HomeMy WebLinkAboutNC0003425_CAMA Assessment Report PART 1.1_201805264 DUKE
ENERGY.
May 26, 2017
Mr. S. Jay Zimmerman, Director
Division of Water Resources
North Carolina Department of Environmental Quality
1611 Mail Service Center
Raleigh, North Carolina 27699-1611
Subject: Additional Site Assessment Required
Roxboro Steam F lectric Plant
W.H. Weatherspoon Power Plant
Dear Mr. Zimmerman:
Pau: Draov tch
Sen or Vice -President
E"nvironmentar, Health & Safety
526 South Church Street:
Mail Code EC3XP
Charlotte, North Carolina 28202
980-373.0408
On August 18, 2016, Duke Energy (Duke) submitted Work Plans for additional assessment
activities at the Roxboro Steam Electric Plant (Roxboro) and W.H. Weatherspoon Power Plant
(Weatherspoon). On November 23, 2016 (revised December 2, 2016) Duke received North
Carolrna Department of Environmental Quality Division of Water Resources (DWR) approval to
the Work Plans. On January 27, 2017 Duke requested a 60 day extension to the assessment
reports whrch was approved by the Division on February 27, 2017 subsequently making the
reports due on May 30, 2017. Rogers Energy Complex was included in the extension request
but has since developed under a separate timeline. Attached you will find Additional Site
Assessment Reports for each of the above facilities in accordance with the correspondence
described above.
This information is also being provided to the respective regional offices.
If you have comments and/or questions, please direct them to Ed Sullivan at 980-373-3719.
inc2Draovitch
Senior Vice -President
Environmental, Health & Safety
Enclosure: Groundwater Assessment Reports- Roxboro Steam Electric Plant and W.H.
Weatherspoon Power Plant
Cc: Danny Smith - Raleigh Regional Office Supervisor (Roxboro)
Trent Allen - Fayetteville Assistant Regional Office Supervisor (Weatherspoon)
synTerra
ASH BASIN EXTENSION IMPOUNDMENTS AND
DISCHARGE CANALS ASSESSMENT REPORT
ROXBORO STEAM ELECTRIC PLANT
1700 DUNNAWAY ROAD
SEMORA, NORTH CAROLINA 27343
MAY 2017
PREPARED FOR
DUKE ENERGY PROGRESS,, LLC
RALEIGH, NORTH CAROLINA
f
,DUKE
ENERGY.
PROGRESS
Kathy
Kathy Webb, NC LG 1328
Project Director
2r
, SERE
��y;� t599 '�•,
Craig Eady, NC LG 1599
Manager
Kathy
Kathy Webb, NC LG 1328
Project Director
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant - Semora, NC SynTerra
TABLE OF CONTENTS
SECTION
EXECUTIVE SUMMARY
PAGE
ES -1
1.0
INTRODUCTION.........................................................................................................1-1
6-1
2.0
BACKGROUND............................................................................................................2-1
3-2
2.1
Site Description.........................................................................................................
2-1
2.2
Site History.................................................................................................................
2-1
2.3
WAB Southern Extension Impoundment and Discharge Canal ........................2-2
4-1
2.4
EAB Eastern Extension Impoundment and Discharge Canal ............................
2-2
3.0
SITE GEOLOGY AND HYDROGEOLOGY............................................................3-1
4-1
3.1
Regional Geology......................................................................................................3-1
6-1
3.2
Site Geology...............................................................................................................
3-2
3.3
Regional Hydrogeology...........................................................................................
3-2
3.4
Site Hydrogeology....................................................................................................
3-2
4.0
PROVISIONAL GROUNDWATER BACKGROUND CONCENTRATIONS.
4-1
4.1
Statistical Method......................................................................................................4-1
6-4
4.2
Background Concentrations....................................................................................
4-1
5.0
SAMPLE COLLECTION..............................................................................................5-1
5.1
Wastewater Samples.................................................................................................5-1
5.2
Sediment and Sediment Core Samples..................................................................
5-1
5.3
Groundwater Monitoring Well Installation..........................................................5-2
5.4
Groundwater Sampling...........................................................................................
5-4
6.0
ASH BASIN EXTENSION IMPOUNDMENTS AND DISCHARGE CANALS
CHARACTERIZATION..............................................................................................
6-1
6.1
WAB Southern Extension Impoundment and Discharge Canal Sample
Results.........................................................................................................................
6-1
6.1.1
SEI Wastewater Data..........................................................................................
6-1
6.1.2
SEI Discharge Canal Wastewater Data............................................................
6-2
6.1.3
SEI Surficial and Core Sediment Data..............................................................
6-2
6.1.4
SEI Discharge Canal Sediment and Core Sediment Data .............................
6-3
6.1.5
SEI Groundwater Data.......................................................................................
6-4
6.1.6
SEI Discharge Canal Groundwater Data .........................................................
6-4
Page i
P: \ Duke Energy Progress.1026 \ 107. Roxboro Ash Basin GW Assessment Plan\ 33.Discharge Canal Assessment
(EHS)\DC Assessment Report \Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant - Semora, NC SynTerra
TABLE OF CONTENTS
SECTION
PAGE
6.2 EAB Eastern Extension Impoundment and Discharge Canal
1951 Aerial Photograph
SampleResults...........................................................................................................
