HomeMy WebLinkAbout20181041 Ver 2_2017-02329 NW 29 REVISED_20181031Revised 10/31/2018, Supersedes NWP 29 verification dated 8/28/2018
U.S. ARMY CORPS OF ENGINEERS
WILMINGTON DISTRICT
Action Id. SAW -2017-02329 County: Alamance U.S.G.S. Quad: NC -Mebane
GENERAL PERMIT (REGIONAL AND NATIONWIDE) VERIFICATION
Permittee: Desco Holdings, LLC
Attn: Eric Dischinger
Address: 600 Market Street
Chapel Hill, NC 27516
Size (acres) 233.89 Nearest Town Mebane
Nearest Waterway Haw Creek River Basin Cape Fear
USGS HUC 03030002 Coordinates 36.049116 N, -79.293125 W
Location description: The prosect area is located between the eastern terminus of Rock Bridge Drive and the western terminus
of Burgess Drive, in Mebane, Alamance County, North Carolina.
Description of projects area and activity: This verification authorizes the permanent discharge of fill material into 175 linear feet
of stream channel (90 linear feet of which constitute a permanent loss of waters), and the temporary discharge of dredged or
fill material into 120 linear feet of stream channel necessary to construct access and infrastructure for phase 1A of the
Cambridge Park residential subdivision.
Applicable Law(s): ® Section 404 (Clean Water Act, 33 USC 1344)
❑ Section 10 (Rivers and Harbors Act, 33 USC 403)
Authorization: NWP 29. Residential Developments
SEE ATTACHED NWP GENERAL, REGIONAL, AND/OR SPECIAL CONDITIONS
Your work is authorized by the above referenced permit provided it is accomplished in strict accordance with the enclosed
Conditions, your application signed and dated 10/30/2018, and additional information provided 8/24/2018 via email, and the
enclosed plans Sheets 1 through 9. Any violation of the attached conditions or deviation from your submitted plans may subject
the permittee to a stop work order, a restoration order, a Class I administrative penalty, and/or appropriate legal action.
This verification will remain valid until the expiration date identified below unless the nationwide authorization is modified, suspended
or revoked. If, prior to the expiration date identified below, the nationwide permit authorization is reissued and/or modified, this
verification will remain valid until the expiration date identified below, provided it complies with all requirements of the modified
nationwide permit. If the nationwide permit authorization expires or is suspended, revoked, or is modified, such that the activity would
no longer comply with the terms and conditions of the nationwide permit, activities which have commenced (i.e., are under construction)
or are under contract to commence in reliance upon the nationwide permit, will remain authorized provided the activity is completed
within twelve months of the date of the nationwide permit's expiration, modification or revocation, unless discretionary authority has
been exercised on a case-by-case basis to modify, suspend or revoke the authorization.
Activities subject to Section 404 (as indicated above) may also require an individual Section 401 Water Quality Certification. You
should contact the NC Division of Water Resources (telephone 919-807-6300) to determine Section 401 requirements.
For activities occurring within the twenty coastal counties subject to regulation under the Coastal Area Management Act (CAMA), prior
to beginning work you must contact the N.C. Division of Coastal Management.
This Department of the Army verification does not relieve the permittee of the responsibility to obtain any other required Federal, State
or local approvals/permits.
If there are any questions regarding this verification, any of the conditions of the Permit, or the Corps of Engineers regulatory program,
please contact David E. Bailev at 919-554-4884 ext. 30 or David.E.Bai1ev2Ausace.armv.mil.
Digitally signed by BAILEY.DAVI D.E. 1379283736
DN: c=US, o=U.S. Government, ou=DoD, ou=PKI,
6 1-'e2'0�v ou=USA, cn=BAILEY.DAVID.E.1379283736
Corps Regulatory Official: Date: 2018.10.31 13:22:31 -04'00 Date: 10/31/2018
Expiration Date of Verification: 03/18/2022
SAW -2017-02329
Determination of Jurisdiction:
A. ❑ There are waters including wetlands, on the above described project area that may be subject to Section 404 of the Clean
Water Act (CWA) (33 USC § 1344) and/or Section 10 of the Rivers and Harbors Act (RHA) (33 USC § 403). This preliminary
determination is not an appealable action under the Regulatory Program Administrative Appeal Process (Reference 33 CFR Part
331). However, you may request an approved JD, which is an appealable action, by contacting the Corps district for further
instruction. Please note, if work is authorized by either a general or nationwide permit, and you wish to request an appeal of an
approved JD, the appeal must be received by the Corps and the appeal process concluded prior to the commencement of any work
in waters of the United States and prior to any work that could alter the hydrology of waters of the United States.
B. ❑ There are Navigable Waters of the United States within the above described project area subject to the permit requirements of
Section 10 of the Rivers and Harbors Act (RHA) (33 USC § 403) and Section 404 of the Clean Water Act (CWA) (33 USC §
1344). Unless there is a change in the law or our published regulations, this determination may be relied upon for a period not to
exceed five years from the date of this notification.
