Loading...
HomeMy WebLinkAbout20140957 Ver 2_ACP_notes_7_20170511Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information U.S. Army Corps of Engineers — Wilmington District cumulative adverse effects on the aquatic environment. NEPA requires consideration of •' all environmental impacts, not only those to aquatic resources, so there may well be situations where aquatic impacts are minimal even though environmental impacts more generally are not. These other environmental impacts would be addressed by the lead agency preparing the environmental impact statement. " [77 FR, Vol 77, No, 34] Atlantic will restore the wetlands to preconstruction elevations and will re -vegetate emergent, scrub -shrub and forested wetlands within the 75 -foot construction corridor. In addition, Atlantic has placed the following additional protective language into the landowner easement agreements on parcels which contain waters of the US that are being negotiated for the pipeline project. This language has been reviewed and approved by Wilmington District. "IfLocal, State or Federally -regulated waters or wetlands (collectively and individually "Regulated Waters or Wetlands) within the Permanent Easement or Temporary Easement are disturbed by Grantee, Grantor acknowledges that Grantee may be required by law to restore and/or re -vegetate any such disturbed Regulated Waters or Wetlands. Additionally, Grantor agrees to: (a) cooperate with Grantee to ensure any such restored or re -vegetated Regulated Waters or Wetlands are maintained as required by applicable laws,; (b) notify Grantee in advance of any proposed plans to disturb any Regulated Waters or Wetlands within the Permanent Easement or Temporary Easement; and (c) notify Grantee of Grantor's efforts to obtain any required permits, permit modifications andlor approvals, prior to conducting any proposed disturbance of Regulated Waters or Wetlands within the Permanent Easement or Temporary Easement. Grantor agrees that any permitting and/or disturbance of Regulated Waters or Wetlands by Grantor within the Permanent Easement or Temporary Easement, Is including any required mitigation and/or penalties, will be at Grantor's own risk and cost. " FERC NEPA ALTERNATIVES ANALYSIS INFORMATION For purposes of the USACE evaluation of single and complete projects, the "alternatives analysis" is to ensure that the crossing of each wetland, stream and/or other waterbody is made in a manner that avoids and minimizes impacts on the aquatic environment to the maximum extent practicable, after considering the approach to the crossing in the uplands immediately adjacent to the water of the United States. For example, to the extent practicable, crossings will be perpendicular to the aquatic feature to minimize the length of the pipeline in the particular aquatic system. As background, information on the FERC alternatives analysis follows, including discussion of the various alternatives FERC is considering. Within the sections below, the numbering of many of the referenced tables and figures has not been changed from their numbering in the FERC documentation, to maintain consistency across documents (e.g., Table 10.8.1-1, Figure 10.8.1-1, etc.).Atlantic has identified and evaluated a number of alternatives to the proposed ACP. These include a no -action alternative; alternative energy sources, including traditional and renewable sources; energy conservatior alternative; and conceptual collocation route alternatives. • Atlantic Coast Pipeline 37 Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information U.S. Army Corps of Engineers — Wilmington District TABLES North Carolina Riparian Buffer Impacts within the Ter -Pamlico and Neuse watersheds ° Area of Workspace Workspace Wetland Area of Wetland within Zone I within Zone 2 Overlap Zone 1 Overlap Zone 2 Buffer Buffer Buffer Buffer Watershed MP Unique ID (Square Feet) (Square Feet) (Square Feet) (Square Feet) Required Mitigation DKSQ_NC_ 1.10.3 010, 9,188 4,971 0 0 35,021 110.3 sjop017 211 699 0 0 1,683 113.1 sjoo007 6,681 4,225 2,090 1,256 18,226 113.7 sjoe007 262 5,590 262 5,590 0 TOTALS 655,608 459,896 362,742 203,743 1,262,826 Feature extended subsequent to agency field review, requires confirmation with NCDEQ. Note: The totals shown in this table may not. equal the sum of addends due to rounding D. IMPACT JUSTIFICATION AND MITIGATION 1. a.1 Avoidance and Minimization For purposes of the USACE evaluation of single and complete projects, the "alternatives analysis" is to ensure that the crossing of each wetland, stream and other waterbody is made in a manner that avoids and minimizes impacts on the aquatic environment to the maximum extent practicable, after considering the approach to the crossing in the uplands immediately adjacent to the water of the United States. For example, to the extent practicable, crossings will be perpendicular to the aquatic feature to minimize the length of the pipeline in the particular aquatic system. The FERC NEPA process includes the evaluation of alternative route alignments that reduce the overall impacts on the human environment of the proposed pipeline including avoiding and minimizing impacts to wetlands, streams, and other waterbodies. In addition all crossings within the Wilmington District have been designed to meet NWP 12 criteria also resulting in further avoidance and minimization of impacts. As background, information on the FERC alternatives analysis follows, including discussion of the various alternatives FERC is considering. The USACE is a cooperating agency on the FERC NEPA EIS and is working with FERC to ensure that USACE comments regarding the overall pipeline alternatives analysis are fully considered in that process. The fact that the ACP will be subject to an EIS does not preclude the use of NWP 12 for the affected waterbody crossings. As provided for in the USACE 2012 NWP Federal Register (FR) final NWPs: "One commenter requested clarification that individual permits are not automatically required for NWP 12 activities when a Corps districtparticipates as a cooperating agency for an environmental impact statement. [Response] "Even though an environmental impact statement may be prepared for a particular utility line, the National Environmental Policy Act process does not prohibit the Corps from using NWP 12 to authorize the construction, maintenance, repair, and removal of utility lines and associated facilities in waters of the United States, as long as the activity complies with all applicable terms and conditions and results in minimal individual and Atlantic Coast Pipeline 36 0 • Ll Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information U.S. Army Corps of Engineers — Wilmington District Atlantic's analysis of route alternatives and variations used a geographic informat system (GIS) to characterize crossings of environmental features and other constraints alc routes. A digital centerline for each route alternative and the corresponding segment of tl baseline was compared with a variety of datasets and map resources in the GIS. Features constraints considered in the analysis included: length, public lands crossed, roads crosses conservation easements crossed, forested lands crossed (based on the National Land Cover Database), wetlands crossed (based on the NWI), waterbodies crossed (based on the National Hydrography Dataset), and known cultural resources sites crossed, such as Civil War battlefields. E Once a baseline route was determined using desktop data, a field oriented routing team consisting of a lead construction router, civil survey staff, and an ecological specialist adjusted the route based on site-specific conditions while weighing competing constraints associated with environmental, tribal, and historical resource protection, constructability, available technology, and logistical constraints. Where practicable, adjustments to the route were made to avoid and/or minimize impacts on wetlands and waterbodies. Johnston County, North Carolina Major Route Alternative Atlantic identified and evaluated an alternative route for the AP -2 mainline at the request of the Johnston County, North Carolina Economic Development Authority in an effort to move the pipeline closer to existing industrial properties along the 1-95 corridor and U.S. Highway 701 south of the town of Four Oaks. The Johnston County Economic Development Authority would like to introduce natural gas into the industrial park. The baseline route for the AP -2 mainline in this area crosses Johnston County east of the towns of Smithfield and Four Oaks. Beginning at MP 92.9 near Smithfield, the alternative route follows an existing electric transmission line southwest of the baseline for approximately 7 miles to a point just south of Four Oaks. The route then heads to the south-southwest for approximately 14 miles, where it rejoins the baseline west of Jumping Run Swamp at MP 114.5. The baseline and Johnston County route alternative are depicted on Figure 10.8.1-14, and comparative information on each route is provided in Table 10.8.1-12. TABLE 10.8.1-12. Johnston County Major Route Alternative for the Atlantic Coast Pipeline Features Unit Baseline (Proposed) Route Johnston County Route Alternative Length (total) miles 21.5 20.7 Primary U.S. or State highways crossed number 7 7 Other State or local mads crossed number 23 22 Adjacent to existing linear corridor facilities miles 0.0 6.1 Federal lands crossed miles 0.0 0.0 State lands crossed miles 0.0 0.0 Conservation easements crossed miles 0.0 0.0 Forested land crossed miles 8.0 5.4 Wetlands crossed — forested/shrub miles 2.5 0.7 Intermittent waterbodies crossed number 33 28 Perennial waterbodies crossed number 8 8 Bentonville Battlefield (total) miles 0.1 0.2 Atlantic Coast Pipeline 46 Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information U.S. Army Corps of Engineers — Wilmington District a i e..nxrAn / nd� 0 ® Conservation Easement IWJI Wetland - Ga ` Existing Industrial Properties • �. ry p, 9 7 OMtlnS Qy AtJantic� N Baseline Atlantic Coast Pipeline R GQtiSt NJohnston County Baseline Figure 10.8.1-14 {ane N Johnston CountyAltemative Major Route Alternative Aft Johnston County / FILE M:1 fienh1U.P O"RPP Am IS%R..,r R! REP WlqumACP_HRtGJahn%Wn_P*untymx4, REVISE0:MUM15. SCAL£1:=,QW DUM BY GIS Atlantic Coast Pipeline 47 f r� r 0 ® Conservation Easement IWJI Wetland - Ga ` Existing Industrial Properties • �. ry p, 9 7 OMtlnS Qy AtJantic� N Baseline Atlantic Coast Pipeline R GQtiSt NJohnston County Baseline Figure 10.8.1-14 {ane N Johnston CountyAltemative Major Route Alternative Aft Johnston County / FILE M:1 fienh1U.P O"RPP Am IS%R..,r R! REP