HomeMy WebLinkAboutNCG020922_Email RE NOI - POM Plan Status to WiRO_20180622Georgoulias, Bethany From: Lambe, Brian Sent: Friday, June 22, 2018 10:39 AM To: Georgoulias, Bethany Subject: RE: NCG020922 NOI - Pumping O&M Plan? No, it is in the engineer's hands for response, namely the wetland delineation. Brian Lambe Environmental Specialist 910-796-7313 State of North Carolina I Environmental Quality I Energy, Mineral and Land Resources 127 Cardinal Drive Extension I Wilmington, NC 28405 910 796 7215 T 1910 350 2004 F I htty://portal.ncdenr.oreweb/lr/ From: Georgoulias, Bethany Sent: Friday, June 22, 2018 9:07 AM To: Lambe, Brian <brian.lambe@ncdenr.gov> Cc: Wunderly, Valerie <valerie.wunderly@ncdenr.gov> Subject: RE: NCG020922 NOI - Pumping O&M Plan? Brian, do you have any updates on this? We are still holding issuance of the NCG02 General Permit coverage for this site. Thanks, Bethany From: Lambe, Brian Sent: Wednesday, April 11, 2018 2:16 PM To: Georgoulias, Bethany<bethany.georgoulias@ncdenr.gov> Subject: RE: NCG020922 NOI - Pumping O&M Plan? No, I spoke to Dave's boss Noah about this yesterday. They do want to address it, just lacking on follow through. Brian Lambe Environmental Specialist 910-796-7314 State of North Carolina I Environmental Quality I Energy, Mineral and Land Resources 127 Cardinal Drive Extension I Wilmington, NC 28405 910 796 7215 T 1910 350 2004 F I httn://portal.ncdenr.org/web/lr/ From: Georgoulias, Bethany Sent: Wednesday, April 11, 2018 9:49 AM To: Lambe, Brian <brian.lambe@ncdenr.gov> Cc: Lucas, Annette <annette.lucas@ncdenr.gov> Subject: NCG020922 NOI - Pumping O&M Plan? Hi, Brian, 1 This NCG02 NOI application (North River Club Mine) has been pending for a while. Has the Engineering firm that Dave referred to down there submitted anything to WiRO for approval? I will continue to hold until you all advise further. Thanks, Bethany Bethany Georgoulias Environmental Engineer Stormwater Program, Division of Energy, Mineral, and Land Resources N.C. Department of Environmental Quality 919 807 6372 office bethanygeor oulias e ncdenr.gov 1612 Mail Service Center, Raleigh, NC 27699-1612 (mailing) 512 N. Salisbury Street, Raleigh, NC 27604 (location) Website: http://deq.nc.gov/about/divisions/energy-mineral-land-resources/stormwater Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. From: Dave Gambardella[mailto:dave@thomassimpsonconstruction.com] Sent: Tuesday, January 09, 2018 3:18 PM To: Georgoulias, Bethany<bethany.georgoulias@ncdenr.gov> Cc: 'Noah Simpson' <noah@thomassimpsonconstruction.com>; 'Ginger Turner' <gturner@stroudengineer.com> Subject: RE: [External] RE: NCG020922 Renewal Inquiry CAUTION: External email. Do not click links or open attachments unless verified. Send all suspicious email as an attachment to report.spam@nc.gov. Hey Bethany, I've referred this to our engineer Stroud Engineering to answer questions on the cone of influence as that is outside my realm of knowledge. They should be contacting you. Thanks Dave Gambardella, PM Thomas Simpson Construction 2401 Arendell St Morehead City, NC 28557 252-247-4401— Office 252-247-0184 — Fax 252-723-9949 — Cell Confidentiality Notice: This email may contain confidential and/or private information. If you received this email in error please delete and notify sender. From: Georgoulias, Bethany [mailto:bethany.georgoulias@ncdenr.gov] Sent: Tuesday, January 09, 2018 9:01 AM To: Dave Gambardella <dave@thomassimpsonconstruction.com> Subject: RE: [External] RE: NCG020922 Renewal Inquiry Dave, I apologize for the delay in returning your call. I was out of the office most of last week because of school delays and closings, and I have a family member that's been home sick this week. Our staff are all trying to catch up from the disruptions last week. I have two meetings this morning and will be in touch as soon as I'm able to. I contacted Shellfish Sanitation before the holidays, and I owe a call to Andy Haines today to discuss, so our office has progressed on the step of obtaining their approval. Have you been in touch with Brian Lambe at the Regional Office about the Pumping O&M Plan? I saw that the one sent was missing some key information, e.g., there was no mention of monitoring wells to ensure wetlands are not impacted or calculations of a cone of influence. These are items listed at the end of the NOI, and I communicated this to Brian on December 20th. Ultimately WiRO will have to approve the plan before dewatering can begin, and they advise the Central Office on whether we can issue a COC sooner (with the stipulation that dewatering can only begin upon Pumping Plan approval). This is