C. ❑ There are waters including wetlands, within the above described project area that are subject to the permit requirements of
Section 404 of the Clean Water Act (CWA) (33 USC § 1344). Unless there is a change in the law or our published regulations,
this determination may be relied upon for a period not to exceed five years from the date of this notification.
D. ® The jurisdictional areas within the above described project area have been identified under a previous action. Please
reference jurisdictional determination issued 06/01/2018. Action ID: SAW -2017-02329.
DINT: c=US,tally signedU.S. GoverBAILEnment,
o .=Doo, 83736
ou=PK
DN: c=6I, o=BAIL Government, 792837, ou=PKI,
III ou=USA, cn=BAILEY.DAVID.E.1379253736
Corps Regulatory Official: Date: 2018.10.31 ,3:22:49-04'00'
David E. Bailey
Date of JD: 06/01/2018 Expiration Date of JD: See previously issued JD
SAW -2017-02329
SPECIAL CONDITIONS
1. In order to compensate for impacts associated with this permit, mitigation shall be provided in
accordance with the provisions outlined on the most recent version of the attached Compensatory
Mitigation Responsibility Transfer Form. The requirements of this form, including any special
conditions listed on this form, are hereby incorporated as special conditions of this permit
authorization.
2. Temporary impact sections of Impacts 2 through 6 as shown on the enclosed plans shall be
restored such that stream banks are re -graded to pre -construction conditions, matted with
biodegradable fiber, and seeded/live staked with native riparian species.
3. Rip rap placed within stream beds at Impacts 1 through 6 shall be "keyed -in" to the stream bed,
such that the top of the rip rap is no higher than the stream be grade. This condition is intended to
ensure that aquatic life passage is preserved within these area by allowing stream low flow to flow
over top of the rip rap.
4. Please note that future impacts and/or phases of the Cambridge Park development project and
related activities associated with Corps Action ID: SAW -2017-02329 will be considered part of a
single and complete project; these impacts will be considered cumulative with impacts permitted
during earlier phases regarding compensatory mitigation and Nationwide Permit thresholds.
Current cumulative impacts to aquatic resources for this single and complete project include
permanent impacts to 175 linear feet (0.02 acre) of stream channel (90 linear feet [0.01 acre] of
which are considered a loss) and temporary impacts to 120 linear feet (0.02 acre) of stream
channel. This amounts to a total loss of potential waters of the US of 90 linear feet (0.01 acre).
Corps Regulatory Official:
Expiration Date of Verification: 3/18/2022
Digitally signed by
""""D
DN: c=US, o=US. Government, ou=DoD,
,U=
PM'
c 13AILEY.DAVID.E.13J9283J35
Date: 2018.10.31 13:23:09 -04'00'
Date: 10/31/2018
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to do so,
please complete the Customer Satisfaction Survey located at ham://co�sma�u.usace.army.mil/cm_a�ex/f1 =136*0co�sma�u.usace.aM.mil/cm_a�ex/f?�=136:4:0.
Copy furnished:
Brad Luckey, Pilot Environmental, Inc. P.O. Box 128, Kernersville, NC 27285
Sue Homewood, NCDEQ-DWR, 450 W. Hanes Mill Rd, Suite 300, Winston-Salem, NC 27105
Compensatory Mitigation Responsibility Transfer Form
Permittee: Desco Holdings, LLC (Attn: Eric Dischinger) Action ID: SAW -2017-02329
Project Name: Cambridge Park / Turner Road / Mebane / Alamance County / residential County: Alamance
Instructions to Permittee: The Permittee must provide a copy of this form to the Mitigation Sponsor, either an approved
Mitigation Bank or the North Carolina Division of Mitigation Services (NCDMS), who will then sign the form to verify the
transfer of the mitigation responsibility. Once the Sponsor has signed this form, it is the Permittee's responsibility to ensure
that to the U.S. Army Corps of Engineers (USACE) Project Manager identified on page two is in receipt of a signed copy of this
form before conducting authorized impacts, unless otherwise specified below. If more than one mitigation Sponsor will be
used to provide the mitigation associated with the permit, or if the impacts and/or the mitigation will occur in more than one
8 -digit Hydrologic Unit Code (HUC), multiple forms will be attached to the permit, and the separate forms for each Sponsor
and/or HUC must be provided to the appropriate mitigation Sponsors.
Instructions to Sponsor: The Sponsor must verify that the mitigation requirements (credits) shown below are available at the
identified site. By signing below, the Sponsor is accepting full responsibility for the identified mitigation, regardless of
whether or not they have received payment from the Permittee. Once the form is signed, the Sponsor must update the bank
ledger and provide a copy of the signed form and the updated bank ledger to the Permittee, the USACE Project Manager, and
the Wilmington District Mitigation Office (see contact information on page 2). The Sponsor must also comply with all
reporting requirements established in their authorizing instrument.
Permitted Impacts and Compensatory Mitigation Requirements:
Permitted Impacts Requiring Mitigation* 8 -digit HUC and Basin: 03030002, Cape Fear River Basin
Stream Impacts (linear feet)
Wetland Impacts (acres)
Warm
Cool
Cold
Riparian Riverine
Riparian Non-Riverine
Non -Riparian
Coastal
90
*If more than one mitigation sponsor will be used for the permit, only include impacts to be mitigated by this sponsor.
