Loading...
HomeMy WebLinkAbout20060264 Ver 1_COMPLETE FILE_20060224t. VP) , Progress Energy 10 60 26? February 15, 2006 Mr. Brad Shaver Regulatory Division U.S. Army Corps of Engineers - CESAW-RG-L P.O. Box 1890 Wilmington, NC 28402-1890 Q12 @ 1E oWF=p FFB 1 7 2006 DENF2 -HATER QUALITY WETLANDS AND 3TCRMWATER ERANICH Subject: Preconstruction Notification (Section 10 only) for Planned Uprate and Maintenance of Progress Energy Carolinas Existing Jacksonville - Jacksonville City East 115kV Transmission Line Dear Mr. Shaver: Progress Energy Carolinas (PEC) is planning to uprate the existing Jacksonville - Jacksonville City East 115kV overhead electric transmission line beginning in March of 2006. This line extends for approximately 4.4 miles from an existing substation generally north of Jacksonville to another existing substation generally south of Jacksonville near the mouth of Chaney Creek (Enclosure 1). While there are no discharges to jurisdictional waters, the line does cross two tidal creeks, and PEC is thus submitting a preconstruction notification (PCN, Enclosure 2), requesting Section 10 authorization for the proposed activity. The uprate will not involve replacing the conductors, but simply increasing the load (amperage) on the line. That increase will create additional sag in the overhead lines, and to comply with PEC's overhead clearances, nine replacement and two new structures will be installed. Those structures, including one three-pole angle structure, two single-pole structures and eight H-frame (two-pole) structures, will utilize steel to replace the existing wooden structures. For the navigable waters crossings, PEC has verified that the conductors, under conditions creating maximum sag, will provide the minimum 20 feet of clearance required for 115kV transmission lines, as measured over the existing bridge clearance. While clearances are provided over the stream channels, clearances over wetlands adjacent to the channels are somewhat less than the channel clearances. All clearances exceed applicable electric safety codes. PEC has conducted a wetlands delineation (Enclosure 3) and, as indicated, all structures will be placed on high ground; no structures or fill will be placed in wetlands or waters. Should PEC need to cross wetlands to access structures, mats or low ground pressure equipment will be used to avoid rutting or other impacts to wetlands. Progress Energy Carolinas, Inc. P.O. Box 1551 Raleigh, NC 27602 r' In addition to the uprate, PEC intends to conduct routine danger tree maintenance on the line. "Danger tree" maintenance involves selective cutting of any trees adjacent to, but outside of, the maintained right-of-way that have grown large enough to endanger the conductors or structures if the trees fell (e.g., during a storm). Trees are cut by hand, and either removed from the ROW or, if removal would damage any waters/wetlands, left on site. Trees left on the ROW will have limbs cut off and trunks will be aligned so as to not impede any flows. No debris will be placed or allowed to remain in any streams. As with all our transmission construction projects, PEC will monitor the work regularly to ensure compliance with all applicable environmental permits and regulations. PEC appreciates your cooperation on this project. If there are any questions or if you need additional information, please contact Mr. Buzz Bryson in our Environmental Services Section at 919-546-6637 (office), 919-812-1120 (cell) or via e-mail at buzz.bryson@p.gnmail.com. Very truly yours, RaLr ao_v Ray Davis, General Manager Transmission Construction & Engineering RD/wtb Enclosures: 1. Location Map 2. Overhead Clearances Maps (2) 3. Preconstruction Notification 4. Wetlands Delineation Maps c: NCDWQ - Courtesy Notification O U : t a I,' a0 Eo mE XI.- O a't 3 C ??m? 60 Deg. F dom i o Bottom NC 17 Bridge I mr , I 212 Deg. F ?? Over New River Elevation 14.42 Ft. 14.42 Feef Creek Channel 4.0 Feet MHW x Mean High Water 4.0 Feet 5} } • ` Per City Of Jacksonville f ? uVr 10 '0 u 11003s21.dgn 2/7/200611:42:46 AM I d%- 4- E Eo X~a xf'a O 3Ca ?c+- o o C5 + 6 oom ° o+oppo° ° me -2 > ui a> nOOfD MOOm I I I x I IY i O-Z I L. ELEV. Bottom NC 17 Bridge c o I? I ICI Over New River Elevation 14,42 Ft, _.-_I _-14,42 Feet. I L. - - - - - - - - - - - - - O r4.0 Feet UHW Mean High Water 4.0 Feet N Per City Of Jacksonville c? 4- ra ?. co 11003s21.dgn 2/7/2006 11:39:28 AM 19@gVgJ FEB 1 1 2006 .-1 IV Office Use Only: ?EN? Altrwvl Fonn Version March 05 .TS P110 STG t?ti TERSRpryCN USACE Action ID No. DWQ No. (If any particular item is not applicable to this project, please enter "Not Applicable" or "N/A".) 