HomeMy WebLinkAbout20181215 Ver 1_CAMA Application_20180830Coastal Management
ENVIRONMENTAL QUALITY
August 28, 2018
MEMORANDUM:
TO:
FROM:
SUBJECT:
Applicant:
20181215
Karen Higgins
Div. of Water Resources
Gregg Bodnar
Major Permits Processing Coordinator
CAMA Permit Application Review
Horizon East LLC
Project Location: Tidal Bluff Court, Pelletier NC 28584
ROY COOPER
Governor
MICHAEL S. REGAN
Secretary
BRAXTON C. DAVIS
Director
Proposed Project: To construct a six slip docking facility to serve an existing six lot subdivision
(Tidal Bluff)
Please indicate below your agency's position or viewpoint on the proposed project and return this form by
September 18, 2018. If you have any questions regarding the proposed project, please contact Gregg
Bodnar, Permit officer at (252) 808-2808. When appropriate, in-depth comments with supporting data is
requested.
REPLY: This agency has no objection to the project as proposed.
This agency has no comment on the proposed project.
This agency approves of the project only if the recommended changes are
incorporated. See attached.
This agency objects to the project for reasons described in the attached comments.
SIGNED DATE
State of North Carolina I Environmental Quality I Coastal Management
Morehead City Office 1 400 Commerce Avenue I Morehead City, NC 28557
252 808 2808
DCM MP -1
APPLICATION for
Maier Development Permit
(last revised 12/27/06)
North Carolina DIVISION OF COASTAL MANAGEMENT
1. Primary Applicant/ Landowner Information
Business Name
Project Name (if applicable)
Horizons East, Llc
Tidal Bluffs
Bell & Phillips Surveying, Pllc
Applicant 1: First Name
MI
Last Name
Agent/ Contractor 1: First Name
Jennifer
M.
Ward
Cyrus
Applicant 2: First Name
MI
Last Name
Agent/ Contractor 2: First Name
If additional applicants, please attach an additional page(s) with names listed.
Last Name
Mailing Address
PO Box
City
PO Box
State
104 Garnet Lane
604E Cedar Point Blvd.
Jacksonville
N.C.
ZIP
Country
Phone No.
Phone No. 1
FAX No.
28540
USA
910 - 459 - 9129 ext.
910 - 346 - 1895
Street Address (if different from above)
City
State
- ext.
ZIP
Same as Above
252 393 3522
-
Email
Street Address (if different from above)
Jennifer@horizon seastbuildingco.com
City
State
2. Agent/Contractor Information
Business Name
Bell & Phillips Surveying, Pllc
Agent/ Contractor 1: First Name
MI
Last Name
Cyrus
A.
Bell
Agent/ Contractor 2: First Name
MI
Last Name
Mailing Address
PO Box
City
State
604E Cedar Point Blvd.
Cedar Point
N.C.
ZIP
Phone No. 1
Phone No. 2
28584
252 - 393 - 6101
ext.
- ext.
FAX No.
Contractor #
252 393 3522
Street Address (if different from above)
City
State
ZIP
Same
-
Email
alanbell@eastnc.twcbc.com
RECEIVED
<Form continues on back>
+SAY 14 2018
3 -MHD CITY
252-808-2808 .. 1-888-4RCOAST .. www.nccoastalroanagernent.net
Form DCM MP -1 (Page 2 of 4)
APPLICATION for
Major Development Permit
3. Project Location
County (can be multiple)
Street Address
State Rd. #
Carteret
Tidal Bluffs Ct.
375'
Subdivision Name
City
State
Zip
Tidal Bluffs
Peletier
N. C.
28584 -
Phone No.
Lot No.(s) (if many, attach additional page with list)
910 - 459 - 9129 ext.
#1, #2, #3, #4, #5 & #6
a. In which NC river basin is the project located?
b. Name of body of water nearest to proposed project
White Oak
Pettiford Creek Bay
c. Is the water body identified in (b) above, natural or manmade?
d. Name the closest major water body to the proposed project site.
®Natural ❑Manmade ❑Unknown
White Oak River
e. Is proposed work within city limits or planning jurisdiction?
f. If applicable, list the planning jurisdiction or city limit the proposed
®Yes ❑No
work falls within.
i. Is the proposed project consistent with the applicable zoning?
Peletier
4.
Site Description
a.
Total length of shoreline on the tract (ft.)
b. Size of entire tract (sq.ft.)
375'
235,224 Sq. Ft.
c.
Size of individual lot(s)
d. Approximate elevation of tract above NHW (normal high water) or
See attached,
NWL (normal water level)
(If many lot sizes, please attach additional page with a list)
10' ®NHW or ❑NWL
e.
Vegetation on tract
Sparce trees & grass on uplands, Typical wetland and coastal wetland species in wetlands
f.
Man-made features and uses now on tract
Tidal Bluffs Ct. is a paved street. Lots are vacant.
g.
Identify and describe the existing land uses adjacent to the proposed project site.
Single family residence to the north and south, vacant land to the east
h.
How does local government zone the tract?
i. Is the proposed project consistent with the applicable zoning?
R-20
(Attach zoning compliance certificate, if applicable)
®Yes ❑No [INA
j.
Is the proposed activity part of an urban waterfront redevelopment proposal? ❑Yes ®No
k.
Hasa professional archaeological assessment been done for the tract? If yes, attach a copy. []Yes ®No ❑NA
If yes, by whom?
I.
Is the proposed project located in a National Registered Historic District or does it involve a ❑Yes ®No ❑NA
National Register listed or eligible property?
<Form continues on next page>
252-808-2808 :. 1-888-4RCOAST :: www.nccoastalmanagernent.net
Form DCM MP -1 (Page 3 of 4)
APPLICATION for
Major Development Permit
m. (i) Are there wetlands on the site? ®Yes ®No
(ii) Are there coastal wetlands on the site? ®Yes ®No
(iii) If yes to either (i) or (ii) above, has a delineation been conducted? ®Yes ❑No
(Attach documentation, if available)
n. Describe existing wastewater treatment facilities.
Common Conventional single family residential septic system, not installed
o. Describe existing drinking water supply source.
West Carteret Water Corp.
p. Describe existing storm water management or treatment systems.
Natural run-off, Low density stormwater permit
5. Activities and Impacts
a.
Will the project be for commercial, public, or private use?
❑Commercial ❑Public/Government
®Private/Community
b.
Give a brief description of purpose, use, and daily operations of the project when complete.
The pier and boat lifts are intended for private use by the future residents of Lots 1-6,
Tidal Bluffs.
c.
Describe the proposed construction methodology, types of construction equipment to be used during construction, the number of each type
of equipment and where it is to be stored.
The pilings will be vibrated in. A barge will be used for accessibility and portable generator for electric supply.
d.
List all development activities you propose.
Construction of 579' of pier and Installation of six boat lifts.
e.
Are the proposed activities maintenance of an existing project, new work, or both?
New work
f.
What is the approximate total disturbed land area resulting from the proposed project?
4,000 ®Sq.Ft or []Acres
g.
Will the proposed project encroach on any public easement, public accessway or other area
❑Yes ®No ❑NA
that the public has established use of?
h.
Describe location and type of existing and proposed discharges to waters of the state.
There are no proposed and no existing discharges to waters of the state
i.
Will wastewater or stormwater be discharged into a wetland?
❑Yes ®No ❑NA
If yes, will this discharged water be of the same salinity as the receiving water?
❑Yes []No ❑NA
j.
Is there any mitigation proposed?
❑Yes ®No ❑NA
If yes, attach a mitigation proposal.
<Form continues on back> MAY 14 20118
9'9CM m4Lio em.s y
Y52-808-2808 „ 1.888-4RC®AST „ www.nccoastallmanagement.net
Form DCM MP -1 (Page 4 of 4)
APPLICATION for
Major Development Permit
6. Additional Information
In addition to this completed application form, (MP -1) the following items below, if applicable, must be submitted in order for the application
package to be complete. Items (a) — (f) are always applicable to any major development application. Please consult the application
instruction booklet on how to properly prepare the required items below.
a. A project narrative.
b. An accurate, dated work plat (including plan view and cross-sectional drawings) drawn to scale. Please give the present status of the
proposed project. Is any portion already complete? If previously authorized work, clearly indicate on maps, plats, drawings to distinguish
between work completed and proposed.
c. A site or location map that is sufficiently detailed to guide agency personnel unfamiliar with the area to the site.
d. A copy of the deed (with state application only) or other instrument under which the applicant claims title to the affected properties.
e. The appropriate application fee. Check or money order made payable to DENR.
f. A list of the names and complete addresses of the adjacent waterfront (riparian) landowners and signed return receipts as proof that such
owners have received a copy of the application and plats by certified mail. Such landowners must be advised that they have 30 days in
which to submit comments on the proposed project to the Division of Coastal Management.
Name Billy M. Norris Phone No. 910-389-1684
Address 377 Norris Landing Rd., Peletier, N.C. 28584
Name Billy R. Parker, Jr. Phone No.
