From: Cahoon, Steve <Steve.Cahoon@duke-energy.com>
Sent: Monday, September 24, 2018 1:38 PM
To: Wicker, Henry M Jr CIV USARMY CESAW (US)
Cc: McLendon, C S CIV USARMY CESAW (US); Higgins, Karen
Subject: [External] RE: Emergency Permit request instructions
Attachments: IMG_0002jpg; Sutton Road.pptx; Vicinity mapjpg; Cooling pond weir
construction.docx
CAUTION: External email. Do not click links or open attachments unless verified. Send all suspicious email as an
attachment to Report Spam.<mailto:report.spam@nc.gov>
Good Afternoon Henry,
Information as requested. Please let me know if you have any questions or need further information.
Steve
-----Original Message -----
From: Wicker, Henry M Jr CIV USARMY CESAW (US) [mai Ito: Henry. M.Wicker.J R@usace.army.mi1]
Sent: Monday, September 24, 2018 11:08 AM
To: Cahoon, Steve
Cc: McLendon, C S CIV USARMY CESAW (US)
Subject: Emergency Permit request instructions
*** Exercise caution. This is an EXTERNAL email. DO NOT open attachments or click links from unknown senders or
unexpected email. ***
Steve,
Please see the attached memo on how to process emergency permit request. You will need to provide the information
that is identified in Section C (1) (2) and (3) back to me. Once I get the required information to confirm it meets the
Emergency Permit Requirements I will provide you with an E-mail stating you have authorization to do the work under
emergency permitting.
Let me know if you have any questions.
Thanks,
Henry
-----Original Message -----
From: Cahoon, Steve [mailto:Steve.Cahoon@duke-energy.com]
Sent: Monday, September 24, 2018 10:36 AM
To: Higgins, Karen (karen.higgins@ncdenr.gov) <karen.higgins@ncdenr.gov>; Wicker, Henry M Jr CIV USARMY CESAW
(US) <Henry.M.Wicker.JR@usace.army.mil>
1
Subject: [Non-DoD Source] FW: Scanned from a Xerox Multifunction Printer
Plan view and cross section.
-----Original Message -----
From: NCI5NEP1@duke-energy.com [mailto:NC15NEP1@duke-energy.com]
Sent: Monday, September 24, 2018 10:33 AM
To: Cahoon, Steve
Subject: Scanned from a Xerox Multifunction Printer
Please open the attached document. It was scanned and sent to you using a Xerox Multifunction Printer.
Attachment File Type: pdf, Multi -Page
Multifunction Printer Location: NCRH 15th floor Device Name: NC15NEP1
For more information on Xerox products and solutions, please visit Blockedhttp://www.xerox.com
Sutton Energy Complex
A
0o earthgie
n�&l
OF .,,I
WO, '. �-m
F RIOAY SATURDAY
Sutton Energy Complex - Emergency Weir Construction
1) Name of Responsible Party - Duke Energy Progress LLC
Bill Forster (919) 429-0361
2) Work Description
a. Construct a 6 foot rock emergency weir within the intake canal upstream of the
breach to isolate Sutton Cooling pond from the Cape Fear River breach
Begin construction of emergency weir on 9/24 as the window to complete
construction prior to river levels potentially draining large portion of pond is 24 to 48
hours based on current NOAA forecast
b. Project will use dump trucks and heavy equipment to place #57 stone, rip rap and
geotextile to construct a 130 foot long 6 foot high 15 foot wide weir (at the top), the
weir is trapezoidal in shape and larger at the base. There will be approximately 650
cubic yards of material placed below the OHWM. The weir will be removed once the
permanent repair to the cooling lake dam is completed.
c. Dredging — No dredging will be performed
d. Filling of Wetlands — No wetlands will be filled, only impact is to open water
e. Please see the attached Plan view and cross section drawing
f. Please see the attached vicinity map
3) Duke Energy will
a. Provide any mitigation required by the Corps of Engineers
b. Duke Energy will perform all work in a manner that would avoid and minimize
impacts to waters of the US, including wetlands to the maximum extent practicle
c. All work will cease should historic or cultural resources be discovered and the Corps
and the State Historic Preservation Officer would be immediately notified
d. No impacts will occur to threatened or endangered species due to this work
e. All work will be done in an expeditious manner
f. There are no areas of temporary fill associated with the project.