HomeMy WebLinkAboutNC0051021_CEI Report_20171222United States Environmental Protection Agency
Form Approved.
EPA Washington, D.C. 20460
OMB No. 2040-0057
Water Compliance Inspection Report
Approval expires 8-31-98
Section A: National Data System Coding (i.e., PCS)
Transaction Code NPDES yr/mo/day Inspection Type Inspector Fac Type
1 IN 1 2 15 I 3 I NC0051021 111 12 I 17/12/21 I17
18 I S J 19 LG] 201 I
211111 1 1 1 1 1 111 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 111 1 1 1 1 1 166
Inspection Work Days Facility Self -Monitoring Evaluation Rating 131 QA
----------------------Reserved-------------------
67 70 I I 71 I I 72 I r l
u ty
73 I I 174 751 1 1 1 1 1 1 180
I I i
Section B: Facility Data
Name and Location of Facility Inspected (For Industrial Users discharging to POTW, also include
Entry Time/Date
Permit Effective Date
POTW name and NPDES oermit Number)
10:OOAM 17/12/21
15/12/01
Eagle's Nest Foundation -Camp
Hart Rd
Exit Time/Date
Permit Expiration Date
Pisgah Forest NC 28768
12:OOPM 17/12/21
20/09/30
Name(s) of Onsite Representative(s)/Titles(s)/Phone and Fax Number(s)
Other Facility Data
H. Keith Bond/ORC/828-877-3555/
Name, Address of Responsible Official/Title/Phone and Fax Number
Contacted
Kyle Young,43 Hart Rd Pisgah Forest INC 28768//828-877-4349/8288842788
No
Section C: Areas Evaluated During Inspection (Check only those areas evaluated)
Flow Measurement 0 Operations & Maintenance 0 Facility Site Review
Section D: Summary of Finding/Comments (Attach additional sheets of narrative and checklists as necessary)
(See attachment summary)
Name(s) and Signature(s) of Inspector(s) Agency/Office/Phone and Fax Numbers
Date
Timothy H Heim ARO WQ//828-296-4665/
12/22/2017
Signature of Management Q A Reviewer Agency/Office/Phone and Fax Numbers
Date
EPA Form 3560-3 (Rev 9-94) Previous editions are obsolete.
Page#
NPDES yr/mo/day Inspection Type
NCO051021 111 121 17/12/21 1 17 18 JCJ
Section D: Summary of Finding/Comments (Attach additional sheets of narrative and checklists as necessary)
Tim Heim of the Asheville Regional Office performed a Compliance Evaluation Inspection on
December 21, 2017. Keith Bond (ORC — Bond H2O) and Kyle Young (Camp Maintenance) assisted
with the inspection and facility review. The facility appeared well maintained and operated, and in
compliance with Permit NC0051021.
The addition of a mechanical bar screen and/or grinder pumps could reduce operator exposure to
wastewater and maintenance effort and may be considered as a future upgrade.
Page#
Permit: NCO051021
Inspection Date: 12/21/2017
Owner - Facility: Eagle's Nest Foundation -Camp
Inspection Type: Compliance Evaluation
Operations & Maintenance
Is the plant generally clean with acceptable housekeeping?
Does the facility analyze process control parameters, for ex: MLSS, MCRT, Settleable
Solids, pH, DO, Sludge Judge, and other that are applicable?
Comment:
Bar Screens
Type of bar screen
a.Manual
b.Mechanical
Are the bars adequately screening debris?
Is the screen free of excessive debris?
Is disposal of screening in compliance?
Is the unit in good condition?
Yes No NA NE
■
❑
❑
❑
■
❑
❑
❑
Yes No NA NE
0
■ ❑ ❑ ❑
■ ❑ ❑ ❑
E ❑ ❑ ❑
■ ❑ ❑ ❑
Comment: Addition of a mechanical bar screen could reduce operator exposure to wastewater and
maintenance effort.
Aeration Basins
Yes No NA NE
Mode of operation
Ext. Air
❑
❑
Type of aeration system
Diffused
0
❑
Is the basin free of dead spots?
0 ❑
❑
❑
Are surface aerators and mixers operational?
0 ❑
❑
❑
Are the diffusers operational?
0 ❑
❑
❑
Is the foam the proper color for the treatment process?
0 ❑
❑
❑
Does the foam cover less than 25% of the basin's surface?
0 ❑
❑
❑
Is the DO level acceptable?
❑ ❑
❑
0
Is the DO level acceptable?(1.0 to 3.0 mg/1)
❑ ❑
❑
0
Comment: ORC stated he maintains DO at 2-3
Secondary Clarifier
Yes No NA NE
Is the clarifier free of black and odorous wastewater?
0
❑
❑
❑
Is the site free of excessive buildup of solids in center well of circular clarifier?
0
❑
❑
❑
Are weirs level?
0
❑
❑
❑
Is the site free of weir blockage?
0
❑
❑
❑
Is the site free of evidence of short-circuiting?
0
❑
❑
❑
Page# 3
Permit: NCO051021 Owner - Facility:
Eagle's Nest Foundation -Camp
Are tablet chlorinators operational?
0
❑
Inspection Date: 12/21/2017 Inspection Type:
Compliance Evaluation
Are the tablets the proper size and type?
0
❑
Secondary Clarifier
Yes No NA NE
Is scum removal adequate?
0
❑
❑
❑
Is the site free of excessive floating sludge?
0
❑
❑
❑
Is the drive unit operational?
❑
❑
0
❑
Is the return rate acceptable (low turbulence)?
0
❑
❑
❑
Is the overflow clear of excessive solids/pin floc?
0
❑
❑
❑
Is the sludge blanket level acceptable? (Approximately 1/, of the sidewall depth)
0
❑
❑
❑
Comment: ORC stated he checks sludge blanket on a monthly basis and be wasting at 1/3
sidewall depth.
Disinfection -Tablet
Yes No NA NE
Are tablet chlorinators operational?
0
❑
❑
❑
Are the tablets the proper size and type?
0
❑
❑
❑
Number of tubes in use?
2
# Is de -chlorination substance stored away from chlorine containers?
❑ ❑
0
Is the level of chlorine residual acceptable?
0
❑
❑
❑
Is the contact chamber free of growth, or sludge buildup?
0
❑
❑
❑
Is there chlorine residual prior to de -chlorination?
❑
❑
❑
0
Comment:
De -chlorination
Yes No NA NE
Type of system ?
Tablet
Is the feed ratio proportional to chlorine amount (1 to 1)?
0 ❑
❑
❑
Is storage appropriate for cylinders?
❑ ❑
0
❑
# Is de -chlorination substance stored away from chlorine containers?
❑ ❑
0
❑
Comment:
Are the tablets the proper size and type? 0 ❑ ❑ ❑
Are tablet de -chlorinators operational? 0 ❑ ❑ ❑
Number of tubes in use? 2
Comment:
Page# 4