FACT SHEET FOR NPDES PERMIT DEVELOPMENT
Duke Energy Carolinas, LLC — Allen Steam Station
NC0004979
Facility Information
Applicant/FacilityName: Duke Energy Carolinas, LLC — Allen Steam Station
Applicant Address: P.O. Box 1006, Charlotte, North Carolina 28201
Facility Address: 253 Plant Allen Road, Belmont, North Carolina 28012
Permitted Flow No limit
Type of Waste: '100% industrial
Primary SIC Code: 4911 — Electric Services
Facility/Permit Status: Class I/Active; Renewal
County: Gaston County
Miscellaneous
Receiving Stream:
Catawba River (11-
Regional Office:
Mooresville
123.5), South Fork
Catawba River
ake W lie)
Stream Classification:
WS -IV B (Catawba
State Grid / USGS Quad:
G14 NE
River) and WS -V B
(South Fork
Catawba River
303(d) Listed?
Yes (Catawba River
Permit Writer:
Sergei Chernikov,
Only)
Ph.D.
Subbasin:
03-08-34
Date:
May 10, 2016
Drainage Area (miz):
635 (Catawba
River
AAMP
001: Lat. 35° 11' 23" N Long. 81° 00'45" W
002: Lat. 35° 10' 30" N Long. 81° 00'23" W
Summer 7Q10 (cfs)
95
Winter 7Q10 (cfs):
95
30Q2 (cfs)
314
Average Flow (cfs):
2470
IWC (%):
23.6 (Outfall 002
and Outfall 006)
002A: Lat. 35° 11'34" N Long. 81° 00' 22" W
00213: Lat. 35° 11' 36" N Long. 81° 00'30" W
004: Lat. 35° 11'35" N Long. 81° 00'22" W
006: Lat. 35° 11' 35" N Long. 81° 00'22" W
007: Lat. 35° 11' 55" N Long. 81° 00'36" W
008: Lat. 35° 10' 55" N Long. 81° 00'24" W
SUMMARY
This revised draft permit incorporates changes made subsequent to a Public Hearing held on April 8,
2015 seeking comments to the original draft NPDES wastewater permit renewal for Allen Steam
Station.
Duke Energy's Allen Steam Station is a coal fired steam electric plant in Gaston County. Units 1, 2,
and 3 are scheduled to retire by December 31, 2024.
The facility is subject to the effluent guidelines - 40 CFR 423.12. The facility is also subject to the
Cooling Water Intake Structure Rule (316(b) Rule) per 40 CFR 125.95 and Coal Ash Management
Act (State Law).
Page 1 of 15
NPDES Permit Fact Sheet
NC0004979
The facility proposes to build a new Retention Basin in 2018 to reroute all waste streams that are
currently discharged to the Ash Pond. This change is necessary to decommission the existing Ash
Pond and meet the requirements of Coal Ash Management Act. After the Retention Basin is
completed, all the waste streams previously discharged to Ash Pond will be re-routed to the
Retention Basin, and the discharges to Ash Pond will cease.
Outfall 001 is comprised of once through, non -contact condenser cooling water. This outfall
discharges to the South Fork Catawba River.
Outfall 002 is the ash basin discharge. This outfall includes domestic wastewater,
stormwater from the coal pile area, miscellaneous stormwater flows, ash sluice, wastewater
from turbine non-destructive testing, a yard drain sump, water treatment filter backwash,
treated groundwater, laboratory wastes, and the power house sump at Unit 5. The domestic
waste is pre-treated by a septic tank. Outfall 002 wastewater is treated using chemical
coagulation, settling, and pH neutralization. This outfall discharges to the Catawba River.
Upon construction of the new Retention Basin, the waste streams currently discharging
through Outfall 002 will be rerouted to the new Retention Basin (Outfall 006). This outfall
discharges to the Catawba River. Outfall 002 and Outfall 006 might be operational at the
same time during the transition period.
• Outfall 002A is an intermittent discharge of emergency overflows from coal yard sump
(discharge from coal handling and storage areas). This outfall discharges to the Catawba
River.
• Outfall 002B is an intermittent discharge of emergency overflows from power house sump
(floor wash water, boiler blowdown, water treatment waste, condensates, equipment cooling
water, sealing water and miscellaneous leakage). This outfall discharges to the Catawba River.
• Outfall 003 is miscellaneous once through non -contact cooling water and seal water. This
outfall discharges to the South Fork Catawba River.
• Outfall 004 is also miscellaneous once through non -contact cooling water. This outfall
includes a small amount of intake screen backwash and car wash rinse water. This outfall
discharges to the Catawba River.
• Outfall 005 is internal, discharging to the Ash Pond. It is comprised of flue gas
desulfurization wastewater. The treatment facilities at this outfall consist of flow
equalization, pH stabilization using lime addition, chemical precipitation, clarification, gravity
filtration, biological selenium removal, aerated sludge holding, and a sludge filter press.