6-5
6.2.1 EEI Wastewater Data..........................................................................................6-5
1977 Aerial Photograph
6.2.2 EEI Discharge Canal Wastewater Data............................................................
6-5
6.2.3 EEI Surficial and Core Sediment Data.............................................................
6-6
6.2.4 EEI Discharge Canal Sediment and Core Sediment Data .............................
6-7
6.2.5 EEI Groundwater Data.......................................................................................
6-7
6.2.6 EEI Discharge Canal Groundwater Data .........................................................
6-8
7.0 GROUNDWATER MODEL AND GEOCHEMICAL MODEL ............................
7-1
7.1 Groundwater Model.................................................................................................
7-1
7.2 Geochemical Model..................................................................................................
7-1
8.0 UPDATED SITE CONCEPTUAL MODEL.............................................................. 8-1
9.0 CONCLUSIONS AND RECOMMENDATIONS...................................................9-1
10.0 REFERENCES..............................................................................................................10-1
LIST OF FIGURES
Figure 1-1 Site Location Map
Figure 1-2 Site Layout Map
Figure 2-1
1951 Aerial Photograph
Figure 2-2
1964 Aerial Photograph
Figure 2-3
1977 Aerial Photograph
Figure 2-4
1993 Aerial Photograph
Figure 2-5
2008 Aerial Photograph
Figure 2-6
2016 Aerial Photograph
Figure 2-7
Operational Flow Diagram
Page ii
P: \ Duke Energy Progress.1026 \ 107. Roxboro Ash Basin GW Assessment Plan\ 33.Discharge Canal Assessment
(EHS)\DC Assessment Report \Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
LIST OF FIGURES (CONTINUED)
Figure 5-1 Sample Locations
Figure 5-2 Sample Locations - Southern Extension Impoundment and Western
Discharge Canal
Figure 5-3 Sample Locations -Eastern Extension Impoundment and Eastern
Discharge Canal
Figure 6-1 Isoconcentration Map - Boron in Bedrock Groundwater
Figure 8-1 Generalized Water Level Map (April 2017)
Figure 8-2 Site Cross-section Location Map
Figure 8-3 Site Cross-section A -A'
Figure 8-4 Site Cross-section B -B'
LIST OF TABLES
Table 4-1 Provisional Background Bedrock Groundwater Concentrations
Table 5-1 CCR / Sediment Thickness Summary - Southern Extension Impoundment
and Western Discharge Canal
Table 5-2 CCR / Sediment Thickness Summary - Eastern Extension Impoundment
and Eastern Discharge Canal
Table 5-3 Well Construction Data
Table 6-1 Wastewater Analytical Results - Southern Extension Impoundment and
Western Discharge Canal
Table 6-2 Sediment Analytical Results - Southern Extension Impoundment and
Western Discharge Canal
Table 6-3 SPLP Analytical Results - Southern Extension Impoundment
Table 6-4 Groundwater Analytical Results - WAB, SEI and WDC Area Wells
Table 6-5 Wastewater Analytical Results - Eastern Extension Impoundment and
Eastern Discharge Canal
Table 6-6 Sediment Analytical Results - Eastern Extension Impoundment and
Eastern Discharge Canal
Table 6-7 SPLP Analytical Results - Eastern Extension Impoundment
Table 6-8 Groundwater Analytical Results - EAB, EEI and EDC Area Wells
Table 8-1 Water Elevation Data - April 10, 2017
Page iii
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS)\DC Assessment Report \Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
LIST OF APPENDICES
Appendix A NCDEQ Correspondence
Appendix B NPDES Permit Development Fact Sheet
Appendix C Well Construction
Appendix C.1 Well Construction Logs
Appendix C.2 Drillers Logs
Appendix C.3 Well Development Logs
Appendix D Sediment Logs
Appendix D.1 Sediment Core Description Logs
Appendix D. 2 Sediment Core Photos
Appendix E Analytical Reports
Appendix E.1 Waste Water Samples
Appendix E.2 Sediment Samples
Appendix E.3 Groundwater Samples
Page iv
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
LIST OF ACRONYMS
2B
NCDEQ/DWR Title 15, Subchapter 2B. Surface Water and Wetland
NAVD 88
Standards
2L
NCDEQ/DWR Title 15, Subchapter 2L. Groundwater Quality
MDL
Standards
bgs
Below ground surface
CAMA
Coal Ash Management Act
CAP
Corrective Action Plan
CCR
Coal Combustion Residuals
CSA
Comprehensive Site Assessment
DFA
Dry Fly Ash
DEP
Duke Energy Progress
DO
Dissolved Oxygen
EEI
Eastern Extension Impoundment
FGD
Flue Gas Desulfurization
IMAC
Interim Maximum Allowable Concentrations
NAVD 88
North American Vertical Datum of 1988
MCL
Federal Maximum Contaminant Level
MDL
Method Detection Limit
NCAC
North Carolina Administrative Code
NCDEQ
North Carolina Department of Environmental Quality
(formerly NCDENR)
NCDWR
North Carolina Division of Water Resources
NPDES
National Pollution Discharge Elimination System
NTU
Nephelometric Turbidity Unit
PBC
Provisional Background Concentrations
Plant/Site
Roxboro Steam Electric Plant
PLM
Polarized Light Microscopy
SCM
Site Conceptual Model
SEI
Southern Extension Impoundment
TDS
Total Dissolved Solids
UTL
Upper Tolerance Limit
USEPA
United States Environmental Protection Agency
Page v
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
EXECUTIVE SUMMARY
In a letter dated July 8, 2016, the North Carolina Department of Environmental Quality
(NCDEQ) Division of Water Resources (DWR) requested that Duke Energy assess the
distribution of coal combustion residual (CCR) at confirmed and potential disposal sites
that included areas at the Roxboro Steam Electric Plant. The purpose of the assessment
is to determine if potential coal ash constituents in the ash basin extension
impoundments and their discharge canals may be an additional contributing source to
groundwater.
The assessment activities were conducted in the summer of 2016 through March 2017
and included:
167 The collection and characterization of wastewater and sediment samples from
each of the extension impoundments and their related discharge canals.
167 The installation of groundwater monitoring wells within each hydrogeologic
unit, as applicable, at strategic locations in the vicinity of the extension
impoundments and their related discharge canals.
167 The collection of groundwater samples from the newly installed and existing
groundwater monitoring wells to evaluate groundwater flow characteristics and
groundwater quality related to the extension impoundments and discharge
canals.
West Ash Basin Extension Impoundment and Discharge Canal Assessment
Water in the extension impoundment and discharge canal are subject only to
NPDES discharge permit requirements to the heated water discharge pond via
Outfall 002 and are not considered waters of the state. In this report, analytical
results are compared to North Carolina 2L or IMAC standards for informational
purposes to assess potential source contribution to groundwater. The analytical
results indicate arsenic, boron, cobalt, iron, manganese, thallium and vanadium
are greater than 2L or IMAC within the impoundment and the discharge canal.
In the discharge canal, the constituents increased in concentration downstream
from the filter dike towards NPDES Outfall #002.
07 Ash thickness from 1 to 5 feet was observed within the impoundment, which
was greatest near the filter dike, and from 1 to 1.5 feet within the discharge canal.
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
17 Analytical results for the sediment samples, as compared to USEPA RSLs for Soil
for Protection of Groundwater (May 2016), revealed arsenic, barium, copper,
lead, mercury, selenium, and vanadium concentrations were greater than the
RSL in one or more sediment samples within the impoundment and the
discharge canal.
101 With the exception of antimony, arsenic, selenium and thallium in the sediment
samples, the SPLP analysis for sediment samples are consistent with SPLP
analysis of soil, including background locations, presented in the CSA.
07 One new groundwater monitoring well, MW-26BR, was installed on the eastside
of the impoundment to support existing wells, CW -04 and MW-04BR, and three
new groundwater monitoring wells, MW-31BR through MW-33BR, were
installed at strategic locations along the discharge canal to support existing wells,
MW-07BR, MW-08BR, and MW -12, to evaluate groundwater conditions in the
upper most bedrock aquifer.
101 One groundwater sampling event from the new and pertinent existing wells
indicate that several constituents were detected above the 2L or IMAC including
total chromium, iron, manganese, sulfate, TDS, and vanadium. Boron was not
detected above the method detection limit. With the exception of total chromium
in MW-33BR and sulfate and TDS in MW-25BR, none of the detected constituents
were above the provisional background concentrations.
167 With the detection of a few constituents above 2L or IMAC and provisional
background concentrations and the lack of boron suggests the impoundment and
discharge canal has not impacted the groundwater in the upper bedrock aquifer.
East Ash Basin Extension Impoundment and Discharge Canal Assessment
17 Water in the extension impoundment and discharge canal are part of the ash
basin and are not considered waters of the state. The water will be subject to
NPDES discharge permit requirements to the intake canal via proposed Outfall
#001 which is currently under regulatory review. In this report, analytical results
are compared to North Carolina 2L or IMAC standards for informational
purposes to assess potential source contribution to groundwater. The analytical
results from water samples in the impoundment and discharge canal indicated
boron, iron, manganese and vanadium concentrations are greater than 2L or
IMAC with no apparent trend with the exception of greater boron concentrations
near the confluence of the discharge canal and the impoundment.
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
,67 Ash thickness from <1 to 20 feet was observed within the impoundment, which
was greatest near the separator dike, and from <0.5 to 1 feet within the discharge
canal, which was greatest near the confluence of the impoundment and the
discharge canal.
,67 Analytical results for the sediment samples, as compared to USEPA Regional
Screening Levels (RSLs) for Soil for Protection of Groundwater (May 2016),
revealed antimony, arsenic, barium, copper, selenium, and vanadium
concentrations were greater than the RSL in one or more surficial and core
sediment samples within the impoundment and the discharge canal.
167 With the exception of antimony and thallium in the deep sediment samples from
the impoundment, the SPLP analysis for sediment samples are consistent with
SPLP analysis of soil, including background locations, presented in the CSA.
167 Three new groundwater monitoring wells, MW-23BR through MW-25BR, were
installed around the impoundment to support existing wells, MW-17BR and
MW-20BRL, and four new groundwater monitoring wells, MW-27BR through
MW-30BR, were installed at strategic locations along the discharge canal to
evaluate groundwater conditions in the upper most bedrock aquifer.
167 One groundwater sampling event from the new and pertinent existing wells
indicate that several constituents were detected above the 2L or IMAC including
total chromium, iron, manganese, TDS, and vanadium. Boron was not detected
above the method detection limit. With the exception of total chromium and
TDS in MW-25BR, none of the detected constituents were above the provisional
background concentrations.
H Boron was not detected in any of the groundwater samples suggesting the ash
and wastewater present in the impoundment and the discharge canal has not
impacted the groundwater in the upper bedrock aquifer.
Based on the findings of the extension impoundment and discharge canal assessment
activities, the following recommendations and observations are offered:
07 Additional monitoring of the impoundment and discharge canal wells is
recommended to confirm the initial constituent concentrations.
