Stephanie,
Here is the email from the USACE concerning the utility line stream crossing.
Let me know if you need anything else.
Sent from my Whone
Begin forwarded message:
From: "Alexander, Tasha L CIV USARMY CESAW (US)" <Tasha.L.AlexanderC@usace.army.mil>
Date: April 17, 2018 at 10:18:05 AM EDT
To: Sarah Menser <sarah@soilservices.us>
Subject: MacTavish
Sarah,
On March 21, 2018 we received a Pre -construction notification (PCN) for temporary impacts associated
with the MacTavish Subdivision's utility line project. Based on the information provided, the work is
authorized by Nationwide Permit (NWP) 12 for Utility Line Activities and does not require a PCN,
provided it is accomplished in strict accordance with the attached conditions below (see link) and your
submitted description. Any violation of the attached conditions or deviation from your submitted
description may subject the permittee to a stop work order, a restoration order and/or appropriate legal
action. Attached is a copy of the NWP 12 and the applicable permit conditions (see link). The expiration
date for the permit authorization is March 18, 2022 unless the nationwide authorization is modified,
suspended or revoked. If the nationwide permit authorization expires or is suspended, revoked, or is
modified, such that the activity would no longer comply with the terms and conditions of the
nationwide permit, activities which have commenced (i.e., are under construction) or are under contract
to commence in reliance upon the nationwide permit, will remain authorized provided the activity is
completed within twelve months of the date of the nationwide permit's expiration, modification or
revocation, unless discretionary authority has been exercised on a case-by-case basis to modify, suspend
or revoke the authorization.
http://saw-reg.usace.army.miI/NW P2017/2017NW P12.pdf
Let me know if you have any questions.
Thank you,
Tasha Alexander
Regulatory Specialist
Raleigh Regulatory Field Office
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
919-554-4884 ext. 35
The Wilmington District is committed to providing the highest level of support to the public. To help us
ensure we continue to do so, please complete the Customer Satisfaction Survey located at our website
at http://Www.saw.usace.army.mil/missions/RegulatoryPermitProgram.aspx to complete the survey
online.
2