SW1180402_Outlet Calcs_20180605
June 5th, 2018 Mr. Corey Anen North Carolina Department of Environmental Quality Division of Energy, Mineral and Land Resources Stormwater Group 1612 Mail Service Center Raleigh, NC 27699-1612 RE: Request for Additional Information - SW1180402 Stormwater Management Permit Application Jo Ellen Ammons Fieldhouse for Mars Hill University Madison County, North Carolina Dear Mr. Anen: Please find below responses to the comments in the Request for Additional Information dated June 5th, 2018 and in regard to Stormwater Permit No. SW1180402. 1. Please submit calculations that show that the proposed erosion control measures are sufficient to prevent erosion at the inlets, outlets, and the receiving water body. A: Please review the calculations included with this submittal for information about the erosion control measures on the site. The erosion and sedimentation control plan for the project has been approved by the North Carolina Department of Environmental Quality-Land Quality Section (NCDEQ-LQS) and construction operations are covered under permit NCG010000. 2. Provide pdfs of all revisions, 2 hardcopies of revised plan sheets, and 1 hardcopy of other documents. Pdfs must be uploaded using the form at: https://edocs.deq.nc.gov/Forms/SW_Project_Submittal A: Noted One (1) hardcopy of the additional calculations and a digital copy of the additional calculations have been provided for this Request for Additional Information. Please feel free to contact us if you have any questions or need any additional information. Sincerely, McGILL ASSOCIATES, P.A. Brad Johnson, P.E. Project Manager I:\Projects\2016\16.00164 - MHU Fieldhouse\Misc\Stormwater\June 2018 Response to NCDEQ Comments Type II 24-hr 10-year Rainfall=3.96"MHU Fieldhouse Stormwater Printed 6/5/2018Prepared by McGill Associates Page 1HydroCAD® 10.00-20 s/n 04263 © 2017 HydroCAD Software Solutions LLC Summary for Pond 3P: Bio. Cell [82] Warning: Early inflow requires earlier time span Inflow Area = 56,628 sf, 57.12% Impervious, Inflow Depth > 2.09" for 10-year event Inflow = 4.218 cfs @ 11.95 hrs, Volume= 9,855 cf Outflow = 3.967 cfs @ 11.98 hrs, Volume= 9,855 cf, Atten= 6%, Lag= 1.7 min Primary = 3.967 cfs @ 11.98 hrs, Volume= 9,855 cf Routing by Stor-Ind method, Time Span= 5.00-36.00 hrs, dt= 0.05 hrs Peak Elev= 2,229.71' @ 11.98 hrs Surf.Area= 2,631 sf Storage= 2,410 cf Plug-Flow detention time= 100.6 min calculated for 9,852 cf (100% of inflow) Center-of-Mass det. time= 100.2 min ( 865.5 - 765.3 ) Volume Invert Avail.Storage Storage Description #1 2,228.50' 3,197 cf Custom Stage Data (Irregular) Listed below (Recalc) Elevation Surf.Area Perim. Inc.Store Cum.Store Wet.Area (feet) (sq-ft) (feet) (cubic-feet) (cubic-feet) (sq-ft) 2,228.50 1,020 168.0 0 0 1,020 2,229.00 2,030 203.0 748 748 2,057 2,230.00 2,893 228.0 2,449 3,197 2,942 Device Routing Invert Outlet Devices #1 Primary 2,225.00'18.0" Round 18" HDPE Pipe L= 81.0' Ke= 0.900 Inlet / Outlet Invert= 2,225.00' / 2,223.25' S= 0.0216 '/' Cc= 0.900 n= 0.012, Flow Area= 1.77 sf #2 Device 1 2,229.50'36.0" W x 6.0" H Vert. Orifice/Grate X 4.00 C= 0.600 #3 Device 1 2,228.50'2.000 in/hr Exfiltration over Surface area Conductivity to Groundwater Elevation = 2,220.00' Primary OutFlow Max=3.822 cfs @ 11.98 hrs HW=2,229.71' (Free Discharge) 1=18" HDPE Pipe (Passes 3.822 cfs of 13.366 cfs potential flow) 2=Orifice/Grate (Orifice Controls 3.688 cfs @ 1.47 fps) 3=Exfiltration ( Controls 0.134 cfs) Type II 24-hr 10-year Rainfall=3.96"MHU Fieldhouse Stormwater Printed 6/5/2018Prepared by McGill Associates Page 2HydroCAD® 10.00-20 s/n 04263 © 2017 HydroCAD Software Solutions LLC Pond 3P: Bio. Cell Inflow Primary Hydrograph Time (hours) 36353433323130292827262524232221201918171615141312111098765Flow (cfs)4 3 2 1 0 Inflow Area=56,628 sf Peak Elev=2,229.71' Storage=2,410 cf 4.218 cfs 3.967 cfs User Input Data Calculated Value Reference Data Designed By:ZPR Date:06.05.2018 Checked By:BKJ Date:06.05.2018 Company:McGill Associates Project Name:MHU Fieldhouse Project No.:16.00164 Site Location (City/Town)Mars Hill Outlet I.D.EX-1.1 Outlet Total Drainage Area (acres)- Rational Method for Flow Outlet pipe diameter, Do (in.)18 Tailwater depth (in.)0 Minimum/Maximum tailwater?Min TW (Fig. 8.06a) Discharge (cfs)3.85 Velocity (ft./s)2.18 Minimum TW Maximum TW Figure 8.06a Figure 8.06b Riprap d50, (ft.)0.3 Minimum apron length, La (ft.)9 Apron width at pipe outlet (ft.)4.5 Apron shape Trapezoid Apron width at outlet end (ft.)10.5 Minimum TW Maximum TW Max Stone Diameter, dmax (ft.)0.45 Minimum TW Maximum TW Apron Thickness(ft.)0.675 Return to Main Worksheet Figure 8.06a: Design of outlet protection from a round pipe flowing full, minimum tailwater condition (Tw<0.5 diameter)