Address 383 Norris Landing Rd., Peletier, N.C., 28584
Name Phone No.
Address
g. A list of previous state or federal permits issued for work on the project tract. Include permit numbers, permittee, and issuing dates.
Stormwater Permit No. SW8 170604
S. & E. Project ID: CARTE -2017-026
h. Signed consultant or agent authorization form, if applicable.
i. Wetland delineation, if necessary.
j. A signed AEC hazard notice for projects in oceanfront and inlet areas. (Must be signed by property owner)
k. A statement of compliance with the N.C. Environmental Policy Act (N.C.G.S. 113A 1-10), if necessary. If the project involves expenditure
of public funds or use of public lands, attach a statement documenting compliance with the North Carolina Environmental Policy Act.
7. Certification and Permission to Enter on Land
I understand that any permit issued in response to this application will allow only the development described in the application.
The project will be subject to the conditions and restrictions contained in the permit.
I certify that I am authorized to grant, and do in fact grant permission to representatives of state and federal review agencies to
enter on the aforementioned lands in connection with evaluating information related to this permit application and follow-up
monitoring of the project.
I further certify that the information provided in this application is truthful to the best of my knowledge.
Date April 26, 2018 Print Name
Signature
Please indicate application attachments pertaining to
❑DCM MP -2 Excavation and Fill Information
❑DCM MP -3 Upland Development
®DCM MP -4 Structures Information
Morton Ward
project.
CM MP -5 Bridges and Culverts
252-808-2808 :. 1-888-4RCOAST :: www.nccoastalmanagement.net
Form DCM MP -1 (Page 2 of 4)
APPLICATION for
Major Development Permit
3. Project Location
County (can be multiple)
Street Address
State Rd. #
Carteret
Tidal Bluffs Ct.
d. Approximate elevation of tract above NHW (normal high water) or
Subdivision Name
City
State
Zip
Tidal Bluffs
Peletier
N.C.
28584 -
Phone No.
Lot No.(s) (if many, attach additional page with list)
910 - 459 - 9129 ext.
#1, #2, #3, #4, #5 & #6
a. In which NC river basin is the project located?
b. Name of body of water nearest to proposed project
White Oak
Pettiford Creek Bay
c. Is the water body identified in (b) above, natural or manmade?
d. Name the closest major water body to the proposed project site.
®Natural ❑Manmade []Unknown
White Oak River
e. Is proposed work within city limits or planning jurisdiction?
f. If applicable, list the planning jurisdiction or city limit the proposed
®Yes []No
work falls within.
Peletier
4. Site Description
a. Total length of shoreline on the tract (ft.)
b. Size of entire tract (sq.ft.)
375'
235,224 Sq. Ft.
c. Size of individual lot(s)
d. Approximate elevation of tract above NHW (normal high water) or
See attached,
NWL (normal water level)
(If many lot sizes, please attach additional page with a list)
10' ®NHW or ❑NWL
e. Vegetation on tract
Sparce trees & grass on uplands, Typical wetland and coastal wetland species in wetlands
f. Man-made features and uses now on tract
Tidal Bluffs Ct. is a paved street. Lots are vacant.
g. Identify and describe the existing land uses adjacent to the proposed project site.
Single family residence to the north and south, vacant land to the east
h. How does local government zone the tract?
i. Is the proposed project consistent with the applicable zoning?
R-20
(Attach zoning compliance certificate, if applicable)
®Yes [:]No [INA
j. Is the proposed activity part of an urban waterfront redevelopment proposal? ❑Yes ®No
k. Hasa professional archaeological assessment been done for the tract? If yes, attach a copy. []Yes ®No [--INA
If yes, by whom?
I. Is the proposed project located in a National. Registered Historic District or does it involve a []Yes ®NoCEIVED
National Register listed or eligible property?
<Form continues on next page> MAY 14 2018
DCM-MHD CITY
252-808-2808 .. 1-888-4RCOA5T .: www.nccoastalmanagement.net
Form DCM MP -1 (Page 3 of 4)
APPLICATION for
Major Development Permit
m. (i) Are there wetlands on the site? ®Yes ®No
(ii) Are there coastal wetlands on the site? ®Yes ®No
(iii) If yes to either (i) or (ii) above, has a delineation been conducted? ®Yes []No
(Attach documentation, if available)
n. Describe existing wastewater treatment facilities.
Common Conventional single family residential septic system, not installed
o. Describe existing drinking water supply source.
West Carteret Water Corp.
p. Describe existing storm water management or treatment systems.
