HomeMy WebLinkAboutAMREP New Facility - SW 3180201_ 11761-A Summit Corporate Center - GEO Report
REPORT
OF
SUBSURFACE EXPLORATION
SUMMIT CORPORATE CENTER
SALISBURY, NORTH CAROLINA
ECS PROJECT NO. 08-11761-A
JULY 12, 2016
REPORT OF SUBSURFACE EXPLORATION
Summit Corporate Center
Salisbury, North Carolina
Prepared For:
Mr. Scott Shelton
Project Manager
RowanWORKS
204 East Innes Street, Suite 220
Salisbury, North Carolina
Prepared By:
ECS CAROLINAS, LLP
1812 Center Park Drive
Suite D
Charlotte, NC 28217
ECS Project No:
08-11761-A
Report Date:
July 12, 2016
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 2 July 12, 2016
1. INTRODUCTION
1.1. Project Information
The project site is approximately 5 acres in size and is located off of Julian Road in Salisbury,
North Carolina. We understand the project will consist of the construction of a 30,000 square-
foot (SF) facility with 2,000 SF of office space. Surface parking and drive areas will be
constructed around the remainder of the site. Based on our review of Google Earth and our
subsequent site visit, the site is undeveloped and moderately to heavily wooded.
Based on the topographic map provided, the existing topography at the site generally slopes
from a high elevation of approximately 796 feet along the southern portion of the site to a low
elevation of approximately 786 feet along the northern portion of the site for a total relief of 10
feet. Final design elevations were not provided to us at the time of this exploration. Therefore,
we assume mass grading will consist of cut and fill depth on the order of 5 feet or less.
Construction methodology and structural loading conditions have not been provided to us at this
time. However, we anticipate the proposed structure will be either wood-framed with brick
veneer or concrete masonry unit (CMU) construction with maximum column and wall footing
loads on the order of 100 kips and 4 kips per linear foot, respectively. No other information was
available at the time of this report.
1.2. Scope of Services
Our scope of services included a subsurface exploration with soil test borings, engineering
analysis of the foundation support options, and preparation of this report with our
recommendations. The subsurface exploration included a total of ten (10) soil test borings (B-1
through B-10) drilled to depths ranging from approximately 19 to 20 feet below existing grades.
Approximate boring locations are shown on the Boring Location Diagram (Figure 2) included in
the Appendix. The soil borings were performed using a SIMCO 2400 track-mounted drill rig
using continuous-flight, hollow-stem augers.
2. FIELD SERVICES
2.1. Test Locations
The soil boring locations were selected and located in the field by ECS using a handheld GPS
device and existing landmarks as reference. The approximate test locations are shown on the
Boring Location Diagram (Figure 2) presented in the Appendix of this report and should be
considered accurate only to the degree implied by the method used to obtain them. Ground
surface elevations at the boring locations were estimated from the provided topographic survey
and should be considered approximate.
2.2. Soil Test Borings
Ten (10) soil test borings were drilled to evaluate the stratification and engineering properties of
the subsurface soils at the project site. Standard Penetration Tests (SPT’s) were performed at
designated intervals in general accordance with ASTM D 1586. The Standard Penetration Test
is used to provide an index for estimating soil strength and density. In conjunction with the
penetration testing, split-barrel soil samples were recovered for soil classification at each test
interval. Boring Logs are included in the Appendix.
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 3 July 12, 2016
The drill crew also maintained a field log of the soils encountered at each of the boring locations.
After recovery, each sample was removed from the split-spoon sampler and visually classified.
Representative portions of each sample were then sealed and brought to our laboratory in
Charlotte, North Carolina for further visual examination and laboratory testing. Groundwater
measurements were attempted at the termination of drilling at each boring location.
3. LABORATORY SERVICES
Soil samples were collected from the borings and examined in our laboratory to check field
classifications and to determine pertinent engineering properties. Data obtained from the
borings and our visual/manual examinations are included on the respective boring logs in the
Appendix.
3.1. Soil Classification
A geotechnical staff professional classified each soil sample on the basis of color, texture, and
plasticity characteristics in general accordance with the Unified Soil Classification System
(USCS). The soil engineer then grouped the various soil types into the major zones noted on
the boring logs. The stratification lines designating the interfaces between earth materials on
the boring logs and profiles are approximate; in situ, the transition between strata may be
gradual in both the vertical and horizontal directions. The results of the visual classifications are
presented on the Boring Logs included in the Appendix.
4. SITE AND SUBSURFACE FINDINGS
4.1. Area Geology
The site is located in the Piedmont Physiographic Province of North Carolina. The native soils in
the Piedmont Province consist mainly of residuum with underlying saprolites weathered from the
parent bedrock, which can be found in both weathered and unweathered states. Although the
surficial materials normally retain the structure of the original parent bedrock, they typically have
a much lower density and exhibit strengths and other engineering properties typical of soil. In a
mature weathering profile of the Piedmont Province, the soils are generally found to be finer
grained at the surface where more extensive weathering has occurred. The particle size of the
soils generally becomes more granular with increasing depth and gradually changes first to
weathered and finally to unweathered parent bedrock. The mineral composition of the parent
rock and the environment in which weathering occurs largely control the resulting soil's
engineering characteristics. The residual soils are the product of the weathering of the parent
bedrock.
4.2. Subsurface Conditions
The subsurface conditions at the site, as indicated by the borings, generally consisted of
residual soils, partially weathered rock (PWR), and refusal materials to the depths explored.
The generalized subsurface conditions are described below. For soil stratification at a particular
test location, the respective Boring Log found in the Appendix should be reviewed.
A layer of surficial organic laden soil, approximately 2 to 3½ inches thick, was encountered at
the existing ground surface at Borings B-1 through B-10. The organic laden soil depths provided
in this report and on the individual Boring Logs are based on driller observation and should be
considered approximate. Since a bulldozer was used to gain access to the boring locations,
some of the surficial organic laden soil may have been removed during clearing. Please note
that these reported values should not be used in determining removal quantities.
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 4 July 12, 2016
Residual soils were encountered beneath the surficial materials at Borings B-1 through B-10.
Residual soils are formed by the in-place chemical and mechanical weathering of the parent
bedrock. The residual soils encountered in the borings generally consisted of Fat CLAY (CH),
Sandy CLAY (CL), Clayey SAND (SC), Sandy SILT (ML), and Silty SAND (SM) exhibiting SPT
N-values ranging from 4 to 94 blows per foot (bpf), with a majority of the N-values between 10
and 32 bpf. Borings B-1 and B-4 through B-10 were terminated in the residual soils at depths of
approximately 20 feet below existing grade.
