HomeMy WebLinkAboutNC0032867_NOV Response_20180911Malik's International, Inc.
400 Dixon School Road
Kings Mountain, NC 28086-8203
September 11, 2018
Mr. W. Corey Basinger, Regional Supervisor
Mooresville Regional Office
NC DEQ Division of Water Resources
610 East Center Avenue, Suite 301
Mooresville, NC 28115
RECEIVEDINCOENRIDWR
SEP 12 2018
WQROS
MOORESVILLE REGIONAL OFFICE
Subject: Notice of Violation, Kings Mountain Travel Plaza, NPDES permit NCO032867
Cleveland County
Dear Mr. Basinger:
This is our response to the post -inspection letter of August 15, 2018 and provides the action plan
and schedule that you requested. An action plan prepared by the operators is attached. Kings
Mountain Travel Plaza will complete work as described in the attached plan by the dates indicated in
the following list of items from the Notice of Violation.
1. Two septic tanks — repair leaks and connection piping
August 1, 2019
2. Inactive aeration basins — install blowers and grating
May 1, 2019
3. Aerobic digester and holding tank leaks and repair — inspect and repair
January 1, 2019
4. Flow meter chart recorder — repair and put in operation
October 15, 2018
5. Right-of-way to the outfall 001- cleating and inspection
November 1, 2018
We look forward to continued discussion of these items if required and ask for your patience while
we work through them.
Sincerely,
Laeeq Khan, President
Cc: Dan Dougherty, ORC
INTERIM MAINTENANCE AND OPERATION REPORT
Action Items from 8/9/2018 Inspection and Permit NCO032867 latest revision
Kings Mountain Travel Plaza
September 3, 2018
1) Repair leak in septic tanks and connect piping to allow operation.
The two septic tanks previously used as oil and grease separators at the plant influent have leaks in
the horizontal seams between the two tanks. On the last pump event for the tank contents it was
found that wastewater leaked from the tanks causing a public health issue and uncontrolled
discharge. The leaks must be stopped and the septic tanks are listed in the new permit, therefore,
they must be available for use. A schedule and budget should be prepared for this work as well as
the other numbered items below.
Repairing the tanks and sealing the leaks may require entry into the tanks or their removal and
replacement. Regardless of the leaks, the tanks need new access lids. The contents of the tanks
must be removed in order to proceed with the work. The piping at the influent must be modified to
connect the tanks with a by-pass. Following are the leak repair options in ascending order of effort
and cost:
(A) Hand auger between the tanks, check for leak location, and attempt to seal with external
application of bentonite clay and/or expansive concrete. This step is recommended and is
expected to entail the lowest cost. The tanks will be filled with water and the repair check by
observing the tank levels. The operators can provide the effort to do this work. If the work
is not successful and the leakage continues, it will be necessary to proceed with the other
options.
(B) Clean the tanks and enter to apply sealing material on the inside of the tanks horizontal
seam. This work could be done by the operators or an outside contractor.
(C) Remove existing tanks and install new tanks. This option will incur the highest cost but
would allow the position of the tanks to be moved back so that the connecting piping can be
more easily installed at the influent. The work would require an outside contractor.
2) Install new blowers in the inactive aeration basin and repair grating to make safe
The blowers for this aeration basin were removed at some time in the past and used on the active
basin. The housing for the blowers and the motors remain. Any equipment or piping including the
electrical system, motors, and diffusers must be inspected and replaced as necessary. New or used
blowers of the correct size must be acquired and installed. The operators can assist with inspection
and locating a source for new blowers. Installing the motors will require an outside contractor
The repairs made to the grating on the unit were found to be unsatisfactory at the DEQ annual
inspection and the grating over the aeration basin should be replaced completely.
3) Check for leaks in the upper septic tanks and repair as needed
This item is less intensive and may not require a large effort outside of operator time. However, the
lids on the septic tanks need replacement. Other leaks that may be identified including stormwater
leakage to fill the tanks undesirably must be repaired.
4) Clear the right-of-way to Outfall 001 and maintain during the year.
The operators have already worked on this item. We found heavy growth of kudzu near the lower
turn to the west of the outfall piping. We can continue to work on this item and using Dan
Dougherty's equipment clear the route to the outfall if you provide the necessary financial backing
by paying promptly for time spent and in advance for estimated costs. As you ate aware, we do the
yard maintenance inside the fence at the wastewater plant. Right-of-way maintenance is an extra
expense that should now be addressed.
We have not been able to identify the exact route of piping from the plant to the outfall after
repeated checks. In order to assure that the piping is intact, we will need to better determine the
pipe route and check flow at the outfall to verify the absence of leak in the system.
5) Repair the flow meter and weir box on the effluent near the chlorine contact basin
The weir box had a leak under the weir plate that required repair. The flow recorder needs to be
made functional with recorder strip chart and annual calibration. This flow recorder is obsolete and
consideration should be given to replacement.
6) Other items — mentioned in the inspection report by DEQ or Operator observations
The plant lighting should be upgraded to allow night time work in the event of failure or schedule
necessity. At present, the existing lighting outside the shed is not functional and the fixtures are
insufficient for work on the flow meter and other locations in the plant. Some of the outlets do not
work or are infested with fire ants causing difficulty in their use. It is recommended to add an
overhead spotlight near the influent and raise the light fixture at the shed.
A file system should be created at the truck stop office for records related to the wastewater plant
operation and maintained by the local site manager with the assistance of the operators. An account
should be set up with Blue Book or other suppliers to allow the operators to order disinfection
tablets and other supplies on a regular basis.