Natural run-off, Low density stormwater permit
5. Activides and impacts
a. Will the project be for commercial, public, or private use?
❑Commercial ❑Public/Government
®Private/Community
b. Give a brief description of purpose, use, and daily operations of the project when complete.
The pier and boat lifts are intended for private use by the future residents of Lots 1-6, Tidal Bluffs.
c. Describe the proposed construction methodology, types of construction equipment to be used during construction, the number of each type
of equipment and where it is to be stored.
The pilings will be vibrated in. A barge will be used for accessibility and portable generator
for electric supply.
d. List all development activities you propose.
Construction of 579' of pier and Installation of six boat lifts.
e. Are the proposed activities maintenance of an existing project, new work, or both?
New work
f. What is the approximate total disturbed land area resulting from the proposed project?
4,000 ®sq.Ft or ❑Acres
g. Will the proposed project encroach on any public easement, public accessway or other area
❑Yes ®No ❑NA
that the public has established use of?
h. Describe location and type of existing and proposed discharges to waters of the state.
There are no proposed and no existing discharges to waters of the state
i. Will wastewater or stormwater be discharged into a wetland?
[]Yes ®No ❑NA
If yes, will this discharged water be of the same salinity as the receiving water?
[]Yes []No ❑NA
j. Is there any mitigation proposed?
❑Yes ®No [INA
If yes, attach a mitigation proposal.
<Form continues on back> RECEIVED
MAY 14 2018
252-808-2808 .. 1-888-4RCOAST .. CITY
Form DCM MP -1 (Page 4 of 4)
APPLICATION for
Major Development Permit
6. Addidonal. Information
In addition to this completed application form, (MP -1) the following items below, if applicable, must be submitted in order for the application
package; to be complete. Items fa) - (0 are; always applicable to any major development application. Please consult the application
instruction booklet on how to properly prepare the required items below.
a. A project narrative.
b. An accurate, dated work plat (including plan view and cross-sectional drawings) drawn to scale. Please give the present status of the
proposed project. Is any portion already complete? If previously authorized work, clearly indicate on maps, plats, drawings to distinguish
between work completed and proposed.
c. A site or location map that is sufficiently detailed to guide agency personnel unfamiliar with the area to the site.
d. A copy of the deed (with state application only) or other instrument under which the applicant claims title to the affected properties.
e. The appropriate application fee. Check or money order made payable to DENR.
f. A list of the names and complete addresses of the adjacent waterfront (riparian) landowners and signed return receipts as proof that such
owners have received a copy of the application and plats by certified mail. Such landowners must be advised that they have 30 days in
which to submit comments on the proposed project to the Division of Coastal Management.
Name Billy M. Norris Phone No. 910-389-1684
Address 377 Norris Landing Rd., Petetier, N.C. 28584
Name Billy R. Parker, Jr. Phone No.
Address 383 Norris Landing Rd., Peletier, N.C., 28584
Name Phone No.
Address
g. A list of previous state or federal permits issued for work on the project tract. Include permit numbers, permittee, and issuing dates.
Stormwater Permit No. SW8 170604
S. & E. Project ID: CARTE -2017-026
h. Signed consultant or agent authorization form, if applicable.
i. Wetland delineation, if necessary.
j. A signed AEC hazard notice for projects in oceanfront and inlet areas. (Must be signed by property owner)
k. A statement of compliance with the N.C. Environmental Policy Act (N.C.G.S. 113A 1-10), if necessary. If the project involves expenditure
of public funds or use of public lands, attach a statement documenting compliance with the North Carolina Environmental Policy Act.
7. Certification and Permission to Enter on Land
I understand that any permit issued in response to this application will allow only the development described in the application.
The project will be subject to the conditions and restrictions contained in the permit.
I certify that I am authorized to grant, and do in fact grant permission to representatives of state and federal review agencies to
enter on the aforementioned lands in connection with evaluating information related to this permit application and follow-up
monitoring of the project.
I further certify that the information provided in this application is truthful to the best of my knowledge.
Date April 26, 2018 Print
Signature _
Please indicate application attachments pertaining to your I
❑DCM MP -2 Excavation and Fill Information
❑DCM MP -3 Upland Development
®DCM MP -4 Structures Information
_Jinnifer Morton Ward
project.
CM MP -5 Bridges and Culverts
RECEIVED
MAY 14 2018
.ne
252-808-2808 .. 1-888-4RCOAST .. www.nccoastallmanagemen
l
Form DCM MP -4
STRUCTURES
(Construction within Public Trust Areas)
Attach this form to Joint Application for CAMA Major Permit, Form DCM MP -1. Be sure to complete all other sections of the Joint
Application that relate to this proposed project. Please include all supplemental information.