Partially weathered rock (PWR) was encountered beneath the residual soils at Borings B-2 and
B-3. The top of PWR was encountered at depths ranging from approximately 8 feet to 17 feet
below existing grades. A lens of PWR was encountered at Boring B-2 from approximately 8 to
12 feet and at B-10 from approximately 5½ to 8 feet below existing grades. PWR is defined as
residual material exhibiting SPT N-values greater than 100 bpf. The PWR encountered
generally consisted of Sandy Silt (ML) and Silty Sand (SM) exhibiting SPT N-values of 50 blows
per 5 inches of penetration to 50 blows per 3 inches of penetration. Boring B-3 was terminated
in PWR at a depth of approximately 20 feet below existing grades.
Auger refusal was encountered at Boring B-2 at a depth of approximately 19 feet below existing
grades. Auger refusal indicates the presence of material that permitted no further advancement
of the hollow stem auger or split spoon sampler. Rock coring would be required to evaluate the
character and continuity of the refusal materials; however, rock coring was beyond the scope of
this investigation.
4.3. Groundwater Observations
Groundwater measurements were attempted at the termination of drilling at the time of our
exploration. Groundwater was encountered at Boring B-1 at a depth of approximately 17 feet
below existing ground surface. The remaining borings were dry at the time groundwater was
measured. Borehole cave-in depths were observed at each boring location at depths ranging
from approximately 15.1 feet to 17.7 feet below the existing ground surface. Cave-in of a soil
test boring can be caused by groundwater hydrostatic pressure, weak soil layers, and/or drilling
activities (i.e. drilling fluid circulation or advancement of bit).
Fluctuations in the groundwater elevation should be expected depending on precipitation, run-
off, utility leaks, and other factors not evident at the time of our evaluation. Normally, highest
groundwater levels occur in late winter and spring and the lowest levels occur in late summer
and fall. Depending on time of construction, groundwater may be encountered at shallower
depths and locations not explored during this study. If encountered during construction,
engineering personnel from our office should be notified immediately.
5. CONCLUSIONS AND RECOMMENDATIONS
The borings performed at this site represent the subsurface conditions at the location of the
borings. Due to inconsistencies associated with the prevailing geology, there can be changes in
the subsurface conditions over relatively short distances that have not been disclosed by the
results of the test location performed. Consequently, there may be undisclosed subsurface
conditions that require special treatment or additional preparation once these conditions are
revealed during construction.
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 5 July 12, 2016
Our evaluation of foundation support conditions has been based on our understanding of the
site, project information, and the data obtained in our exploration. The general subsurface
conditions utilized in our foundation evaluation have been based on interpolation of subsurface
data between and away from the borings. In evaluating the boring data, we have examined
previous correlations between penetration resistance values and foundation bearing pressures
observed in soil conditions similar to those at your site.
5.1. Organic Laden Soils
A layer of surficial organic laden soil, ranging from approximately 2 to 3½ inches, was
encountered at the ground surface. Since a bulldozer was used to gain access to a majority of
the boring locations, some of the surficial organic laden soils may have been removed during
clearing. Please note that these reported values should not be used in determining topsoil
removal quantities.
The surficial organic laden soil is typically a dark-colored soil material containing roots, fibrous
matter, and/or other organic components, and is generally unsuitable for support of engineering
fill, foundations, or slabs-on-grade. ECS has not performed laboratory testing to determine the
organic content or other horticultural properties of the observed surficial organic laden soils.
Therefore, the phrase “surficial organic laden soil” is not intended to indicate suitability for
landscaping and/or other purposes. The surficial organic laden soil depths provided in this
report and on the individual Boring Logs are based on driller observations and should be
considered approximate. Please note that the transition from surficial organic laden soils to
underlying materials may be gradual, and therefore the observation and measurement of the
surficial organic laden soil depth is approximate. Actual surficial organic laden soil depths
should be expected to vary and generally increases with the amount of vegetation present over
the site.
5.2. Moisture Sensitive Soils (CH)
Fat CLAY (CH) was encountered at Boring B-3 at depths ranging from approximately 3 to 5½
feet below existing grades. Soils classified as CH are fine-grained and have a Liquid Limit
greater than 50 percent. Additionally, CH soils are considered highly moisture sensitive and can
shrink and swell with moisture variations. Depending on final design grades, some of the CH
soils may be removed during mass grading or excavated during foundation installation.
CH soils should not be used for direct support of foundations, slabs-on-grade, or pavement
subgrades. CH encountered within proposed structural areas should be undercut and replaced
with low plasticity engineered fill to a minimum depth of 2 feet below foundations and 2 feet
below subgrade elevations in slab and pavement areas. The quality of the subgrade soils
should be evaluated by the geotechnical engineer on a case-by-case basis in order to evaluate
the need for remediation. As previously mentioned, some isolated undercutting in the vicinity of
Boring B-3 (building pad) should be anticipated.
5.3. Weak Near-Surface Soils
Weak near-surface soils, with an N-value of 5 bpf or less, were encountered at Boring B-7 and
extended to depths of approximately 3 feet below existing grades. In their present condition,
these soils are generally considered marginally suitable to unsuitable for fill placement,
foundations, floor slabs and pavement subgrades and should be undercut from beneath
structural areas.
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 6 July 12, 2016
Pending a successful proofroll and acceptable dynamic cone penetrometer (DCP) testing, these
soils may remain in place. However, if these soils do not pass a proofroll or DCP testing, some
undercutting and/or recompaction should be anticipated. The resulting undercut should be
backfilled with structural fill placed and compacted in accordance with the recommendations
contained in this report. This should be further evaluated by ECS personnel in the field during
construction. Depending on final design grades, some of these soils may be removed or filled
over during site grading operations.
5.4. Seismic Site Classification
The North Carolina Building Code (NCBC) requires that the stiffness of the top 100-ft of soil
profile be evaluated in determining a site seismic classification. The method for determining the
Site Class is presented in Section 1613 of the NCBC. The seismic Site Class is typically
determined by calculating a weighted average of the N-values or shear wave velocities recorded
to a depth of 100 feet within the proposed building footprint. The SPT values measured in the
soil profile at the site indicate that a seismic site class of “D” is appropriate for this project.
5.5. Structure Foundations
Provided the recommendations outlined herein are implemented, the proposed building can be
adequately supported on a shallow foundation system consisting of spread footings bearing on
low plasticity residual soil or newly-placed engineered fill. A bearing capacity of up to 3,000 psf
is recommended for foundations bearing on approved low plasticity residual soil or newly-placed
engineered fill.
As previously mentioned, CH soils should not be used for direct support of foundations or slabs-
on-grade. CH soils encountered should be undercut and replaced with approved engineered fill
to a minimum depth of 2 feet below foundations provided that the resulting subgrade is stable.
For this project, minimum wall and column footing dimensions of 18 and 24 inches, respectively,
should be maintained to reduce the possibility of a localized, “punching” type, shear failure.
