HomeMy WebLinkAboutNC0004961_Special Order By Consent_20180425 DUKE
`►. ENERGY® James Wells
Vice President
Environmental,Health&Safety-
Programs and Environmental Sciences
526 South Church Street
Mail Code EC13K
Charlotte, NC 28202
(980)373-9646
April 25, 2018
Via Overnight Mail
Corey Basinger
Mooresville Regional Supervisor RECEIVED/DENR/DWR
North Carolina Department of Environmental Quality
Division of Water Resources APR 2 6 2018
Regional Water Quality Operations Section
601 East Center Avenue, Suite 301 Water Resources
Mooresville, NC 28115 Permitting Section
Bob Sledge
North Carolina Department of Environmental Quality
Water Quality Permitting Program
Division of Water Resources
1617 Mail Service Center
Raleigh, NC 27699-1617
Subject. Report Under Special Order by Consent - SOC No S16-005
Duke Energy Carolinas, LLC - Riverbend Steam Station
NPDES Permit NC0004961
Dear Mr Basinger and Mr. Sledge.
On behalf of Duke Energy Carolinas, LLC ("DEC"), I am submitting to you the Riverbend Steam
Station Progress Report summarizing the work and activities undertaken with respect to closure
of coal ash surface impoundments as required by the Riverbend Steam Station NPDES Permit
NC0004961 Special Order by Consent ("SOC"), SOC No S16-005 Section 2. d.
As required by the SOC, I certify under penalty of law that this document and all attachments
were prepared under my direction or supervision in accordance with a system designed to
assure that qualified personnel properly gather and evaluate the information submitted. Based
on my inquiry of the person or persons who manage the system, or those persons directly
responsible for gathering the information, the information submitted is, to the best of my
knowledge and belief, true, accurate, and complete I am aware that there are significant
penalties for submitting false information, including the possibility of fine and imprisonment for
knowing violations.
Mr. Corey Basinger and Mr. Bob Sledge
April 25, 2018
Page 2
Please direct any questions concerning the Riverbend Steam Station NPDES Permit
NC0004961 SOC No S16-005 to Brad Loveland at (704) 609-5637.
Sin y, .17(ii
James ells
Vice P sident, Environmental, Health & Safety
ProgiO s and Environmental Sciences
Duke Energy
CC• Richard Baker, Duke Energy
Brad Loveland, Duke Energy
Rick Massey, Duke Energy
George Hamrick, Duke Energy
Paul Draovitch, Duke Energy
Matt Hanchey, Duke Energy
NPDES PERMIT NC0004961
SPECIAL ORDER BY CONSENT EMC SOC WQ S16-005
QUARTERLY EXCAVATION PROGRESS REPORT
RIVERBEND STEAM STATION
APRIL 25, 2018
I. Background and Summary
On November 10, 2016, Duke Energy Carolinas, LLC ("DEC") and the North Carolina
Environmental Management Commission entered into Special Order by Consent—EMC SOC
WQ S 16-005 ("SOC") applicable to the Riverbend Steam Station ("Riverbend"). This report is
submitted in accordance with paragraph 2.d of the SOC. In compliance with Section 2.d., this
report summarizes the work and activities undertaken with respect to closure of coal ash surface
impoundments at Riverbend, including a status update for necessary permits. The quarterly
reports are due no later than the last day of January, April,July, and October for the duration of
the SOC.
A. Riverbend Steam Station Closure Summary
Riverbend is located off of Horseshoe Bend Beach Road near the town of Mt. Holly in
Gaston County, North Carolina, on the south bank of the Catawba River. The site contains two
ash basins, as well as the Dry Ash Stack and the Cinder Pit. As of April 2013, all of the coal-
fired units were retired. As of March 31, 2018, approximately 4,180,840 tons of ash has been
excavated from the site, representing 87% of the total estimated ash on site.
