Loading...
HomeMy WebLinkAbout20171134 Ver 1_393-2018-02-28 - Proposed Revised Phasing - Temp Shoring RSA_20180313MOUNTAIN CREEK CONTRACTORS, INC. 205 E. Central Ave Catawba, NC 28609 www.mtcreekinc.com 2/28/2018 NCDOT 4142 Haywood Rd. Mills River, NC 28759 Attn: Mr. Chris Kirkman Project: Contract ID: C203984 WBS: 46061.3.1 Fed-Aid NO.: STATE FUNDED TIP No.: B-5347 County: Alamance Phone 828.241.20472 Fax 828.241.3642 ID# 393-2018-02-28 Description: Bridge#170 Over a Prong of Big Alamance Creek On SR-1145 (Pond Rd.) Subject: Proposed Revised Phasing - Temporary Shoring Dear Mr. Powell As I briefly discussed in my emailed on 2/19/2018, our engineer has laid out this project including the proposed detour and required excavations to install the temporary 84" pipe and associated junction box. It appears that temporary shoring will be required along the existing roadway in order to install the temporary junction box, and additional temporary shoring (MSE wall) will be required over stage 1 of the culvert to build the detour. RSA Option 1, presented in the detail sheet attached to this letter shows the anticipated quantities and cost to the department. Upon further evaluation of the situation, we believe we have a solution that will mitigate some of the additional costs, and create a more efficient phasing plan for the project. Included with this letter you will find our "Proposed Revised Construction Sequence C203984". Our plan is to shift the detour 10ft to the west, to be offset 60ft from the center line of the existing roadway. By doing this we eliminate the need for temporary shoring against the existing roadway, and will have enough room to construct the complete culvert in one stage. Further, by utilizing a temporary pumping operation while we install the temporary pipe in the existing creek, we will be able to eliminate the temporary junction box, 28' of the temporary 84" pipe and the associated pipe plugs. More quantity of MSE wall will be required, but at a lower cost than the shoring required in Option 1. I have attached the detail for the added temporary shoring cost (RSA Option 2), as well and the anticipated savings for the deducted items. We believe Option 2 is the best course of action, and are anxious to get started on the required submittals. In addintion, we also request shifting the date of availability by 30 days to April 15th, 2018. We believe this time will be needed to design, submit and get approval for the shoring required. Please review in detail and let us know if you have any questions or concerns. We are also happy to meet in person to discuss this. Sincerely, Mountain Creek Contractors, Inc. t � I . ,. - r���� - Mr. Russell Rockett Vice President CC: MC393 Project File John Holcombe, MCC Don Phillips, MCC Brown Rollins, MCC Eric Towner, MCC John Williams, NCDOT Option 1- Phasing and Detour as shown in contract plans Description SA - Temporary Shoring - H-Pile and Lagging SA - Temporary Shoring - MSE Wall Option 2- Proposed Revised Construction Sequence Description SA - Temporary Shoring - MSE Wall SA - Portland Concrete Barrier - Anchored Deduct - 84" Draingage Pipe Deduct - Pipe Removal Deduct - Masonry Drainage Str. Deduct - Pipe Plug Deduct - Temporary Guardrail Additional - Asp Conc Surf Crs SF9.5A Additional - Asp for Plant Mix Additional - ABC Stone Unit Unit Price Total 660 SF 84.53 $ 55,791.89 886 SF 40.24 $ 35,655.03 Total: $ 91,446.93 Unit 1900 SF 168 ft -28 LF -28 LF -12.8 CY -5 CY -168 LF 10 tn 0.5 tn 30 tn Unit Price Total 39.24 $ 74,552.36 62.92 $ 10,571.03 375 $ (10,500.00) 19 $ (532.00) 600 $ (7,680.00) 900 $ (4,500.00) 10 $ (1,680.00) 123 $ 1,230.00 480 $ 240.00 45 $ 1,350.00 Total: $ 63,051.39 1'�"[� �.i l`� �T�,. I I� � I�� E i� ��l`� T 1�.��T'� l�� � 11"� �. Request for Supplemental Agreement (RSA) Project: Alamance County C203984 MCC RSA No. 1 MCC Project NO. MC393 Date 2/28/2018 MCC RSA Description: Temporary Shoring - Option 1 Quantity 1.0 LS RECAP SHEET Description Total Labor Travel Material Equipment Subcontract Temporary H-Pile Lagging $ 48,501.87 $ 11,156.45 $ - $ 32,366.60 $ 4,978.82 Temporary MSE Wall $ 31,620.71 $ 11,222.69 $ - $ 17,445.07 $ 2,952.95 $ - $ - $ - $ - Sub-total $ 80,122.58 $ 22,379.14 $ - $ 49,811.67 $ 4,978.82 $ 2,952.95 Additives Burden 109-3 (A) Additive 109-3( C) FOG 109-3 (D) Additive 109-3 (G) 0.00% 15.00% 15.00% 10% uto $t0,000, then 5% Additive TotaL $ 8,513.87 $ - $ - $ 7,471.75 $ 746.82 $ 295.30 Sub-total $ 88,636.45 $ 22,379.14 $ - $ 57,283.42 $ 5,725.64 $ 3,248.25 Overhead and Profit Overhead and Profit Total $ Sub-total $ 2,810.48 $ 91,446.93 $ 10.00 % 10.00% 2,237.91 $ - $ 24,617.05 $ - $ Item Qty Unit Unit Price Total Temporary H-Pile Lagging 660.0 SF $ 84.53 $ 55,791.89 Temporary MSE Wall 886.0 SF $ 40.24 $ 35,655.03 TOTAL $ 91,446.93 Notes: 1. 2. 3. 4. � *For the purposes of this supplement agreement, we have applied markups similar to the standard specifications for Force Account work. PAG E 1 0.00% _ $ 57,283.42 $ 10.00 % 572.56 $ 6,298.21 $ 3,248.25 �"�i� � l�,[[ T`.� I �I � l�� � �. ��1�[ T �..�,,,�T`� 1�.� , 1 �,l �. Request for Supplemental Agreement (RSA) Project: Alamance County C203984 MCC Project N0. MC393 MCC RSA Description: Temporary Shoring - Option 2 Quantity 1.0 LS RECAP SHEET MCC RSA No. 1 Date 2/28/2018 Description Total Labor Travel Material Equipment Subcontract Temporary MSE Wall $ 66,161.47 $ 22,418.69 $ - $ 37,410.28 $ 6,332.50 Portland Concrete Barrier - Anchored $ 9,744.00 $ - $ - $ - $ - Sub-total $ 75,905.47 $ 22,418.69 $ - $ 37,410.28 $ - $ 16,076.50 Additives Burden 109-3 (A) Additive 109-3( C) FOG 109-3 (D) Additive 109-3 (G) 0.00% 15.00% 15.00% 10% uto $t0,000, then 5% Additive TotaL $ 6,915.37 $ - $ - $ 5,611.54 $ - $ 1,303.83 Sub-total $ 82,820.84 $ 22,418.69 $ - $ 43,021.82 $ - $ 17,380.33 Overhead and Profit Overhead and Profit Total $ Sub-total $ 2,241.87 $ 85,062.71 $ 10.00 % 2,241.87 $ 24,660.56 $ Item Qty Unit Unit Price Total Temporary MSE Wall 1,900.0 SF $ 39.24 $ 74,552.36 Portland Concrete Barrier - Anchored 168.0 If $ 62.92 $ 10,571.03 TOTAL $ 85,123.39 Notes: 1. 2. 3. 4. 5. 10.00% _ $ _ $ *For the purposes of this supplement agreement, we have applied markups similar to the standard specifications for Force Account work. PAG E 1 0.00 % _ $ 43,021.82 $ 10.00%a 17,380.33