Exterior foundations and foundations in unheated areas should be embedded deep enough
below exterior grades to reduce potential movements from frost action or excessive drying
shrinkage. For this region, we recommend footings bear at least 18 inches below finished
grade.
Total settlement is anticipated to be less than 1 inch, while differential settlement between
columns is anticipated to be less than ½ inch for shallow foundations bearing on low plasticity
residual soil or newly-placed structural fill. Foundation geometry, loading conditions, and/or
bearing strata different than those described in this report may result in magnitudes of
settlement inconsistent with the previous estimates.
5.6. Slab-On-Grade Support
Slabs-on-grade can be adequately supported on undisturbed low plasticity natural soils or
newly-placed engineered fill provided the site preparation and fill recommendations outlined
herein are implemented. For a properly prepared site, a modulus of subgrade reaction (ks) for
the soil of 90 pounds per cubic inch for the soil can be used. This value is representative of a 1-
ft square loaded area and may need to be adjusted depending on the size and shape of the
loaded area and depending on the method of structural analysis.
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 7 July 12, 2016
CH soils should not be used for direct support of slabs-on-grade. If these soils are encountered
at or near final design grades, they should be undercut and replaced with approved engineered
fill to a minimum depth of 2 feet below the slab-on-grade provided that the resulting subgrade is
stable.
We recommend the slab-on-grade be underlain by a minimum of 4 inches of granular material
having a maximum aggregate size of 1½ inches and no more than 2 percent fines. Prior to
placing the granular material, the floor subgrade soil should be properly compacted, proofrolled,
and free of standing water, mud, and frozen soil. A properly designed and constructed capillary
break layer can often eliminate the need for a moisture retarder and can assist in more uniform
curing of concrete. If a vapor retarder is considered to provide additional moisture protection,
special attention should be given to the surface curing of the slabs to minimize uneven drying of
the slabs and associated cracking and/or slab curling. The use of a blotter or cushion layer
above the vapor retarder can also be considered for project specific reasons.
Please refer to ACI 302.1R04 Guide for Concrete Floor and Slab Construction and ASTM E
1643 Standard Practice for Installation of Water Vapor Retarders Used in Contact with Earth or
Granular Fill Under Concrete Slabs for additional guidance on this issue.
ECS recommends that the slab be isolated from the footings so differential settlement of the
structure will not induce shear stresses on the floor slab. Also, in order to minimize the crack
width of shrinkage cracks that may develop near the surface of the slab, we recommend mesh
reinforcement as a minimum be included in the design of the floor slab. For maximum
effectiveness, temperature and shrinkage reinforcements in slabs on ground should be
positioned in the upper third of the slab thickness. The Wire Reinforcement Institute
recommends the mesh reinforcement be placed 2 inches below the slab surface or upper one-
third of slab thickness, whichever is closer to the surface.
Adequate construction joints, contraction joints and isolation joints should also be provided in the
slab to reduce the impacts of cracking and shrinkage. Please refer to ACI 302.1R04 Guide for
Concrete Floor and Slab Construction for additional information regarding concrete slab joint
design.
5.7. Pavement Considerations
Undisturbed low-plasticity residual soils or newly placed engineered fill can provide adequate
support for pavement structures and walkways designed for appropriate subgrade strength and
traffic characteristics. Based on the soil types encountered in the soil test borings, we
recommend a CBR value of 3 be used in design of the project pavements. For the design and
construction of exterior pavements, the subgrades should be prepared in accordance with the
recommendations in the “Site and Subgrade Preparation” and “Engineered Fill” sections of this
report.
We emphasize that good base course drainage is essential for successful pavement
performance. Water buildup in the base course will result in premature pavement failures. The
subgrade and pavement should be graded to provide effective runoff to either the outer limits of
the paved area or to catch basins so that standing water will not accumulate on the subgrade or
pavement.
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 8 July 12, 2016
The pavement at locations for refuse dumpsters should be properly designed for the high axial
loads and twisting movements of the trucks. Consideration should be given to the use of
concrete pavement for the dumpster and approach areas. We recommend that the refuse
collector be consulted to determine the size and thickness of the concrete pads for dumpsters.
At locations where delivery truck, semi-trailers, and/or buses will be turning and maneuvering,
the flexible pavement section should be designed to resist the anticipated shear stress on the
pavement throughout the required pavement service life. When the traffic volumes, wheel
loading conditions, and service life have been estimated, ECS can perform pavement analyses
for flexible and rigid pavements for an additional fee.
5.8. Excavation Characteristics
We anticipate a majority of the near-surface subgrade soils at the site can be excavated with
backhoes, front-end loaders or other similar equipment using conventional means and methods.
Partially weathered rock (PWR) was encountered Borings B-2, B-3, and B-10 at various depths
ranging from approximately 5½ to 20 feet below existing grades. In addition, auger refusal was
encountered at Boring B-2 at a depth of approximately 19 feet below existing grades. Partially
weathered rock and auger refusal depths should be taken into consideration by the site civil
designer when developing foundation, storm drainage, and utility plans.
We would like to point out that our experience indicates rock in a weathered, boulder, and/or
massive form varies erratically in location and depth within the Piedmont Geologic Province, of
which Rowan County is part. Due to the variability of the Piedmont soils, there is always a
potential that these materials could be encountered at shallower depths between the boring
locations. The depth to, and thickness of weathered rock, rock lenses or seams, and bedrock,
can vary dramatically in short distances and between boring locations; therefore, weathered rock
and/or bedrock should be anticipated during construction at locations or depths, between boring
locations, not encountered during this exploration.
Typically, in mass excavation for general site work, materials with an N-value of 50 blows per 3
to 6 inches of penetration can be excavated with moderate to heavy effort using appropriately
sized equipment, such as a large track-hoe (e.g., Caterpillar 330 with rock teeth or a D-8
bulldozer with a single ripping tooth). In confined excavations such as foundations, utility
trenches, etc., removal of PWR may require use of heavy duty backhoes, pneumatic spades, or
blasting. Material that exhibits less than 3 inches of penetration per 50 blows and material
causing auger refusal will likely require jack hammering, blasting or drilling to facilitate removal.
Due to the apparent quality of the refusal materials and local geology, we anticipate that blasting
will be required in excavations that extend below the elevations indicated as “Auger Refusal” in
our boring logs.
Rock materials will normally require blasting for removal in all types of excavations. Any blasting
in foundation excavations must be done carefully to prevent damage to the bearing materials
and nearby buildings or roadways/utilities. The gradation of the material removed by ripping or
blasting will likely be erratic.
As noted in the Geology section of this report, the weathering process in the Piedmont can be
erratic and significant variations of the depths of the more dense materials can occur in relatively
short distances. In some cases, isolated boulders or thin rock seams may be present in the soil
matrix. We have generally found that material that our soil drilling augers can penetrate can
also be excavated with a large backhoe or ripped with a dozer mounted ripper. Weathered rock
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 9 July 12, 2016
or rock that cannot be penetrated by the mechanical auger will normally require blasting to
loosen it for removal.
5.9. Cut and Fill Slopes
We recommend that permanent cut slopes with less than 10 feet crest height through
undisturbed residual soils be constructed at 2:1 (horizontal: vertical) or flatter. Permanent fill
slopes may be constructed using engineered fill at a slope of 2.5:1 or flatter. However, a slope
of 3:1 (or flatter) may be desirable to permit establishment of vegetation, safe mowing, and
maintenance. The surface of cut and fill slopes should be adequately compacted. Permanent
slopes should be protected using vegetation or other means to prevent erosion.
A slope stability analysis should be performed on cut and fill slopes exceeding 10 feet in height
to determine a slope inclination resulting in a factor of safety greater than 1.4. Upon finalization
of site civil drawings, ECS should be contacted to perform slope stability analysis and determine
if further exploration is necessary.
The outside face of building foundations and the edges of pavements placed near slopes should
be located an appropriate distance from the slope. Buildings or pavements placed at the top of
fill slopes should be placed a distance equal to at least 1/3 of the height of the slope behind the
crest of the slope. Buildings or pavements near the bottom of a slope should be located at least
½ of the height of the slope from the toe of the slope. Slopes with structures located closer than
these limits or slopes taller than the height limits indicated should be specifically evaluated by
the geotechnical engineer and may require approval from the building code official.
Temporary slopes in confined or open excavations should perform satisfactorily at inclinations of
2H:1V. Excavations should comply with the requirements of OSHA 29CFR, Part 1926, Subpart P,
"Excavations" and its appendices, as well as other applicable codes. This document states that
the contractor is solely responsible for the design and construction of stable, temporary
excavations. The excavations should not only be in accordance with current OSHA excavation
and trench safety standards but also with applicable Local, State and Federal regulations. The
contractor should shore, slope or bench the excavation sides when appropriate. Site safety is
the sole responsibility of the contractor, who shall also be responsible for the means, methods and
sequencing of construction operations. Appropriately sized ditches should run above and parallel
to the crest of all permanent slopes to divert surface runoff away from the slope face. To aid in
obtaining proper compaction on the slope face, the fill slopes should be overbuilt with properly
compacted structural fill and then excavated back to the proposed grades.
6. CONSTRUCTION CONSIDERATIONS
6.1. Site Preparation
Prior to construction, the proposed construction area should be stripped of all topsoil, organic
material, CH soils as previously discussed, and other soft or unsuitable material. Upon
completion of these razing and stripping operations, the exposed subgrade in areas to receive
fill should be proofrolled with a loaded dump truck or similar pneumatic-tired vehicle having a
loaded weight of approximately 25 tons. After excavation, the exposed subgrades in cut areas
should be similarly proofrolled.
Proofrolling operations should be performed under the observation of a geotechnical engineer or
his authorized representative. The proofrolling should consist of two (2) complete passes of the
exposed areas, with each pass being in a direction perpendicular to the preceding one. Any
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 10 July 12, 2016
areas which deflect, rut or pump during the proofrolling, and fail to be remedied with successive
passes, should be undercut to suitable soils and backfilled with compacted fill.
The ability to dry wet soils, and therefore the ability to use them for fill, will likely be enhanced if
earthwork is performed during summer or early fall. If earthwork is performed during winter or
after appreciable rainfall then subgrades may be unstable due to wet soil conditions, which could
increase the amount of undercutting required. Drying of wet soils, if encountered, may be
accomplished by spreading and disking or by other mechanical or chemical means.
6.2. Fill Material and Placement
The project fill should be soil that has less than five percent organic content and a liquid limit and
plasticity index less than 50 and 30, respectively. Soils with Unified Soil Classification System
group symbols of SP, SW, SM, SC, and ML are generally suitable for use as project fill. Soils
with USCS group symbol of CL that meet the restrictions for liquid limit and plasticity index are
also suitable for use as project fill. Soils with USCS group symbol of MH or CH (high elasticity
or plasticity soil) or corrosive soils are generally not suitable for use as project fill.
The fill should exhibit a maximum dry density of at least 90 pounds per cubic foot, as determined
by a standard Proctor compaction test (ASTM D 698). We recommend that moisture control
limits of -3 to +2 percent of the optimum moisture content be used for placement of project fill
with the added requirement that fill soils placed wet of optimum remain stable under heavy
pneumatic-tired construction traffic. During site grading, some moisture modification (drying
and/or wetting) of the onsite soils will likely be required.
Project fill should be compacted to at least 95 percent of its standard Proctor maximum dry
density except within 24 inches of finished soil subgrade elevation beneath slab-on-grade and
pavements. Within the top 24 inches of finished soil subgrade elevation beneath slab on grade
and pavements, the approved project fill should be compacted to at least 100 percent of its
standard Proctor maximum dry density. Aggregate base course (ABC) stone should be
compacted to 95 percent of modified Proctor maximum dry density. However, for isolated
excavations around footing locations or within utility excavations, a hand tamper will likely be
required. ECS recommends that field density tests be performed on the fill as it is being placed,
at a frequency determined by an experienced geotechnical engineer, to verify that proper
compaction is achieved.
The maximum loose lift thickness depends upon the type of compaction equipment used. The
table below provides maximum loose lifts that may be placed based on compaction equipment.
LIFT THICKNESS RECOMMENDATIONS
Equipment Maximum Loose Lift
Thickness, in.
Large, Self-Propelled Equipment (CAT 815, etc.) 8
Small, Self-Propelled or Remote Controlled (Rammax, etc.) 6
Hand Operated (Plate Tamps, Jumping Jacks, Wacker-
Packers) 4
ECS recommends that fill operations be observed and tested by an engineering technician to
determine if compaction requirements are being met. The testing agency should perform a
sufficient number of tests to confirm that compaction is being achieved. For mass grading
operations we recommend a minimum of one density test per 2,500 SF per lift of fill placed or
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 11 July 12, 2016
per 1 foot of fill thickness, whichever results in more tests. When dry, the majority of the site soil
should provide adequate subgrade support for fill placement and construction operations. When
wet, the soil may degrade quickly with disturbance from construction traffic. Good site drainage
should be maintained during earthwork operations to prevent ponding water on exposed
subgrades.
We recommend at least one test per 1 foot thickness of fill for every 100 linear ft of utility trench
backfill. Where fill will be placed on existing slopes, we recommend that benches be cut in the
existing slope to accept the new fill. Fill slopes should be overbuilt and then cut back to expose
compacted material on the slope face. While compacting adjacent to below-grade walls, heavy
construction equipment should maintain a horizontal distance of 1(H):1(V). If this minimum
distance cannot be maintained, the compaction equipment should run perpendicular, not parallel
to, the long axis of the wall.