normally only done when DEQ is assured the applicant understands all the necessary pieces of the Plan. I phone you as soon as I'm able to follow up. Thanks, Bethany Georgoulias Environmental Engineer Stormwater Program, Division of Energy, Mineral, and Land Resources N.C. Department of Environmental Quality 919 807 6372 office bethanygeor oulias e ncdenr.gov 1612 Mail Service Center, Raleigh, NC 27699-1612 (mailing) 512 N. Salisbury Street, Raleigh, NC 27604 (location) Website: http://deq.nc.gov/about/divisions/energy-mineral-land-resources/stormwater Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. From: Dave Gambardella [mailto:dave@thomassimpsonconstruction.com] Sent: Tuesday, December 19, 2017 4:29 PM To: Georgoulias, Bethany <bethany.georgoulias@ncdenr.gov> Cc: Lambe, Brian <brian.lambe@ncdenr.gov>; 'Noah Simpson' <nosh@thomassim psonconstruction.com> Subject: RE: [External] RE: NCG020922 Renewal Inquiry CAUTION: External email. Do not click links or open attachments unless verified. Send all suspicious email as an attachment to report.spam@nc.gov. Bethany, Please see the attached revised NOI Pages, and our pumping O & M plan. Contact me with any questions or concerns. Thank You Dave Gambardella, PM Thomas Simpson Construction 2401 Arendell St Morehead City, NC 28557 252-247-4401— Office 252-247-0184 — Fax 252-723-9949 — Cell Confidentiality Notice: This email may contain confidential and/or private information. If you received this email in error please delete and notify sender. From: Georgoulias, Bethany[mailto:bethany.georgoulias@ncdenr.gov] Sent: Friday, December 15, 2017 10:18 AM To: Dave Gambardella<dave@thomassimpsonconstruction.com> Cc: Lambe, Brian <brian.lambe@ncdenr.gov> Subject: RE: [External] RE: NCG020922 Renewal Inquiry Dave, Thank you for the additional information —this is helpful. We still need answers c) (2) and (3) on the NOI page, though. They do not need to be long, but the section does need to be completed. You referred to an another NOI or permit, but this is an application for a new NPDES permit. I don't see any record of existing NCG02 permit coverage for this mine. If there had been an application in the past but a permit never issued, we would not be using any other documents or plans previously submitted. The Mining and Capacity Use permits are completely separate from the NPDES permit. Because of the dewatering and the wetlands indicated nearby and dewatering taking place, a pumping operation & monitoring plan will be necessary. The nearest receiving waters appear to be Wading Creek, a class SA;HQW waters. Because these are shellfishing waters, we also need approval by DMF's Shellfish Sanitation section before issuing an NPDES permit (standard procedure and also required by our rules). I've included a screen shot below. We will include a request to them during our review once we have all additional information. You will need to work with the Wilmington Regional Office to develop and submit a Pumping O&M Plan. I've copied Brian Lambe at WiRO so you can get in touch for more information, but the items required for that are listed on the back page of the NOI. The WiRO will have to approve that before operation can begin. I have a meeting this morning, but I'll be in later today until 2:30 pm, and also next week Monday — Wednesday if you would like to talk more. Uld !i5w-L ir' G - 1 rli^$ .as Cow 4n �4 i:A Nrpr,ae Ln a 1gi�r14 �r{y $5nr� �r oncir -• WPM ?M,.rCW4 C r.itw famsk Rd Suriaco WAor Cimsshlca iamr Deffflp:30-M- ROM HWNPor Rivar r Clre�iFeaaon: �.3 SA,HQW dine MOni.. May S'.. 1956 F{iMr �ahry.White Dr1€ WHR dm" *4 CEJfi FB2210l2 mean? L �x Best regards, Bethany Georgoulias Environmental Engineer Stormwater Program, Division of Energy, Mineral, and Land Resources N.C. Department of Environmental Quality 919 807 6372 office bethanygeor oulias e ncdenr.gov 1612 Mail Service Center, Raleigh, NC 27699-1612 (mailing) 512 N. Salisbury Street, Raleigh, NC 27604 (location) Website: httD:Hdea.nc.Lyov/about/divisions/enerLv-mineral-land-resources/stormwater Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. 