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
,67 Future groundwater flow and transport modeling and geochemical modeling
will need to incorporate additional data to evaluate the impoundments and
discharge canals.
17 No substantive changes to previous site conceptual model or previously
predicted migrations of constituents from the ash basins were observed.
,67 Extend the compliance boundary to include the impoundments and related
discharge canals per the 'Proposed Waste and Compliance Boundary" submitted
by Duke Energy on August 19, 2016 in response to the Division of Water
Resources July 8, 2016 request.
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
1.0 INTRODUCTION
Duke Energy Progress, LLC (Duke Energy, DEP) owns and operates the Roxboro Steam
Electric Plant (the Roxboro Plant, Plant or Site) located at 1700 Dunnaway Road in
Semora, Person County, North Carolina (Figure 1-1). The Roxboro Plant is located on
approximately 6,095 acres between McGhees Mill Road to the east and Hyco Lake,
formed from the impoundment of the Hyco River, to the west. The Site is developed
with the power plant structures, coal ash management areas and associated discharge
canals (Figure 1-2).
In 2014, the North Carolina General Assembly passed the Coal Ash Management Act
(CAMA) which required owners of a coal combustion residuals (CCR) surface
impoundment to conduct detailed site assessments. Results of CAMA related site
assessments are documented in the following reports:
167 Comprehensive Site Assessment Report - Roxboro Steam Electric Plant
(SynTerra, September 2, 2015).
167 Corrective Action Plan Part 1- Roxboro Steam Electric Plant (SynTerra,
December 1, 2015).
167 Corrective Action Plan Part 2 - Roxboro Steam Electric Plant (SynTerra, February
29, 2016); and
101 Comprehensive Site Assessment Supplement 1- Roxboro Steam Electric Plant
(SynTerra, August 1, 2016).
In a letter dated July 8, 2016, the North Carolina Department of Environmental Quality
(NCDEQ) Division of Water Resources (DWR) requested that Duke Energy provide
data and conduct additional site assessment as needed to characterize CCR materials in
areas that could contain potential source material that could impact groundwater
(Appendix A). The request encompassed the West Ash Basin (WAB) southern
extension impoundment (SEI) and associated discharge canal (WDC) and the East Ash
Basin (EAB) eastern extension impoundment (EEI) and associated discharge canal
(EDC). An assessment of water, sediment and groundwater of the EEI and a
preliminary assessment of groundwater for the SEI were reported in the CSA
Supplement I (SynTerra, August, 2016). The purpose of this assessment is to determine
if potential coal ash constituents in the ash basin extension impoundments and their
discharge canals may be a contributing source to groundwater.
Page 1-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
2.0 BACKGROUND
2.1 Site Description
The Roxboro Plant is located approximately 10 miles northwest of the City of Roxboro,
NC. The Plant is located on approximately 6,095 acres between McGhees Mill Road to
the east; Concord-Ceffo Road to the south; Semora Road to the west and Hyco Lake to
the north. The Site is developed with the power plant structures, ash management
areas and associated canals. The power plant structures are located primarily on the
north side of the Site near the Hyco Lake and the ash management areas are located
generally south of the power plant buildings. Land beyond the ash management areas
to the east, south and west are wooded and transected by transmission lines. Hyco
Lake borders the Site to the west and north.
The approximate size of the combined ash basins is 220 acres with a total estimated ash
inventory in both ash basins of 19,500,000 tons. The landfill ash inventory in the lined
and unlined landfills is estimated to be 7,320,000 tons. Ash fill areas, including the
structural fill under the gypsum pad, contain an estimated 7,800,000 tons. The total
estimated CCR at the Roxboro facility is approximately 34,620,000 tons
(https://www.duke-energy.com/pdfs/duke-energy-ash-metrics.pdf, updated June 2,
2016). The East Ash Basin is covered with vegetation and ponded water outside of the
landfill footprint and the West Ash Basin has some grass cover and ponded water,
mostly along the southern and eastern edges of the basin.
2.2 Site History
A 1951 aerial photograph shows the Site consisting of a combination of agricultural
land, rural residential, and woodlands prior to the impoundment of the Hyco River
(Figure 2-1). By 1964, clearing operations for the Plant and construction of the main
dam for the East Ash Basin had begun (Figure 2-2). The Plant began operations in 1966
as a coal-fired electrical generating station with additional generating units added in
1968, 1973, and 1980, with a combined electric generating capacity of 2,422 megawatts.
CCRs have historically been managed at the Plant's two on-site ash basins: the semi-
active East Ash Basin, which began operations from the mid-1960s, and the active West
Ash Basin, which started operations from the early 1970s. CCRs were initially
deposited in the EAB by hydraulic sluicing operations until the Plant was modified for
dry fly ash (DFA) handling in the 1980s. An unlined landfill was constructed on top of
the East Ash Basin for the placement of the DFA. A lined landfill was constructed in
phases over the unlined landfill beginning in 2004. Most of the fly ash material
produced at the facility is currently collected by dry handling operations and are
Page 2-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
disposed within the lined landfill or transported offsite for beneficial reuse. The WAB
was constructed in 1973 and still receives bottom ash by hydraulic sluicing methods.
2.3 WAB Southern Extension Impoundment and Discharge Canal
The West Ash Basin was created in 1973 with the construction of an earthen dam (main
dam) in a former stream channel to the southwest of the main plant. Figure 2-3 depicts
the configuration of the WAB from a 1977 aerial photograph. In 1986, the main dam
was raised 13 feet and a series of dikes (Dikes #1 through 4) and a discharge canal were
constructed to increase the storage capacity of the WAB and modify the circulation
pattern to increase ash settling time. The rock filter dike (Dike #1), constructed of rock
fill with a sand filter blanket, was installed at the southern end of the WAB to create a
secondary settling basin and to isolate the major portion of the ash basin, separating the
SEI from the WAB. The SEI is located south of the filter dike (Dike #1) and is comprised
of several "fingers" encompassing approximately 38.5 acres. The SEI has likely received
ash from the WAB before the rock filter dike was constructed. Dikes #2, 3, and 4 were
placed in topographic low areas along the excavated discharge canal on the west side of
the WAB. The dikes were constructed by end -dumping soil fill from the excavated
discharge canal and were supported with stone berms (buttresses), approximately 20 to
30 feet thick, on the downstream side of the dikes. The configuration of the WAB with
the filter dike and the discharge canal as depicted in 1993 is shown in Figure 2-4. By
2008, the flue gas desulfurization lagoons were constructed within the WAB (Figure 2-
5) and the area has remained similar to present day (Figure 2-6).
Drainage of the WAB and additional waste streams across the site are directed to the
western discharge canal. The discharge canal receives waste streams from various on-
site sources including: WAB effluent from bottom ash sluicing; landfill drainage and
runoff from the EAB lined landfill; storm water runoff from the two ash basins;
discharge from the Flue Gas Desulfurization Pond treatment process; cooling tower
blowdown; domestic sewage treatment plant discharge; and surface water runoff
(Figure 2-7). Effluent from the discharge canal passes through NPDES Internal Outfall
#002 with discharge into the heated water discharge pond, which ultimately flows into
Hyco Lake through NPDES Outfall# 003.
2.4 EAB Eastern Extension Impoundment and Discharge Canal
The East Ash Basin was originally developed in 1964 with the construction of an
earthen dam, to the southeast of the main plant, in a former stream channel (Figure 2-2).
A discharge canal from the EAB was constructed as part of the original ash basin
development and provided direct discharge of ash basin water and secondary surface
water runoff from adjacent streams to the intake canal of the Hyco Lake (Figure 2-3).
Page 2-2
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
The discharge was initially regulated under NPDES Permit #0003425 through internal
Outfall #001. In 1994, the NCDEQ (former NC Department of Environment and Natural
Resources (NCDENR)) no longer required discharge from the canal to be monitored
under NPDES regulations. The former outfall location is currently under consideration
for reinsertion into the NPDES permit. The NPDES Permit #0003425 fact sheet is
provided in Appendix B.
