HomeMy WebLinkAbout20171134 Ver 1_393-2018-02-28 - Proposed Revised Phasing - Temp Shoring RSA_20180313MOUNTAIN CREEK CONTRACTORS, INC.
205 E. Central Ave
Catawba, NC 28609
www.mtcreekinc.com
2/28/2018
NCDOT
4142 Haywood Rd.
Mills River, NC 28759
Attn: Mr. Chris Kirkman
Project: Contract ID: C203984
WBS: 46061.3.1
Fed-Aid NO.: STATE FUNDED
TIP No.: B-5347
County: Alamance
Phone 828.241.20472
Fax 828.241.3642
ID# 393-2018-02-28
Description: Bridge#170 Over a Prong of Big Alamance Creek On SR-1145 (Pond Rd.)
Subject: Proposed Revised Phasing - Temporary Shoring
Dear Mr. Powell
As I briefly discussed in my emailed on 2/19/2018, our engineer has laid out this project including the proposed
detour and required excavations to install the temporary 84" pipe and associated junction box. It appears that
temporary shoring will be required along the existing roadway in order to install the temporary junction box,
and additional temporary shoring (MSE wall) will be required over stage 1 of the culvert to build the detour.
RSA Option 1, presented in the detail sheet attached to this letter shows the anticipated quantities and cost to
the department.
Upon further evaluation of the situation, we believe we have a solution that will mitigate some of the additional
costs, and create a more efficient phasing plan for the project. Included with this letter you will find our
"Proposed Revised Construction Sequence C203984". Our plan is to shift the detour 10ft to the west, to be
offset 60ft from the center line of the existing roadway. By doing this we eliminate the need for temporary
shoring against the existing roadway, and will have enough room to construct the complete culvert in one
stage. Further, by utilizing a temporary pumping operation while we install the temporary pipe in the existing
creek, we will be able to eliminate the temporary junction box, 28' of the temporary 84" pipe and the associated
pipe plugs. More quantity of MSE wall will be required, but at a lower cost than the shoring required in Option
1. I have attached the detail for the added temporary shoring cost (RSA Option 2), as well and the anticipated
savings for the deducted items.
We believe Option 2 is the best course of action, and are anxious to get started on the required submittals. In
addintion, we also request shifting the date of availability by 30 days to April 15th, 2018. We believe this time
will be needed to design, submit and get approval for the shoring required. Please review in detail and let us
know if you have any questions or concerns. We are also happy to meet in person to discuss this.
Sincerely,
Mountain Creek Contractors, Inc.
t
� I . ,. -
r���� -
Mr. Russell Rockett
Vice President
CC: MC393 Project File
John Holcombe, MCC
Don Phillips, MCC
Brown Rollins, MCC
Eric Towner, MCC
John Williams, NCDOT
Option 1- Phasing and Detour as shown in contract plans
Description
SA - Temporary Shoring - H-Pile and Lagging
SA - Temporary Shoring - MSE Wall
Option 2- Proposed Revised Construction Sequence
Description
SA - Temporary Shoring - MSE Wall
SA - Portland Concrete Barrier - Anchored
Deduct - 84" Draingage Pipe
Deduct - Pipe Removal
Deduct - Masonry Drainage Str.
Deduct - Pipe Plug
Deduct - Temporary Guardrail
Additional - Asp Conc Surf Crs SF9.5A
Additional - Asp for Plant Mix
Additional - ABC Stone
Unit Unit Price Total
660 SF 84.53 $ 55,791.89
886 SF 40.24 $ 35,655.03
Total: $ 91,446.93
Unit
1900 SF
168 ft
-28 LF
-28 LF
-12.8 CY
-5 CY
-168 LF
10 tn
0.5 tn
30 tn
Unit Price Total
39.24 $ 74,552.36
62.92 $ 10,571.03
375 $ (10,500.00)
19 $ (532.00)
600 $ (7,680.00)
900 $ (4,500.00)
10 $ (1,680.00)
123 $ 1,230.00
480 $ 240.00
45 $ 1,350.00
Total: $ 63,051.39
1'�"[� �.i l`� �T�,. I I� � I�� E i� ��l`� T 1�.��T'� l�� � 11"� �.
