Loading...
HomeMy WebLinkAbout20030179 Ver 6_More Info Received_20090126Dillsboro Dam and Powerhouse Removal Project (FERC #2602) Demolition Plan DUKE ENERGY P Duke IEnergy. January 2009 DEVINE TARBELL & ASSOCIATES, INC. D TA Devine Tarbell & Associates, Inc. C minting E^ 'S'-.n &Req."'sp-i.6. DrJD JAN 6 2009 ;I?1JK ° ?VA(?R G1Ulu.l it M WETLANDS 010 STQRM\p"?,TER B,NS:r' Prepared for: Prepared by: Dillsboro Dam and Powerhouse Removal Project (FERC #2602) Demolition Plan DUKE ENERGY Duke /Energy. DEVINE TARBELL & ASSOCIATES, INC. ZT?A? Devine Tarbell & ,associates, Inc. 4r??..?4??q F.?" K.,.. k?i..r?.i.. k kcK ,• !-lx i?.a January 2009 Prepared for: Prepared by: Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan 1.0. INTRODUCTION ................................................................................................... 1 1.1 Background ............................................................................. ......................... 2 2.0 DAM AND POWERHOUSE REMOVAL PLAN ......................... ......................... 5 2.1 Engineering analysis ................................................................ ......................... 5 2.2 Powerhouse superstructure removal ........................................ ......................... 8 2.3 Dam removal ............................................................................ ......................... 8 2.4 Powerhouse substructure removal ........................................... ......................... 8 3.0 LITERATURE CITED ................................................................... ....................... 14 i Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan DILLSBORO DAM AND POWERHOUSE REMOVAL PROCESS PLAN AND SCHEDULE 1.0. INTRODUCTION The Order Accepting Surrender and Dismissing Application for Subsequent License was issued by the Federal Energy Regulatory Commission (FERC) on July 19, 2007. A subsequent Order on Rehearing and Clarification was issued on April 22, 2008. These Orders accepted an application made by Duke Energy Carolinas, LLC (Duke) to remove the Dillsboro Dam, located on the Tuckasegee River in Jackson County, NC. In ordering Paragraph 50 (D) of the Order Accepting Surrender and Dismissing Application for Subsequent License, the FERC required Duke: At least 60 days before starting removal of the project works, the licensee shall submit one copy of the following documents to the Commission's Division of Dam Safety and Inspections (D2SI) Atlanta Regional Office, and two copies to the Commission (one of these shall be a copy to the Director, D2SI): (1) a detailed description of the sequence of activities and schedule for removing the project features and restoring the site; (2) final contract plans and specifications; (3) Quality Control and Inspection Program; (4) Temporary Construction Emergency Action Plan; (5) a blasting plan, if necessary; (6) a public safety plan for the period during removal activities; and (7) a detailed erosion and sediment control plan that includes but is not limited to descriptions and locations of the erosion and sediment control measures to be implemented during removal of the project features and site restoration, to also include deconstruction staging areas, access locations, and sediment and debris disposal areas. The detailed activities presented here and in the associated attachments fulfill items 1-4 and 6 above and provide the detailed removal/demolition specifications and drawings required by the FERC. A blasting plan (Item 5) is not necessary because explosives will not be used. A detailed erosion and sediment control plan (Item 7) was submitted (May 1 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan 22, 2008) to the FERC under a separate cover for Paragraph H of this order and was approved on July 15, 2008. 1.1. BACKGROUND The Dillsboro Hydroelectric Project is located in western North Carolina, on the Tuckasegee River, near the town of Dillsboro at River Mile 31.7. The Dillsboro Dam is a 310 feet-long concrete masonry structure that is 12 feet in height. A full description of the Dillsboro Hydroelectric Project is provided in the Application for Surrender of License (Duke Energy 2004). The project operates in a limited storage mode with reservoir levels remaining within 6 inches of full pond elevation. 2.0 PURPOSE Dillsboro Dam and Powerhouse will be removed in a phased manner during the January to March time-period and the removal process was described fully in the Application for Surrender of License (Duke Energy 2004). The purpose of this section is to detail the schedule and sequence of events leading up to demolition of the dam and powerhouse and to detail the plan associated with demolition. 3.0 SCHEDULE AND SEQUENCE OF EVENTS DETAILED SCHEDULE AND SEOUENCE OF EVENTS Start Date Activity D?udraation End Date Sand Mining -Site preparation within the 1/15/2009 Project Boundary 30 2/15/2009 File Dillsboro Demolition Plan, Specification and Process Schedule with the FERC *these plans and specifications were prepared with consultation from the NCWRC NCDENR, USFWS, and Eastern Band of Cherokee Indians. Duke allowed at least 30 days for agency comment on these plans and specification before this submittal to the 2/15/2009 FERC. 1 2/15/2009 2 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan Start Date Activity D u r ation End Date ( d a Commence sand mining activities within the 2/15/2009 reservoir 150 7/15/2009 Develop and implement hazardous waste plan 2/15/2009 for the powerhouse 60 4/15/2009 FERC Order approving demolition plans, 3/27/2009 specifications and schedule 1 3/27/2009 Release Bid Package to potential demolition 4/23/2009 contractors 1 4/23/2009 Receive Bids from potential demolition 6/30/2009 contractors 1 6/30/2009 8/15/2009 Commence demolition contractor selection 15 9/1/2009 Appalachian Elktoe relocation completed, as 10/1/2009 detailed in the Mussel Relocation Plan 15 10/15/2009 11/1/2009 Demolition contact awarded 1 11/1/2009 11/8/2009 Remove Bats from Powerhouse, if necessary 2 11/9/2009 1/2/2010 Commence dam and powerhouse demolition 1 1/2/2010 Remove existing Transmitting Facility 1/2/2010 (transformers, wires) 4 1/5/2010 1/8/2010 Remove/disperse left training wall in Tailrace 4 1/11/2010 Install Forebay work pad upstream of 1/9/2010 Powerhouse 3 1/11/2010 Dismantle/demolish wood/steel 1/12/2010 Superstructure 4 1/16/2010 Remove Turbine/Generators and Electrical 1/17/2010 Components 4 1/21/2010 1/22/2010 Remove Draft Tubes 4 1/26/2010 1/27/2010 Install Generator Cover Plates 1 1/27/2010 1/28/2010 Remove Foreba Work ad 3 1/30/2010 1/30/2010 Public breach notifications 1 1/30/2010 Install Access Road/work pad from left 2/5/2010 abutment along upstream face of Dam 5 2/9/2010 Coordinate release schedule with Hydro 2/10/2010 Central 1 2/10/2010 Notch Dam (remove first lift) adjacent to Powerhouse and initiate partial and controlled 2/11/2010 drainage of reservoir 6 2/16/2010 Remove Access Road/work pad to 2 d Stage 2/17/2010 Demolition Location 2 2/18/2010 First Stage Dillsboro Reservoir flushing flow 2/19/2010 event 3 2/21/2010 2 d Stage Dam Demolition (remove additional 2/22/2010 lifts) 10 2/31/2010 Phase I Archeological Study with Eastern 2/23/2010 Band of Cherokee Indian assistance 10 3/1/2010 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan Start Date Activity D u r ation End Date ( d a Remove Access Road/work pad to 3rd Stage 3/1/2010 Demolition Location 2 3/2/2010 Apply erosion control measures and revegetate exposed and potential high erosion 3/2/2010 areas, as detailed in the Restoration Plan 43 4/15/2010 2 d Stage Dillsboro Reservoir Flushing Flow 3/3/2010 Event 3 3/5/2010 3rd Stage Dam Demolition (remove additional 3/6/2010 lifts) 10 3/15/2010 Riprap Ramp construction from Parking Lot 3/13/2010 to Powerhouse Intake 3 3/15/2010 Remove Access Road/work pad to 4th/Final 3/16/2010 Stage Demolition Location 2 3/17/2010 Demolish/Remove Concrete Substructure and 3/16/2010 fill to grade 14 4/1/2010 3rd Stage Dillsboro Reservoir flushing flow 3/18/2010 event 3 3/20/2010 4'h/Final Stage Dam Demolition (remove 3/21/2010 additional lifts), if necessary 10 4/2/2010 4/2/2010 Remove Construction Ram 3 4/4/2010 Remove Access Road, work pad, and remaining sediment to original river channel 4/3/2010 grade 2 4/4/2010 4'h Stage Dillsboro Reservoir flushing, flow 4/5/2010 event, if necessary 3 4/7/2010 4/5/2010 Restore Left Abutment area 2 4/6/2010 4/5/2010 Restore Right Abutment area 2 4/6/2010 Commence additional or remaining revegetation measures (seeding and woody 4/5/2010 plantings), as detailed in the Restoration Plan 180 11/4/2010 File Revegetation Implementation Report with FERC, as detailed in the Restoration 6/4/2010 Plan 1 6/4/2010 Commence various post-removal monitoring 6/1/2010 programs 1095 6/1/2014 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan 4.0 DAM AND POWERHOUSE REMOVAL PLAN The decommissioning of the Project includes the full removal to grade of the existing Dillsboro Dam and Powerhouse on the Tuckasegee River. A plan view and cross-section view of the dam and powerhouse are shown in Figure 3. 1.1 and Figure 3.1.2. The dam and powerhouse are to be removed to the original riverbed over the full width of the river and no natural rock ledge will be removed. The river will be returned to its assumed pre- dam bank-to-bank width and depth. In accordance with the Sediment Management Plan and the Section 401/404 authorizations, the required 70,000 cubic yards of sediment will be removed prior to demolition of the dam and subsequent drawdown of the reservoir. Removal will be accomplished by use of hydraulic equipment to remove the dam and powerhouse structures in accordance with a staged demolition plan. An excavator with a hoe-ram attachment or similar mechanism will demolish the dam, with an excavator and a track loader used to remove additional sediment, if necessary, and remove rubble/concrete. There is no blasting associated with this demolition project. During the demolition process, river flow will be, at various times and sometimes in combination, passed through a notch in the dam, and/or passed over the partially demolished dam crest. A complete hazardous material inventory will be conducted within the powerhouse prior to demolition. Proper steps for the removal and disposal of discovered hazardous material will be conducted in accordance with applicable state and federal regulations, as well as Duke Energy standards. Upstream and downstream environmental monitoring will also be conducted during the dam and powerhouse removal phase of the Project. The existing transmission equipment, useable wood, powerhouse controls, and turbine- generator equipment contained within and adjoining the powerhouse will be removed for salvage purposes to the maximum extent possible. 5 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan 4.1 Engineering analysis The Dillsboro Dam and Powerhouse are to be removed to the original riverbed over the full width of the river with no natural rock ledge to be removed. The dam consists of two separate uncontrolled spillway sections and a gated section, and has an overall length of approximately 230 feet. The concrete dam height is approximately 12 feet. The powerhouse consists of a steel frame and wooden superstructure along with a three-unit intake section. The overall powerhouse length is approximately 80 feet. The right (north) abutment wall, approximately 10 feet long, and the left (south) abutment wall, approximately 5 feet long, will be left in place during the demolition of the dam and powerhouse. The respective abutment wall removal will be the last part of the dam demolition and will occur just prior to site restoration. The Dillsboro Dam and Powerhouse removal will consist of three demolition phases. The first phase includes the removal of the powerhouse superstructure, removal of generating equipment, and establishing water passage through the vacated hydro unit openings and draft tubes. Consideration shall be given to salvaging as much of the turbine-generator equipment as possible. The second phase consists of removing the dam, and the third phase involves removal of the powerhouse substructure. Figure 3.2.1 and Figure 3.2.2 present diagrams of the dam and powerhouse removal sequence. Powerhouse demolition access will be from the powerhouse parking lot off North River Road (if possible), while access to the left (south) abutment will be off Mockingbird Lane. An existing sewer line is located along the north reservoir rim and generally runs parallel with the Dillsboro Reservoir and North River Road. The same sewer line continues in a westerly direction downstream of the powerhouse. The sewer line will be monitored during all phases of the demolition and removal. However, based on pre- removal geotechnical studies, no sewer line issues are expected. A detailed hazardous waste inspection/inventory will be conducted at the powerhouse prior to Project demolition. The inventory will include all solvents, lubricants, paints, 6 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan oils, and the presence of asbestos and lead paint. The existing Dillsboro Spill Prevention, Control, and Countermeasure Plan (or equivalent Oil Spill Response Manual) along with existing plant Material Safety Data Sheets will be reviewed and utilized during the inspection. The inventory shall include type and quantity of each substance. A Hazardous Waste Removal & Disposal Plan will be developed for the Dillsboro Project based on the inspection inventory. Potentially hazardous material will be removed from the powerhouse prior to commencing powerhouse superstructure demolition. Mechanical sediment removal (i.e., hydraulic removal) will be conducted upstream of the dam along the left bank (looking downstream). This removal will be accomplished through use of a backhoe or vacuum dredging. The upstream sediment volume within the existing reservoir is estimated at approximately 100,000 cubic yards. The quantity of sediment to be mechanically removed is equal to 70,000 cubic yards, as detailed in the Sediment Management Plan and required by the Section 401/404 authorizations. Once removed this material will be properly disposed of in an upland disposal site or sold for use on upland sites. Items 50(D) (2 through 7) of the FERC Surrender Order have been submitted under a separate cover and provide the detailed removal/demolition specifications and drawings. A Section 401 (Clean Water Act) Water Quality Certification was issued from the NCDWQ on November 27, 2007. A U.S. Army Corps of Engineers, Section 404 "dredge and fill" permit (i.e., Nationwide Permit 27 and 16) was also required for this work within the "waters of the U. S." This nationwide permit was authorized on June 5, 2008. Other items required by the FERC Order or the Section 401 and approved for this project include: ¦ Site Restoration Plan-50 (E) of the FERC Order ¦ Mussel Relocation Plan -50 (F) of the FERC Order ¦ Bat Relocation Plan - 50 (G) of the FERC Order ¦ Sediment Management Plan - 50 (H) of the FERC Order 7 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan ¦ Fish Monitoring Plan - 50 (L) of the FERC Order ¦ Water Quality Monitoring Plan- Section 401 condition 4.2 Powerhouse superstructure removal The powerhouse superstructure and machinery are to be removed prior to the start of dam removal activities. The estimated duration of powerhouse removal is 4 to 5 weeks. 4.3 Dam removal The crest of the 12-foot-high dam is at elevation 1972.0 feet msl. The dam is 230 feet wide, including a 34-foot-wide gate and overflow spillway structure at the left (south) abutment of the dam. Dam demolition will begin during the mid-winter to early spring months (i.e., January to late March/early April 2010). 4.4 Powerhouse substructure removal The removal of the powerhouse concrete substructure will be performed after completing the majority of the dam removal phase. The substructure depth is approximately 23 feet. The estimated duration of removal is 4 to 5 weeks. 8 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan z I I w? 1 l ?L f OM.# 31q -IEA? 1411 MAO PlZ QPC- II tt '.?UrH?Lffti Figure 3.1.1 9 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan I i I, ,1 I irtFx5i M,T F( IEP4YI?u[ pl iq r]r K.Fi3C IM F 14 [rot a e '......... ... ,... .. .. _. _: F'I •?. 4?[3 ,? Ili{Y 1 1- _ - =? - Figure 3.1.2 10 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan Figure 3.21 Dillsboro Dam Removal Sequence Powerhouse Gate 0 0 0 0 Dam I Spillway Structure 1) Place access ramp, pre-demolition activities, start pre-removal monitoring 2) Remove powerhouse superstructure, initiate removal phase monitoring Remove initial dam section, 40 - 0 ft. 11 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan Figure 32.1 DiUsboro Dam Removal Sequence (cont). Powerhouse Gate Darn/ Spillway Structure 5) Continue sequential removal and flow control 6) Continue removal working to left bank 7) Dam removal completed to left bank 8) Remove Powerhouse substructure, post-removal monitoring 12 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan 1)i11shoro Dorm Rein oial Sequence "4 a 411 at? ? ? I! Itkw V ?F^ x J r ? a ?':?y -{ ..fix ?yC• y? - ? f` _ ?yA ?' MI's' F ? ?l? h•V ?Y???, - .?.k. y h '-7 ?N S' R R t a. ? 'Ar JIy' _ 13 Duke Energy Carolinas Dillsboro Dam Removal Demolition Plan 5.0 LITERATURE CITED Duke Energy. 2004. Application for the Surrender of the Dillsboro Hydroelectric Project License, FERC # 2602 Duke Energy. 2003. Dillsboro Hydroelectric Project, FERC # 2602, License Application Volume 1 14 DILLSBORO HYDROELECTRIC DECOMMISSIONING & REMOVAL SPECIFICATIONS SPECIFICATION NO.: 024.0029.0000 Prepared for: P Duke ?Ener Duke Energy Carolinas, LLC 526 South Church Street Charlotte, North Carolina 28201-1006 By: 400 S. Tryon Street, Suite 2401 Charlotte, NC 28285 December 18, 2008 © Copyright 2008 by: Devine Tarbell & Associates, Inc. Note: This specification contains confidential and proprietary information. This specification shall not be reproduced, or transmitted in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without prior written permission of Devine Tarbell & Associates, Inc. This specification shall not be disclosed, in whole or in part, to any third party without prior written permission of Devine Tarbell & Associates, Inc. Devine Tarbell & Associates, Inc. Consulting Engineers, Scientists, & Regulatory Specialists Verification of Specification Project: Dillsboro Hydroelectric Decommissioning & Removal Project Title of Specification: Dillsboro Hydroelectric Decommissioning & Removal Specification Specification No.: 024.0029.0000 Revision No.: 0 This document specifies items that are important to the operation of a hydroelectric generation facility. The contents of this document have been reviewed for accuracy and define the functional requirements and quality level commensurate with the intended application. Prepared by: Date: Checked by: Approved by: Inspection Waived By: Inspection Waived For: ? Electrical Inspected By: Date: Date: Date: ? Mechanical ? Civil Date: Professional Engineer Approval: Signature: Name: Title: No. & State: Devine Tarbell & Associates, Inc. 400 South Tryon Street Charlotte, NC 28285 REVISION DESCRIPTION SHEET REVISION + PAGES REVISED AND DESCRIPTION NUMBER I Review Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina December 18, 2008 Duke Energy Carolinas, LLC Division Section. Title Rev. No. Pages] DIVISION 01- GENERAL REQUIREMENTS 010000 GENERAL 0 3 011000 SUMMARY 0 3 012200 UNIT PRICES 0 2 013100 PROJECT MANAGEMENT AND COORDINATION 0 9 013200 CONSTRUCTION PROGRESS DOCUMENTATION 0 8 013233 PHOTOGRAPHIC DOCUMENTATION 0 4 013300 SUBMITTAL PROCEDURES 0 9 014000 QUALITY REQUIREMENTS 0 7 014200 REFERENCES 0 4 015000 TEMPORARY FACILITIES AND CONTROLS 0 7 015639 TEMPORARY TREE AND PLANT PROTECTION 0 6 017300 EXECUTION 0 7 017329 CUTTING AND PATCHING 0 4 017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 0 7 017700 CLOSEOUT PROCEDURES 0 4 017839 PROJECT RECORD DOCUMENTS 0 4 DIVISION 02 - EXISTING CONDITIONS 024116 STRUCTURE DEMOLITION 0 6 024119 SELECTIVE STRUCTURE DEMOLITION 0 6 DIVISION 03 - CONCRETE 033000 CAST-IN-PLACE CONCRETE 0 16 DIVISION 05 - METALS 055213 PIPE AND TUBE RAILINGS 0 9 DIVISION 10 - SPECIALTIES 101400 SIGNAGE 0 7 DIVISION 31- EARTHWORK 311000 SITE CLEARING 0 5 312000 EARTH MOVING 0 12 312501 EROSION AND SEDIMENT CONTROL 0 5 DIVISION 32 - EXTERIOR IMPROVEMENTS 321216 ASPHALT PAVING 0 8 323113 CHAIN LINK FENCES AND GATES 0 10 329200 TURF AND GRASSES 0 9 TABLE OF CONTENTS Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029. 0000 Revision No.: Review 2 December 18, 2008 SECTION 010000 - GENERAL PART 1 - GENERAL 1.1 PROJECT NAME A. Dillsboro Hydroelectric Project Decommissioning & Removal 1.2 PROJECT INFORMATION A. Project Location: 150 North River Road; Dillsboro, North Carolina B. Owner: Duke Energy Carolinas, LLC C. Owner's Representative: Jack Jenkins; 526 South Church Street; Charlotte, North Carolina 28201-1006. 1.3 DEFINITIONS A. Engineer: Devine Tarbell & Associates, Inc. B. Contractor/Seller: The successful bidder to whom the contract has been awarded, and who has executed the contract and furnished acceptable contract bonds. C. Furnish: Except as otherwise defined in greater detail, the term "furnish' is used to mean supply and deliver to the project site, ready for unloading, unpacking, assembly, erection, installation, etc., applicable to each instance. D. Install: Except as otherwise defined in greater detail, the term "install" is used to describe operations at the project site, including unloading, unpacking, assembly, erection, placing, anchoring, alignment, finishing, curing, protecting, cleaning and similar operations as applicable in each instance and in accordance with specification, drawings, and other contract documents. E. Provide: Except as otherwise defined in greater detail, the term "provide" means furnish and install, complete and ready for intended purpose and, as applicable in each instance. F. Accept: The term "accept" and "acceptance" where used in conjunction with the Engineer's action on the Contractor's submittals, applications and requests are limited to the duties and responsibilities of the Engineer as stated. Such acceptance shall not release the Contractor from responsibility to fulfill contract requirements unless otherwise provided in the contract documents. G. Work: "Work" shall mean all Contractor items of responsibility as set out in the awarded order. SECTION 010000 - GENERAL Page 1 of 3 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC 1.4 PERFORMANCE OF WORK DT,A Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Contractor shall diligently, duly and properly perform and complete the Work and shall provide and pay for all items and services necessary for the proper execution and completion of the Work. Additionally, Contractor shall perform and provide all Work not specifically delineated in the Agreement to the extent necessary to complete the Work in accordance with standard industry practices. Contractor shall be solely responsible for all means, methods, techniques, sequences, procedures, safety and quality assurance, and quality control programs in connection with the performance of the Work. B. Contractor shall employ a sufficient number of qualified persons, who shall be licensed if required by laws, so that Contractor completes the Work and Contractor's other obligations under the awarded order, in an efficient, prompt, economical and professional manner. Furthermore, Contractor shall supervise, coordinate, and direct the Work using Contractor's best skill, judgment, and attention. Contractor shall provide at all times during the progress of the Work, a competent resident superintendent. The superintendent will be the Contractor's representative at the site and shall have the authority to act on behalf of the Contractor. C. Contractor shall develop, implement, and maintain a written plan for the Work that shall include: Work safety; security at the Site; quality assurance; management and control of the Work; and management and control of Subcontractors and their subcontracts. That plan shall meet the requirements of all laws. D. Contractor shall maintain in good order at the Site and available to Owner for inspection at all times at least one record copy of all Documentation marked current to record changes made during the Work. E. In the event of any emergency endangering life or property, Contractor shall take all actions as may be reasonable and necessary to prevent, avoid, or mitigate injury, damage or loss and shall report as soon as possible all of those incidents and Contractor's responses to Owner. F. Contractor shall provide adequate facilities required for the performance of the Work and obtain all the necessary permits and licenses required for the construction and operation of such facilities. Facilities shall be subject to approval by Owner and shall be removed at completion of the Work and the area restored to original condition or as required by the Project Drawings. Contractor shall confine its facilities, operations and materials at the project site to areas permitted by laws and as shown or designated on the Project Drawings. G. Contractor shall secure and pay for all permits, licenses, Government fees, inspections and Government approvals necessary for the proper execution and completion of the Work, other than the Owner's Permits. Contractor shall provide reasonable assistance and documents to Owner in connection with Owner's efforts to obtain the Owner's permits. H. Until the completion of the Work, Contractor shall attend and participate in regular meetings with Owner, which shall occur as scheduled by Owner for the purpose of discussing the status of the Work and anticipating and resolving problems. Those meetings may also include, at the request of Owner, consultants and other persons. I. Contractor shall carry out the Work so as not to interfere unnecessarily or improperly with (a) operations on the Site or (b) access to, use of or occupation of public or private roads footpaths SECTION 010000 - GENERAL Page 2 of 3 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 or properties in the possession of Owner or any other persons. Contractor shall be deemed to have satisfied itself as to, and shall be fully responsible for, the routing for delivery of heavy or large loads to the Site. At all times during the performance of the Work, Contractor shall keep the site and surrounding streets, properties, sidewalks and other areas free from waste materials, equipment, rubbish, debris and other garbage, and liquid and non-liquid materials whether spilled, dropped, discharged, blown out or leaked. Contractor shall employ adequate dust control measures. Contractor and all Subcontractors shall handle and dispose of properly all chemicals used in cleaning processes. Upon completion of the Work, Contractor shall remove from the project site all tools, trailers, surplus and waste materials, and rubbish, and otherwise leave the site neat and clean. 1.5 GENERAL REQUIREMENTS A. The Contractor shall insure that employee's park in designated parking areas. Failure to park in designated parking areas may result in vehicle being towed at Contractor's expense. B. All supervisors and at least one (1) employee on each of Contractor's crews must be able to speak and understand English during all work activities. 1.6 DISCREPANCIES A. If, in the course of performing the Work, the Contractor finds any discrepancy between the Project Drawings and the Project Specifications, or any error or omission in dimensions or instructions in these drawings or specifications, Contractor shall immediately notify Owner, and Owner will promptly do the same. END OF SECTION 010000 SECTION 010000 - GENERAL Page 3 of 3 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Work covered by the Contract Documents. 2. Products ordered in advance. 3. Owner-furnished items. 4. Use of premises. 5. Work restrictions. 6. Specification formats and conventions. 1.3 WORK COVERED BY CONTRACT DOCUMENTS A. Project Identification: Dillsboro Hydroelectric Project Decommissioning & Removal 1. Project Location: 150 North River Road; Dillsboro, North Carolina B. Owner: Duke Energy Carolinas, LLC; 526 South Church Street; Charlotte, North Carolina 28201-1006 1. Owner's Representative: Jack Jenkins; 526 South Church Street; Charlotte, North Carolina 28201-1006 C. Engineer: Devine Tarbell & Associates, Inc.; 400 South Tryon Street, Suite 2401; Charlotte, North Carolina 28285 D. Contractor: To Be Determined by Owner. E. The Work consists of the following: 1. Complete removal of the Powerhouse structure. Refer to Contract Drawings for details. 2. Partial removal of the Powerhouse substructure. Refer to Contract Drawings for details. 3. Complete removal of the Spillway and Flood Control Gate structures. Refer to Contract Drawings for details. SECTION 011000 - SUMMARY Page 1 of 3 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1.4 PRODUCTS ORDERED IN ADVANCE A. General: Owner has negotiated Purchase Orders with suppliers of material and equipment to be incorporated into the Work. Owner will assign these Purchase Orders to Contractor. Costs for receiving, handling, storage if required, and installation of material and equipment are included in the Contract Sum. Contractor's responsibilities are same as if Contractor had negotiated Purchase Orders, including responsibility to renegotiate purchase and to execute final Purchase-Order agreements. 1.5 OWNER-FURNISHED ITEMS A. Owner will furnish items indicated. 1. Owner will arrange for and deliver Shop Drawings, Product Data, and Samples to Contractor. 2. Owner will arrange and pay for delivery of Owner-furnished items according to Contractor's Construction Schedule. 3. After delivery, Owner will inspect delivered items for damage. Contractor shall be present for and assist in Owner's inspection. 4. If Owner-furnished items are damaged, defective, or missing, Owner will arrange for replacement. 5. Owner will arrange for manufacturer's field services and for delivery of manufacturer's warranties to Contractor. 6. Owner will furnish Contractor the earliest possible delivery date for Owner-furnished products. Using Owner-furnished earliest possible delivery dates, Contractor shall designate delivery dates of Owner-furnished items in Contractor's Construction Schedule. 7. Contractor shall review Shop Drawings, Product Data, and Samples and return them to Engineer noting discrepancies or anticipated problems in use of product. 8. Contractor is responsible for receiving, unloading, and handling Owner-furnished items at Project site. 9. Contractor is responsible for protecting Owner-furnished items from damage during storage and handling, including damage from exposure to the elements. 10. If Owner-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them. 11. Contractor shall install and otherwise incorporate Owner-furnished items into the Work. 1.6 USE OF PREMISES A. General: Contractor shall have limited use of premises for construction operations as indicated on Contract Drawings and/or Owner. B. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated. 1. Limits: Confine constructions operations to areas approved by Owner and/or shown in Contract Documents. SECTION 011000 - SUMMARY Page 2 of 3 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 2. No fill of any type shall be placed in the river on the downstream side. 3. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. a. Schedule deliveries to minimize use of driveways and entrances. b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. 1.7 WORK RESTRICTIONS A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except otherwise indicated. 1. Weekend Hours: Weekend hours will normally not be permitted and will require the written approval of Duke Energy's Project Manager at least 72 hours in advance. 2. Early Morning Hours: Early Morning hours will normally not be permitted and will require the written approval of Duke Energy's Project Manager at least 72 hours in advance. END OF SECTION 011000 SECTION 011000 - SUMMARY Page 3 of 3 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC SECTION 012200 - UNIT PRICES PART 1 - GENERAL 1.1 RELATED DOCUMENTS DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes administrative and procedural requirements for unit prices. B. Related Sections include the following: 1. Division 01 Section "Quality Requirements" for general testing and inspecting requirements. 2. Contract terms and conditions for procedures for submitting and handling Change Orders. 1.3 DEFINITIONS A. Unit price is an amount established as a price per unit of measurement for materials or services added to or deducted from the Contract Sum by appropriate modification, if estimated quantities of Work required by the Contract Documents are increased or decreased. 1.4 PROCEDURES A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit. B. Measurement and Payment: Refer to individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are defined by the contract. C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent party acceptable to Contractor. D. List of Unit Prices: A list of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price. SECTION 012200 - UNIT PRICES Page 1 of 2 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 LIST OF UNIT PRICES A. Unit Price No. - Work Element - Unit of Measurement 1. Excavation: Cubic Yard 2. Backfill Placement and Compaction: Cubic Yard 3. Backfill Material: Type and Cubic Yardage 4. Concrete: Cubic Yard 5. Reinforcing Steel: Tonnage 6. Piping: Nominal size and Linear Footage 7. Coatings Application: Square Foot 8. Coatings Materials: Gallon 9. Paving Placement: Cubic Yard 10. Paving Materials: Type and Cubic Yardage 11. Other Items: As agreed by Owner and Contractor. END OF SECTION 012200 SECTION 012200 - UNIT PRICES Page 2 of 2 Dillsboro Hydroelectric Project Decommissioning & Demolition Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: 1. Coordination Drawings. 2. Administrative and supervisory personnel. 3. Project meetings. 4. Requests for Interpretation (RFIs). B. Contractor shall participate in coordination requirements. Certain areas of responsibility will be assigned to specific contractor personnel. C. Related Sections include the following: 1. Division 01 Section "Construction Progress Documentation" for preparing and submitting Contractor's Construction Schedule. 2. Division 01 Section "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points. 3. Division 01 Section "Closeout Procedures" for coordinating closeout of the Contract. 1.3 DEFINITIONS A. RFI: Request for Information from Contractor seeking interpretation or clarification of the Contract Documents. 1.4 COORDINATION A. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation and/or demolition of each part of the Work. Each contractor shall coordinate its operations with operations, included in different Sections, which depend on each other for proper demolition installation, connection, and operation. SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION Page 1 of 9 Dillsboro Hydroelectric Project Decommissioning & Demolition Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Schedule construction operations in sequence required to obtain the best results where installation and/or demolition of one part of the Work depends on installation and/or demolition of other components, before or after its own installation/demolition. 2. Coordinate installation and/or demolition of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair. 3. Make adequate provisions to accommodate items scheduled for later installation and/or demolition. 4. Where availability of space is limited, coordinate installation and/or demolition of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components. B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings. 1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required. C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following: 1. Preparation of Contractor's Construction Schedule. 2. Preparation of the Schedule of Values. 3. Installation and demolition of temporary facilities and controls. 4. Delivery and processing of submittals. 5. Progress meetings. 6. Pre-installation and/or demolition conferences. 7. Project closeout activities. 8. Startup and adjustment of systems. D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. 1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. Refer to other Sections for disposition of salvaged materials that are designated as Owner's property. 1.5 SUBMITTALS A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation and/or demolition of different components or if coordination is required for installation of products and materials fabricated by separate entities. 1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable: SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION Page 2 of 9 Dillsboro Hydroelectric Project Decommissioning & Demolition Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems. b. Indicate required installation or demolition sequences. C. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Owner or Owner's representative for resolution of such conflicts. Minor dimension changes and difficult installations or demolitions will not be considered changes to the Contract. 2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 30 by 40 inches. 3. Number of Copies: Submit two opaque copies of each submittal. Owner or Owner's representative will return one copy. a. Submit three copies where Coordination Drawings are required for operation and maintenance manuals. Owner or Owner's representative will retain two copies; remainder will be returned. Mark up and retain one returned copy as a Project Record Drawing. 4. Refer to individual Sections for Coordination Drawing requirements for Work in those Sections. B. Key Personnel Names: Within 30 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home and office telephone numbers. Provide names, addresses, and telephone numbers of individuals assigned as standbys in the absence of individuals assigned to Project. 1. Post copies of list in Project meeting room, in temporary field office, and by each temporary telephone. Keep list current at all times. 1.6 ADMINISTRATIVE AND SUPERVISORY PERSONNEL A. General: In addition to Project superintendent, provide other administrative and supervisory personnel as required for proper performance of the Work. 1. Include special personnel required for coordination of operations with other contractors. 1.7 A. PROJECT MEETINGS General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated. 1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Engineer of scheduled meeting dates and times. 2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees. SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION Page 3 of 9 Dillsboro Hydroelectric Project Decommissioning & Demolition Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner or Owner's representative, within three days of the meeting. B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Owner or Owner's representative, but no later than 15 days after execution of the Agreement. Hold the conference at Project site or another convenient location. Conduct the meeting to review responsibilities and personnel assignments. 1. Attendees: Authorized representatives of Owner or Owner's representative, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work. 2. Agenda: Discuss items of significance that could affect progress, including the following as appropriate. a. Tentative construction schedule. b. Critical work sequencing and long-lead items. C. Designation of key personnel and their duties. d. Procedures for processing field decisions and Change Orders. e. Procedures for RFIs. f. Procedures for testing and inspecting. g. Procedures for processing Applications for Payment. h. Distribution of the Contract Documents. i. Submittal procedures. j. Preparation of Record Documents. k. Use of the premises. 1. Work restrictions. M. Responsibility for temporary facilities and controls. n. Construction waste management and recycling. o. Parking availability. p. Office, work, and storage areas. q. Equipment deliveries and priorities. r. First aid. S. Security. t. Progress cleaning. U. Working hours. 3. Minutes: Record and distribute meeting minutes. C. Pre-installation and/or demolition Conferences: Conduct a pre-installation and/or demolition conference at Project site before each construction activity that requires coordination with other construction. Attendees: Installer and/or demolition crew and representatives of manufacturers and fabricators involved in or affected by the installation/demolition and its coordination or integration with other materials and installations and/or demolitions that have preceded or will follow, shall attend the meeting. Advise Owner or Owner's representative of scheduled meeting dates. SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION Page 4 of 9 Dillsboro Hydroelectric Project Decommissioning & Demolition Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following as appropriate. a. The Contract Documents. b. Options. C. Related RFIs. d. Related Change Orders. e. Purchases. f. Deliveries. g. Submittals. h. Review of mockups. i. Possible conflicts. j. Compatibility problems. k. Time schedules. 1. Weather limitations. M. Manufacturer's written recommendations. n. Warranty requirements. o. Compatibility of materials. p. Acceptability of substrates. q. Temporary facilities and controls. r. Space and access limitations. S. Regulations of authorities having jurisdiction. t. Testing and inspecting requirements. U. Installation and/or removal procedures. V. Coordination with other work. W. Required performance results. X. Protection of adjacent work. y. Protection of construction and personnel. 3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions. 4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present. 5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date. D. Progress Meetings: Conduct progress meetings at biweekly intervals. Coordinate dates of meetings with preparation of payment requests. I. Attendees: In addition to representatives of Owner, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work. 2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project. SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION Page 5 of 9 Dillsboro Hydroelectric Project Decommissioning & Demolition Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. 1) Review schedule for next period. b. Review present and future needs of each entity present, including the following: 1) Interface requirements. 2) Sequence of operations. 3) Status of submittals. 4) Deliveries. 5) Off-site fabrication. 6) Access. 7) Site utilization. 8) Temporary facilities and controls. 9) Work hours. 10) Hazards and risks. 11) Progress cleaning. 12) Quality and work standards. 13) Status of correction of deficient items. 14) Field observations. 15) RFIs. 16) Status of proposal requests. 17) Pending changes. 18) Status of Change Orders. 19) Pending claims and disputes. 3. Minutes: Owner or Owner's representative will record and distribute to Contractor the meeting minutes. 4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present. a. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting. E. Coordination Meetings: Conduct Project coordination meetings at weekly intervals. Project coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and pre-installation conferences. Attendees: In addition to representatives of Owner, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work. SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION Page 6 of 9 Dillsboro Hydroelectric Project Decommissioning & Demolition Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 Agenda: Review and correct or approve minutes of the previous coordination meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project. a. Combined Contractor's Construction Schedule: Review progress since the last coordination meeting. Determine whether each contract is on time, ahead of schedule, or behind schedule, in relation to Combined Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. b. Schedule Updating: Revise Combined Contractor's Construction Schedule after each coordination meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with report of each meeting. C. Review present and future needs of each subcontractor present, including the following: 1) Interface requirements. 2) Sequence of operations. 3) Status of submittals. 4) Deliveries. 5) Off-site fabrication. 6) Access. 7) Site utilization. 8) Temporary facilities and controls. 9) Work hours. 10) Hazards and risks. 11) Progress cleaning. 12) Quality and work standards. 13) Change Orders. 3. Reporting: Record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting. 1.8 REQUESTS FOR INTERPRETATION (RFIs) A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified. 1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response. 2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors. B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following: 1. Project name. SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION Page 7 of 9 Dillsboro Hydroelectric Project Decommissioning & Demolition Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 2. Date. 3. Name of Contractor. 