6.3. Foundation Construction & Testing
Foundation excavations should be tested to confirm adequate bearing prior to installation of
reinforcing steel or placement of concrete. Unsuitable soils should be undercut to firm soils and the
undercut excavations should be backfilled with compacted controlled fill. Exposure to the
environment may weaken the soils at the footing bearing level if the foundation excavations
remain open for too long a time; therefore, foundation concrete should be placed the same day
that foundations are excavated. If the bearing soils are softened by surface water intrusion or
exposure, the softened soils must be removed from the foundation excavation bottom
immediately prior to placement of concrete. If the excavation must remain open overnight, or if
rainfall becomes imminent while the bearing soils are exposed, a 1- to 3-inch thick "mud mat" of
"lean" concrete may be placed on the bearing surface to protect the bearing soils. The mud mat
should not be placed until the bearing soils have been tested for adequate bearing capacity.
Foundations undercut should be backfilled with engineered fill. If lean concrete is placed within
the undercut zone, the foundation footprint does not require oversizing. However, if soil or ABC
stone is used in lieu of lean concrete, the foundation footprint should be oversized on a 1V:1H
scale.
We recommend testing shallow foundations to confirm the presence of foundation materials
similar to those assumed in the design. We recommend the testing consist of hand auger
borings with Dynamic Cone Penetrometer (DCP) testing performed by an engineer or
engineering technician.
7. GENERAL COMMENTS
The borings performed at this site represent the subsurface conditions at the location of the
borings only. Due to the prevailing geology, changes in the subsurface conditions can occur
over relatively short distances that have not been disclosed by the results of the borings
performed. Consequently, there may be undisclosed subsurface conditions that require special
treatment or additional preparation once these conditions are revealed during construction.
Our evaluation of foundation support conditions has been based on our understanding of the site
and project information and the data obtained in our exploration. The general subsurface
conditions utilized in our foundation evaluation have been based on interpolation of subsurface
data between and away from the test holes. If the project information is incorrect or if the
structure locations (horizontal or vertical) and/or dimensions are changed, please contact us so
that our recommendations can be reviewed. The discovery of any site or subsurface conditions
during construction which deviate from the data outlined in this exploration should be reported to
Report of Subsurface Exploration Mr. Scott Shelton
Summit Corporate Center RowanWORKS
Salisbury, North Carolina ECS Project No. 08-11761-A
Page 12 July 12, 2016
us for our evaluation. The assessment of site environmental conditions for the presence of
pollutants in the soil, rock, and groundwater of the site was beyond the scope of this exploration.
The recommendations outlined herein should not be construed to address moisture or water
intrusion effects after construction is completed. Proper design of landscaping, surface and
subsurface water control measures are required to properly address these issues. In addition,
proper operation and maintenance of building systems is required to minimize the effects of
moisture or water intrusion. The design, construction, operation, and maintenance of
waterproofing and dampproofing systems are beyond the scope of services for this project.
Site Vicinity Map
Boring Location Diagram
Borelogs
ASFE Documents
APPENDIX
0
5
10
15
20
25
30
860
855
850
845
840
835
830
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
18
18
18
18
14
16
18
16
18
14
Topsoil Depth [3"]
(CL) RESIDUUM - SANDY CLAY, Tan, Moist,
Medium Stiff
(ML) SANDY SILT, Trace Sand, Gray Tan to
Orange Tan, Moist, Very Stiff to Stiff
(ML) SANDY SILT, Trace Sand, Gray Orange
Tan, Moist, Medium Stiff to Stiff
END OF BORING @ 20.0'
2
3
4
5
7
10
5
5
8
2
2
3
3
4
6
2
4
7
7
17
13
5
10
11
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-1
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 17.7'
WL(SHW)WL(ACR) 17.0 BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT860
1 OF 1
0
5
10
15
20
25
30
845
840
835
830
825
820
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
18
10
18
8
12
18
18
5
6
4
Topsoil Depth [3"]
(SM) RESIDUUM - SILTY FINE TO MEDIUM
SAND, Brown, Moist, Medium Dense
(ML) SANDY SILT, Red Gray, Moist, Very Hard
(SM) SILTY FINE SAND, Gray Orange, Moist,
Very Dense
(SM PWR) PARTIALLY WEATHERED ROCK
SAMPLED AS SILTY MEDIUM TO COARSE
SAND, Gray
(SM) RESIDUUM SILTY MEDIUM TO COARSE
SAND, Orange Gray, Moist, Very Dense
(SM PWR) PARTIALLY WEATHERED ROCK
SAMPLED AS SILTY MEDIUM TO COARSE
SAND, Gray Orange
AUGER REFUSAL @ 19.0'
5
5
6
11
26
39
33
44
50
50/5
50/5
34
42
50
50/4
50/4
11
65
94
100+
92
100+
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-2
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 15.8'
WL(SHW)WL(ACR) GNE BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT846
1 OF 1
0
5
10
15
20
25
30
845
840
835
830
825
820
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
18
16
15
14
8
18
18
9
15
10
Topsoil Depth [3.5"]
(SM) RESIDUUM - SILTY FINE TO MEDIUM
SAND, Brown, Moist, Medium Dense
(CH) PLASTIC CLAY, Gray Orange, Moist, Stiff
(CL) SANDY CLAY, Orange Gray, Moist, Very
Stiff
(SM PWR) PARTIALLY WEATHERED ROCK
SAMPLED AS SILTY MEDIUM TO COARSE
SAND, Gray Orange to Brown Orange
END OF BORING @ 20.0'
5
6
8
4
6
8
6
9
13
36
50/5
50/5
36
44
50/3
28
50/4
50/4
14
14
22
100+
100+
100+
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-3
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 16.9'
WL(SHW)WL(ACR) GNE BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT847
1 OF 1
0
5
10
15
20
25
30
865
860
855
850
845
840
835
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
18
18
18
18
16
18
16
8
16
18
Topsoil Depth [2.5"]