5 From: Dave Gambardella [mailto:dave@thomassimpsonconstruction.com] Sent: Wednesday, December 13, 2017 4:22 PM To: Georgoulias, Bethany<bethany.georgoulias@ncdenr.gov> Subject: RE: [External] RE: NCG020922 Renewal Inquiry CAUTION: External email. Do not click links or open attachments unless verified. Send all suspicious email as an attachment to report.spam@nc.gov. Bethany, Please see the attached documentation on the North River Club permit and the Simpson mine permit info I have attached a siteplan showing what we would like to do. The north River Club received an NOI in 2012 before it went bankrupt which preceded my entry into this project. The only change we would like to make is dewatering the mine to the south instead of the north. I do not know if there was ever an official wetlands delimitation done on the site again due to the property switching hands in bankruptcy, and I do not know if there was a pumping O& M plan done during the original review. I will call Thursday or Friday to go over this if you will be available. Thanks Dave Gambardella, PM Thomas Simpson Construction 2401 Arendell St Morehead City, NC 28557 252-247-4401— Office 252-247-0184 — Fax 252-723-9949 — Cell Confidentiality Notice: This email may contain confidential and/or private information. If you received this email in error please delete and notify sender. From: Georgoulias, Bethany [mailto:bethany.georgoulias@ncdenr.gov] Sent: Wednesday, December 13, 2017 2:45 PM To: Dave Gambardella <dave@thomassimpsonconstruction.com> Subject: RE: [External] RE: NCG020922 Renewal Inquiry Dave, Yes, there is a need for a dewatering NPDES permit in this case. Any potential to discharge of wastewater, even if it would be rare, triggers the requirement for an NPDES permit. In this case there is also dewatering near wetlands, which needs to be addressed in a Pumping Operation Monitoring Plan. We will need additional information for this application: • On the last page of the NOI, there is a check next to "2 copies of large scale (minimum 24" x 36") site plan with topographic lines with all outfalls..."; however, no site plans were included. Please provide a site plan, and include the location where overflows would occur from the pond in a very large event — this will be the most appropriate outfall point for mine dewatering water. Please review the attached marked up aerial plan and let me know if this will suffice • Aline drawing water flow through the facility or block flow diagram. (No drawing was included, and this item was not checked). This information can be included on the site plan. Please review the marked up aerial site plan • The Wastewater Treatment Alternatives section of the NOI (Question 38) needs to be completed for mine dewatering discharges. Please revise this section of the NOI application. I have attached the revised pages • The NOI application indicates that wetlands are 320' from the mine pit. However, the last page of the NOI only has a check next to the statement that indicates the operation will not impact any nearby wetlands, instead of any information about a Pumping O&M Plan. Did you verify with the Wilmington Regional Office that a Pumping O&M Plan was not necessary? Who was the RO contact? I will request input from the WiRO specifically on this item before issuing the permit, so please be aware that if it is required, the POM Plan must be approved by the RO before operation can begin. See answer above. Please let me know if you have any questions. Thank you, Bethany Georgoulias Environmental Engineer Stormwater Program, Division of Energy, Mineral, and Land Resources N.C. Department of Environmental Quality 919 807 6372 office bethanygeor oulias e ncdenr.gov 1612 Mail Service Center, Raleigh, NC 27699-1612 (mailing) 512 N. Salisbury Street, Raleigh, NC 27604 (location) Website: http://deq.nc.gov/about/divisions/energy-mineral-land-resources/stormwater Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. From: Dave Gambardella[mailto:dave@thomassimpsonconstruction.com] Sent: Thursday, December 07, 2017 2:26 PM To: Georgoulias, Bethany<bethany.georgoulias@ncdenr.gov>; Lucas, Annette <annette.lucas@ncdenr.gov> Cc: Sams, Dan <dan.sams@ncdenr.gov> Subject: [External] RE: NCG020922 Renewal Inquiry CAUTION: External email. Do not click links or open attachments unless verified. Send all suspicious email as an attachment to report.spam@nc.gov. Hey Bethany Please see below answers to questions in red. From: Georgoulias, Bethany[mailto:bethany.georgoulias@ncdenr.gov] Sent: Thursday, December 07, 2017 1:26 PM To: Lucas, Annette <annette.lucas@ncdenr.gov> Cc: Dave Gambardella <dave@thomassimpsonconstruction.com>; Sams, Dan <dan.sams@ncdenr.gov> Subject: RE: NCG020922 Renewal Inquiry Thanks, Annette. I just issued two COCs ahead of this one yesterday, and I am working on this and another one this week. The request to the region for comments went out Nov 1St, so their 30 day window for input just concluded. To date I've not received any feedback from the Wilmington Regional Office on the proposed North River Club mine. I do notice that no outfall locations were submitted on the NOI application, and it said that