4. Name Owner or Owner's representative. 5. RFI number, numbered sequentially. 6. Specification Section number and title and related paragraphs, as appropriate. 7. Drawing number and detail references, as appropriate. 8. Field dimensions and conditions, as appropriate. 9. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time or the Contract Sum, Contractor shall state impact in the RFI. 10. Contractor's signature. 11. Attachments: Include drawings, descriptions, measurements, photos, Product Data, Shop Drawings, and other information necessary to fully describe items needing interpretation. a. Supplementary drawings prepared by Contractor shall include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments. C. Hard-Copy RFIs: Form at end of this Section. Identify each page of attachments with the RFI number and sequential page number. D. Software-Generated RFIs: Software-generated form with substantially the same content as indicated above. 1. Attachments shall be electronic files in Adobe Acrobat PDF format. E. Owner or Owner's representative Action: Owner or Owner's representative will review each RFI, determine action required, and return it. Allow five working days for Engineer's response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day. 1. Owner or Owner's representative action may include a request for additional information, in which case Engineer's time for response will start again. 2. Owner or Owner's representative action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Division 01 Section "Contract Modification Procedures." a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Owner or Owner's representative in writing within five working days of receipt of the RFI response. F. On receipt of Owner or Owner's representative action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and Owner or Owner's representative within five working days if Contractor disagrees with response. G. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log biweekly. Use CSI Log Form 13.213. Include the following: 1. Project name. 2. Name and address of Contractor. SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION Page 8 of 9 Dillsboro Hydroelectric Project Decommissioning & Demolition Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3. Name and address of Owner or Owner's representative. 4. RFI number including RFIs that were dropped and not submitted. 5. RFI description. 6. Date the RFI was submitted. 7. Date Owner or Owner's representative response was received. 8. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate. 9. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate. END OF SECTION 013100 SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION Page 9 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following: 1. Preliminary Construction Schedule. 2. Contractor's Construction Schedule. 3. Submittals Schedule. 4. Daily construction reports. 5. Material location reports. 6. Field condition reports. 7. Special reports. B. Related Sections include the following: 1. Division 01 Section "Project Management and Coordination" for submitting and distributing meeting and conference minutes. 2. Division 01 Section "Photographic Documentation" for submitting construction photographs. 3. Division 01 Section "Submittal Procedures" for submitting schedules and reports. 4. Division 01 Section "Quality Requirements" for submitting a schedule of tests and inspections. 1.3 DEFINITIONS A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources. 1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times. 2. Predecessor Activity: An activity that precedes another activity in the network. 3. Successor Activity: An activity that follows another activity in the network. SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION Page I of 8 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by Owner or Owner's representative. C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project. D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float. E. Event: The starting or ending point of an activity. F. Float: The measure of leeway in starting and completing an activity. 1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date. 2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity. 3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date. G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail. H. Major Area: A story of construction, a separate building, or a similar significant construction element. 1. Milestone: A key or critical point in time for reference or measurement. J. Network Diagram: A graphic diagram of a network schedule, showing activities and activity relationships. K. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled. 1.4 SUBMITTALS A. Qualification Data: For scheduling consultant. B. Submittals Schedule: Submit three copies of schedule. Arrange the following information in a tabular format: 1. Scheduled date for first submittal. 2. Specification Section number and title. 3. Submittal category (action or informational). 4. Name of subcontractor. 5. Description of the Work covered. SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION Page 2 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 6. Scheduled date for Owner or Owner's representative final release or approval. C. Preliminary Construction Schedule: Submit two opaque copies. Approval of cost-loaded preliminary construction schedule will not constitute approval of Schedule of Values for cost-loaded activities. D. Preliminary Network Diagram: Submit two opaque copies, large enough to show entire network for entire construction period. Show logic ties for activities. E. Contractor's Construction Schedule: Submit two opaque copies of initial schedule, large enough to show entire schedule for entire construction period. Submit an electronic copy of schedule, using software indicated, on CD-R, and labeled to comply with requirements for submittals. Include type of schedule (Initial or Updated) and date on label. F. CPM Reports: Concurrent with CPM schedule, submit three copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days. 1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known. 2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known. 3. Total Float Report: List of all activities sorted in ascending order of total float. 4. Earnings Report: Compilation of Contractor's total earnings from the Notice to Proceed until most recent Application for Payment. G. Daily Construction Reports: Submit two copies at weekly intervals. H. Material Location Reports: Submit two copies at monthly intervals. 1. Field Condition Reports: Submit two copies at time of discovery of differing conditions. Special Reports: Submit two copies at time of unusual event. 1.5 QUALITY ASSURANCE A. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of Owner or Owner's representative request. B. Pre-scheduling Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination." Review methods and procedures related to the Preliminary Construction Schedule and Contractor's Construction Schedule, including, but not limited to, the following: SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION Page 3 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Review software limitations and content and format for reports. 2. Verify availability of qualified personnel needed to develop and update schedule. 3. Discuss constraints, including area separations and interim milestones. 4. Review delivery dates for Owner-furnished products. 5. Review schedule for work of Owner's separate contracts. 6. Review time required for review of submittals and re-submittals. 7. Review requirements for tests and inspections by independent testing and inspecting agencies. 8. Review time required for completion and startup procedures. 9. Review and finalize list of construction activities to be included in schedule. 10. Review submittal requirements and procedures. 11. Review procedures for updating schedule. 1.6 COORDINATION A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors. B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports. 1. Secure time commitments for performing critical elements of the Work from parties involved. 2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence. PART 2 - PRODUCTS 2.1 SUBMITTALS SCHEDULE A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, re-submittal, ordering, manufacturing, fabrication, and delivery when establishing dates. 1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule. 2. Initial Submittal: Submit concurrently with preliminary bar-chart schedule. Include submittals required during the first 60 days of construction. List those required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication. a. At Contractor's option, show submittals on the Preliminary Construction Schedule, instead of tabulating them separately. 3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's Construction Schedule. SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION Page 4 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL A. Procedures: Using the procedures contained in AGC's "Construction Planning & Scheduling", prepare a complete construction schedule showing start and end dates, task/activity duration, sequence, logic ties, constraints and milestones. B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order. C. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following: 1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Owner or Owner's representative. 2. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery. 3. Submittal Review Time: Include review and re-submittal times indicated in Division 01 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule. 4. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Owner or Owner's representative administrative procedures necessary for certification of Substantial Completion. D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected. 1. Work under More Than One Contract: Include at least one separate activity for each contract. 2. Work by Owner: Include a separate activity for each portion of the Work performed by Owner. 3. Products Ordered in Advance: Include a separate activity for each product. Include delivery date indicated in Division 01 Section "Summary." Delivery dates indicated stipulate the earliest possible delivery date. 4. Owner-Furnished Products: Include a separate activity for each product. Include delivery date indicated in Division 0l Section "Summary." Delivery dates indicated stipulate the earliest possible delivery date. 5. Work Restrictions: Show the effect of the following items on the schedule: a. Coordination with existing construction. b. Use of premises restrictions. C. Provisions for future construction. d. Seasonal variations. e. Environmental control. SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION Page 5 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 6. Work Stages: Indicate important stages of construction for each major portion of the Work, including, but not limited to, the following: a. Subcontract awards. b. Submittals. C. Purchases. d. Mockups. C. Fabrication. f. Sample testing. g. Deliveries. h. Installation. i. Tests and inspections. j. Adjusting. k. Curing. !. Startup and placement into final use and operation. 7. Area Separations: Identify each major area of construction for each major portion of the Work. E. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion. F. Contract Modifications: For each proposed contract modification, and concurrent with its submission, prepare a time-impact analysis using fragnets as necessary to demonstrate the effect of the proposed change on the overall project schedule. G. Computer Software: Prepare schedules using a program that has been developed specifically to manage construction schedules. 2.3 PRELIMINARY CONSTRUCTION SCHEDULE A. Bar-Chart Schedule: Submit preliminary horizontal bar-chart-type construction schedule within seven days of date established for the Notice to Proceed. B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line. Outline significant construction activities for first 60 days of construction. Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on indicated activities. 2.4 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART) A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 30 days of date established for the Notice to Proceed. Base schedule on the Preliminary Construction Schedule and whatever updating and feedback was received since the start of Project. B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line. SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION Page 6 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 2.5 REPORTS A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site as appropriate. 1. List of subcontractors at Project site. 2. List of separate contractors at Project site. 3. Approximate count of personnel at Project site. 4. Equipment at Project site. 5. Material deliveries. 6. High and low temperatures and general weather conditions. 7. Accidents. 8. Meetings and significant decisions. 9. Unusual events (refer to special reports). 10. Stoppages, delays, shortages, and losses. 11. Meter readings and similar recordings. 12. Emergency procedures. 13. Orders and requests of authorities having jurisdiction. 14. Change Orders received and implemented. 15. Construction Change Directives received and implemented. 16. Services connected and disconnected. 17. Partial Completions. 18. Substantial Completions authorized. B. Material Location Reports: At weekly intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List shall be cumulative, showing materials previously reported plus items recently delivered. Include with list a statement of progress on and delivery dates for materials or items of equipment fabricated or stored away from Project site. C. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents. 2.6 SPECIAL REPORTS A. General: Submit special reports directly to Owner or Owner's representative within one day of an occurrence. Distribute copies of report to parties affected by the occurrence. B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Owner or Owner's representative in advance when these events are known or predictable. SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION Page 7 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 PART 3 - EXECUTION 3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting. 1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting. 2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations. 3. As the Work progresses, indicate Actual Completion percentage for each activity. B. Distribution: Distribute copies of approved schedule to Owner or Owner's representative, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility. 1. Have copies available in Project meeting rooms and/or temporary field offices during scheduled meetings. 2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities. END OF SECTION 013200 SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION Page 8 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION PART 1-GENERAL 1.1 RELATED DOCUMENTS DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes administrative and procedural requirements for the following: 1. Preconstruction photographs. 2. Periodic construction photographs. 3. Final Completion construction photographs. B. Related Sections include the following: 1. Division 01 Section "Submittal Procedures" for submitting photographic documentation. 2. Division 01 Section "Closeout Procedures" for submitting photographic negatives and digital media as Project Record Documents at Project closeout. 3. Division 02 Section "Structure Demolition" for photographic documentation before building demolition operations commence. 4. Division 02 Section "Selective Structure Demolition" for photographic documentation before selective demolition operations commence. 1.3 SUBMITTALS A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same label information as corresponding set of photographs. B. Construction Photographs: Submit two prints of each photographic view within seven days of taking photographs. Format: 8-by-10-inch smooth-surface matte prints on single-weight commercial-grade photographic paper, enclosed back to back in clear plastic sleeves that are punched for standard 3-ring binder. Identification: On back of each print, provide an applied label or rubber-stamped impression with the following information: a. Name of Project. b. Name of Owner or Owner's representative. C. Name of Contractor. d. Date photograph was taken if not date stamped by camera. SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION Page 1 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029. 0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 e. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction. f. Unique sequential identifier. 3. Negatives: Submit a complete set of photographic negatives in individually protected negative sleeves with each submittal of prints as a Project Record Document. Identify negatives with label matching photographic prints. 4. Digital Images: Submit a complete set of digital image electronic files with each submittal of prints as a Project Record Document on CD-ROM. Identify electronic media with date photographs were taken. Submit images that have same aspect ratio as the sensor, uncropped. 1.4 COORDINATION A. Auxiliary Services: Cooperate with photographer and provide auxiliary services requested, including access to Project site and use of temporary facilities, including temporary lighting required to produce clear, well-lit photographs without obscuring shadows. 1.5 USAGE RIGHTS A. Obtain and transfer copyright usage rights to Owner for unlimited reproduction of photographic documentation. 1.6 EXTRA PRINTS A. Negatives: Contractor shall retain photographic negatives for three years after date of Substantial Completion. During this period, Contractor shall fill orders by Owner or Owner's representatives for extra prints. Contractor shall price extra prints at prevailing local commercial prices. B. Extra Prints: If requested by Owner or Owner's representative, Contractor shall prepare extra prints of photographs. Contractor shall distribute these prints directly to designated parties who will pay the costs for extra prints. PART 2 - PRODUCTS 2.1 PHOTOGRAPHIC MEDIA A. Photographic Film: 35 mm, medium speed (ISO 100-200). B. Digital Images: Provide images in uncompressed TIFF format, produced by a digital camera with minimum sensor size of 4.0 megapixels, and at an image resolution of not less than 1024 by 768 pixels. SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION Page 2 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 PART 3 - EXECUTION 3.1 CONSTRUCTION PHOTOGRAPHS A. General: Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted. Maintain key plan with each set of construction photographs that identifies each photographic location. B. Film Images: 1. Date Stamp: Unless otherwise indicated, date and time stamp each photograph as it is being taken so stamp is integral to photograph. 2. Field Office Prints: Retain one set of prints of progress photographs in the field office at Project site, available at all times for reference. Identify photographs same as for those submitted to Owner or Owner's representative. C. Digital Images: Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software. 1. Date and Time: Include date and time in filename for each image. 2. Field Office Images: Maintain one set of images on CD-ROM in the field office at Project site, available at all times for reference. Identify images same as for those submitted to Owner or Owner's representative. D. Preconstruction Photographs: Before commencement of demolition, take color photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Owner or Owner's representative. The amount of photographs will be determined by Owner or Owner's representative. 1. Photographs to show existing conditions adjacent to property before starting the Work. 2. Photographs of existing buildings either on or adjoining property to accurately record physical conditions at start of construction. 3. Take additional photographs as required to record settlement or cracking of adjacent structures, pavements, and improvements. E. Periodic Construction Photographs: Take 10 color photographs monthly, coinciding with the cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last photographs were taken. F. Owner-Directed Construction Photographs: From time to time, Construction Manager will instruct photographer about number and frequency of color photographs and general directions on vantage points. Select actual vantage points and take photographs to show the status of construction and progress since last photographs were taken. G. Time-Lapse Sequence Construction Photographs: Take five color photographs as indicated, to show status of construction and progress since last photographs were taken. SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION Page 3 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 1. Frequency: Take photographs monthly, coinciding with the cutoff date associated with each Application for Payment. 2. Vantage Points: Following suggestions by Owner or Owner's representative and Contractor, photographer to select vantage points. H. Final Completion Construction Photographs: Take eight color photographs after date of Substantial Completion for submission as Project Record Documents. Owner or Owner's representative will direct photographer for desired vantage points. Do not include date stamp. 1. Additional Photographs: Owner or Owner's representative may issue requests for additional photographs, in addition to periodic photographs specified. Additional photographs will be paid for by Change Order and are not included in the Contract Sum. 1. Three days' notice will be given, where feasible. 2. In emergency situations, take additional photographs within 24 hours of request. 3. Circumstances that could require additional photographs include, but are not limited to, the following: a. Special events planned at Project site. b. Immediate follow-up when on-site events result in construction damage or losses. C. Photographs to be taken at fabrication locations away from Project site. These photographs are not subject to unit prices or unit-cost allowances. d. Substantial Completion of a major phase or component of the Work. e. Extra record photographs at time of final acceptance. f. Owner's request for special publicity photographs. END OF SECTION 013233 SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION Page 4 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL L 1 RELATED DOCUMENTS DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals. B. Related Sections include the following: 1. Division 01 Section "Project Management and Coordination" for submitting and distributing meeting and conference minutes and for submitting Coordination Drawings. 2. Division 01 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's Construction Schedule and the Submittals Schedule. 3. Division 01 Section "Photographic Documentation" for submitting construction photographs. 4. Division 01 Section "Quality Requirements" for submitting test and inspection reports. 5. Division 01 Section "Closeout Procedures" for submitting warranties. 6. Division 01 Section "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data. 7. Divisions 02 through 32 Sections for specific requirements for submittals in those Sections. 1.3 DEFINITIONS A. Action Submittals: Written and graphic information that requires Owner or Owner's representative responsive action. B. Informational Submittals: Written information that does not require Owner or Owner's representative responsive action. Submittals may be rejected for not complying with requirements. 1.4 SUBMITTAL PROCEDURES A. General: Electronic copies of CAD Drawings of the Contract Drawings will be provided by Engineer for Contractor's use in preparing submittals. B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. SECTION 013300 - SUBMITTAL PROCEDURES Page I of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. 2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination. a. Owner or Owner's representative reserve the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received. C. Submittals Schedule: Comply with requirements in Division 01 Section "Construction Progress Documentation" for list of submittals and time requirements for scheduled performance of related construction activities. D. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on Owner or Owner's representative receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals. 1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Owner or Owner's representative will advise Contractor when a submittal being processed must be delayed for coordination. 2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal. 3. Re-submittal Review: Allow 15 days for review of each re-submittal. 4. Sequential Review: Where sequential review of submittals by Owner or Owner's representative , or other parties is indicated, allow 21 days for initial review of each submittal. E. Identification: Place a permanent label or title block on each submittal for identification. 1. Indicate name of firm or entity that prepared each submittal on label or title block. 2. Provide a space approximately 6 by 8 inches on label or beside title block to record Contractor's review and approval markings and action taken by Owner or Owner's representative. 3. Include the following information on label for processing and recording action taken: a. Project name. b. Date. C. Name and address of Owner. d. Name and address of Contractor. e. Name and address of subcontractor (as appropriate) f. Name and address of supplier (as appropriate) g. Name of manufacturer. h. Submittal number or other unique identifier, including revision identifier. 1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01). Re- SECTION 013300 - SUBMITTAL PROCEDURES Page 2 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 submittals shall include an alphabetic suffix after another decimal point (e.g., 061000.0l.A). i. Number and title of appropriate Specification Section. j. Drawing number and detail references, as appropriate. k. Location(s) where product is to be installed, as appropriate. 1. Other necessary identification. F. Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract Documents on submittals. G. Additional Copies: Unless additional copies are required for final submittal, and unless Owner or Owner's representative observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal. Submit one copy of submittal to concurrent reviewer in addition to specified number of copies to Owner or Owner's representative. Additional copies submitted for maintenance manuals will be marked with action taken and will be returned. H. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Owner or Owner's representative will return submittals, without review, received from sources other than Contractor. 1. If retaining last option in subparagraph below, insert a sample of the form to be used at end of Section. 2. Transmittal Form: Provide locations on form for the following information: a. Project name. b. Date. C. Destination (To:). d. Source (From:). e. Names of subcontractor, manufacturer, and supplier. f. Category and type of submittal. g. Submittal purpose and description. h. Specification Section number and title. i. Drawing number and detail references, as appropriate. j. Transmittal number. k. Submittal and transmittal distribution record. 1. Remarks. M. Signature of transmitter. On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Owner or Owner's representative on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same label information as related submittal. 1. Re-submittals: Make re-submittals in same form and number of copies as initial submittal. SECTION 013300 - SUBMITTAL PROCEDURES Page 3 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Note date and content of previous submittal. 2. Note date and content of revision in label or title block and clearly indicate extent of revision. 3. Resubmit submittals until they are marked "Approved." J. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms. K. Use for Construction: Use only final submittals with mark indicating "Approved". PART 2 - PRODUCTS 2.1 ACTION SUBMITTALS A. General: Prepare and submit Action Submittals required by individual Specification Sections. 1. Submit electronic submittals directly to extranet specifically established for Project. B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment. 1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data. 2. Mark each copy of each submittal to show which products and options are applicable. 3. Include the following information, as applicable: a. Manufacturer's written recommendations. b. Manufacturer's product specifications. C. Manufacturer's installation instructions. d. Manufacturer's catalog cuts. e. Wiring diagrams showing factory-installed wiring. f. Printed performance curves. g. Operational range diagrams. h. Mill reports. i. Standard product operation and maintenance manuals. j. Compliance with specified referenced standards. k. Testing by recognized testing agency. 1. Application of testing agency labels and seals. 4. Submit Product Data before or concurrent with Samples. 5. Number of Copies: Submit three copies of Product Data, unless otherwise indicated. Engineer, through Owner or Owner's representative, will return two copies. Mark up and retain one returned copy as a Project Record Document. C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data. SECTION 013300 - SUBMITTAL PROCEDURES Page 4 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable: a. Dimensions. b. Identification of products. C. Fabrication and installation drawings. d. Shopwork manufacturing instructions. e. Templates and patterns. f. Schedules. g. Design calculations. h. Compliance with specified standards. i. Notation of dimensions established by field measurement. j. Seal and signature of professional engineer if specified. 2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 24 by 36 inches. 3. Number of Copies: Submit three opaque copies of each submittal, unless copies are required for operation and maintenance manuals. Owner or Owner's representative will retain two copies; remainder will be returned. D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed. 1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package. 2. Identification: Attach label on unexposed side of Samples that includes the following: a. Generic description of Sample. b. Product name and name of manufacturer. C. Sample source. d. Number and title of appropriate Specification Section. 3. Disposition: Maintain sets of approved Samples at Project site, available for quality- control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set. a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use. b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor. 4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available. a. Number of Samples: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Engineer, through Owner or Owner's representative, will return submittal with options selected. SECTION 013300 - SUBMITTAL PROCEDURES Page 5 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 E. Contractor's Construction Schedule: Comply with requirements specified in Division 01 Section "Construction Progress Documentation" for Owner's action. F. Submittals Schedule: Comply with requirements specified in Division 01 Section "Construction Progress Documentation." G. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form: 1. Name, address, and telephone number of entity performing subcontract or supplying products. 2. Number and title of related Specification Section(s) covered by subcontract. 3. Drawing number and detail references, as appropriate, covered by subcontract. 4. Number of Copies: Submit three copies of subcontractor list, unless otherwise indicated. Engineer, through Construction Manager, will return two copies. a. Mark up and retain one returned copy as a Project Record Document. 2.2 INFORMATIONAL SUBMITTALS A. General: Prepare and submit Informational Submittals required by other Specification Sections. 1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated. Owner or Owner's representative will not return copies. 2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. 3. Test and Inspection Reports: Comply with requirements specified in Division 01 Section "Quality Requirements." B. Coordination Drawings: Comply with requirements specified in Division 01 Section "Project Management and Coordination." C. Contractor's Construction Schedule: Comply with requirements specified in Division 01 Section "Construction Progress Documentation." D. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of Engineers and Owners, and other information specified. E. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified. SECTION 013300 - SUBMITTAL PROCEDURES Page 6 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18. 2008 F. Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project. G. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required. H. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents. 1. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents. K. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency. L. Schedule of Tests and Inspections: Comply with requirements specified in Division 01 Section "Quality Requirements." M. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents. N. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers. 0. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer. Include the following, as applicable: 1. Preparation of substrates. 2. Required substrate tolerances. 3. Sequence of installation or erection. 4. Required installation tolerances. 5. Required adjustments. 6. Recommendations for cleaning and protection. SECTION 013300 - SUBMITTAL PROCEDURES Page 7 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18. 2008 P. Manufacturer's Field Reports: Prepare written information documenting factory-authorized service representative's tests and inspections. Include the following, as applicable: 1. Name, address, and telephone number of factory-authorized service representative making report. 2. Statement on condition of substrates and their acceptability for installation of product. 3. Statement that products at Project site comply with requirements. 4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken. 5. Results of operational and other tests and a statement of whether observed performance complies with requirements. 6. Statement whether conditions, products, and installation will affect warranty. 7. Other required items indicated in individual Specification Sections. Q. Insurance Certificates and Bonds: Prepare written information indicating current status of insurance or bonding coverage. Include name of entity covered by insurance or bond, limits of coverage, amounts of deductibles, if any, and term of the coverage. R. Construction Photographs: Comply with requirements specified in Division 01 Section "Photographic Documentation." S. Material Safety Data Sheets (MSDSs): Submit information directly to Owner; do not submit to Engineer. 2.3 DELEGATED DESIGN A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Owner or Owner's representative. B. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit three copies of a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services. SECTION 013300 - SUBMITTAL PROCEDURES Page 8 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC PART 3 - EXECUTION 3.1 CONTRACTOR'S REVIEW DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Owner or Owner's representative. B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents. 3.2 OWNER'S ACTION A. General: Owner or Owner's representative will not review submittals that do not bear Contractor's approval stamp and will return them without action. B. Action Submittals: Owner or Owner's representative will review each submittal, make marks to indicate corrections or modifications required, and return it. Owner or Owner's representative will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows: C. Informational Submittals: Owner or Owner's representative will review each submittal and will not return it, or will return it if it does not comply with requirements. Owner or Owner's representative will forward each submittal to appropriate party. D. Partial submittals are not acceptable, will be considered nonresponsive, and will be returned without review. E. Submittals not required by the Contract Documents may not be reviewed and may be discarded. END OF SECTION 013300 SECTION 013300 - SUBMITTAL PROCEDURES Page 9 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements. 1. Specific quality-assurance and quality-control requirements for individual construction activities are specified in the Sections that specify those activities. Requirements in those Sections may also cover production of standard products. 2. Specified tests, inspections, and related actions do not limit Contractor's other quality- assurance and quality-control procedures that facilitate compliance with the Contract Document requirements. 3. Requirements for Contractor to provide quality-assurance and quality-control services required by Engineer, Owner, or authorities having jurisdiction are not limited by provisions of this Section. C. Related Sections include the following: 1. Division 01 Section "Construction Progress Documentation" for developing a schedule of required tests and inspections. 2. Division 01 Section "Cutting and Patching" for repair and restoration of construction disturbed by testing and inspecting activities. 3. Divisions 02 through 32 Sections for specific test and inspection requirements. 1.3 DEFINITIONS A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements. B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and SECTION 014000 - QUALITY REQUIREMENTS Page 1 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 completed construction comply with requirements. Services do not include contract enforcement activities performed by Engineer or Construction Manager. C. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria. D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards. E. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop. F. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work. G. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency. H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generic name. 1.4 CONFLICTING REQUIREMENTS A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Engineer for a decision before proceeding. B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Owner or Owner's representative for a decision before proceeding. 1.5 SUBMITTALS A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority. SECTION 014000 - QUALITY REQUIREMENTS Page 2 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 B. Schedule of Tests and Inspections: Prepare in tabular form and include the following as appropriate. 1. Specification Section number and title. 2. Description of test and inspection. 3. Identification of applicable standards. 4. Identification of test and inspection methods. 5. Number of tests and inspections required. 6. Time schedule or time span for tests and inspections. 7. Entity responsible for performing tests and inspections. 8. Requirements for obtaining samples. 9. Unique characteristics of each quality-control service. C. Reports: Prepare and submit certified written reports that include the following as appropriate. 1. Date of issue. 2. Project title and number. 3. Name, address, and telephone number of testing agency. 4. Dates and locations of samples and tests or inspections. 5. Names of individuals making tests and inspections. 6. Description of the Work and test and inspection method. 7. Identification of product and Specification Section. 8. Complete test or inspection data. 9. Test and inspection results and an interpretation of test results. 10. Record of temperature and weather conditions at time of sample taking and testing and inspecting. 11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements. 12. Name and signature of laboratory inspector. 13. Recommendations on retesting and re-inspecting. D. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work. 1.6 QUALITY ASSURANCE A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements. B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance. C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. SECTION 014000 - QUALITY REQUIREMENTS Page 3 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or products that are similar to those indicated for this Project in material, design, and extent. F. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated. Requirement for specialists shall not supersede building codes and regulations governing the Work. G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 548; and with additional qualifications specified in individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities. 1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7. 2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory Accreditation Program. H. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project. Preconstruction Testing: Where testing agency is indicated to perform preconstruction testing for compliance with specified requirements for performance and test methods, comply with the following: Contractor responsibilities include the following: a. Provide test specimens representative of proposed products and construction. b. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work. C. Provide sizes and configurations of test assemblies, mockups, and laboratory mockups to adequately demonstrate capability of products to comply with performance requirements. d. Build site-assembled test assemblies and mockups using installers who will perform same tasks for Project. e. Build laboratory mockups at testing facility using personnel, products, and methods of construction indicated for the completed Work. f. When testing is complete, remove test specimens, assemblies, mockups, and laboratory mockups; do not reuse products on Project. SECTION 014000 - QUALITY REQUIREMENTS Page 4 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 2. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Engineer, through Owner or Owner's representative, with copy to Contractor. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents. 1.7 QUALITY CONTROL A. Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not. 1. Where services are indicated as Contractor's responsibility, engage a qualified independent testing agency to perform these quality-control services. 2. Retain first subparagraph below to assure validity of agencies' reports. 3. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed. 4. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service. 5. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor's responsibility. 6. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct. B. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Division 01 Section "Submittal Procedures." C. Retesting/Re-inspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and re-inspecting, for construction that replaced Work that failed to comply with the Contract Documents. D. Testing Agency Responsibilities: Cooperate with Owner or Owner's representative and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections. 1. Notify Owner or Owner's representative, and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services. 2. Determine the location from which test samples will be taken and in which in-situ tests are conducted. 3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements. 4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor. 5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work. SECTION 014000 - QUALITY REQUIREMENTS Page 5 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 6. Do not perform any duties of Contractor. E. Associated Services provided by Contractor: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following: 1. Access to the Work. 2. Incidental labor and facilities necessary to facilitate tests and inspections. 3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples. 4. Facilities for storage and field curing of test samples. 5. Delivery of samples to testing agencies. 6. Preliminary design mix proposed for use for material mixes that require control by testing agency. 7. Security and protection for samples and for testing and inspecting equipment at Project site. F. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting. Schedule times for tests, inspections, obtaining samples, and similar activities. G. Schedule of Tests and Inspections: Prepare a schedule of tests, inspections, and similar quality- control services required by the Contract Documents. Submit schedule within 30 days of date established for the Notice to Proceed. Distribution: Distribute schedule to Owner or Owner's representative, testing agencies, and each party involved in performance of portions of the Work where tests and inspections are required. H. Authority: Tests and inspections performed by the Contractor as part of the Quality Control for the Work shall be in accordance with applicable methods and ASTM Standards. The Owner's Field Quality Assurance Supervisor shall be responsible for assuring the tests and inspections performed to verify that the Work conforms to the Contract Documents, Project procedures and ASTM Standards. The Contractor shall modify testing and inspection procedures when noted by the Field Quality Assurance Supervisor to be in conflict with Contract Documents, Project procedures or ASTM Standards. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 TEST AND INSPECTION LOG A. Prepare a record of tests and inspections. Include the following: SECTION 014000 - QUALITY REQUIREMENTS Page 6 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Date test or inspection was conducted. 2. Description of the Work tested or inspected. 3. Date test or inspection results were transmitted to Engineer. 4. Identification of testing agency or special inspector conducting test or inspection. B. Maintain log at Project site. Post changes and modifications as they occur. Provide access to test and inspection log for Owner or Owner's representative reference during normal working hours. 3.2 REPAIR AND PROTECTION A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes. 1. Provide materials and comply with installation requirements specified in other Specification Sections. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible. 2. Comply with the Contract Document requirements for Division 01 Section "Cutting and Patching." B. Protect construction exposed by or for quality-control service activities. C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services. END OF SECTION 014000 SECTION 014000 - QUALITY REQUIREMENTS Page 7 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC SECTION 014200 - REFERENCES PART 1 - GENERAL 1.1 RELATED DOCUMENTS DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 DEFINITIONS A. General: Basic Contract definitions are included in the Conditions of the Contract. B. "Approved": When used to convey Owner's action on Contractor's submittals, applications, and requests, "approved" is limited to Owner or Owner's representative duties and responsibilities as stated in the Conditions of the Contract. C. "Directed": A command or instruction by Owner or Owner's representative. Other terms including "requested," "authorized," "selected," "required," and "permitted" have the same meaning as "directed." D. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as "indicated." E. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work. F. "Project Site": Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built. 1.3 INDUSTRY STANDARDS A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference. B. Publication Dates: Comply with standards in effect as of date of the Contract Documents unless otherwise indicated. SECTION 014200 - REFERENCES Page 1 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 C. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source. D. Abbreviations and Acronyms for Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the organizations responsible for the standards and regulations in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents. ADAAG Americans with Disabilities Act (ADA) Architectural Barriers Act (ABA) Accessibility Guidelines for Buildings and Facilities Available from Access Board www.access-board.gov CFR Code of Federal Regulations Available from Government Printing Office www.gpoaccess.gov/cfr/index.htnd UFAS Uniform Federal Accessibility Standards Available from Access Board www.access-board.gov 1.4 ABBREVIATIONS AND ACRONYMS (800) 872-2253 (202) 272-0080 (866) 512-1800 (202) 512-1800 (800) 872-2253 (202) 272-0080 A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents. AASHTO American Association of State Highway and Transportation Officials www.transportation.org AATCC American Association of Textile Chemists and Colorists (The) www.aatcc.org ACI ACI International (American Concrete Institute) www.aci-int.org ACPA American Concrete Pipe Association www.concrete-pipe.org (202) 624-5800 (919) 549-8141 (248) 848-3700 (972) 506-7216 SECTION 014200 - REFERENCES Page 2 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 Al Asphalt Institute (859) 288-4960 www.asphaltinstitute.org AIA American Institute of Engineers (The) (800) 242-3837 www.aia.org (202) 626-7300 AISC American Institute of Steel Construction (800) 644-2400 www.aisc.org (312) 670-2400 AISI American Iron and Steel Institute (202) 452-7100 www.steel.org ALCA Associated Landscape Contractors of America (Now PLANET - Professional Landcare Network) ANSI American National Standards Institute (202) 293-8020 www.ansi.org ASCE American Society of Civil Engineers (800) 548-2723 www.asce.org (703) 295-6300 ASME ASME International (800) 843-2763 (The American Society of Mechanical Engineers International) (973) 882-1170 www.asme.org ASTM ASTM International (610) 832-9585 (American Society for Testing and Materials International) www.astm.org AWS American Welding Society (800) 443-9353 www.aws.org (305) 443-9353 AWWA American Water Works Association (800) 926-7337 www.awwa.org (303) 794-7711 CLFMI Chain Link Fence Manufacturers Institute (301) 596-2583 www.chainlinkinfo.org CRSI Concrete Reinforcing Steel Institute (847) 517-1200 www.ersi.org GSI Geosynthetic Institute (610) 522-8440 www.geosynthetic-institute.org ISO International Organization for Standardization 41 22 749 01 11 www.iso.ch Available from ANSI (202) 293-8020 www.ansi.org SECTION 014200 - REFERENCES Page 3 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 NCMA National Concrete Masonry Association (703) 713-1900 www.nema.org NRMCA National Ready Mixed Concrete Association (888) 846-7622 www.nrmca.org (301) 587-1400 SAE SAE International (877) 606-7323 www.sae.org (724) 776-4841 B. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up- to-date as of the date of the Contract Documents. ICC International Code Council www.iccsafe.org (888) 422-7233 (703) 931-4533 C. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents. CE Army Corps of Engineers www.usace.army.mil (828) 271-7980 EPA Environmental Protection Agency (202) 272-0167 www.epa.gov OSHA Occupational Safety & Health Administration (800) 321-6742 www.osha.gov (202) 693-1999 D. State Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents. NCDENR North Carolina Department of Environment and Natural Resources (877) 623-6748 www.enr.state.nc.us NCDOT North Carolina Department of Transportation (877) 368-4968 www.cpuc.ca.gov (919) 733-3109 END OF SECTION 014200 SECTION 014200 - REFERENCES Page 4 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes requirements for temporary utilities, support facilities, and security and protection facilities. B. Related Sections include the following: 1. Division 01 Section "Summary" for limitations on utility interruptions and other work restrictions. 2. Division 01 Section "Submittal Procedures" for procedures for submitting copies of implementation and termination schedule and utility reports. 3. Division 01 Section "Execution" for progress cleaning requirements. 1.3 DEFINITIONS A. Permanent Enclosure: As determined by Owner or Owner's representative, permanent or temporary roofing is complete, insulated, and weathertight; exterior walls are insulated and weathertight; and all openings are closed with permanent construction or substantial temporary closures. 1.4 USE CHARGES A. General: Cost or use charges for temporary facilities shall be included in the Contract Sum. Allow other entities to use temporary services and facilities without cost, including, but not limited to, Owner's construction forces, Engineer, occupants of Project, testing agencies, and authorities having jurisdiction. B. Electric Power Service: Pay electric power service use charges for electricity used by all entities for construction operations. SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS Page 1 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1.5 SUBMITTALS A. Construction Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction personnel. 1.6 QUALITY ASSURANCE A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70. B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits. PART 2 - PRODUCTS 2.1 MATERIALS A. Chain-Link Fencing: Minimum 2-inch, 0.148-inch- thick, galvanized steel, chain-link fabric fencing; minimum 6 feet high with galvanized steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top rails. B. Portable Chain-Link Fencing: Minimum 2-inch, 9-gage, galvanized steel, chain-link fabric fencing; minimum 6 feet high with galvanized steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top and bottom rails. Provide concrete or galvanized steel bases for supporting posts. 2.2 TEMPORARY FACILITIES A. Field Offices, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading. B. Common-Use Field Office: Of sufficient size to accommodate needs of construction personnel, Owner, and Project Design Engineer. Keep office clean and orderly. Furnish and equip offices as follows: 1. Furniture required for Project-site documents including file cabinets, plan tables, plan racks, and bookcases. 2. Conference room of sufficient size to accommodate meetings of 10 individuals. Provide electrical power service and 120-V ac duplex receptacles, with not less than 1 receptacle on each wall. Furnish room with conference table, chairs, and 4-foot- square tack board. 3. Drinking water, private toilet and hand washing/sanitizing facilities. 4. Heating and cooling equipment necessary to maintain a uniform indoor temperature of 68 to 72 deg F. 5. Lighting fixtures capable of maintaining average illumination of 20 fc at desk height. SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS Page 2 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18. 2008 C. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations. Store combustible materials apart from building. 2.3 EQUIPMENT A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures. B. HVAC Equipment: Unless Owner authorizes use of permanent HVAC system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units are prohibited. PART 3 - EXECUTION 3.1 INSTALLATION, GENERAL A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work. 1. Locate facilities to limit site disturbance as specified in Division 01 Section "Summary." B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities. 3.2 TEMPORARY UTILITY INSTALLATION A. General: Install temporary service or connect to existing service. 1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services. B. Sewers and Drainage: Provide temporary utilities to remove effluent lawfully. Connect temporary sewers as directed by authorities having jurisdiction. C. Water Service: Install water service and distribution piping in sizes and pressures adequate for construction. SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS Page 3 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 D. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities. E. Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed. F. Ventilation and Humidity Control: Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption. G. Electric Power Service: Use of Owner's existing electric power service will not be permitted. H. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions. 1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system. 2. Install lighting for Project identification sign. I. Telephone Service: Provide temporary telephone service in common-use facilities for use by all construction personnel. Install at least one telephone line for each field office. 1. Provide additional telephone lines for the following: a. Provide a dedicated telephone line for each facsimile machine and computer in each field office. 2. At each telephone, post a list of important telephone numbers. a. Police and fire departments. b. Ambulance service. C. Contractor's home office. d. Engineer's office. e. Owner's Representative office. f. Principal subcontractors' field and home offices. Provide superintendent with cellular telephone or portable two-way radio for use when away from field office. Electronic Communication Service: Provide temporary electronic communication service, including electronic mail, in common-use facilities. Provide DSL or T-1 line in primary field office. SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS Page 4 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3.3 SUPPORT FACILITIES INSTALLATION A. General: Comply with the following: Provide incombustible construction for offices, shops, and sheds located within construction area or within 30 feet of building lines. Comply with NFPA 241. B. Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas adequate for construction operations. Locate temporary roads and paved areas as indicated on Drawings and/or as Approved by Owner or Owner's representative for construction operations. 1. Provide dust-control treatment that is nonpolluting and non-tracking. Reapply treatment as required to minimize dust. C. Traffic Controls: Comply with requirements of authorities having jurisdiction. 1. Protect existing site improvements to remain including curbs, pavement, and utilities. 2. Maintain access for fire-fighting equipment and access to fire hydrants. D. Parking: Provide temporary driveway entrance and parking areas for construction personnel. E. Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction. Maintain Project site, excavations, and construction free of water. 1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties nor endanger permanent Work or temporary facilities. 2. Remove snow and ice as required to minimize accumulations. F. Project Identification and Temporary Signs: Provide Project identification and other signs as indicated in Contract Documents. Install signs where indicated to inform public and individuals seeking entrance to Project. Unauthorized signs are not permitted. 1. Provide temporary, directional signs for construction personnel and visitors. 2. Maintain and touchup signs so they are legible at all times. G. Waste Disposal Facilities: Comply with requirements specified in Division 01 Section "Construction Waste Management and Disposal." H. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel. 1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities. 3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS Page 5 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects. Comply with work restrictions specified in Division 01 Section "Summary." B. Temporary Erosion and Sedimentation Control: Comply with requirements specified in Division 31 Section "Site Clearing." C. Stormwater Control: Comply with authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains. D. Tree and Plant Protection: Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations. Protect tree root systems from damage, flooding, and erosion. E. Site Enclosure Fence: Before construction operations begin, furnish and install site enclosure fence in a manner that will prevent people and animals from easily entering site except by entrance gates. 1. Extent of Fence: As required to enclose entire Project site or portion determined sufficient to accommodate construction operations. 2. Maintain security by limiting number of keys and restricting distribution to authorized personnel. Provide Owner with one set of keys. F. Security Enclosure and Lockup: Install substantial temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. G. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting. H. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241. 1. Prohibit smoking in construction areas. 2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction. 3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information. 4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed. Match hose size with outlet size and equip with suitable nozzles. SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS Page 6 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 3.5 OPERATION, TERMINATION, AND REMOVAL A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses. B. Maintenance: Maintain facilities in good operating condition until removal. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage. C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion. D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired. 1. Materials and facilities that constitute temporary facilities are property of Contractor. Owner reserves right to take possession of Project identification signs. 2. Remove temporary paving not intended for or acceptable for integration into permanent paving. Where area is intended for landscape development, remove soil and aggregate fill that do not comply with requirements for fill or subsoil. Remove materials contaminated with road oil, asphalt and other petrochemical compounds, and other substances that might impair growth of plant materials or lawns. Repair or replace street paving, curbs, and sidewalks at temporary entrances, as required by authorities having jurisdiction. 3. At Substantial Completion, clean and renovate permanent facilities used during construction period. Comply with final cleaning requirements specified in Division 01 Section "Closeout Procedures." END OF SECTION 015000 SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS Page 7 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No. Review 2 December 18, 2008 SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION PART 1 - GENERAL 1.1 A. 1.2 RELATED DOCUMENTS Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. SUMMARY A. This Section includes the protection and trimming of existing trees that interfere with, or are affected by, execution of the Work, whether temporary or permanent construction. B. Related Sections include the following: 1. Division 01 Section "Summary" for limits placed on Contractor's use of the site. 2. Division 01 Section "Temporary Facilities and Controls" for temporary tree protection. 3. Division 31 Section "Site Clearing" for removal limits of trees, shrubs, and other plantings affected by new construction. 4. Division 31 Section "Earth Moving" for building and utility trench excavation, backfilling, compacting and grading requirements, and soil materials. 1.3 DEFINITIONS A. Tree Protection Zone: Area surrounding individual trees or groups of trees to remain during demolition, and defined by the drip line of individual trees or the perimeter drip line of groups of trees, unless otherwise indicated. 1.4 SUBMITTALS A. Product Data: For each type of product indicated. B. Tree Pruning Schedule: Written schedule from arborist detailing scope and extent of pruning of trees to remain that interfere with or are affected by construction. C. Qualification Data: For tree service firm and arborist. SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION Page 1 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No. Review 2 December 18, 2008 D. Certification: From arborist, certifying that trees indicated to remain have been protected during construction according to recognized standards and that trees were promptly and properly treated and repaired when damaged. E. Maintenance Recommendations: From arborist, for care and protection of trees affected by demolition during and after completing the Work. t.5 QUALITY ASSURANCE A. Tree Service Firm Qualifications: An experienced tree service firm that has successfully completed tree protection and trimming work similar to that required for this Project and that will assign an experienced, qualified arborist to Project site during execution of tree protection and trimming. B. Arborist Qualifications: An arborist certified by ISA or licensed in the jurisdiction where Project is located. C. Tree Pruning Standard: Comply with ANSI A300 (Part 1), "Tree, Shrub, and Other Woody Plant Maintenance--Standard Practices (Pruning)." D. Preinstallation Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination." 1. Before tree protection and trimming operations begin, meet with representatives of authorities having jurisdiction, Owner, Engineer, consultants, and other concerned entities to review tree protection and trimming procedures and responsibilities. PART 2 - PRODUCTS 2.1 MATERIALS A. Drainage Fill: Selected crushed stone, or crushed or uncrushed gravel, washed, ASTM D 448, Size 24, with 90 to 100 percent passing a 2-1/2-inch sieve and not more than 10 percent passing a 3/4-inch sieve. B. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 2 inches in diameter; and free of weeds, roots, and toxic and other nonsoil materials. 1. Obtain topsoil only from well-drained sites where topsoil is 4 inches deep or more; do not obtain from bogs or marshes. SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION Page 2 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No. Review 2 Duke Energy Carolinas, LLC December 18, 2008 C. Filter Fabric: Manufacturer's standard, nonwoven, pervious, geotextile fabric of polypropylene, nylon, or polyester fibers. D. Chain-Link Fence: Metallic-coated steel chain-link fence fabric of 0.120-inch- diameter wire; a minimum of 48 inches high; with 1.9-inch- diameter line posts; 2-3/8- inch- diameter terminal and corner posts; 1-5/8-inch- diameter top rail; and 0.177-inch- diameter bottom tension wire; with tie wires, hog ring ties, and other accessories for a complete fence system. E. Organic Mulch: Wood and bark chips, free of deleterious materials. PART 3 - EXECUTION 3.1 PREPARATION A. Temporary Fencing: Install temporary fencing around tree protection zones to protect remaining trees and vegetation from construction damage. Maintain temporary fence and remove when construction is complete. 1. Install chain-link fence according to ASTM F 567 and manufacturer's written instructions. B. Protect tree root systems from damage caused by runoff or spillage of noxious materials while mixing, placing, or storing construction materials. Protect root systems from ponding, eroding, or excessive wetting caused by dewatering operations. C. Mulch areas inside tree protection zones and within drip line of trees to remain and other areas indicated. 1. Apply 2-inch average thickness of organic mulch. Do not place mulch within 6 inches of tree trunks. D. Do not store construction materials, debris, or excavated material inside tree protection zones. Do not permit vehicles or foot traffic within tree protection zones; prevent soil compaction over root systems. E. Maintain tree protection zones free of weeds and trash. F. Do not allow fires within tree protection zones. 3.2 EXCAVATION A. Install shoring or other protective support systems to minimize sloping or benching of excavations. SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION Page 3 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No. Review 2 December 18, 2008 B. Do not excavate within tree protection zones, unless otherwise indicated. C. Where excavation for new construction is required within tree protection zones, hand clear and excavate to minimize damage to root systems. Use narrow-tine spading forks and comb soil to expose roots. 1. Redirect roots in backfill areas where possible. If encountering large, main lateral roots, expose roots beyond excavation limits as required to bend and redirect them without breaking. If encountered immediately adjacent to location of new construction and redirection is not practical, cut roots approximately 3 inches back from new construction. 2. Do not allow exposed roots to dry out before placing permanent backfill. Provide temporary earth cover or pack with peat moss and wrap with burlap. Water and maintain in a moist condition. Temporarily support and protect roots from damage until they are permanently relocated and covered with soil. D. Where utility trenches are required within tree protection zones, tunnel under or around roots by drilling, auger boring, pipe jacking, or digging by hand. 1. Root Pruning: Do not cut main lateral roots or taproots; cut only smaller roots that interfere with installation of utilities. Cut roots with sharp pruning instruments; do not break or chop. 3.3 REGRADING A. Grade Lowering: Where new finish grade is indicated below existing grade around trees, slope grade beyond tree protection zones. Maintain existing grades within tree protection zones. B. Grade Lowering: Where new finish grade is indicated below existing grade around trees, slope grade away from trees as recommended by arborist, unless otherwise indicated. 1. Root Pruning: Prune tree roots exposed during grade lowering. Do not cut main lateral roots or taproots; cut only smaller roots. Cut roots with sharp pruning instruments; do not break or chop. C. Minor Fill: Where existing grade is 6 inches or less below elevation of finish grade, fill with topsoil. Place topsoil in a single uncompacted layer and hand grade to required finish elevations. D. Moderate Fill: Where existing grade is more than 6 inches but less than 12 inches below elevation of finish grade, place drainage fill, filter fabric, and topsoil on existing grade as follows: SECTION 015639 -TEMPORARY TREE AND PLANT PROTECTION Page 4 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No. Review 2 December 18, 2008 1. Carefully place drainage fill against tree trunk approximately 2 inches above elevation of finish grade and extend not less than 18 inches from tree trunk on all sides. For balance of area within drip-line perimeter, place drainage fill up to 6 inches below elevation of grade. 2. Place filter fabric with edges overlapping 6 inches minimum. 3. Place fill layer of topsoil to finish grade. Do not compact drainage fill or topsoil. Hand grade to required finish elevations. 3.4 TREE PRUNING A. Prune trees to remain that are affected by temporary and permanent construction. B. Prune trees to remain to compensate for root loss caused by damaging or cutting root system. Provide subsequent maintenance during Contract period as recommended by arborist. C. Pruning Standards: Prune trees according to ANSI A300 (Part 1). D. Retain subparagraph below if applicable, and select one or more options. Identify on Drawings individual trees or site zones requiring multiple types of pruning. Augment or replace with arborist's report if an arborist is retained by Owner. See Evaluations for a discussion of pruning. Add detailed instructions for removing specific branches, or branches of a specific minimum or maximum diameter, if required. E. Retain subparagraph below if applicable. If retaining, select one or more of four options, which are identified in ANSI A300 (Part 1). Coordinate with options selected from subparagraph above. F. Cut branches with sharp pruning instruments; do not break or chop. G. Chip removed tree branches and dispose of off-site. 3.5 TREE REPAIR AND REPLACEMENT A. Promptly repair trees damaged by construction operations within 24 hours. Treat damaged trunks, limbs, and roots according to arborist's written instructions. B. Remove and replace trees indicated to remain that die or are damaged during construction operations that arborist determines are incapable of restoring to normal growth pattern. 1. Provide new trees of same size and species as those being replaced. 2. Provide new trees of 6-inch caliper size and of a species selected by Engineer when damaged trees more than 6 inches in caliper size, measured 12 inches above grade, are required to be replaced. SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION Page 5 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No. Review 2 December 18, 2008 C. Aerate surface soil, compacted during construction, 10 feet beyond drip line and no closer than 36 inches to tree trunk. Drill 2-inch- diameter holes a minimum of 12 inches deep at 24 inches o.c. Backfill holes with an equal mix of augered soil and sand. 3.6 DISPOSAL OF WASTE MATERIALS A. Burning is not permitted. B. Disposal: Remove excess excavated material and displaced trees from Owner's property. END OF SECTION 015639 SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION Page 6 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 017300 - EXECUTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following: 1. Construction layout. 2. Field engineering and surveying. 3. General installation of products. 4. Coordination of Owner-installed items. 5. Progress cleaning. 6. Starting and adjusting. 7. Protection of installed construction. 8. Correction of the Work. B. Related Sections include the following: 1. Division 01 Section "Project Management and Coordination" for procedures for coordinating field engineering with other construction activities. 2. Division 01 Section "Submittal Procedures" for submitting surveys. 3. Division 01 Section "Cutting and Patching" for procedural requirements for cutting and patching necessary for the installation or performance of other components of the Work. 4. Division 01 Section "Closeout Procedures" for submitting final property survey with Project Record Documents, recording of Owner-accepted deviations from indicated lines and levels, and final cleaning. 1.3 SUBMITTALS A. Qualification Data: For land surveyor. B. Certificates: Submit certificate signed by land surveyor certifying that location and elevation of improvements comply with requirements. C. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept hazardous materials, for hazardous waste disposal. D. Certified Surveys: Submit two copies signed by land surveyor. SECTION 017300 - EXECUTION Page 1 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 E. Final Property Survey: Submit 10 copies showing the Work performed and record survey data. 1.4 QUALITY ASSURANCE A. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing land-surveying services of the kind indicated. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 EXAMINATION A. Existing Conditions: The existence and location of site improvements, utilities, and other construction indicated as existing are not guaranteed. Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work. Before construction, verify the location and points of connection of utility services. B. Existing Utilities: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities and other construction affecting the Work. 1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, and water-service piping; and underground electrical services. 2. Furnish location data for work related to Project that must be performed by public utilities serving Project site. C. Acceptance of Conditions: Examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations. 1. Written Report: Where a written report listing conditions detrimental to performance of the Work is required by other Sections, include the following: a. Description of the Work. b. List of detrimental conditions, including substrates. C. List of unacceptable installation tolerances. d. Recommended corrections. 2. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers. SECTION 017300 - EXECUTION Page 2 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions. 3.2 PREPARATION A. Existing Utility Information: Furnish information to Owner that is necessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction. Coordinate with authorities having jurisdiction. B. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work. C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings. D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to Engineer. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents. 3.3 CONSTRUCTION LAYOUT A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify Construction Manager promptly. B. General: Engage a land surveyor to lay out the Work using accepted surveying practices. I. Establish benchmarks and control points to set lines and levels at each story of construction and elsewhere as needed to locate each element of Project. 2. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions. 3. Inform installers of lines and levels to which they must comply. 4. Check the location, level and plumb, of every major element as the Work progresses. 5. Notify Owner or Owner's representative when deviations from required lines and levels exceed allowable tolerances. 6. Close site surveys with an error of closure equal to or less than the standard established by authorities having jurisdiction. C. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and invert elevations. D. Building Lines and Levels: Locate and lay out control lines and levels for structures, building foundations, column grids, and floor levels, including those required for mechanical and SECTION 017300 - EXECUTION Page 3 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 electrical work. Transfer survey markings and elevations for use with control lines and levels. Level foundations and piers from two or more locations. E. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by Owner or Owner's representative. 3.4 FIELD ENGINEERING A. Identification: Owner will identify existing benchmarks, control points, and property corners. B. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations. 1. Do not change or relocate existing benchmarks or control points without prior written approval of Owner or Owner's representative. Report lost or destroyed permanent benchmarks or control points promptly. Report the need to relocate permanent benchmarks or control points to Engineer and Construction Manager before proceeding. 2. Replace lost or destroyed permanent benchmarks and control points promptly. Base replacements on the original survey control points. C. Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark. Record benchmark locations, with horizontal and vertical data, on Project Record Documents. Where the actual location or elevation of layout points cannot be marked, provide temporary reference points sufficient to locate the Work. Remove temporary reference points when no longer needed. Restore marked construction to its original condition. D. Certified Survey: On completion of foundation walls, major site improvements, and other work requiring field-engineering services, prepare a certified survey showing dimensions, locations, angles, and elevations of construction and sitework. E. Final Property Survey: Prepare a final property survey showing significant features (real property) for Project. Include on the survey a certification, signed by land surveyor, that principal metes, bounds, lines, and levels of Project are accurately positioned as shown on the survey. 1. Show boundary lines, monuments, streets, site improvements and utilities, existing improvements and significant vegetation, adjoining properties, acreage, grade contours, and the distance and bearing from a site corner to a legal point. 2. Recording: At Substantial Completion, have the final property survey recorded by or with authorities having jurisdiction as the official "property survey." SECTION 017300 - EXECUTION Page 4 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18. 2008 3.5 INSTALLATION A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated. 1. Make vertical work plumb and make horizontal work level. 2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement. 3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated. B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated. C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion. D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy. E. Tools and Equipment: Do not use tools or equipment that produces harmful noise levels. F. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements. G. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work. 1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by Owner or Owner's representative. 2. Allow for building movement, including thermal expansion and contraction. 3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation. H. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints. 1. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous. 3.6 OWNER-INSTALLED ITEMS A. Site Access: Provide access to Project site for Owner's construction forces. B. Coordination: Coordinate construction and operations of the Work with work performed by Owner's construction forces. SECTION 017300 - EXECUTION Page 5 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Construction Schedule: Inform Owner of Contractor's preferred construction schedule for Owner's portion of the Work. Adjust construction schedule based on a mutually agreeable timetable. Notify Owner if changes to schedule are required due to differences in actual construction progress. 2. Pre-installation Conferences: Include Owner's construction forces at pre-installation conferences covering portions of the Work that are to receive Owner's work. Attend pre- installation conferences conducted by Owner's construction forces if portions of the Work depend on Owner's construction. 3.7 PROGRESS CLEANING A. General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully. 1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris. 2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F. 3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations. B. Site: Maintain Project site free of waste materials and debris. C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work. 1. Remove liquid spills promptly. 2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate. D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces. E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space. F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion. G. Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted. H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion. SECTION 017300 - EXECUTION Page 6 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 1. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects. J. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. 3.8 STARTING AND ADJUSTING A. Start equipment and operating components to confirm proper operation. Remove malfunctioning units, replace with new units, and retest. B. Adjust operating components for proper operation without binding. Adjust equipment for proper operation. C. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. D. Manufacturer's Field Service: If a factory-authorized service representative is required to inspect field-assembled components and equipment installation, comply with qualification requirements in Division 01 Section "Quality Requirements." 3.9 PROTECTION OF INSTALLED CONSTRUCTION A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion. B. Comply with manufacturer's written instructions for temperature and relative humidity. 3.10 CORRECTION OF THE WORK A. Repair or remove and replace defective construction. Restore damaged substrates and finishes. Comply with requirements in Division 01 Section "Cutting and Patching." 1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. B. Restore permanent facilities used during construction to their specified condition. C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair. END OF SECTION 017300 SECTION 017300 - EXECUTION Page 7 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 017329 - CUTTING AND PATCHING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes procedural requirements for cutting and patching. B. Related Sections include the following: 1. Division 02 Section "Selective Structure Demolition" for demolition of selected portions of the building. 2. Divisions 02 through 32 Sections for specific requirements and limitations applicable to cutting and patching individual parts of the Work. 1.3 DEFINITIONS A. Cutting: Removal of in-place construction necessary to permit installation or performance of other Work. B. Patching: Fitting and repair work required to restore surfaces to original conditions after installation of other Work. 1.4 SUBMITTALS A. Cutting and Patching Proposal: Submit a proposal describing procedures at least 10 days before the time cutting and patching will be performed, requesting approval to proceed. Include the following information: 1. Extent: Describe cutting and patching, show how they will be performed, and indicate why they cannot be avoided. 2. Changes to In-Place Construction: Describe anticipated results. Include changes to structural elements and operating components as well as changes in building's appearance and other significant visual elements. 3. Products: List products to be used and firms or entities that will perform the Work. 4. Dates: Indicate when cutting and patching will be performed. 5. Utility Services and Mechanical/Electrical Systems: List services/systems that cutting and patching procedures will disturb or affect. List services/systems that will be SECTION 017329 - CUTTING AND PATCHING Page 1 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 relocated and those that will be temporarily out of service. Indicate how long services/systems will be disrupted. 6. Structural Elements: Where cutting and patching involve adding reinforcement to structural elements, submit details and engineering calculations showing integration of reinforcement with original structure. 7. Owner's Approval: Obtain approval of cutting and patching proposal before cutting and patching. Approval does not waive right to later require removal and replacement of unsatisfactory work. 1.5 QUALITY ASSURANCE A. Structural Elements: Do not cut and patch structural elements in a manner that could change their load-carrying capacity or load-deflection ratio. B. Miscellaneous Elements: Do not cut and patch miscellaneous elements or related components in a manner that could change their load-carrying capacity that results in reducing their capacity to perform as intended, or that result in increased maintenance or decreased operational life or safety. C. Visual Requirements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would, in Engineer's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner. D. Cutting and Patching Conference: Before proceeding, meet at Project site with parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding. 1.6 WARRANTY A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during cutting and patching operations, by methods and with materials so as not to void existing warranties. PART 2 - PRODUCTS 2.1 MATERIALS A. General: Comply with requirements specified in other Sections. B. In-Place Materials: Use materials identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible. SECTION 017329 - CUTTING AND PATCHING Page 2 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. If identical materials are unavailable or cannot be used, use materials that, when installed, will match the visual and functional performance of in-place materials. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed. 1. Compatibility: Before patching, verify compatibility with and suitability of substrates, including compatibility with in-place finishes or primers. 2. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected. 3.2 PREPARATION A. Temporary Support: Provide temporary support of Work to be cut. B. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations. C. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas. D. Existing Utility Services: Where existing services are required to be removed, relocated, or abandoned, bypass such services before cutting to minimize interruption to occupied areas. 3.3 PERFORMANCE A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay. 1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition. B. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations. 1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size SECTION 017329 - CUTTING AND PATCHING Page 3 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use. 2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces. 3. Concrete, Stone, and Masonry Elements: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill. 4. Proceed with patching after construction operations requiring cutting are complete. C. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections. 1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation. 2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing. 3. Insert specific refinishing requirements for floors, walls, and ceilings. Revise subparagraph and associated subparagraph below to suit Project. 4. Floors and Walls: Where walls that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance. 5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition. D. Cleaning: Clean areas and spaces where cutting and patching are performed. Completely remove paint, mortar, oils, putty, and similar materials. END OF SECTION 017329 SECTION 017329 - CUTTING AND PATCHING Page 4 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1-GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes administrative and procedural requirements for the following: 1. Salvaging nonhazardous demolition and construction waste. 2. Recycling nonhazardous demolition and construction waste. 3. Disposing of nonhazardous demolition and construction waste. B. Related Sections include the following: 1. Division 01 Section "Temporary Facilities and Controls" for environmental-protection measures during construction. 2. Division 02 Section "Structure Demolition" for disposition of waste resulting from demolition of buildings, structures, and site improvements. 