HomeMy WebLinkAbout20140762 Ver 3_TIP R-2915B Temp Causeway SAW-2012-00882_20171208Wanucha, Dave
From: Alsmeyer, Eric C CIV USARMY CESAW (US) <Eric.C.Alsmeyer@usace.army.mil>
Sent: Friday, December 08, 2017 10:39 AM
To: Slaughter, Johnathan H
Cc: Kichefski, Steven L CIV USARMY CESAW (US); Wanucha, Dave; Dagnino, Carla S
Subject: [External] RE: IP Mod RE: NCDOT; TIPR-2915B; Construction Causeway; Ashe County; AID SAW-2012-00882.
Attachments: SAW-2012-00882_TIP NO R 2915_SLAUGHTER.PDF; 17-11-20_R-2915B_US 221 Bridge Demol.Plan.pdf
CAUTION: External email. Do not click links or open attachments unless verified. Send all suspicious email as an attachment to
report.spam@nc.gov.
All: I apologize for putting the wrong subject on this email yesterday.
Please reply or call if you have any questions or if I may serve you in any other way.
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to
do so, please complete the Customer Satisfaction Survey located at http://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0.
Eric A
Eric Alsmeyer
Project Manager
Regulatory Division Office
US Army Corps of Engineers, Wilmington District
3331 Heritage Trade Drive, Suite 105, Wake Forest, NC 27587
Tel: (919) 554-4884, x23
Fax: (919) 562-0421
Regulatory Homepage: http://www.saw.usace.army.mil/Missions/RegulatoryPermitProgram.aspx
-----Original Message-----
From: Alsmeyer, Eric C CIV USARMY CESAW (US)
Sent: Thursday, December 7, 2017 3:37 PM
To: 'Slaughter, Johnathan H' <hslaughter@ncdot.gov>
Cc: Kichefski, Steven L CIV USARMY CESAW (US) <Steven.L.Kichefski@usace.army.mil>; Wanucha, Dave
<dave.wanucha@ncdenr.gov>; Dagnino, Carla S <cdagnino@ncdot.gov>
Subject: IP Mod RE: NCDOT; TIP U-2901; NC 55 Improvements, Apex, Wake County; AID SAW-2017-01023.
Heath: See att. mod.
Please reply or call if you have any questions or if I may serve you in any other way.
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to
do so, please complete the Customer Satisfaction Survey located at http://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0.
Eric A
Eric Alsmeyer
Project Manager
Regulatory Division Office
US Army Corps of Engineers, Wilmington District
3331 Heritage Trade Drive, Suite 105, Wake Forest, NC 27587
Tel: (919) 554-4884, x23
Fax: (919) 562-0421
Regulatory Homepage: http://www.saw.usace.army.mil/Missions/RegulatoryPermitProgram.aspx
From: Slaughter, Johnathan H [mailto:hslaughter@ncdot.gov]
Sent: Monday, November 20, 2017 8:00 AM
To: Alsmeyer, Eric C CIV USARMY CESAW (US) <Eric.C.Alsmeyer@usace.army.mil>; Wanucha, Dave
<dave.wanucha@ncdenr.gov>
Cc: Miles, Randall S<rsmiles@ncdot.gov>; Eller, Douglas W<dweller@ncdot.gov>; Doug Moxley <doug.moxley@jrvannoy.com>;
Dagnino, Carla S<cdagnino@ncdot.gov>; Cheely, Erin K<ekcheely@ncdot.gov>
Subject: [EXTERNAL] R-2915B Demo Plan US 221 Bridge 10
Importance: High
Eric/Dave,
Vannoy Construction has requested authorization to increase the size of the southern causeway under the old bridge crossing
the South Fork New River. The causeway change is needed due to the condition of the old bridge. There is concern about
sections of the old bridge falling into the river as pieces are cut. The expanded causeway would catch those sections should
their assumption be correct. This is a parallel impact to the causeway on the other side from a linear foot perspective but will be
a larger area of temporary impact than shown in the final plans.
Please advise as to whether you need to officially modify the plans or if this email to the file will suffice.
Erin - Please handle any official permit modification if one is required.
From: Gary Eisner [mailto:gary.eisner@jrvannoy.com]
Sent: Thursday, November 16, 2017 1:26 PM
To: Eller, Douglas W <dweller@ncdot.gov>
Cc: Miles, Randall S<rsmiles@ncdot.gov>; Doug Moxley <doug.moxley@jrvannoy.com>; Slaughter, Johnathan H
<hslaughter@ ncdot.gov>
Subject: [External] RE: Demo Plan US 221 Bridge 10
CAUTION: External email. Do not click links or open attachments unless verified. Send all suspicious email as an attachment to
report.spam@nc.gov.
Mr. Eller
I have attached a Drawing with the second Phase Causeway for bridge Demo on it . It look to be about 57'6" long and 30' wide .
I come up with an area of 192 SY . This Causeway would be installed after the removal of the Causeway drawn on the plans on
the North end .
Please contact me with any questions.
Thankyou
Gary D Eisner
Vannoy Construction
Bridge Construction Manger
Office 336-846-4228
CeI I 336-877-0670
E-mail gary.eisner@jrvannoy.com
From: Gary Eisner
Sent: Thursday, November 09, 2017 8:35 AM
To: Eller, Douglas W (dweller@ncdot.gov)
Cc:'Miles, Randall S'; Doug Moxley
Subject: Demo Plan US 221 Bridge 10
CONTRACT : C203758
W BS: 34518.3.6,34518.3.7
COUNTY: ASHE,WATAUGA
T.I.P.NO: R-2915A,R-2915B
Mr. Eller
Vannoy Construction would like to submit for your Review, the Demo Plan for Bridge # 10 on the Above mentioned project .
Please contact me with any Questions .
Thankyou
Gary D Eisner
Vannoy Construction
Bridge Construction Manger
Office 336-846-4228
CeI I 336-877-0670
E-mail gary.eisner@jrvannoy.com
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.