Compensatory Mitigation Requirements: 8 -digit HUC and Basin: 03030002, Cape Fear River Basin
Stream Mitigation (credits) Wetland Mitigation (credits)
Warm Cool Cold Riparian Riverine
Riparian Non-Riverine Non -Riparian
Coastal
180
Mitigation Site Debited: NCDMS
(List the name of the bank to be debited. For umbrella banks, also list the specific site.
acceptance letter identifies a specific site, also list the specific site to be debited).
For NCDMS, list NCDMS. If the NCDMS
Section to be completed by the Mitigation Sponsor
Statement of Mitigation Liability Acceptance: I, the undersigned, verify that I am authorized to approve mitigation
transactions for the Mitigation Sponsor shown below, and I certify that the Sponsor agrees to accept full responsibility for
providing the mitigation identified in this document (see the table above), associated with the USACE Permittee and Action
ID number shown. I also verify that released credits (and/or advance credits for NCDMS), as approved by the USACE, are
currently available at the mitigation site identified above. Further, I understand that if the Sponsor fails to provide the
required compensatory mitigation, the USACE Wilmington District Engineer may pursue measures against the Sponsor to
ensure compliance associated with the mitigation requirements.
Mitigation Sponsor Name:
Name of Sponsor's Authorized Representative:
Signature of Sponsor's Authorized Representative Date of Signature
Conditions for Transfer of Compensatory Mitigation Credit:
• Once this document has been signed by the Mitigation Sponsor and the USACE is in receipt of the signed form, the
Permittee is no longer responsible for providing the mitigation identified in this form, though the Permittee remains
responsible for any other mitigation requirements stated in the permit conditions.
• Construction within jurisdictional areas authorized by the permit identified on page one of this form can begin only after
the USACE is in receipt of a copy of this document signed by the Sponsor, confirming that the Sponsor has accepted
responsibility for providing the mitigation requirements listed herein. For authorized impacts conducted by the North
Carolina Department of Transportation (NCDOT), construction within jurisdictional areas may proceed upon permit
issuance; however, a copy of this form signed by the Sponsor must be provided to the USACE within 30 days of permit
issuance. NCDOT remains fully responsible for the mitigation until the USACE has received this form, confirming that the
Sponsor has accepted responsibility for providing the mitigation requirements listed herein.
• Signed copies of this document must be retained by the Permittee, Mitigation Sponsor, and in the USACE administrative
records for both the permit and the Bank/ILF Instrument. It is the Permittee's responsibility to ensure that the USACE
Project Manager (address below) is provided with a signed copy of this form.
• If changes are proposed to the type, amount, or location of mitigation after this form has been signed and returned to
the USACE, the Sponsor must obtain case-by-case approval from the USACE Project Manager and/or North Carolina
Interagency Review Team (NCIRT). If approved, higher mitigation ratios may be applied, as per current District guidance
and a new version of this form must be completed and included in the USACE administrative records for both the permit
and the Bank/ILF Instrument.
Comments/Additional Conditions: A letter from NCDMS, confirming their willing and able to accept the applicants
compensatory mitigation responsibility, dated 7/17/2018 was included with the preconstruction notification.
This form is not valid unless signed below by the USACE Project Manager and by the Mitigation Sponsor on Page 1. Once
signed, the Sponsor should provide copies of this form along with an updated bank ledger to: 1 j the Permittee, 2) the USACE
Project Manager at the address below, and 3) the Wilmington District Mitigation Office, Attn: Todd Tugwell, 11405 Falls
of Neuse Road, Wake Forest, NC27587 (email: todd.tugwell@usace.army. mil). Questions regarding this form or any of the
permit conditions may be directed to the USACE Project Manager below.
USACE Project Manager: David E. Bailey
USACE Field Office: Raleigh Regulatory Office
US Army Corps of Engineers
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Email: David.E.Bailey2@usace.army.mil
Digitally signed by BAILEY.DAVID.E.1379283736
DN: c=US, o=U.S. Government, ou=DoD, ou=PKI,
ou=USA, cn=BAILEY.DAVID.E.1379283736
Date: 2018.10.31 13:23:25 -04'00' 10/31/2018
USACE Project Manager Signature Date of Signature
Current Wilmington District mitigation guidance, including information on mitigation ratios, functional assessments, and
mitigation bank location and availability, and credit classifications (including stream temperature and wetland groupings) is
available at http://ribits.usace.army.mil
PROPOSED
FORCE MAIN
0. f
n fir' a5r1 , `:.�ar't
FUTURE
PRASE -NOT
DESIGNED
- 1�
PROPOSED SEWER
OUTFALL
p
PROPOSED WET
_ DETENTION
POND -A
YC �
i
r
j PROPOSED S
1
1`
OUTFALL
PROPOSED
FORCE MAIN
1 ,
PROPOSED PUMP
�I 1
r=ail �•,
,•�
! ;L_ 1 I 1
- 1�
PROPOSED SEWER
OUTFALL
p
PROPOSED WET
_ DETENTION
POND -A
YC �
i
r
j PROPOSED S
1
1`
OUTFALL
f
1 ,
PROPOSED PUMP
STATION
s
1
�
l
t
�
`4
x
CONNECTION
f"vr��4
WATERLINE
'S' IMPACT -1
I
OVERALL
' - CAMBRIDGE PARK -PHASE I A
STREAM IMPACTS
g MELVILLETOWNSH[P--ALA.MANCBCOUNTY
C MBBANE-NORTH CAROLWA
OCTOBER 29, 2018
a � apo a 20 +aa eoo
w 1 inch —110011_
46D9 Dundas Dr1w
E vans GreensboM
.E ngineering, Inc. Fm336.Nprtb 54 8876 '
--Binet 1974-- Phw a 336.854M77
I Engineers surveyors Planners firm License No.: C -D[68
D=6,546,43' JONES
951
SHEET 2 OF S
$ E
ww°'Ta�
♦ 15 �'° i i�^r S30'27'51 'E
S3294'45YC �Lr S29E '❑d25' 115.82• S36;911'E 5324096$3 'E wcurm•Nnp
�.
