Loading...
HomeMy WebLinkAboutBridge 197 Ver 1_Meeting Notes_20180730NORTH CAROLINA DEPARTMENT OF TRANSPORTATION FIELD SCOPING MEETING WORKSHEET Design Build Process TIP .: WBS .: 17BP.6.PE.1 Field Scoping Meeting Date: Division: 6 Location: On-site Route (US/NC/SR): SR1534 County: Bladen Project Description: Structure. 080197 over Kelly Canal on SR 1534 (Over Lyon Road) Tier: Subregional Funding: Federal Municipality: N/A A+tP_f1fiP_P_S Name Phone . E-mail Division Bridge Program Manager Christy Huff, PE 910-364-0603 chuff@ncdot.gov Division Environmental Officer James Rerko 910-364-0834 jjrerko@ncdot.gov Division Environmental Specialist Division Construction Engineer Rusty Marsh, PE 910-364-0600 rmarsh@ncdot.gov Division Bridge Maintenance Darren Pittman 910-364-0670 dpittman@ncdot.gov Engineer Division Utility Coordinator Randy Rogers 910-364-0841 rdrogers4@ncdot.gov PP� PaEmie Lancaster, 919-707-6620 jjlancaster@ncdot.gov pp� Jess Earley, PE 979-707-6606 jsearley@ncdot.gov Hydraulics Engineer Willllam Cail, PE 919-707-6711 gcail@ncdot.gov Hydraulics Engineer Chris Lewis, PE 919-707-6774 crlewis2@ncdot.gov USACE NCDEQ-DWR USFWS NCWRC Asst Div Bridge Program Manager Region 3 Locating Engineer Structure No: 080197 1 of 5 Existinq Features Feature Bridged: Structure 080197 over Kelly Canal on SR 1534 Ex. Bridge Clear Deck Width: 24.083 (Ft.) Roadway width: 18 (Ft.) (Bridge / Culvert) Length: 61 (Ft.) Deck Width (Out To Out): 25.583 (Ft.) Water Depth: 2(Ft.) Height Bed-To-Crown: 10 (Ft.) Year Built: 1967 Posted: SV 24 TTST: 32 Superstructure: Prestressed Abutment: _ Pier Type: 2@ 30'6" Concrete Channels Temp. Shored: _ Historic High Water (Elev. To The Existing Structure ): (Ft) PRI: 56.712 DP: 2 SR: 25.97 School Bussing crossings per day: Division Posted Speed Limit Vicinity: 55 (mph) Detour Off-Site ❑ Stage Construction ❑ New Alignment ❑ On-site � If Off-Site, Description Of Detour Route: Dead End Road � ( � C� �, �� i�L _ �i;, , Approximate Length Of Detour? N/A �� /% , � � J, i,� f r' ', i �� f�� 'c> `7 � Improvements Needed To Road(s) On Detour? N/A � � Div. Traffic Eng. Recommend Off-site detour signing? Trailblazing with StreeURoad names Improvements Needed To Bridges On Detour? N/A Are future plans for upgrading this roadway either at or in the vicinity of this project? N/A Are Bridges On Detour Currently Programmed? N/A Are There EMS Or Business Access Issues? Yes, churches and houses Are There Any Railroad Crossings On Detour? N/A Should Work Zone Pedestrian Access Be Maintained During Construction? N/A Overhead Utility Lines Power Transmission Lines Telephone Cable Lines Fiber Optic Water Sewer Natural Gas Other In Conflict Yes In Conflict In Conflict In Conflict In Conflict In Conflict In Conflict In Conflict In Conflict Is There Any Future Utility Construction Anticipated In The Project Area: Is A FEMA Buy-Out Property Being Impacted: Gheck final surveys.when receiVed �: i' r'���,. <. i� .j L� �. � , Structure No: 080197 2 of5 ' �.t_+ � � '.;i:' � r�' n L �� , ° Hvdraulics ' � ; ��� �� _ � FEMA Approval? � (MOA ) State Stormwater Permit? I,�^-� Is There Unusual Scour Potential? �`,' Is Protection Needed? '''� Are Banks Stable? Is Protection Needed? %� Appreciable Amount Of Large Debris? %: ' � ' . ' � �' , ' ` � / � � =-j: ,��� .t_, Placement Of Bents In The Water Be Allowed: � Where: V� � ) Structure Type: Bridge If Bridge: CS or BB If girder; why? Length Of Structure: ' Min. Number Of Spans: Span Arrangement: �(-> ��I �� Waive offset: EB Cap; 2'-6" pr 4'-0" Skewed: %��C ) , � � _J; . , .. : : � � � . r� - � , ., /� , �,• � � y � ' /��77 Items To Be Discussed /�Res�lved'At F&M'Bv Attendeea , Off-Site ❑ Stage Construction ❑ New Alignment ❑ On-site ❑ � ' Clear roadway width: Clear roadway width: , %� i�- ' Temp. Signals: one lane w/ signals: or two lanes CRW: Alignment: N, E, W, S Alignment: N, E, W, S Alignment: N, E, W, S Environmental Document Prepared by DEO Or PEF: CE (federal) ❑ Minimum Criteria Checklist (state) ❑ ADT: 170 per BIR NHS: 0 Tier. Subregional Func. Class: Local ' Bridge Min. Clear Deck Width Recommended by Div.�.�T7-ft O O �J `� 1�,, . Roadway lane width: 10' with 3' shoulders, including 0' paved shoulders Extension of Paved shoulders: end of construction limits or end of guardrail (Blunt end or taper 8:1) Pave to face of guardrail and taper 8:1 to travel lane/paved shoulder? Min. Pavement Surface Course: _" Existing Roadway: Pavement Marking: Thermoplastic or Paint Pavement Markers: R�seii(Swplowable/none Will Railroad Involvement Be Required: No Method of Clearing: � '' � Truck Percentage: 6% per BIR Reasonable Safe Speed per SIR: mph (from speed study) Liquidated damages: will be imposed after �days of closure/construction. Amt: $-_� per day CEI by? NCDOT R/W by? '' DBT , RM/ monuments? �`onc. Salvageablematerials: ������ — � � �` - � . -t', �`'' �' ��� � � ,� � -, ^ ContactPerson/number: � � -� � � �� � i ` �� I�J , �� � I Deliver to: � � � � �� �� � �� , �� � ��,1 '- I� Removal of previous structure remnant abutments/piers Sequencing priority in construction? � Comments: Not on an evacuation route Structure No: 080197 r - � �� � J �`,; ', '' : 4 of 5 /', :._- , , , _, Structure No: 080197 5 of 5