3. Division 02 Section "Selective Structure Demolition" for disposition of waste resulting from partial demolition of buildings, structures, and site improvements. 4. Division 31 Section "Site Clearing" for disposition of waste resulting from site clearing and removal of above- and below-grade improvements. 1.3 DEFINITIONS A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging. B. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations. C. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction. D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse. E. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility. SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL Page 1 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 F. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work. 1.4 PERFORMANCE REQUIREMENTS A. General: Develop waste management plan that results in end-of-Project rates for salvage/recycling of at least 50 percent by weight of total waste generated by the Work. B. Salvage/Recycle Requirements: Owner's goal is to salvage and recycle as much nonhazardous demolition waste as possible, including the following types of materials. a. Asphaltic concrete paving. b. Concrete. C. Concrete reinforcing steel. d. Wood studs. e. Wood joists. f. Structural and miscellaneous steel. g. Equipment. h. Piping, i. Valves. j. Mechanical equipment. k. Electrical conduit. 1. Copper wiring. M. Ballasts. n. Electrical devices. o. Switchgear and panelboards. p. Transformers. 1.5 SUBMITTALS A. Waste Management Plan: Submit 3 copies of plan within 7 days of date established for the Notice to Proceed. B. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices. C. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices. D. Qualification Data: For Waste Management Coordinator. 1.6 QUALITY ASSURANCE A. Regulatory Requirements: Comply with hauling and disposal regulations of authorities having jurisdiction. SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL Page 2 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18. 2008 B. Waste Management Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination." Review methods and procedures related to waste management including, but not limited to, the following: 1. Review and discuss waste management plan including responsibilities of Waste Management Coordinator. 2. Review requirements for documenting quantities of each type of waste and its disposition. 3. Review and finalize procedures for materials separation and verify availability of containers and bins needed to avoid delays. 4. Review procedures for periodic waste collection and transportation to recycling and disposal facilities. 5. Review waste management requirements for each trade. 1.7 WASTE MANAGEMENT PLAN A. General: Develop plan consisting of waste identification, waste reduction work plan, and cost/revenue analysis. Include separate sections in plan for demolition and construction waste. Indicate quantities by weight or volume, but use same units of measure throughout waste management plan. B. Waste Identification: Indicate anticipated types and quantities of demolition and construction waste generated by the Work. Include estimated quantities and assumptions for estimates. C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include points of waste generation, total quantity of each type of waste, quantity for each means of recovery, and handling and transportation procedures. 1. Salvaged Materials for Reuse: For materials that will be salvaged and reused in this Project, describe methods for preparing salvaged materials before incorporation into the Work. 2. Salvaged Materials for Sale: For materials that will be sold to individuals and organizations, include list of their names, addresses, and telephone numbers. 3. Salvaged Materials for Donation: For materials that will be donated to individuals and organizations, include list of their names, addresses, and telephone numbers. 4. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers. 5. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility. 6. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location on Project site where materials separation will be located. D. Cost/Revenue Analysis: Indicate total cost of waste disposal as if there was no waste management plan and net additional cost or net savings resulting from implementing waste management plan. Include the following: 1. Total quantity of waste. SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL Page 3 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 2. Estimated cost of disposal (cost per unit). Include hauling and tipping fees and cost of collection containers for each type of waste. 3. Total cost of disposal (with no waste management). 4. Revenue from salvaged materials. 5. Revenue from recycled materials. 6. Savings in hauling and tipping fees by donating materials. 7. Savings in hauling and tipping fees that are avoided. 8. Handling and transportation costs. Include cost of collection containers for each type of waste. 9. Net additional cost or net savings from waste management plan. E. Forms: Prepare waste management plan on forms included at end of Part 3. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 PLAN IMPLEMENTATION A. General: Implement waste management plan as approved by Owner. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract. 1. Comply with Division 01 Section "Temporary Facilities and Controls" for operation, termination, and removal requirements. B. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work occurring at Project site. 1. Distribute waste management plan to everyone concerned within three days of submittal return. 2. Distribute waste management plan to entities when they first begin work on-site. Review plan procedures and locations established for salvage, recycling, and disposal. C. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities. 1. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged, recycled, reused, donated, and sold. 2. Comply with Division 01 Section "Temporary Facilities and Controls" for controlling dust and dirt, environmental protection, and noise control. 3.2 SALVAGING DEMOLITION WASTE A. Salvaged Items for Reuse in the Work: SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL Page 4 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Clean salvaged items. 2. Pack or crate items after cleaning. Identify contents of containers. 3. Store items in a secure area until installation. 4. Protect items from damage during transport and storage. 5. Install salvaged items to comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make items functional for use indicated. B. Salvaged Items for Sale and Donation: Not permitted on Project site. C. Salvaged Items for Owner's Use: 1. Clean salvaged items. 2. Pack or crate items after cleaning. Identify contents of containers. 3. Store items in a secure area until delivery to Owner. 4. Transport items to Owner's storage area designated by Owner. 5. Protect items from damage during transport and storage. 3.3 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL A. General: Recycle paper and beverage containers used by on-site workers. B. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Owner. C. Procedures: Separate recyclable waste from other waste materials, trash, and debris. Separate recyclable waste by type at Project site to the maximum extent practical. 1. Provide appropriately marked containers or bins for controlling recyclable waste until they are removed from Project site. Include list of acceptable and unacceptable materials at each container and bin. a. Inspect containers and bins for contamination and remove contaminated materials if found. 2. Stockpile processed materials on-site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust. 3. Stockpile materials away from construction area. Do not store within drip line of remaining trees. 4. Store components off the ground and protect from the weather. 5. Remove recyclable waste off Owner's property and transport to recycling receiver or processor. 3.4 RECYCLING DEMOLITION WASTE A. Concrete: Remove reinforcement and other metals from concrete and sort with other metals as directed by Owner. SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL Page 5 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 B. Wood Materials: Sort and stack members according to size, type, and length. Separate lumber, engineered wood products, panel products, and treated wood materials. C. Metals: Separate metals by type. 1. Structural Steel: Stack members according to size, type of member, and length. 2. Remove and dispose of bolts, nuts, washers, and other rough hardware. D. Equipment: Drain tanks, piping, and fixtures. Seal openings with caps or plugs. Protect equipment from exposure to weather. E. Piping: Reduce piping to straight lengths and store by type and size. Separate supports, hangers, valves, sprinklers, and other components by type and size. F. Electrical Devices: Separate switches, receptacles, switchgear, transformers, meters, panelboards, circuit breakers, and other devices by type. G. Conduit: Reduce conduit to straight lengths and store by type and size. 3.5 RECYCLING CONSTRUCTION WASTE A. Packaging: 1. Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location. 2. Polystyrene Packaging: Separate and bag materials. 3. Pallets: As much as possible, require deliveries using pallets to remove pallets from Project site. For pallets that remain on-site, break down pallets into component wood pieces and comply with requirements for recycling wood. 4. Crates: Break down crates into component wood pieces and comply with requirements for recycling wood. 3.6 DISPOSAL OF WASTE A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction. 1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site. 2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas. B. Burning: Do not burn waste materials. C. Disposal: Transport waste materials off Owner's property and legally dispose of them. SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL Page 6 of 7 Dilbboro Flvelroeleciric Projert Decommissioning & Removal Dillsbvro, !North Carolina Dicke f'trergy Carolinas. LLC END OF SECTION 017419 DTA Specification No. 024.0029.0000 Revision No.: Reviest, 2 Derensber 18, 2008 SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL Page 7 cif 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 017700 - CLOSEOUT PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following: 1. Inspection procedures. 2. Warranties. 3. Final cleaning. B. Related Sections include the following: 1. Division 01 Section "Photographic Documentation" for submitting Final Completion construction photographs and negatives. 2. Division 01 Section "Execution" for progress cleaning of Project site. 3. Division 01 Section "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data. 4. Divisions 02 through 32 Sections for specific closeout and special cleaning requirements for the Work in those Sections. 1.3 SUBSTANTIAL COMPLETION A. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request. 1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete. 2. Advise Owner of pending insurance changeover requirements. 3. Submit specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents. 4. Obtain and submit releases permitting Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases. 5. Prepare and submit Project Record Documents, operation and maintenance manuals, Final Completion construction photographs, damage or settlement surveys, property surveys, and similar final record information. SECTION 017700 - CLOSEOUT PROCEDURES Page 1 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 6. Deliver tools, spare parts, extra materials, and similar items to location designated by Owner. Label with manufacturer's name and model number where applicable. 7. Submit test/adjust/balance records. 8. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements. 9. Complete final cleaning requirements, including touchup painting. 10. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects. B. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, Owner or Owner's representative will either proceed with inspection or notify Contractor of unfulfilled requirements. Owner or Owner's representative will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Owner or Owner's representative, that must be completed or corrected before certificate will be issued. 1. Re-inspection: Request re-inspection when the as incomplete is completed or corrected. 2. Results of completed inspection will form Completion. 1.4 FINAL COMPLETION Work identified in previous inspections the basis of requirements for Final A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following: 1. Submit certified copy of Owner's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Owner or Owner's representative. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance. 2. Submit evidence of final, continuing insurance coverage complying with insurance requirements. B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, Engineer and Construction Manager will either proceed with inspection or notify Contractor of unfulfilled requirements. Owner or Owner's representative will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued. Re-inspection: Request re-inspection when the Work identified in previous inspections as incomplete is completed or corrected. 1.5 LIST OF INCOMPLETE ITEMS (PUNCH LIST) A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction. 1. Include the following information at the top of each page: SECTION 017700 - CLOSEOUT PROCEDURES Page 2 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18. 2008 a. Project name. b. Date. C. Name of Owner's Representative. d. Name of Contractor. e. Page number. 1.6 WARRANTIES A. Submittal Time: Submit written warranties on request of Engineer for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated. B. Partial Occupancy: Submit properly executed warranties within 15 days of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor. C. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual. 1. Bind warranties and bonds in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-1l-inch paper. 2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer. 3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor. D. Provide additional copies of each warranty to include in operation and maintenance manuals. PART 2 - PRODUCTS 2.1 MATERIALS A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces. SECTION 017700 - CLOSEOUT PROCEDURES Page 3 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC PART 3 - EXECUTION 3.1 FINAL CLEANING DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations. B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. 1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project: a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances. b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits. C. Rake grounds that are neither planted nor paved to a smooth, even-textured surface. d. Remove tools, construction equipment, machinery, and surplus material from Project site. e. Remove snow and ice to provide safe access to building. f. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition. g. Touch up and otherwise repair and restore marred, exposed finishes and surfaces. Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration. h. Leave Project clean. C. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Owner's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully. END OF SECTION 017700 SECTION 017700 - CLOSEOUT PROCEDURES Page 4 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 017839 - PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and other Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes administrative and procedural requirements for Project Record Documents, including the following: 1. Record Drawings. 2. Record Specifications. 3. Record Product Data. B. Related Sections include the following: 1. Division 01 Section "Closeout Procedures" for general closeout procedures. 2. Divisions 02 through 32 Sections for specific requirements for Project Record Documents of the Work in those Sections. 1.3 SUBMITTALS A. Record Drawings: Comply with the following: 1. Number of Copies: Submit one set of marked-up Record Prints. 2. Number of Copies: Submit copies of Record Drawings as follows: a. Initial Submittal: Submit one set of plots from corrected Record CAD Drawings and one set of marked-up Record Prints. Engineer will initial and date each plot and mark whether general scope of changes, additional information recorded, and quality of drafting are acceptable. Engineer will return plots and prints for organizing into sets, printing, binding, and final submittal. b. Final Submittal: Submit one set of marked-up Record Prints, one set of Record Transparencies, and three copies printed from Record Transparencies. Print each Drawing, whether or not changes and additional information were recorded. C. Final Submittal: Submit one set of marked-up Record Prints, one set of Record CAD Drawing files, one set of Record CAD Drawing plots, and three copies printed from record plots. Plot and print each Drawing, whether or not changes and additional information were recorded. SECTION 017839 - PROJECT RECORD DOCUMENTS Page 1 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 B. Record Specifications: Submit one copy of Project's Specifications, including addenda and contract modifications. C. Record Product Data: Submit one copy of each Product Data submittal. Where Record Product Data is required as part of operation and maintenance manuals, submit marked-up Product Data as an insert in manual instead of submittal as Record Product Data. PART 2-PRODUCTS 2.1 RECORD DRAWINGS A. Record Prints: Maintain one set of blue- or black-line white prints of the Contract Drawings and Shop Drawings. 1. Preparation: Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints. a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later. b. Accurately record information in an understandable drawing technique. C. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations. 2. Content: Types of items requiring marking include, but are not limited to, the following: a. Dimensional changes to Drawings. b. Revisions to details shown on Drawings. C. Locations and depths of underground utilities. d. Changes made by Change Order or Construction Change Directive. e. Changes made following Engineer's written orders. f. Details not on the original Contract Drawings. g. Field records for variable and concealed conditions. h. Record information on the Work that is shown only schematically. 3. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross-reference on the Contract Drawings. 4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location. 5. Mark important additional information that was either shown schematically or omitted from original Drawings. 6. Note Construction Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable. SECTION 017839 - PROJECT RECORD DOCUMENTS Page 2 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 B. Format: Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. 1. Record Prints: Organize Record Prints and newly prepared Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets. 2. Record CAD Drawings: Organize CAD information into separate electronic files that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each CAD file. 3. Identification: As follows: a. Project name. b. Date. C. Designation "PROJECT RECORD DRAWINGS." d. Name of Engineer and Owner. e. Name of Contractor. 2.2 RECORD SPECIFICATIONS A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications. 1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later. 2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected. 3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made. 4. For each principal product, indicate whether Record Product Data has been submitted in operation and maintenance manuals instead of submitted as Record Product Data. 2.3 RECORD PRODUCT DATA A. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal. 1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later. 2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation. 2.4 MISCELLANEOUS RECORD SUBMITTALS A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference. SECTION 017839 - PROJECT RECORD DOCUMENTS Page 3 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 PART 3 - EXECUTION 3.1 RECORDING AND MAINTENANCE A. Recording: Maintain one copy of each submittal during the construction period for Project Record Document purposes. Post changes and modifications to Project Record Documents as they occur; do not wait until the end of Project. B, Maintenance of Record Documents and Samples: Store Record Documents and Samples in the field office apart from the Contract Documents used for construction. Do not use Project Record Documents for construction purposes. Maintain Record Documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to Project Record Documents for Owner or Owner's representative reference during normal working hours. END OF SECTION 017839 SECTION 017839 - PROJECT RECORD DOCUMENTS Page 4 of 4 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 024116 - STRUCTURE DEMOLITION PART 1-GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Demolition and removal of spillway and flood gates structure to original riverbed. 2. Salvaging items for reuse by Owner. B. Related Sections include the following: 1. Division 01 Section "Summary" for use of the premises and phasing requirements. 2. Division 01 Section "Photographic Documentation" for preconstruction photographs taken before building demolition. 3. Division 01 Section "Temporary Facilities and Controls" for temporary construction, protection facilities, and environmental-protection measures for building demolition operations. 4. Division 01 Section "Construction Waste Management and Disposal" for recycling and disposal of nonhazardous demolition wastes and for removal and storage of refrigerant. 5. Division 02 Section "Selective Structure Demolition" for partial demolition of buildings, structures, and site improvements. 6. Division 31 Section "Site Clearing" for site clearing and removal of above- and below- grade site improvements not part of building demolition. 1.3 DEFINITIONS A. Demolish: Completely remove and legally dispose of off-site. B. Recycle: Recovery of demolition waste for subsequent processing in preparation for reuse. C. Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner. Include fasteners or brackets needed for reattachment elsewhere. 1.4 MATERIALS OWNERSHIP A. Unless otherwise indicated, demolition waste becomes property of Contractor. SECTION 024116 - STRUCTURE DEMOLITION Page 1 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner. Carefully salvage in a manner to prevent damage and promptly return to Owner. 1.5 SUBMITTALS A. Proposed Protection Measures: Submit informational report, including drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control and, for noise control. Indicate proposed locations and construction of barriers. B. Schedule of Building Demolition Activities: Indicate the following: Detailed sequence of demolition work, with starting and ending dates for each activity. C. Inventory: Submit a list of items to be removed and salvaged and deliver to Owner prior to start of demolition. D. Predemolition Photographs: Show existing conditions of adjoining construction and site improvements, including finish surfaces that might be misconstrued as damage caused by building demolition operations. Comply with Division 0l Section "Photographic Documentation." Submit before the Work begins. 1.6 QUALITY ASSURANCE A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning demolition. Comply with hauling and disposal regulations of authorities having jurisdiction. B. Standards: Comply with ANSI A10.6 and NFPA 241. C. Predemolition Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination." Review methods and procedures related to building demolition including, but not limited to, the following: 1. Inspect and discuss condition of construction to be demolished. 2. Review structural load limitations of existing structures. 3. Review and finalize building demolition schedule and verify availability of demolition personnel, equipment, and facilities needed to make progress and avoid delays. 4. Review and finalize protection requirements. 5. Review procedures for noise control and dust control. 6. Review procedures for protection of adjacent buildings. 7. Review items to be salvaged and returned to Owner. SECTION 024116 - STRUCTURE DEMOLITION Page 2 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 1.7 PROJECT CONDITIONS A. Buildings to be demolished will be vacated and their use discontinued before start of the Work. B. Buildings immediately adjacent to demolition area will be occupied. Conduct building demolition so operations of occupied buildings will not be disrupted. 1. Provide not less than 72 hours' notice of activities that will affect operations of adjacent occupied buildings. 2. Maintain access to existing walkways, exits, and other facilities used by occupants of adjacent buildings. a. Do not close or obstruct walkways, exits, or other facilities used by occupants of adjacent buildings without written permission from authorities having jurisdiction. C. Owner assumes no responsibility for structures to be demolished. D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work. 1. Hazardous materials will be removed by Owner before start of the Work. 2. If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify Engineer and Owner. E. On-site storage or sale of removed items or materials is not permitted. 1.8 COORDINATION A. Arrange demolition schedule so as not to interfere with operations of adjacent occupied buildings. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 EXAMINATION A. Review Project Record Documents of existing construction provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents. B. Inventory and record the condition of items to be removed and salvaged. Provide photographs of conditions that might be misconstrued as damage caused by salvage operations. Comply with Division 01 Section "Photographic Documentation." SECTION 024116 - STRUCTURE DEMOLITION Page 3 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3.2 PREPARATION A. Temporary Shoring: Provide and maintain interior and exterior shoring, bracing, or structural support to preserve stability and prevent unexpected movement or collapse of construction being demolished. Strengthen or add new supports when required during progress of demolition. B. Salvaged Items: Comply with the following: 1. Clean salvaged items of dirt and demolition debris. 2. Pack or crate items after cleaning. Identify contents of containers. 3. Store items in a secure area until delivery to Owner. 4. Transport items to storage area designated by Owner. 5. Protect items from damage during transport and storage. 3.3 PROTECTION A. Existing Facilities: Protect adjacent walkways, loading docks, building entries, and other building facilities during demolition operations. Maintain exits from existing buildings. B. Temporary Protection: Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction and as indicated. Comply with requirements in Division 01 Section "Temporary Facilities and Controls." 1. Protect adjacent buildings and facilities from damage due to demolition activities. 2. Protect existing site improvements, appurtenances, and landscaping to remain. 3. Erect a plainly visible fence around drip line of individual trees or around perimeter drip line of groups of trees to remain. 4. Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain. 5. Provide protection to ensure safe passage of people around building demolition area and to and from occupied portions of adjacent buildings and structures. 6. Protect walls, windows, roofs, and other adjacent exterior construction that are to remain and that are exposed to building demolition operations. 7. Erect and maintain dustproof partitions and temporary enclosures to limit dust, noise, and dirt migration to occupied portions of adjacent buildings. C. Remove temporary barriers and protections where hazards no longer exist. Where open excavations or other hazardous conditions remain, leave temporary barriers and protections in place. 3.4 DEMOLITION, GENERAL A. General: Demolish indicated existing site improvements completely. Use methods required to complete the Work within limitations of governing regulations and as follows: SECTION 024116 - STRUCTURE DEMOLITION Page 4 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 B. Engineering Surveys: During demolition, perform surveys to detect hazards that may result from demolition activities. C. Site Access and Temporary Controls: Conduct demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities. 1. Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by authorities having jurisdiction. 2. Use water mist and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations. Do not use water when it may damage adjacent construction or create hazardous or objectionable conditions, such as ice, flooding, and pollution. D. Explosives: Use of explosives is not permitted. 3.5 DEMOLITION BY MECHANICAL MEANS A. Proceed with demolition of spillway and flood gates as indicated on other Contract Documents. B. Salvage: Items to be salvaged will be as indicated by Owner. C. Spillway and Flood Gate Construction: Demolish spillway and flood gate construction. 1. Completely remove all below-grade construction for spillway and flood gate construction. However, do not disturb or remove any boulders or rock from riverbed. 3.6 DEMOLITION BY EXPLOSIVES A. Demolition by explosives is not permitted. 3.7 SITE RESTORATION A. Silt Removal: Stabilize or remove and dispose of any remaining silt within riverbed within demolition limits according to Contract Documents. 3.8 REPAIRS A. Promptly repair damage to adjacent buildings caused by demolition operations. SECTION 024116 - STRUCTURE DEMOLITION Page 5 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 3.9 DISPOSAL OF DEMOLISHED MATERIALS A. Remove demolition waste materials from Project site. See Division 01 Section "Construction Waste Management and Disposal" for recycling and disposal of demolition waste. B. Remove demolition waste materials from Project site and legally dispose of them in an EPA- approved landfill acceptable to authorities having jurisdiction. 1. Do not allow demolished materials to accumulate on-site. 2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas. C. Do not burn demolished materials. 3.10 CLEANING A. Clean adjacent structures and improvements of dust, dirt, and debris caused by building demolition operations. Return adjacent areas to condition existing before building demolition operations began. END OF SECTION 024116 SECTION 024116 - STRUCTURE DEMOLITION Page 6 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of powerhouse structure. 2. Salvage of existing items to be reused or recycled. B. Related Sections include the following: 1. Division 01 Section "Summary" for use of premises. 2. Division 01 Section "Photographic Documentation" for preconstruction photographs taken before selective demolition operations. 3. Division 01 Section "Temporary Facilities and Controls" for temporary construction and environmental-protection measures for selective demolition operations. 4. Division 01 Section "Cutting and Patching" for cutting and patching procedures. 5. Division 01 Section "Construction Waste Management and Disposal" for disposal of demolished materials. 6. Division 02 Section "Structure Demolition" for demolition of entire buildings, structures, and site improvements. 7. Division 31 Section "Site Clearing" for site clearing and removal of above- and below- grade improvements. 1.3 DEFINITIONS A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled. B. Remove and Salvage: Detach items from existing construction and deliver them to Owner. C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated. D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled. SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION Page 1 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 1.4 MATERIALS OWNERSHIP A. Carefully remove and salvage each item or object in a manner to prevent damage and deliver promptly to Owner. 1.5 SUBMITTALS A. Schedule of Selective Demolition Activities: Indicate the following: 1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. 2. Locations of proposed dust- and noise-control temporary partitions and means of egress. 3. Means of protection for items to remain and items in path of waste removal from building. B. Inventory: After selective demolition is complete, submit a list of items that have been removed and salvaged. C. Predemolition Photographs: Show existing conditions of adjoining construction and site improvements, including finish surfaces that might be misconstrued as damage caused by selective demolition operations. Comply with Division 0l Section "Photographic Documentation." Submit before Work begins. D. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes. 1. Comply with submittal requirements in Division 01 Section "Construction Waste Management and Disposal." 1.6 QUALITY ASSURANCE A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project. B. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction. C. Standards: Comply with ANSI A10.6 and NFPA 241. D. Predemolition Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination." Review methods and procedures related to selective demolition including, but not limited to, the following: 1. Inspect and discuss condition of construction to be selectively demolished. 2. Review structural load limitations of existing structure. SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION Page 2 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays. 4. Review plans for removal and handling of hazardous waste that may be encountered. 5. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations. 6. Review areas where existing construction is to remain and requires protection. 1.7 PROJECT CONDITIONS A. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical. B. Notify Engineer of discrepancies between existing conditions and Drawings before proceeding with selective demolition. C. Hazardous Materials: The owner will remove a majority of the hazardous material prior to demolition. Some Hazardous materials may be present in the following locations during the Work. 1. Asbestos packing and gasket material may be present at flanges and valves to be removed. 2. Asbestos insulation material may be present in and around electrical bus work and components to be demolished. 3. Lead based paint may be present on painted steel components to be demolished. 4. If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify Owner. D. Owner will remove the bulk volume of oil from hydraulic systems to be completely or partially demolished. A residual volume of oil may remain in systems. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 EXAMINATION A. Verify that applicable systems have been disconnected and de-energized. B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required. C. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged. SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION Page 3 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to Engineer. E. Engage a professional engineer to survey condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective demolition operations. F. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities. 3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS A. Existing Services/Systems: Maintain services/systems indicated to remain and protect them against damage during selective demolition operations. B. Service/System Requirements: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished. 1. Owner will arrange to shut off and/or de-energize indicated services/systems as necessary to facilitate equipment removal and demolition activities when requested by Contractor. 2. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit after bypassing. 3.3 PREPARATION A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities. Comply with requirements for access and protection specified in Division 01 Section "Temporary Facilities and Controls." B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain. 1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building. C. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished. 1. Strengthen or add new supports when required during progress of selective demolition. SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION Page 4 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3.4 SELECTIVE DEMOLITION, GENERAL A. General: Demolish and remove existing construction only to the extent required and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows: 1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level. 2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain. 3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire- suppression devices during flame-cutting operations. 4. Maintain adequate ventilation when using cutting torches. 5. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation. 6. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing. 7. Dispose of demolished items and materials promptly. Comply with requirements in Division 01 Section "Construction Waste Management and Disposal". B. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. 3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS A. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals, using power-driven saw, then remove concrete between saw cuts. B. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, then break up and remove. 3.6 DISPOSAL OF DEMOLISHED MATERIALS A. General: Except for items or materials indicated to be recycled, reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill. 1. Do not allow demolished materials to accumulate on-site. 2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas. SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION Page 5 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029. 0000 Revision No.: Review 2 December 18, 2008 3. Comply with requirements specified in Division 01 Section "Construction Waste Management and Disposal." B. Burning: Do not burn demolished materials. C. Disposal: Transport demolished materials off Owner's property and legally dispose of them. 3.7 CLEANING A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began. END OF SECTION 024119 SECTION 024119 - SELECTIVE STRUCTURE DEMOLITION Page 6 of 6 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 033000 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section specifies cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes, for the following: 1. Footings. 2. Retaining walls. 3. Buttresses. 1.3 DEFINITIONS A. Cementitious Materials: Portland cement alone or in combination with, fly ash and silica fume; subject to compliance with requirements. 1.4 SUBMITTALS A. General: In addition to the following, comply with submittal requirements in ACI 301. B. Product Data: For each type of product indicated. C. Design Mixtures: For each concrete mixture, include ingredient proportions, characteristics, and test data. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments. Provide batch ticket with each truck load indicating amounts of mixing water to be withheld for later addition at Project site. D. Steel Reinforcement Shop Drawings: Placing drawings that detail fabrication, bending, and placement. Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and supports for concrete reinforcement. E. Formwork Shop Drawings: Prepared by or under the supervision of a qualified professional engineer detailing fabrication, assembly, and support of formwork. Drawings shall be sealed by a Professional Engineer licensed in North Carolina. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 1 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Shoring and Reshoring: Indicate proposed schedule and sequence of stripping formwork, shoring removal, and installing and removing reshoring. F. Qualification Data: For Installer, manufacturer, and testing agency. G. Material Test Reports: For the following, from a qualified testing agency, indicating compliance with requirements: 1. Aggregates. Provide types, pit or quarry location, producer name gradings, specific gravities, absorption, and evidence not more than 90 days old demonstrating compliance with ASTM C33. Include service record data indicating absence of deleterious expansion of concrete due to alkali aggregate reactivity. 2. Mixing water: Provide source and verification of compliance with ASTM C 1602/C 1602M. H. Material Certificates: For each of the following, signed by manufacturers: 1. Cementitious materials - initially and for each shipment used in project 2. Admixtures - initially and for each shipment used in project 3. Form materials and form-release agents. 4. Steel reinforcement and accessories (Mill test certification for each heat used) 5. Curing and curing/sealing compounds. 6. Floor and slab treatments. 7. Bonding agents. 8. Adhesives. 9. Vapor retarders. 10. Semirigid joint filler. 11. Joint-filler strips. 12. Repair materials. 13. Evaporation retarders. 14. Curing sheet materials. 1. Floor surface flatness and levelness measurements to determine compliance with specified tolerances. J. Field quality-control test and inspection reports. K. Minutes of preinstallation conference. 1.5 QUALITY ASSURANCE A. Installer Qualifications: A qualified installer who employs on Project personnel qualified as ACI-certified Flatwork Technician and Finisher and a supervisor who is an ACI-certified Concrete Flatwork Technician. B. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 2 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete Production Facilities." C. Testing Agency Qualifications: An independent agency, acceptable to authorities having jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated, as documented according to ASTM E 548. 1. Personnel conducting field tests shall be qualified as ACI Concrete Field Testing Technician, Grade 1, according to ACI CP-01 or an equivalent certification program. 2. Personnel performing laboratory tests shall be ACI-certified Concrete Strength Testing Technician and Concrete Laboratory Testing Technician - Grade I. Testing Agency laboratory supervisor shall be an ACI-certified Concrete Laboratory Testing Technician - Grade II. D. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant, obtain aggregate from one source, and obtain admixtures through one source from a single manufacturer. E. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents: 1. ACI 301, "Specification for Structural Concrete." 2. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials." F. Preinstallation Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination." Before submitting design mixtures, review concrete design mixture and examine procedures for ensuring quality of concrete materials. Require representatives of each entity directly concerned with cast-in-place concrete to attend, including the following: a. Contractor's superintendent. b. Independent testing agency responsible for field quality control. C. Ready-mix concrete manufacturer. d. Concrete subcontractor. e. Engineer. f. Owner QCIP representative. 2. Review testing and inspecting agency procedures for field quality control, concrete finishes and finishing, cold- and hot-weather concreting procedures, curing procedures, construction contraction and isolation joints, and joint-filler strips, semirigid joint fillers, forms and form removal limitations, shoring and reshoring procedures, vapor-retarder installation, anchor rod and anchorage device installation tolerances, steel reinforcement installation, concrete repair procedures, and concrete protection. 1.6 DELIVERY, STORAGE, AND HANDLING A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending, damage, coating with oil, soil or other materials that might prevent proper bonding. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 3 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC PART 2 - PRODUCTS 2.1 MANUFACTURERS DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. In other Part 2 articles where titles below introduce lists, the following requirements apply to product selection: 1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, products specified. 2.2 FORM-FACING MATERIALS A. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit. B. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch, minimum. C. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces. 1. Formulate form-release agent with rust inhibitor for steel form-facing materials. D. Form Ties: Factory-fabricated, removable or snap-off metal or glass-fiber-reinforced plastic form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal. 1. Furnish units that will leave no corrodible metal closer than 1 inch to the plane of exposed concrete surface. 2. Furnish ties that, when removed, will leave holes no larger than 1 inch in diameter in concrete surface. 