Internal Outfall 005 and Internal Outfall 007 might be operational at the same time during
the transition period.
Proposed Outfall 006 is the new Retention Basin discharge. Upon construction of the new
Retention Basin, the waste streams currently discharging through Outfall 002 will be
rerouted to the new Retention Basin (Outfall 006). This outfall discharges to the Catawba
River. Outfall 002 and Outfall 006 might be operational at the same time during the
transition period.
This outfall includes domestic wastewater, stormwater from the coal pile area, miscellaneous
stormwater flows, ash sluice, wastewater from turbine non-destructive testing, a yard drain
sump, water treatment filter backwash, treated groundwater, laboratory wastes, and the
Page 2 of 15
NPDES Permit Fact Sheet NC0004979
power house sump at Unit 5. The domestic waste is pre-treated by a septic tank. Outfall
002 wastewater is treated using chemical coagulation, settling, and pH neutralization. This
outfall discharges to the Catawba River.
• Proposed Outfall 007 is the emergency spillway of the new Retention Basin. The spillway is
designed for a flood greater than 100 -year event. Sampling of this spillway is waived due to
unsafe conditions associated with sampling during overflow event. This outfall discharges to
the Catawba River.
• Proposed Outfall 008 is the emergency spillway of the retired Ash Pond. The spillway is
designed for a flood greater than 100 -year event. Sampling of this spillway is waived due to
unsafe conditions associated with sampling during overflow event. This outfall discharges to
the Catawba River.
• Proposed Toe Drain Outfalls 103, 104, 108, and 108B - 4 potentially contaminated toe
drains. These outfalls discharge to the Catawba River, except for outfall 104, which
discharges to unnamed tributary to Catawba River.
On December 15, 2016 the station personnel observed a minor drainage from a corrugated metal
pipe along Catawba River, the coordinates of the pipe are 35011'20.6" N, 8100'27.55" W. The facility
inspected the pipe and determined it is clogged by debris 10 feet from the opening. The flow from
this pipe is extremely small, only about 114 GPD. The analysis of the water indicate that most
parameters of concern are either below detection level or below water quality standards. Based on the
analysis of the sample and on the flow amount it is likely a groundwater infiltrating into the pipe.
The facility has grouted the pipe to eliminate discharge of the groundwater.
TOE DRAINS —OUTFALLS 103, 104, 108, and 108B
The facility identified 4 unpermitted toe drains from the ash settling basin.
The locations of the toe drains are identified below and are depicted on the map attached to the
permit.
Table 1. Discharge Coordinates and Assigned Outfall Numbers
Discharge ID of toe
drains
Latitude
Longitude
Outfall number
S-3
35010.512'
8100.360'
103
S-4
35110.541'
8100.364'
104
S-8
35010.710'
8100.384'
108
S -8B
35010.689'
8110.391'
108B
Page 3 of 15
NPDES Permit Fact Sheet
NC0004979
Each outfall discharges through its own effluent channel meeting the requirements in 15A NCAC 2B
.0228.
ASH POND DAMS
Seepage through earthen dams is common and is an expected consequence of impounding water
with an earthen embankment. Even the tightest, best -compacted clays cannot prevent some water
from seeping through them. Seepage is not necessarily an indication that a dam has structural
problems, but should be kept in check through various engineering controls and regularly monitored
for changes in quantity or quality which, over time, may result in dam failure.
REASONABLE POTENTIAL ANALYSIS IRPA)-OUTFALL 002, OUTFALL 006, OUTFALLS 103,
104,108 AND 108B.
The Division conducted EPA -recommended analyses to determine the reasonable potential for
toxicants to be discharged at levels exceeding water quality standards/EPA criteria by this facility.
For the purposes of the RPA, the background concentrations for all parameters were assumed to be
below detections level. The RPA uses 95% probability level and 95% confidence basis in accordance
with the EPA Guidance entitled "Technical Support Document for Water Quality -based Toxics
Control." The RPA included evaluation of dissolved metals' standards, utilizing a default hardness
value of 25 mg/L CaCO3 for hardness -dependent metals. The RPA spreadsheets are attached to this
Fact Sheet.
a) RPA for Decanting of Ash Pond (Outfall 002).
The RPA was conducted for decanting of Ash Pond, Calculations included: As, Be, Cd,
Chlorides, Total Phenolic Compounds, Cr, Cu, CN, Pb, Hg, Mo, Ni, Se, Ag, Zn, Co, Sulfate,
Ba, B, and Al (please see attached). The flow of 18.9 MGD was used in the RPA as the highest
reported flow during the last permit cycle. The RPA concludes that the limits for Ag are
necessary to protect the receiving stream. In addition, the WQBELs for Cu will be substituted
for TBELs, since WQBELs are more stringent.
b) RPA for Dewatering of Ash pond (Outfall 002).