(SM) RESIDUUM - SILTY FINE SAND, Brown,
Moist, Medium Dense
(CL) SANDY CLAY, Brown Gray, Moist, Very
Stiff
(ML) SANDY SILT, Gray Brown, Moist, Very
Hard to Hard
(SM) SILTY FINE SAND, Brown White, Moist,
Medium Dense
END OF BORING @ 20.0'
5
8
4
4
10
17
16
26
38
12
21
20
8
11
15
8
10
13
12
27
64
41
26
23
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-4
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 16.9'
WL(SHW)WL(ACR) GNE BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT865
1 OF 1
0
5
10
15
20
25
30
870
865
860
855
850
845
840
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
18
18
18
18
10
14
10
18
16
18
Topsoil Depth [3"]
(CL) RESIDUUM - SANDY CLAY, Brown Red,
Moist, Very Stiff to Stiff
(ML) SANDY SILT, Brown Gray, Moist, Very
Stiff
(SM) SILTY FINE SAND, Brown Orange, Moist,
Medium Dense
END OF BORING @ 20.0'
6
9
11
4
6
8
6
10
11
4
6
10
8
11
13
5
12
17
20
14
21
16
24
29
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-5
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 16.5'
WL(SHW)WL(ACR) GNE BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT870
1 OF 1
0
5
10
15
20
25
30
800
795
790
785
780
775
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
18
18
18
18
16
18
16
18
18
18
Topsoil Depth [2.5"]
(CL) RESIDUUM - SANDY CLAY, Brown Red,
Moist, Very Stiff
(ML) SANDY SILT, Gray Red to Tan Gray,
Moist, Hard to Very Stiff
(ML) SANDY SILT, Tan Orange Gray, Moist,
Medium Stiff to Soft
(ML) SANDY SILT, Orange Gray, Moist, Stiff
END OF BORING @ 20.0'
8
9
13
10
15
16
6
8
11
3
3
5
2
2
2
2
4
5
22
31
19
8
4
9
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-6
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 17.1'
WL(SHW)WL(ACR) GNE BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT803
1 OF 1
0
5
10
15
20
25
30
855
850
845
840
835
830
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
18
18
18
18
12
14
10
16
18
14
Topsoil Depth [3.5"]
(CL) RESIDUUM - SANDY CLAY, Gray Brown,
Moist, Soft
(CL) SANDY CLAY, Orange Brown, Moist, Stiff
to Very Stiff
(ML) SANDY SILT, Gray Orange Tan, Moist,
Stiff
END OF BORING @ 20.0'
1
2
2
5
6
9
7
11
15
3
5
7
5
5
8
4
5
5
4
15
26
12
13
10
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-7
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 17.5'
WL(SHW)WL(ACR) GNE BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT859
1 OF 1
0
5
10
15
20
25
30
855
850
845
840
835
830
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
18
18
18
18
6
14
18
18
18
18
Topsoil Depth [2"]
(SM) RESIDUUM - SILTY FINE SAND, Brown,
Moist, Medium Dense
(SM) SILTY FINE SAND, Brown, Moist, Very
Dense
(SM) SILTY FINE SAND, Brown, Moist, Medium
Dense
(ML) SANDY SILT, Brown, Moist, Stiff
END OF BORING @ 20.0'
5
5
7
17
23
29
14
20
31
7
9
14
4
5
8
3
5
7
12
52
51
23
13
12
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-8
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 17.6'
WL(SHW)WL(ACR) GNE BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT859
1 OF 1
0
5
10
15
20
25
30
855
850
845
840
835
830
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
18
18
18
18
2
14
10
18
10
16
Topsoil Depth [2.5"]
(SM) RESIDUUM - SILTY FINE SAND, Brown,
Moist, Medium Dense
(ML) SANDY SILT, Brown, Moist, Very Stiff
(SM) SILTY FINE SAND, Brown, Moist, Very
Dense
(ML) SANDY SILT, Tan, Moist, Stiff
(SM) SILTY MEDIUM TO COARSE SAND, Tan,
Moist, Medium Dense
(ML) SANDY SILT, Orange Brown, Moist, Very
Stiff
END OF BORING @ 20.0'
6
11
12
6
10
14
16
27
37
4
5
9
11
14
14
5
8
11
23
24
64
14
28
19
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-9
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 17.2'
WL(SHW)WL(ACR) GNE BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT858
1 OF 1
0
5
10
15
20
25
30
860
855
850
845
840
835
S-1
S-2
S-3
S-4
S-5
S-6
SS
SS
SS
SS
SS
SS
18
18
17
18
18
18
2
18
17
18
18
18
Topsoil Depth [2"]
(NO RECOVERY), Cuttings - (SC) CLAYEY
FINE SAND, Brown, Moist, Medium Dense
(SM) RESIDUUM - SILTY FINE SAND, Tan,
Moist, Very Dense
(ML PWR) PARTIALLY WEATHERED ROCK
SAMPLED AS SANDY SILT, Tan
(ML) RESIDUUM SANDY SILT, Orange Brown,
Moist, Very Stiff
(SM) SILTY FINE SAND, Brown White Orange,
Moist, Medium Dense to Dense
END OF BORING @ 20.0'
8
8
8
10
20
36
20
32
50/5
7
11
15
6
8
11
7
13
19
16
56
100+
26
19
32
CLIENT
RowanWORKS
JOB #
08:11761-A
BORING #
B-10
SHEET
PROJECT NAME
Summit Corporate Center - GEO
ARCHITECT-ENGINEER
SITE LOCATION
Julian Road, Salisbury, Rowan County, NC
NORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL GNE WS WD BORING STARTED 06/29/16 CAVE IN DEPTH @ 15.1'
WL(SHW)WL(ACR) GNE BORING COMPLETED 06/29/16 HAMMER TYPE Manual
WL RIG ATV FOREMAN Cody DRILLING METHOD ATV on TracksDRILLING METHOD ATV on TracksDEPTH (FT)SAMPLE NO.SAMPLE TYPESAMPLE DIST. (IN)RECOVERY (IN)SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WATER LEVELSELEVATION (FT)BLOWS/6"10 20 30 40 50+
20%40%60%80%100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTIC
LIMIT %
WATER
CONTENT %
LIQUID
LIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD%REC.%
STANDARD PENETRATION
BLOWS/FT863
1 OF 1
Major Divisions Group
Symbols Typical Names Laboratory Classification Criteria
GW Well graded gravels, gravel-
sand mixtures, little or no fines
Cu=D60/D10 greater than 4
Cc= (D30)2/(D10 x D60) between 1 and 3 Clean Gravels (Little or no fines) GP Poorly graded gravels, gravel-
sand mixtures, little or no fines Not meeting all gradation requirements for GW
d
GMa
u
Silty Gravels, gravel-sand-silt
mixtures
Atterberg limits
below “A” line or P.I.
less than 4 Gravels (More than half of coarse fraction is larger than No. 4 sieves size) Gravels with fines GC Clayey Gravels, gravel-sand-
clay mixtures
Atterberg limits
above “A” line with
P.I. greater than 7
Above “A” line with P.I.
between 4 and 7 are
borderline cases requiring
use of dual symbols
SW Well-graded sands, gravelly
sands, little or no fines
Cu=D60/D10 greater than 6
Cc= (D30)2/(D10 x D60) between 1 and 3 Clean Sands (Little or no fines) SP Poorly graded sands, gravelly
sands, little or no fines Not meeting all gradation requirements for SW
d SMa
u
Silty sands, sand-silt mixtures
Atterberg limits
below “A” line or P.I.