3. Furnish ties with integral water-barrier plates to walls indicated to receive dampproofing or waterproofing. 2.3 STEEL REINFORCEMENT A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed. B. Plain-Steel Welded Wire Reinforcement: ASTM A 185, plain, fabricated from as-drawn steel wire into flat sheets. 2.4 REINFORCEMENT ACCESSORIES A. Joint Dowel Bars: ASTM A 615/A 615M, Grade 60, plain-steel bars, cut bars true to length with ends square and free of burrs. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 4 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 B. Tie Wire: Black annealed, 16 gauge or heavier C. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows: For concrete surfaces exposed to view where legs of wire bar supports contact forms, use CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports. 2.5 CONCRETE MATERIALS A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source, throughout Project: Portland Cement: ASTM C 150, Type II. Supplement with the following when permitted by the Engineer: a. Fly Ash: ASTM C 618, Class F. B. Silica Fume: ASTM C 1240, amorphous silica. C. Normal-Weight Aggregates: ASTM C 33, Class 3S coarse aggregate or better, non-alkali reactive, and well-graded. Provide aggregates from a single source. 1. Maximum Coarse-Aggregate Size: 3/4 inch nominal. 2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement. D. Water: ASTM C 94/C 94M and potable. 2.6 ADMIXTURES A. Air-Entraining Admixture: ASTM C 260. B. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and that will not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride. 1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A. 2. Retarding Admixture: ASTM C 494/C 494M, Type B. 3. Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D. 4. High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F. 5. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type G. 6. Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 5 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 2.7 CURING MATERIALS A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete. 1. Available Products: a. ChemMasters; Spray-Film. b. Dayton Superior Corporation; Sure Film. C. Sika Corporation, Inc.; SikaFilm. d. Others as approved by Engineer and/or Owner. B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. when dry. C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet. D. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, dissipating. E. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, nondissipating. F. Clear, Waterborne, Membrane-Forming Curing and Sealing Compound: ASTM C 1315, Type 1, Class A. 2.8 RELATED MATERIALS A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber or ASTM D 1752, cork or self-expanding cork. B. Semirigid Joint Filler: Two-component, semirigid, 100 percent solids, aromatic polyurea with a Type A shore durometer hardness range of 90 to 95 per ASTM D 2240. C. Bonding Agent: ASTM C 1059, Type II, non-redispersible, acrylic emulsion or styrene butadiene. D. Epoxy Bonding Adhesive: ASTM C 881, two-component epoxy resin, capable of humid curing and bonding to damp surfaces, of class suitable for application temperature and of grade to suit requirements, and as follows: 1. Types IV and V, load bearing, for bonding hardened or freshly mixed concrete to hardened concrete. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 6 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 2.9 REPAIR MATERIALS A. Repair Underlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/8 inch and that can be feathered at edges to match adjacent floor elevations. 1. Cement Binder: ASTM C 150, portland cement or hydraulic or blended hydraulic cement as defined in ASTM C 219. 2. Primer: Product of underlayment manufacturer recommended for substrate, conditions, and application. 3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch or coarse sand as recommended by underlayment manufacturer. 4. Compressive Strength: Not less than 4100 psi at 28 days when tested according to ASTM C 109/C 109M. B. Repair Overlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/8 inch and that can be feathered at edges to match adjacent floor elevations. 1. Cement Binder: ASTM C 150, portland cement or hydraulic or blended hydraulic cement as defined in ASTM C 219. 2. Primer: Product of topping manufacturer recommended for substrate, conditions, and application. 3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch or coarse sand as recommended by topping manufacturer. 4. Compressive Strength: Not less than 5000 psi at 28 days when tested according to ASTM C 109/C 109M. 2.10 CONCRETE MIXTURES, GENERAL A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301. B. Cementitious Materials: Limit percentage, by weight, of cementitious materials other than portland cement in concrete as follows: 1. Fly Ash: 25 percent. 2. Silica Fume: 10 percent. C. Limit water-soluble, chloride-ion content in hardened concrete to 0.15 percent by weight of cement. D. Admixtures: Use admixtures according to manufacturer's written instructions. 1. Use water-reducing, high-range water-reducing, or plasticizing admixture in concrete, as required, for placement and workability. 2. Use water-reducing and retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 7 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3. Use water-reducing admixture in pumped concrete, concrete for heavy-use industrial slabs and parking structure slabs, concrete required to be watertight, and concrete with a water-cementitious materials ratio below 0.50. 2.11 CONCRETE MIXTURES FOR BUILDING ELEMENTS A. Footings, Retaining Walls, Slabs-on-Grade, and Buttresses: Proportion normal-weight concrete mixture as follows: 1. Minimum Compressive Strength: 4000 psi at 28 days. 2. Maximum Water-Cementitious Materials Ratio: 0.45. 3. Slump Limit: 4 inches, 8 inches for concrete with verified slump of 2 to 4 inches before adding high-range water-reducing admixture or plasticizing admixture, plus or minus 1 inch. 4. Air Content: 6 percent, plus or minus 1.5 percent at point of delivery for 3/4-inch nominal maximum aggregate size. 2.12 FABRICATING REINFORCEMENT A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice." 2.13 CONCRETE MIXING A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M, and furnish batch ticket information. 1. When air temperature is between 85 and 90 deg F, reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes from batch ticket time to placement of concrete. PART 3 - EXECUTION 3.1 FORMWORK A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads. B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117. C. Limit concrete surface irregularities, designated by ACI 347R as abrupt or gradual, as follows: 1. Class B, 1/4 inch. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 8 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 D. Construct forms tight enough to prevent loss of concrete mortar. E. Fabricate forms for easy removal without hammering or prying against concrete surfaces. Provide crush or wrecking plates where stripping may damage cast concrete surfaces. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical. 1. Install keyways, reglets, recesses, and the like, for easy removal. 2. Do not use rust-stained steel form-facing material. F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds. G. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations. H. Chamfer exterior corners and edges of permanently exposed concrete. 1. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work. Determine sizes and locations from trades providing such items. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete. K. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment. L. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement. 3.2 EMBEDDED ITEMS A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded. 1. Install anchor rods, accurately located, to elevations required and complying with tolerances in Section 7.5 of AISC's "Code of Standard Practice for Steel Buildings and Bridges." 3.3 REMOVING AND REUSING FORMS A. General: Remove forms in accordance with the requirements of ACI 301. Formwork for sides of retaining walls, buttresses, and similar parts of the Work that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F for 24 hours after SECTION 033000 - CAST-IN-PLACE CONCRETE Page 9 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 placing concrete, if concrete is hard enough to not be damaged by form-removal operations and curing and protection operations are maintained. 1. Remove forms only if shores have been arranged to permit removal of forms without loosening or disturbing shores. B. Clean and repair surfaces of forms to be reused in the Work. Split, frayed, delaminated, or otherwise damaged form-facing material will not be acceptable for exposed surfaces. Apply new form-release agent. C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints. Align and secure joints to avoid offsets. Do not use patched forms for exposed concrete surfaces unless approved by Engineer. 3.4 SHORES AND RESHORES A. Comply with ACI318 and ACI301 for design, installation, and removal of shoring and reshoring. 1. Do not remove shoring or reshoring until measurement of slab tolerances is complete. B. Plan sequence of removal of shores and reshore to avoid damage to concrete. Locate and provide adequate reshoring to support construction without excessive stress or deflection. 3.5 STEEL REINFORCEMENT A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement. B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that would reduce bond to concrete. C. Accurately position, support, and secure reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars. D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces. E. Install welded wire reinforcement in longest practicable lengths on bar supports spaced to minimize sagging. Lap edges and ends of adjoining sheets at least one mesh spacing. Offset laps of adjoining sheet widths to prevent continuous laps in either direction. Lace overlaps with wire. 3.6 JOINTS A. General: Construct joints true to line with faces perpendicular to surface plane of concrete. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 10 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Engineer. 1. Place joints perpendicular to main reinforcement. Continue reinforcement across construction joints, unless otherwise indicated. Do not continue reinforcement through sides of strip placements of floors and slabs. 2. Form keyed joints as indicated. Embed keys at least 1-1/2 inches into concrete. 3. Locate horizontal joints in walls and columns at underside of floors, slabs, beams, and girders and at the top of footings or floor slabs. 4. Space vertical joints in walls as indicated. Locate joints beside piers integral with walls, near corners, and in concealed locations where possible. 5. Use a bonding agent at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces. C. Doweled Joints: Install dowel bars and support assemblies at joints where indicated. Lubricate or asphalt coat one-half of dowel length to prevent concrete bonding to one side of joint. 3.7 CONCRETE PLACEMENT A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed. B. Do not add water to concrete during delivery, at Project site, or during placement unless approved by Engineer. C. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301 and acceptance by the Engineer. 1. Do not add water to concrete after adding high-range water-reducing admixtures to mixture. D. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation. 1. Deposit concrete in horizontal layers of depth to not exceed formwork design pressures and in a manner to avoid inclined construction joints. 2. Consolidate placed concrete with mechanical vibrating equipment according to ACI 301. 3. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches into preceding layer. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity. At each insertion, limit duration of vibration to time necessary to consolidate concrete and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate. E. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 11 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 1. Consolidate concrete during placement operations so concrete is thoroughly worked around reinforcement and other embedded items and into corners. 2. Maintain reinforcement in position on chairs during concrete placement. 3. Screed slab surfaces with a straightedge and strike off to correct elevations. 4. Slope surfaces uniformly to drains where required. 5. Begin initial floating using bull floats or darbies to form a uniform and open-textured surface plane, before excess bleedwater appears on the surface. Do not further disturb slab surfaces before starting finishing operations. F. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures. 1. When average high and low temperature is expected to fall below 40 deg F for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301. 2. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials. 3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs. G. Hot-Weather Placement: Comply with ACI 301 and as follows: 1. Maintain concrete temperature below 90 deg F at time of placement. Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option. 2. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete. Keep subgrade uniformly moist without standing water, soft spots, or dry areas. 3.8 FINISHING FORMED SURFACES A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie holes and defects repaired and patched. Remove fins and other projections that exceed specified limits on formed-surface irregularities. B. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed surfaces, strike off smooth and finish with a texture matching adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent unformed surfaces, unless otherwise indicated. 3.9 MISCELLANEOUS CONCRETE ITEMS A. Filling In: Fill in holes and openings left in concrete structures, unless otherwise indicated, after work of other trades is in place. Mix, place, and cure concrete, as specified, to blend with in-place construction. Provide other miscellaneous concrete filling indicated or required to complete the Work. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 12 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3.10 CONCRETE PROTECTING AND CURING A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI306.1 for cold-weather protection and ACI301 for hot- weather protection during curing. B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing. C. Formed Surfaces: Cure formed concrete surfaces, including underside of beams, supported slabs, and other similar surfaces. If forms remain during curing period, moist cure after loosening forms. If removing forms before end of curing period, continue curing for the remainder of the curing period. D. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, including floors and slabs, concrete floor toppings, and other surfaces. E. Cure concrete according to ACI 308. 1, by one or a combination of the following methods: 1. Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials: a. Water. b. Continuous water-fog spray. C. Absorptive cover, water saturated, and kept continuously wet. Cover concrete surfaces and edges with 12-inch lap over adjacent absorptive covers. 2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period using cover material and waterproof tape. 3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period. a. After curing period has elapsed, remove curing compound without damaging concrete surfaces by method recommended by curing compound manufacturer. 4. Curing and Sealing Compound: Apply uniformly to floors and slabs indicated in a continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Repeat process 24 hours later and apply a second coat. Maintain continuity of coating and repair damage during curing period. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 13 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC 3.11 JOINT FILLING DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Prepare, clean, and install joint filler according to manufacturer's written instructions. Defer joint filling until concrete has aged at least one month. Do not fill joints until construction traffic has permanently ceased. B. Remove dirt, debris, saw cuttings, curing compounds, and sealers from joints; leave contact faces of joint clean and dry. C. Install semirigid joint filler full depth in saw-cut joints and at least 2 inches deep in formed joints. Overfill joint and trim joint filler flush with top of joint after hardening. 3.12 CONCRETE SURFACE REPAIRS A. Defective Concrete: Repair and patch defective areas when approved by Engineer. Remove and replace concrete that cannot be repaired and patched to Engineer's approval. B. Patching Mortar: Mix dry-pack patching mortar, consisting of one part portland cement to two and one-half parts fine aggregate passing a No. 16 sieve, using only enough water for handling and placing. C. Repairing Formed Surfaces: Surface defects include color and texture irregularities, cracks, spalls, air bubbles, honeycombs, rock pockets, fins and other projections on the surface, and stains and other discolorations that cannot be removed by cleaning. 1. Immediately after form removal, cut out honeycombs, rock pockets, and voids more than 1/2 inch in any dimension in solid concrete, but not less than 1 inch in depth. Make edges of cuts perpendicular to concrete surface. Clean, dampen with water, and brush- coat holes and voids with bonding agent. Fill and compact with patching mortar before bonding agent has dried. Fill form-tie voids with patching mortar or cone plugs secured in place with bonding agent. 2. Repair defects on surfaces exposed to view by blending white portland cement and standard portland cement so that, when dry, patching mortar will match surrounding color. Patch a test area at inconspicuous locations to verify mixture and color match before proceeding with patching. Compact mortar in place and strike off slightly higher than surrounding surface. 3. Repair defects on concealed formed surfaces that affect concrete's durability and structural performance as determined by Engineer. D. Repairing Unformed Surfaces: Test unformed surfaces, such as floors and slabs, for finish and verify surface tolerances specified for each surface. Correct low and high areas. Test surfaces sloped to drain for trueness of slope and smoothness; use a sloped template. 1. Repair finished surfaces containing defects. Surface defects include spalls, popouts, honeycombs, rock pockets, crazing and cracks in excess of 0.01 inch wide or that penetrate to reinforcement or completely through unreinforced sections regardless of width, and other objectionable conditions. 2. After concrete has cured at least 14 days, correct high areas by grinding. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 14 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3. Correct localized low areas during or immediately after completing surface finishing operations by cutting out low areas and replacing with patching mortar. Finish repaired areas to blend into adjacent concrete. 4. Correct other low areas scheduled to receive floor coverings with a repair underlayment. Prepare, mix, and apply repair underlayment and primer according to manufacturer's written instructions to produce a smooth, uniform, plane, and level surface. Feather edges to match adjacent floor elevations. 5. Correct other low areas scheduled to remain exposed with a repair topping. Cut out low areas to ensure a minimum repair topping depth of 1/4 inch to match adjacent floor elevations. Prepare, mix, and apply repair topping and primer according to manufacturer's written instructions to produce a smooth, uniform, plane, and level surface. 6. Repair defective areas, except random cracks and single holes 1 inch or less in diameter, by cutting out and replacing with fresh concrete. Remove defective areas with clean, square cuts and expose steel reinforcement with at least a 3/4-inch clearance all around. Dampen concrete surfaces in contact with patching concrete and apply bonding agent. Mix patching concrete of same materials and mixture as original concrete except without coarse aggregate. Place, compact, and finish to blend with adjacent finished concrete. Cure in same manner as adjacent concrete. 7. Repair random cracks and single holes 1 inch or less in diameter with patching mortar. Groove top of cracks and cut out holes to sound concrete and clean off dust, dirt, and loose particles. Dampen cleaned concrete surfaces and apply bonding agent. Place patching mortar before bonding agent has dried. Compact patching mortar and finish to match adjacent concrete. Keep patched area continuously moist for at least 72 hours. E. Repair materials and installation not specified above may be used, subject to Engineer's approval. 3.13 FIELD QUALITY CONTROL A. Testing and Inspecting: Owner will engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports. B. Inspections: 1. Steel reinforcement placement. 2. Verification of use of required design mixture. 3. Concrete placement, including conveying and depositing. 4. Curing procedures and maintenance of curing temperature. 5. Verification of concrete strength before removal of shores and forms from beams and slabs. C. Concrete Tests: Testing of composite samples of fresh concrete obtained according to ASTM C 172 shall be performed according to the following requirements: Testing Frequency: Obtain at least one composite sample for each 50 cu. yd. or fraction thereof of each concrete mixture placed each day. SECTION 033000 - CAST-IN-PLACE CONCRETE Page 15 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 a. When frequency of testing will provide fewer than five compressive-strength tests for each concrete mixture, testing shall be conducted from at least five randomly selected batches or from each batch if fewer than five are used. 2. Slump: ASTM C 143/C 143M; one test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mixture. Perform additional tests when concrete consistency appears to change. 3. Air Content: ASTM C 231, pressure method, for normal-weight concrete; one test for each composite sample, but not less than one test for each day's pour of each concrete mixture. 4. Concrete Temperature: ASTM C 1064/C 1064M; one test hourly when air temperature is 40 deg F and below and when 80 deg F and above, and one test for each composite sample. 5. Compression Test Specimens: ASTM C 31/C 31M. a. Cast and laboratory cure two sets of two standard cylinder specimens for each composite sample. Compressive-Strength Tests: ASTM C 39/C 39M; test one set of two laboratory-cured specimens at 7 days and one set of two specimens at 28 days. The extra set may be used for 56 day test if 28 day specimens do not meet strength requirements. a. A compressive-strength test shall be the average compressive strength from a set of two specimens obtained from same composite sample and tested at age indicated. 7. Strength of each concrete mixture will be satisfactory if every average of any three consecutive compressive-strength tests equals or exceeds specified compressive strength and no compressive-strength test value falls below specified compressive strength by more than 500 psi. 8. Test results shall be reported in writing to Engineer, concrete manufacturer, and Contractor within 48 hours of testing. Reports of compressive-strength tests shall contain Project identification name and number, date of concrete placement, name of concrete testing and inspecting agency, location of concrete batch in Work, design compressive strength at 28 days, concrete mixture proportions and materials, compressive breaking strength, and type of break for both 7- and 28-day tests. 9. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be permitted by Engineer but will not be used as sole basis for approval or rejection of concrete. 10. Additional Tests: Testing and inspecting agency shall make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Engineer. Testing and inspecting agency may conduct tests to determine adequacy of concrete by cored cylinders complying with ASTM C 42/C 42M or by other methods as directed by Engineer. 11. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements. 12. Correct deficiencies in the Work that test reports and inspections indicate does not comply with the Contract Documents. END OF SECTION 033000 SECTION 033000 - CAST-IN-PLACE CONCRETE Page 16 of 16 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 055213 - PIPE AND TUBE RAILINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Steel pipe and tube railings. B. Related Sections include the following: 1.3 PERFORMANCE REQUIREMENTS A. General: In engineering railings to withstand structural loads indicated, determine allowable design working stresses of railing materials based on the following: 1. Steel: 72 percent of minimum yield strength. B. Structural Performance: Provide railings capable of withstanding the effects of gravity loads and the following loads and stresses within limits and under conditions indicated: 1. Handrails: a. Uniform load of 50 lbf/ ft. applied in any direction. b. Concentrated load of 200 lbf applied in any direction. C. Uniform and concentrated loads need not be assumed to act concurrently. 2. Top Rails of Guards: a. Uniform load of 50 lbf/ ft. applied in any direction. b. Concentrated load of 200 lbf applied in any direction. C. Uniform and concentrated loads need not be assumed to act concurrently. 3. Infill of Guards: a. Concentrated load of 200 lbf applied horizontally on an area of 1 sq. ft.. b. Uniform load of 25 lbf/sq. ft. applied horizontally. C. Infill load and other loads need not be assumed to act concurrently. SECTION 055213 - PIPE AND TUBE RAILINGS Page 1 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 C. Thermal Movements: Provide exterior railings that allow for thermal movements resulting from the following maximum change (range) in ambient and surface temperatures by preventing buckling, opening of joints, overstressing of components, failure of connections, and other detrimental effects. Base engineering calculation on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss. 1. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces. D. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals and other materials from direct contact with incompatible materials. 1.4 SUBMITTALS A. Product Data: For the following: 1. Manufacturer's product lines of mechanically connected railings. 2. Grout, anchoring cement, and paint products. B. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work. For installed products indicated to comply with design loads, include structural analysis data signed and sealed by the qualified professional engineer responsible for their preparation. C. Samples for Initial Selection: For products involving selection of color, texture, or design. D. Samples for Verification: For each type of exposed finish required. 1. Sections of each distinctly different linear railing member, including handrails, top rails, posts, and balusters. 2. Fittings and brackets. 3. Assembled Sample of railing system, made from full-size components, including top rail, post, handrail, and infill. Sample need not be full height. a. Show method of connecting & finishing members at intersections. E. Mill Certificates: Signed by manufacturers of stainless-steel products certifying that products furnished comply with requirements. F. Welding certificates. G. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing, agency, according to ASTM E 894 and ASTM E 935. 1.5 QUALITY ASSURANCE A. Source Limitations: Obtain each type of railing through one source from a single manufacturer. SECTION 055213 - PIPE AND TUBE RAILINGS Page 2 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 B. Welding: Qualify procedures and personnel according to the following: 1. AWS DL1, "Structural Welding Code--Steel." 1.6 PROJECT CONDITIONS A. Field Measurements: Verify actual locations of walls and other construction contiguous with railings by field measurements before fabrication and indicate measurements on Shop Drawings. Provide allowance for trimming and fitting at site. 1.7 COORDINATION AND SCHEDULING A. Coordinate installation of anchorages for railings. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation. B. Schedule installation so wall attachments are made only to completed walls. Do not support railings temporarily by any means that do not satisfy structural performance requirements. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: B. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Steel Pipe and Tube Railings: a. Pisor Industries, Inc. b. Sharpe Products. C. Wagner, R & B, Inc.; a division of the Wagner Companies. d. Others as approved b Owner. 2.2 METALS, GENERAL A. Metal Surfaces, General: Provide materials with smooth surfaces, without seam marks, roller marks, rolled trade names, stains, discolorations, or blemishes. SECTION 055213 - PIPE AND TUBE RAILINGS Page 3 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 B. Brackets, Flanges, and Anchors: Cast or formed metal of same type of material and finish as supported rails, unless otherwise indicated. 2.3 STEEL AND IRON A. Tubing: ASTM A 500 (cold formed) or ASTM A 513, Type 5 (mandrel drawn). B. Pipe: ASTM A 53/A 53M, Type F or Type S, Grade A, Standard Weight (Schedule 40), unless another grade and weight are required by structural loads. 1. Provide galvanized finish for exterior installations and where indicated. C. Plates, Shapes, and Bars: ASTM A 36/A 36M. D. Woven-Wire Mesh: Intermediate-crimp, square pattern, 2-inch woven-wire mesh, made from 0.135-inch nominal diameter wire complying with ASTM A 510. 2.4 FASTENERS A. General: Provide the following: 1. Steel Railings: Plated steel fasteners complying with ASTM B 633, Class Fe/Zn 25 for electrodeposited zinc coating. B. Fasteners for Anchoring Railings to Other Construction: Select fasteners of type, grade, and class required to produce connections suitable for anchoring railings to other types of construction indicated and capable of withstanding design loads. C. Fasteners for Interconnecting Railing Components: 1. Provide concealed fasteners for interconnecting railing components and for attaching them to other work, unless exposed fasteners are unavoidable or are the standard fastening method for railings indicated. 2. Provide square or hex socket flat-head machine screws for exposed fasteners, unless otherwise indicated. D. Anchors: Provide cast-in-place chemical or torque-controlled expansion anchors, fabricated from corrosion-resistant materials with capability to sustain, without failure, a load equal to six times the load imposed when installed in unit masonry and equal to four times the load imposed when installed in concrete, as determined by testing per ASTM E 488 conducted by a qualified independent testing agency. 2.5 MISCELLANEOUS MATERIALS A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded. B. Shop Primers: Provide primers that comply with Division 09 painting Sections. SECTION 055213 - PIPE AND TUBE RAILINGS Page 4 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 C. Shop Primer for Galvanized Steel: Zinc-dust, zinc-oxide primer formulated for priming zinc- coated steel and for compatibility with finish paint systems indicated, and complying with SSPC-Paint 5. D. Galvanizing Repair Paint: High-zinc-dust-content paint for regalvanizing welds in steel, complying with SSPC-Paint 20. E. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187. F. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous grout complying with ASTM C 1107. Provide grout specifically recommended by manufacturer for interior and exterior applications. G. Anchoring Cement: Factory-packaged, nonshrink, nonstaining, hydraulic-controlled expansion cement formulation for mixing with water at Project site to create pourable anchoring, patching, and grouting compound. 1. Water-Resistant Product: At exterior locations provide formulation that is resistant to erosion from water exposure without needing protection by a sealer or waterproof coating and that is recommended by manufacturer for exterior use. 2.6 FABRICATION A. General: Fabricate railings to comply with requirements indicated for design, dimensions, member sizes and spacing, details, finish, and anchorage, but not less than that required to support structural loads. B. Assemble railings in the shop to greatest extent possible to minimize field splicing and assembly. Disassemble units only as necessary for shipping and handling limitations. Clearly mark units for reassembly and coordinated installation. Use connections that maintain structural value of joined pieces. C. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch, unless otherwise indicated. Remove sharp or rough areas on exposed surfaces. D. Form work true to line and level with accurate angles and surfaces. E. Fabricate connections that will be exposed to weather in a manner to exclude water. Provide weep holes where water may accumulate. F. Cut, reinforce, drill, and tap as indicated to receive finish hardware, screws, and similar items. G. Connections: Fabricate railings with either welded or nonwelded connections, unless otherwise indicated. H. Welded Connections: Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings. SECTION 055213 - PIPE AND TUBE RAILINGS Page 5 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals. 2. Obtain fusion without undercut or overlap. 3. Remove flux immediately. 4. At exposed connections, finish exposed surfaces smooth and blended so no roughness shows after finishing and welded surface matches contours of adjoining surfaces. 1. Nonwelded Connections: Connect members with concealed mechanical fasteners and fittings. Fabricate members and fittings to produce flush, smooth, rigid, hairline joints. 1. Fabricate splice joints for field connection using an epoxy structural adhesive if this is manufacturer's standard splicing method. J. Form simple and compound curves by bending members in jigs to produce uniform curvature for each repetitive configuration required; maintain cross section of member throughout entire bend without buckling, twisting, cracking, or otherwise deforming exposed surfaces of components. K. Close exposed ends of railing members with prefabricated end fittings. L. Provide wall returns at ends of wall-mounted handrails, unless otherwise indicated. Close ends of returns. M. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings, and anchors to interconnect railing members to other work, unless otherwise indicated. N. Provide inserts and other anchorage devices for connecting railings to concrete or masonry work. Fabricate anchorage devices capable of withstanding loads imposed by railings. Coordinate anchorage devices with supporting structure. 0. For railing posts set in concrete, provide steel sleeves not less than 6 inches long with inside dimensions not less than 1/2 inch greater than outside dimensions of post, with steel plate forming bottom closure. P. For removable railing posts, fabricate slip-fit sockets from steel tube or pipe whose ID is sized for a close fit with posts; limit movement of post without lateral load, measured at top, to not more than one-fortieth of post height. Provide socket covers designed and fabricated to resist being dislodged. Q. Toe Boards: Where indicated, provide toe boards at railings around openings and at edge of open-sided floors and platforms. Fabricate to dimensions and details indicated. 2.7 FINISHES, GENERAL A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes. B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping. SECTION 055213 - PIPE AND TUBE RAILINGS Page 6 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 C. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are acceptable if they are within one-half of the range of approved Samples. Noticeable variations in the same piece are not acceptable. Variations in appearance of other components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast. D. Provide exposed fasteners with finish matching appearance, including color and texture, of railings. 2.8 STEEL AND IRON FINISHES A. Galvanized Railings: 1. Hot-dip galvanize exterior steel and iron railings, including hardware, after fabrication. 2. Comply with ASTM A 123/A 123M for hot-dip galvanized railings. 3. Comply with ASTM A 153/A 153M for hot-dip galvanized hardware. B. Fill vent and drain holes that will be exposed in the finished Work, unless indicated to remain as weep holes, by plugging with zinc solder and filing off smooth. C. For galvanized railings, provide hot-dip galvanized fittings, brackets, fasteners, sleeves, and other ferrous components. PART 3 - EXECUTION 3.1 INSTALLATION, GENERAL A. Fit exposed connections together to form tight, hairline joints. B. Perform cutting, drilling, and fitting required for installing railings. Set railings accurately in location, alignment, and elevation; measured from established lines and levels and free of rack. 1. Do not weld, cut, or abrade surfaces of railing components that have been coated or finished after fabrication and that are intended for field connection by mechanical or other means without further cutting or fitting. 2. Set posts plumb within a tolerance of 1/16 inch in 3 feet. 3. Align rails so variations from level for horizontal members and variations from parallel with rake of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet. C. Adjust railings before anchoring to ensure matching alignment at abutting joints. D. Fastening to In-Place Construction: Use anchorage devices and fasteners where necessary for securing railings and for properly transferring loads to in-place construction. SECTION 055213 - PIPE AND TUBE RAILINGS Page 7 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3.2 RAILING CONNECTIONS A. Nonwelded Connections: Use mechanical or adhesive joints for permanently connecting railing components. Seal recessed holes of exposed locking screws using plastic cement filler colored to match finish of railings. B. Welded Connections: Use fully welded joints for permanently connecting railing components. Comply with requirements for welded connections in Part 2 "Fabrication" Article whether welding is performed in the shop or in the field. C. Expansion Joints: Install expansion joints at locations indicated but not farther apart than required to accommodate thermal movement. Provide slip joint internal sleeve extending 2 inches beyond joint on either side, fasten internal sleeve securely to I side, and locate joint within 6 inches of post. 3.3 ANCHORING POSTS A. Use steel pipe sleeves preset and anchored into concrete for installing posts. After posts have been inserted into sleeves, fill annular space between post and sleeve with nonshrink, nonmetallic grout or anchoring cement, mixed and placed to comply with anchoring material manufacturer's written instructions. B. Form or core-drill holes not less than 5 inches deep and 3/4 inch larger than OD of post for installing posts in concrete. Clean holes of loose material, insert posts, and fill annular space between post and concrete with nonshrink, nonmetallic grout or anchoring cement, mixed and placed to comply with anchoring material manufacturer's written instructions. C. Cover anchorage joint with flange of same metal as post, welded to post after placing anchoring material. D. Anchor posts to metal surfaces with oval flanges, angle type, or floor type as required by conditions, connected to posts and to metal supporting members as follows: 1. For steel pipe railings, weld flanges to post and bolt to metal supporting surfaces. 3.4 ANCHORING RAILING ENDS A. Anchor railing ends to concrete and masonry with round flanges connected to railing ends and anchored to wall construction with anchors and bolts. 3.5 ATTACHING HANDRAILS TO WALLS A. Attach handrails to wall with wall brackets. Provide brackets with 1-1/2-inch clearance from inside face of handrail and finished wall surface. 1. Use type of bracket with flange tapped for concealed anchorage to threaded hanger bolt. 2. Use type of bracket with predrilled hole for exposed bolt anchorage. SECTION 055213 - PIPE AND TUBE RAILINGS Page 8 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 B. Locate brackets as indicated or, if not indicated, at spacing required to support structural loads. C. Secure wall brackets to building construction as follows: 1. For concrete and solid masonry anchorage, use drilled-in expansion shields and hanger or lag bolts. 3.6 ADJUSTING AND CLEANING A. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780. 3.7 PROTECTION A. Protect finishes of railings from damage during construction period with temporary protective coverings approved by railing manufacturer. Remove protective coverings at time of Substantial Completion. B. Restore finishes damaged during installation and construction period so no evidence remains of correction work. Return items that cannot be refinished in the field to the shop; make required alterations and refinish entire unit, or provide new units. END OF SECTION 055213 SECTION 055213 - PIPE AND TUBE RAILINGS Page 9 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, L.LC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 101400 - SIGNAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Plaques. 2. Dimensional characters. 3. Panel signs. 1.3 DEFINITIONS A. ADA-ABA Accessibility Guidelines: U.S. Architectural & Transportation Barriers Compliance Board's "Americans with Disabilities Act (ADA) Accessibility Guidelines for Buildings and Facilities; Architectural Barriers Act (ABA) Accessibility Guidelines." 1.4 SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: Show fabrication and installation details for signs. 1. Show sign mounting heights, locations of supplementary supports to be provided by others, and accessories. 2. Provide message list, typestyles, graphic elements and layout for each sign. C. Samples for Initial Selection: Manufacturer's color charts consisting of actual units or sections of units showing the full range of colors available for the following: 1. Aluminum. 2. Acrylic sheet. 3. Polycarbonate sheet. 4. Fiberglass sheet. 5. Die-cut vinyl characters and graphic symbols. D. Samples for Verification: For each of the following products and for the full range of color, texture, and sign material indicated, of sizes indicated: SECTION 101400 - SIGNAGE Page 1 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Plaque: 6 inches square. 2. Dimensional Characters: Full-size Samples of each type of dimensional character (letter, number, and graphic element). 3. Aluminum: For each form, finish, and color, on 6-inch- long sections of extrusions and squares of sheet at least 4 by 4 inches. 4. Acrylic Sheet: 8 by 10 inches for each color required. 5. Polycarbonate Sheet: 8 by 10 inches for each color required. 6. Fiberglass Sheet: 8 by 10 inches for each color required. 7. Panel Signs: Not less than 12 inches square including border. 8. Frame: 6-inch- long sections of each profile. 9. Accessories: Manufacturer's full-size unit. E. Sign Schedule: Use same designations indicated on Drawings. F. Qualification Data: For fabricator. G. Maintenance Data: For signs to include in maintenance manuals. 1.5 QUALITY ASSURANCE A. Installer Qualifications: Fabricator of products. B. Fabricator Qualifications: Shop that employs skilled workers who custom-fabricate products similar to those required for this Project and whose products have a record of successful in- service performance. C. Source Limitations for Signs: Obtain each sign type indicated from one source from a single manufacturer. D. Regulatory Requirements: Comply with applicable provisions in ADA-ABA Accessibility Guidelines. 1.6 PROJECT CONDITIONS A. Weather Limitations: Proceed with installation only when weather conditions permit installation of signs in exterior locations to be performed according to manufacturers' written instructions and warranty requirements. B. Field Measurements: Verify recess openings by field measurements before fabrication and indicate measurements on Shop Drawings. 1.7 COORDINATION A. Coordinate placement of anchorage devices with templates for installing signs. SECTION 101400 - SIGNAGE Page 2 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 PART 2 - PRODUCTS 2.1 MATERIALS A. Aluminum Sheet and Plate: ASTM B 209, alloy and temper recommended by aluminum producer and finisher for type of use and finish indicated, and with at least the strength and durability properties of Alloy 5005-1132. B. Acrylic Sheet: ASTM D 4802, Category A-1 (cell-cast sheet), Type UVA (UV absorbing). C. Polycarbonate Sheet: Of thickness indicated, manufactured by extrusion process, coated on both surfaces with abrasion-resistant coating: 1. Impact Resistance: 16 ft-lbf/in. per ASTM D 256, Method A. 2. Tensile Strength: 9000 lbf/sq. in. per ASTM D 638. 3. Flexural Modulus of Elasticity: 340,000 lbf/sq. in. per ASTM D 790. 4. Heat Deflection: 265 deg F at 264 lbf/sq. in. per ASTM D 648. 5. Abrasion Resistance: 1.5 percent maximum haze increase for 100 revolutions of a Taber abraser with a load of 500 g per ASTM D 1044. D. Applied Vinyl: Die-cut characters from vinyl film of nominal thickness of 3 mils with pressure- sensitive adhesive backing, suitable for exterior applications. 