King, Art C
Tuesday, Apri) 03, 2018 9:00 AM
Williams, Andrew E CIV USARMY CESAW (US)
Norton, Apri) R
RE: [External] USACE Action ID SAW-2018-00108
Bridge 124 Montgomery County INCOMPLETE
NOTIFICATION
Attachments: Montgomery Bridge 124 Causeway.docx;
Montgomery Bridge 124 Hydro comment From.docx;
610124_Permit Drawings_20180329.pdf
Follow Up Flag:
Flag Status:
Andy,
Follow up
Flagged
Attached are the replies we received from the PEF and Galen Cail addressing your
questions about the need and placement of the causeway, and the bent placement and
span configuration. Also attached is an updated set of plans that shows the
corresponding site numbers with the data on the impact table.
If you need additional information please contact me.
Thanks,
A rt
-----Original Message-----
From: Williams, Andrew E CIV USARMY CESAW (US)
[mailto:Andrew.E.Williams2@usace.army.mil]
Sent: Wednesday, February 07, 2018 2:35 PM
To: King, Art C
Cc: Norton, April R; Williams, Andrew E CIV USARMY CESAW (US)
Subject: [External] USACE Action ID SAW-2018-00108 Bridge 124 Montgomery County
INCOMPLETE NOTIFICATION
CAUTION: External email. Do not click links or open attachments unless verified. Send all
suspicious email as an attachment to Report Spam.<mailto:report.spam@nc.gov>
A rt,
This email serves as an incomplete notification for the following NCDOT projects:
Bridge 124 replacement project in Montgomery County
It is identified by the following Corps of Engineers Action ID/Project Description:
SAW-2018-00108 (NCDOT/SR 1340 (Okeewemee Star Road/BR124/Division 8)
Please provide the following:
1. Please label each fill listed in the PCN with a corresponding letter/number/specific
identifier on the Permit Drawings.
2. Please provide additional information regarding avoidance and minimization.
Specifically, please provide addition information regarding the placement of the bridge
bent within the existing stream. The existing stream width is listed as 52 feet. Please
indicate reasons that the bridge can't be designed to span the entire width.
3. Please provide additional information regarding avoidance and minimization.
Specifically, please provide a brief discussion on the need to use a temporary
workpad/causeway.
If you have any questions or concerns, please contact me. Thanks.
Andrew Williams
Regulatory Project Manager
US Army Corps of Engineers
Wilmington District, Raleigh Regulatory Field Office
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
919-554-4884 ext. 26