Permit Class Permit Number
MODIFICATION/MAJOR 113-17
STATE OF NORTH CAROLINA
Department of Environmental Quality
and
Coastal Resources Commission
Permit
for
X Major Development in an Area of Environmental Concern
pursuant to NCGS 113A-118
X Excavation and/or filling pursuant to NCGS 113-229
Issued to William Black Jr., 132 Country Club Rd., Edenton, NC 27932
Authorizing development in Chowan County along the Albemarle Sound, at 132 and
136 Country Club Rd., Edenton as requested in the permittee's application dated 5/25/18 (MP -1) and
6/4/18 (MP 2) including the attached workplan drawings (2) both dated 5/23/18.
This permit, issued on August 6, 2018 , is subject to compliance with the application (where consistent
with the permit), all applicable regulations, special conditions and notes set forth below. Any violation of these terms may
)e subject to Imes, imprisonment or civil aoLluu, or may caua, Lnc JJ .....L w w .wag ....,., •...
Excavation
1) In order to reduce the potential for negative effects on the spawning migration of anadromous fish, no
excavation or filling shall be permitted between February 15 and June 30 of any year without the
prior approval of the Division of Coastal Management, in consultation with appropriate resource
agencies.
2) No excavation shall take place outside of the area indicated on the workplan drawings.
3) Excavation shall not exceed -8 feet below the normal water level. In no case shall the depth of
excavation exceed the depth of connecting waters.
(See attached sheets for additional conditions)
This permit action may be appealed by the permittee or other
qualified persons within twenty (20) days of the issuing date.
This permit must be accessible on-site to Department
personnel when the project is inspected for compliance.
Any maintenance work or project modification not covered
hereunder requires further Division approval.
All work must cease when the permit expires on
December 31, 2021
In issuing this permit, the State of North Carolina agrees that
your project is consistent with the North Carolina Coastal
Management Program.
slgnea Dy me autnOrity of uln OCUICL41Y u. �%'e auu .....
Chairman of the Coastal Resources Commission.
Braxton'. Davis, Director
Division of Coastal Management
This permit and its conditions are hereby accepted.
Signature of Permittee
William Black Jr. Permit No. 113-17
Page 2 of 3
ADDITIONAL CONDITIONS
4) The temporary placement or double handling of excavated or fill materials within waters or vegetated
wetlands is not authorized.
5) No excavated or fill material shall be placed at any time in any vegetated wetlands or surrounding
waters.
Spoil Disposal
6) No spoil material shall be placed within 30 feet of the normal water line.
7) All excavated materials shall be confined above normal high water and landward of regularly or
irregularly flooded marsh behind adequate dikes or other retaining structures to prevent spillover of
solids into any marsh or surrounding waters.
8) The permittee and/or his contractor shall take all necessary precautions to ensure that the spoil material
is properly contained during transport to the disposal site, and that all the proper coordination has taken
place with the local or state governments to ensure that any damage to public streets caused by transport
of the spoil material has been addressed.
9) The area adjacent to the spoil offloading site is a NCWRC boating access area. The offloading
operations shall not encroach upon the NCWRC property or deter the use of the NCWRC boating access
area by the public.
Maintenance Clause
10) The Division of Coastal Management shall be notified in writing at least two (2) weeks in advance of
any maintenance work authorized by this permit, and such notification shall include:
A. The number of the original permit.
B. A statement that no dimensional changes are proposed.
C. A copy of the original permit plans with cross -hatching indicating the area to be maintained, the
area to be used for spoil disposal, and the estimated amount of material to be removed. The
location, design and holding capacity of the spoil disposal site shall be approved by a
representative of the Division prior to the initiation of any maintenance dredging activities.
D. The date of map revision and the permittee's signature shown anew on the original plan.
Navigational Aides
11) Unless specifically altered herein, this permit authorizes the installation of 6 day marker type
navigational aids, all as expressly and specifically set forth in the attached permit application and
workplan drawings.
12) The navigational aids shall conform with any and all appropriate regulations governing such structures,
including but not limited to marking and lighting requirements of the N.C. Wildlife Resources
Commission and/or the U.S. Coast Guard.
William Black Jr.
ADDITIONAL CONDITIONS
General
Permit No. 113-17
Page 3 of 3
13) This permit shall not be assigned, transferred, sold, or otherwise disposed of to a third party without the
written approval of the Division of Coastal Management.
14) The permittee and/or his or her contractor shall meet with a representative of the Division prior to
project initiation.
15) This Major Modification shall be attached to the original Permit No. 113-17, which was issued to the
permittee on 9/28/17, and copies of both documents must be readily available on site when Division
personnel inspect the project for compliance.
16) All conditions and stipulations of the active permit remain in force, under this Major Modification,
unless specifically altered herein.
NOTE: The U.S. Army Corps of Engineers assigned the proposed project COE Action Id. No. SAW -
2018 -01288, issued 7/24/18.
NOTE: The Division of Water Resources assigned the proposed project DWR Project No. 85-0177 V3.
NOTE: An application processing fee of $475 was received by DCM for this project. This fee also
satisfied the Section 401 application processing fee requirements of the Division of Water
Resources.