2.2 PLAQUES A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Sign Art, Charlotte, NC 2. Andco, Greensboro, NC 2.3 DIMENSIONAL CHARACTERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Sign Art, Charlotte, NC 2. Andco, Greensboro, NC B. Vinyl: Pressure sensitive, 3.5 mils thick. 1. Custom Paint Colors: Match Pantone color matching system. 2. Color: As indicated. 3. Mounting: Based on location and surface material mounting to. C. Dimensional Character Sign Schedule: SECTION 101400 - SIGNAGE Page 3 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029. 0000 Revision No.: Review 2 December 18, 2008 1. Sign Type and location to be determined by Owner: a. Sign Size: As indicated. b. Character Size: As indicated. C. Text/Message: As indicated. d. Location: As indicated. 2.4 PANEL SIGNS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Sign Art, Charlotte, NC 2. Andco, Greensboro, NC B. Exterior Panel Signs: Provide smooth sign panel surfaces constructed to remain flat under installed conditions within a tolerance of plus or minus 1/16 inch measured diagonally from corner to corner, complying with the following requirements: 1. Aluminum Sheet: 0.050 inch thick. 2. Laminated, Aluminum-Faced Sheet: 0.020-inch- thick aluminum sheet laminated to each side of 0.197-inch- thick, acrylic backing. 3. Acrylic Sheet: 0.060 inch thick. 4. Edge Condition: Beveled. 5. Corner Condition: Square. 6. Mounting: To be determined by Owner. 7. Custom Paint Colors: Match Pantone color matching system. 8. Color: As selected by Owner from manufacturer's full range. C. Brackets: Fabricate brackets and fittings for bracket-mounted signs from extruded aluminum to suit panel sign construction and mounting conditions indicated. Factory paint brackets in color matching background color of panel sign. D. Panel Sign Schedule: 1. Sign Type to be determined a. Sign Size: As indicated. b. Message Panel Material: As indicated. C. Message Panel Finish/Color: d. Background Finish/Color: e. Character Size: As indicated. f. Character Finish/Color: g. Panel Sign Frame Finish/Color: h. Text/Message: As indicated. i. Location: As indicated. j. Quantity: SECTION 101400 - SIGNAGE Page 4 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029. 0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 2.5 ACCESSORIES A. Anchors and Inserts: Provide nonferrous-metal or hot-dip galvanized anchors and inserts for exterior installations and elsewhere as required for corrosion resistance. Use toothed steel or lead expansion-bolt devices for drilled-in-place anchors. Furnish inserts, as required, to be set into concrete or masonry work. 2.6 FABRICATION A. General: Provide manufacturer's standard signs of configurations indicated. 1. Welded Connections: Comply with AWS standards for recommended practices in shop welding. Provide welds behind finished surfaces without distortion or discoloration of exposed side. Clean exposed welded surfaces of welding flux and dress exposed and contact surfaces. 2. Mill joints to tight, hairline fit. Form joints exposed to weather to exclude water penetration. 3. Preassemble signs in the shop to greatest extent possible. Disassemble signs only as necessary for shipping and handling limitations. Clearly mark units for reassembly and installation, in location not exposed to view after final assembly. 4. Conceal fasteners if possible; otherwise, locate fasteners where they will be inconspicuous. 2.7 FINISHES, GENERAL A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes. B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping. C. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are acceptable if they are within one-half of the range of approved Samples. Noticeable variations in the same piece are not acceptable. Variations in appearance of other components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast. 2.8 ALUMINUM FINISHES A. Clear Anodic Finish: Manufacturer's standard Class 1 clear anodic coating, 0.018 mm or thicker, over a nonspecular as fabricated] mechanical finish, complying with AAMA 611. B. Color Anodic Finish: Manufacturer's standard Class 1 integrally colored or electrolytically deposited color anodic coating, 0.018 mm or thicker, in light bronze applied over a nonspecular as fabricated mechanical finish, complying with AAMA 611. SECTION 101400 - SIGNAGE Page 5 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18. 2008 C. Baked-Enamel Finish: AA-C12C42R1x (Chemical Finish: cleaned with inhibited chemicals; Chemical Finish: acid-chromate-fluoride-phosphate conversion coating; Organic Coating: as specified below). Apply baked enamel complying with paint manufacturer's written instructions for cleaning, conversion coating, and painting. Organic Coating: Thermosetting, modified-acrylic enamel primer/topcoat system complying with AAMA 2603 except with a minimum dry film thickness of 1.5 mils, medium gloss. 2.9 ACRYLIC SHEET FINISHES A. Colored Coatings for Acrylic Sheet: For copy, background and frame colors, provide colored coatings, including inks, dyes, and paints, that are recommended by acrylic manufacturers for optimum adherence to acrylic surface and that are UV and water resistant for five years for application intended. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of work. B. Verify that items, including anchor inserts, are sized and located to accommodate signs. C. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 INSTALLATION A. Locate signs and accessories where indicated, using mounting methods of types described and complying with manufacturer's written instructions. 1. Install signs level, plumb, and at heights indicated, with sign surfaces free of distortion and other defects in appearance. 2. Interior Wall Signs: Install signs on walls adjacent to latch side of door where applicable. Where not indicated or possible, such as double doors, install signs on nearest adjacent walls. Locate to allow approach within 3 inches of sign without encountering protruding objects or standing within swing of door. B. Wall-Mounted Signs: Comply with sign manufacturer's written instructions except where more stringent requirements apply. 1. Two-Face Tape: Mount signs to smooth, nonporous surfaces. Do not use this method for vinyl-covered or rough surfaces. 2. Hook-and-Loop Tapes: Mount signs to smooth, nonporous surfaces. 3. Magnetic Tape: Mount signs to smooth, nonporous surfaces. SECTION 101400 - SIGNAGE Page 6 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029. 0000 Revision No.: Review 2 December 18, 2008 4. Silicone-Adhesive Mounting: Attach signs to irregular, porous, or vinyl-covered surfaces. 5. Shim Plate Mounting: Provide 1/8-inch- thick, concealed aluminum shim plates with predrilled and countersunk holes, at locations indicated, and where other mounting methods are not practicable. Attach plate with fasteners and anchors suitable for secure attachment to substrate. Attach panel signs to plate using method specified above. 6. Mechanical Fasteners: Use nonremovable mechanical fasteners placed through predrilled holes. Attach signs with fasteners and anchors suitable for secure attachment to substrate as recommended in writing by sign manufacturer. 7. Signs Mounted on Glass: Provide matching opaque plate on opposite side of glass to conceal mounting materials. C. Bracket-Mounted Signs: Provide manufacturer's standard brackets, fittings, and hardware for mounting signs that project at right angles from walls and ceilings. Attach brackets and fittings securely to walls and ceilings with concealed fasteners and anchoring devices to comply with manufacturer's written instructions. D. Dimensional Characters: Mount characters using standard fastening methods to comply with manufacturer's written instructions for character form, type of mounting, wall construction, and condition of exposure indicated. Provide heavy paper template to establish character spacing and to locate holes for fasteners. Flush Mounting: Mount characters with backs in contact with wall surface. Projected Mounting: Mount characters at projection distance from wall surface indicated. E. Cast-Metal Plaques: Mount plaques using standard fastening methods to comply with manufacturer's written instructions for type of wall surface indicated. 1. Concealed Mounting: Mount plaques by inserting threaded studs into tapped lugs on back of plaque. Set in predrilled holes filled with quick-setting cement. 2. Face Mounting: Mount plaques using exposed fasteners with rosettes attached through face of plaque into wall surface. 3.3 CLEANING AND PROTECTION A. After installation, clean soiled sign surfaces according to manufacturer's written instructions. Protect signs from damage until acceptance by Owner. END OF SECTION 101400 SECTION 101400 - SIGNAGE Page 7 of 7 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC SECTION 311000 - SITE CLEARING PART 1 - GENERAL 1.1 RELATED DOCUMENTS DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Protecting existing trees shrubs groundcovers plants and grass to remain. 2. Removing above- and below-grade site improvements. 3. Temporary erosion and sedimentation control measures. B. Related Sections include the following: 1. Division 01 Section "Temporary Facilities and Controls" for temporary utilities, temporary construction and support facilities, temporary security and protection facilities, and temporary erosion and sedimentation control procedures. 2. Division 01 Section "Execution" for verifying utility locations and for recording field measurements. 3. Division 02 Section "Structure Demolition" for demolition of buildings, structures, and site improvements. 4. Division 02 Section "Selective Structure Demolition" for partial demolition of buildings or structures undergoing alterations. 5. Division 31 Section "Earth Moving" for soil materials, excavating, backfilling, and site grading. 1.3 DEFINITIONS A. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 2 inches in diameter; and free of subsoil and weeds, roots, toxic materials, or other nonsoil materials. B. Tree Protection Zone: Area surrounding individual trees or groups of trees to be protected during construction, and defined by the drip line of individual trees or the perimeter drip line of groups of trees, unless otherwise indicated. SECTION 311000 - SITE CLEARING Page 1 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1.4 MATERIAL OWNERSHIP A. Except for stripped topsoil, riprap, natural boulders/stone or other materials indicated to remain on the Owner's property, cleared materials shall become Contractor's property and shall be disposed of legally off-site. 1.5 SUBMITTALS A. Photographs or videotape, sufficiently detailed, of existing conditions of trees and plantings, adjoining construction, and site improvements that might be misconstrued as damage caused by site clearing. B. Record drawings, according to Division 01 Section "Project Record Documents," identifying and accurately locating capped utilities and other subsurface structural, electrical, and mechanical conditions. C. Materials Specification Data: At least 14 days prior to use of any manufactured erosion and sediment control products on-site, the Contractor shall submit the specification data sheets and manufacturer's installation requirements for all products that will be incorporated into the erosion and sediment control measures. 1.6 QUALITY ASSURANCE A. Preinstallation Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination." 1.7 PROJECT CONDITIONS A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations. 1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. 2. Provide alternate routes around closed or obstructed traffic ways if required by authorities having jurisdiction. B. Salvable Improvements: Carefully remove items indicated to be salvaged and store as directed by owner. C. Utility Locator Service: Notify utility locator service for area where Project is located before site clearing. D. Do not commence site clearing operations until temporary erosion and sedimentation control measures are in place. SECTION 311000 - SITE CLEARING Page 2 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 PREPARATION DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Protect and maintain benchmarks and survey control points from disturbance during construction. B. Locate and clearly flag trees and vegetation to remain or to be relocated. C. Protect existing site improvements to remain from damage during construction. Restore damaged improvements to their original condition, as acceptable to Owner. 3.2 TEMPORARY EROSION AND SEDIMENTATION CONTROL A. Provide temporary erosion and sedimentation control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways, according to sediment and erosion control Drawings. B. Inspect, repair, and maintain erosion and sedimentation control measures during construction until permanent vegetation has been established. C. Remove erosion and sedimentation controls and restore and stabilize areas disturbed during removal. 3.3 TREE PROTECTION A. Erect and maintain temporary fencing around tree protection zones before starting site clearing. Remove fence when construction is complete. 1. Do not store construction materials, debris, or excavated material within fenced area. 2. Do not permit vehicles, equipment, or foot traffic within fenced area. 3. Maintain fenced area free of weeds and trash. B. Do not excavate within tree protection zones, unless otherwise indicated. C. Repair or replace trees and vegetation indicated to remain that are damaged by construction operations, in a manner approved by Owner. 1. Employ an arborist, licensed in jurisdiction where Project is located, to submit details of proposed repairs and to repair damage to trees and shrubs. 2. Replace trees that cannot be repaired and restored to full-growth status, as determined by Engineer. SECTION 311000 - SITE CLEARING Page 3 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 3.4 A. B. C. 3.5 A. B 3.6 A. B UTILITIES Owner will arrange for disconnecting and sealing indicated utilities that serve existing structures before site clearing, when requested by Contractor. 1. Verify that utilities have been disconnected and capped before proceeding with site clearing. Locate, identify, disconnect, and seal or cap off utilities indicated to be removed. 1. Arrange with utility companies to shut off indicated utilities. 2. Owner will arrange to shut off indicated utilities when requested by Contractor. Excavate for and remove underground utilities indicated to be removed. CLEARING AND GRUBBING Remove obstructions, trees, shrubs, grass, and other vegetation to permit installation of new construction. 1. Do not remove trees, shrubs, and other vegetation indicated to remain or to be relocated. 2. Cut minor roots and branches of trees indicated to remain in a clean and careful manner where such roots and branches obstruct installation of new construction. 3. Grind stumps and remove roots, obstructions, and debris extending to a depth of 18 inches below exposed subgrade. 4. Use only hand methods for grubbing within tree protection zone. Fill depressions caused by clearing and grubbing operations with satisfactory soil material unless further excavation or earthwork is indicated. 1. Place fill material in horizontal layers not exceeding a loose depth of 8 inches, and compact each layer to a density equal to adjacent original ground. TOPSOIL STRIPPING Remove sod and grass before stripping topsoil. Strip topsoil to whatever depths are encountered in a manner to prevent intermingling with underlying subsoil or other waste materials. Remove subsoil and nonsoil materials from topsoil, including trash, debris, weeds, roots, and other waste materials. C. Stockpile topsoil materials away from edge of excavations without intermixing with subsoil. Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust. 1. Limit height of topsoil stockpiles to 72 inches. SECTION 311000 - SITE CLEARING Page 4 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 2. Do not stockpile topsoil within tree protection zones. 3. Dispose of excess topsoil as specified for waste material disposal. 4. Stockpile surplus topsoil to allow for respreading deeper topsoil. 3.7 SITE IMPROVEMENTS A. Remove existing above- and below-grade improvements as indicated and as necessary to facilitate demolition. 3.8 DISPOSAL A. Disposal: Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials, and waste materials including trash and debris, and legally dispose of them off Owner's property according to Section 01 "Construction Waste Management and Disposal". END OF SECTION 311000 SECTION 311000 - SITE CLEARING Page 5 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, L.LC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Preparing subgrades for pavements, lawns and grasses. 2. Excavating and backfilling for buildings and structures. 3. Aggregate base course for asphalt paving. 4. Subsurface drainage backfill for walls and trenches. B. Related Sections include the following: 1. Division 01 Section "Unit Prices" for unit-price rock excavation and authorized additional excavation provisions. 2. Division 01 Section "Construction Progress Documentation" and "Photographic Documentation" for recording preexcavation and earthwork progress. 3. Division 01 Section "Temporary Facilities and Controls" for temporary controls, utilities, and support facilities. 4. Division 31 Section "Site Clearing" for temporary erosion and sedimentation control measures, and removal of above- and below-grade improvements and utilities. 5. Division 31 Section "Erosion and Sediment Control". 6. Division 32 Section "Turf and Grasses" for finish grading, including preparing and placing topsoil and planting soil for lawns. 7. Division 32 Section "Plants" for planting bed establishment and tree and shrub pit excavation and planting. 1.3 DEFINITIONS A. Backfill: Soil material or controlled low-strength material used to fill an excavation. 1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe. 2. Final Backfill: Backfill placed over initial backfill to fill a trench. B. Aggregate Base Course: Course placed between the subgrade and hot-mix asphalt paving. C. Bedding Course: Course placed over the excavated subgrade in a trench before laying pipe. SECTION 312000 - EARTH MOVING Page 1 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 D. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill. E. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated. 1. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Engineer. Authorized additional excavation and replacement material will be paid for according to Contract provisions for unit prices. 2. Bulk Excavation: Excavation more than 10 feet in width and more than 30 feet in length. 3. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Engineer. Unauthorized excavation, as well as remedial work directed by Engineer, shall be without additional compensation. F. Fill: Soil materials used to raise existing grades. G. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below the ground surface. H. Subgrade: Surface or elevation remaining after completing excavation, or top surface of a fill or backfill immediately below subbase, drainage fill, or topsoil materials. 1. Utilities: On-site underground pipes, conduits, ducts, and cables, as well as underground services within buildings. 1.4 SUBMITTALS A. Product Data: For the following: 1. Each type of plastic warning tape. 2. Geotextile. B. Material Test Reports: From a qualified testing agency indicating and interpreting test results for compliance of the following with requirements indicated: 1. Classification according to ASTM D 2487 of each on-site and borrow soil material proposed for fill and backfill. 2. Laboratory compaction curve according to ASTM D 698 for each on-site and borrow soil material proposed for fill and backfill. 3. Laboratory compaction curve according to ASTM D 1557 for each Aggregate Base Course material proposed. 4. Aggregate Materials: Provide types, pit or quarry location, producer name, gradings, gravities, and evidence not more than 90 days old demonstrating compliance with ASTM C33 and/or NCDOT requirements. SECTION 312000 - EARTH MOVING Page 2 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 C. Preexcavation Photographs: Show existing conditions of adjoining construction and site improvements, including finish surfaces, that might be misconstrued as damage caused by earthwork operations. Submit before earthwork begins. 1.5 QUALITY ASSURANCE A. Geotechnical Testing Agency Qualifications: An independent testing agency qualified according to ASTM E 329 to conduct soil materials and rock-definition testing, as documented according to ASTM D 3740 and ASTM E 548. B. Preexcavation Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination." 1.6 PROJECT CONDITIONS A. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted in writing by Owner and then only after arranging to provide temporary utility services according to requirements indicated. 1. Notify Owner not less than two days in advance of proposed utility interruptions. 2. Do not proceed with utility interruptions without Owner's written permission. 3. Contact utility-locator service for area where Project is located before excavating. PART 2 - PRODUCTS 2.1 SOIL MATERIALS A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations. B. Satisfactory Soils: ASTM D 2487 Soil Classification Groups GW, GP, GM, SW, SP, SM, SC and ML or a combination of these groups; free of rock or gravel larger than 3 inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter. C. Unsatisfactory Soils: Soil Classification Groups CL, OL, CH, MH, OH, and PT according to ASTM D 2487, or a combination of these groups. 1. Unsatisfactory soils also include satisfactory soils not maintained within 3 percent of optimum moisture content at time of compaction. D. Aggregate Base Course (ABC): Material shall conform to the requirement of NCDOT Aggregate Base Course. SECTION 312000 - EARTH MOVING Page 3 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 E. Drainage Course: Narrowly graded mixture of washed crushed stone, or crushed or uncrushed gravel; ASTM D 448; coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2-inch sieve and 0 to 5 percent passing a No. 8 sieve. F. Filter Material: Narrowly graded mixture of natural or crushed gravel, or crushed stone and natural sand; ASTM D 448; coarse-aggregate grading Size 67; with 100 percent passing a f- inch sieve and 0 to 5 percent passing a No. 4 sieve. G. Sand: ASTM C 33; fine aggregate, natural, or manufactured sand. H. Impervious Fill: Clayey gravel and sand mixture capable of compacting to a dense state. 2.2 GEOTEXTILES A. Subsurface Drainage Geotextile: Nonwoven needle-punched geotextile, manufactured for subsurface drainage applications, made from polyolefins or polyesters; with elongation greater than 50 percent; complying with AASHTO M 288 and the following, measured per test methods referenced: 1. Survivability: Class 2; AASHTO M 288. 2. Grab Tensile Strength: 157 lbf; ASTM D 4632. 3. Sewn Seam Strength: 142 lbf; ASTM D 4632. 4. Tear Strength: 561bf; ASTM D 4533. 5. Puncture Strength: 56 lbf; ASTM D 4833. 6. Apparent Opening Size: No. 70 sieve, maximum; ASTM D 4751. 7. Permittivity: 0.1 per second, minimum; ASTM D 4491. 8. UV Stability: 50 percent after 500 hours' exposure; ASTM D 4355. B. Separation Geotextile: Woven geotextile fabric, manufactured for separation applications, made from polyolefins or polyesters; with elongation less than 50 percent; complying with the following, measured per test methods referenced: (Mirafi 50OX or approved equivalent) 1. Grab Tensile Strength: 230 lbf (CD/MD); ASTM D 4632. 2. Tear Strength: 105 lbf; ASTM D 4533. 3. Puncture Strength: 122 lbf; ASTM D 4833. 4. Apparent Opening Size: No. 60 sieve, maximum; ASTM D 4751. 5. Permittivity: 0.16 per second, minimum; ASTM D 4491. 6. UV Stability: 70 percent after 500 hours' exposure; ASTM D 4355. C. RIPRAP MATERIALS 1. Material shall consist of sound, angular, well graded, non-calcareous fieldstone, quarry stone or rock fragments, free from structural defects. 2. Material shall conform to the requirement of NCDOT Class A Riprap, Class B Riprap, Class 1 Riprap, or Class 2 Riprap; as indicated on Drawings. 3. Riprap material shall meet requirements above and blend in with existing boulders/stones from existing powerhouse demolition debris to be placed on the embankments. 4. The Contractor will submit samples to Owner for approval. SECTION 312000 - EARTH MOVING Page 4 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 2.3 ACCESSORIES A. Warning Tape: Acid- and alkali-resistant polyethylene film warning tape manufactured for marking and identifying underground utilities, 6 inches wide and 4 mils thick, continuously inscribed with a description of the utility; colored as follows: B. Detectable Warning Tape: Acid- and alkali-resistant polyethylene film warning tape manufactured for marking and identifying underground utilities, a minimum of 6 inches wide and 4 mils thick, continuously inscribed with a description of the utility, with metallic core encased in a protective jacket for corrosion protection, detectable by metal detector when tape is buried up to 30 inches deep; colored as follows: 1. Red: Electric. 2. Yellow: Gas, oil, steam, and dangerous materials. 3. Orange: Telephone and other communications. 4. Blue: Water systems. 5. Green: Sewer systems. PART 3 - EXECUTION 3.1 PREPARATION A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations. B. Preparation of subgrade for earthwork operations including removal of vegetation, topsoil, debris, obstructions, and deleterious materials from ground surface is specified in Division 31 Section "Site Clearing." C. Protect and maintain erosion and sedimentation controls, which are specified in Division 31 Section "Site Clearing," during earthwork operations. D. Provide protective insulating materials to protect subgrades and foundation soils against freezing temperatures or frost. 3.2 EXPLOSIVES A. Explosives: Do not use explosives. 3.3 EXCAVATION, GENERAL A. Classified Excavation: Excavate to subgrade elevations. Material to be excavated will be classified as earth and rock. Do not excavate rock until it has been classified and cross sectioned by Engineer. The Contract Sum will be adjusted for rock excavation according to unit SECTION 312000 - EARTH MOVING Page 5 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 prices included in the Contract Documents. Changes in the Contract time may be authorized for rock excavation. 1. Earth excavation includes excavating pavements and obstructions visible on surface; underground structures, utilities, and other items indicated to be removed; together with soil, boulders, and other materials not classified as rock or unauthorized excavation. a. Intermittent drilling; blasting, if permitted; ram hammering; or ripping of material not classified as rock excavation is earth excavation. 3.4 EXCAVATION FOR STRUCTURES A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1 inch. If applicable, extend excavations a sufficient distance from structures for placing and removing concrete formwork, for installing services and other construction, and for inspections. 3.5 EXCAVATION FOR WALKS AND PAVEMENTS A. Excavate surfaces under walks and pavements to indicated lines, cross sections, elevations, and subgrades. 3.6 SUBGRADE INSPECTION A. Notify Owner when excavations have reached required subgrade. B. If Owner determines that unsatisfactory soil is present, continue excavation and replace with compacted backfill or fill material as directed. C. Proof-roll subgrade below the pavements with heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding. Do not proof-roll wet or saturated subgrades. 1. Completely proof-roll subgrade in one direction, repeating proof-rolling in direction perpendicular to first direction. Limit vehicle speed to 3 mph. 2. Proof-roll with a loaded 10-wheel, tandem-axle dump truck weighing not less than 15 tons. 3. Excavate soft spots, unsatisfactory soils, and areas of excessive pumping, or rutting, as determined by Owner, and replace with compacted backfill or fill as directed. D. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by Engineer, without additional compensation. 3.7 UNAUTHORIZED EXCAVATION A. Fill unauthorized excavation under foundations or wall footings by extending bottom elevation of concrete foundation or footing to excavation bottom, without altering top elevation. Lean SECTION 312000 - EARTH MOVING Page 6 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 concrete fill, with 28-day compressive strength of 2500 psi, may be used when approved by Engineer. 1. Fill unauthorized excavations under other construction or utility pipe as directed by Owner. 3.8 STORAGE OF SOIL MATERIALS A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust. 1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees. 2. Stockpile soil materials in areas approved by the Owner. 3.9 BACKFILL A. Place and compact backfill in excavations promptly, but not before completing the following: 1. Construction below finish grade including, where applicable, subdrainage, dampproofing, waterproofing, and perimeter insulation. 2. Surveying locations of underground utilities for Record Documents. 3. Surveying locations of below grade retaining structures, to remain. 4. Testing and inspecting underground utilities. 5. Removing concrete formwork. 6. Removing trash and debris. 7. Removing temporary shoring and bracing, and sheeting. 8. Installing permanent or temporary horizontal bracing on horizontally supported walls. B. Place backfill on subgrades free of mud, frost, snow, or ice. 3.10 UTILITY TRENCH BACKFILL A. Place backfill on subgrades free of mud, frost, snow, or ice. B. Place and compact bedding course on trench bottoms and where indicated. Shape bedding course to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits. C. Backfill trenches excavated under footings and within 18 inches of bottom of footings with satisfactory soil; fill with concrete to elevation of bottom of footings. Concrete is specified in Division 03 Section "Cast-in-Place Concrete." D. Provide 4-inch- thick, concrete-base slab support for piping or conduit less than 30 inches below surface of roadways. After installing and testing, completely encase piping or conduit in SECTION 312000 - EARTH MOVING Page 7 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 a minimum of 4 inches of concrete or low-strength flowable fill before backfilling or placing roadway ABC stone. E. Place and compact initial backfill of satisfactory soil, free of particles larger than 1 inch in any dimension, to a height of 12 inches over the utility pipe or conduit. Carefully compact initial backfill under pipe haunches and compact evenly up on both sides and along the full length of utility piping or conduit to avoid damage or displacement of piping or conduit. Coordinate backfilling with utilities testing. F. Backfill voids with satisfactory soil while installing and removing shoring and bracing. G. Place and compact final backfill of satisfactory soil to final subgrade elevation. H. Install warning tape directly above utilities, 12 inches below finished grade, except 6 inches below subgrade under pavements and slabs. 3.11 SOIL FILL A. Plow, scarify, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing material. B. Place and compact fill material in layers to required elevations as follows: C. Place soil fill on subgrades free of mud, frost, snow, or ice. 3.12 SOIL MOISTURE CONTROL A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill soil layer before compaction to within 3 percent of optimum moisture content. 1. Do not place backfill or fill soil material on surfaces that are muddy, frozen, or contain frost or ice. 2. Remove and replace, or scarify and air dry otherwise satisfactory soil material that exceeds optimum moisture content by 3 percent and is too wet to compact to specified dry unit weight. 3.13 COMPACTION OF SOIL BACKFILLS AND FILLS A. Place backfill and fill soil materials in layers not more than 8 inches in loose depth for material compacted by heavy compaction equipment, and not more than 4 inches in loose depth for material compacted by hand-operated tampers. B. Place backfill and fill soil materials evenly on all sides of structures to required elevations, and uniformly along the full length of each structure. SECTION 312000 - EARTH MOVING Page 8 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18. 2008 C. Compact soil materials to not less than the following percentages of maximum dry unit weight according to ASTM D 698: 1. Under structures, building slabs, steps, and pavements, scarify and recompact top 12 inches of existing subgrade and each layer of backfill or fill soil material at 98 percent. 2. Under walkways, scarify and recompact top 6 inches below subgrade and compact each layer of backfill or fill soil material at 92 percent. 3. Under lawn or unpaved areas, scarify and recompact top 6 inches below subgrade and compact each layer of backfill or fill soil material at 85 percent. 4. For utility trenches, compact each layer of initial and final backfill soil material at 95 percent. 3.14 GRADING A. General: Uniformly grade areas to a smooth surface, free of irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated. 1. Provide a smooth transition between adjacent existing grades and new grades. 2. Cut out soft spots, fill low spots, and trim high spots to comply with required surface tolerances. B. Site Grading: Slope grades to direct water away from buildings and to prevent ponding. Finish subgrades to required elevations within the following tolerances: 1. Lawn or Unpaved Areas: Plus or minus 1 inch. 2. Walks: Plus or minus 1 inch. 3. Pavements: Plus or minus 1/2 inch. 3.15 SUBSURFACE DRAINAGE A. Subsurface Drain: Place subsurface drainage geotextile around perimeter of subdrainage trench. Place a 6-inch course of filter material on subsurface drainage geotextile to support subdrainage pipe. Encase subdrainage pipe in a minimum of 12 inches of filter material, placed in compacted layers 6 inches thick, and wrap in subsurface drainage geotextile, overlapping sides and ends at least 6 inches. Compact each filter material layer to 85 percent of maximum dry unit weight according to ASTM D 698. B. Drainage Backfill: Place and compact filter material over subsurface drain, in width indicated, to within 12 inches of final subgrade, in compacted layers 6 inches thick. Overlay drainage backfill with 1 layer of subsurface drainage geotextile, overlapping sides and ends at least 6 inches. Compact each filter material layer to 85 percent of maximum dry unit weight according to ASTM D 698. SECTION 312000 - EARTH MOVING Page 9 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029. 0000 Revision No.: Review 2 December 18. 2008 2. Place and compact impervious fill over drainage backfill in 6-inch- thick compacted layers to final subgrade. 3.16 AGGREGATE BASE COURSE A. Place aggregate base course on subgrades free of mud, frost, snow, or ice. B. On prepared subgrade, place aggregate base course under pavements and walks as follows: 1. Place aggregate base course over subgrade under hot-mix asphalt pavement. 2. Shape aggregate base course to required crown elevations and cross-slope grades. 3. Place aggregate base course 6 inches or less in compacted thickness in a single layer. 4. Place aggregate base course that exceeds 6 inches in compacted thickness in layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 inches thick. 5. Compact aggregate base course at optimum moisture content to required grades, lines, cross sections, and thickness to not less than 98 percent of maximum dry unit weight according to ASTM D 1557. 3.17 DRAINAGE COURSE A. Place drainage course on subgrades free of mud, frost, snow, or ice. B. On prepared subgrade, place and compact drainage course under cast-in-place concrete slabs- on-grade as follows: 1. Place drainage course 6 inches or less in compacted thickness in a single layer. 2. Place drainage course that exceeds 6 inches in compacted thickness in layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 inches thick. 3. Compact each layer of drainage course to required cross sections and thicknesses to not less than 95 percent of maximum dry unit weight according to ASTM D 698. 3.18 FIELD QUALITY CONTROL A. Testing Agency: Engage a qualified independent geotechnical engineering testing agency to perform field quality-control testing. B. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earthwork only after test results for previously completed work comply with requirements. C. Aggregate Base Course (ABC): Classification will be determined according to ASTM D 2847 for each test sample. SECTION 312000 - EARTH MOVING Page 10 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18. 2008 2. Gradation and Atterberg limits will be determined according to ASTM D 422 and ASTM D 4318, respectively. a. 3 samples tested prior to material acceptance and use. b. 1 sample tested per 1000 cu. yd placed. C. 1 sample tested for each Proctor sample. 3. Material moisture-density relationship will be determined according to ASTM D 1557. a. 2 samples tested prior to material acceptance and use. b. Additional samples tested when conditions change. 4. In-place density will be determined according to ASTM D 6938. a. 1 test per 3,500 sq. ft. placed. D. Soil Materials: 1. Classification will be determined according to ASTM D 2847 for each Soil Material test sample. 2. Gradation and Atterberg limits will be determined according to ASTM D 422 and ASTM D 4318, respectively. a. 3 samples tested prior to material acceptance and use. b. 1 sample tested per 2,500 cu. yd placed. C. 1 sample tested for each Proctor sample. 3. Material moisture-density relationship will be determined according to ASTM D 698. a. 2 samples tested prior to material acceptance and use. b. 1 sample tested per 10,000 cu. yd placed. C. Additional samples tested when conditions change 4. In-place density will be determined according to ASTM D 1556 or ASTM D 6938. a. Area wider than 10 ft.: 1 test per 10,000 sq. ft placed and at least 1 per lift. b. Area 10 ft. wide or less (trench): 1 test per 300 linear ft. of trench. E. Footing Subgrade: At footing subgrades, at least one test of each soil stratum will be performed to verify design bearing capacities. Subsequent verification and approval of other footing subgrades may be based on a visual comparison of subgrade with tested subgrade when approved by Engineer. F. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil to depth required; recompact and retest until specified compaction is obtained. SECTION 312000 - EARTH MOVING Page 11 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 3.19 PROTECTION A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris. B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions. 1. Scarify or remove and replace soil material to depth as directed by Engineer; reshape and recompact. C. Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing. 1. Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to greatest extent possible. 3.20 DISPOSAL OF SURPLUS AND WASTE MATERIALS A. Disposal: Remove surplus satisfactory soil and waste material, including unsatisfactory soil, trash, and debris, and legally dispose of it off Owner's property. END OF SECTION 312000 SECTION 312000 - EARTH MOVING Page 12 of 12 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, L.LC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 312501- EROSION AND SEDIMENT CONTROL PART 1-GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. B. U.S. Environmental Protection Agency Publication 430/9-73-007 Processes, Procedures and Methods to Control Pollution Resulting from All Construction Activity. C. North Carolina Erosion and Sediment Control Planning and Design Manual, 2006 Revision. 1.2 SUMMARY A. Related Section include the following: 1. Division 31 Section "Earth Moving." 2. Division 31 Section "Site Clearing." 3. Division 32 Section "Turf and Grasses." 1.3 REVIEW AND/OR INSPECTION OF EROSION AND SEDIMENTATION CONTROL MEASURES A. Construction under this project shall be subject to review and/or inspection by the appropriate state and federal agencies responsible for ensuring the adequacy of erosion and sedimentation control measures. B. An erosion and sedimentation control plan shall be approved by NCDENR prior to disturbance of any work area. Any deviations from the State-approved plan proposed by the Contractor shall be: 1. Designed and sealed by a qualified Professional Engineer registered in the State of North Carolina. 2. Submitted to the Owner for review and approval 3. Approved in writing by the NCDENR. a. Work involving proposed deviations shall not be performed until the deviations have been approved by NCDENR. b. All costs associated with designing and obtaining approval of the proposed deviations shall be paid by the Contractor. SECTION 312501- EROSION AND SEDIMENT CONTROL Page 1 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1.4 SUBMITTALS A. Materials Specification Data: At least 14 days prior to use of any manufactured erosion and sediment control products on site, the Contractor shall submit the specification data sheets and manufacturer's installation requirements for all products that will be incorporated into the erosion and sediment control measures. PART 2 - PRODUCTS 2.1 GEOTEXTILE A. See Contract Drawings. 2.2 SEED AND MULCH A. See Division 32 Section "Turf and Grasses" of these Specifications. 2.3 EXTRA STRENGTH SILT FENCE A. See Contract Drawings. 2.4 EROSION CONTROL BLANKET A. See Division 32 Section "Turf and Grasses" of these Specifications. 2.5 CHANNEL CHECK STRUCTURES A. Channel check structures may be constructed using stone, wattles of appropriate diameter, or other suitable products accepted by the Owner. B. Application and anticipated flows will determine required product size. 2.6 TEMPORARY SLOPE DRAINS A. A flexible tubing (conduit) extending from the top to the bottom of a cut or fill slope sized to adequately transmit runoff with out overtopping. B. Construct the conduit from heavy-duty, flexible material such as non-perforated, corrugated plastic pipe. Anchor the conduit in position using pairs of wooden stakes. C. Construct the entrance to the slope drain of a standard flared-end section of pipe with a minimum 6-inch metal toe plate. A standard T-section fitting may be used as long as piping is prevented. SECTION 312501- EROSION AND SEDIMENT CONTROL Page 2 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 D. Utilize a diversion dike, ditch, or other structure approved by the Owner to direct surface runoff to the inlet of the slope drain. 2.7 RIPRAP: A. See Division 31 Section "Earth Moving" of these Specifications. PART 3 - EXECUTION 3.1 GENERAL A. An Erosion and Sedimentation Control (E&SC) plan shall be approved by NCDENR prior to disturbance of any work area. B. Provide, install, maintain, and remove E&SC components necessary for the implementation of E&SC measures specified herein, on the Drawings, in the E&SC plan, and in accordance with local, state, and federal requirements to minimize soil erosion and sedimentation from disturbed areas. 1. E&SC measures, including sediment barriers, shall be installed prior to the disturbance of any work area. 2. The Contractor shall minimize the total amount of disturbed area, at any time, during construction. 3. The limits of disturbed areas are shown on the Drawings. The Contractor shall not disturb any areas outside the disturbance limits shown on the Drawings without prior written authorization from the Owner. 4. Maintain undisturbed vegetated buffers adjacent to streams, wetlands, or other designated resources in accordance with federal, state, and local requirements and as shown on the Drawings. 5. Install sediment barriers along the perimeter of disturbed areas to remove sediments from surficial runoff as shown on the Drawings. C. A Spill Prevention Control and Countermeasure Plan shall be prepared by a qualified engineer and implemented at the beginning of the Work. 3.2 ROADWAYS A. Construct and stabilize ditches, cross drains, silt fences, and slope protection concurrently with roadways. B. Install channel check structures or Erosion Control Blankets (ECBs) within ditches. Remove sediment accumulated behind check structures when it reaches one half the original height of the check structure. SECTION 312501- EROSION AND SEDIMENT CONTROL Page 3 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 3.3 TEMPORARY STOCKPILES A. See Division 31 Section "Site Clearing" of these Specifications. 3.4 TEMPORARY SEEDING A. See Division 32 Section "Turf and Grasses" of these Specifications. 3.5 EROSION CONTROL BLANKET A. See Division 32 Section "Turf and Grasses" of these Specifications. 3.6 SILT FENCES A. See Project Drawings. 3.7 FLEXIBLE GROWTH MEDIUM (FGM) AND BONDED FIBER MATRIX (BFM) A. See Division 32 Section "Turf and Grasses" of these Specifications. 