To meet the requirements of the Coal Ash Management Act of 2014, the facility needs to
dewater ash ponds by removing the interstitial water. The facility's highest discharge rate
from the dewatering process will be 1.0 MGD. The facility submitted data for the standing
surface water in the ash ponds, interstitial water in the ash, and interstitial ash water that was
treated by filters of various sizes. To evaluate the impact of the dewatering on the receiving
stream the RPA was conducted for the wastewater that will be generated by the dewatering
process. To introduce the margin of safety, the highest measured concentration for a
particular parameter was used. The RPA was conducted for As, Cd, Chlorides, Cr, Cu, F, Pb,
Mo, Hg, Ni, Se, Zn, Sulfate, Ba, Sb, Tl, B, Al, and Pb (please see attached). The flow of 1.0
MGD was used in the RPA. The RPA indicated no need for water -quality based limits
during the dewatering phase.
c) RPA for Toe Drains (Outfalls 103, 104, 108, and 108B).
The RPA was also conducted for the combined Toe Drains 103, 108, and 108B flow.
Separate RPA was conducted for Toe Drain 104 because it is discharges to a different stream
(UT to Catawba River). Calculations included: As, Cd, Chlorides, Cr, Cu, F, Pb, Hg, Mo, Ni,
Se, Zn, Sulfate, Sb, Al, B, Ba, and Tl (please see attached). The analysis indicates no
reasonable potential to violate the water quality standards or EPA criteria for all toe drains.
The flow volume for the combined Toe Drains discharging to Catawba River (103, 108, and
108B) flow was measured at 0.0084 MGD during initial sampling. However, the flow of 0.1
MGD was used for the RPA to incorporate a safety factor and account for potential increase
Page 4 of 15
NPDES Permit Fact Sheet NC0004979
in flow volume. The flow volume for Toe drain 104 was measured 0.0008 MGD during
initial sampling. However, the flow of 0.01 MGD was used for the RPA to incorporate a
safety factor and account for potential increase in flow volume.
d) RPA for New Retention Basin (Outfall 006).
The RPA that was conducted for Outfall 002 was used for Outfall 006 since the Retention
Basin will be receiving all the waste streams that were previously discharged to Ash Pond.
The only change was the flow volume, the new basin is designed for 3.3 MGD, this number
was used for RPA.
The proposed permit requires that EPA methods 200.7 or 200.8 (or the most current versions) shall
be used for analyses of all metals except for total mercury.
FGD TECHNOLOGY BASED EFFLUENT LIMITS -INTERNAL OUTFALL 005 AND INTERNAL
OUTFALL 007.
The new federal 40 CFR 423 Technology Based Effluent Limits (TBELs) have been added to the
permit:
Total Arsenic — 8.0 µg/L (Monthly Average); 11.0 µg/L (Daily Maximum)
Total Selenium —12.0 µg/L (Monthly Average); 23.0 µg/L (Daily Maximum)
Total Mercury — 356.0 ng/L (Monthly Average); 788.0 ng/L (Daily Maximum)
Nitrate/nitrite as N — 4.4 mg/L (Monthly Average); 17.0 mg/L (Daily Maximum)
The federal rule 40 CFR 423 states that "dischargers must meet the effluent limitations for FGD
wastewater in this paragraph by a date determined by the permitting authority that is as soon as
possible beginning November 1, 2018, but no later than December 31, 2023".
Duke provided the justification for the proposed deadline of December 31, 2023 and the DWR
concurred with the compliance date. This deadline incorporates an uncertainty due to the proposed
EPA rulemaking that might result in different deadlines and/or BAT determinations.
The existing FGD system for the facility is unable to meet the proposed As and Se limit with 100%
consistency. Therefore, Duke needs to optimize the performance of the existing system or install the
membrane ultrafiltration to meet the proposed FGD limits with 100% compliance. Review of the
FGD discharge data from 1/1/2011 through 8/2/2016 indicates that:
a) Se daily maximum limit would have been violated 5 times out of 141 if it was implemented during
the last renewal.
b) As daily maximum limit would have been violated 17 times out of 68 if it was implemented during
the last renewal.
MERCURY EVALUATION- OUTFALL 002
The State of North Carolina has a state-wide mercury impairment. The TMDL has been developed
to address this issue in 2012. The TMDL included the implementation strategy, both documents were
approved by EPA in 2012.
The mercury evaluation was conducted in accordance with the Permitting Guidelines for Statewide
Mercury TMDL.
Year
2010
2011
2012
2013
2014
Annual average
concentration n /L
1.6
1.18
6.9
0.93
0.83
Maximum sampling
result n /L
2.4
1.8
22.6
1.6
1.0
Number of samples
4
4
4
4
3
Page 5 of 15
NPDES Permit Fact Sheet
NC0004979
The allowable mercury concentration for this facility is 50.9 ng/L. All annual average mercury
concentrations are below the allowable level. All maximum sampling results are below the TBEL of
47.0 ng/L. Based on the Permitting Guidelines for Statewide Mercury TMDL, the limits are not
required.