1. Processing 1. Check all of the approval(s) requested for this project: ? Section 404 Permit ? Riparian or Watershed Buffer Rules ® Section 10 Permit ? Isolated Wetland Permit from DWQ ® 401 Water Quality Certification ? Express 401 Water Quality Certification 2. Nationwide, Regional or General Permit Number(s) Requested: Nationwide 12 3. If this notification is solely a courtesy copy because written approval for the 401 Certification is not required, check here: 4. If payment into the North Carolina Ecosystem Enhancement Program (NCEEP) is proposed for mitigation of impacts, attach the acceptance letter from NCEEP, complete section VIII, and check here: ? 5. If your project is located in any of North Carolina's twenty coastal counties (listed on page 4), and the project is within a North Carolina Division of Coastal Management Area of Environmental Concern (see the top of page 2 for further details), check here: II. Applicant Information Owner/Applicant Information Name: Carolina Power & Light Company dba Progress Energy Carolinas Mailing Address: c/o RE Davis P.O. Box 1981, TPP 18 Raleigh, NC 27602-1891 Telephone Number: 919-546-4359 Fax Number: E-mail Address: ray.davis@12gnmail.com 2. Agent/Consultant Information (A signed and dated copy of the Agent Authorization letter must be attached if the Agent has signatory authority for the owner/applicant.) Name: William T. (Buzz) Bryson Company Affiliation: Progress Energy Service Company Mailing Address: 410 S. Wilmington Street, PEB 4A Raleigh, NC 27601 [Bryson is contact for permitting questions] Telephone Number: 919-546-6637 Fax Number: 919-546-4409 E-mail Address: buzz.brysonna,pgnmail.com Updated 11/1/2005 Page I of 9 III. Project Information 5. Attach a vicinity map clearly showing the location of the property with respect to local landmarks such as towns, rivers, and roads. Also provide a detailed site plan showing property boundaries and development plans in relation to surrounding properties. Both the vicinity map and site plan must include a scale and north arrow. The specific footprints of all buildings, impervious surfaces, or other facilities must be included. If possible, the maps and plans should include the appropriate USGS Topographic Quad Map and NRCS Soil Survey with the property boundaries outlined. Plan drawings, or other maps may be included at the applicant's discretion, so long as the property is clearly defined. For administrative and distribution purposes, the USACE requires information to be submitted on sheets no larger than 11 by 17-inch format; however, DWQ may accept paperwork of any size. DWQ prefers full-size construction drawings rather than a sequential sheet version of the full-size plans. If full-size plans are reduced to a small scale such that the final version is illegible, the applicant will be informed that the project has been placed on hold until decipherable maps are provided. 1. Name of project: Jacksonville -Jacksonville City East 115kV Transmission Line 2. T.I.P. Project Number or State Project Number (NCDOT Only): N/A 3. Property Identification Number (Tax PIN): Progress Energy does not own the right-of-way, but purchased easement rights only. Underlying ownership remains with the original adiacent property owner. 4. Location County: Onslow Nearest Town: Jacksonville Subdivision name (include phase/lot number): N/A Directions to site (include road numbers/names, landmarks, etc.): The line is existing and extends between existing_ substations near downtown Jacksonville, as shown on attached maps and can be accessed from several city streets and secondary roads. Site coordinates (For linear projects, such as a road or utility line, separately lists the coordinates for each crossing of a distinct waterbody.) Decimal Degrees (6 digits minimum): Attached ON 6. Property size (acres): Existing right-of-way encompasses approximately 53 acres 7. Name of nearest receiving body of water: Mill Creek, Chaney Creek, New River 8. River Basin: New River (Note - this must be one of North Carolina's seventeen designated major river basins. The River Basin map is available at http:Hh2o.enr.state.ne.us/admin/maps/.) attach a sheet that ow Updated 11/1/2005 Page 2 of 9 9. Describe the existing conditions on the site and general land use in the vicinity of the project at the time of this application: Existing line and right-of-way passes through largely developed areas in and adjacent to Jacksonville. 10. Describe the overall project in detail, including the type of equipment to be used: The proiect involved "uprating" the existing line by replacing nine and adding two new structures, to meet current overhead clearance specifications. At the same time, routine danger tree maintenance cutting will be performed. None of the new or replacement structures are in wetlands or waters, and there will be no discharges to waters. Should access to structures require crossing wetlands, mats or low ground pressure equipment will be used. Minimum clearances required for Section 10 crossings will be ensured. 