERVE ACTIVITIES OTHER THAN THE EXISTING STRUCTURE SHALL BE
PROPERLY PRESERVED AND PROTECTED.
10. THE CONTRACTOR SHALL IMMEDIATELY REPORT TO THE OWNER AND
ENGINEER ANY UNFORESEEN OR ADVERSE CONDITIONS, INCLUDING
UNCHARTED UTILITIES, DISCOVERED DURING DEMOLITION OPERATIONS.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR AND/OR
REPLACEMENT OF ANY ITEMS OR EXISTING IMPROVEMENTS (NOT SCHEDULED
FOR DEMOLITION) WHICH ARE DAMAGED DURING CONSTRUCTION, INCLUDING
PROPERTY CORNERS, MONUMENTS, VEGETATION, ETC.
SOIL TYPE BOUNDARY
SOIL TYPE
TEMPORARY PROTECTION FENCE/
HIGH HAZARD SILT FENCE
TEMPORARY SLOPE DRAIN
SEE DETAIL SHEET
LIMITS OF DISTURBANCE
EXISTING MAJOR CONTOUR
STONE FILTER RING
EXISTING MINOR CONTOUR
PROPOSED MAJOR CONTOUR
PROPOSED MINOR CONTOUR
TEMPORARY JUTE NET BAFFLES
LIMITS OF DRAINAGE SUB-BASIN
TEMPORARY/PERMANENT DIVERSION
DITCH OR BERM, SEE DETAIL SHEET
PERMANENT SEEDING
SEE DETAIL SHEET FOR SCHEDULE
PROPERTY LINE
CONSTRUCTION EXIT
SEE DETAIL SHEET
ROCK CHECK DAM
SEE DETAIL SHEET
12" COIR WATTLE/FILTREX FILTER
SOX, SEE DETAIL SHEET.
INLET PROTECTION
TEMPORARY RISER SKIMMER, SEE
DETAIL SHEET
SLOPE MATTING
(SC150 UNLESS OTHERWISE SPECIFIED)
IdB
DD4 CD
TYP.
SD 2B
CW
LOD
LOD
LOD
LOD LOD
LOD
LOD
SFR
SFR
SFR
IP
RR 2B
RR
JN
JN
SD 3A
RR3A
RR 3B
ECBECB
ECB
ECB
SD 2A
RR2A
RR 2C
SD 3B
DD6
CD
TYP.ECB
PS
PS
PS
PS
PS
PS
PS
PS
CONSTRUCTION SEQUENCE
PIEDMONT CONCORD LAKEPREPARED FORCAROLINA DEVELOPMENT SERVICESEROSION CONTROLPHASE 2C2-4Know what's
R
NORTH
SEDIMENT BASIN WITH PIPE OUTLET
TEMPORARY SKIMMER RISER SEDIMENT BASIN WITH PIPE OUTLETTEMPORARY SKIMMER RISER SEDIMENT BASIN WITH PIPE OUTLET
PIEDMONT CONCORD LAKEPREPARED FORCAROLINA DEVELOPMENT SERVICESEROSION CONTROLDETAILSC2-5
BAFFLE SPECIFICATIONS
MATERIALS:
1.USE MATTING MADE OF 100% COCONUT FIBER (COIR) TWINE WOVEN INTO HIGH STRENGTH
MATRIX WITH THE PROPERTIES SHOWN IN TABLE 6.65A.
2.STAPLES SHOULD BE MADE OF 0.125 INCH DIAMETER NEW STEEL WIRE FORMED INTO A 'U'
SHAPE NOT LESS THAN 12 INCHES IN LENGTH WITH A THROAT OF 1 INCH IN WIDTH. THE STAPLES
ANCHOR THE POROUS BAFFLES INTO THE SIDES AND BOTTOM OF THE BASIN.
3. ENSURE THAT STEEL POSTS FOR POROUS BAFFLES ARE OF A SUFFICIENT HEIGHT TO SUPPORT
BAFFLES AT DESIRED HEIGHT. POSTS SHOULD BE APPROXIMATELY 1-3/8" WIDE MEASURED
PARALLEL TO THE FENCE, AND HAVE A MINIMUM WEIGHT OF 1.25 LB/LINEAR FT. THE POSTS MUST
BE EQUIPPED WITH AN ANCHOR PLATE HAVING A MINIMUM AREA OF 14.0 SQUARE INCHES AND
BE OF THE SELF-FASTENER ANGLE STEEL TYPE TO HAVE A MEANS OF RETAINING WIRE AND
COIR FIBER MAT IN THE DESIRED POSITION WITHOUT DISPLACEMENT.
4. USE 9-GAUGE HIGH TENSION WIRE FOR SUPPORT WIRE.
CONSTRUCTION:
1. GRADE THE BASIN SO THAT THE BOTTOM IS LEVEL FRONT TO BACK AND SIDE TO SIDE.
2. INSTALL THE COIR FIBER BAFFLES IMMEDIATELY UPON EXCAVATION OF THE BASINS.
3. INSTALL POSTS ACROSS THE WIDTH OF THE SEDIMENT TRAP.
4.STEEL POSTS SHOULD BE DRIVEN TO A DEPTH OF 24 INCHES AND SPACED A MAXIMUM OF 4
FEET APART. THE TOP OF THE FABRIC SHOULD BE A MINIMUM OF 6 INCHES HIGHER THAN THE
INVERT OF THE SPILLWAY. TOPS OF BAFFLES SHOULD BE A MINIMUM OF 2 INCHES LOWER THAN
THE TOP OF THE EARTHEN EMBANKMENT.
5. INSTALL AT LEAST THREE ROWS OF BAFFLES BETWEEN THE INLET AND OUTLET DISCHARGE
POINT. BASINS LESS THAN 20 FEET IN LENGTH MAY USE 2 BAFFLES.
6.ATTACH A 9 GAUGE HIGH TENSION WIRE STRAND TO THE STEEL POSTS AT A HEIGHT OF 6
INCHES ABOVE THE SPILLWAY ELEVATION WITH PLASTIC TIES OR WIRE FASTENERS TO PREVENT
SAGGING. IF THE TEMPORARY SEDIMENT BASIN WILL BE CONVERTED TO A PERMANENT
STORMWATER BASIN OF A GREATER DEPTH, THE BAFFLE HEIGHT SHOULD BE BASED ON THE
POOL DEPTH DURING USE AS A TEMPORARY SEDIMENT BASIN.
7. EXTEND 9 GAUGE MINIMUM HIGH TENSION WIRE STRAND TO SIDE OF BASIN OR INSTALL STEEL
T-POSTS TO ANCHOR BAFFLE TO SIDE OF BASIN AND SECURE TO VERTICAL END POSTS.
8.DRAPE THE COIR FIBER MAT OVER THE WIRE STRAND MOUNTED AT A HEIGHT OF 6 INCHES
ABOVE THE SPILLWAY ELEVATION. SECURE THE COIR FIBER MAT TO THE WIRE STRAND WITH
PLASTIC TIES OR WIRE FASTENERS. ANCHOR THE MATTING TO THE SIDES AND FLOOR OF THE
BASIN WITH 12 INCH WIRE STAPLES, APPROXIMATELY 1 FT APART, ALONG THE BOTTOM AND SIDE
SLOPES OF THE BASIN.
9. DO NOT SPLICE THE FABRIC, BUT USE A CONTINUOUS PIECE ACROSS THE BASIN.
10.ADJUSTMENTS MAY BE REQUIRED IN THE STAPLING REQUIREMENTS TO FIT INDIVIDUAL SITE
CONDITIONS.
MAINTENANCE:
1. INSPECT BAFFLES AT LEAST ONCE A WEEK AND AFTER EACH RAINFALL. MAKE ANY REQUIRED
REPAIRS IMMEDIATELY.
2.BE SURE TO MAINTAIN ACCESS TO THE BAFFLES. SHOULD THE FABRIC OF A BAFFLE COLLAPSE,
TEAR, DECOMPOSE, OR BECOME INEFFECTIVE, REPLACE IT PROMPTLY.
3.REMOVE SEDIMENT DEPOSITS WHEN IT REACHES HALF FULL, TO PROVIDE ADEQUATE STORAGE
VOLUME FOR THE NEXT RAIN AND TO REDUCE PRESSURE ON THE BAFFLES. TAKE CARE TO
AVOID DAMAGING THE BAFFLES DURING CLEANOUT, AND REPLACE IF DAMAGED DURING
CLEANOUT OPERATIONS. SEDIMENT DEPTH SHOULD NEVER EXCEED HALF THE DESIGNED
STORAGE DEPTH.
4.AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN PROPERLY STABILIZED, REMOVE ALL
BAFFLE MATERIALS AND UNSTABLE SEDIMENT DEPOSITS, BRING THE AREA TO GRADE, AND
STABILIZE IT.
COIR FIBER BAFFLE MATERIAL PROPERTY REQUIREMENTS (TABLE 6.65A)
THICKNESS
TENSILE STRENGTH (WET)
ELONGATION (WET)
FLOW VELOCITY
WEIGHT
MINIMUM WIDTH
OPEN AREA
900 x 680 LB/FT MINIMUM
0.30 IN. MINIMUM
69% x 34% MAXIMUM
10-12 FT/SEC
20 oz/SY (680 G/M^2) MINIMUM
6.5 FEET
50% MAXIMUM
PIEDMONT CONCORD LAKEPREPARED FORCAROLINA DEVELOPMENT SERVICESEROSION CONTROLDETAILSC2-6
WITH PERMANENT WOODY PLANTS.
COIR WATTLE AND WILLOW FASCINES STABALIZING SLOPE
FIGURE2A
FIGURE2B
PROPER PLACEMENT OF COIR WATTLE IN SLOPE
NOTES:
www.CADdetails.comPROTECTED BY COPYRIGHT - 11/06/06
COIR WATTLE: CHECK DAMS IN
SLOPES & WATERWAYS
1. INSTALLATION TO BE COMPLETED IN ACCORDANCE WITH MANUFACTURER'S SPECIFICATIONS.
2. DO NOT SCALE DRAWINGS.
3. ON DRAINAGE WAY LINED WITH TURF REINFORCEMENT MAT (TRM) OR EROSION CONTROL
BLANKET (ECB), COIR WATTLE SHAL INSTALLED AS CHECK DAMS (FIG.1).
4. ON UNVEGETATED AND DISTURBED SLOPES OR SLOPES LINED WITH ECB, COIR WATTLE SHALL
BE INSTALLED AS CHECK DAMS (FIG. 2B).
5. CONTRACTORS NOTE: FOR PRODUCT AND COMPANY INFORMATION VISIT
http://www.rolanka.com/GN/scWatl.html.
6. 9" WATTLES ANCHOR IN TRENCH 1/4-1/3 ROLL AND SHOW STAKE SPACING.
THE CONTRACTOR MAY
CHOOSE TYPE OF CHECK
DAM TO BE USED.
CHECK DAM MAINTENANCE:PIEDMONT CONCORD LAKEPREPARED FORCAROLINA DEVELOPMENT SERVICESEROSION CONTROLDETAILSC2-7