' � ♦ � F �� � i'� - m a eY ' 1e
Pte°'`*`rw ,esx�K Ieusr, Iauss
4 �� ' - ttr r iusf r ' sse ' v !(NytER t taryrE.s rveiE�'y
`r� t � i Yd � � � 4m �- atTv= 41f�i v= t m Ufx r= � • 4X. v- !q . 1� �r+�m�� i an�ixn
A•w r- V •ID'v- 41�e,= - EbSrtra ltSE� v oF[Hrv,E
ren*ctto sE: � µrx+iw
a ~ !D1.cdI umm� w x cawn
—
_____
1 1�
tI (•' naom 4AI�e v n� 4 Mma. . J 'X-
21' sr1°se Ra
A' 1
i 21. 1
HA _
. r 0a •e,, .9r r
INSET ~ ` gra `�s `Is.
, —_��-••.ems` �` ��
UR4Y - m neR, va mt-ee]
Y
rwxr nrarx............... .....Ro'C•uF. RS' 10 C,•Wv:eY
� a,...,. _.......... ...... ncutEwn
-
win sErnra.— ...................._.....te•
FA
wel]epv ryel a,
fpIwN1
j
Hv
7 i�¢vJId1]E:5eu
II
r. •a1•%�`'
�,
r
I±
r
,s`M'�Ep,= rue�irc
PH S� ey{+ra r
-��
Irfav[! eYry tt�a FAIN m rww !xo
alar FrrrwF wr. wxn
r
xnt4
F crust rm ,w
�y3�a
rcn°' iowc�wl.c sei.
!A• SL3E_Yti�ti
B
Nle/BEALOE Yte>s n U uwrs
rx r
W A a�..s!a
.fe u i b,' FrC IOrK •eEx v 1]e • 7
i .
lr
,ee eco ro 44cs IUInyEFI ••4r�r !n'v iuw�r�n.
•
a e•
_ r
1}]GEiI.•ww�
`d
�r
F
p
•�. "Ilk
r
a y '
f
rdrN•F
s'P+.
INSET ~ ` gra `�s `Is.
, —_��-••.ems` �` ��
"°'n'' H° CAMBRIi]OR PARK
PHASE IA CT1NS(•j LM ON PLANS
DEMMERANP PARTNERS• LLC
oWa t.�r•W-a�iwr�
ana
cring,
w, SrTES AND UIiUI'f PUN �.
UR4Y - m neR, va mt-ee]
Y
rwxr nrarx............... .....Ro'C•uF. RS' 10 C,•Wv:eY
� a,...,. _.......... ...... ncutEwn
-
win sErnra.— ...................._.....te•
FA
wel]epv ryel a,
fpIwN1
j
Hv
7 i�¢vJId1]E:5eu
,
V17iwa
oSjn;wrms
CLA':r
�,
r
]
sans CnaR• ata, cam: ae>•. mti �. me
r
,s`M'�Ep,= rue�irc
4
r
Irfav[! eYry tt�a FAIN m rww !xo
alar FrrrwF wr. wxn
r
xnt4
F crust rm ,w
�y3�a
rcn°' iowc�wl.c sei.
!A• SL3E_Yti�ti
B
Nle/BEALOE Yte>s n U uwrs
rx r
W A a�..s!a
.fe u i b,' FrC IOrK •eEx v 1]e • 7
i .
uan;
rx� +nc re rceste euw a
,ee eco ro 44cs IUInyEFI ••4r�r !n'v iuw�r�n.
•
•Kax x.wEr ,uxx�arw. ww]-r4Rol�sel, ncwxe.n
Fva ruxr®n•, urxo]mr.,4 E.aa-n,eawru, ncr-eesn
�
1}]GEiI.•ww�
`d
�r
F
F�
"°'n'' H° CAMBRIi]OR PARK
PHASE IA CT1NS(•j LM ON PLANS
DEMMERANP PARTNERS• LLC
oWa t.�r•W-a�iwr�
ana
cring,
w, SrTES AND UIiUI'f PUN �.