11. Explain the purpose of the proposed work: Uprating involves passing more electricity (amperage) through the lines (conductors). The conductors themselves will not be replaced, nor will the majority of the structures. "Danger tree" maintenance involves selective cutting of any trees adjacent to, but outside of, the maintained right-of-way that have grown large enough to endanger the conductors or structures if the trees fell (e.g., during a storm). IV. Prior Project History If jurisdictional determinations and/or permits have been requested and/or obtained for this project (including all prior phases of the same subdivision) in the past, please explain. Include the USACE Action ID Number, DWQ Project Number, application date, and date permits and certifications were issued or withdrawn. Provide photocopies of previously issued permits, certifications or other useful information. Describe previously approved wetland, stream and buffer impacts, along with associated mitigation (where applicable). If this is a NCDOT project, list and describe permits issued for prior segments of the same T.I.P. project, along with construction schedules. Progress Energy bought this already-constructed line many decades ago, and has not obtained any permits previously. V. Future Project Plans Are any future permit requests anticipated for this project? If so, describe the anticipated work, and provide justification for the exclusion of this work from the current application. No future permits are anticipated for this project. Updated 11/1/2005 Page 3 of 9 VI. Proposed Impacts to Waters of the United States/Waters of the State It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to wetlands, open water, and stream channels associated with the project. Each impact must be listed separately in the tables below (e.g., culvert installation should be listed separately from riprap dissipater pads). Be sure to indicate if an impact is temporary. All proposed impacts, permanent and temporary, must be listed, and must be labeled and clearly identifiable on an accompanying site plan. All wetlands and waters, and all streams (intermittent and perennial) should be shown on a delineation map, whether or not impacts are proposed to these systems. Wetland and stream evaluation and delineation forms should be included as appropriate. Photographs may be included at the applicant's discretion. If this proposed impact is strictly for wetland or stream mitigation, list and describe the impact in Section VIII below. If additional space is needed for listing or description, please attach a separate sheet. 1. Provide a written description of the proposed impacts: No wetlands impacts are anticipated. The project already exists. The proposed new and replacement structures will all be located outside of jurisdictional wetlands. Any access across wetlands will utilize mats or low ground pressure equipment 2. Individually list wetland impacts. Types of impacts include, but are not limited to mechanized clearing, grading, fill, excavation, flooding, ditching/drainage, etc. For dams, separately list impacts due to both structure and flooding. Wetland Impact Site Number (indicate on map) Type of Impact Type of Wetland (e.g., forested, marsh, herbaceous, bog, etc.) Located within 100-year Floodplain ( es/no) Distance to Nearest Stream (linear feet Area of Impact (acres) N/A Total Wetland Impact (acres) N/A 3. List the total acreage (estimated) of all existing wetlands on the property: 23.8 acres Updated 11/1/2005 Page 4 of 9 4. Individually list all intermittent and perennial stream impacts. Be sure to identify temporary impacts. Stream impacts include, but are not limited to placement of fill or culverts, dam construction, flooding, relocation, stabilization activities (e.g., cement walls, rip-rap, crib walls, gabions, etc.), excavation, ditching/straightening, etc. If stream relocation is proposed, plans and profiles showing the linear footprint for both the original and relocated streams must be included. To calculate acreage, multiply length X width, then divide by 43,560. Stream Impact Number (indicate on ma) Stream Name Type of Impact Perennial or Intermittent? Average Stream Width Before Impact Impact Length (linear feet Area of Impact (acres) S-2a and 2b Mill Creek Overhead crossing Perennial 76 & 125 feet N/A N/A S-4 Chaney Creek Overhead crossing Perennial 172 feet N/A N/A Total Stream Impact (by length and acreage) N/A N/A 5. Individually list all open water impacts (including lakes, ponds, estuaries, sounds, Atlantic