3.8 TEMPORARY SLOPE DRAINS A. Place slope drains on undisturbed soil or well-compacted fill at locations shown on the Drawings. B. Slightly slope the section of pipe under the dike toward its outlet. C. Hand tamp the soil under and around the entrance section. Minimize risk of washouts by properly backfilling around the "haunches" with stable soil material and hand compacting in 4- inch lifts to achieve firm contact between the pipe and the soil. D. Ensure that the fill over the drain at the top of the slope has minimum dimensions of 1.5 ft depth, 4 ft top width, and 3:1 top slopes E. Ensure that all slope drain connections are watertight. F. Ensure that all fill material is well-compacted. Securely fasten the exposed section of the drain with grommets or stakes spaced a maximum of 10 ft apart. G. Extend the drain beyond the toe of the slope and protect the outlet from erosion. H. Make the settled, compacted dike ridge no less than 1 ft above the top of the pipe at every point. 1. Immediately stabilize all disturbed areas following construction SECTION 312501- EROSION AND SEDIMENT CONTROL Page 4 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC 3.9 SEDIMENT BASINS DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. Embankment portions of sediment basins shall be constructed as shown on the Drawings using fill, placed and compacted in accordance with the requirements of Division 31 Section "Earth Moving." 1. The subgrade for each embankment shall be inspected and approved by the Owner prior to fill placement. 2. Undercutting and replacement of unsuitable material may be required by the Owner. 3. Compaction of fill using hand-operated equipment may be required around the riser and discharge pipes. B. Provide risers, trash guards, discharge pipes, aggregate materials, and other items as shown on the Drawings. 3.10 MAINTENANCE A. See Division 31 Section "Site Clearing" of these Specifications. 3.11 REMOVAL OF TEMPORARY WORKS A. Remove all trapped sediments from structures prior to removing the structures. Properly dispose of sediments in accordance with North Carolina Department of Environment and Natural Resources (NCDENR) guidelines. B. Remove embankments and other structures and dispose of removed materials properly. C. Backfill depressions with properly compacted fill and grade areas to the extent required to promote positive drainage and to restore an appearance in keeping with the surrounding undisturbed areas. END OF SECTION 312501 SECTION 312501- EROSION AND SEDIMENT CONTROL Page 5 of 5 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 321216 - ASPHALT PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Cold milling of existing hot-mix asphalt pavement. 2. Hot-mix asphalt patching. 3. Hot-mix asphalt paving. 4. Hot-mix asphalt paving overlay. B. Related Sections: 1. Division 31 Section "Earth Moving" for aggregate base course and for aggregate pavement shoulders. 1.3 DEFINITION A. Hot-Mix Asphalt Paving Terminology: Refer to ASTM D 8 for definitions of terms. 1.4 SUBMITTALS A. Product Data: For each type of product indicated. Include technical data and tested physical and performance properties. 1. Job-Mix Designs: Certification, by authorities having jurisdiction, of approval of each job mix proposed for the Work. B. Qualification Data: For qualified manufacturer, Installer, and testing agency. C. Material Certificates: For each paving material, from manufacturer. D. Material Test Reports: For each paving material. SECTION 321216 - ASPHALT PAVING Page 1 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 1.5 QUALITY ASSURANCE A. Manufacturer Qualifications: A paving-mix manufacturer registered with and approved by authorities having jurisdiction or the NCDOT of state in which Project is located. 1. Source shall be on the NCDOT Approved Source List B. Testing Agency Qualifications: Qualified according to ASTM D 3666 for testing indicated. C. Regulatory Requirements: Comply with materials, workmanship, and other applicable requirements of NCDOT for asphalt paving work. 1. Measurement and payment provisions and safety program submittals included in standard NCDOT specifications do not apply to this Section. D. Preinstallation Conference: Conduct conference at Project site. Review methods and procedures related to hot-mix asphalt paving including, but not limited to, the following: a. Review proposed sources of paving materials, including capabilities and location of plant that will manufacture hot-mix asphalt. b. Review condition of subgrade and preparatory work. C. Review requirements for protecting paving work, including restriction of traffic during installation period and for remainder of construction period. d. Review and finalize construction schedule and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays. 1.6 DELIVERY, STORAGE, AND HANDLING A. Deliver pavement-marking materials to Project site in original packages with seals unbroken and bearing manufacturer's labels containing brand name and type of material, date of manufacture, and directions for storage. B. Store pavement-marking materials in a clean, dry, protected location within temperature range required by manufacturer. Protect stored materials from direct sunlight. 1.7 PROJECT CONDITIONS A. Environmental Limitations: Do not apply asphalt materials if subgrade is wet or excessively damp, if rain is imminent or expected before time required for adequate cure, or if the following conditions are not met: 1. Prime Coat: Minimum surface temperature of 60 deg F. 2. Tack Coat: Minimum surface temperature of 60 deg F. 3. Slurry Coat: Comply with weather limitations in ASTM D 3910. SECTION 321216 - ASPHALT PAVING Page 2 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 4. Asphalt Base Course: Minimum surface temperature of 40 deg F and rising at time of placement. 5. Asphalt Surface Course: Minimum surface temperature of 60 deg F at time of placement. B. Pavement-Marking Paint: Proceed with pavement marking only on clean, dry surfaces and at a minimum ambient or surface temperature of 40 deg F for oil-based materials, 55 deg F for water-based materials, and not exceeding 95 deg F. PART2-PRODUCTS 2.1 AGGREGATES A. General: Use materials and gradations that have performed satisfactorily in previous installations. B. Coarse Aggregate: ASTM D 692, sound; angular crushed stone, crushed gravel, or cured, crushed blast-furnace slag. C. Fine Aggregate: AASHTO M 29, sharp-edged natural sand or sand prepared from stone, gravel, cured blast-furnace slag, or combinations thereof. 1. For hot-mix asphalt, limit natural sand to a maximum of 20 percent by weight of the total aggregate mass. D. Mineral Filler: AASHTO M 17, rock or slag dust, hydraulic cement, or other inert material. 2.2 ASPHALT MATERIALS A. Asphalt Binder: AASHTO M 320, PG 64-22. B. Prime Coat: Asphalt emulsion prime coat complying with NCDOT requirements. C. Tack Coat: Unless otherwise specified in the contract, the Contractor may utilize any of the grades accepted by NCDOT. D. Water: Potable. 2.3 AUXILIARY MATERIALS A. Pavement-Marking Paint: The pavement-marking paint complying with NCDOT requirements. 2.4 MIXES A. Hot-Mix Asphalt: Dense, hot-laid, hot-mix asphalt plant mixes approved by Owner and NCDOT; designed according to procedures in North Carolina Department of Transportation, SECTION 321216 - ASPHALT PAVING Page 3 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 "Hot Mix Asphalt, Quality Management System Manual, Superpave," 2006 Edition; and complying with the following requirement: 1. Provide approved mixes with a history of satisfactory performance in geographical area where Project is located. PART 3 - EXECUTION 3.1 EXAMINATION A. Verify that subgrade is dry and in suitable condition to begin paving. B. Proof-roll subgrade below pavements with heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding. Do not proof-roll wet or saturated subgrades. 1. Completely proof-roll subgrade parallel to the direction of the roadway. Limit vehicle speed to 3 mph. 2. Proof roll with a loaded 10-wheel, tandem-axle dump truck weighing not less than 15 tons. 3. Excavate soft spots, unsatisfactory soils, and areas of excessive pumping or rutting, as determined by Owner, and replace with compacted backfill or fill as directed. C. Proceed with paving only after unsatisfactory conditions have been corrected. 3.2 COLD MILLING A. Clean existing pavement surface of loose and deleterious material immediately before cold milling. Remove existing asphalt pavement by cold milling to grades and cross sections indicated. 1. Mill to a depth specified by Owner. 2. Mill to a uniform finished surface free of excessive gouges, grooves, and ridges. 3. Control rate of milling to prevent tearing of existing asphalt course. 4. Repair or replace curbs, manholes, and other construction damaged during cold milling. 5. Excavate and trim unbound-aggregate base course, if encountered, and keep material separate from milled hot-mix asphalt. 6. Transport milled hot-mix asphalt to asphalt recycling facility. 7. Keep milled pavement surface free of loose material and dust. 3.3 PATCHING A. Hot-Mix Asphalt Pavement: Saw cut perimeter of patch and excavate existing pavement section to sound base. Excavate rectangular or trapezoidal patches, extending 12 inches into adjacent sound pavement, unless otherwise indicated. Cut excavation faces vertically. Remove excavated material. Recompact existing unbound-aggregate base course to form new subgrade. SECTION 321216 - ASPHALT PAVING Page 4 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 B. Tack Coat: Apply uniformly to vertical surfaces abutting or projecting into new, hot-mix asphalt paving at a rate of 0.05 to 0.15 gal./sq. yd.. 1. Allow tack coat to cure undisturbed before applying hot-mix asphalt paving. 2. Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Remove spillages and clean affected surfaces. C. Patching: Partially fill excavated pavements with hot-mix asphalt base mix and, while still hot, compact. Cover asphalt base course with compacted, hot-mix surface layer finished flush with adjacent surfaces. 3.4 SURFACE PREPARATION A. General: Immediately before placing asphalt materials, remove loose and deleterious material from substrate surfaces. Ensure that prepared subgrade is ready to receive paving. B. Prime Coat: Apply uniformly over surface of compacted unbound-aggregate base course at a rate of 0.15 to 0.50 gal./sq. yd.. Apply enough material to penetrate and seal but not flood surface. Allow prime coat to cure. 1. If prime coat is not entirely absorbed within 24 hours after application, spread sand over surface to blot excess asphalt. Use enough sand to prevent pickup under traffic. Remove loose sand by sweeping before pavement is placed and after volatiles have evaporated. 2. Protect primed substrate from damage until ready to receive paving. C. Tack Coat: Apply uniformly to surfaces of existing pavement at a rate of 0.05 to 0.15 gal./sq. yd.. 1. Allow tack coat to cure undisturbed before applying hot-mix asphalt paving. 2. Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Remove spillages and clean affected surfaces. 3.5 HOT-MIX ASPHALT PLACING A. Machine place hot-mix asphalt on prepared surface, spread uniformly, and strike off. Place asphalt mix by hand to areas inaccessible to equipment in a manner that prevents segregation of mix. Place each course to required grade, cross section, and thickness when compacted. 1. Place hot-mix asphalt base course in number of lifts and thicknesses indicated. 2. Place hot-mix asphalt surface course in single lift. 3. Spread mix at minimum temperature of 250 deg F. 4. Begin applying mix along centerline of crown for crowned sections and on high side of one-way slopes unless otherwise indicated. 5. Regulate paver machine speed to obtain smooth, continuous surface free of pulls and tears in asphalt-paving mat. B. Place paving in consecutive strips not less than 10 feet wide unless infill edge strips of a lesser width are required. SECTION 321216 - ASPHALT PAVING Page 5 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 After first strip has been placed and rolled, place succeeding strips and extend rolling to overlap previous strips. Complete a section of asphalt base course before placing asphalt surface course. C. Promptly correct surface irregularities in paving course behind paver. Use suitable hand tools to remove excess material forming high spots. Fill depressions with hot-mix asphalt to prevent segregation of mix; use suitable hand tools to smooth surface. 3.6 JOINTS A. Construct joints to ensure a continuous bond between adjoining paving sections. Construct joints free of depressions, with same texture and smoothness as other sections of hot-mix asphalt course. 1. Clean contact surfaces and apply tack coat to joints. 2. Offset longitudinal joints, in successive courses, a minimum of 6 inches. 3. Offset transverse joints, in successive courses, a minimum of 24 inches. 4. Construct transverse joints at each point where paver ends a day's work and resumes work at a subsequent time. Construct these joints using either "bulkhead" or "papered" method according to Al MS-22, for both "Ending a Lane" and "Resumption of Paving Operations." 5. Compact joints as soon as hot-mix asphalt will bear roller weight without excessive displacement. 6. Compact asphalt at joints to a density within 2 percent of specified course density. 3.7 COMPACTION A. General: Begin compaction as soon as placed hot-mix paving will bear roller weight without excessive displacement. Compact hot-mix paving with hot, hand tampers or with vibratory- plate compactors in areas inaccessible to rollers. Complete compaction before mix temperature cools to 185 deg F. B. Breakdown Rolling: Complete breakdown or initial rolling immediately after rolling joints and outside edge. Examine surface immediately after breakdown rolling for indicated crown, grade, and smoothness. Correct laydown and rolling operations to comply with requirements. C. Intermediate Rolling: Begin intermediate rolling immediately after breakdown rolling while hot-mix asphalt is still hot enough to achieve specified density. Continue rolling until hot-mix asphalt course has been uniformly compacted to the following density: Average Density: 92 percent of reference maximum theoretical density according to ASTM D 2041, but not less than 90 percent nor greater than 96 percent. D. Finish Rolling: Finish roll paved surfaces to remove roller marks while hot-mix asphalt is still warm. SECTION 321216 - ASPHALT PAVING Page 6 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18. 2008 E. Edge Shaping: While surface is being compacted and finished, trim edges of pavement to proper alignment. Bevel edges while asphalt is still hot; compact thoroughly. F. Repairs: Remove paved areas that are defective or contaminated with foreign materials and replace with fresh, hot-mix asphalt. Compact by rolling to specified density and surface smoothness. G. Protection: After final rolling, do not permit vehicular traffic on pavement until it has cooled and hardened. H. Erect barricades to protect paving from traffic until mixture has cooled enough not to become marked. 3.8 INSTALLATION TOLERANCES A. Pavement Thickness: Compact each course to produce the thickness indicated within the following tolerances: 1. Intermediate Base Course: Plus or minus 1/2 inch. 2. Surface Course: Plus 1/4 inch, no minus. B. Pavement Surface Smoothness: Compact each course to produce a surface smoothness within the following tolerances as determined by using a 10-foot straightedge applied transversely or longitudinally to paved areas: 1. Intermediate Base Course: 1/4 inch. 2. Surface Course: 1/8 inch. 3. Crowned Surfaces: Test with crowned template centered and at right angle to crown. Maximum allowable variance from template is 1/4 inch. 3.9 PAVEMENT MARKING A. Do not apply pavement-marking paint until layout, colors, and placement have been verified with Owner. B. Allow paving to age for 30 days before starting pavement marking. C. Sweep and clean surface to eliminate loose material and dust. 3.10 FIELD QUALITY CONTROL A. Testing Agency: Engage a qualified testing agency to perform tests and inspections. B. Thickness: In-place compacted thickness of hot-mix asphalt courses will be determined according to ASTM D 3549. SECTION 321216 - ASPHALT PAVING Page 7 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 C. Surface Smoothness: Finished surface of each hot-mix asphalt course will be tested for compliance with smoothness tolerances. D. In-Place Density: Testing agency will take samples of uncompacted paving mixtures and compacted pavement according to AASHTO T 168. 1. Reference maximum theoretical density will be determined by averaging results from four samples of hot-mix asphalt-paving mixture delivered daily to site, prepared according to ASTM D 2041, and compacted according to job-mix specifications. 2. In-place density of compacted pavement will be determined by testing core samples according to ASTM D 1188 or ASTM D 2726. a. The amount and frequency of core samples shall be in accordance with NCDOT specifications. E. Replace and compact hot-mix asphalt where core tests were taken. F. Remove and replace or install additional hot-mix asphalt where test results or measurements indicate that it does not comply with specified requirements at Contractor's expense. 3.11 DISPOSAL A. Except for material indicated to be recycled, remove excavated materials from Project site and legally dispose of them in an EPA-approved landfill. 1. Do not allow milled materials to accumulate on-site. END OF SECTION 321216 SECTION 321216 - ASPHALT PAVING Page 8 of 8 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 323113 - CHAIN LINK FENCES AND GATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Chain-Link Fences: Industrial. 2. Gates: horizontal slide or swing. B. Related Sections include the following: 1. Division 31 Section "Earth Moving" for site excavation, fill, and backfill where chain- link fences and gates are located. 1.3 PERFORMANCE REQUIREMENTS A. Structural Performance: Provide chain-link fences and gates capable of withstanding the effects of gravity loads and the following loads and stresses within limits and under conditions indicated: 1. Minimum Post Size and Maximum Spacing for Wind Velocity Pressure: Determine based on mesh size and pattern specified, and on the following minimum design wind pressures and according to CLFMI WLG 2445: a. Wind Speed: 90 mph. b. Fence Height: 8 feet. C. Line Post Group: IA, ASTM F 1043, Schedule 40 steel pipe. d. Wind Exposure Category: B. 2. Determine minimum post size, group, and section according to ASTM F 1043 for framework up to 12 feet high, and post spacing not to exceed 10 feet. B. Grounding Protection System: Maximum grounding-resistance value of 25 ohms under normal dry conditions. SECTION 323113 - CHAIN LINK FENCES AND GATES Page 1 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 1.4 SUBMITTALS A. Product Data: Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for chain-link fences and gates. 1. Fence and gate posts, rails, and fittings. 2. Chain-link fabric, reinforcements, and attachments. 3. Gates and hardware. 4. Gate operators, including operating instructions. 5. Accessories: Barbed wire and Barbed tape. B. Drawings: Show locations of fences, gates, posts, rails, tension wires, details of extended posts, extension arms, gate swing, or other operation, hardware, and accessories. Indicate materials, dimensions, sizes, weights, and finishes of components. Include plans, gate elevations, sections, details of post anchorage, attachment, bracing, and other required installation and operational clearances. C. Qualification Data: For Installer. 1.5 QUALITY ASSURANCE A. Installer Qualifications: An experienced installer who has completed chain-link fences and gates similar in material, design, and extent to those indicated for this Project and whose work has resulted in construction with a record of successful in-service performance. 1.6 PROJECT CONDITIONS A. Field Measurements: Verify layout information for chain-link fences and gates shown on Drawings in relation to property survey and existing structures. Verify dimensions by field measurements. B. Interruption of Existing Utility Service: Do not interrupt utility services to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated: 1. Notify Owner no less than one regular work week in advance of proposed interruption of utility services. 2. Do not proceed with interruption of utility services without Owner's written permission. PART 2 - PRODUCTS 2.1 CHAIN-LINK FENCE FABRIC A. General: 8 feet height. Provide fabric in one-piece heights measured between top and bottom of outer edge of selvage knuckle or twist. Comply with ASTM A 392, CLFMI CLF 2445, and requirements indicated below: SECTION 323113 - CHAIN LINK FENCES AND GATES Page 2 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 1. Steel Wire Fabric: Metallic-coated wire with a diameter of 0.192 inch. a. Mesh Size: 2 inches. b. Weight of Metallic (Zinc) Coating: ASTM A 392, Type II, Class 1, 1.2 oz./sq. ft. with zinc coating applied after weaving. 2. Selvage: Twisted top and knuckled bottom. 2.2 INDUSTRIAL FENCE FRAMING A. Posts and Rails: Comply with ASTM F 1043 for framing, ASTM F 1083 for Group IC round pipe, and the following: I. Group: IA, round steel pipe, Schedule 40. 2. Fence Height: 8 feet. 3. Strength Requirement: Heavy industrial according to ASTM F 1043. 4. Post Diameter and Thickness: According to ASTM F 1043. 5. Post Size and Thickness: According to ASTM F 1043. a. Top Rail: 1.66 inches. b. Line Post: 2.375 inches. C. End, Corner and Pull Post: 2.875 inches. d. Swing Gate Post: According to ASTM F 900. e. Horizontal-Slide Gate Post: According to ASTM F 1184. 6. Coating for Steel Framing: a. Metallic Coating: 1) Type A, consisting of not less than minimum 2.0-oz./sq. ft. average zinc coating per ASTM A 123/A 123M or 4.0-oz./sq. ft. zinc coating per ASTM A 653/A 653M. 2.3 TENSION WIRE A. General: Provide horizontal tension wire at the following locations: 1. Location: As indicated. B. Metallic-Coated Steel Wire: 0.177-inch- diameter, marcelled tension wire complying with ASTM A 817, ASTM A 824, and the following: 1. Metallic Coating: Type II, zinc coated (galvanized) by hot-dip process, with the following minimum coating weight: a. Matching chain-link fabric coating weight. SECTION 323113 - CHAIN LINK FENCES AND GATES Page 3 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC 2.4 INDUSTRIAL SWING GATES DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 A. General: Comply with ASTM F 900 for single and double swing gate types. 1. Metal Pipe and Tubing: Galvanized steel. Comply with ASTM F 1043 and ASTM F 1083 for materials and protective coatings. B. Frames and Bracing: Fabricate members from round, galvanized steel tubing with outside dimension and weight according to ASTM F 900 and the following: 1. Gate Fabric Height: 2 inches less than adjacent fence height. 2. Leaf Width: 36 inches. 3. Frame Members: a. Tubular Steel: 1.66 inches round. C. Frame Corner Construction: 1. Welded or assembled with corner fittings and 5/16-inch- diameter, adjustable truss rods for panels 5 feet wide or wider. D. Hardware: Latches permitting operation from both sides of gate, hinges, center gate stops and keepers for each gate leaf more than 5 feet wide. Fabricate latches with integral eye openings for padlocking; padlock accessible from both sides of gate. 2.5 FITTINGS A. General: Comply with ASTM F 626. B. Post and Line Caps: Provide for each post. 1. Line post caps with loop to receive tension wire or top rail. C. Rail and Brace Ends: Attach rails securely to each gate, corner, pull, and end post. D. Rail Fittings: Provide the following: 1. Top Rail Sleeves: Pressed-steel or round-steel tubing not less than 6 inches long. 2. Rail Clamps: Line and corner boulevard clamps for connecting intermediate and bottom rails in the fence line-to-line posts. E. Tension and Brace Bands: Pressed steel. F. Tension Bars: Steel, length not less than 2 inches shorter than full height of chain-link fabric. Provide one bar for each gate and end post, and two for each corner and pull post, unless fabric is integrally woven into post. G. Truss Rod Assemblies: Steel, hot-dip galvanized after threading rod and turnbuckle or other means of adjustment. SECTION 323113 - CHAIN LINK FENCES AND GATES Page 4 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 H. Barbed Wire Arms: Pressed steel or cast iron, with clips, slots, or other means for attaching strands of barbed wire, and means for attaching to posts, integral with post cap; for each post, unless otherwise indicated, and as follows: 1. Line posts with arms that accommodate top rail or tension wire. 2. Corner arms at fence corner posts, unless extended posts are indicated. 3. Type II, single vertical arm. 1. Tie Wires, Clips, and Fasteners: According to ASTM F 626. 1. Standard Round Wire Ties: For attaching chain-link fabric to posts, rails, and frames, complying with the following: a. Hot-Dip Galvanized Steel: 0.148-inch- diameter wire; galvanized coating thickness matching coating thickness of chain-link fence fabric. J. Finish: 1. Metallic Coating for Pressed Steel or Cast Iron: Not less than 1.2 oz. /sq. ft. zinc. 2.6 BARBED WIRE A. Zinc-Coated Steel Barbed Wire: Comply with ASTM A 121, Chain-Link Fence grade for the following two-strand barbed wire: 1. Standard Size and Construction: 0.099-inch- diameter line wire with 0.080-inch- diameter, 2-point round barbs spaced not more than 4 inches o.c. 2.7 BARBED TAPE A. Wire-Reinforced Tape: 430 Series stainless steel hardened to Rockwell (30N) 40 to 45, 0.025 inch thick by 1 inch wide before fabrication; with 4-point, needle-sharp barbs permanently cold clenched to a minimum of 230 deg F around a core wire. 1. Core wire: 0.098-inch- diameter, high-tensile-strength, zinc-coated steel complying with ASTM A 764 stainless steel complying with ASTM A 313/A 313M. B. Clips: Stainless steel, 0.065 inch thick by 0.375 inch wide, capable of withstanding a minimum 150-lbf pull load to limit extension of coil, resulting in a concertina pattern when deployed. C. Tie Wires: Stainless steel, 0.065 inch diameter. D. Fabrication: Continuous coils of barbed tape as defined in ASTM F 1379 for the following characteristics: 1. Configuration: Single coil. 2. Style: Concertina pattern. 3. Coil Diameter(s): 18 inches. SECTION 323113 - CHAIN LINK FENCES AND GATES Page 5 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 4. Coil Loop Spacing(s): Manufacturer's standard. 5. Barb Length Classification: Medium, 0.4-inch barb. 6. Barb Spacing: 4 inches o.c. 7. Barb Set: Straight. 2.8 FENCE GROUNDING A. Conductors: Bare, solid wire for No. 6 AWG and smaller; stranded wire for No. 4 AWG and larger. 1. Material above Finished Grade: Copper. 2. Material on or below Finished Grade: Copper. 3. Bonding Jumpers: Braided copper tape, 1 inch wide, woven of No. 30 AWG bare copper wire, terminated with copper ferrules. B. Connectors and Grounding Rods: Comply with UL 467. 1. Connectors for Below-Grade Use: Exothermic welded type. 2. Grounding Rods: Copper-clad steel. a. Size: 3/4 by 6 foot, minimum. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine areas and conditions, with Installer present, for compliance with requirements for a verified survey of property lines and legal boundaries, site clearing, earthwork, pavement work, and other conditions affecting performance. 1. Do not begin installation before final grading is completed, unless otherwise permitted by Owner. 2. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 PREPARATION A. Stake locations of fence lines, gates, and terminal posts. Do not exceed intervals of 500 feet or line of sight between stakes. Indicate locations of utilities, lawn sprinkler system, underground structures, benchmarks, and property monuments. 3.3 INSTALLATION, GENERAL A. Install chain-link fencing to comply with ASTM F 567 and more stringent requirements specified. SECTION 323113 - CHAIN LINK FENCES AND GATES Page 6 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 3.4 CHAIN-LINK FENCE INSTALLATION A. Post Setting: Set posts by mechanically driving into soil at indicated spacing into firm, undisturbed soil. 1. Verify that posts are set plumb, aligned, and at correct height and spacing, and hold in position during setting with mechanical devices. 2. Mechanically Driven Posts: Drive into soil to depth of 36 inches. Protect post top to prevent distortion. B. Terminal Posts: Locate terminal end, corner, and gate posts per ASTM F 567 and terminal pull posts at changes in horizontal or vertical alignment of 15 degrees or more. C. Line Posts: Space line posts uniformly at 10 feet o.c. D. Post Bracing and Intermediate Rails: Install according to ASTM F 567, maintaining plumb position and alignment of fencing. Install braces at end and gate posts and at both sides of corner and pull posts. Locate horizontal braces at midheight of fabric 6 feet or higher, on fences with top rail and at 2/3 fabric height on fences without top rail. Install so posts are plumb when diagonal rod is under proper tension. E. Tension Wire: Install according to ASTM F 567, maintaining plumb position and alignment of fencing. Pull wire taut, without sags. Fasten fabric to tension wire with 0.120-inch- diameter hog rings of same material and finish as fabric wire, spaced a maximum of 24 inches o.c. Install tension wire in locations indicated before stretching fabric. 1. Top Tension Wire: Install tension wire through post cap loops. 2. Bottom Tension Wire: Install tension wire within 6 inches of bottom of fabric and tie to each post with not less than same diameter and type of wire. F. Top Rail: Install according to ASTM F 567, maintaining plumb position and alignment of fencing. Run rail continuously through line post caps, bending to radius for curved runs and terminating into rail end attached to posts or post caps fabricated to receive rail at terminal posts. Provide expansion couplings as recommended in writing by fencing manufacturer. G. Bottom Rails: Install, spanning between posts. H. Chain-Link Fabric: Apply fabric to outside of enclosing framework. Leave 2 inches between finish grade or surface and bottom selvage, unless otherwise indicated. Pull fabric taut and tie to posts, rails, and tension wires. Anchor to framework so fabric remains under tension after pulling force is released. Tension or Stretcher Bars: Thread through fabric and secure to end, corner, pull, and gate posts with tension bands spaced not more than 15 inches o.c. Tie Wires: Use wire of proper length to firmly secure fabric to line posts and rails. Attach wire at 1 end to chain-link fabric, wrap wire around post a minimum of 180 degrees, and attach other SECTION 323113 - CHAIN LINK FENCES AND GATES Page 7 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 end to chain-link fabric per ASTM F 626. Bend ends of wire to minimize hazard to individuals and clothing. 1. Maximum Spacing: Tie fabric to line posts at 12 inches o.c. and to braces at 24 inches O.C. K. Fasteners: Install nuts for tension bands and carriage bolts on the side of the fence opposite the fabric side. L. Barbed Wire: Install barbed wire uniformly spaced, angled toward security side of fence. Pull wire taut and install securely to extension arms and secure to end post or terminal arms. M. Barbed Tape: Install barbed tape uniformly in configurations indicated and fasten securely to prevent movement or displacement. N. Tennis Court Fencing: Construct tennis court fence according to ASTM F 969. 3.5 GATE INSTALLATION A. Install gates according to manufacturer's written instructions, level, plumb, and secure for full opening without interference. Attach fabric as for fencing. Attach hardware using tamper- resistant or concealed means. Install ground-set items in concrete for anchorage. Adjust hardware for smooth operation and lubricate where necessary. 3.6 GROUNDING AND BONDING A. Fence Grounding: Install at maximum intervals of 500 feet except as follows: I. Gates and Other Fence Openings: Ground fence on each side of opening. a. Bond metal gates to gate posts. b. Bond across openings, with and without gates, except openings indicated as intentional fence discontinuities. Use No. 2 AWG wire and bury it at least 18 inches below finished grade. B. Protection at Crossings of Overhead Electrical Power Lines: Ground fence at location of crossing and at a maximum distance of 10 feet on each side of crossing. C. Grounding Method: At each grounding location, drive a grounding rod vertically until the top is 6 inches below finished grade. Connect rod to fence with No. 6 AWG conductor. Connect conductor to each fence component at the grounding location, including the following: I. Each Barbed Wire Strand. Make grounding connections to barbed wire with wire-to-wire connectors designed for this purpose. 2. Each Barbed Tape Coil: Make grounding connections to barbed tape with connectors designed for this purpose. D. Bonding Method for Gates: Connect bonding jumper between gate post and gate frame. SECTION 323113 - CHAIN LINK FENCES AND GATES Page 8 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 E. Connections: Make connections so possibility of galvanic action or electrolysis is minimized. Select connectors, connection hardware, conductors, and connection methods so metals in direct contact will be galvanically compatible. I. Use electroplated or hot-tin-coated materials to ensure high conductivity and to make contact points closer in order of galvanic series. 2. Make connections with clean, bare metal at points of contact. 3. Make aluminum-to-steel connections with stainless-steel separators and mechanical clamps. 4. Make aluminum-to-galvanized-steel connections with tin-plated copper jumpers and mechanical clamps. 5. Coat and seal connections having dissimilar metals with inert material to prevent future penetration of moisture to contact surfaces. F. Bonding to Lightning Protection System: If fence terminates at lightning-protected building or structure, ground the fence and bond the fence grounding conductor to lightning protection down conductor or lightning protection grounding conductor complying with NFPA 780. 3.7 FIELD QUALITY CONTROL A. Grounding-Resistance Testing: Engage a qualified independent testing and inspecting agency to perform field quality-control testing. 1. Grounding-Resistance Tests: Subject completed grounding system to a megger test at each grounding location. Measure grounding resistance not less than two full days after last trace of precipitation, without soil having been moistened by any means other than natural drainage or seepage and without chemical treatment or other artificial means of reducing natural grounding resistance. Perform tests by two-point method according to IEEE 81. 2. Excessive Grounding Resistance: If resistance to grounding exceeds specified value, notify Engineer promptly. Include recommendations for reducing grounding resistance and a proposal to accomplish recommended work. 3. Report: Prepare test reports certified by a testing agency of grounding resistance at each test location. Include observations of weather and other phenomena that may affect test results. 3.8 ADJUSTING A. Gate: Adjust gate to operate smoothly, easily, and quietly, free of binding, warp, excessive deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire operational range. Confirm that latches and locks engage accurately and securely without forcing or binding. END OF SECTION 323113 SECTION 323113 - CHAIN LINK FENCES AND GATES Page 9 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DT,A Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 SECTION 329200 - TURF AND GRASSES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract and Division 01 Specification Sections apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Seeding. 2. Hydroseeding. 3. Turf renovation. 4. Erosion-control material(s). B. Related Sections: 1. Division 31 Section "Site Clearing" for topsoil stripping and stockpiling. 2. Division 31 Section "Earth Moving" for excavation, filling and backfilling, and rough grading. 1.3 DEFINITIONS A. Finish Grade: Elevation of finished surface of planting soil. B. Subgrade: Surface or elevation of subsoil remaining after excavation is complete, or top surface of a fill or backfill before planting soil is placed. C. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms. D. Surface Soil: Soil that is present at the top layer of the existing soil profile at the Project site. In undisturbed areas, the surface soil is typically topsoil, but in disturbed areas such as urban environments, the surface soil can be subsoil. E. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown than the underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than two inches in diameter; and free of weeds, roots, toxic materials, or other nonsoil material. SECTION 329200 - TURF AND GRASSES Page 1 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1.4 SUBMITTALS A. Product Data: For each type of product indicated. 1. Pesticides and Herbicides: Include product label and manufacturer's application instructions specific to this Project. B. Certification of Grass Seed: From seed vendor for each grass-seed monostand or mixture stating the botanical and common name, percentage by weight of each species and variety, and percentage of purity, germination, and weed seed. Include the year of production and date of packaging. C. Qualification Data: For qualified landscape Installer. D. Materials Specification Data: At least 14 days prior to use of any manufactured erosion and sediment control products utilized on site, the Contractor shall submit the specification data sheets and manufacturer's installation requirements for all products that will be incorporated into the erosion and sediment control measures. 1.5 DELIVERY, STORAGE, AND HANDLING A. Seed and Other Packaged Materials: Deliver packaged materials in original, unopened containers showing weight, certified analysis, name and address of manufacturer, and indication of conformance with state and federal laws, as applicable. B. Bulk Materials: 1. Do not dump or store bulk materials near structures, utilities, walkways and pavements, or on existing turf areas or plants. 2. Provide erosion-control measures to prevent erosion or displacement of bulk materials, discharge of soil-bearing water runoff, and airborne dust reaching adjacent properties, water conveyance systems, or walkways. 3. Accompany each delivery of bulk fertilizers, lime, and soil amendments with appropriate certificates. 1.6 PROJECT CONDITIONS A. Weather Limitations: Proceed with planting only when existing and forecasted weather conditions permit planting to be performed when beneficial and optimum results may be obtained. Apply products during favorable weather conditions according to manufacturer's written instructions. 1.7 MAINTENANCE SERVICE A. Initial Turf Maintenance Service: Provide full maintenance by skilled employees of landscape Installer. Maintain as required in Part 3. Begin maintenance immediately after each area is SECTION 329200 - TURF AND GRASSES Page 2 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 planted and continue until acceptable turf is established but for not less than the following periods: 1. Seeded Turf: 60 days from date of Substantial Completion. a. When initial maintenance period has not elapsed before end of planting season, or if turf is not fully established, continue maintenance during next planting season. PART 2 - PRODUCTS 2.1 SEED A. Grass Seed: Fresh, clean, dry, new-crop seed complying with AOSA's "Journal of Seed Technology; Rules for Testing Seeds" for purity and germination tolerances. B. Seed Species: Seed of grass species as follows, with not less than 95 percent germination, not less than 85 percent pure seed, and not more than 0.5 percent weed seed: 1. Full Sun: Kentucky bluegrass (Poa pratensis), a minimum of three cultivars. 2. Sun and Partial Shade: Proportioned by weight as follows: a. 50 percent Kentucky bluegrass (Poa pratensis). b. 30 percent chewings red fescue (Festuca rubra variety). C. 10 percent perennial ryegrass (Lolium perenne). d. 10 percent redtop (Agrostis alba). 3. Shade: Proportioned by weight as follows: a. 50 percent chewings red fescue (Festuca rubra variety). b. 35 percent rough bluegrass (Poa trivialis). C. 15 percent redtop (Agrostis alba). 2.2 INORGANIC SOIL AMENDMENTS A. Lime: ASTM C 602, agricultural liming material containing a minimum of 80 percent calcium carbonate equivalent and as follows: 1. Class: T, with a minimum of 99 percent passing through No. 8 sieve and a minimum of 75 percent passing through No. 60 sieve. 2.3 FERTILIZERS A. Slow-Release Fertilizer: Granular or pelleted fertilizer consisting of 50 percent water-insoluble nitrogen, phosphorus, and potassium in the following composition: SECTION 329200 - TURF AND GRASSES Page 3 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. Composition: 20 percent nitrogen, 10 percent phosphorous, and 10 percent potassium, by weight. 2. Composition: Nitrogen, phosphorous, and potassium in amounts recommended in soil reports from a qualified soil-testing laboratory. 2.4 MULCHES A. Straw or Hay Mulch: Provide air-dry, clean, mildew- and seed-free, salt hay or threshed straw of wheat, rye, oats, or barley. 1. No material shall be used which is so wet, decayed, or compacted as to inhibit even and uniform spreading. 2. Chopped hay, grass clippings, or other short fibered material shall not be used. B. Binder for straw or hay mulch shall be approved non-staining, commercially available products that are specifically formulated for the purpose of anchoring or tacking dry mulches. 1. Asphalt binders will not be permitted. 2. The materials shall be furnished in the manufacturer's standard containers with the name of the material, the manufacturer's name, and the instructions for mixing and application appearing on each container. C. Approved mulch control netting may be used in place of or in combination with spray binders to stabilize dry mulches. D. Hydraulically Applied Mulch or Bonded Fiber Matrix (BFM): 1. The BFM shall be a spray applied wood fiber mulch with pre-mixed tackifier and vegetable based dye. 2. Composition: a. Wood Fiber: 90% (max) b. Polysaccharide crosslinked hydro-colloid polymer tackifier: 10% ±2% C. Moisture Content: 12% ±3% d. Ash Content: 1% ±1% e. Vegetable based dyed green (preferred) 3. Shall be wood fiber mulch, which shall be processed so that the fibers will remain in uniform suspension in water under agitation and will blend with grass seed, fertilizer and other additives to form a homogenous slurry. It shall have the characteristics which, upon hydraulic application, shall form a blotter-liker ground coating with moisture absorption and percolation properties and the ability to cover and hold grass seed in intimate contact with the soil. 4. The BFM shall be applied per the manufacturer's recommendations. E. Flexible Growth Medium (FGM): SECTION 329200 - TURF AND GRASSES Page 4 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 1. The FGM shall be a hydraulically-applied, flexible erosion control blanket composed of long strand, thermally processed wood fibers, crimped, interlocking fibers and performance enhancing additives. 2. Composition: a. Thermally Processed Wood Fibers: 85% (max) b. Proprietary Crosslinked Hydro-Colloid Tackifier: 10% ±1% C. Proprietary Crimped Interlocking Fibers: 5% ±1% d. Moisture Content: 12% ±3% The FGM when applied at a rate of 3500 pounds per acre, shall conform to the following; measured per test methods referenced: a. Mass per unit area: 11.5 ounces/yd 2; ASTM D 6566 b. Thickness: 0.19 inches; ASTM D 6525 C. Percent ground cover: 99%; ASTM D 6567 d. Water holding capacity: 1500%; ASTM WK2652 e. Flexural rigidity (wet): 12 ounces/yd; ASTM D 6575 f. Cover factor: 0.0066; ECTC Test Method #2 g. Percent effectiveness: 99.00%; ECTC Test Method #2 h. Shear Stress: I pound/ft2; ECTC Test Method #3 F. Mulches shall contain no growth or germination inhibiting factors. Wood fibers shall be supplied in the manufacturer's stand containers with the name of the material, net weight of contents, the manufacturer's name and the air dry weight of fiber (equivalent to 10 percent moisture appearing on each container. 2.5 EROSION-CONTROL MATERIALS A. Erosion-Control Blankets: Biodegradable wood excelsior, straw, or coconut-fiber mat enclosed in a photodegradable plastic mesh. Include manufacturer's recommended steel wire staples, 6 inches long. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine areas to be planted for compliance with requirements and other conditions affecting performance. I. Verify that no foreign or deleterious material or liquid such as paint, paint washout, concrete slurry, concrete layers or chunks, cement, plaster, oils, gasoline, diesel fuel, paint thinner, turpentine, tar, roofing compound, or acid has been deposited in soil within a planting area. 2. Do not mix or place soils and soil amendments in frozen, wet, or muddy conditions. SECTION 329200 - TURF AND GRASSES Page 5 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 3. Suspend soil spreading, grading, and tilling operations during periods of excessive soil moisture until the moisture content reaches acceptable levels to attain the required results. 