Subject: Inspection-US Highway 19/19E
DWQ Project 07-1134
Individual Certification No. 3706
TIP Nos. R-2518A and R-2518B
Madison and Yancey Counties
Dear Mr. Swain:
On March 4, 2009 I inspected the construction work on the US Highway 19/19E project in Madison and
Yancey Counties. Major grading, culvert extension and bridgework are underway along the entire length of
the project.
The Division of Water Quality continues to have concerns about sediment and turbidity in streams from the
construction areas. Please continue to ensure that all sediment and erosion control structures are maintained
and that seeding and mulching are performed as required to protect State surface waters.
Also, please refer to the attached inspection report for any specific items noted during the inspection.
If you have questions, please call me at 828-296-4500.
Sincerely,
Michael R. Parker l7
Environmental Senior Specialist
Attachment
cc: Randy McKinney, PE
Roger Bryan, Division 13, DEO
Ed Ingle, Roadside Environmental
Transportation Permitting Unit }
Niki Maher, NPS Assistance and Compliance Oversight Unit
Mike Parker, Asheville Regional Office
SURFACE WATER PROTECTION SECTION - Asheville Regional Office
2090 U.S. 70 Highway. Swannanoa. NC 28778-8211
Phone: 820-M-4600 t FAX: 828-299-7043 One
Customer Service: 1-877-6236746 1 fla
An Internet. vnwencvvalergualitvora N O rta Equal Op(wnunily%Afrimative Action Employer NaLFl CClaro" ??" a(fin
lly
i
DWQ Site Visits for DOT Projects
Field Sheet
DWQ representative: Michael R. Parker Date: March 4, 2009
County: Buncombe Region: Asheville
DOT Division: Division 13
Activity: X 401 Compliance Evaluation ? Complaint
?DWQ Follow Up Evaluation ? Other
DWQ 4019: wOC No. 3706 NW Permit 9:1== IP #:
Project Name:
Location of Project:
Improvements to US Hivhwav 19E -
US Highway 19 and 19E from fixture 1-26 in Madison County to SR 1336 in Yancey
County
Project Complete:. ?Yes X No
Activities (DOT):
X? Bridge
X? Culvert
? Bottomless Culvert
? Bottomless Arch
X? Riprap fnlet/Outlet Stabilization
? Spoil Pile
? Borrow Pit
X? Wetland Mitigation
? Stream Restoration
X? On-site Stream Relocation
? Buffer Restoration
? Bank Stabilization
? Other Fill
If no, estimated date of completion:
Water Quality Concerns (DWQ):
X? Steam Standards Violation
X? Turbidity
? Evidence of spills
? Oil/Petroleum
? Solid Waste
X? Failed E & S control measures
X? Sedimentation Impacts
? Stormwater Permit Violation
? Fill
? Buffer Impacts (see below)
? Other
Additional Wetland Impacts: ? yes ? no Estimated Acres
? Zone 1 Est Acres E7== ? Zone 2 Est Acres Additional Stream Impacts: ? yes X? no Est Linear feet
Estimated linear feet of impact: F-
Buffer Impacts:. ?Neuse []Tar-Pam []Randleman []Catawba
Zone 1: ?Yes ?No Est linear ft/ acreage of buffer impact ft/ ac
Zone 2: ?Yes ?No Est linear ft/ acreage of buffer impact ft/ ac
Buffer Designation: ?Exernpt []Allowable []Allowable w/mitigation []Prohibited
Name of Waterway(s):
DWQ Site Visits for DOT Protects
Background Info
Middle Fork Creek, Bailey Branch, Turkey Branch, Polly Branch,
Holland Creek, Ivy Gap Branch, Bald Creek, Price's Creek, Phipps
Creek and Cane River
Basin/ Subbasin: PBR 040304 and 040307
Wetland Type: ?Isolated X?Non-Isolated (Waters of US)
Stream Class: ?Class B ?303d Listed X?WS-11 ?WS-V ?SB
X?ClassC ?ORW X?Trout ?WS-III ?NSW
X?HQW ?WS-1 ?WS-IV ?SA ?CA
Type of Authorized Impact: X?Culvert ?Bottomless Culvert
X?Bridge ?Bottomless Arch
X?Riprap lnlet/OUtlet Stabilization X?Fill
Authorized Wetland Impacts
Authorized Stream Impacts
?0 - I/ 10"' acre
X? 1/3`a to 1.0 acre
?< 150 linear feet
X? 1/11"' to 1 /3'a acre
?> 1.0 acre
X?> 150 linear feet
Additional comments: 7,059 linear ft. of stream impacts and 0.42 acres of wetlands for R-251 8A;
3,675 linear ft. of stream impacts and 0.23 acres of wetlands for R-2518B. Compensatory
mitigation for impacts of 5, 453 linear feet is required.
1. Heavy grading and construction work is taking place along the entire length of the project.
2.Construction work includes bridge construction, culvert extension, fill and borrow.
3.Observations include the muddy water discharge into streams, and soil material remaining on the
work pads from drill holes.
4.Please ensure that all sediment and erosion control devices are maintained and working properly.
5.As a reminder the streams on the Madison County construction area are classified as Fligh Quality
Waters and all measures necessary to protect State surface waters should be employed.
6. In-water Work Moratoriums reminder:
Cane River and tributaries April I to June 30
Bald Creek and tributaries January I to April 15
Price Creek and tributaries January I to April 15
March 2009 Inspection US Highway 19 R-2518 A &B