Ocean and any other water of the U.S.). Open water impacts include, but are not limited to fill. excavation, dredaina, flooding, drainage, bulkheads, etc. Open Water Impact Site Number (indicate on map) Name of Waterbody (if applicable) Type of Impact Type of Waterbody (lake, pond, estuary, sound, bay, ocean, etc.) Area of Impact (acres) N/A Total Open Water Impact (acres) N/A 6. List the cumulative im act to all Waters of the U.S. resulting from the project: Stream Im act (acres): N/A Wetland Impact (acres): N/A Open Water Impact (acres): N/A Total Impact to Waters of the U.S. (acres) N/A Total Stream Impact (linear feet): N/A 7. Isolated Waters Do any isolated waters exist on the property? ? Yes ® No Describe all impacts to isolated waters, and include the type of water (wetland or stream) and the size of the proposed impact (acres or linear feet). Please note that this section only applies to waters that have specifically been determined to be isolated by the USACE. Updated 11/1/2005 Page 5 of 9 8. Pond Creation If construction of a pond is proposed, associated wetland and stream impacts should be included above in the wetland and stream impact sections. Also, the proposed pond should be described here and illustrated on any maps included with this application. Pond to be created in (check all that apply): ? uplands ? stream ? wetlands Describe the method of construction (e.g., dam/embankment, excavation, installation of draw-down valve or spillway, etc.): N/A Proposed use or purpose of pond (e.g., livestock watering, irrigation, aesthetic, trout pond, local stormwater requirement, etc.): N/A Current land use in the vicinity of the pond: N/A Size of watershed draining to pond: N/A Expected pond surface area: N/A VII. Impact Justification (Avoidance and Minimization) Specifically describe measures taken to avoid the proposed impacts. It may be useful to provide information related to site constraints such as topography, building ordinances, accessibility, and financial viability of the project. The applicant may attach drawings of alternative, lower-impact site layouts, and explain why these design options were not feasible. Also discuss how impacts were minimized once the desired site plan was developed. If applicable, discuss construction techniques to be followed during construction to reduce impacts. The project consists of "upratin " an existing line and conducting routine periodic danger tree maintenance. The footprint of the right-of-way will not be expanded. New and replacement structures will be used only to raise the line to meet required ground clearances. No structures will be placed in wetlands or waters Any access across wetlands will utilize mats or low ground pressure equipment No roads will be built. VIII. Mitigation DWQ - In accordance with 15A NCAC 2H .0500, mitigation may be required by the NC Division of Water Quality for projects involving greater than or equal to one acre of impacts to freshwater wetlands or greater than or equal to 150 linear feet of total impacts to perennial streams. USACE - In accordance with the Final Notice of Issuance and Modification of Nationwide Permits, published in the Federal Register on January 15, 2002, mitigation will be required when necessary to ensure that adverse effects to the aquatic environment are minimal. Factors including size and type of proposed impact and function and relative value of the impacted aquatic resource will be considered in determining acceptability of appropriate and practicable mitigation as proposed. Examples of mitigation that may be appropriate and practicable include, but are not limited to: reducing the size of the project; establishing and maintaining wetland and/or upland vegetated buffers to protect open waters such as streams; and replacing losses of aquatic resource functions and values by creating, restoring, enhancing, or preserving similar functions and values, preferable in the same watershed. Updated 11/1/2005 Page 6 of 9 If mitigation is required for this project, a copy of the mitigation plan must be attached in order for USACE or DWQ to consider the application complete for processing. Any application lacking a required mitigation plan or NCEEP concurrence shall be placed on hold as incomplete. An applicant may also choose to review the current guidelines for stream restoration in DWQ's Draft Technical Guide for Stream Work in North Carolina, available at http://h2o.enr.state.nc.us/ncwetlands/stnngide.html. Provide a brief description of the proposed mitigation plan. The description should provide as much information as possible, including, but not limited to: site location (attach directions and/or map, if offsite), affected stream and river basin, type and