HomeMy WebLinkAbout20110309 Ver 4_More Info Requested_20180717Wojoski, Paul A
From: Wojoski, Paul A
Sent: Tuesday, July 17, 2018 4:01 PM
To: 'Thomas Brown'
Subject: RE: [External] RE: Martin Marietta's Onslow Quarry Expansion (DWR# 20110309 V4)
Thomas —
Thank you for the quick reply and for answering my questions regarding the stormwater discharge.
After our email exchange I was notified that that Corps has some comments they received during their public notice that
will need to be address before issuing the 404. Therefore I am holding the 401 until the response to those comments are
received, so we can review them also. Rather than duplicating the Corps request for more info, I'll just ask that you copy
me on your response to the Corps' request for more info letter.
Please be aware that this email is a formal request for information and stops our processing time clock until the
information is received:
Pursuant to Title 15A NCAC 02H.0502(e), the applicant shall furnish all of the above requested information for the
proper consideration of the application. Please respond in writing within 30 calendar dans of receipt of this letter by
sending one (1) copy of all of the above requested information to the 401 & Buffer Permitting Branch, 1617 Mail Service
Center, Raleigh, NC 2 7699-1 61 7 OR by submitting a# of the above requested information through this
link: https.//edocs.deg, nc.Rov/Forms/Supplemental-Information-Form (please note that the DWR#requested on the
link is referenced above) OR by direct response to this email.
if all of the requested information is not received within 30 calendar days of receipt of this letter, the Division will be
unable to approve the application and it will be returned. The return of this project will necessitate reapplication to the
Division for approval, including a complete application package and the appropriate fee.
Please be aware that you have no authorization under Section 401 of the Clean Water Act for this activity and any work
done within waters of the state may be a violation of North Carolina General Statutes and Administrative Code.
Please don't hesitate to reach out to me if you have any questions.
Thanks,
Paul
Paul Wojoski
401 & Buffer Permitting Branch
Division of Water Resources
Department of Environmental Quality
(919) 807-6364 office
Paul. W oioski(c�ncdenr.gov
512 N. Salisbury Street (Archdale Building), Suite 942-F, Raleigh, NC 27604
1617 Mail Service Center, Raleigh, NC 27699-1617
Kc. -''Nothing Compares
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
From: Thomas Brown[mailto:Thomas.Brown@martinmarietta.com]
Sent: Thursday, July 05, 2018 2:58 PM
To: Wojoski, Paul A <Paul.Wojoski@ncdenr.gov>
Cc: Phillip Pressley <PhilIip.Pressley@ma rtinmarietta.com>
Subject: [External] RE: Martin Marietta's Onslow Quarry Expansion (DWR# 20110309 V4)
Paul,
I just spoke with our Environmental Engineer for this district about this. The apron is actually outside of our Soft
wetland buffer, and will continue to be outside of this buffer when it is relocated. Being that it is only a 1" pipe, we do
not for see any problems in relocating its outlet. Please feel free to call or email if you have any other questions.
Thanks,
Thomas Brown, PWS
Sr. Environmental Engineer I Mid -Atlantic Division
Martin Marietta
2700 Wycliff Road Suite 104, Raleigh, NC 27607
m.(919) 268- 5297 t. (919) 783-4592 f. (919) 787-9577
e. Thomas. BrownPmartinmarietta.com
www.martinmarietta.com
From: Wojoski, Paul A [mailto:Paul.Woioski@ncdenr aov]
Sent: Thursday, July 5, 2018 2:38 PM
To: Thomas Brown <Thomas. Brown@ martinmarietta.com>
Subject: Martin Marietta's Onslow Quarry Expansion (DWR# 20110309 V4)
EXTERNAL MAIL
Mr. Brown —
I am nearly finished processing the 401 for Martin Marietta's Onslow Quarry Expansion (DWR# 20110309 V4) and had a
question:
The project proposes impacts to a wetland area for the re -alignment of a road to remove a blind turn in the south west
portion of the northern active pit. Upon consulting the DEMLR files, there appears to be a stromwater pond or
sedimentation basin in the vicinity that has an outlet pipe and riprap and it discharges to the wetland proposed to be
impacted. Where will the outlet be relocated? Will there be any impacts associated with its realignment? Will diffuse
flow still be maintained before entering the water resource?
Please let me know if you have any questions or would like to discuss.
Thank you,
Paul
Paul Wojoski
401 & Buffer Permitting Branch
Division of Water Resources
Department of Environmental Quality
(919) 807-6364 office
Paul. W oioski(5,ncdenr.gov
512 N. Salisbury Street (Archdale Building), Suite 942-F, Raleigh, NC 27604
1617 Mail Service Center, Raleigh, NC 27699-1617
e -�:�Nothing Compares.-._
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.