dewatering would be directed to the adjacent property's mine basin. There will still be an outfall point where samples are taken, however, and we'll need to know that (and latitude/longitude coordinates). Dave, can you please provide that information? The application indicates that the mine settling pond will overflow in events exceeding the 10 -year, 24-hour event, so there appears to be a potential for wastewater discharge. The previous permit directed all discharge north via a culvert to the Beaufort Club/North River club golf course irrigation ponds, which would then be used to irrigate the golf course. Ultimately the goal is to dewater south into the adjacent Simpson mine basin by pump, but we would leave the culvert in place in case a 10 year, 24 hour event occurred which would then direct water north into the existing irrigation ponds for the golf course. Also, where will stormwater be discharged? Or will it all drain to the pit that will then be dewatered? There is only a topo map and a picture of the property with mine acreage marked. There is no diagram of where treatment devices or outfall points are located. The stormwater will drain to the pit which will then be dewatered. If the situation here results in no discharge at all (is that what discharge to the neighboring basin attempts to achieve?), then we need a better understanding of what the discharge permit is for. Typically we would require sampling at the point it leaves the mine property to report parameters. If the actual outfall is beyond the property (this is occasionally the case), then we need to understand exactly where, and where the surface waters are. The goal is not to have any discharge at all, but I understand that based upon the a sizeable rain event this may not be the case. The Simpson Family Properties Permit plans showed a potential discharge point that was never used (the mine basin was sectioned off and dewatered into each section as mining occurred). Would I specify this as the discharge or the culvert draining north to the golf course irrigation ponds. Or should I specify both discharge points. Also, I note the application checks "Yes" next to the dewatering being near wetlands or other waterbodies, but there is no delineation on any site plan of where those are. And, the wastewater treatment alternatives review has been left uncompleted with a note that says "NO DISCHARGE." We cannot issue a discharge permit without this review (it is required by our rules), and I am also unclear about the need for an NPDES discharge permit if the application is asserting no discharge. This is a point of confusion I need to understand better. I was told by one engineer that based upon the amount of dewatering needed to dig the Beaufort Club mine that we would need a dewatering permit, regardless of there being no discharge. But if we do not need the permit renewed then I would be fine with that. Its been about 10 years since I permitted a sand mine. Dave, please follow up with me on this when you are able to. Thanks, Bethany Georgoulias Environmental Engineer Stormwater Program, Division of Energy, Mineral, and Land Resources N.C. Department of Environmental Quality 919 807 6372 office bethanygeor oulias e ncdenr.gov 1612 Mail Service Center, Raleigh, NC 27699-1612 (mailing) 512 N. Salisbury Street, Raleigh, NC 27604 (location) Website: http://deq.nc.gov/about/divisions/energy-mineral-land-resources/stormwater Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. From: Lucas, Annette Sent: Thursday, December 07, 2017 10:28 AM To: Georgoulias, Bethany<bethany.georgoulias@ncdenr.gov> Cc: Dave Gambardella<dave(@thomassimosonconstruction.com> Subject: NCG020922 Renewal Inquiry Georgoulias Bethany Mining Activities Stormwater Discharge COC New Project Hi Bethany, NCG020922 North River Cl I just got a call from Mr. Gambardella inquiring as to the status of his application for the above project. I explained about our backlog and agreed to send you an email and copy him so that you two would have each other's contact information in case you need to talk with him during the review. Thanks so much! Annette Annette Lucas, PE Stormwater Program Supervisor Division of Energy, Mineral and Land Resources Department of Environmental Quality 919 807-6381 office annette.lucas(a)ncdenr.gov https://deg.nc.gov/sw-bmp-manual 512 N. Salisbury Street, Office 942-V, Raleigh, NC 27604 1612 Mail Service Center, Raleigh, NC 27699-1612 Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. Before printing this email, please consider your budget and the environment. E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties.