Cr. Eason, Patty P
Subject: RE: [External] RE: U-2524D Turbid Discharge
After yesterday's site visit, it has been determined that all cleanup efforts are sufficient.
There does not appear to be an adverse impact to water quality due to faulty
dewatering operations. Preventative measures have been put in place to avoid
instances such as this one in the future. Additional training may prove to be beneficial.
The NPDES records were reviewed. Please ensure that all inspection dates are entered
on the sheets.
Again, thank you for your efforts with the cleanup.
Thanks,
April
-----Original Message-----
From: Bailey, David E CIV USARMY CESAW (US)
[mailto:David.E.Bailey2@usace.army.mil]
Sent: Friday, January 26, 2018 11:57 AM
To: Harper, Aaron A<aaharper@ncdot.gov>; Norton, April R
<april.norton@ncdenr.gov>; Parker, Jerry A<jparker@ncdot.gov>; Thomson, Nicole J
<njthomson2@ncdot.gov>; Ingram, Jonathan P<pingram@ncdot.gov>; Hayes, Meredith
D<mdhayes3@ncdot.gov>; Moon, Chris D<cdmoon@ncdot.gov>; mpettus@rkk.com
Cc: Eason, Patty P <peason@ncdot.gov>
Subject: [External] RE: U-2524D Turbid Discharge
CAUTION: External email. Do not click links or open attachments unless verified. Send all
suspicious email as an attachment to report.spam@nc.gov.
Thanks for the notification, pictures, and report, Aaron. The Corps appreciates your
coordination and approves of the corrected measures, pending any concerns from
NCDWR.
-Dave Bailey
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: (919) 554-4884, Ext. 30.
Fax: (919) 562-0421
Email: David.E.Bailey2@usace.army.mil
We would appreciate your feedback on how we are performing our duties. Our
automated Customer Service Survey is located at:
http://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0
Thank you for taking the time to visit this site and complete the survey.
-----Original Message-----
From: Harper, Aaron A [mailto:aaharper@ncdot.gov]
Sent: Thursday, January 25, 2018 7:44 PM
To: Bailey, David E CIV USARMY CESAW (US) <David.E.Bailey2@usace.army.mil>;
Norton, April R<april.norton@ncdenr.gov>; Parker, Jerry A<jparker@ncdot.gov>;
Thomson, Nicole J<njthomson2@ncdot.gov>; Ingram, Jonathan P
<pingram@ncdot.gov>; Hayes, Meredith D<mdhayes3@ncdot.gov>; Moon, Chris D
<cdmoon@ncdot.gov>; mpettus@rkk.com
Cc: Eason, Patty P <peason@ncdot.gov>
Subject: [EXTERNAL] Re: U-2524D Turbid Discharge
�
Attached is my report for U-2524D in Guilford County, the Greensboro Loop between
Battleground Ave and Lawndale Dr.
If you have any questions please feel free to call.
Much Thanks
Aaron Harper, PE
Field Operations Engineer Div 7&8
NCDOT Roadside Environmental Unit
919 776 2279 office
919 777 3038 cell
aaharper@ncdot.gov <mailto:aaharper@ncdot.gov> P.O. Box 429
1530 South 7th Street
Sanford, NC 27330
cid: i mage001. png@01D10DA4.5CC88DA0
Email correspondence to and from this address is subject to the North Carolina Public
Records Law and may be disclosed to third parties.
From: Harper, Aaron A
Sent: Thursday, January 25, 2018 3:24:41 PM
To: david.e.bailey2@usace.army.mil; Norton, April R; Parker, Jerry A; Thomson, Nicole J;
Ingram, Jonathan P; Hayes, Meredith D; Moon, Chris D; mpettus@rkk.com
Cc: Eason, Patty P
Subject: U-2524D Turbid Discharge
�
This email is to serve as notification of turbid discharge on NCDOT Project U-2524D, The
Greensboro Loop between Battleground Ave and Lawndale Dr.
During my monthly EC ride through it was noted that turbid water was overflowing
basin ID 7.2 at approximate Sta 462+/- into the existing stream channel. The drawdown
of the retention pond at approximate Sta 457+50 Rt was opened with the intent of
draining the pond the perform permanent storm pipe work at this location. However,
flow from the retention pond draw down overflowed the adjacent small skimmerbasin,
flowed down the open ditch into basin 7.2, and overflowed basin 7.2.
When I arrived at this site the draw down had already been closed by Chris Utt. The
contractor stopped work in this area and Kevin Haas immediately installed 3 wattles
with PAM in the ditch line, and added PAM to the slope drain inlet. Upon the
recommendation of Nikki, they also added three wattles in the existing channel
downstream of basin 7.2 to prevent any potential sediment from migrating further
down stream. There was no appreciable sediment accumulation noted at this time.
My EC report will be forthcoming. Attached are photos showing the site. If you have
any questions please feel free to call.
Much Thanks
Aaron Harper
Field Operations Engineer Div 7&8
NCDOT Roadside Environmental Unit
919 776 2279 office
919 777 3038 cell
aaharper@ncdot.gov <mailto:aaharper@ncdot.gov> P.O. Box 429
1530 South 7th Street
Sanford, NC 27330
cid: i mage001. png@01D10DA4.5CC88DA0
Email correspondence to and from this address is subject to the North Carolina Public
Records Law and may be disclosed to third parties.
Email correspondence to and from this sender is subject to the N.C. Public Records Law
and may be disclosed to third parties.