HomeMy WebLinkAbout20140957 Ver 2_DEQ Press Release_20180126Higgins, Karen
From: Munger, Bridget <bridget.munger@ncdenr.gov>
Sent: Friday, January 26, 2018 3:14 PM
To: NCDENR.DENR.DWR
Subject: Press release: State issues major water permit for Atlantic Coast Pipeline project
Attachments: ATT00001.txt; ATT00002.txt
Roy Cooper, Governor
Release: IMMEDIATE
Date: Jan. 26, 2018
Contact: Bridget Munger
Phone: 919-807-6363; 919-207-7786
Michael S. Regan, Secretary
State issues major water permit for Atlantic Coast Pipeline project
The state Department of Environmental Quality on Friday issued a 401 water quality certification that is required for the Atlantic Coast Pipeline
project to move forward in North Carolina. Projects that will impact wetlands, buffers or waterways must obtain this certification.
Since Atlantic Coast Pipeline, LLC applied for the 401 certification in May 2017, staff with DEQ's Division of Water Resources have
conducted an exhaustive review of the project plans, requiring the company to submit additional application information on five occasions. As
part of the review process, DEQ held a public comment period June 16—Aug. 19, 2017 and public hearings in Fayetteville and Rocky Mount.
"DEQ left no stone unturned in our exhaustive eight month review of every aspect of the 401 application," said DEQ Secretary Michael Regan
on Friday. "Our job doesn't end with the granting of the permit but continues as we hold the company accountable to live up to its
commitments. Our efforts have resulted in a carefully crafted permit that includes increased environmental protections, while giving us the tools
we need to continue close oversight of this project as it moves forward."
Based on information obtained through the review process and public comment period, water resources staff drafted the final 401 water quality
certification to include numerous more stringent requirements, including but not limited to:
• Stream and Wetland Monitoring: Upon restoration of temporary impacts, restored areas must be monitored for three years with photo
documentation. DEQ may extend monitoring requirements.
• Work in the Dry: Unless an exemption is granted for a specific location, all stream -crossing construction activities must be conducted
using best practices to divert water and limit potential sediment pollution in streams.
• Horizontal Directional Drill: To better protect the Neuse River and its riparian buffers, the project must use a horizontal directional
drill for crossing the waterway.
• Documentation of Drilling Components: The composition and properties of drilling fluids and additives for each horizontal directional
drilling crossing must be submitted to DEQ and will be available online for public access.
• Well Testing: Private well testing will be required before and after construction within 150 feet of the disturbed area or 500 feet from
blasting areas. Testing after impacts must be conducted by an independent qualified groundwater specialist.
• Regular Inspections: DEQ water resources and erosion control staff will conduct monthly onsite inspections of pipeline construction
activities.
• Construction Stormwater Protections: Though not required by state or federal regulations, the project will obtain coverage of and meet
the requirements of the state's construction stormwater permit for the entire construction corridor in North Carolina.
Atlantic Coast Pipeline, LLC must still obtain from DEQ an air quality permit for a compressor station in Northampton County, two general
stormwater permits for impacts in Nash and Cumberland counties, an individual stormwater permit for a contractors' work yard in Cumberland
County and approval of the erosion and sediment control plan for the northern segment of the pipeline's North Carolina route. The erosion and
sediment control plan for the southern segment was approved in December. At the federal level, the project must also obtain a 404 permit from
the U.S. Army Corps of Engineers for stream and wetland impacts.
The Federal Energy Regulatory Commission is the lead regulatory agency for natural gas pipeline projects. That agency approved the Atlantic
Coast Pipeline October 13, 2017 following a public review of the project's environmental impact statement and a public comment period.
The Atlantic Coast Pipeline project will include 604 miles of new natural gas pipeline and related facilities as it runs from West Virginia to
southeastern regions of Virginia and North Carolina. For more information on the pipeline project or to review the 401 permit and approved
erosion plans, please visit: https:Hdeq.nc.gov/about/divisions/energy-mineral-land-resources/acp.
444
Website. htteT.t7c lwr.
Faeeboak.., �,N�,,w.ficebook com" cde
Twitter: 1�ttp..-tti�itter,ti:om�7a �tCDEt
RSS Feed. bttp;;„ pital.nc ler�u.c,i`�.eli'�} t�e��s-teleses g°;s
1601 Mail Service Center, Raleigh.. NC 27699-1601
If you would rather not receive future communications from North Carolina Department of Environmental Quality, let us know by clicking here.
North Carolina Department of Environmental Quality, 217 W. Jones St., Raleigh, North Carolina 27699 United States