HomeMy WebLinkAbout20171563 Ver 1_More Info Received_20180108
Johnson, Alan
From:Rote, Rick <rrote@LaBellaPC.com>
Sent:Monday, January 08, 2018 10:39 AM
To:Johnson, Alan
Cc:Houston, Brian; Chris Hopper (chris.hopper@carolinaeco.com)
Subject:\[External\] Draft Response to DWQ Concerns, Gastonia SE Sewer
Attachments:DRAFT Cover Letter Ph 1 PCN Revised 201.01.08.docx; Avoidance & Minimization -
Baltimore Buffers Shift Review.pdf; BUFFER IMAGE_010418.pdf; Pages from .2170369
(Revs Only) DRAWINGS - SOUTH EAST SEWER Rev1 20180105.pdf - Adobe Acrobat
Standard.pdf
CAUTION: External email. Do not click links or open attachments unless verified. Send all suspicious email as an attachment to
report.spam@nc.gov.
Good Morning Alan
We are working on a few additional things before filing a revised PCN. I wanted to get this draft to you for your review
in advance, if that is acceptable with you, so that we can keep this rolling for time efficiencies.
I have attached portions of the documents meant to address the issues and concerns you raised regarding buffer
impacts. Does this response adequately address your concerns and requests?
Thank you
Richard Rote, CIH
LaBella Associates, P.C.
Cell: 704-575-0179
From: Johnson, Alan \[mailto:alan.johnson@ncdenr.gov\]
Sent: Thursday, January 04, 2018 3:05 PM
To: Rote, Rick
Cc: caryr@cityofgastonia.com; Janiczak, Catherine M CIV USARMY CESAW (US)
Subject: RE: Buffer revised drawings needed per Alan
From our site visit:
The “back” slue was not within the project boundary….so please submit a redrawing for that area with the new buffer
line
The “ditch” was not a stream….so please submit a redrawing for that area
There was a question of a Manhole being “in the stream”…might have been a “scale” issue, but provide clarification and
submit clarifying diagram. I believe this was near the pump station (the second stop).
The more substantial issue was the line cutting down near the lake on the side of the hill. I sent a conceptual drawing
with my thoughts. Please respond with comments why this isn’t possible.
Thanks
1
Alan
From: Munzer, Olivia
Sent: Thursday, January 04, 2018 10:24 AM
To: rrote@labellapc.com
Cc: caryr@cityofgastonia.com; Janiczak, Catherine M CIV USARMY CESAW (US) <Catherine.M.Janiczak@usace.army.mil>;
Johnson, Alan <alan.johnson@ncdenr.gov>; Hamstead, Byron (byron_hamstead@fws.gov) <byron_hamstead@fws.gov>
Subject: SAW-2017-01449 Gastonia - Phase I Gastonia South East Sewer Project - NCWRC Comments
Mr. Rote,
Please see NCWRC’s comments on the Phase I Gastonia South East Sewer Project. Please let me know if you have
questions.
Olivia
Olivia Munzer
Western Piedmont Habitat Conservation Coordinator
®
Certified Wildlife Biologist
NC Wildlife Resources Commission
Sykes Depot, 2430 Turner Rd.
Mebane, NC 27302
Office: 336.290.0056 // Cell: 336.269.0074
olivia.munzer@ncwildlife.org
www.ncwildlife.org
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties