Loading...
HomeMy WebLinkAbout20131200 Ver 5_USACE Notice of Permit Noncompliance_20180330DEPARTMENT OF THE ARMY WILMINGTON DISTRICT, CORPS OF ENGINEERS 151 PATTON AVENUE ROOM 208 ASHEVILLE, NORTH CAROLINA 28801-5006 March 30, 2018 Regulatory Division Action ID: SAW -2013-02262 lYMNI I M Tryon Equestrian Partners, LLC PO Box 2141 Rutherfordton, North Carolina 28139 �-. U_ :_9ui. Ar 4 H18 C ff5-WA-TER RESOURCES 1 & BUFFER PERMITTING Please reference the September 14, 2017, Department of the Army (DA) permit that authorizes permanent impacts to 10,281 linear feet of jurisdictional stream and 0.09 acres of jurisdictional wetlands associated with the ongoing development of the Tryon International Equestrian Center (TIEC) in Mill Spring, North Carolina. On January 25, 2018, Mr. Steve Kichefski, of the U.S. Anny Corps of Engineers Asheville Field Office (Corps) and Mr. Andrew Moore of the North Carolina Division of Water Resources (D WR) met on-site with your consultant, Clement Riddle of Clearwater Environmental Consultants, Inc. and Wayne Watkins, a representative from Odem Engineering, the third parry contractor involved in the project. During this onsite meeting we found three areas of permit noncompliance which were detailed in an email sent February 13, 2018. That email summarized the compliance site visit, including action items, and requested a response by February 28, 2018. On February 28, 2018, an email response was received to the action items requested by the Corps. As a result of our on-site meeting and the response, we found three (3) separate issues of permit non-compliance: 1. Construction at impact location's E4 and E5 were not completed in accordance with the permitted plans. Specifically, the non-compliance involves the pipe network, including the stormwater plan and bypass outlet structure, and additional fill placed within the jurisdictional stream channel beyond those authorized. The plans submitted and approved by the Corps with the September 14, 2017, permit authorization include a french drain as shown on Sheet 5 of 7 for Area A: Hotel and Bam/Stables Proposed French Drain. During the site inspection, it was observed that the Waters of the United States (WoUS) were being diverted through culverts being placed parallel to the french drain system already constructed, stormwater was being tied into this pipe network, the -2 - proposed outlet was located further downstream than the impacts/plans authorized and the outlet of this pipe network carries the WoUS through 3 rip -rap plunge pools and approximately 20 feet of overland flow before joining the jurisdictional stream channel again. The Corps requested, both in the field and in the summary email, that since plans for the outlet construction were different than those originally authorized, the revised plans should be submitted for approval, prior to construction. Additionally, the fill placed at impact location E4 and E5 exceeded what was authorized in this location. As such, TIEC is non-compliant with the terms and conditions of the subject DA authorization including special conditions 1, 3 and 5, and therefore are in violation of Section 301 of the Clean Water Act (33 USC 1344). 2. Several areas of bank stabilization activities along the equestrian trail on the north bank of White Oak Creek, between Bridge I and impact E3. This area was visited during the January compliance visit and included in the Corps February visit summary. A portion of this area had been previously authorized/constructed by the former owners in order to construct a small trail along the creek. TIEC widened and improved this trail, adding areas of bank stabilization and additional rock debris along the steep banks. Some of this debris is now below the Ordinary High Water Mark (OHWM) of White Oak Creek without authorization. An area of new bank stabilization was also constructed below the OHWM without authorization and a portion of it is failing and encroaching into White Oak Creek. These unauthorized impacts are also a violation of Section 301 of the Clean Water Act (33 USC 1344). We are concerned that the high flows of White Oak Creek will cause further failure if.not corrected soon. TIEC's February 28, 2018, response indicated that a long term solution was being developed and would be submitted for approval by March 30, 2018. This plan should ensure that all unauthorized fill is removed from this section of White Oak Creek and include a design more appropriate for stabilizing the stream bank slopes along such a large. dynamic channel. 3. Compensatory mitigation required by the September 14, 2017, permit authorization. The majority of this compensatory mitigation is being delivered via the approved Herman Dairy off-site, permittee -responsible compensatory mitigation. As of the January compliance visit, very little progress had been shown on this portion of the project .. despite the terms and condition of TIEC's permit, "Activities prescribed by this plan shall be initiated prior to, or concurrently with, commencement of any construction activities within jurisdictional areas authorized by this permit." In the February 28, 2018, response email, a timeline was given for the completion of the Herman Dairy project. If there are to be changes to this timeline, notification should be provided to the Corps with an explanation of how and when mitigation requirements will be resolved. In an effort to correct these issues, TIEC has the option of applying for an after -the -fact DA permit modification for the new impacts, or removing the non-compliant structures and replacing them in accordance with the previously approved plans. The assessment of any after - the -fact permit modification will rely on the information you provide, which should detail the reasons why additional impacts are needed and/or were constructed differently than the original plans. Keep in mind that you will be required to remove all non-compliant structures if you do not receive after -the -fact authorization. -3- TIEC may submit additional information needed to complete the after -the -fact DA authorization request or undertake full restoration of the non-compliant structures and unauthorized by April 20, 2018. Please be aware that compliance with these directives does not foreclose the Department of the Army's option to initiate additional appropriate legal action including pursuing a Class I Administrative Penalty under the authority of 33 U.S.C. § 1319(g) and 33 CFR Part 326.6 or referral to the United States Environmental Protection Agency with a recommendation for civil action. If you have any questions regarding this matter, please contact Mr. Steve Kichefski at (828) 271-7980 ext. 4234 with the Asheville Regulatory Field Office. FOR THE DISTRICT ENGINEER Sincerely, amt .��-�-�-- M. Scott Jones Chief Ashville and Charlotte Regulatory Feld Offices Enclosure cc: ClearWater Environmental Consultants, Inc. Mr. Clement Riddle 32 Clayton Road Asheville, North Carolina 28801 Odom Engineering PLLC Mr. David Odom 169 Oak Street Forest City, North Carolina 28043 NC Division of Water Resources Asheville Regional Office Mr. Andrew Moore 2090 U.S. 70 Highway Swannanoa, North Carolina 28778-8211 me NC Division of Water Resources 401 Buffer and Permitting Unit Ms. Karen Higgins 1617 Mail Service Center Raleigh, North Carolina 27699-1617 NC Division of Wildlife Resources Ms. Andrea Leslie 645 Fish Hatchery Rd., Building B Marion, NC 28752 Mr. Todd Bowers U.S. EPA Region 4 61 Forsyth Street, S.W. 9T25 Atlanta, Georgia 30303-8960 Ms. Molly Davis, Chief, Wetlands Enforcement Section Water Protection Division, Clean Water Enforcement Branch U.S. Environmental Protection Agency 61 Forsyth Street, SW Atlanta, Georgia 30303-8960