The N ("CAMA")Carolina Coal Ash Management Act of 2014 ( CAMA") requires that ash
from Riverbend's ash basins be excavated and relocated to a lined facility, with the ash basins
closed by August 1, 2019. The initial Excavation Plan was submitted to the North Carolina
Department of Environmental Quality ("NCDEQ") on November 13, 2014, detailing the first
12-18 months of projected ash basin excavation activities. Updated Excavation Plans, including
the status of necessary permits, have been submitted annually since then.
The Riverbend facility continues to excavate ash by rail to the Brickhaven Structural Fill
site. Between January 1, 2018 and March 31, 2018, the site has excavated and transported
328,141 tons of ash from the Riverbend basins. Excavation and transportation of the remaining
ash is expected to be completed in 2018. Post closure activities, including decommissioning of
the Primary and Secondary Dams, will begin following the completion of ash excavation
activities. The Riverbend site is on track to comply with the CAMA deadline of complete
excavation of the ash basins by August 1, 2019. Since completing bulk dewatering in February
2017, the basins have been maintained in a dewatered state with interstitial and contact
stormwater being treated through the on-site water treatment facility.
1
Ash Transported Off Site in Thousands of Tons I January 2018 to March 2018
Riverbend Ash Transportation
Monthly Progress
300
250
g ecu
F
t ■Baseline
150 ■Actual
■Forecast
L)0
1111
111. 11. 1
til ti'1 ti� ,�� til ti'1 tib ,4� tib tiE tii• tib tib ,tib tib tib tie tib
o- �c oO ��° oO c�a ,- `ss � eT'44' ti� ' #‘,44- F `,pe` o'O �,oa Ja
P Q? O� z Ce�z ti3 See
Ash Transported Off Site in Millions of Tons
Riverbend Ash Transportation
Overall Progress
5 00
8/31118 8::i13
GC'.,
4 50
90%
a 00
30%
350 -... __
70%
300
5 sox
2
2 50 -Baseline
15 504'. -Actual
os .00
Forecast
40x -Regulatory Date
1 50
30%
100 20%
050
lOx
000 •
09.
b\�ti5 \�tih o�~etie ^\�o<0 y\�ti� \�oti� \v0\e ptia \�otia no 4
.4,
o\
2
Status of Permits and Permit Applications
RECEIVED DATE(R)
PERMIT COMMENTS
3s /TARGET DATE (T)
NCDEQ issued the ISW
NPDES Industrial permit to the Company
May 15, 2015 (R) May 15, 2015. SPPP
Stormwater Permit Implementation date was
November 15, 2015.
NPD Permit became effective
ES Wastewater First quarter 2016(R)
December 1
Permit— Major (Modified by SOC
2016.
Water Modification in 04 2016)
Jurisdictional Wetlands There are no identified
and Stream Impacts/ N/A jurisdictional
404 Permitting and wetlands/stream impacts.
401 WQC
Intermediate Dam Submitted May 31, 2016.
Decommissioning June 16, 2016 (R) Received approval
Request June 16, 2016.
Approval
Primary Dam was modified
in late 1970s by adding 10
Primary Dam feet, partially over ash.
Modification August 7, 2017 (R) This soil requires removal in
order to excavate the ash
below.
Transportation and
Dam Safety excavation activities must
not impact a jurisdictional
dam or dike.
Primary and Secondary Excavation activities are
Dam Decommissioning May 1, 2018 (T) initially staying 50 feet
Request Approval away from the jurisdictional
dike. Removing ash from
the Primary and Secondary
Ash Basins will have to be
reviewed with Dam Safety.
Breaching of dike will
require Dam Safety
approval.
Mine Reclamation
Individual Structural Received Owner/Operator obtained
Fill Permit Permit to Operate an individual structural fill
Waste October 15, 2015 permit as set forth in Part II,
§ 130A-309.219 of CAMA.
Site-specific
Nuisance/Noise/Odor/
Other Requirements Other Requirements, N/A None identified.
including DOT and
FERC Requirements
3