CWA SECTION 316(a) TEMPERATURE VARIANCE – OUTFALL 001
The facility has a temperature variance. In order to maintain the variance the facility has to conduct
annual biological and chemical monitoring of the receiving stream to demonstrate that it has a
balanced and indigenous macroinvertebrate and fish community. The latest BIP (balanced and
indigenous population) report was submitted to DWR in November of 2014. The DWR has
reviewed the report and concluded that the receiving stream near Allen Steam Station has a balanced
and indigenous macroinvertebrate and fish community.
CWA SECTION 316(b)
The permittee shall comply with the Cooling Water Intake Structure Rule per 40 CFR 125.95. The
Division approved the facility request for an alternative schedule in accordance with 40 CFR
125.95(a)(2). The permittee shall submit all the materials required by the Rule with the next renewal
application. The following materials shall be submitted:
— �122.21(r)(2) Source Water Physical Data
— �/22.21(r)(3) Cooling Water Intake Structure Data
— �122.21(r)(4) Source Water Baseline Biological Characterization Data
— �/22.21(r)(5) Cooling Water System Data
— �122.21(r)(6) Chosen Method(s) of Compliance with the Impingement Mortality
Standard (the chosen method will be defined after the site-specific BTA
determination is made)
— �122.21(r)(7) Entrainment Performance Studies
— �122.21(r)(8) Operational Status
— 122.21(r) (9) Entrainment Characterization Study
— �122.21(r)(10) Comprehensive Technical Feasibility and Cost Evaluation Study
— �122.21(r)(11) Benefits Valuation Study
—�122.21(r)(12) Non -water Quality and Other Environmental Impacts Study
Currently, the facility withdraws a water for all five units through a single CWIS located in a small
embayment on the west bank of Lake Wylie. The CWIS is flush with the shoreline and is
approximately 247.2 feet long. The CWIS is divided into 15 screens bays, three per unit. Each screen
bay is 14 feet wide and equipped with a trash rack and traveling water screen.
The trash racks prevent large debris from entering the CWIS protects the traveling screens from
damage. Typically, debris loading on the trash racks is minimal. Top elevation of the trash racks is
580 feet with an overall height of 34.5 feet. The width of each trash rack is approximately 14 feet.
The trash rack bars are made of steel bars that are 4 inches by 0.375 inch spaced 3 -inches on center,
which provides 2.6 -inch clear bar spacing.
After water flows through the trash racks, it then passes through an isolation gate. The dimensions
for the isolations gates are as follows:
Units 1 and 2: six feet by eight feet
• Units 3, 4, and 5: eight feet by eight feet
Page 6 of 15
NPDES Permit Fact Sheet
NC0004979
Downstream of the isolation gates, are 15 traveling screens - three traveling screens per unit. Each
screen is ten feet wide with an invert elevation of 544.5 feet. The intake bays constrict down to 11
feet 2 inches wide at the traveling screens compared to the approximately 14 feet wide at the trash
racks. The traveling screens consist of #12 gauge wire mesh with 3/8 inch square mesh openings. A
high-pressure front wash spray system is used to remove impinged fish and debris from the traveling
screens. The fish is returned through front trough that travels —421 ft south of CWIS where it joins a
72 inch corrugated metal drain pipe and travels an additional —374 ft back to the lake.
Each unit has two circulating water pumps located downstream of the traveling screens.
The rule requires the Director to establish interim BTA requirements in the permit on a site-specific
basis based on the Director's best professional judgment in accordance with 5125.90(b) and 40 CFR
401.14.
The modified traveling screens with the fish return system is one of the pre -approved compliance
alternatives for impingement. The rule requires to make a site specific determination for entrainment.
In the absence of the comprehensive information required by the 316(b) rule the DEQ has
determined that the existing traveling screen system which includes a fish handling return system
meets the criteria of the interim BTA.
INSTREAM MONITORING -OUTFALL 002
The permit required semi-annual upstream and downstream monitoring near the ash pond discharge.
The upstream site (Station 250) is approximately 1.1 miles upstream of the discharge and
downstream location (Station 235) is approximately 3 miles downstream of the discharge. These
monitoring stations have been established through the BIP monitoring program, which was required
to maintain the 316(a) temperature variance. The monitored parameters are: As, Cd, Cr, Cu, Hg, Pb,
Se, Zn, turbidity, and Total Dissolved Solids (TDS). The majority of the results are below detection
level (Hg, As, Cd, Cr, Pb, Se), the rest of the results are below water quality standards (Cu, Zn, TDS).
No parameter demonstrated any increase in the concentration at the monitoring stations below the
discharge.
It is required that the monitoring of the instream stations will continue during the next permit cycle.
It is also required that the facility uses low level method 1631E for all Hg analysis.
FISH TISSUE MONITORING -NEAR OUTFALL 002
The permit required fish tissue monitoring for As, Se, and Hg near the ash pond discharge once
every 5 years. This frequency is consistent with EPA guidance. Redear sunfish and largemouth bass
tissues were analyzed for these trace elements. The results were below action levels for Se and Hg
(10.0 µg/g — Se, 0.4 µg/g — Hg, NC) and screening value for As (1.2 — µg/g, EPA). These results are
consistent with the previous monitoring results.
TOXICITY TESTING -OUTFALL 002 AND OUTFALL 006
Current Requirement: Outfall 002 — Chronic P/F @ 20% using Ceriodaphnia
Recommended Requirement: Outfall 002 — Chronic P/F @ 23.6% using Ceriodaphnia
Outfall 006 — Chronic P/F @ 23.6% using Ceriodaphnia
This facility has passed all toxicity tests during the previous permit cycle (20 out of 20), please see
attached.
The Division will increase the Instream Waste Concentration from 20% to 23.6% due to the increased
wastewater flow, reported as 18.9 MGD. For the purposes of the permitting, the long term average
Page 7 of 15
NPDES Permit Fact Sheet
NC0004979
flow was used in conjunction with the 7Q10 summer flow was used to calculate the percent effluent
concentrations to be used for WET.
COMPLIANCE SUMMARY
During the last permit cycle, the facility has exceeded limits 4 times, please see attached. Three limit
violations were for temperature (Outfall 001) and one limit violation was for Fe (Outfall 002).
PERMIT LIMITS DEVELOPMENT
• The temperature limits (Outfall 001) are based on the North Carolina water quality standards
(15A NCAC 2B.0200) and 316(a) Thermal Variance.
• The limits for Oil and Grease and Total Suspended Solids (Outfalls 002, 002A, 002B, 004
(oil and grease only), 006, 103, 104, 108, and 108B) were established in accordance with 40
CFR 423.
• The BOD limits (Outfalls 002, 002A, and 006) were established in accordance with 40 CFR
122.123.
• The pH limits (Outfalls 002, 002A, 002B, 006, 103, 104, 108, and 108B) in the permit are
based on the North Carolina water quality standards (15A NCAC 2B .0200).
• The fecal coliform limits (Outfall 002 and Outfall 006) in the permit are based on the North
Carolina water quality standards (15A NCAC 2B .0200).
• The limits for Total Copper and Total Iron (Outfalls 002, 002A, 002B, and 006) were
established in accordance with 40 CFR 423.
• The turbidity limit in the permit (Outfall 002) is based on the North Carolina water quality
standards (15A NCAC 2B .0200).
• The total silver limits in the permit (Outfall 002) are based on the North Carolina water
quality standards (15A NCAC 2B .0200).
• The Technology Based Effluent Limits for Total Arsenic, Total Mercury, Total Selenium,
and Nitrate/nitrite as N (Outfall 005 and Outfall 007) are based on the requirements of 40
CFR 123.
• The Whole Effluent Toxicity limit (Outfall 002 and Outfall 006) is based on the
requirements of 15A NCAC 2B .0500.
PROPOSED CHANGES
• The Toe Drains Outfalls 103, 104, 108, and 108B (Please see A. (12.), A. (13.), A. (14.), and
A. (15.)) were added to the permit.
• The turbidity limit was added to the permit (Outfall 002) to meet the state turbidity standard
per 15A NCAC 2B.0211(3) (k).
• The pH limits were added to the permit (Outfalls 002A and 002B) to meet the state pH
standard per 15A NCAC 2B .0200.
• The Technology Based Effluent Limits for Total Arsenic, Total Mercury, Total Selenium,
and Nitrate/nitrite as N were added to the permit (Outfall 005) and are based on the
requirements of 40 CFR 123.
• Monitoring for Chlorides was removed from the permit (Outfall 002) based on the results of
Reasonable Potential Analysis.
• Monitoring for COD, Total Cadmium, Total Chromium, Chlorides, Total Nickel, Total
Silver, Total Zinc and Total Beryllium was removed from the permit (Internal Outfall 005)
based on the results of the discharge evaluation.
• Federal regulations require electronic submittal of all discharge monitoring reports (DMRs)
and program reports. The final NPDES Electronic Reporting Rule was adopted and became
effective on December 21, 2015. The requirement to begin reporting discharge monitoring
Page 8 of 15
NPDES Permit Fact Sheet
NC0004979
data electronically using the NC DWR's Electronic Discharge Monitoring Report (eDMR)
internet application has been added to your final NPDES permit. [See Special Condition
A. (26.)]
For information on eDMR, registering for eDMR and obtaining an eDMR user account,
please visit the following web page: http: / /deq.nc.gov/about/divisions /water-
resources/edmr.
For more information on EPA's final NPDES Electronic Reporting Rule, please visit the
following web site: htWs://www.federalregister.gov/documents/2015/10/22/2015-
24954 /national-pollutant-discharge-elimination-system-npdes-electronic-reporting-rule
• The Applicable State Law Special Condition was added to the permit to meet the requirements
of Senate Bill 729 (Coal Ash Management Act, please see Special Condition A. (27.)).