In the mid-1980s, an earthen separator dike was constructed on the eastern portion of
the EAB to allow development of the overlying unlined landfill. The separator dike
formed a barrier separating the EAB from the discharge canal and a portion of the
former basin, creating the 9.4 acre eastern extension impoundment (Figure 2-4).
Historical information indicates the EEI received ash directly through sluicing. A lined
landfill was constructed in phases over the unlined landfill beginning in 2004 and can
be seen in a 2008 aerial photograph (Figure 2-5). The final phase (Phase 6) of the lined
landfill is currently used to handle DFA with the current configuration shown in Figure
2-6.
Page 2-3
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
3.0 SITE GEOLOGY AND HYDROGEOLOGY
The Roxboro Plant is situated in the eastern Piedmont Region of north -central North
Carolina. The Piedmont is characterized by well-rounded hills and rolling ridges cut by
small streams and drainages. Elevations in the area of the Roxboro Plant range between
410 feet above mean sea level (msl) during full pool at Hyco Lake to 570 feet msl near
the Dunnaway Road and McGhees Mill Road intersection southeast of the Plant.
3.1 Regional Geology
Geologically, the Site is located near the contact of two regional geologic zones: the
Inner Piedmont zone and the Carolina zone. Both zones are generally comprised of
igneous and metamorphosed igneous and sedimentary rocks of Paleozoic age. In
general, the rocks are highly fractured and folded and have been subjected to long
periods of physical and chemical weathering. The origination, genesis, and
characteristics of the rocks of the region have been the focus of detailed study by
researchers for many years. These investigations have resulted in a number of
interpretations and periodic refinements to the overall geological model of the region.
Rocks of the region, except where exposed in road cuts, stream channels, and steep
hillsides, are covered with unconsolidated material formed from the in-situ chemical
and physical breakdown of the bedrock. This unconsolidated material is referred to as
saprolite or residuum. Direct observations at the Site confirm the presence of saprolite,
developed above the bedrock, which is generally 10 to 30 feet thick. The residuum
extends from the ground surface (soil zones) downward, transitioning through a zone
comprised of unconsolidated silt and sand, downward through a transition zone of
partially weathered rock in a silt/sand matrix, down to the contact with competent
bedrock.
The Geologic Map of North Carolina (1985) places the rocks of the Plant area in the
Charlotte Terrane: a belt of metamorphic rock trending generally southwest to
northeast characterized by strongly foliated felsic mica gneiss and schist and
metamorphosed intrusive rocks. The rocks of the area near the Plant are described as
biotite gneiss and schist with abundant potassic feldspar and garnet, and interlayered
and gradational with calcic -silicate rock, sillimanite-mica schist and amphibolite. The
gneiss contains small masses of granite rock. The felsic mica gneiss of the Charlotte
Terrane is described as being interlayered with biotite and hornblende schist. Later
mapping generally confirms these observations and places the Roxboro Plant near the
contact between the Inner Piedmont zone, characterized by the presence of biotite
gneiss and schist, and the Charlotte Belt (or Charlotte Terrane), characterized by felsic
Page 3-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
mica gneiss (USGS, 2007). A detailed description of the regional geology is presented in
Section 5.1 of the CSA Report (SynTerra, September 2015).
3.2 Site Geology
The Site is underlain by crystalline metamorphic rock, predominately gneiss. Biotite
gneiss of the Inner Piedmont, felsic mica gneiss of the Charlotte and Minton Belts, and
granitic gneiss of the Eastern Slate Belt were observed in rock cores collected at
monitoring well locations. Field observations determined that biotite gneiss was more
common in the north/northwest portion of the Site, felsic gneiss in the central portion,
and a very hard granitic gneiss or granite in the south southeastern portion of the Site.
3.3 Regional Hydrogeology
Groundwater within the Site area exists under unconfined, or water table, conditions
within the residuum and/or saprolite zone and in fractures and joints of the underlying
bedrock. The water table and bedrock water -bearing zones are interconnected. The
saprolite, where saturated thickness is sufficient, acts as a reservoir for supplying
groundwater to the fractures and joints in the bedrock. Shallow groundwater generally
flows from local recharge zones in topographically high areas, such as ridges, toward
groundwater discharge zones, such as stream valleys. Ridge and topographic high
areas serve as groundwater recharge zones, and groundwater flow patterns in recharge
areas tend to develop a somewhat radial pattern from the center of the recharge area
outward toward the discharge areas and are expected to mimic surface topography.
3.4 Site Hydrogeology
The position, geometry, topography, and hydrogeologic character of the ash basins, the
former stream valleys to the Hyco River in which the basins were constructed, and
Hyco Lake are the primary influences on groundwater flow and constituent transport at
the Site. The former natural drainage features generally trend southeast to northwest
across the site. The ash basins are separated by a northwest -southeast trending
topographic ridge. Groundwater flow across the site is generally from upland areas
south and southeast (recharge areas) toward Hyco Lake which is situated to the
north/northwest. Localized areas of groundwater discharge to surface water occur from
the two ash basins and the topographic ridge separating the basins. Further influences
to groundwater flow include the earthen impoundments (dams and separator dikes)
creating the basins; the intake canal (north of the EAB); the discharge canals; and the
heated water discharge pond.
Page 3-2
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
Based on the CSA investigation, the groundwater system in the natural materials
(alluvium, soil, soil/weathered bedrock, and bedrock) at Roxboro is consistent with the
Piedmont regolith -fractured rock system and is an unconfined, connected system of
flow layers. Groundwater is rarely present in the shallow zones, can be present in the
transition zone, and is typically present in fractures within the competent bedrock, with
water bearing fractures decreasing with depth.
Page 3-3
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
4.0 PROVISIONAL GROUNDWATER BACKGROUND
CONCENTRATIONS
Statistical analyses were conducted on groundwater data representative of locations
that have not been influenced by coal ash constituents or other significant
anthropogenic sources. Statistical methodology and results are presented in the
following subsections.
4.1 Statistical Method
Natural background concentrations for constituents within bedrock groundwater at the
Site were determined to assess the potential impact of the impoundments and discharge
canals on downgradient groundwater. Natural background concentrations for the
transition zone were not evaluated as part of this assessment since the transition zone in
the vicinity of the impoundments and the discharge canals is unsaturated (i.e., dry).
Provisional background concentrations were determined for each constituent by
calculating the upper tolerance limit (UTL) using a dataset consisting of sample results
from bedrock background wells BG-1BR, MW-10BR, MW-13BR, MW-14BR, MW-15BR,
MW-16BR, MW-17BR, MW-18BR and MW-19BRL. UTLs represent values in which a
specified proportion (e.g., 95 percent) of a background dataset will fall below with a
specified level of confidence (e.g., 95 percent). UTLs were calculated following the
procedures outlined in the revised draft of Duke Energy's Statistical Methods for
Developing Reference Background Concentrations for Groundwater and Soil at Coal Ash
Facilities (submitted January 2017) and in accordance with conditional approval
provided in NCDEQ's response dated April 28, 2017.
4.2 Background Concentrations
UTLs representing natural background concentrations for constituents within bedrock
groundwater at the Site are provided in Table 4-1. UTLs for the chromium (VI),
chromium (total), cobalt, iron, manganese, TDS, radium and vanadium are greater than
the applicable regulatory standard, while UTLs for arsenic, barium, chloride, copper,
nickel, sulfate, uranium and zinc are below the applicable regulatory standard. UTLs
could not be calculated for constituent datasets consisting of fewer than two detectable
concentrations which include: antimony, beryllium, boron, cadmium, lead, mercury,
selenium and thallium.
Page 4-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
5.0 SAMPLE COLLECTION
Aqueous and solid media sampling was performed to determine presence or absence of
CCR in the extension impoundments and discharge canals at the Roxboro Plant.
SynTerra followed the sampling procedures as outlined in the Ash Basin Extension
Impoundments and Discharge Canals Assessment Work Plan (Work Plan) (SynTerra,
August 2016). Site wide sample locations are indicated on Figure 5-1. Figure 5-2 and
Figure 5-3 focus on the impoundments and discharge canals.
NCDEQ conditionally approved the Work Plan in November 2016 (NCDEQ, November
23, 2016). The main caveat by NCDEQ included additional monitoring wells to be
installed in each water -bearing hydrostratigraphic unit at a nested well location
southwest of existing well MW-12BR. The proposed well cluster location is indicated as
MW -33.