?. DUCKING FAGILITY/MARINA GHARAE;TERISTICS This section not applicable
a. (i) Is the docking facility/marina: b. (i) Will the facility be open to the general public?
❑Commercial ❑Public/Government ®Private/Community ❑Yes ENo
c. (i) Dock(s) and/or pier(s)
(ii) Number 1
(iii) Length 579'
(iv) Width 5'
(v) Floating ❑Yes ENo
e. (i) Are Platforms included? []Yes ENo
If yes:
(ii) Number
(iii) Length
(iv) Width
(v) Floating []Yes ❑No
Note: Roofed areas are calculated from dripline dimensions.
g. (i) Number of slips proposed
0
(ii) Number of slips existing
0
i. Check the proposed type of siting:
❑ Land cut and access channel
❑Open water; dredging for basin and/or channel
EOpen water; no dredging required
❑Other; please describe:
k. Typical boat length: Max. 26'
m. (i) Will the facility have tie pilings?
❑Yes ENo
(ii) If yes number of tie pilings?
2. DOCKING FACILITY/MA,
d. (!)Are Finger Piers included? EYes ENo
If yes:
(ii) Number 3
(iii) Length 24'
(iv) Width 3'
(v) Floating ❑Yes ENo
f. (i) Are Boatlifts included? EYes []No
If yes:
(ii) Number 6
(iii) Length 13'
(iv) Width 13'
h. Check all the types of services to be provided.
❑ Full service, including travel lift and/or rail, repair or
maintenance service
❑ Dockage, fuel, and marine supplies
❑ Dockage ('Vet slips") only, number of slips:
❑ Dry storage; number of boats:
❑ Boat ramp(s); number of boat ramps:
E Other, please describe:
Private Boat Lifts
j. Describe the typical boats to be served (e.g., open runabout,
charter boats, sail boats, mixed types).
Open Runabout
I. (i) Will the facility be open to the general public?
❑Yes ENo
252-808-2808 :: 1-888-4RCOAST :: www.nccoastaimanagement.net
RECEIVED
to This section not applicable
Mm i 4 2018
DCM-MHD CITY
revised: 12/27/06
Form ®CM MP -4 (Structures, Page 2 of 4)
a. Check each of the following sanitary facilities that will be included in the proposed project.
❑ Office Toilets
❑ Toilets for patrons; Number: ; Location:
❑ Showers
❑ Boatholding tank pumpout; Give type and location:
b. Describe treatment type and disposal location for all sanitary wastewater.
c. Describe the disposal of solid waste, fish offal and trash.
d. How will overboard discharge of sewage from boats be controlled?
e. (i) Give the location and number of "No Sewage Discharge" signs proposed.
(ii) Give the location and number of "Pumpout Available" signs proposed.
f. Describe the special design, if applicable, for containing industrial type pollutants, such as paint, sandblasting waste and petroleum products.
g. Where will residue from vessel maintenance be disposed of?
h• Give the number of channel markers and "No Wake" signs proposed.
i. Give the location of fuel -handling facilities, and describe the safety measures planned to protect area water quality.
j. What will be the marina policy on overnight and live -aboard dockage?
k. Describe design measures that promote boat basin flushing?
I. If this project is an expansion of an existing marina, what types of services are currently provided?
m. Is the marina/docking facility proposed within a primary or secondary nursery area? RECEIVED
❑Yes ❑No
n. Is the marina/docking facility proposed within or adjacent to any shellfish harvesting area? MAY 14 2018
❑Yes ❑No
DCIV/-MHD CI
252-808-2808 :: 1-888-4RCOAST :: www.nccoastalmanaaement.not
revised: 12/27/06
V
Form DCM MP -4 (Structures, Page 3 of 5)
o. Is the marina/docking facility proposed within or adjacent to coastal wetlands/marsh (CW), submerged aquatic vegetation (SAV), shell bottom
(SB), or other wetlands (WL)? If any boxes are checked, provide the number of square feet affected.
❑CW ❑SAV OSB
OWL []None
p. Is the proposed marina/docking facility located within or within close proximity to any shellfish leases? []Yes ❑No
If yes, give the name and address of the leaseholder(s), and give the proximity to the lease.
3. BOATHOUSE (including covered lifts) This section not applicable
a. (i) Is the boathouse structure(s):
❑Commercial ❑Public/Government ❑Private/Community
(ii) Number
(iii) Length
(iv) Width
Note: Roofed areas are calculated from dripline dimensions.