• The Additional Conditions and Definitions Special Condition was added to the permit. Please
see Special Condition A. (19).
• Monitoring for Bromide was added to the Outfall 002 and the Instream Monitoring Special
Condition (Please see A. (24.)) to address the comment from the Public Water Supply Section.
• Monitoring for Hardness was added to Outfall 002 and the Instream Monitoring Special
Condition A. (24.) to assist in implementation of the new dissolved standards.
• The Outfall 006 was added to the permit to accommodate a future retention basin discharge.
• The IWC for the Whole Effluent Toxicity Test (Outfall 002) was increased to 23.6% based on
the new flow data.
• The monitoring frequency for the Whole Effluent Toxicity was increased to Monthly (Outfall
002 -dewatering) to address the EPA comment.
• The monitoring frequency for the Total Arsenic, Total Selenium, and Total Mercury was
increased to Weekly (Outfall 002 - dewatering) to address the EPA comment.
• The monitoring frequency for the Total Arsenic, Total Selenium, Total Mercury, and
Nitrate/nitrite was reduced to Quarterly based on the evaluation of the effluent data (Internal
Outfall 005).
• The daily maximum limit for TSS was reduced to 50.0 mg/L (Outfall 002) to meet the
requirements of 40 CFR 423.
• The Decanting and Dewatering Special Conditions in the footnotes were added to Outfall
002, please see A. (2.) and A. (3.).
• The Outfall 008 was added to the permit to accommodate discharge from the emergency
spillway of the retired Ash Pond.
• The total silver limits were added to the permit (Outfall 002) based on the results of the
Reasonable Potential Analysis.
• The groundwater compliance boundary map was added to the permit.
• The Compliance Boundary special condition was added to the permit, please see A. (28.).
• Monitoring frequency for fish tissue sampling was reduced from once every five years to
annually.
OPROPOSED SCHEDULE
Draft Permit to Public Notice: April 18, 2018 (est.)
Permit Scheduled to Issue: June 18, 2018 (est.)
STATE CONTACT
If you have any questions on any of the above information or on the attached permit, please contact
Sergei Chernikov at (919) 807-6386 or sergei.chernikovnncdenr.gov.
Page 9 of 15
NPDES Permit Fact Sheet NC0004979
CHANGES IN THE FINAL PERMIT
To address the public comments, the following changes have been made in the final permit:
1) The monitoring frequency for As, Se, Hg, and Ag were reduced to weekly from monthly
(Outfall 002 — normal operation/decanting).
2) The downstream monitoring location was relocated closer to the ash pond discharge; the
sampling will be conducted 250 meters below Outfall 002.
3) The schedule to submit documentation required for 316(b) was reduced to 3.5 years.
4) The compliance date for the latest updates to 40 CFR 423 was changed to February 28,
2020.
5) The new requirement for the decanting and dewatering stages was added to the permit. The
facility shall immediately discontinue the discharge and report to the DEQ if the identified
pollutants of concern reach 85% of the allowable level.
6) The requirement to select a new cold water reference area for the next 316(a) study was
added to the permit.
7) The instream monitoring frequency was increased to monthly from semi-annually.
Page 10 of 15
NPDES Permit Fact Sheet
NC0004979
NPDES Implementation of Instream Dissolved Metals Standards - Freshwater
Standards
The NC 2007-2015 Water Quality Standard (WQS) Triennial Review was approved by the NC Environmental
Management Commission (EMC) on November 13, 2014. The US EPA subsequently approved the WQS
revisions on April 6, 2016, with some exceptions. Therefore, metal limits in draft permits out to public notice
after April 6, 2016 must be calculated to protect the new standards - as approved.
Table 1. NC Dissolved Metals Water Quality Standards/Aquatic Life Protection
Parameter
Acute FW, µg/l
(Dissolved)
Chronic FW, µg/l
(Dissolved)
Acute SW, µg/l
(Dissolved)
Chronic SW, µg/l
(Dissolved)
Arsenic
340
150
69
36
Beryllium
65
6.5
---
---
Cadmium
Calculation
Calculation
40
8.8
Chromium I1I
Calculation
Calculation
---
---
Chromium VI
16
11
1100
50
Copper
Calculation
Calculation
4.8
3.1
Lead
Calculation
Calculation
210
8.1
Nickel
Calculation
Calculation
74
8.2
Silver
Calculation
0.06
1.9
0.1
Zinc
Calculation
Calculation
90
81
Table 1 Notes:
1. FW= Freshwater, SW= Saltwater
2. Calculation = Hardness dependent standard
3. Only the aquatic life standards listed above are expressed in dissolved form. Aquatic
life standards for Mercury and selenium are still expressed as Total Recoverable
Metals due to bioaccumulative concerns (as are all human health standards for all
metals). It is still necessary to evaluate total recoverable aquatic life and human
health standards listed in 15A NCAC 213.0200 (e.g., arsenic at 10 µg/l for human
health protection; cyanide at 5 µg/L and fluoride at 1.8 mg/L for aquatic life
protection).