WlqumACP_HRtGJahn%Wn_P*untymx4, REVISE0:MUM15. SCAL£1:=,QW DUM BY GIS Atlantic Coast Pipeline 47 Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information • U.S. Army Corps of Engineers — Wilmington District environmental impacts are expected should an inadvertent release occur. Similarly, while native soils may mix with the drilling fluid as a result of the drilling process, drilling fluid is still not considered fill material and no adverse environmental impacts from these materials are expected should an inadvertent return occur. Due to the possibility of drilling fluid loss during HDD operations, Atlantic has prey --4 and will implement a HDD Plan. The plan describes measures to prevent, detect, and resp( inadvertent returns, including but not limited to, monitoring during drilling operations, the 1 of equipment and materials that must be readily available to contain and clean up drilling in l i/�I✓1 ll� containment and mitigation measures, notification requirements, and guidelines for abandol the directional drill, if necessary. The use of HDD was considered for wetland and waterbody crossings, but was determined to not be feasible in all crossing locations based on logistical, economic, tempor and engineering constraints, additional environmental impacts, and potential environmental The HDD method requires that a prefabricated segment of pipe at least the length of the bon hole be staged in line with the drill path at the exit hole, opposite the placement of the drilliny, rig. This "pullback" generally requires a false right-of-way that can deviate from the right-of- way approaching the crossing, unless the drill alignment is directly in-line with the construction right-of-way for the length of the prefabricated pipe segment. In many cases the drill path is not in-line with the construction right-of-way and additional workspace that extends well outside of the standard construction right-of-way must be cleared and graded to accommodate the • prefabrication of the pipe segment described above. The path of the drill is constrained by the flexibility of the pipe; the depth beneath the wetland and/or waterbody needed to achieve a successful installation; and the elevation of the entry and exit points. The entry and exit points should be similar in elevation to prevent a significant pressure differential that can contribute to failure of the HDD operation and by maintaining consistent pressure this helps maintain predictable flow of drilling mud and thus greater likelihood of a successful HDD. As a rule of thumb used in evaluating the feasibility of the HDD method, the 36 -inch diameter pipe requires a minimum drill path of 1,800 feet to achieve an acceptable radius of curvature that will prevent a catastrophic "crinkling" of the pipe as it conforms to the path of the drill hole. All proposed HDD crossings have been designed based on specific site constraints at the crossing and geologic conditions, therefore site-specific designs may vary from the planning guidelines. Atlantic explored use of the HDD method at the Rocky Swamp crossing, but based on geotechnical results, due to heavily weathered bedrock and overlying unconsolidated materials, the likelihood of experiencing an inadvertent release was high. Therefore, the HDD method is not proposed for the Rocky Swamp crossing. A large drill can be more expensive than traditional crossing methods and can take as long as several months to install. Traditional crossing methods of major waterbodies can typically be completed in less than 30 days for major waterbody crossings, whereas typical • minor or intermediate waterbody crossings can be completed within a day or a few days. Due to Atlantic Coast Pipeline 80 Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information U.S. Arany Corps of Engineers — Wilmington District the extended time of exposure of additional workspace associated with HDD coupled with the potential for an inadvertent return, traditional crossing methods can often reduce the environmental impact when compared with HDD. Based on these constraints and design considerations the HDD method is feasible and practicable where large, deep waterbodies are encountered and sufficient space to place the pullback and work area for drilling equipment is available. The proposed HDD crossing locations on ACP constitute those where it is feasible and the potential for a successful drill is acceptable. Once construction is complete, the pipeline will be buried below the ground surface and, therefore, will not impact water retention or floodplain storage within riparian corridors. Atlantic is routing the proposed pipelines to avoid sharp angle crossings or crossing streams where high stream energy could result in bank erosion. Atlantic will implement measures outlined in the Procedures to minimize impacts on the waterbodies crossed, including the installation of trench plugs to prevent water from flowing along the trenchline during and after construction. These measures will minimize potential impacts on surface and below ground hydrology. All waterbody crossings will be in accordance with the requirements identified in the federal or state waterbody crossing permits obtained for the ACP. During operations, the proposed pipelines will transport natural gas, which consist primarily of methane. Methane is