STREAM IMPACTS:
TEMP. STREAM IMPACT FOR PIPE PUMP AROUND: 20 LF
PERM. STREAM IMPACT — CULVERT do FILL: 90 LF
— KEYED—IN RIP RAP: 35 LF
BUFFER IMPACTS:
ZONE I IMPACT: 7,532 SF
ZONE 2 IMPACT: 3,938 SF
SCALE: -
PLAN: V'=40'
SECTION: WOR. -1"=40'
VERT.—f4'
SHEET 3 OF 9
CAMBRIDGE PARK - PHASE I A
STRFAM IMPACTS
NELVTLLE TOWNSHIP—ALAMANCE COUNTY
MEBANE -NORTH CAROLINA
OCTOBER 29, 2018
40 0 20 b so
1 inch -40R.
E vans 4609 Dundas Drive
Greensbom,
TE ngineering, Inc. NF ", 85 64°'
—Sk"1974— Phnnc33W4.8877
I Engineers Surveyors Planners Firm Lice s¢ No.: 0.0168
�� nwAcrsowc
SREEt 4 OF 9
1-1 + +--+' + + + •-} + +
DOUBLE ROW OF SILT tI`tCC ++ + 1 ' +' +' +' . , ' + +� ++ +
g" FARCE MAIN AT TOP OF BUFFER (TYP)+ +y *'�+ �'++ r }w r
++*�++ +++++++++
+yam+ ++� r • + +�+'
•� �� , ++'.',' + TEMP. STREAM TIMPACT:+`+ +++++ + +++ 'v
+ .
+ +',+ + SEE LITTLE HAW CREEK TEMPORARY * + + + *+ + .+ «
�• '�,�dy '�"'� * ++,+ '� CROSSING DETAIL (CHANNEL MUST BE +++++' .r;+, * + *i+
+ «:�{ . '1+ +� + RESTORED TO EXISTING CONDITION UPON ++ t *. *+++++r- + +r
+�+.�:•+��y, .2 N .=r: i+.'7�
COMPLETION) *++ 'r.'*�.iF
+* *++i ++ + ++ 9 t + + + *+++,+ ++ .+ • 100-YRLOOD+++�4 rte.
++ . + . "p++ + % :/, • rte++.++++ + +•� , • • �+•+ ,` + � ■
�+�• �! pFy1 �. r� .'�.++ + �' +�t+i •+' +yt' Eta, L5
++ r • + ++ • Z +++i + i 1 + + + 'r
+ + .+++ + .3.-+ ^�'+ + PERMANENT STREAM ii a E �+•+a+ .i
t +++,++ 1.•-++ +1. + CROSSING + yyFR +
t+ + +-t-4 CRE CREEK. +�r + + .:f,+R ��+++ L
++++.�+ LI LTLE4}iAW + ,-.«.-: .�++++i'++ +jam + + O +
tom+ �� + .,q + .� + ,•+ l+[�
, + + � # /`-
« « « 4+.++++ « « + + + + • r •� rj7
4 4 4 + « + • • +' • • • art + ^-a—� + t { + + + • * i7
+ + • • + + + +� + , 1 + + +
+++`i.+ + + ZONE , cy «++ + + + + i +�c�+� gyp.70
► . + •
y + 4 + + + •1 '1 1
k"MAINTdNANCE *�+�•�(� '
'
CORRIDOR
+ RU . + 1 r* irj #
W ++ + Y
DOUBLE ROW OF SILT FENCE++ +r+ �{++ e �Q
AT TOP OF BUFFER (TYP) + +� 17��
�+ ++r ++ 4
+ ` 4
FACTS:
TEMP. STREAM IMPACT FOR PIPE PUMP AROUND: 20 LF
TEMP. STREAM MPACT FOR PPE: 4 LF
PERM. STREAM IMPACT FOR STREAM CROSSING: 10 LF
■
IMPACT -2
CAMBRIDGE PARD - PHASE IA
STREAM IMPACTS
MELVILLE TOWNSHIP-ALAMANCE COUNTY
MEBANE-NORTH CAROLINA
OCTOBER 29, 2018
•o o 20 4D ao
I I inch =90[L.