Table 2. Dissolved Freshwater Standards for Hardness -Dependent Metals
The Water Effects Ratio (WER) is equal to one unless determined otherwise
under 15A NCAC 0213 .0211 Subparagraph (11)(d)
Metal
NC Dissolved Standard, µ /l
Cadmium, Acute
WER*11.136672-[ln hardness](0.041838)1 e^10.9151 [ln hardness] -
3.14851
Cadmium, Acute Trout
waters
WER*{1.136672-[In hardness](0.041838)1 e^10.9151[ln hardness] -
3.62361
Cadmium, Chronic
WER*{1.101672-[In hardness](0.041838)1 e^10.7998[ln hardness] -
4.44511
Chromium III, Acute
WER*0.316 e^10.8190[ln hardness] +3.72561
Chromium III, Chronic
WER*0.860 e^10.8190[ln hardness] +0.68481
Page 11 of 15
NPDES Permit Fact Sheet
NC0004979
Copper, Acute
WER*0.960 e"{0.9422[ln hardness] -1.700}
Copper, Chronic
WER*0.960 e^ 10.8545[/n hardness] -1.702}
Lead, Acute
WER* { 1.46203- [ln hardness] (0.145712)1 e^ { 1.273 [ln hardness]-
ardness]-
1.4601
1.460}
Lead, Chronic
WER* { 1.46203- [ln hardness] (0.145712)) e^ { 1.273 [ln hardness]-
ardness]-
4.7051
4.705}
Nickel, Acute
WER*0.998 e^{0.8460[ln hardness] +2.2551
Nickel, Chronic
WER*0.997 e^{0.8460[ln hardness] +0.05841
Silver, Acute
WER*0.85 • e^ 11.72[/n hardness] -6.59}
Silver, Chronic
Not applicable
Zinc, Acute
WER*0.978 e^{0.8473[In hardness] +0.8841
Zinc, Chronic
WER*0.986 e^{0.8473[ln hardness] +0.8841
General Information on the Reasonable Potential Analysis (RPA)
The RPA process itself did not change as the result of the new metals standards. However,
application of the dissolved and hardness -dependent standards requires additional
consideration in order to establish the numeric standard for each metal of concern of each
individual discharge.
The hardness -based standards require some knowledge of the effluent and instream
(upstream) hardness and so must be calculated case-by-case for each discharge.
Metals limits must be expressed as `total recoverable' metals in accordance with 40 CFR
122.45(c). The discharge -specific standards must be converted to the equivalent total values
for use in the RPA calculations. We will generally rely on default translator values developed
for each metal (more on that below), but it is also possible to consider case -specific
translators developed in accordance with established methodology.
RPA Permitting Guidance/WOBELs for Hardness -Dependent Metals - Freshwater
The RPA is designed to predict the maximum likely effluent concentrations for each metal of concern, based
on recent effluent data, and calculate the allowable effluent concentrations, based on applicable standards and
the critical low -flow values for the receiving stream.
If the maximum predicted value is greater than the maximum allowed value (chronic or
acute), the discharge has reasonable potential to exceed the standard, which warrants a
permit limit in most cases. If monitoring for a particular pollutant indicates that the pollutant
is not present (i.e. consistently below detection level), then the Division may remove the
monitoring requirement in the reissued permit.
To perform a RPA on the Freshwater hardness -dependent metals the Permit Writer
compiles the following information:
Page 12 of 15
NPDES Permit Fact Sheet
NC0004979
• Critical low flow of the receiving stream, 7Q10 (the spreadsheet
automatically calculates the 1Q10 using the formula 1Q10 = 0.843 (s7Q10,
cfs) 0.993
• Effluent hardness and upstream hardness, site-specific data is preferred
• Permitted flow
• Receiving stream classification
2. In order to establish the numeric standard for each hardness -dependent metal of
concern and for each individual discharge, the Permit Writer must first determine
what effluent and instream (upstream) hardness values to use in the equations.
The permit writer reviews DMR's, Effluent Pollutant Scans, and Toxicity Test results
for any hardness data and contacts the Permittee to see if any additional data is
available for instream hardness values, upstream of the discharge.
If no hardness data is available, the permit writer may choose to do an initial
evaluation using a default hardness of 25 mg/L (CaCO3 or (Ca + Mg)). Minimum
and maximum limits on the hardness value used for water quality calculations are 25
mg/L and 400 mg/L, respectively.
If the use of a default hardness value results in a hardness -dependent metal showing
reasonable potential, the permit writer contacts the Permittee and requests 5 site-
specific effluent and upstream hardness samples over a period of one week. The
RPA is rerun using the new data.
The overall hardness value used in the water quality calculations is calculated as follows:
Combined Hardness (chronic)
_ (Permitted Flow. cfs *Avg. Effluent Hardness. mg/4 + (s7010; cfs *Avg. Upstream Hardness. mg/4
(Permitted Flow, cfs + s7Q10, cfs)
The Combined Hardness for acute is the same but the calculation uses the 1Q10 flow.