5.1 Wastewater Samples
As detailed in the Work Plan, grab water samples from the impoundments and
discharge canals were collected directly into sample bottleware provided by the
analytical laboratory. For shallow water samples (with a SW or S designation), the
sample was collected by gently lowering lab provided bottleware into the water until a
portion of the mouth was just below the water surface. Bottleware containing a
preservative (e.g., acid) were filled with the grab water sample collected in bottleware
that did not contain a preservative. Water samples were collected from a boat or
samplers standing on the shoreline depending upon the sampling location and
accessibility. For deeper water samples, a peristaltic pump with weighted tubing was
used to sample at depth, typically approximately 2 feet above the bottom of the
impoundment/discharge canal. New tubing was used between each sample location.
Samples were analyzed for CAMA parameters as outlined in the Work Plan.
5.2 Sediment and Sediment Core Samples
Sediment samples and sediment cores were collected from the impoundments and
discharge canals by hand or manually pushing a clear acetate sleeve into the sediment
to refusal. Sample locations were accessed by boat or samplers standing on the
shoreline depending on sampling location and accessibility. Sediment samples were
analyzed for parameters as outlined in the Work Plan. SynTerra collected sediment
cores from the SEI and the EEI using direct push methods by a barge mounted
GeoProbe or manually with the clear acetate sleeves.
Visual inspection of sediment samples and sediment cores identified the presence of
coal ash in the impoundments and their corresponding discharge canals. A summary of
Page 5-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
the ash - sediment thickness within the impoundments and the discharge canals are
provided in Table 5-1 (SEI and WDC) and Table 5-2 (EEI and EDC). Sediment core
descriptions and photos are located in Appendix D.
5.3 Groundwater Monitoring Well Installation
Four groundwater monitoring wells were installed in June 2016 to assess bedrock
groundwater quality associated with the impoundments (Figure 1-2). MW-23BR, MW-
24BR and MW -25 were installed at strategic locations associated with the EEI to support
existing wells, MW-17BR and MW-20BRL to evaluate groundwater conditions in the
upper bedrock. MW-26BR was installed east and upgradient of the SEI to support
existing wells, CW -04 and MW-04BR, to evaluate groundwater quality in the upper
bedrock. Saturated conditions were not observed in the saprolite and/or transition
zones around the impoundments; therefore, only bedrock wells were installed. Boring
and well installation details were presented in the CSA Supplement (SynTerra, August
1, 2016). Well construction logs, drillers' logs and well development logs for the four
impoundment wells are provided in Appendix C.
In February 2017, MW-23BR was replaced due to elevated pH conditions in
groundwater samples collected from the well. MW-23BRR was installed approximately
25 feet northeast of MW-23BR by Geologic Exploration (GeoEx) of Statesville, NC using
air hammer drilling techniques. A water bearing fracture zone greater than 1.0 gpm
was determined from 197 to 203 feet bgs, even though the fracture zone in MW-23BR
was observed at 126 feet bgs. The replacement well, MW-23BRR, was drilled to a total
depth of 204 feet bgs with a 10 -foot pre -packed screen set at 194-204 feet bgs. The depth
to water in MW-23BRR was determined to be 3.99 feet bgs, whereas the depth to water
in MW-23BR was indicated at 46.72 feet bgs, as measured on April 10, 2017. Therefore,
the water bearing fracture zone in MW-23BRR is under greater hydrostatic head
consistent to artesian conditions demonstrated at nearby MW-20BRL. The boring log
with lithologic descriptions and well information for MW-23BRR is included in
Appendix C.
Seven groundwater monitoring wells were installed to assess groundwater quality
associated with the impoundment discharge canals. The wells were installed in
February 2017 using air hammer drilling techniques in accordance with the Work Plan.
During drilling, unsaturated conditions were observed in the saprolite/transition zones
at each location, leading to the installation of bedrock wells without the accompaniment
of a shallow or transition zone well. Bedrock monitoring wells were installed to the
first measureable water bearing fracture (> 1 gpm) in the bedrock, similar to the
previous extension impoundment investigation conducted in June 2016.
Page 5-2
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
Monitoring wells MW-27BR through MW-30BR were installed at strategic locations
associated with the EEI discharge canal (Figure 1-2). MW-27BR is located northeast of
the EAB and west of the EDC, in an area previously used as a soil borrow pit. The well
is screened from 65 - 75 feet bgs to intersect a bedrock fracture observed at 70 feet bgs.
MW-28BR, MW-29BR and MW-30BR are located east of the EDC. MW-28BR is screened
from 124 -134 feet bgs to monitor a bedrock fracture zone observed at 127 -128 feet
bgs. During drilling of MW-29BR, a water bearing fracture was observed at 83 feet bgs.
The borehole was extended one foot and a well was installed at the bottom of the
borehole, screened from 74 - 84 feet bgs. At MW-30BR, a water bearing fracture,
producing more than five gallons per minute, was observed from 136 -138 feet bgs.
MW-30BR was installed from 130 -140 bgs to monitor the fracture zone.
Monitoring wells MW-31BR through MW -33 were installed at strategic locations
associated with the SEI discharge canal. MW-31BR is screened from 68 - 78 feet bgs in
granite gneiss to monitor a water bearing fracture observed at 70 feet bgs. MW-32BR
and MW-33BR were installed significantly deeper in comparison to MW-31BR. MW-
32BR was installed from 250 - 260 feet bgs to capture a fracture observed at 257 feet bgs
in granite gneiss. No significant water bearing fractures were observed in MW-32BR
prior to 257 feet bgs. Equally for MW-33BR, no significant water bearing fractures were
observed in the bedrock to a depth of 300 feet bgs based on field observations during
drilling. To aid in screen placement in MW-33BR, packer tests were conducted
throughout the borehole to locate a suitable water bearing zone. A double packer
assembly with an approximate 15 foot screen was used. Based on the packer test
results, a water bearing zone was determined from 284 - 299 feet bgs, though the yield
was observed to be low (< 1 gpm). Therefore, a 15 foot screen was installed from 283 -
298 feet bgs in MW-33BR to evaluate the fracture zone. Each well was developed for
minimum of two hours in accordance with Work Plan. Well construction logs, drillers'
logs and well development logs are provided in Appendix C.
During the February 2017 assessment activities, the background monitoring well, BG-
1BRL was replaced due to elevated pH conditions with very low yield observed in the
well. The BG-01BRL borehole was initially installed on February 2016 and completed
on March 2016 by Cascade Drilling Company (Cascade). Upon completion of boring
installation and packer testing, no water bearing fractures were observed from 200 to
300 feet below ground surface (320 feet to 200 feet NAVD 88). With the Woodland
Elementary School well reported at a total depth of 280 below ground surface (260 feet
NAVD 88), a 10 -foot pre -packed screen was placed within a 30 -foot sand pack (252 feet
to 220 feet NAVD 88) to intercept potential low yield fractures in possible
communication with the school well. However, after multiple well development
Page 5-3
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
events; the well made very little water with very slow recovery (weeks) after pumping
and was utilized as a piezometer. A replacement of BG-01BRL was verbally approved
by DEQ on November 17, 2016 (E. Rice, DEQ, to K. Witt, DEP).
The replacement well, BG-01BRLR, was installed to a depth of 400 bgs by GeoEx using
air hammer drilling techniques. No significant water bearing fractures (> 1.0 gpm) were
encountered during borehole installation with the exception of a zone determined at
154 feet bgs. Therefore, a 10 foot pre -packed screen was set from 150 to 160 feet bgs.
The remainder of the boring below the screened interval was backfilled with a high
solids bentonite grout (AquaGuard®). The boring log with lithologic descriptions and
well information for BG-1BRLR is included in Appendix C.
Well construction information for the existing and newly monitoring wells is
summarized in Table 5-3.
5.4 Groundwater Sampling
One groundwater sampling event of the existing and newly installed monitoring wells
associated with the impoundments and discharge canals was conducted in March 2017.