amount (acreage/linear feet) of mitigation proposed (restoration, enhancement, creation, or preservation), a plan view, preservation mechanism (e.g., deed restrictions, conservation easement, etc.), and a description of the current site conditions and proposed method of construction. Please attach a separate sheet if more space is needed. No mitigation is planned since there are no impacts to waters or wetlands, and project is requesting only Section 10 and CAMA approvals 2. Mitigation may also be made by payment into the North Carolina Ecosystem Enhancement Program (NCEEP). Please note it is the applicant's responsibility to contact the NCEEP at (919) 715-0476 to determine availability, and written approval from the NCEEP indicating that they are will to accept payment for the mitigation must be attached to this form. For additional information regarding the application process for the NCEEP, check the NCEEP website at http://h2o.enr.state.ne.us/wrp/index.htm. If use of the NCEEP is proposed, please check the appropriate box on page five and provide the following information: Amount of stream mitigation requested (linear feet): N/A Amount of buffer mitigation requested (square feet): N/A Amount of Riparian wetland mitigation requested (acres): N/A Amount of Non-riparian wetland mitigation requested (acres): N/A Amount of Coastal wetland mitigation requested (acres): N/A IX. Environmental Documentation (required by DWQ) Does the project involve an expenditure of public (federal/state/local) funds or the use of public (federal/state) land? Yes ? No 2. If yes, does the project require preparation of an environmental document pursuant to the requirements of the National or North Carolina Environmental Policy Act (NEPA/SEPA)? Note: If you are not sure whether a NEPA/SEPA document is required, call the SEPA coordinator at (919) 733-5083 to review current thresholds for environmental documentation. Yes ? No ? 3. If yes, has the document review been finalized by the State Clearinghouse? If so, please attach a copy of the NEPA or SEPA final approval letter. Yes ? No ? Updated 11/12005 Page 7 of 9 X. Proposed Impacts on Riparian and Watershed Buffers (required by DWQ) It is the applicant's (or agent's) responsibility to determine, delineate and map all impacts to required state and local buffers associated with the project. The applicant must also provide justification for these impacts in Section VII above. All proposed impacts must be listed herein, and must be clearly identifiable on the accompanying site plan. All buffers must be shown on a map, whether or not impacts are proposed to the buffers. Correspondence from the DWQ Regional Office may be included as appropriate. Photographs may also be included at the applicant's discretion. 1. Will the project impact protected riparian buffers identified within 15A NCAC 2B .0233 (Meuse), 15A NCAC 2B .0259 (Tar-Pamlico), 15A NCAC 02B .0243 (Catawba) 15A NCAC 2B .0250 (Randleman Rules and Water Supply Buffer Requirements), or other (please identify )? Yes ? No 2. If "yes", identify the square feet and acreage of impact to each zone of the riparian buffers. If buffer mitigation is required calculate the required amount of mitigation by applying the buffer multipliers. * Impact Required Zone Multiplier 3 (2 for Catawba) 1.5 Total I I * Zone I extends out 30 feet perpendicular from the top of the near bank of channel; Zone 2 extends an additional 20 feet from the edge of Zone 1. 3. If buffer mitigation is required, please discuss what type of mitigation is proposed (i.e., Donation of Property, Riparian Buffer Restoration / Enhancement, or Payment into the Riparian Buffer Restoration Fund). Please attach all appropriate information as identified within 15A NCAC 2B .0242 or .0244, or .0260. N/A XI. Stormwater (required by DWQ) Describe impervious acreage (existing and proposed) versus total acreage on the site. Discuss stormwater controls proposed in order to protect surface waters and wetlands downstream from the property. If percent impervious surface exceeds 20%, please provide calculations demonstrating total proposed impervious level. The project involves replacement of nine existinp, structures and the addition of two new structures. There is no other impervious surface on this line The total "footprint" of the two additional structures is approximately six square feet. Updated 11/1/2005 Page 8 of 9 XII. Sewage Disposal (required by DWQ) Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of wastewater generated from the proposed project, or available capacity of the subject facility. N/A XIII. Violations (required by DWQ) Is this site in violation of DWQ Wetland Rules (15A NCAC 2H.0500) or any Buffer Rules? Yes ? No Is this an after-the-fact