E+ Vans 4699 Dundas Ihiw
Greenehom,
ngxneering, �%7C• North Curolina 27407
F.336,854-8876
—St -1974-- Phone 336.8548877
1 Engineers Surveyors Planners Firm License Na: C-0168
SHEET 5 OF 9
+ + • I'+'+'+'+'+-+-+-+ 4 +•+-+ t•+ + +-+•+-+ +-+-+ + + +r '
++.++++'+++ + + + + . + + + + + + + + + + + +
+++++.++++,++++ + + ++ ++++++r+++r+++
++++++.+. ♦ r r + +r
+ t + + + + +++++ + + + + + + . . + . . . 1
+ t • + ++ +DOUBLE ROW OF SILT FENCE ,,
+ +++ + + +++ r + ++ AT TOP OF BUFFER (TYP} �/ Q a
+ + + + t + + + + + r
+ + + + + +++�+ . t + + + r +`++ IMPACT:
+ + + + + + PERMANENT STREAMi*\++ ••�•++++ SANG BAGS, X57 STONE &HOSE FOR
+r+++r++r+r++++++++{ CROSSING .+r+++++. CULVERT PUMP AROUND (CHANNEL MUST
'+ + + r r r + r + + + +++ + + BE RESTORED TO EXISTING CONDITION
+ ,'f .'+ + + + + UPON COMPLETION)
++ 100—YR'FLOOD ++++.+ +�. .+.*
1
++++++ + + 0� MAI
+2NTENANCE •` + +r+++ +{++ + +���+. ,
CORRIDOR THRU ' a �' ,+` t+ TONE 2 N
+'+++*r*+++i+ BUFFER + +�� •!�
• + + . ++i + • • + ++ +f�!�
`rf+f+ rf + r +++ TONE 1 O
+++++ ++++ +�+ + + + ,
+ + + + + i,
++.++++++++ + •
++,�T 1 ' , ZONE 1 po
po
TONE 2 N
O PERM. SEWER EASEMENT J
--LSC
10" SEWED CSS
CSS �� C55
DOUBLE ROW OF SILT FENCE
AT TOP OF BUFFER (TYP)
IMPACT -3
CAMBRIDGE PARK - PHASE 1 A
STREAM IMPACTS
MELVILLE TIOWNS141P--ALAMANCE COUNTY
MEBANE,NORTH CAROLINA
OCTOBER 29, 2018
40 a 20 40 W
SSSEAPCTS:
TEMP. STREAM IMPACT FOR PIPE PUMP AROUND: 20 LF
TEMP. STREAM MPACT FOR PIPE: 4 LF 1 inch =aoft.
PERM. STREAM IMPACT FOR STREAM CROSSING: 10 LF 1
SUFFER IMPACTS-. E Valls 4609 Tu
Greemnsboro,
ALLOWABLE — IVorthCaralina 27807
-E ngineelrillg,11C+ Fa. 336 854876
—Siam 1974— Phone 336-854.8877
1 Engineers Su-cyorm Flannen Fiml License No.: C-0166
FKM" SwiNcs\cvneaoce
S 141;137 6 OF 9
.+++.+.++++s++++.+++.. +.��
+ + + + r r . . + + + . ` + + p
+,++++ + . ++, +++• r . + . + + ++ . tl
'++++r++rrr++++++++ 20� MAINTFNANCE+++++
+ + + +` N
`+++++++++'+'+++++` CORRIDOR THRU ++i+++ v
+++ . ♦ • • a r + + ++ BUFFER r+r+r+r++�
++++ + `+` '. + + + . + . + r y
{. + +++++++++...++• +• +`PERMA1VEhITISiREAM • + + + + �
+'+r + + + CROSSING + + +++++� r +++�� DOUBLE ROW OF SILT FENCE
+ + + + + ++++.+ • +
+ + + + + + . + + + + AT TOP OF BUFFER (TYP)
♦++ + + + r r + •+� + + +
+ .++r.+r+.++r+++ *++ +++++ +++L+J+�
`+ 10b—YR FI.DOD`+ ++. ++++ + ++++ + +++ 4. + */�+
+ + +
.+ + + + + + + + + + r +
+++ ++ ++. rS�T
« + . . + + + + + + + + r +
++�. ++ + + + + + + ++ +
+ +`. . . p
+++ + + + + . +r ++ ++ +
• DOUBLE ROW OF SILT FENCE +++*+ +
+++ AT TOP OF BUFFER (T)P} +*
�+ )( \
::: + :�
+ ++ ++++++
EASoc TEMP. STREAM EMPACT: \
++++++++ SA, ND BAGS, #57 STONE & HOSE F
` 30rPEFA
��ULVERT PUMP AROUND (CHANNEL MAT
t55
JR BE RESTORED To
CONDITION
TION) UPONCOMPLE\ ;
`
STREAMPA�AC
TEMP+ STREAM IMPACT FOR PIPE PUMP AROUND: 20 LF
TEMP. STREAM IMPACT FOR PIPE: 4 LF
PERM. STREAM IMPACT FOR STREAM CROSSING: 10 LF
BUFFER IMPACT&
ALLOWABLE
HAPACC-0
CAMBRIDGE PARK - PHASE 1 A
STREAM HVIPACTS
MELVLLLE TOWNSEU—ALAMANCE COUNTY
MEBANE-NORTH CAROLINA
OCTOBER 29, 2018
w o 20 m e0
moll
inch -401L
Twins 4609 Dundas Drive
_ Inc.Greensboro,
E ina ngineering, INFxx331r854-SB76077
—Sin= 1974— Phone 33&854-8877
i Engin-m Surveyors Plrnners Firm License No.: C-0168
+ + + + + +++++ DOUBLE ROW OF SILT FENCE.'.'.'.'.1
* + ***+ AT TOP OF BUFFER (TYP)
+
♦ r ++++ .V + + + .+.+
+ + +++
r+F+++ ++T +. + ++ ++++ +�. + f+ ++ « f
♦+ ++'+.��,r *
.. + idM.iiAIaNTEN+NCiE.++++. . + . . CORRIDOR THRU ce + +. .. i+
++ +-
+ r+
.++ ++ +
++T+++.+++++*BUFFER •++
+ + . . . + + +
+ .+++++ + . . . + . + + +
10++0-YR+FIAODvP+++
+++ + + CRPSSING '- ,+
�T/
*
++++�+ + + . + +
+++f ++ + .+ 4 ++ +•++++++* f .y
i+.. +*
++ ++ +I
+ ++ + + + .+.++r.r.. .
+++ �
+ + L
+ + + A +
. ++++�r + +++ + F�+Y+ .+�. + + + +
++++
*+ �.. ., zow 7 p
LSS
JO. se �5� �1 , zp7ve T
.SE• R 6a � � ', •. ,�
DOUBLE ROW OF SILT FENCE Ec�ati T
AT TOP OF BUFFER (TYP)-
7R
5HM 7 OF 9
� w
Q
nTEMP. STREAM IMPACT+
�l SAND HAGS, ,#57 STONE & HOSE FOR
CULVERT PUMP AROUND (CHANNEL MUST
BE RESTORED TO EXISTING CONDITION
UPON COMPLETION)
IMPACT -5
CAMBRIDGE PARK - PHASE 1A
STREAM IMPACTS
STREAM IMPACTS:
TEMP. STREAM IMPACT FOR PIPE PUMP AROUND: 20 LF
MELVILLE TOWNSRW-ALAMANCE COUNTY
TEMP.STREAM IMPACT FOR PIPE: 4 LF
MEBANEr-NORTH CAROLINA
PERM. STREAM IMPACT FOR STREAM CROSSING: 10 LF
OCTOBER 29 2018
40 a 2e w w
BUFFER IMPACTS-.
ALLOWABLE
1 inch =dOFC.
4609 Dundas Drive
E moans Gaeenslwm,
— - North Carolina 27407
E+ nginee3ring, Inc. Fax 336.854-8676
---151.-1974— Phone 336.854-SB77
I Eng mcrs 5urvcyu- Plan m Firm License No.: C-0168
�OnlxmG5�0E8C0�ilIaHFR aoln\onArsr♦ 5\\ UR. A PMN— C[ D IYPALS A.
DOUBLE ROW OF SILT FENCE
AT TOP OF BUFFER (TYP)
PERMANENT STREAM
CROSSING
ti
TEMP. STREAM IMPACT:
SEE LITTLE HAW CREEK TEMPORARY
CROSSING DETAIL (CHANNEL MUST 8E
RESTORED TO EXISTING CONDITION UPON
COMPLETION)
STREAM IMPACTS:
TEMP. STREAM IMPACT FOR PIPE PUMP AROUND: 20 LF
TEMP. STREAM IMPACT FOR PIPE: 4 LF
PERM. STREAM IMPACT FOR STREAM CROSSING: 10 LF
SHEET OF
OUBLE ROW OF SILT FENCE
AT TOP OF BUFFER (TYP)
C
EMPAC -6
CAMBRIDGE PARK - PHASE 1A
STREAM IMPACTS
MF L,V [LLE TOWNSHIP--AI.AMANCE COUNTY
MBBANE-NORTH CAROLINA
OCTOBER 29.2018
40 0 29 40 so
BUFFER IMPACTS: 1 inch =40rt.
ALLOWABLE
_ Vari5 4609 Dundu Ddw
T Greensboro,
E ngineering, InC• F> 3 fr854.8876na 07
—&-1974— Phom33&854.8877
Engine m 8u eyom Planners Firm 13c."e Na.: C-0168
Pu -we Q WAMDROI
m
— 1 1-mr y
E J ELI
[ns.7
Wup
pEXvi [,ACX Y!O{Yi 10 IRIOt Rp �POEnnrnrx IIpK pE
PwP�a, p te)[ w11Y.1x 111DIIIR `� a R n�
SECTION A -A
TEMPORARY "PIPE CROSSING - PUMP AROUND"
FOR PIPE INSTALLATION
�sroNE ro 9[ i1Ki$ f RP-R!P YIELSS O[SNJIAi[➢ pFFEREN[Er ON
PUX.
91 RWv .wo u1E 9!E RI 6E L1Ep0YWm 91' IHC LblIpPMTOH V9w". THE 6YSE iIOX'
EVlptll ON 1HE WHYpRVCINH P4W5
da�Moem Dsw � s wi mHan of wm++ws w1ecH rnE Aclrrurt ro
IRIPMOLk WWiIpL tWenQ Ie10
m 4.E.. C iw0 WO,V. nwmr Rpyp1 io
Pia�vn vuuce MI wiErw �. aw+o. nNE ceA.xti Ena
(%M131RgI'LWN 5FOUENCE FOR PIPE CROSSING-NJUP ARf1URD
1 J NSEHf. p'11NF AND ME m nuw Er
FADY Xaa uP51RL1Y K i[YPOPARY
SRiEW Cwo 1 }O APG 7GRITXEAM OP A.'fPVCpIPH MIA 9pN FylsalNp IAD
[:OXCIKVIHC N"G Ne<U. N K•ND — THE 5mF
gVS,vn1
OMR1 W
C OW SCHE M AND 191. A F DD m �EW1i
flDw W 0 DCNSfRN"[14H MFA
sTIe1 PT1P03[O NO FF LE 1iO11G TOP W pW[ Ew1 spE of RIE
AEA
�f1] �-P-L-H� -Lu�.MRWif[H COXEILTPY, X[pm RV mp E PWS, Rim iasec. OEPR6S
•EMWkWi' [YJ1 BmNMP PHO SmEIM Em �wnE mP M RIP HM IS EC4L1 X'lp11
smEw Pu[iN.1.
e uFar+ �ire�uavnDN of cwran AVEw Awurc rEXronnm• uAm EEXM, sEwuEN[
. uro oEw.rEwno �.