4. GROIN (e.g., wood, sheetpile, etc. If a rock groin, use MP -2, Excavation and Fill.) ®This section not applicable
a. (i) Number
(ii) Length
(iii) Width
5. BREAKWATER (e.g., wood, sheetpile, etc.) ®This section not applicable
a. Length b. Average distance from NHW, NWL, or wetlands
c. Maximum distance beyond NHW, NWL or wetlands
6. MOORING PILINGS and BUOYS ® This section not applicable
a. Is the structure(s):
❑Commercial ❑Public/Government ❑Private/Community
c. Distance to be placed beyond shoreline
Note: This should be measured from marsh edge, if present.
e. Arc of the swing
7. GENERAL
a. Proximity of structure(s) to adjacent riparian property lines
83+'
b. Number
d. Description of buoy (color, inscription, size, anchor, etc.)
b. Proximity of structure(s) to adjacent docking faciElities
520+'
Note: For buoy or mooring piling, use arc of swing including length
of vessel. MAY 14 2018
1-31QM H ®r-ITY
252-808-2808 :: 1-888-4RCOAST :: wwwmccoastalmanagement.net revised: 12/27/06
Form DCAJI P- (Structures, Page 4 of 4)
c. Width of water body
690+'
e. (i) Will navigational aids be required as a result of the project?
❑Yes ®No ❑NA
(ii) If yes, explain what type and how they will be implemented.
d. Water depth at waterward end of structure at NLW or NWL
2.2'-2.4'
8. OTHER El This section not applicable
a. Give complete description:
See Narrative
04/24/18
Date
Tidal Bluffs
Project Name
MAY 14 2018
DCM- HD CITY
252-808-2808 :: 1-888-4RCOAST :: www.nccoastaimanagement.net revised.- 12/27/05
DIVISION OF COASTAL MANAGEMENT
FIELD INVESTIGATION REPORT
1. APPLICANT'S NAME: Horizion East LLC. (Tidal Bluffs)
2. LOCATION OF PROJECT SITE: Tidal Bluff Ct., Pelletier
Latitude: 3442'59.34"N Longitude: 77'05'11.91"W
3. INVESTIGATION TYPE: CAMA
4. INVESTIGATIVE PROCEDURE: Dates of Site Visit — 6/12/18
Was Applicant Present — No
5. PROCESSING PROCEDURE: Application Received — 5/14/18
Application Complete- 8/2/18
Office — Morehead City
6. SITE DESCRIPTION:
(A) Local Land Use Plan — Carteret County
Land Classification from LUP — Limited Transition
(B) AEC(s) Involved: EW, PTA, ES, CW
(C) Water Dependent: (yes)
(D) Intended Use: Residential
(E) Wastewater Treatment: Existing — N/A
Planned — NA
(F) Type of Structures: Existing — N/A
Planned — Dock
(G) Estimated Annual Rate of Erosion: N/A
Source — N/A
7. HABITAT DESCRIPTION:
DREDGED CHADFD lTCiTRPF.n
(A) Open Water
N/A
1,222.5ft2
3,675ft2
(B) Coastal Wetlands
(C) Section 404
1375ft2
675ft2
(D) Total Area Disturbed: 5,725ft2
(E) Primary Nursery Area: Yes
(F) Water Classification: SA
(G) Shellfish Classification: Closed
8. PROJECT SUMMARY: Horizions East, LLC. is proposing to construct a six slip docking
facility to serve an existing six lot subdivision (Tidal Bluff).
A Field Investigation Report:
Horizions East, LLC.
Page 02
9. NARRATIVE DESCRIPTION: The Horizons East, LLC. project is located at Tidal
Bluff Ct. which is a cul-de-sac in Tidal Bluff subdivision in Pelletier. Tidal Bluff
subdivision is located by turning West off of Hwy. 58 onto Pelletier Loop Rd. Travel .lmi
down Pelletier Loop Rd. before turning South on Norris Landing Rd. Norris Landing Rd.
is a gravel road and Tidal Bluff is located near the end and is contiguous with Pettiford
Creek Bay.
Tidal Bluff is a six lot(5.4ac) subdivision. Roads and utilities are complete within the
subdivision. No houses have been constructed at this time. This project would occur on a
dedicated community access between lots 3 and 5. The high ground is vegetated with
grasses and woody vegetation. An area of Coastal Wetlands and high ground hammocks
exist between the high ground and Pettiford Creek Bay within the project area. Coastal
Wetland plants consist of Smooth Cordgrass and Black Needle Rush. The bottom of
Pettiford Creek Bay in this area is sand and silt. Water depths in the area are -1' to -3' at
NLW. No SAV was observed in the area. Adjacent properties are large track residential.