buoyant at atmospheric temperatures and pressure, and disperses rapidly in air. The proposed pipelines will not carry liquids. Therefore, in the unlikely event of a leak, impacts on surface waters or groundwater from methane are not anticipated. Moreover, Atlantic will utilize a rigorous Integrity Management Plan to prevent leaks on the system. The impacts associate with construction are planned to occur in an expedient and efficient manner such that impacts on the waterbody its banks are temporary in nature. In addition, while there are numerous of waterbody crossings across the project in North Carolina, the crossings are distributed across many watersheds. Tables 3 and 4 in section C, Proposed Impacts Inventory, summarize the impacts on waterbodies by sub -basin (HUC 8). Based on the short duration and distant nature of the waterbody crossings, Atlantic anticipates that cumulative impacts will result in no more than minimal adverse impacts on the basin and sub -basins crossed. See Appendix K — Tables K-1 to Table K-3 for a list of General, Regional and Specific NWT 12 permit conditions and how Atlantic will comply with the conditions. 2. Compensatory Mitigation for Impacts on Waters of the U.S. or Waters of the State In order to authorize any activity under the NWP Program the USACE must determine that the authorized activity in waters of the U.S. meets the terms and conditions of the relevant NWP, in this case NWP 12, which allows no more than 0.5 acre loss at each single and complete project (crossing). Furthermore, provided the activity meets the terms and conditions of NWP 12 USACE must determine that the activity will result in no more than minimal individual or cumulative impacts on the aquatic environment after considering proposed compensatory Atlantic Coast Pipeline 81 Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information U.S. Army Corps of Engineers — Wilmington. District • mitigation. Such impacts would include the conversion impacts from one type of wetland to another. As stated in the Preamble to 33 CFR 330/NWP Rule issued on November 22, 1991 (56 FR 59118-59119) mitigation can be used to reduce impacts on the aquatic environment to the minimal level: "In response to the comments concerning whether the District Engineer (DE) should allow an activity to proceed under a relevant NWP when the mitigation reduces the adverse environmental effects to the minimal level (the "buy down" or "write down " concept), we believe it is indeed appropriate for the DE to consider mitigation in determining whether the proposed activity will result in no more than a minimal level of adverse environmental effects.' and "In summary, the net impact concept regarding the determination of minimal is consistent with NEPA, the Army/EPA Mitigation Memorandum of Agreement and the Section 404(b)(1) Guidelines as they pertain to general permits." Atlantic will provide compensatory mitigation for the conversion within the 30 foot permanently maintained right of way (15 feet either side of the pipeline centerline) reseeding with native wetland seed mix and mitigating at a 1:1 ratio for permanent conversion of palustrine forested wetlands to scrub -shrub or to emergent wetlands, and within the temporary disturbed construction right of way reseeding with native wetland seed mix to stabilize the area, along the ACP right-of-way. Permanent loss of wetlands is not proposed for anticipated to occur as a result of the ACP;:' mainline pipeline construction or associated facilities in North Carolina. However, loss of 40 waters of the U.S. will occur as a result of access road improvements. Existing access roads will be utilized as much as possible where feasible. Where access road improvements are necessary for use, impacts will be minimized to the maximum extent practicable, and, in conjunction with other impacts will not result in more than 0.5 acre loss of waters of the U.S. at any single and complete project. Permanent losses of wetlands, streams, and other waters as a result of access roads are proposed to be mitigated at a 2:1 ratio for riparian wetland type and 1.5:1 ratio for non -riparian wetland type through the purchase of commercially available mitigation credits from an agency - approved mitigation bank as a first option, and from the Department of Mitigation Services (DMS), which offers In -Lieu Fee mitigation programs, as a second option. Atlantic requested authorization from DMS to reserve 100% of the credit need for the permanent loss of wetlands and streams while submitting requests for letters of credit availability from mitigation banks servicing the HUC 8 watershed or approved service area where the loss will occur. In-kind mitigation bank credits will be purchased from mitigation banks servicing the areas (HUC 8 watershed, or approved service area) where the conversion or loss occurs. Atlantic received notification that DMS is willing to accept payment for compensatory mitigation for the total permanent loss of wetlands and streams associated with the construction and maintenance of access roads. Should mitigation banks indicate that credits are available, Atlantic will purchase all available credits before making a payment to DMS for the balance. In addition, in the event that a conversion or loss occurs in a service area where mitigation bank credits