Request for Supplemental Agreement (RSA)
Project: Alamance County C203984 MCC RSA No. 1
MCC Project NO. MC393 Date 2/28/2018
MCC RSA Description: Temporary Shoring - Option 1
Quantity 1.0 LS
RECAP SHEET
Description Total Labor Travel Material Equipment Subcontract
Temporary H-Pile Lagging $ 48,501.87 $ 11,156.45 $ - $ 32,366.60 $ 4,978.82
Temporary MSE Wall $ 31,620.71 $ 11,222.69 $ - $ 17,445.07 $ 2,952.95
$ -
$ -
$ -
$ -
Sub-total $ 80,122.58 $ 22,379.14 $ - $ 49,811.67 $ 4,978.82 $ 2,952.95
Additives Burden 109-3 (A) Additive 109-3( C) FOG 109-3 (D) Additive 109-3 (G)
0.00% 15.00% 15.00% 10% uto $t0,000, then 5%
Additive TotaL $ 8,513.87 $ - $ - $ 7,471.75 $ 746.82 $ 295.30
Sub-total $ 88,636.45 $ 22,379.14 $ - $ 57,283.42 $ 5,725.64 $ 3,248.25
Overhead and Profit
Overhead and Profit Total $
Sub-total $
2,810.48 $
91,446.93 $
10.00 % 10.00%
2,237.91 $ - $
24,617.05 $ - $
Item Qty Unit Unit Price Total
Temporary H-Pile Lagging 660.0 SF $ 84.53 $ 55,791.89
Temporary MSE Wall 886.0 SF $ 40.24 $ 35,655.03
TOTAL $ 91,446.93
Notes:
1.
2.
3.
4.
�
*For the purposes of this supplement agreement, we have applied markups similar to the
standard specifications for Force Account work.
PAG E 1
0.00%
_ $
57,283.42 $
10.00 %
572.56 $
6,298.21 $
3,248.25
�"�i� � l�,[[ T`.� I �I � l�� � �. ��1�[ T �..�,,,�T`� 1�.� , 1 �,l �.
Request for Supplemental Agreement (RSA)
Project: Alamance County C203984
MCC Project N0. MC393
MCC RSA Description: Temporary Shoring - Option 2
Quantity 1.0 LS
RECAP SHEET
MCC RSA No. 1
Date 2/28/2018
Description Total Labor Travel Material Equipment Subcontract
Temporary MSE Wall $ 66,161.47 $ 22,418.69 $ - $ 37,410.28 $ 6,332.50
Portland Concrete Barrier - Anchored $ 9,744.00
$ -
$ -
$ -
$ -
Sub-total $ 75,905.47 $ 22,418.69 $ - $ 37,410.28 $ - $ 16,076.50
Additives Burden 109-3 (A) Additive 109-3( C) FOG 109-3 (D) Additive 109-3 (G)
0.00% 15.00% 15.00% 10% uto $t0,000, then 5%
Additive TotaL $ 6,915.37 $ - $ - $ 5,611.54 $ - $ 1,303.83
Sub-total $ 82,820.84 $ 22,418.69 $ - $ 43,021.82 $ - $ 17,380.33
Overhead and Profit
Overhead and Profit Total $
Sub-total $
2,241.87 $
85,062.71 $
10.00 %
2,241.87 $
24,660.56 $
Item Qty Unit Unit Price Total
Temporary MSE Wall 1,900.0 SF $ 39.24 $ 74,552.36
Portland Concrete Barrier - Anchored 168.0 If $ 62.92 $ 10,571.03
TOTAL $ 85,123.39
Notes:
1.
2.
3.
4.
5.
10.00%
_ $
_ $
*For the purposes of this supplement agreement, we have applied markups similar to the
standard specifications for Force Account work.
PAG E 1
0.00 %
_ $
43,021.82 $
10.00%a
17,380.33