HomeMy WebLinkAbout20090281 Ver 1_USACE Correspondence_20090515o9-0X31
DEPARTMENT OF THE ARMY
WILMINGTON DISTRICT, CORPS OF ENGINEERS
PO BOX 1890
WILMINGTON NC 28402-1890
May 29, 2009
Regulatory Division
Action ID. SAW-2009-00632
@ 162
JUN 2009
DENR - WATER QUALITY
WETLANDS AND STORMWATER BRANCH
Mr. Doug Huggett
Division of Coastal Management
N.C. Department of Environment
and Natural Resources
400 Commerce Avenue
Morehead City, North Carolina 28557-3421
Dear Mr. Huggett:
Reference the application of the North Carolina Wildlife Resources Commission (NCWRC)
for a Department of for expansion of the existing parking lot, reconstruction of the existing boat
ramps, addition of a new launch lane, four floating docks with a wave attenuator and excavation
of the channel boat ramp area at the existing NCWRC boat ramp facility, adjacent to the AIWW,
at 3400 Arendell Street in Morehead City, Carteret County, North Carolina
The Federal agencies have completed review of the proposal as presented by the application
and your field investigation report.
We recommend that the following conditions be included in the State authorization:
1. All work authorized by this permit must be performed in strict compliance with the
attached plans, which are a part of this permit. Any modification to these plans must be approved
by the U.S. Army Corps of Engineers (USACE) prior to implementation.
2. The permittee understands and agrees that, if future operations by the United States
require the removal, relocation, or other alteration, of the structure or work herein authorized, or
if, in the opinion of the Secretary of the Army or his authorized representative, said structure or
work shall cause unreasonable obstruction to the free navigation of the navigable waters, the
permittee will be required, upon due notice from the U.S. Army Corps of Engineers, to remove,
relocate, or alter the structural work or obstructions caused thereby, without expense to the
United States. No claim shall be made against the United States on account of any such removal,
-2-
relocation, or alteration. The permittee shall notify NOAA/NATIONAL OCEAN SERVICE
Chief Source Data Unit N CS261, 1315 E West HWY- RM 7316, Silver Spring, MD 20910-
3282 at least two weeks prior to beginning work and upon completion of work.
3. Except as specified in the plans attached to this permit, no excavation, fill or
mechanized land-clearing activities shall take place at any time in the construction or
maintenance of this project, in such a manner as to impair normal flows and circulation patterns
within waters or wetlands or to reduce the reach of waters or wetlands.
4. The docks and piers extending over wetlands will be elevated sufficiently (a
minimum of 3 feet) above the wetland substrate to prevent total shading of vegetation, substrate,
or other elements of the aquatic environment.
5. Except as authorized by this permit or any USACE approved modification to this
permit, no excavation, fill or mechanized land-clearing activities shall take place at any time in
the construction or maintenance of this project, within waters or wetlands. This permit does not
authorize temporary placement or double handling of excavated or fill material within waters or
wetlands outside the permitted area. This prohibition applies to all borrow and fill activities
connected with this project.
6. Unless otherwise authorized by this permit, all fill material placed in waters or
wetlands shall be generated from an upland source and will be clean and free of any pollutants
except in trace quantities. Metal products, organic materials (including debris from land clearing
activities), or unsightly debris will not be used.
7. All mechanized equipment will be regularly inspected and maintained to prevent
contamination of waters and wetlands from fuels, lubricants, hydraulic fluids, or other toxic
materials. In the event of a spill of petroleum products or any other hazardous waste, the
permittee shall immediately report it to the N.C. Division of Water Quality at (919) 733-5083,
Ext. 526 or (800) 662-7956 and provisions of the North Carolina Oil Pollution and Hazardous
Substances Control Act will be followed.
8. The authorized structure and associated activity must not interfere with the public's
right to free navigation on all navigable waters of the United States. No attempt will be made by
the permittee to prevent the full and free use by the public of all navigable waters at or adjacent
to the authorized work for reason other than safety.
9. The permittee must install and maintain, at his expense, any signal lights and signals
prescribed by the U.S. Coast Guard, through regulations or otherwise, on authorized facilities.
For further information, the permittee should contact the U.S. Coast Guard Marine Safety Office
at (910) 772-2191.
-5-
Mr. David Rackley
NMFS, Habitat Conservation Division
219 Fort Johnson Road
Charleston, South Carolina 29412-9110
Mr. Ronald J. Mikulak, Chief
Wetlands Regulatory Section
Water Management Division
U.S. Environmental Protection Agency
61 Forsyth Street, SW
Atlanta, Georgia 30303
Commanding Officer
U.S. Coast Guard Marine Safety Office
721 Medical Center Drive, Suite 100
Wilmington, North Carolina 28401-4895
Ms. Tere Barrett, District Manager
Morehead City Regional Office
N.C. Division of Coastal Management
400 Commerce Avenue
Morehead City, North Carolina 28557-3421