A!1
V—mg
AJ
PLAN NEW
P►-1yrRy�e6'>'edE
��Cl�ac
SECiIGN A -A
rcax
,. PusuRPA m at :anumirra riim.
x se mwncr a nrrem PNf[ srtmanc niw FNgXr Mm 1m�-Pw u w1DK1E
PERIAAHENT STREAM CROSSING
NTS
gpRNEM cwArne� F W Xp
TMWP1aR � a IN[ Oµ.Xu, 11YA
yS�.L lll!A At m pEmW1 owLfe
tlfII
OmNflMA pEAMiO — �Cmlwo olmt
� �xE
wlunw EPW m Mm1u s1ACW � sosue.^Pv
r.>am smE oX
usm�ev. ilwl X1u Mut nnr
P°�"imc wnx wmRn Rurne ap
w�uou rrr
spin .vX1i
s. Iuiw Easmc ew++ aa.c
NTS
SHEET 9 OF 4
X,tmrlra I+ wi iwn u..m ,xE cMa�la.
9. }rpt`µ [trlslnuu pX sEWENcc� p�TNXOH ow
- °E:wn¢ sirrw wee ra eNE Pux
���y� PC YpgH[ a THE rnx69H¢ IAo
4.
raw mvmilsl �� o Ism mN � of 512 wEwHl..
rWWnTdI vcu�nlEs
••wFEni pwe o-vrm. 9PE a ME sil,Eua
�R9E o�iP11[sm� eu� �wPRMt ,ISI fa WI f� �
tih R� T¢ ci µYoeRs'cssw*1 .�
A PN'µnEw w n1E si1mM aE1Er_ eE wwuilu WR+� � �W4s of
lPK pinx 10 uwwRE nmXnr. n..rcis.
rxp�pl:wm v.1rt�i+x5 �peE � aMui MtA.� Nm
[%u'u.+1o1.s swr. at P1olnum m Ewowr. alwC.
xmpm fo PM1E� PS� Y�10 leml us� 1¢�'lI�e10
XAiDYµ 9AI nW nq Yminm SrnFAM MACH XXrca nt �AS[IR
�5
11D
==,M
yYpb'i 10 ��t u lusp fx
Cn►Kn 10 51IYH+ PYncs Mx m R Aimoxm m pn[-0koiA•.tY�W
AV[ ND KartWre.
F ALL [Gpuf2Fn 1?.:AS w�JrmiaYEnE�eFm�,mt� � H Imi+1[Im
Xn�wosrmlcio«°°Piwsr°N Al=nnia"'Ne. w eE
CrvE'1Eit OCiWEm 11niNbs vwi E RE4NLmfilo
pE-5¢i.n �c xuD�P
DEEAII,SHFEE
CAMBRIDGE PARK - PHASE IA
STREAM IMPACTS
MMVILLE TOWHSHP-ALAMANCE. COUNTY
MEBANE-NORTH CAROLINA
OCTOBER 29.2018
40 O so 40 e0
F in�•h =40ft
4609 Dundws D
vans rive
- - .E ngineering, Inc. North Carolina 276 oz
---31> 1474— Phaw 336.854-8877
Eri&x a Surveyors Planners Fp— Licr w No.-. C-0168
Pua-�u NrAcr m I
Action ID Number: SAW -2017-02329 County: Alamance
Permittee: Desco Holdings, LLC (Attn: Eric Dischinger)
Project Name: Cambridge Park / Turner Road / Mebane / Alamance County / residential
Date Verification Issued: 10/31/2018
Project Manager: David E. Bailey
Upon completion of the activity authorized by this permit and any mitigation required by the permit,
sign this certification and return it to the following address:
US ARMY CORPS OF ENGINEERS
WILMINGTON DISTRICT
Attn: David E. Bailey
Raleigh Regulatory Office
U.S Army Corps of Engineers
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
or
David.E.Bailey2 @usace.army.mil
Please note that your permitted activity is subject to a compliance inspection by a U. S. Army Corps of
Engineers representative. Failure to comply with any terms or conditions of this authorization may
result in the Corps suspending, modifying or revoking the authorization and/or issuing a Class I
administrative penalty, or initiating other appropriate legal action.
I hereby certify that the work authorized by the above referenced permit has been completed in
accordance with the terms and condition of the said permit, and required mitigation was completed in
accordance with the permit conditions.
Signature of Permittee
Date