HomeMy WebLinkAbout20180817 Ver 1_Email to Applicant_20180726Wojoski, Paul A
From: Wojoski, Paul A
Sent: Thursday, July 26, 2018 3:52 PM
To: 'billy.lee@townofcary.org'
Subject: Speight Branch Basin Sewer Improvements - Additional Info Needed
Hi Billy —
I just wanted to follow up my voicemail with an email. I'm reviewing the Speight Branch Basin Sewer Improvements
project (DWR#20180817), and have one issue with the project as proposed:
The impact at Site 1 show fill and excavation to realign the channel. The issue is that the fill in this area is proposed to be
armored with riprap stone through the buffer. Because it's buffer it would have to be replanted with native hardwoods
and vegetation. I think there may be confusion as the top of the bank is called out at 359.78' in this fill area, but it's at
351.60' on the other side of the channel in that Site 1 and at about 350' for rest of the channel. A bank of 10' higher is in
the Site 1 area would no longer be channel bank, but sloping riparian buffer area. The top of bank would be
approximately "351', equal elevation as the opposite bank.
I'll need revised plans to show plantings in the buffer pursuant to 260 trees/acre and no rip rap armoring. I can't issue
approval until this issue is resolved, therefore the project processing is hold until this information is received.
Please give me a call if you need to discuss or if I'm missing something.
Thanks,
Paul
Paul Wojoski
401 & Buffer Permitting Branch
Division of Water Resources
Department of Environmental Quality
(919) 707-3631 office
Paul.Woioski(a)ncdenr oov
512 N. Salisbury Street (Archdale Building), Suite 942-F, Raleigh, NC 27604
1617 Mail Service Center, Raleigh, NC 27699-1617
Nothing Compares
Email correspondence to and born this address is subject to the
Not Carolina Public Records Law and maybe disclosed to third parties,