less than 4 Coarse-Grained Soils (More than half of the material is larger than No. 200 sieve size) Sands (More than half of coarse fraction is smaller than No. 4 sieve size) Sands with fines SC Clayey sands, sand-clay
mixtures Determine percentages of sand and gravel from grain size curve Depending on the percentage of the fines (fraction smaller than No. 200 sieve size), Coarse grained soils are classified as follows: Less than 5% GW, GP, SW, SP More than 12% GM, GC, SM, SC 5 to 12% Borderline cases requiring dual symbolsb Atterberg limits
above “A” line with
P.I. greater than 7
Limits plotting in hatched
zone with P.I. between 4
and 7 are borderline cases
requiring use of dual
symbols
ML
Inorganic silts and very fine sands,
rock flour, silty or clayey fine
sands, or clayey silts with slight
plasticity
CL
Inorganic clays of low to medium
plasticity, gravelly clays, sandy
clays, silty clays, lean clays Silts and Clays (Liquid Limit less than 50) OL Organic silts and organic silty
clays of low plasticity
MH
Inorganic silts, micaceous or
diatomaceous fine sandy or silty
soils, elastic silts
CH Inorganic clays of high plasticity,
fat clays Silts and Clays (Liquid Limit greater than 50) OH Organic clays of medium to high
plasticity, organic silts Fine-Grained Soils (More than half of material is smaller than No. 200 sieve) Highly Organic Soils Pt Peat and other highly organic soils
Reference: Winterkorn & Fang, 1975 (ASTM D-2487)
aDivision of GM and SM groups into subdivision of d and u are for road and airfields only. Subdivision is based on Atterberg limits; suffix d used
when L.L. is 28 or less and the P.I. is 6 or less; the suffix u is used when L.L. is greater that 28.
bBorderline classifications, used for soils possessing characteristics of two groups, are designated by combinations of group symbols. For example:
GW-GC, well-graded gravel-sand mixture with clay binder.
UNIFIED SOIL
CLASSIFICATION SYSTEM
1812 CENTER PARK DRIVE
SUITE D
CHARLOTTE, NC 28217
704/525-5152
FAX/704-357-0023
REFERENCE NOTES FOR BORING LOGS
I. Drilling Sampling Symbols
SS Split Spoon Sampler ST Shelby Tube Sampler
RC Rock Core, NX, BX, AX PM Pressuremeter
DC Dutch Cone Penetrometer RD Rock Bit Drilling
BS Bulk Sample of Cuttings PA Power Auger (no sample)
HSA Hollow Stem Auger WS Wash sample
REC Rock Sample Recovery % RQD Rock Quality Designation %
II. Correlation of Penetration Resistances to Soil Properties
Standard Penetration (blows/ft) refers to the blows per foot of a 140 lb. hammer falling 30
inches on a 2-inch OD split-spoon sampler, as specified in ASTM D 1586. The blow count is
commonly referred to as the N-value.
A. Non-Cohesive Soils (Silt, Sand, Gravel and Combinations)
Density Relative Properties
Under 4 blows/ft Very Loose Adjective Form 12% to 49%
5 to 10 blows/ft Loose With 5% to 12%
11 to 30 blows/ft Medium Dense
31 to 50 blows/ft Dense
Over 51 blows/ft Very Dense
Particle Size Identification
Boulders 8 inches or larger
Cobbles 3 to 8 inches
Gravel Coarse 1 to 3 inches
Medium ½ to 1 inch
Fine ¼ to ½ inch
Sand Coarse 2.00 mm to ¼ inch (dia. of lead pencil)
Medium 0.42 to 2.00 mm (dia. of broom straw)
Fine 0.074 to 0.42 mm (dia. of human hair)
Silt and Clay 0.0 to 0.074 mm (particles cannot be seen)
B. Cohesive Soils (Clay, Silt, and Combinations)
Blows/ft Consistency
Unconfined
Comp. Strength
Qp (tsf)
Degree of
Plasticity
Plasticity
Index
Under 2 Very Soft Under 0.25 None to slight 0 – 4
3 to 4 Soft 0.25-0.49 Slight 5 – 7
5 to 8 Medium Stiff 0.50-0.99 Medium 8 – 22
9 to 15 Stiff 1.00-1.99 High to Very High Over 22
16 to 30 Very Stiff 2.00-3.00
31 to 50 Hard 4.00–8.00
Over 51 Very Hard Over 8.00
III. Water Level Measurement Symbols
WL Water Level BCR Before Casing Removal DCI Dry Cave-In
WS While Sampling ACR After Casing Removal WCI Wet Cave-In
WD While Drilling Est. Groundwater Level Est. Seasonal High GWT
The water levels are those levels actually measured in the borehole at the times indicated by the
symbol. The measurements are relatively reliable when augering, without adding fluids, in a granular
soil. In clay and plastic silts, the accurate determination of water levels may require several days for
the water level to stabilize. In such cases, additional methods of measurement are generally applied.
Important Information About Your
Geotechnical Engineering Report
Subsurface problems are a principal cause of construction delays, cost overruns, claims, and disputes
The following information is provided to help you manage your risks.
Geotechnical Services Are Performed for
Specifi c Purposes, Persons, and Projects
Geotechnical engineers structure their services to meet the specifi c needs of
their clients. A geotechnical engineering study conducted for a civil engineer
may not fulfi ll the needs of a construction contractor or even another civil
engineer. Because each geotechnical engineering study is unique, each geo-
technical engineering report is unique, prepared solely for the client. No one
except you should rely on your geotechnical engineering report without fi rst
conferring with the geotechnical engineer who prepared it. And no one - not
even you - should apply the report for any purpose or project except the one
originally contemplated.
Read the Full Report
Serious problems have occurred because those relying on a geotechnical
engineering report did not read it all. Do not rely on an executive summary.
Do not read selected elements only.
A Geotechnical Engineering Report Is Based on
A Unique Set of Project-Specifi c Factors
Geotechnical engineers consider a number of unique, project-specifi c factors
when establishing the scope of a study. Typical factors include: the client’s
goals, objectives, and risk management preferences; the general nature of the
structure involved, its size, and confi guration; the location of the structure
on the site; and other planned or existing site improvements, such as access
roads, parking lots, and underground utilities. Unless the geotechnical engi-
neer who conducted the study specifi cally indicates otherwise, do not rely on
a geotechnical engineering report that was:
• not prepared for you,
• not prepared for your project,
• not prepared for the specifi c site explored, or
• completed before important project changes were made.
Typical changes that can erode the reliability of an existing geotechnical
engineering report include those that affect:
• the function of the proposed structure, as when it’s changed from a
parking garage to an offi ce building, or from alight industrial plant
to a refrigerated warehouse,
• elevation, confi guration, location, orientation, or weight of the
proposed structure,
• composition of the design team, or
• project ownership.