are not available, Atlantic will seek authorization to participate in an • agency approved In -Lieu Fee program and/or, Atlantic will seek authorization to purchase Atlantic Coast Pipeline 82 Nationwide Permit No. 12, Pre -Construction Notification — Supplemental Information U.S. Army Corps of Engineers — Wilmington District credits from outside the service area of the next nearest mitigation bank and/or conduct permittee responsible mitigation (PRM) under an umbrella approach. These options will be based on practicality to replace the ecological function of the temporal loss and amount of compensation required. Atlantic will coordinate with Wilmington District in such cases in order to obtain approval of either option in instances where credits are not available from an agency -approved mitigation bank. Atlantic has completed research to identify wetland mitigation banks with available credits, and will continue to contact wetland mitigation banks to identify available wetland mitigation banks as the primary source of compensatory mitigation for the ACP. As a secondary source of compensatory mitigation, Atlantic will pursue participation in the North Carolina In - Lieu Fee program and/or conduct PRM if adequate wetland mitigation bank credits are not available from an agency -approved bank. For purposes of NCDEQ for the 401 Water Quality Certification Atlantic has received a response letter from DMS outlining required mitigation for loss of wetlands, loss of linear feet of stream bed, and for riparian buffer impacts. Atlantic has attached this letter as evidence of intent to satisfy NCDEQ required mitigation. The letter is included in Appendix P. With respect to PRM, Atlantic's team is currently in the process of identifying RUC's where an umbrella PRM approach may be applicable. Based on this research, Atlantic's team has `1abegun coordinating with landowners to identify suitable sites and is in the process of negotiating with landowners in order to conduct site research and assessments. Once suitable sites are selected and upon coordination with Wilmington District, Atlantic's team will be available to coordinate and schedule site visits to review the selected sites prior to final approval of the umbrella PRM approach. Atlantic intends to complete field survey on remaining inaccessible parcels, analyze and confirm impacts, and finally purchase adequate mitigation credits and/or secure sites to support the umbrella PRM approach. Atlantic will pursue this sequence of steps to provide for compensatory mitigation prior to final issuance of the JPA. 3. Complete if Using a Mitigation bank See Section D2 above for mitigation options. Additional details will be provided in the final application regarding Atlantic's plans for mitigation bank use and availability in North Carolina. At the time of this draft application, Atlantic continues to plan for mitigation and has provided a conceptual plan in Section D2 above. 4. Complete if Making a Payment to In -lieu Fee Program See Section D2 above for mitigation options. Additional details will be provided in the final application if Atlantic plans to utilize payment to the North Carolina in -lieu fee program as a compensatory mitigation option. Atlantic Coast Pipeline 83 Cumulative Impacts Assessment for the • Atlantic Coast Pipeline and Supply Header Project The distance into the past and future that other projects could cumulatively impact the same areas as the Projects is based on whether the impacts are short term, long term, or permanent. The majority of the impacts related to the Projects will occur during the construction phase. Atlantic and DTI are proposing to begin construction in the Fall of 2016, assuming all necessary permits and regulatory approvals are obtained, and placing the proposed ACP and SHP facilities into service by the end of 2018. Where a potential for cumulative impacts was indicated, those impacts have been quantified to the extent practicable. In most cases, however, the potential impacts could only be described qualitatively (e.g., impacts from projects that are in planning stages or are contingent on economic conditions, availability of financing, or the issuance of permits). The criteria listed below define the Projects' region of influence, which is used in this cumulative impacts assessment to describe the general area for which the Projects could contribute to cumulative impacts. The region of influence varies depending on the resource being discussed. Potential impacts of the Projects on geology and soils, land uses, residential areas, visual resources, cultural resources, and traffic will be highly localized; therefore, other projects within 0.5 mile of the ACP and SHP work areas (e.g., commercial 40 developments or transportation projects) were evaluated for cumulative impa on these resources. Waterbody and wetland crossings, as well as potential impacts on groundwat �t vegetation, and wildlife by the ACP and SHP will be localized. Therefore, d analysis included cumulative impacts on these resources from other projects within the same watersheds crossed by the Projects. Ongoing operation of the ACP and SHP compressor stations will result in continuing impacts on air quality in various Air Quality Control Regions (AQCRs). Therefore, other projects with the potential to result in continuing impacts on air quality (e.g., natural gas compressor stations or industrial facil...... within the AQCRs that will also be impacted by an ACP or SHP compressor station were considered. Continuing noise impacts from the ACP or SHP compressor stations will be localized to within 0.5 mile of each compressor station. Therefore, other projects that will result in continuing impacts on noise affecting the same noise -sensitive areas (NSAs) as the ACP and SHP compressor stations were evaluated. The anticipated cumulative impacts of the Projects and other actions are discussed below. 