permit application? Yes ? No XIV. Cumulative Impacts (required by DWQ) Will this project (based on past and reasonably anticipated future impacts) result in additional development, which could impact nearby downstream water quality? Yes ? No If yes, please submit a qualitative or quantitative cumulative impact analysis in accordance with the most recent North Carolina Division of Water Quality policy posted on our website at http://h2o.enr.state.nc.us/ncwetlands. If no, please provide a short narrative description: The line uprating and structure replacement and the danger tree maintenance, are intended to meet existing electricity demands XV. Other Circumstances (Optional): It is the applicant's responsibility to submit the application sufficiently in advance of desired construction dates to allow processing time for these permits. However, an applicant may choose to list constraints associated with construction or sequencing that may impose limits on work schedules (e.g., draw-down schedules for lakes, dates associated with Endangered and Threatened Species, accessibility problems, or other issues outside of the applicant's control). - pa Q ,/ , 2-1141,-40 Applicant/Agent's Signature V Date (Agent's signature is valid only if an authorization letter from the applicant is provided.) Updated 11/1/2005 Page 9 of 9 Navigable Waters Crossings Site Coordinates ° North ° West Chaney Creek 34.758019 -77.427492 Mill Creek 34.765228 -77.423403 Radio Tower + N + *+ : • i * { 1 ' jJ?l t kt ?1 A. TIC ?. US C( (let TC. WNW \ \ .? i ,? ••r 1. ]. ' ' r -».•? 1 i ? / v ?: ?? i i i ,i ? lit n,. ( , t?. r`.?? 1" i; ? `j{ 1?, ,•u..., i 4 SS , N34° 48' 23" Roper ,fry ''? ' f Approximate Easement ~ Boundary Line Sheet 2 Sheet I of 3 Quadrangle Name Jacksonville North Field Work And Graphics By' Propareo Date Onslow County, NC Environmental Services. Inc Novemttar2005 0 500 1000 Environmental Services, Inc. 624 South New Hope Road Raleigh. North Carolina 27610 Scale In Feet C and N h Energy 15W +4S' 11 Match Line Sheet 1 ?••' ' ,'?'' ?1 FEB 1 7 2006 ?( i `•? Z ?i ?• QENk - WATEF2 UUALITY N f f , ej • ?? K > DS AND STORMWATER B 7/ 03 •: ? • I ?, •? SSS i i jl ? I f ` i AM- % • _ /?' + • ? ? ?, i ? T yam, l,? UbSta ! V •i M ? Approximate Easement ?` `` ••'+•• + • a ??„ ;/ ?/; Boundary Match Lint Shot 3 if f I Sheet 2 of 3 Quadrangle Name F Jacksonville North progress Energy Fuld Work And Graphics By, Prepared Date Onslow County, NC Fnv ronmentoi Services, hx: November 200b o Soo 1000 Jacksonville 115 kV 1drk Ail Environmental Services. Inc. .-{""Offill Transmission Line Project 624 South New Hope Road Raleigh, North Carolina 27610 ScebmFeet Wetland and Stream Identification i1 h, Sheet 3 of 3- I Quadrangle Name Jacksonville North progress Energy Frew Work And Craplua ay Props halo. OnsloW County, NC 5 ? Ernironmental Services. Inc Novomber 2L ] Jacksonville 115 W Environmental Services, Inc. 624 South New Hope Road Raleigh, North Gro 4 27610 o BOG ,wo Scale In Feel Transmission Line Project Wetland and Stream Identification WO' ?U Sheet 1: Detail 1 1998 CIR Image Jacksonville North progress Energy Feld `hark And Graphite By PrapaE bate Onslow County, NC Environmental Eer-Ams. Inc Novamrwf 2005 Environmental services. Inc. AV 524 South New Hope Road Raleigh. North Carolina relo 0 lip aoo ? l Scale to Feel Jacksonville 115 kV Transmission Line Project Wetland and Stream Identification LM ?? FEB 1 7 2006 ?r y 1T t o Mill Creek 'ere al nn ; ---- Approximate Easement Boundary z ;a ;0;, - + IA ty [ Jurisdictional Wetland CAMA Wetland ;: ?• ?,rA + =„,a - Jurisdictional Stream 1 ?. ;~, • t,r --- Approximate Jurisdictional Stream 4 '•? ;^? Jurisdictional Surface Water A -1 is i Sheet 3: Detail 1 1998 CIR Image Jacksonville North Progress Energy F,eid'NOrk Ana G,apmcs By Prepared Date' OnsloW County, NC Envronmenta semces Inc November 2005 o Soo 1000 Jacksonville 115 kV 'RhAV Environmental Services, inc. Transmission Line Project 524 South New Hope Road Raleigh, North Carolina 27610 Scab u: Feel Wetland and Stream Identification i it Ill Creek erennial ridth: 76 Mill Creek Pr;rennial y+ A f A iO% I tr r Chaney (rra k?; s "Perennial « of 1 r' ' "Width- 172 ft ' r - Approximate Easement Boundary l Jurisdictional Wetland CAMA Wetland ' . - Jurisdictional Stream --- Approximate Jurisdictional Stream ?, ?- . L Jurisdictional Surface Water Sheet 3: Detail 2 1998 CIR Image Jacksonville North Progress Energy rigid `cork Arid Grapnics riy trraparea Data, onslow County, NC Environmental Services, Inc November 2005 0 250 500 Jacksonville 115 kV *WE Environmental Services, Inc.-'' Transmission Line Project ti24 South Now Hope Road Raleigh, North Carolina 27610 $010111 Feel Wetland and Stream Identification I 6