As a general rule, always inform your geotechnical engineer of project
changes - even minor ones - and request an assessment of their impact.
Geotechnical engineers cannot accept responsibility or liability for problems
that occur because their reports do not consider developments of which they
were not informed.
Subsurface Conditions Can Change
A geotechnical engineering report is based on conditions that existed at the
time the study was performed. Do not rely on a geotechnical engineering
report whose adequacy may have been affected by: the passage of time; by
man-made events, such as construction on or adjacent to the site; or by natu-
ral events, such as fl oods, earthquakes, or groundwater fl uctuations. Always
contact the geotechnical engineer before applying the report to determine if it
is still reliable. A minor amount of additional testing or analysis could prevent
major problems.
Most Geotechnical Findings Are Professional
Opinions
Site exploration identifi es subsurface conditions only at those points where
subsurface tests are conducted or samples are taken. Geotechnical engineers
review fi eld and laboratory data and then apply their professional judgment
to render an opinion about subsurface conditions throughout the site. Actual
subsurface conditions may differ-sometimes signifi cantly from those indi-
cated in your report. Retaining the geotechnical engineer who developed your
report to provide construction observation is the most effective method of
managing the risks associated with unanticipated conditions.
A Report’s Recommendations Are Not Final
Do not overrely on the construction recommendations included in your re-
port. Those recommendations are not fi nal, because geotechnical engineers
develop them principally from judgment and opinion. Geotechnical engineers
can fi nalize their recommendations only by observing actual
subsurface conditions revealed during construction. The geotechnical engi-
neer who developed your report cannot assume responsibility or liability for
the report’s recommendations if that engineer does not perform construction
observation.
A Geotechnical Engineering Report Is Subject to
Misinterpretation
Other design team members’ misinterpretation of geotechnical engineer-
ing reports has resulted in costly problems. Lower that risk by having your
geotechnical engineer confer with appropriate members of the design team
after submitting the report. Also retain your geotechnical engineer to review
pertinent elements of the design team’s plans and specifi cations. Contractors
can also misinterpret a geotechnical engineering report. Reduce that risk by
having your geotechnical engineer participate in prebid and preconstruction
conferences, and by providing construction observation.
Do Not Redraw the Engineer’s Logs
Geotechnical engineers prepare fi nal boring and testing logs based upon
their interpretation of fi eld logs and laboratory data. To prevent errors or
omissions, the logs included in a geotechnical engineering report should
never be redrawn for inclusion in architectural or other design drawings.
Only photographic or electronic reproduction is acceptable, but recognize
that separating logs from the report can elevate risk.
Give Contractors a Complete Report and
Guidance
Some owners and design professionals mistakenly believe they can make
contractors liable for unanticipated subsurface conditions by limiting what
they provide for bid preparation. To help prevent costly problems, give con-
tractors the complete geotechnical engineering report, but preface it with a
clearly written letter of transmittal. In that letter, advise contractors that the
report was not prepared for purposes of bid development and that the report’s
accuracy is limited; encourage them to confer with the geotechnical engineer
who prepared the report (a modest fee may be required) and/or to conduct ad-
ditional study to obtain the specifi c types of information they need or prefer.
A prebid conference can also be valuable. Be sure contractors have suffi cient
time to perform additional study. Only then might you be in a position to give
contractors the best information available to you, while requiring them to at
least share some of the fi nancial responsibilities stemming from unantici-
pated conditions.
Read Responsibility Provisions Closely
Some clients, design professionals, and contractors do not recognize that
geotechnical engineering is far less exact than other engineering disciplines.
This lack of understanding has created unrealistic expectations that have led
to disappointments, claims, and disputes. To help reduce the risk of such
outcomes, geotechnical engineers commonly include a variety of explanatory
provisions in their reports. Sometimes labeled “limitations” many of these
provisions indicate where geotechnical engineers’ responsibilities begin
and end, to help others recognize their own responsibilities and risks. Read
these provisions closely. Ask questions. Your geotechnical engineer should
respond fully and frankly.
Geoenvironmental Concerns Are Not Covered
The equipment, techniques, and personnel used to perform a geoenviron-
mental study differ signifi cantly from those used to perform a geotechnical
study. For that reason, a geotechnical engineering report does not usually re-
late any geoenvironmental fi ndings, conclusions, or recommendations; e.g.,
about the likelihood of encountering underground storage tanks or regulated
contaminants. Unanticipated environmental problems have led to numerous
project failures. If you have not yet obtained your own geoenvironmental in-
formation, ask your geotechnical consultant for risk management guidance.
Do not rely on an environmental report prepared for someone else.
Obtain Professional Assistance To Deal with Mold
Diverse strategies can be applied during building design, construction, op-
eration, and maintenance to prevent signifi cant amounts of mold from grow-
ing on indoor surfaces. To be effective, all such strategies should be devised
for the express purpose of mold prevention, integrated into a comprehensive
plan, and executed with diligent oversight by a professional mold prevention
consultant. Because just a small amount of water or moisture can lead to
the development of severe mold infestations, a number of mold prevention
strategies focus on keeping building surfaces dry. While groundwater, wa-
ter infi ltration, and similar issues may have been addressed as part of the
geotechnical engineering study whose fi ndings are conveyed in-this report,
the geotechnical engineer in charge of this project is not a mold prevention
consultant; none of the services performed in connection with
the geotechnical engineer’s study were designed or conducted
for the purpose of mold prevention. Proper implementation of
the recommendations conveyed in this report will not of itself
be suffi cient to prevent mold from growing in or on the struc-
ture involved.
Rely on Your ASFE-Member Geotechnical
Engineer For Additional Assistance
Membership in ASFE/The Best People on Earth exposes geotechnical engi-
neers to a wide array of risk management techniques that can be of genuine
benefi t for everyone involved with a construction project. Confer with your
ASFE-member geotechnical engineer for more information.
8811 Colesville Road/Suite G106, Silver Spring, MD 20910
Telephone:’ 301/565-2733 Facsimile: 301/589-2017
e-mail: info@asfe.org www.asfe.org
Copyright 2004 by ASFE, Inc. Duplication, reproduction, or copying of this document, in whole or in part, by any means whatsoever, is strictly prohibited, except with ASFE’s specifi c
written permission. Excerpting, quoting, or otherwise extracting wording from this document is permitted only with the express written permission of ASFE, and only for purposes
of scholarly research or book review. Only members of ASFE may use this document as a complement to or as an element of a geotechnical engineering report. Any other fi rm,
individual, or other entity that so uses this document without being anASFE member could be committing negligent or intentional (fraudulent) misrepresentation.
IIGER06045.0M
The Best People on Earth