Samples were collected using low -flow sampling techniques utilizing either a peristaltic
pump or submersible pump per the groundwater sampling procedures presented in the
CSA Work Plan (SynTerra, September 2015). Groundwater samples were submitted to
the Duke Energy analytical laboratory and analyzed for CSA constituents in accordance
with the Work Plan.
Page 5-4
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
6.0 ASH BASIN EXTENSION IMPOUNDMENTS AND DISCHARGE
CANALS CHARACTERIZATION
All water and sediment samples were submitted to the Duke Energy analytical
laboratory for inorganic and grain size analysis in accordance with the Work Plan.
Analytical reports are presented in Appendix E and tabulated herein for easy reference.
6.1 WAB Southern Extension Impoundment and Discharge Canal
Sample Results
SynTerra assessed the WAB SEI water and sediment quality from July 18-21, 2016 in
unison with AMEC Foster Wheeler (AMECFW). The depth of the water column was
measured from each sample location using an electronic water level tape and "tagging"
the bottom of the pond. The deepest part of the SEI measured approximately 30 feet of
water column at CF -01 (Figure 5-2). The deepest part of the impoundment is adjacent
to the filter dike and depth decreases away from the filter dike within each of the
fingers.
6.1.1 SEI Wastewater Data
Six shallow water samples (WF -2S, WF -4S, CF -2S, CF -4S, EF -2S and EF -4S) and
six deep water samples (WF -2D, WF -4D, CF -21), CF -41), EF -21) and EF -41)) were
collected (Figure 5-2). The water samples were analyzed for CSA parameters
with results compared to 2L and IMAC values. Water in the extension
impoundment is subject only to NPDES discharge permit requirements to the
heated water discharge pond via Outfall #002 and is not considered waters of the
state. In this report, analytical results are compared to North Carolina 2L or
IMAC standards for informational purposes to assess potential source
contribution to groundwater.
The analytical results indicated arsenic and cobalt greater than 2L for deep water
samples collected at CF -2, CF -04, EF -02, and WF -02. Boron concentrations were
greater than 2L at all locations with the exception of the deep water sample at EF -
04 (696 pg/L). Iron and manganese concentrations were greater than 2L in deep
water samples at CF -02, CF -04, EF -02, EF -04 and WF -02. Manganese is also
greater than 2L in surface water samples at CF -04, and WF -02, as well as deep
and surface water samples at WF -04. Thallium concentrations were greater than
2L at CF -02 SW, WF-02SW and WF-04DW. Vanadium concentrations were
detected above IMAC in all water samples. Constituent concentrations in
samples collected within two feet of the impoundment bottom tended to be
greater than 2L and exhibited higher turbidities than the corresponding surface
water sample. In most cases, constituent concentrations decreased with distance
Page 6-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
from filter dike. Analytical results are summarized in Table 6-1 and the
analytical reports are provided in Appendix E.
6.1.2 SEI Discharge Canal Wastewater Data
Six water samples (WDC -1 through WDC -6) were collected from the discharge
canal. Sample locations WDC -3 — WDC -6 were accessed using a pontoon boat
following DEP-approved boat safety protocol. Sample locations WDC -1 and
WDC -2 were accessed on foot and collected from the shore line.
The water samples were analyzed for CSA parameters and the results compared
to 2L and IMAC values. Water in the discharge canal is subject only to NPDES
discharge permit requirements to the heated water discharge pond via Outfall
#002 and is not considered waters of the state. Therefore, the 2L comparisons are
for informational purposes to assess potential source contribution to
groundwater. Analytical results indicate boron, iron, manganese, and vanadium
greater than 2L and IMAC at all sample locations. In general, the constituents
increased in concentration downstream from the filter dike (WDC -01) towards
NPDES Outfall #2 (WDC -06). Analytical results are summarized in Table 6-1
and the analytical reports are provided in Appendix E.
6.1.3 SEI Surficial and Core Sediment Data
Surficial sediment samples and cores were collected from seven locations in the
SEI (EF -1, EF -3, CW -1, CF -3, CF -5, WF -1 and WF -3) using a direct push barge
mounted GeoProbe with core samples collected to probe refusal. The depth to
the bottom of the impoundment was recorded and the lithology of intact core
samples described. Ash of variable thickness from 1— 5 feet was observed in the
surficial and core sediment samples. Field verification determined the presence
of CCR material at all locations; therefore, no additional laboratory confirmation
was warranted. The sediment core photographs and boring logs are provided in
Appendix D.
The sediment samples were analyzed for CSA parameters and compared to the
USEPA Regional Screening Levels (RSLs) for Soil for Protection of Groundwater.
Analytical results indicate arsenic, selenium, and vanadium concentrations were
in exceedance of the RSL in all sediment samples collected. Barium and lead
were detected above the RSL in most samples with the exception of EF -01 and
EF -03 (barium) and EF -03 and WF -03 (lead). Copper was detected above the RSL
in CF -03. Analytical results are summarized in Table 6-2 and the analytical
reports are provided in Appendix E.
Page 6-2
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
The SPLP leaching test was used to assess if the metals present in sediment
samples may leach to groundwater. Leachate samples collected from CL -02, CL -
04, CL -06, CL -07, CV -01, and CV -02 were analyzed for CSA parameters and
compared to 2L and IMAC values. Cobalt, iron, manganese and vanadium
leachate concentrations were greater than 2L or IMAC at all sample locations.
Antimony and arsenic leachate concentrations were greater than 2L at CF -03, CF -
05, EF -01 and WF -01. The arsenic leachate concentration is also greater than 2L
at CF -01. At sample location WF -01, beryllium, cadmium and selenium leachate
concentrations were greater than 2L. Chromium and lead leachate
concentrations were greater than 2L at CF -01 and WF -01 and thallium leachate
concentrations were greater than 2L at sample locations EF -01 and WF -01. With
the exception of antimony, arsenic, selenium and thallium in the sediment
samples, the SPLP analysis for sediment samples from the SEI are consistent with
SPLP analysis of soil, including background locations, presented in the CSA. The
SPLP results are summarized in Table 6-3. Laboratory analytical reports are
provided in Appendix E.
6.1.4 SEI Discharge Canal Sediment and Core Sediment Data
Six sediment samples (WDC -1 through WDC -6) were collected using a Ponar
Dredge. Sample locations WDC -3 through WDC -6 were accessed using a
pontoon boat. Sample locations WDC -1 and WDC -2 were accessed on foot and
collected from the shore line.
Sediment core samples were manually collected with the clear acetate sleeves at
WDC -1, WDC -2, WDC -4, WDC -5 and WDC -6. Field observations indicated the
presence of coal ash in the samples ranging from less than 1 foot to 1.5 feet in
thickness. Field verification determined the presence of CCR material at all
locations; therefore, no additional laboratory confirmation was warranted. The
sediment core photographs and boring logs are provided in Appendix D.
The sediment samples were analyzed for CSA parameters and compared to the
USEPA RSLs for Soil for Protection of Groundwater. Analytical results indicate
arsenic, selenium, and vanadium concentrations were in exceedance of the RSL
in all sediment samples collected. Barium was detected above the RSL in most
samples with the exception of WDC --03. Antimony was detected above the RSL
in WDC -04. Copper was detected above the RSL in WDC -04, WDC -05 and
WDC -06. Mercury was above the RSL in WDC -05 and WDC -06. As with the
water samples, the constituents increased in concentration downstream from the
filter dike (WDC -01) towards NPDES Outfall #002 (WDC -06). Analytical results
Page 6-3
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
are summarized in Table 6-2 and the analytical reports are provided in
Appendix E.
6.1.5 SEI Groundwater Data
The monitoring well, MW-26BR, was installed near the eastern side of the eastern
finger of the SEI to support existing wells, CW -04 and MW-04BR, to evaluate
groundwater quality in the upper bedrock. Groundwater samples were collected
in one event during the first quarter of 2017 and analyzed for CSA parameters.
Analytical results are compared to 2L and IMAC values as well as the
provisional background concentrations. Analytical results indicate iron and
manganese greater than 2L in MW-26BR. However, the detected concentrations
are consistent with background concentrations. No boron was detected above
the method detection limit (50 µg/L) in the impoundment wells. An
isoconcentration map representing the most recent analytical data for boron is
provided in Figure 6-1. The most recent analytical data is summarized in Table
6-4 and the laboratory analytical reports are included in Appendix E.