The shoreline is irregular and is 560' in -length.
The Division of Water Resources classifies this area of Pettiford Creek as SA waters. This
is a Primary Nursery Area. This portion of Pettiford Bay is closed to harvesting shellfish.
The parcel is classified in the Carteret Co. LUP as Limited Transition. The subdivision
Stormwater Permit No. is SW8 170604 and the S & E Project ID is CARTE -2017-026.
10. PROJECT DESCRIPTION: The proposed community dock in Tidal Bluff subdivision
would be 5' wide and would leave high ground before crossing 135' of Sec. 404
Jurisdictional Wetlands and 275' of regular and irregularly flooded Coastal Wetlands. A
3' clearance would be maintained between the dock and wetland substrate in this area.
- The dock would continue for 135' into the waterbody before connecting to a
5'X67.6'(338ft2) platform. Three 3'X24' finger piers would extend from the platform
creating a total of 6 slips. A 13'X13' boatlift would be placed in each slip. This docking
facility would extend a total of 160' from the waterward edge of marsh into the 1000' wide
waterbody with a non-linear shoreline. The dock as proposed would not extend further
than similar docks already existing along the shoreline. Adjacent properties are 83' and
240' from the dock respectively. Water depths in the area of the slips range from -2'to -
2.2' at NLW as surveyed by Bell & Phillips Surveying.
11. ANTICIPATED IMPACTS: The proposed docking facility would shade 1,222.5ft2 of
Shallow bottom, 1375ft2 of Coastal Wetland, 675ft2 of Federal wetlands and usurp 3,675ft2
of Public Trust Area. A temporary increase in turbidity would occur during construction.
Bottom disturbance by boats could occur during extreme low tide events as
a result of power loading boats onto lifts. Marsh substrate would be disturbed during
construction and would be restored after completion. Conclusion: no substantive changes
to impacts on upland or aquatic resources would result from proposed pier access and
docking facility.
Name: Ryan Davenport Date: 8/16/18 Morehead City
Qrr
April 24, 2018
PLLC
ProfessionaC Land Surveyors ,
604E Cedar Point Bfv& Cedar Point, .NC 28584
(252) 393-6101 Fax: (252) 393-3522
Ryan Davenport
Division of Coastal Management
400 Commerce Ave.
Morehead City, N.C. 28557
Dear Mr. Davenport:
I am applying for a CAMA Major permit on behalf of Jennifer M. Ward, Horizons East, LLC to construct a
pier and six (6) boatlifts, located in Tidal Bluffs Subdivision, Town of Peletier, in Carteret County, North
Carolina. Please find enclosed the following:
DCM MP -1, Application for Major Development Permit
DCM MP -4, Structures
Check in the amount of $400
Copy of the subject property deed
Copy of the recorded subdivision plat
Drawing consisting of one (1) sheet, vicinity map, existing upland conditions, proposed construction,
plan view and cross-section view, and profile section of proposed construction
Owner Authorization form.
The boatlifts are for the private use of the eventual owners of the six lots in Tidal Bluffs. The property
owner to the south and east is Billy M. Norris and the property owner to the north is Billy R. Parker, Jr.
If you should have any questions on this project, please call me at 252-393-6101 or e-mail me at
alanbell(@eastnc.twcbc.com.
Sincerely,
an UII. P.L.S.
Major Permit Fee Schedule
Circle One
DCM %
DWQ %
Development Type
Fee
(14300160143510009316256253)
(2430016024351000952341)
I. Private, non-commercial
development that does not involve
the filling or excavation of any
wetlands or open water areas:
$250
100%($250)
0% ($0)
Il. Public or commercial
development that does not involve
the filling or excavation of any
wetlands or open water areas:
$400
100%($400)
o%($0)
Ilf. For development that involves
the filling and/or excavation of up
to 1 acre of wetlands and/or open
water areas, determine if A,B, C.
or D below applies:
III(A). Private, non-commercial
development, if General Water
Quality Certification No. 3490
(See attached) can be applied:
$250
100%($250)
0%0 ($0) .