3. The permit writer converts the numeric standard for each metal of concern to a total
recoverable metal, using the EPA Default Partition Coefficients (DPCs) or site-
specific translators, if any have been developed using federally approved
methodology.
Page 13 of 15
NPDES Permit Fact Sheet
4. The
NC0004979
EPA default partition coefficients or the "Fraction Dissolved" converts the value for
dissolved metal at laboratory conditions to total recoverable metal at in -stream ambient
conditions. This factor is calculated using the linear partition coefficients found in The
Metals Translator: Guidance for Calculating a Total Recoverable Permit Limit from a
Dissolved Criterion (EPA 823-B-96-007, June 1996) and the equation:
Cdis --I
Ctotal 1 + { [Kpo] [sslt+a>] [10-6] }
Where:
ss = in -stream suspended solids concentration [mg/1], minimum of 10 mg/L used, and
Kpo and a = constants that express the equilibrium relationship between dissolved and
adsorbed forms of metals. A list of constants used for each hardness -dependent metal can
also be found in the RPA program under a sheet labeled DPCs.
numeric standard for each metal of concern is divided by the default partition
coefficient (or site-specific translator) to obtain a Total Recoverable Metal at ambient
conditions.
In some cases, where an EPA default partition coefficient translator does not exist
(ie. silver), the dissolved numeric standard for each metal of concern is divided by
the EPA conversion factor to obtain a Total Recoverable Metal at ambient
conditions. This method presumes that the metal is dissolved to the same extent as it
was during EPA's criteria development for metals. For more information on
conversion factors see the June, 1996 EPA Translator Guidance Document.
5. The RPA spreadsheet uses a mass balance equation to determine the total allowable
concentration (permit limits) for each pollutant using the following equation:
Ca = (s7O10 + Owl (Cwas) — (s7O10) (Cb
Qw
Where: Ca = allowable effluent concentration (µg/L or mg/L)
Cwqs = NC Water Quality Standard or federal criteria (µg/L or mg/L)
Cb = background concentration: assume zero for all toxicants except NH3* (µg/L or mg/L)
Qw = permitted effluent flow (cfs, match s7Q10)
s7Q10 = summer low flow used to protect aquatic life from chronic toxicity and human health
through the consumption of water, fish, and shellfish from noncarcinogens (cfs)
* Discussions are on-going with EPA on how best to address background concentrations
Flows other than s7Q10 may be incorporated as applicable:
1Q10 = used in the equation to protect aquatic life from acute toxicity
QA = used in the equation to protect human health through the consumption of water, fish,
and shellfish from carcinogens
30Q2 = used in the equation to protect aesthetic quality
Page 14 of 15
NPDES Permit Fact Sheet
NC0004979
6. The permit writer enters the most recent 2-3 years of effluent data for each pollutant
of concern. Data entered must have been taken within four and one-half years prior
to the date of the permit application (40 CFR 122.21). The RPA spreadsheet
estimates the 95th percentile upper concentration of each pollutant. The Predicted
Max concentrations are compared to the Total allowable concentrations to
determine if a permit limit is necessary. If the predicted max exceeds the acute or
chronic Total allowable concentrations, the discharge is considered to show
reasonable potential to violate the water quality standard, and a permit limit (Total
allowable concentration) is included in the permit in accordance with the U.S.
EPA Technical Support Document for Water Quality -Based Toxics Control
published in 1991.
7. When appropriate, permit writers develop facility specific compliance schedules in
accordance with the EPA Headquarters Memo dated May 10, 2007 from James
Hanlon to Alexis Strauss on 40 CFR 122.47 Compliance Schedule Requirements.
8. The Total Chromium NC WQS was removed and replaced with trivalent chromium
and hexavalent chromium Water Quality Standards. As a cost savings measure, total
chromium data results may be used as a conservative surrogate in cases where there
are no analytical results based on chromium III or VI. In these cases, the projected
maximum concentration (95th %) for total chromium will be compared against water
quality standards for chromium III and chromium VI.
9. Effluent hardness sampling and instream hardness sampling, upstream of the
discharge, are inserted into all permits with facilities monitoring for hardness -
dependent metals to ensure the accuracy of the permit limits and to build a more
robust hardness dataset.
10. Hardness and flow values used in the Reasonable Potential Analysis for this permit
included:
Parameter
Value
Comments (Data Source)
Average Effluent Hardness
(mg/L)
25.0
Default value
[Total as, CaCO3 or (Ca+M )]
Average Upstream Hardness
(mg/L)
25.0
Default value
[Total as, CaCO3 or (Ca+M )]
7Q10 summer (cfs)
0
Lake or Tidal
1Q10 cfs
0
Lake or Tidal
Permitted Flow (MGD)
2.1
For dewatering
Page 15 of 15