6.1.6 SEI Discharge Canal Groundwater Data
The monitoring wells MW-31BR, MW-32BR and MW-33BR were installed to
support existing wells, MW-07BR, MW-08BR, and MW -12, to evaluate
groundwater quality in the bedrock along the western discharge canal.
Groundwater samples were collected in one event during the first quarter of 2017
and analyzed for CSA parameters. Analytical results are compared to 2L and
IMAC values as well as the provisional background concentrations.
Analytical results indicate that constituents were detected above the 2L or IMAC
including chromium (16.2 µg/L (MW-33BR)); manganese (575 µg/L (MW-31BR),
76 pg/L (MW-32BR), and 100 µg/L (MW-33BR)); sulfate (310 µg/L (MW-32BR));
total dissolved solids (660 µg/L (MW-32BR)); and vanadium (2.28 µg/L (MW-
31BR), 0.876 µg/L (MW-32BR) and 1.3 pg/L (MW-33BR)). Boron was not detected
in any of the groundwater samples above the method detection limit (50 pg/L).
An isoconcentration map representing the most recent analytical data for boron
is provided in Figure 6-1. The detected concentrations are consistent with
background concentrations with the exception of sulfate and total dissolved
solids in MW-32BR, though the data reflects one sampling event. The most
recent analytical data is summarized in Table 6-4 and the laboratory analytical
reports are included in Appendix E.
Page 6-4
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
6.2 EAB Eastern Extension Impoundment and Discharge Canal
Sample Results
SynTerra was retained to evaluate the water, sediment and groundwater quality
conditions associated with the EEI. SynTerra conducted water and sediment sampling
of the EEI on April 26-27, 2016 and installed and sampled groundwater monitoring
wells in June 2016. Results of the EEI investigation were presented in the CSA
Supplement 1 report (SynTerra, August 1, 2016).
6.2.1 EEI Wastewater Data
A total of four shallow water samples (CL -2S, CL -5S, CV -2 and CL -7) and two
deep water samples (CL -2 and CL -5) were collected (Figure 5-3). Sample
locations were accessed using an inflatable boat. The shallow water samples
were collected from the top foot of the water column. Deep water samples were
collected using a peristaltic pump with weighted tubing approximately two feet
from the bottom of the water column. The sample depth, sample location, and
field parameters (pH, conductivity, dissolved oxygen, temperature, and
turbidity) were recorded. The water samples were analyzed for CSA parameters
and results compared to 2L and IMAC values. Water in the extension
impoundment is part of the ash basin and is not considered waters of the state.
In this report, analytical results are compared to North Carolina 2L or IMAC
standards for informational purposes to assess potential source contribution to
groundwater.
The analytical results indicated boron, manganese, and vanadium greater than
2L or IMAC in all samples. Iron was detected greater than 2L in CL -02 and CL -
05. Analytical results are summarized in Table 6-5 and the analytical reports are
provided in Appendix E.
6.2.2 EEI Discharge Canal Wastewater Data
Five water samples (EDC -1- EDC -5) were collected from the eastern discharge
canal. EDC -1 was accessed using a pontoon boat. All other sample locations
were accessed on foot. Grab water samples from the discharge canal were
collected into sample bottleware provided by the analytical laboratory. The
water samples were analyzed for CSA parameters and results compared to 2L
and IMAC values. Water in the discharge canal is part of the ash basin and is not
considered waters of the state. In this report, analytical results are compared to
North Carolina 2L or IMAC standards for informational purposes to assess
potential source contribution to groundwater.
Page 6-5
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
The analytical results indicated boron, manganese (with the exception of EDC -
02), and vanadium are greater than 2L or IMAC in all samples. Cobalt was
detected in EDC -05 greater than 2L at 1.53 µg/L. Iron was detected greater than
2L in EDC -01, EDC -04 and EDC -05. There appears to be no apparent trend
regarding constituent concentration from the confluence of the discharge canal
with the impoundment (EDC -01) to the discharge point near the intake canal
(EDC -05). Though, boron concentrations appear greater near the impoundment
(EDC -01). Analytical results are summarized in Table 6-5 and the analytical
reports are provided in Appendix E.
6.2.3 EEI Surficial and Core Sediment Data
Four shallow sediment samples (NL -8, SL -8, CV -2, and NL -4) and five deeper
sediment cores (CL -2, CL -4, CL -6, CV -1, and CL -7) were collected. Shallow
sediment was collected from the top six inches of the sediment using a Ponar
dredge. Intact core samples were collected using the direct push barge mounted
GeoProbe with core samples collected to probe refusal. Sediment samples were
collected after the shallow water samples to minimize potential sediment
disturbance.
The depth to the bottom of the impoundment was recorded and the lithology of
intact core samples described. Ash thickness from <1 to 20 feet was observed
within the impoundment, which was greatest near the separator dike. Field
verification determined the presence of CCR material at all locations; therefore,
no additional laboratory confirmation was warranted. The sediment boring logs
are provided in Appendix D.
The sediment samples were analyzed for CSA parameters and compared to the
USEPA RSLs for Soil for Protection of Groundwater. Analytical results indicate
arsenic, selenium, and vanadium concentrations were greater than the RSL in all
sediment samples collected with the exception of CL -02, CL -06 (arsenic and
selenium) and CV -01. Barium was detected greater than the RSL in CL -06, CL -
07, and NL -04. Analytical results are summarized in Table 6-6 and the analytical
reports are provided in Appendix E.
The SPLP leaching test was used to assess if the metals present in sediment
samples may leach to groundwater. For the shallow sediment samples, cobalt,
manganese and vanadium were detected greater than the 2L or IMAC in the
leachate. In the deep sediment samples, antimony, arsenic, chromium, cobalt,
iron, manganese, thallium and vanadium were noted higher than the 2L or
IMAC in the leachate. With the exception of antimony and thallium in the deep
Page 6-6
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
sediment samples, the SPLP analysis for sediment samples from the EEI are
consistent with SPLP analysis of soil, including background locations, presented
in the CSA. The SPLP analytical results are summarized in Table 6-7 and the
laboratory analytical reports are provided in Appendix E.
6.2.4 EEI Discharge Canal Sediment and Core Sediment Data
Six locations (EDC -0 through EDC -05) were slated for sediment sampling along
the discharge canal. Of the six locations, four sediment samples (EDC -1, EDC -2,
EDC -3, and EDC -5) were collected from the discharge canal using a clam shell
sampler. A sample was not collected from EDC -4 location due to no sediment
present in the concrete channel within 100 feet upstream and downstream of the
location. EDC -0 and EDC -1 were accessed using a pontoon boat while all other
sample locations were accessed on foot.
An ash and sediment profile sample was collected from the EDC -0 location
which is located in a pool at the mouth of the EDC. The pool is separated from
the SEI by reeds and other organic material. Several attempts for sample
collection were made at the EDC -0 location with a sample EDC -00 collected for
sediment profiling. SynTerra described the sample core and determined the
presence of ash of approximately 1 foot in thickness in the EDC -00 sample. Ash
thickness was determined from <1 foot to 1 feet within the discharge canal,
which was greatest near the confluence of the impoundment and the discharge
canal. Field verification determined the presence of CCR material at all locations;
therefore, no additional laboratory confirmation was warranted. The sediment
core photographs and a boring log for EDC -00 are provided in Appendix D.
The sediment samples were analyzed for CSA parameters and compared and
compared to the USEPA RSLs for Soil for Protection of Groundwater. Analytical
results indicate antimony, arsenic, barium, copper (with the exception of EDC -
05), selenium (with the exception of EDC -03), and vanadium concentrations were
greater than the RSL in all sediment samples collected. Analytical results are
summarized in Table 6-6 and the analytical reports are provided in Appendix E.