III(B). Public or commercial
development, if General Water
Quality Certification No. 3490
(See attached) can be applied:
$400
100% ($400)
0% ($0)
III(C). If General Water Quality
Certification No. 3490 (see
attached) could be applied, but
DCM staff determined that
additional review and written
DWQ concurrence is needed
because of concerns related to
water quality or aquatic life:
$400
60%($240)
40%($160)
III(D). If General Water Quality
Certification No. 3490 (see
attached) cannot be applied:
$400
60%($240)
40%($160)
IV. Development that involves the
filling and/or excavation of more
than one acre of wetlands and/or
open water areas:
$475
60%($285)
400/.($190)
mm
Norris
Pettiford
Creek Bay
Vicinity Map -Not to Scale
,318 x8" Calv. Lag Bolt
-5/8 xt8' Galv. Timber Bolt
518K16" GGIV, Timber Bolt
318X8 " Golv. Lag Bolt
2"x6" S.T Sill
Pe t tiford Cre ek Bay
Plan View
a
'"M 10- Giraffe
`(2) 5181.x78®
Golv. umber
Head Thru
2,5 Marine Grade
8' Piles -8, 04
(8, to 10' Pile
Penetration)
Section View
Scale: 1 " = 4
2 '9
Finger Pier
cv
Water Depths at Normai �ow Water
4'x8'x4" 6000 PSI
— Conc. Slats, Marine
Grade W1 Rebar
(2) 518 "x 18
— Golv, Timber
Head Thru
2.5 Marine Grade
8" Piles -8' O.C.
4'x8'x4" 6000 PSI
- Conc, Slats, Marine
Grade W1 Reber
6"x6" S.T. Ground Contc,:
10.0
7.
0,(1-
7, C
6, C,
5,0
4.0
JC"
2.0
7.c
0. 0
_1,c
—2, '
_30
- 4, C
—50
676'
Platform
car Finger Pier
1 \v[j:6/ U2 \M'W/ 3
rScale: 1 ?0'
Z ___ SixProposed
IJ, x 13Boat Lifts
Common Area
C,
C, 0^ 605 Sq. Ft.
0^
L 48
L44
L
C� L43
�A
`o'
pen Vater
Open Water ell
-cx
CE
4`5
18
15�
/7
17
0,vp51 en Water
17
x 2,3
L
r
N,)
0 N)
'9'
Normal High Wcter
Finger Oier /7 '9 /7Y
0r 487' 5' Wide Car
7R /7
6Y1 2
N 57-,'41 " "E E N3
Y, 2,3I3,
17 56 1
.19 Y, '5;r
C),
19
i ,ger Pier Normal High Water Line
15' from Riparian Corridor Line
Riparian Corridor Line
a
go
L
Billy M. Norris
Bk. 14 705 Pg. 446
M.B. 32, Pg. 446
Pin #537502572097000 2
Timber Piles: Embea-rent,
Diameter, Placement, etc.,
per structural design,
Building Code, Controv,toi
& where applicable, Poot
Lift Manufacturer.
Six Proposed
.S
IJ' x IJ' Boat L '
"Iuu ZJU
Horizontal Scale: 1" = 40'
Vertical e® 1"
ZUU 7�U 100
'M
x
t
LEGEND
0 SET IRON PIPEIROD
0 -EXISTING IRON
'OHP-OVERHEAO POWER
>0
Billy R. Parker, Jr. GW -GUY WIRE
Bk
619 + -NONMONUMENTED POINT
115r . 126 71 Pg. 355 000 0 AG -ABOVE GROUND
BG -BELOW GROUND
M. B. 3 1, Pg. 4 3 7 -POWER POLE
SOT -SIGHT DISTANCE TRIANGLE
Pin #537502570694000 A —SET MAG NAIL (CONTROL)
10 0
9.0
8,0
7.0
60
5.0
4,O
3.0
2.0
7.0 1.2: (Normal High Water)
0. 0: (Normal Low Water)
—1.0
—2. 0
_J.o
—4.0
—5.0
I
Z
REV DESCRIPTION DA TE
REV DESCRIFnON XX/XX/XX
<- Tidal Bluffs Ct. (50' R/f
39.66'
S 57'23'41
P W
JO' M. 3. L.
4-
Q14
N3
30' M. 8. L.
1,3,3.74 F
0 0%,
<>1
am
40 0 40 8
G,"APHIC SCALE — FEET
W
co
COD)
CZ
Date 06111118
Job 16785CAMA2
Cagy 16785NLW
Drown CA B
Scale 1 40'
120 Sheet
I of
Q
ftIq
(b
q)
kO
(U
W
co
COD)
CZ
Date 06111118
Job 16785CAMA2
Cagy 16785NLW
Drown CA B
Scale 1 40'
120 Sheet
I of