2.0 PROJECTS AND ACTIVITIES CONSIDERED Atlantic and DTI identified past, present, or reasonably foreseeable projects from review • of topographic maps, intemet research, and by contacting County and City officials regarding 10-5 Cumulative Impacts Assessment for the Atlantic Coast Pipeline and Supply Header Project recent or planned developments and significant commercial/industrial developments within the Counties and Cities crossed or affected by the Projects. Table A-1 in Attachment A lists past, present, and reasonably foreseeable future projects that may cumulatively or additively impact resources that could be affected by construction and operation of the ACP and/or SHP. 5 As noted in the following subsections, some projects were eliminated from further consideration if it was determined that they will not meet the criteria listed above or if insufficient information is available to allow for a meaningful analysis. Descriptions of potential cumulative impacts by resource category are presented in Section 3.0. In cases where quantitative information is not available for the projects considered in this analysis (e.g., projects in the planning stages or those contingent on economic conditions, availability of financing, or the issuance of permits), the potential impacts of those projects have been considered qualitatively. Other Known Federal Energy Regulatory Commission -Jurisdictional Projects In addition to the projects listed in Table A-1, there are FERC jurisdictional natural gas projects recently completed, currently proposed, recently approved, or under consideration in the States/Commonwealths crossed by the ACP and SHP, but not the same Counties or Cities. These include the Atlantic Sunrise Project in North Carolina, Pennsylvania, and Virginia; Constitution Pipeline and Wright Interconnect Projects in Pennsylvania; East Side Expansion Project in Pennsylvania; Marcellus to Manhattan Project in Pennsylvania; Niagara Expansion Project in Pennsylvania; Northeast Expansion Project in Pennsylvania; Northern Access 2015 — West Side Expansion Project in Pennsylvania; West to East Overbeck to Leidy Project in Pennsylvania; Giles County Project in Virginia and West Virginia; Kingsport Expansion Project in Virginia; Smithfield III Expansion Project in West Virginia; Uniontown to Gas City Expansion (U2GC) Project in Pennsylvania; and West Side Expansion and Modernization Project in Pennsylvania and West Virginia. None of.these projects will occur within the same region of influence as the ACP and SHP; therefore, they are not discussed further. There are several FERC jurisdictional projects currently proposed, under consideration, being constructed, or recently completed that are located in whole or in part in the same Counties or Cities as some of the ACP and SHP facilities. These include the Mountain Valley Pipeline Project in Doddridge, Harrison, Lewis, Tyler, and Wetzel Counties, West Virginia (in pre -filing); Rover Pipeline Project in Tyler and Doddridge Counties, West Virginia (in pre -filing); Natrium to Market Project in Greene and Westmoreland Counties, Pennsylvania (completed in 2014); Texas Eastern Appalachia Market 2014 Project in Westmoreland County, Pennsylvania (construction ongoing), and Virginia Southside Expansion Project in Brunswick County, Virginia (construction ongoing). These projects are included in the cumulative impacts assessment (see Table A-1 in Attachment A). ' Because the majority of potential project impacts will occur during the construction phase, the past projects included in Table A -I primarily are recently completed projects (2014 or later). Projects completed prior to 2014 are considered part of the environmental baseline and are removed from fiuther consideration unless operational impacts would affect the same resources as the ACP and SHP. 10-6 • i Ll Cumulative Impacts Assessment for the Atlantic Coast Pipeline and Supply Header Project TABLE A-1 (cont'd) Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project ^" Closest Distance Facility/State/ Common and Direction Project Name Proponent Counties/Cities Description From Project Status Atlantic Coast Atlantic Coast Northampton, Microwave towers at Intersects at Proposed, to coincide Pipeline Pipeline, LLC Wilson, various sites along the proposed with construction of Communications Johnston, Atlantic Coast Pipeline aboveground the compressor Network ` Sampson, facility sites station Cumberland, Robeson Halifax Solar Power Duke Energy Halifax 20 -megawatt (alternating 7.4 miles In progress Project Renewables current) solar project northwest Rocky Mount— Dominion Nash Construction of electric Unknown Anticipated Fall 2014 Wilson transmission tap through Spring 2016 Transmission Line — Elm City Solar Facility Rocky Mount— Dominion Nash Construction of electric Unknown Anticipated Spring Wilson transmission tap 2016 through Transmission Line Summer 2017 —Davenport Tap Wilson—Zebulon Dominion Wilson Line rebuild Unknown In progress — Spring 230 kV Line 2014 through Summer 2015 Aurom-Cmenville Dominion Wilson Line relocation Unknown In progress — Spring 230 kilovolt (kV) 2012 through Line Relocation Summer 2015 Black Creek -Wilson Dominion Wilson Install new line switch Unknown In progress — Spring Line Switch 2012 through Summer 2015 T.R. Lemon T.R. Lamm Wilson Planned residential Intersects near Unknown Subdivision development MP 67.2 Elm City Solar Duke Energy Wilson Expansion of existing 10.2 mile In progress Facility solar facility southeast Greenville V.P. Dominion Wilson Line rebuild Unknown Anticipated — Winter Everette 230kV 2016 through Line Summer 2017 Greenville— Dominion Wilson Line relocation Intersects near In progress — Spring Zebulon 230 kV MP 62.5 2012 through Line Relocation Summer 2015 U.S. 70 Corridor North Carolina Johnston Raleigh to Morehead City Intersects near Future, no current Department of major road expansion MP 92.2 date set Transportation from U.S. Highway to -.; sc Interstate Highway I �;'�.� North Carolina Johnston Completion of Highway 's• Anticipated Department of 540 toll road . Spring 2018 to Spring Transportation 2022 140 Widening— North Carolina Johnston Road widening 20.4 miles Anticipated Southeast Raleigh Department of northwest completion 2015 to Clayton Project Transportation (although not yet in progress) Lee -Selma 115 kV Dominion Johnston Line relocation Unknown Anticipated Spring Line 2016 through Summer 2017 Erwin-Sehna 230 Dominion Johnston Line replacement 0.8 mile Anticipated Summer kV Line northwest 2015 through . 'Winter 1016 10-A-7 Cumulative Impacts Assessment for the Atlantic Coast Pipeline and Supply Header Project TABLE A-1 (cont'd) Past, Present, and Reasonably Foreseeable Furore Projects for the Atlantic Coast Pipeline and Supply Header Project ^ Closest Distance Facility/State/ Common and Direction Project Name Proponent Counties/Citi" Description From Project Status Atlantic Coast Atlantic Coast Johnston A new office building for Entirely within Proposed, to coincide Pipeline Office Pipeline, LLC pipeline operations to be the Smithfield with construction of Building' built on the same site as M&R Station the M&R station the Smithfield M&R Station Atlantic Coast Atlantic Coast Johnston Utility services for the Intersects Proposed, to coincide Pipeline Utility Pipeline, LLC Smithfield M&R Station Smithfield with constructmai of Services ` and office M&R Station the M&R Station Atlantic Coast Atlantic Coast Johnston Microwave tower at the Within the Proposed, to coincide Pipeline Pipeline, LLC Smithfield M&R Station Smithfield with construction of Communications M&R Station ACP aboveground Network' facilities Selma -Wake 230 Dominion Johnston Construction of line tap Unknown Anticipated Summer kV Line 2015 through Winter 2017 Piedmont Facility Piedmont Natural Gas Johnston, Upgrades to existing intersects at the Anticipated Winter of Modifications ` Cumberland, facilities Smithfield, 2016 Robeson Fayetteville, and Pembroke M&R Stations Chemtex Cellulosic Chemtex Sampson New bminel plant facility Unknown Anticipated Biolfuel Plant Clinton -Erwin 230 Dominion Sampson Line replacement Unknown In progress — Fall kV Line 2014 through Summer 2016 Euviva Project Enviva Sampson New wood pellet Unknown Anticipated production facilities completion in 2017 Erwin -Fayetteville Dominion Cumberland Relocate structures for Intersects near In progress—Summer 115 kV —Change North Carolina MPs 131.0 and 2013 through Spring and Relocate Department of 135.4 2015 Transportation project Fayetteville Dupont Dominion Cumberland Install new tap line Unknown In progress — Winter 115 kV Line — 2014 through Spring Cumberland Solar 2016 City Fayetteville Dupont Dominion Cumberland Install new tap line Unknown In progress — Spring 115 kV Line — 2014 through Grays Creek Tap Summer 2015 Fayetteville Dupont Dominion Cumberland Install line switches Unknown Anticipated — Winter 115 kV Line — Line 2014 through Spring Switches f ' 2016 Fayetteville Fort Dominion Cumberland Line relocation Unknown In progress — Winter Bragg 230 kV Line 2014 through Winter — Clifdale Road 2015 Fayetteville Fort Dominion Cumberland Line relocation Intersects near Anticipated — Winter Bragg 230 kV Line MP 135.1 2014 through Spring —I-295 Bypass 2016 Fayetteville Vander Dominion Cumberland Install new tap line Intersects near In progress — Summer 115 kV Line — Tap MP 144.1; runs 2014 through Spring to Vander parallel from 2016 MPs 144.6 to 145.8 Fart Bragg Dominion Cumberland Install reconductor line Unknown In progress— Winter Woodruff Street 2014 through Loop into Raeford Spring 2017 10-A-8 • • Cumulative Impacts Assessment for the Atlantic Coast Pipeline and Supply Header Project TABLE A-1 (coned) Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project'" Closest Distance Facility/State/ Common and Direction Project Name Proponent Counties/Cities Description From Project Status Richmond -Fort Dominion Cumberland Install transmission loop Unknown Anticipated - Bragg 230 kV Summer 2015 through Winter 2018 gy I -" or North Carolina Cumberland Road expansion study _ "' Anticipated "Suy Department of -; environmental impact Transportation statement date 2015 Atlantic Coast Atlantic Coast Cumberland Utility services for the Intersects Proposed, to coincide Pipeline Utility Pipeline, LLC Fayetteville M&R Station Fayetteville with construction of Services' M&R Station the M&R Station Atlantic Coast Atlantic Coast Cumberland Microwave tower at the Within the Proposed, to coincide Pipeline , Pipeline, LLC Fayetteville M&R Station Fayetteville with construction of Communications M&R Station ACP aboveground Network c facilities Piedmont Piedmont Natural Gas Cumberland, Modifications to existing Varies Anticipated Winter of Aboveground Robeson aboveground facilities 2018 Facilities Piedmont Pipeline' Piedmont Natural Gas Robeson 26 miles of 20 -inch Intersects at MP Anticipated Winter of natural gas pipeline 181.8 2018 St. Pauls Johnson Johnson Brothers Robeson New asphalt plant 2.2 miles In progress - Phase I Brothers Facility Utility and Paving southeast completed July 2014. Company I-95 Diverging North Carolina Robeson Intersection improvement 9.2 miles south- In progress - Diamond - Department of project southeast anticipated Interchange in Transportation completion Spring Lumberton 2015 Weatherspoon- Dominion Robeson Convert. to remote control Unknown in progress - Spring LOP 115 kV 2014 through Fall 2015 Weathcrspoon Plant Dominion Robeson Install tap for solar facility Unknown Anticipated - Spring -Delco Bladen 2015 through Winter Soler Farm Tap 2016 Weatherspoon Plant Dominion Robeson Replace stmctiues Unknown Anticipated -Spring - Delco Replace 2015 through Solar Tap Summer 2016 Weatherspoon Plant Dominion Robeson Install tap for solar facility Unknown Anticipated - Winter - Fayetteville Solar 2014 through Farm Tap Summer 2016 Weatherspoon Plant Dominion Robeson Install tap for solar facility Unknown In progress - Fall - Fayetteville Solar 2014 through Spring Tap 2016 Weatherspoon Plant Dominion Robeson Line replacement Unknown Anticipated - Winter - Latta Replace and 2016 through Pole Transmission Summer 2017 Weatherspoon Plant Dominion Robeson Replace existing Unknown Anticipated - Winter - LOF 115 kV structures 2016 through Spring Structure Replace 2017 Weatherspoon Plant Dominion Robeson Replace existing Unknown Anticipated- Winter -Marion 115 kV structures 2015 through Structure Replace Summer 2016 Weatherspoon- Dominion Robeson Line relocation Unknown Anticipated - Raeford 115 kV Summer 2016 Line Relocate through Winter 2018 Weatherspoon- Dominion Robeson Line replacement Unknown Anticipated - Raeford 115 kV Summer 2015 Line Replacement through Summer 2017 • T e Cumulative Impacts Assessment for the Atlantic Coast Pipeline and Supply Header Project TABLE A-1 (cont'd) Past, Present, and Reasonably Foreseeable Future Projects for the Atlantic Coast Pipeline and Supply Header Project ^ ° Closest Distance Facility/State/ Common and Direction Project Name Proponent Counties/Cities Description From Project Status Atlantic Coast Atlantic Coast Robeson Utility services for the Intersects Proposed, to coincide Pipeline Utility Pipeline, LLC Pembroke M&R Station Pembroke M&R with construction of Services' Station the M&R Station Atlantic Coast Atlantic Coast Robeson Microwave tower at the Within the Prgposed, to coincide Pipeline Pipeline, LLC Pembroke M&R Station Pembroke M&R with construction of Communications Station ACP aboveground Network' facilities SUPPLY HEADER PROJECT Pennsylvania Jeannette to Amos Pennsylvania Westmoreland Road expansion project 6.7 miles In progress — Winter K Bypass Department of northeast 2012 through Winter Transportation 2014 PA 66 Beaver Run Pennsylvania Westmoreland Road resurfacing and 5.3 miles In progress — Spring to 356 Department of widening northeast 2014 through Transportation Summer 2014 Texas Eastern Texas Eastern Westmoreland FERC jurisdictional 3.5 miles Construction in Appalachia Market Transmission, LP natural gas pipeline and northeast progress, originally 2014 Project associated facilities in anticipated to be in Pennsylvania, West service in late 2014 Virginia, Ohio, Kentucky, Tennessee, Alabama, and Mississippi; includes upgrades to Delmont Station in Westmoreland County Natrium to Market Dominion Greene, FERC -jurisdictional Shared facilities Construction Project Transmission, Inc. Westmoreland natural gas facilities in include the completed in 2014 Pennsylvania Cmyne Compressor Station in Greene County and the JB Tonkin Compressor Station in Westmoreland County Leidy South Project Dominion None" Expanded compression 96.5 miles Anticipated—May Transmission, hie. and new metering and 2016 through October regulation along 2017 Dominion Transmission, Inc.'s existing transmission pipeline Leidy Southeast Transcontinental Gas None' Construction of 227.2 miles In progress — May Expansion Project Pipe Line approximately 30 miles of through December Company, LLC pipeline looping and 2015 modification of existing pipeline facilities West Virginia Buckhannon—Glen Trans -Allegheny Harrison New 138 kV transmission 5.0 miles east Anticipated Falls 138kV Interstate Line line from West Milford completion December Transmission Company (TrAILCo), Substation to existing 2015 Project a FirstEnergy Buckhannon to Glen Falls Company 138 KV transmission line 10-A-10