6.2.5 EEI Groundwater Data
Three groundwater monitoring wells, MW-23BR, MW-24BR and MW-25BR, were
installed around the EEI impoundment to support existing wells, MW-17BR and
MW-20BRL to evaluate groundwater conditions in the upper bedrock (Figure 5-
3). Groundwater samples were initially collected from the EEI impoundment
wells on June 16-17, 2016 for CSA parameters and compared to 2L and IMAC
values. Analytical results indicated that several constituents were detected
Page 6-7
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
greater than the 2L or IMAC in one or more of the wells including antimony,
total chromium, iron, manganese, TDS, and vanadium. With the exception total
chromium and TDS in MW-25BR, none of the detected constituents were above
the provisional background concentrations. Boron was not detected in any of the
groundwater samples suggesting the ash present in the EEI has not impacted the
groundwater in the upper bedrock aquifer. Analytical summary tables and
laboratory analytical reports were provided in the CSA Supplement 1 report.
Groundwater samples were collected in a second sample event from the EEI
impoundment wells during the first quarter of 2017 and analyzed for CSA
parameters with comparison to 2L and IMAC values. Analytical results
indicated that several constituents were detected greater than the 2L or IMAC in
one or more of the wells including total chromium, iron, manganese, TDS, and
vanadium. With the exception of TDS in MW-25BR, none of the detected
constituents were above the provisional background concentrations. Boron was
not detected in any of the groundwater samples which continue to support that
ash present in the EEI has not impacted the groundwater in the upper bedrock
aquifer. An isoconcentration map representing the most recent analytical data
for boron is provided in Figure 6-1. The most recent analytical data is
summarized in Table 6-8 and the laboratory analytical reports are included in
Appendix E.
6.2.6 EEI Discharge Canal Groundwater Data
The monitoring wells MW-27BR through MW-30BR were installed to evaluate
groundwater quality in the bedrock along the EEI discharge canal. Groundwater
samples were collected during the first quarter of 2017 and analyzed for CSA
parameters. Analytical results are compared to 2L and IMAC values as well as
the provisional background concentrations.
Analytical results indicated that several constituents were detected greater than
the 2L or IMAC in one or more of the wells including iron (MW-30BR),
manganese (MW-27BR, MW-28BR and MW-30BR), TDS (MW-27BR and MW-
30BR), and vanadium (all wells). None of the detected constituents were above
the provisional background concentrations. Boron was not detected in any of the
groundwater samples. An isoconcentration map representing the most recent
analytical data for boron is provided in Figure 6-1. Analytical data demonstrates
the ash present in the discharge canal has not impacted groundwater in the
upper bedrock aquifer. The most recent analytical data is summarized in Table
6-8 and the laboratory analytical reports are included in Appendix E.
Page 6-8
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
7.0 GROUNDWATER MODEL AND GEOCHEMICAL MODEL
Groundwater modeling and geochemical modeling of the Roxboro Site have been
conducted to predict the fate of coal ash constituents in groundwater and changes in
groundwater geochemistry under differing remediation scenarios. Integration of
impoundment and discharge canal assessment data into future groundwater modeling
and geochemical modeling is discussed in the following subsections.
7.1 Groundwater Model
Future updates to the Site's groundwater flow and transport model will account for the
newly installed impoundment and discharge canal assessment wells and associated
groundwater data. The findings from the initial assessment data appear similar to
projections provided in previous models presented in the CAP Part 1 and CAP Part 2.
7.2 Geochemical Model
Future updates to the Site's geochemical model will include groundwater data collected
from the newly installed impoundment and discharge canal assessment wells. No
significant differences in pH/ORP from the assessment data were determined to
anticipate changes to the outcome of the geochemical model.
Page 7-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
8.0 UPDATED SITE CONCEPTUAL MODEL
Hydrogeologic and geochemical site conceptual models (SCMs) were developed for the
coal ash basins and presented in Section 6.0 of the CSA Report (SynTerra, September
2015) and revised, based on fate and transport modeling, in the CAP Part 1 (SynTerra,
December 2015). A refined SCM was presented in the CAP Part 2 (SynTerra, February
2016) based on the updated fate and transport and geochemical modeling. Additional
site specific geologic, hydrogeologic and geochemical information was presented in the
CSA Supplement 1 (SynTerra, August 2016). The SCM will continue to be refined as
additional site-specific information is obtained from the impoundment and discharge
canal assessment process.
Water level measurements for all CSA wells were collected during a 24-hour period on
April 10, 2017 for comparison to previous measurements collected during the CSA. The
water level data are presented in Table 8-1. Individual water level maps for the
saprolite and the transition zones were not made due to the limited occurrence of
saturated conditions in those units. A generalized water level map for the bedrock
aquifer, including the saprolite and transition zone hydrogeologic units, is included on
Figure 8-1. No significant changes in water levels or groundwater flow directions were
noted in April 2017 water level map as compared to the previous maps presented in the
CAP Part 2 report (SynTerra, February 29, 2016) and the CSA Supplement 1 report
(SynTerra, August 1, 2016).
Downward gradients were noted in most locations between transition zone and
bedrock wells and between upper and lower bedrock wells. The vertical gradient
magnitude and direction is similar to vertical gradient presented in the CSA report
(September 2015).
Revised conceptual geological cross-sections across the East and West Ash Basins were
developed incorporating lithological information obtained from the impoundment and
discharge canal assessment activities, data compiled from the NCDEQ water supply
well sampling events, and groundwater elevations from April 2017. The cross-sectional
transect lines A -A' and B -B' are indicated on Figure 8-2. Section A -A' show conditions
in the West Ash Basin in relation to the upgradient area to the south and the
downgradient area to the north (WAB main dam and Hyco Lake) (Figure 8-3). Section
B -B' illustrates conditions across the East Ash Basin, lined landfill and the extension
impoundment in relation to the upgradient areas, including residential properties, to
the south and downgradient areas to the north, including the Roxboro plant and intake
canal (Figure 8-4).
Page 8-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
9.0 CONCLUSIONS AND RECOMMENDATIONS
Based on the findings of the extension impoundment and discharge canal assessment
activities, the following recommendations and observations are offered:
167 Additional monitoring of the impoundment and discharge canal wells is
recommended to confirm the initial constituent concentrations.
07 Future groundwater flow and transport modeling and geochemical modeling
will need to incorporate additional data to evaluate the impoundments and
discharge canals.
,67 No substantive changes to previous site conceptual model or previously
predicted migrations of constituents from the ash basins were observed.
H Extend the compliance boundary to include the impoundments and related
discharge canals per the 'Proposed Waste and Compliance Boundary" submitted
by Duke Energy on August 19, 2016 in response to the Division of Water
Resources July 8, 2016 request.
Page 9-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS) \ DC Assessment Report \ Final Roxboro Discharge Canal Assess Rpt.docx
Ash Basin Extension Impoundments and Discharge Canals Assessment Report May 2017
Roxboro Steam Electric Plant — Semora, NC SynTerra
10.0 REFERENCES
AMEC Foster Wheeler, Duke Energy Coal Combustion Residuals Management Program,
Roxboro Steam Station, June 16, 2015.
Duke Energy, 2014; http://www.duke-energy.com/pdfs/duke-energy-ash-metrics.pdf
(Updated June 23, 2016)
SynTerra. Drinking Water Well and Receptor Survey for Roxboro Steam Electric Plant,
NPDES Permit# NC0038377. September 2014.
SynTerra. Supplement to Drinking Water Well and Receptor Survey for Roxboro Steam
Electric Plant, NPDES Permit# NC0038377. November 2014.
SynTerra. Proposed Groundwater Assessment Work Plan for Roxboro Steam Electric Plant
(Revision 1). December 30, 2014.
SynTerra. Comprehensive Site Assessment Report - Roxboro Steam Electric Plant. September
2, 2015.
SynTerra. Corrective Action Plan Part 1 - Roxboro Steam Electric Plant. December 1, 2015
SynTerra, Corrective Action Plan Part 2 — Roxboro Steam Electric Plant. February 29, 2016
SynTerra, Comprehensive Site Assessment Supplement 1— Roxboro Steam Electric Plant.
August 1, 2016
Page 10-1
P:\Duke Energy Progress.1026\107. Roxboro Ash Basin GW Assessment Plan\33.Discharge Canal Assessment
(EHS)\DC Assessment Report \Final Roxboro Discharge Canal Assess Rpt.docx