4. Uniformly moisten excessively dry soil that is not workable and which is too dusty. B. Proceed with installation only after unsatisfactory conditions have been corrected. C. If contamination by foreign or deleterious material or liquid is present in soil within a planting area, remove the soil and contamination as directed by Owner and replace with new planting soil. 3.2 PREPARATION A. Protect structures, utilities, sidewalks, pavements, and other facilities, trees, shrubs, and plantings from damage caused by planting operations. 1. Protect adjacent and adjoining areas from hydroseeding and hydromulching overspray. 2. Protect grade stakes set by others until directed to remove them. B. Install erosion-control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways. 3.3 PREPARATION FOR EROSION-CONTROL MATERIALS A. Prepare area as specified in accordance with manufacturer's recommendations. B. For erosion-control mats, install planting soil in two lifts, with second lift equal to thickness of erosion-control mats. Install erosion-control mat and fasten as recommended by material manufacturer. C. Fill cells of erosion-control mat with planting soil and compact before planting. D. For erosion-control blanket or mesh, install from top of slope, working downward, and as recommended by material manufacturer for site conditions. Install as recommended by material manufacturer. E. Moisten prepared area before planting if surface is dry. Water thoroughly and allow surface to dry before planting. Do not create muddy soil. 3.4 SEEDING A. Sow seed with spreader or seeding machine. Do not broadcast or drop seed when wind velocity exceeds 5 mph. Evenly distribute seed by sowing equal quantities in two directions at right angles to each other. 1. Do not use wet seed or seed that is moldy or otherwise damaged. 2. Do not seed against existing trees. Limit extent of seed to outside edge of planting saucer. SECTION 329200 - TURF AND GRASSES Page 6 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal Dillsboro, North Carolina Duke Energy Carolinas, LLC B. Sow seed at a total rate of 21b/1000 sq. ft for Kentucky Fescue. DTA Specification No. 024.0029.0000 Revision No.: Review 2 December 18, 2008 C. Rake seed lightly into top 1/8 inch of soil, roll lightly, and water with fine spray. D. Protect seeded areas with slopes exceeding 1:4 with erosion-control blankets installed and stapled according to manufacturer's written instructions. E. Protect seeded areas with slopes not exceeding 1:4 by spreading straw mulch. Spread uniformly at a minimum rate of 2 tons/acre to form a continuous blanket 1-1/2 inches in loose thickness over seeded areas. Spread by hand, blower, or other suitable equipment. 1. Anchor straw mulch by crimping into soil with suitable mechanical equipment. 2. Bond straw mulch by spraying with asphalt emulsion at a rate of 10 to 13 gallons/1000 ftz. Take precautions to prevent damage or staining of structures or other plantings adjacent to mulched areas. Immediately clean damaged or stained areas. F. Protect seeded areas from hot, dry weather or drying winds within 24 hours after completing seeding operations. G. Seeding should occur within the first 3 weeks of the fall season. 3.5 HYDROSEEDING A. Hydroseeding: Mix specified seed, fertilizer, and fiber mulch in water, using equipment specifically designed for hydroseed application. Continue mixing until uniformly blended into homogeneous slurry suitable for hydraulic application. 1. Mix slurry with fiber-mulch manufacturer's recommended tackifier. 2. Apply slurry uniformly to all areas to be seeded in a one-step process. Apply slurry at a rate so that mulch component is deposited at not less than 1500-1b/acre dry weight, and seed component is deposited at not less than the specified seed-sowing rate. 3.6 TURF RENOVATION A. Renovate existing turf. B. Renovate existing turf damaged by Contractor's operations, such as storage of materials or equipment and movement of vehicles. 1. Reestablish turf where settlement or washouts occur or where minor regrading is required. 2. Install new planting soil as required. C. Remove sod and vegetation from diseased or unsatisfactory turf areas; do not bury in soil. D. Remove topsoil containing foreign materials such as oil drippings, fuel spills, stones, gravel, and other construction materials resulting from Contractor's operations, and replace with new planting soil. SECTION 329200 - TURF AND GRASSES Page 7 of 9 Dillsboro Hydroelectric Project Decommissioning & Removal DTA Specification No. 024.0029.0000 Dillsboro, North Carolina Revision No.: Review 2 Duke Energy Carolinas, LLC December 18, 2008 E. Till stripped, bare, and compacted areas thoroughly to a soil depth of 6 inches. F. Apply soil amendments and initial fertilizers required for establishing new turf and mix thoroughly into top 4 inches of existing soil. Install new planting soil to fill low spots and meet finish grades. G. Apply seed and protect with straw mulch as required for new turf. H. Water newly planted areas and keep moist until new turf is established. 3.7 TURF MAINTENANCE A. Maintain and establish turf by watering, fertilizing, weeding, mowing, trimming, replanting, and performing other operations as required to establish healthy, viable turf. Roll, regrade, and replant bare or eroded areas and remulch to produce a uniformly smooth turf. Provide materials and installation the same as those used in the original installation. 1. Fill in as necessary soil subsidence that may occur because of settling or other processes. Replace materials and turf damaged or lost in areas of subsidence. 2. In areas where mulch has been disturbed by wind or maintenance operations, add new mulch and anchor as required to prevent displacement. 3. Maintenance shall be performed as often as is necessary to establish a permanent healthy stand of grass cover. 3.8 SATISFACTORY TURF A. Turf installations shall meet the following criteria as determined by Engineer: Satisfactory Seeded Turf: At end of maintenance period, a healthy, uniform, close stand of grass has been established, free of weeds and surface irregularities, with coverage exceeding 90 percent over any 10 sq. ft. and bare spots not exceeding 5 by 5 inches. B. Use specified materials to reestablish turf that does not comply with requirements and continue maintenance until turf is satisfactory. 3.9 CLEANUP AND PROTECTION A. Promptly remove soil and debris created by turf work from paved areas. Clean wheels of vehicles before leaving site to avoid tracking soil onto roads, walks, or other paved areas. B. Erect temporary fencing or barricades and warning signs as required to protect newly planted areas from traffic. Maintain fencing and barricades throughout initial maintenance period and remove after plantings are established. C. Remove nondegradable erosion-control measures after grass establishment period. SECTION 329200 - TURF AND GRASSES Page 8 of 9 1)illsborv Flydroelearic Project Decommissioning & Removal Dillsboro. North Carolina Duke Energy Carolinas, LLf; END OF SECTION 323200 DTA Specification No. 021.0029 U!)00 Revision No.: Review 2 December 18, 2008 SECTION 329200 -TURF AND GRASSES page 9 ?r 9 QUALITY CONTROL AND INSPECTION PROGRAM (QCIP) DILLSBORO HYDROELECTRIC DECOMMISSIONING & REMOVAL PROJECT DILLSBORO HYDROELECTRIC PROJECT (FERC NO. 2602) (Addressing Paragraph D of the FERC Decommissioning Order 120 FERC 61,054) Prepared for: P Duke IEnergy@ Duke Energy Carolinas, LLC 526 South Church Street Charlotte, North Carolina 28201-1006 By: D 7'A Devine Tarbell & Associates, Inc. Cnntiultin{ Eru,inccm, Scientists, & Regulawn Specialists 400 S. Tryon Street, Suite 2401 Charlotte, NC 28285 December 18, 2008 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 TABLE OF CONTENTS 1.0 INTRODUCTION .................................................................................... 1 1.1 Purpose .............................................................................................. 1 1.2 Background ......................................................................................... 1 1.3 Description of Type of Structures and Construction .......................................... 2 1.3.1 Type of Structures to be Demolished ..................................................... 2 1.3.2 Description of Construction ................................................................ 3 1.4 Specialized Construction Techniques and Equipment ......................................... 4 2.0 ORGANIZATION AND STAFFING RESPONSIBILITIES ................................. 4 2.1 Responsibilities of Various Organizations .................................... ................... 4 2. 1.1 Duke Energy Carolinas, LLC ........................................... ................... 4 2.1.2 Devine Tarbell & Associates, Inc ....................................... ................... 4 2.1.3 General Contractor ........................................................ ................... 5 2.1.4 The Federal Energy Regulatory Commission ......................... ................... 5 2.2 Number of Staff and Availability Required ................................. .................... 5 2.3 Titles, Duties and Responsibilities of Staff .................................. .................... 5 2.3.1 Project Manager (Duke) ................................................. ................... 5 2.3.2 Project Design Engineer (DTA) ........................................ .................... 6 2.3.3 Construction Manager (Duke) .......................................... .................... 6 2.3.4 Environmental-Health & Safety Manager (Duke) .................... ................... 6 2.3.5 Inspectors ................................................................... ................... 7 2.4 Specialty Inspectors ............................................................. ................... 7 2.5 Lines of Communication and Authority ..................................... .................... 8 2.6 Approval and Rejection of Work ............................................. ........................ 8 2.7 Authority to Stop Work ......................................................... .................... 8 2.8 Statement of Independence ..................................................... .................... 8 2.9 QCIP Personnel Qualification .................................................. ....................... 8 2.10 Resumes .............................................................................. .................... 8 3.0 INSPECTION PLAN AND FIELD PRACTICES .............................................. 9 3.1 Inspection Criteria .................................................................................. 9 3.2 Knowledge of Contract Plans and Specifications ............................................. 9 3.3 Inspection Equipment and Resources .............................................................. 9 3.4 Contractor Operations .............................................................................. 9 3.5 Coordination with Contractor's Schedule ....................................................... 9 3.6 QCIP Operations ....................................................................................... 10 Duke Energy Carolinas, LLC I of III Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 3.7 Frequency of Inspections ......................................... .................................... 10 3.8 Documentation and Follow-up Action ......................... ................................ 10 3.9 Training ............................................................ ................................ 11 4.0 DOCUMENTATION ............................................... ................................. 11 4.1 Daily Work Reports .............................................. ................................ 11 4.2 Nonconformance Reports ....................................... ................................. 12 4.3 Environmental Deficiency Reports ............................. ................................ 13 4.4 Other Periodic Reports ........................................... ................................ 13 4.4.1 Coordination Meetings .................................... ................................. 13 4.4.2 Bi-Weekly Construction Progress Report .............. .................................. 14 4.4.3 Test Reports ................................................. .................................. 14 4.5 Maintenance of Records ......................................... ................................. 14 4.5.1 General Correspondence .................................. ................................. 14 4.5.2 Manufacturer's Drawings ................................. .................................. 14 4.5.3 Contract ...................................................... ................................. 14 4.6 Photographs ........................................................................................ 15 5.0 TRAINING ............................................................................................. 15 5.1 Study Materials .................................................................................... 15 5.2 Classroom Instruction ............................................................................ 15 5.3 On-the-job -training & Supervision ................................................................ 15 5.4 Proficiency Testing and Certification .......................................................... 15 5.5 Resume Update .................................................................................... 15 6.0 MATERIAL TESTING .............................................................................. 15 6.1 Testing Schedule ................................................................................... 15 6.2 Testing Standards ................................................................................. 16 6.3 Inspection and Testing Organization .............................................................. 16 6.4 Adequacy of On-site Laboratory ............................................................... 16 6.5 Adequacy of Off-site Laboratory ............................................................... 16 6.6 Evaluation of Testing Data and Actions Required ........................................... 16 6.7 Documentation .................................................................................... 16 7.0 EROSION CONTROL AND ENVIRONMENTAL COMPLIANCE .................... 16 7.1 Environmental Compliance Plan ............................................................... 16 7. 1.1 Disposal of Non Hazardous Waste Solid Construction Debris ..................... 16 7.1.2 Hazardous Waste Inspection/Inventory .................................................. 17 Duke Energy Carolinas, LLC H of III Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 12118108 7.1.3 Pollution Control ........................................................................... 17 7.2 Erosion and Sediment Control Plan (ESC Plan) ............................................. 17 7.3 License Requirements ........................................................................... 17 7.4 Specialized Plans, Permits and Approvals .................................................... 18 7.5 Frequency of Inspections ....................................................................... 18 7.6 Documentation and Corrective Actions ....................................................... 18 7.7 Environmental Deficiency Report ............................................................ 18 8.0 SCHEDULE ........................................................................................... 18 8.1 Start and Finish Dates ........................................................................... 18 8.2 Anticipated Construction Sequence ........................................................... 19 8.3 Staged Construction ................................................................................... 19 9.0 PLANNED USE OF CONSULTANTS ......................................................... 19 9.1 Areas of Inspection and Review ............................................................... 19 9.2 Specialized Consultant Names and Resumes ................................................ 19 APPENDICES Appendix A: Organizational Chart Appendix B: QCIP Personnel Resumes Appendix C: List of Contract Documents Appendix D: Example of Reports to be Used Appendix E: Contractor's Schedule Appendix F: Specialized Plans, Permits and Approvals Duke Energy Carolinas, LLC III of III Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 1. INTRODUCTION This report has been prepared in accordance with the January 1993, Quality Control Inspection Program (QCIP) described in Chapter VII of the "Federal Energy Regulatory Commission's (FERC) Engineering Guidelines for the Evaluation of Hydropower Projects ". 1.1 Purpose Duke Energy Carolinas, LLC (Duke) intends to decommission the Dillsboro Hydroelectric Project (FERC No. 2602) located in Western North Carolina on the Tuskasegee River. The goals of this Quality Control Inspection Program (QCIP) document are to assure that the work is performed in accordance with applicable safety and environmental requirements and meets the technical requirements set forth in the Contract Documents. The QCIP defines personnel responsibilities, the methods, documentation requirements, and types and frequencies of quality assurance testing that will be performed to assure that a quality job is obtained conforming to the requirements of the Project Specifications and Project Drawings. Devine Tarbell & Associates, Inc. (DTA), Charlotte, NC, will serve as the Project Design Engineer reporting to the Licensee and is responsible for assisting in the development of the QCIP in accordance with FERC guidelines. 1.2 Background The Dillsboro Hydroelectric Project is located in western North Carolina on the Tuckasegee River near the town of Dillsboro, at River Mile 31.7, in Jackson County, NC. Duke owns and operates the Dillsboro Hydroelectric Project in a limited storage mode. The project has an installed capacity of 225 kW. The project's reservoir is filled to near capacity with an estimated 100,000 to 120,000 cubic yards of sediment. Channel depths for about 500 feet upstream of the powerhouse range from 8 to 12 feet. Most of the remaining portions of the reservoir are 3 to 7 feet deep. Historically, Duke has operated the project in a run-of-river mode, maintaining the headpond within 6 inches of full pond elevation. Project operation depends on available now in the Tuckasegee River, which is regulated by Duke's upstream East Fork and West Fork projects (Project Nos. 2698 and 2686, respectively). The Order Accepting Surrender and Dismissing Application for Subsequent License were issued by FERC on July 19, 2007. A subsequent Order on Rehearing and Clarification was issued on April 22, 2008. These Orders accept an application made by Duke to remove the Dillsboro Hydroelectric Project. In ordering paragraph (D) of the Order Accepting Surrender and Dismissing Application for Subsequent License, the FERC requires Duke to provide "a detailed description of activities and schedule for removing the project features and restoring the site." The detailed activities schedule provided covers the removal of all project features through site restoration and has been developed in consultation with the North Carolina Division of Water Quality, North Carolina Division of Water Resources, North Carolina Wildlife Resource Commission, U.S. Fish and Wildlife Service, North Carolina Department Duke Energy Carolinas, LLC 1 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 12118108 of Environmental and Natural Resources, and the Eastern Band of Cherokee Indians. The removal is scheduled to be removed during the mid-winter to early spring months (i.e. December to March time period) in accordance with Application for Surrender of License (Duke Energy 2004). Devine Tarbell & Associates (DTA), headquartered in Portland, Maine, and has been contracted by Duke as the design firm for the Dillsboro Hydroelectric Decommissioning proj ect. , headquartered in , , has been contracted by Duke as the General Construction Contractor, who will construct the project in accordance with the General Construction Specification titled "Dillsboro Hydroelectric Decommissioning & Removal Specification", General Construction Specification No. 024.0029.0000. , headquartered in will serve as Duke's resident Construction Manager on the project. 1.3 Description of Type of Structures and Construction The Dillsboro Hydroelectric Project is to be decommissioned and removed to restore the Tuckasegee River back to the original riverbed over the full width of the river and rock ledges will not be removed. The following sections will explain the type of structures present and construction to be anticipated. Main access to the construction site will be at the intersection of Mockingbird Lane and Monroe Buchanan Road. Refer to the project drawings and specifications for details. 1.3.1 Type of Structures to be Demolished The Dillsboro Hydroelectric Project consists of a Powerhouse, spillway overflow dam, concrete piers, and steel flood gates. The Dillsboro Dam is a concrete masonry structure that is about 310 feet in length and 12 feet high. Major components of the Dillsboro Dam are listed below, beginning at the left abutment (facing downstream). All elevations are referenced in U. S. Geological Survey (USGS) datum and are expressed in feet above mean sea level (MSL). Main components of the dam include: • A concrete, non-overflowing section with a crest elevation of 1978.2 feet above MSL. • An uncontrolled 14 foot-wide spillway section with a crest elevation of 1972.0 feet above MSL. • A 20-foot wide spillway section with two six foot wide spill gates. The gates sill elevation is at 1961.0 feet above MSL. Duke Energy Carolinas, LLC 2 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 12118108 • A 197-foot uncontrolled spillway with a crest elevation of 1972 feet above MSL. • A 64.5-foot wide powerhouse with a wood/timber superstructure and concrete substructure. • An 80-foot long intake section. • A concrete, non-overflowing section with a crest elevation of 1980 feet above MSL. The powerhouse consists of a 64.5-foot wide reinforced concrete substructure and a wood/steel superstructure. Inside the powerhouse are two generating units. The unit closest to the open spillway, Unit No. 1, consists of an S. Morgan Smith vertical Francis- type turbine rated at 276 horsepower (hp) under 12-foot of head and 225 revolutions per minute (rpm) connected to a 219 kilovolt-ampere (kVa) Westinghouse generator at 0.80- power factor and a DC exciter. Unit No. 2 has a Leffel Type - Z turbine rated at 44 hp under 12-foot of head and 200 rpm connected to a 62.5 kVa General Electric generator at 0.80-power factor and a DC exciter. Each unit has an open pit concrete penstock. The rated hydraulic capacities of the turbines are 190 cubic feet per second (cfs) for Unit No. 1 and 44 cfs for Unit No. 2. 1.3.2 Description of Construction The decommissioning of the Project includes the full removal to grade of the existing Spillway and partial removal of the Powerhouse. The dam is to be removed to the original riverbed over the full width of the river and no rock ledge will be removed. The powerhouse superstructure will be removed completely and the substructure will be partially removed. The river will be returned to its assumed pre-dam bank-to-bank width and depth. Removal will be accomplished by use of hydraulic equipment to remove the dam and powerhouse structures in accordance with a staged demolition plan. An excavator with a hoe-ram attachment or similar mechanism will demolish the dam, with an excavator and a track loader used to remove remaining sediment, if necessary, and remove rubble/concrete. Additionally, mechanical sediment removal will be performed in the forebay area to help conduct flows during the demolition process. During the demolition process, river flow will be diverted through a notch in the dam, and/or passed over the partially demolished crest. To provide stability of the embankment along the river at the powerhouse, the powerhouse basement slab and walls on the embankment will be evaluated during construction to determine if they can be left in place. However, if the structures are removed a slope stabilizing system shall be installed to support embankment. Refer to the project schedule for more details. Duke Energy Carolinas, LLC 3 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 1.4 Specialized Construction Techniques and Equipment The removal of the dam and powerhouse will require careful water and soil management to minimize erosion and sediment releases into the river. 2. ORGANIZATION AND STAFFING RESPONSIBILITIES 2.1 Responsibilities of Various Organizations Organizational responsibilities are established such that the QCIP personnel and Testing Organizations are independent of the General Contractor but are aligned to assure the effort achieves a quality end result. See Appendix A for an organizational chart for this project. 2.1.1 Duke Energy Carolinas, LLC (Duke) Duke is the owner/licensee of this project. The owner is ultimately responsible for implementation of the QCIP. The owner will provide an on-site Construction Manager, Environment-Health & Safety Manager and Inspectors if necessary to provide support to the project via Duke's Hydro Engineering & Technical Services group and Project Management Group as needed, to oversee and verify that work is performed in accordance with the Contract Documents, Drawings and Specifications. Duke's Hydro Engineering & Technical Services Group will perform periodic inspections of the work in conjunction with the Project Design Engineer, DTA, to assure compliance with design intent. 2.1.2 Devine Tarbell & Associates, Inc., (DTA) DTA will serve as Project Design Engineer for the facility and shall be responsible for design of the work including development and issue of design documents, project drawings, and specifications that designate those items and activities requiring inspection or tests; and for indicating the frequency, testing and inspection standards, and acceptance criteria for those items. DTA will provide support to the Licensee, as needed, to coordinate and oversee surveillance and inspection activities of Licensee's Inspectors. In general, responsibilities of the Project Design Engineer shall be as follows: • Issue and revise Project Drawings, Specifications, or other documents. • Perform periodic inspections of the various disciplines of on-going work to assure compliance with design intent. • Review and resolve variations and nonconforming items dealing with design and notify Construction Manager and General Contractor of resolutions. • Inspect the correction of nonconforming items when needed. • Where required, perform and/or witness qualification and acceptance testing. Duke Energy Carolinas, LLC 4 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 2.1.3 General Contractor (TBD) The General Contractor will serve as the demolition contractor for the site and shall be responsible for maintaining the quality of the work to meet the general demolition specifications. The General Contractor and suppliers will have no authority or control over implementation of the QCIP, or financial relationships with any organization that has responsibility for implementing the plan. The General Contractor is responsible for its own QA/QC plan, which is independent of this QCIP. 2.1.4 The Federal Energy Regulatory Commission (FERC) The FERC licensed and oversaw the operation of the Dillsboro Hydroelectric Project and therefore has jurisdiction over the decommissioning of the project. The FERC shall have the authority to inspect demolition activities to ensure that the terms and conditions of the decommissioning of the Dillsboro Hydroelectric Project are met in accordance to the Order Accepting Surrender and Dismissing Application on July 19, 2007 and modification by the Order on Rehearing and Clarification issued by the FERC on April 22, 2008. 2.2 Number of Staff and Availability Required The Construction Manager is Duke's full-time field representative responsible for implementing the QCIP. Duke and DTA personnel will support the Construction Manager as required. 2.3 Titles, Duties and Responsibilities of Staff 2.3.1 Project Manager (Duke) Jack Jenkins, the Project Manager, is responsible for coordinating project design and demolition for Duke (Licensee/Owner). He will be based out of Charlotte, North Carolina, and will make periodic inspection trips to the site. The Project Manager will also assure that the following activities are carried out: • QCIP Staff activities are managed. • Through the staff, assure the proper monitoring of the quality of the General Contractor's work. • Monitor the General Contractor's engineering, demolition reporting, scheduling, demolition progress, and quality control activities. • Review nonconformance's with Project Engineering and assures resolution of all. • Review design changes and General Contractor claims. • Interface with FERC and assure compliance with FERC licensing. Duke Energy Carolinas, LLC 5 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 12118108 • Have the authority and responsibility to stop work as appropriate when conditions adverse to quality are encountered. 2.3.2 Project Design Engineer (DTA) Chris Ey, the Project Design Engineer, is responsible for providing oversight and coordination of project design and demolition support services for Duke. The Project Design Engineer will advise and support the Construction Manager with the implementation of QCIP and perform regular on-site surveillance of all phases of construction to assure full compliance with the engineering drawings and specifications. He/she will be base out of Charlotte, North Carolina. 2.3.3 Construction Manager , the Construction Manager representing Duke, is responsible for implementation of the QCIP to verify the demolition is in conformance with the project plans and specifications, and is consistent with industry standards and practices. The Construction Manager is also responsible for construction interface and coordination between the Licensee he/she will be based the project site. The Construction Manager will be responsible for demolition interface and coordination between the Licensee and the Contractor and will report to the Licensee's Project Manager. Duties and responsibilities of the Construction Manager shall include the following: • Monitors the General Contractor's engineering, demolition reporting, scheduling, demolition progress, and quality control activities. • Participates in reviews and resolution of all nonconformances. • Reviews design changes and General Contractor claims. • Supports FERC interfaces and compliance with FERC licensing conditions • Has authority and responsibility to stop work as appropriate when adverse conditions are encountered. • Coordinates closely with the site EHS Manager and Field Quality Assurance Supervisor • Interfaces with the Project Design Engineer and assures communications between the Project Design Engineer and the General Contractor are clear, complete and acted upon. • Order all measures which, in his opinion, are necessary for the safety and protection of the public, existing facilities, and constructed facilities. 2.3.4 Environmental-Health & Safety Manager , the Environmental-Health & Safety Manager representing Duke, is responsible for reviewing and monitoring project demolition on a daily basis to assure Duke Energy Carolinas, LLC 6 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 12118108 compliance with environmental permits and health and safety regulations. Duties and responsibilities include: • Review General Contractor's Environmental Compliance Plan for compliance with project license and permits. Reviews and recommends modifications during demolition when activities are deemed to be unsatisfactory. • Serve as liaison with resource agencies on environmental issues. • Monitor work on daily basis and document environmental, health & safety compliance or noncompliance with erosion and sedimentation control measures, excavation techniques, and other construction activities. • Provide training to inspectors and demolition personnel as needed. • Maintains records of all environmental inspections and provides reports to relevant agencies when required. • Keep Project Manager, Construction Manager, and General Contractor abreast of environmental, health & safety issues and concerns. • Ensures that the ESC Certification is posted and maintained at the construction entrance during the Project. 2.3.5 INSPECTORS Inspectors may be provided from the Licensee's organization or from an independent testing firm reporting to the Licensee if necessary. Inspectors shall be responsible for monitoring all demolition activities in their specific areas of assignment and performing the tests and inspections required to verify the correctness and adequacy of the demolition contractor's work in accordance with the Contract Documents. Inspectors shall document the results of the test or inspection performed for each item or activity on the designated reporting form and informs responsible personnel about unsatisfactory or nonconforming items. When items or activities are found to be defective or in noncompliance with Contract Documents, the Inspector shall initiate a nonconformance report and submit the report to the Construction Manager for resolution. Inspectors shall verify that the specified corrective actions are properly completed. Inspectors shall have the authority to recommend stop work to the Construction Manager and their supervisor. Inspectors shall also be responsible for reporting any inadequacies or suspected violations of the Environmental Compliance Plan or Erosion and Sedimentation Control Plan to the Environmental-Health & Safety Manager for review and further action. 2.4 Specialty Inspectors Not applicable for this project. Duke Energy Carolinas, LLC 7 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 2.5 Lines of Communication and Authority The lines of communication and authority are illustrated in the QCIP Organizational Chart presented in Appendix A. 2.6 Approval and Rejection of Work The approval and rejection of work will be the responsibility of the Construction Management Team shown in the Organization Chart in Appendix A. Specifically, the on-site Construction Manager will use the General Construction Specification as the guide for determining the acceptability of the work; however, judgment may supplement the General Construction Specification requirements when the quality of the work would be equal to or greater than that presented in the General Construction Specification. The other QCIP personnel have the authority to nonconform work found to be in noncompliance with Contract Documents but do not have the authority to approve or reject work. The authority to approve or reject work lies solely with the Licensee or the Project Engineer. 2.7 Authority to Stop Work When work is believed defective or nonconforming with the Contract Documents, or when work conditions are unsafe or adverse to quality, the Project Manager, Project Design Engineer, and Construction Manager shall have authority to stop work for nonconforming work until such time that corrective measures can be implemented. All supervisory personnel will have the authority to temporarily stop work when there appears to be a health or safety concern until that concern is corrected. 2.8 Statement of Independence All parties, including the Licensee, the Project Design Engineer, and the General Construction Contractor, are independent of one another. The Project Design Engineer and the General Construction Contractor are under separate contracts with the Licensee to provide services associated with the demolition of the project. 2.9 QCIP Personnel Qualification The Project Design Engineer shall be a registered professional engineer with at least 10 years work experience with hydropower plants and dam structures. The Owner's Project Manager shall be a registered professional engineer with at least 10 years experience in the design and/or construction of hydropower plants. The Construction Manager shall be a trained engineer and shall have a minimum of 10 years experience in construction or construction QA. 2.10 Resumes Essential project personnel resumes are provided in Appendix B. Duke Energy Carolinas, LLC 8 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 3. INSPECTION PLAN AND FIELD PRACTICES Work will be inspected to verify conformance with the criteria set forth in the Contract Documents. 3.1 Inspection Criteria The inspection criteria are set forth in the Contract Documents if necessary. 3.2 Knowledge of Contract Plans and Specifications The Construction Manager shall maintain at the job site current copies of the Contract Documents which shall include reproductions of original Contract Documents along with all Work Directive Changes, Addendums, Change Orders, Field Orders, Drawing and Specification revisions, additional Drawings issued subsequent to execution of the Project, progress reports, and other Project related documents including environmental permits and plans. QCIP personnel shall become familiar with the Contract Documents and shall review said documents periodically to ensure that current documents are being used and that all requirements are being met. 3.3 Inspection Equipment and Resources The independent inspection and testing firm will supply the necessary sampling and testing personnel and equipment if necessary. 3.4 Contractor Operations The Construction Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. The Construction Contractor shall be solely responsible for site safety and for the means, methods, techniques, sequences, and procedures of construction employed in performance of the Work. The Construction Contractor shall provide quality and schedule controls over materials, workmanship and methods, as needed, to ensure compliance with the Contract Documents. The General Contractor's operations with regard to quality control, however, are independent of the QCIP. It is not the intent of this manual to address the quality control and inspection functions performed by the Construction Contractor. The Project Design Engineer will be available during construction to respond to technical issues that arise and to provide clarifications regarding the project design and specifications. 3.5 Coordination with Contractor's Schedule The General Contractor will be required to provide a 24-hour notice when inspection by the Construction Manager is needed before proceeding with demolition, for example, prior to Duke Energy Carolinas, LLC 9 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 12118108 any field testing. Weekly demolition coordination meetings will be held between Duke and the General Contractor, and notification of pending inspections will be part of the meeting agenda. 3.6 QCIP Operations The General Contractor is responsible for performing his work to the quality level established by and as agreed and accepted by Duke. Duke is responsible for monitoring the General Contractor's work quality. QCIP personnel are responsible for performing tests and inspections as necessary to verify that all contract work conforms to the Contract Documents and Procedures. QCIP personnel shall not be responsible for directing or controlling the General Contractor's field construction operations. The Construction Manager, or his designee, is responsible for immediately advising the General Contractor of nonconforming work so the work can be corrected. The Construction Manager is responsible for documenting the quality control inspections and results. The Construction Manager shall be familiar with General Demolition Specifications and demolition drawings and will known when and where to perform inspections. Whenever nonconforming work is detected, the Inspector shall immediately notify his supervisor and the General Contractor. The Inspector may recommend that work be stopped but does not have the authority to stop work. The Construction Manager may require that work be stopped until such time that the nonconforming work can be corrected. Nonconforming work shall be documented in accordance with 4.2 "Nonconformance Reports". No design changes shall be made to the work without prior approval of the Project Design Engineer. Quality control communications will be between the Project personnel listed in Section 2.3 and the General Contractor's superintendent. The General Contractor is required to have a superintendent at the site, who can receive directives regarding quality issues. A meeting should be held early in the construction to determine if other General Contractor supervisory staff members can receive directives regarding quality conditions. 3.7 Frequency of Inspections Frequency of Inspections and testing will be provided if necessary. 3.8 Documentation and Follow-up Action Inspections can result in the issuance of a Nonconformance Report. Refer to Section 4.2 for discussion on nonconformance reports and follow-up actions. If the project requires independent sampling and testing firm, testing reports will be maintained in the project records in accordance with Section 4.4. Duke Energy Carolinas, LLC 10 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 3.9 Training Information regarding training for the project is provided in Section 5 labeled "Training". 4. DOCUMENTATION 4.1 Daily Work Reports Duke's Construction Manager will maintain a Daily Log. The Daily Log is a factual recording of events affecting the project. The log book shall be factual and written with the presumption that everything in it may be recalled publicly. Daily entries should begin with the date of the entry and end with the author's initials or signature. Entries should be written in ink and be continuous with no lines skipped; lines are not to be skipped between daily entries. Any error made in an entry should be crossed out or erased. Pages should not be torn out of the log book or left blank. Daily entries should include, but are not limited to, the following information. • Weather and ground conditions; • Demolition start and stop times; • A brief description of the demolition activities of the day, including the commencement or completion of any major unit of work. This also includes materials and equipment used for work on that day; • A description of any rejected work, material or equipment, together with the reasons for rejection and actions taken; • All directions given to a contractor that are not documented elsewhere; • Description of any delays in the demolition, along with reason for delay; • Description of disputes involving contractors, subcontractors, the Owner, or the Engineer; • A brief description of any accident the inspection staff observes or is involved in; • Description of a work item for which there is reason to believe a claim for extra compensation may be filed; • The names of any visitors; • A record of any telephone calls, with a brief description of the conversation; • General observations of any activities that seem significant at the time. The Environmental-Health & Safety Manager shall also maintain a daily log of demolition activity documenting Contractor's compliance or noncompliance with the approved Environmental Compliance Plan. Duke Energy Carolinas, LLC 11 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 12118108 Only one log book should be maintained by the Construction Manager at one time. Completed log books should be filed in the project files. The log books are important documents and are often used in settlement of disputes, to reconstruct events after the fact. Entries should be made in the log book on a daily basis while the subject matter is fresh in the author's mind. 4.2 Nonconformance Reports A Nonconformance Report (NCR) and procedure have been developed to provide a standard document format and procedure for communicating with the General Construction Contractor regarding demolition quality nonconformance and required corrective action. A nonconformance is defined as a deficiency in characteristic, documentation, or procedure which renders the contractor's work unacceptable with respect to the quality requirements of the contract documents. A NCR form is presented in Appendix D. A NCR shall be issued to the General Construction Contractor when he presents any portion of his work as complete and a serous deficiency exists or a deficiency trend is occurring in subsequent similar work. NCRs are not to be utilized for documenting contractor acknowledged incomplete "Punch List" type work items or for problems relating to project design. The Construction Manager is responsible for initiating NCRs. The NCRs shall be numbered sequentially and filed in accordance with Duke's Record Keeping Procedures. The NCRs shall be reviewed weekly by the Construction Manager to determine contractor compliance with corrective action requirements and identify the need for any follow-up action. In the event of contractor failure to comply with the corrective action requirements of a NCR, either unsatisfactory work or failure to meet the time requirements, the following procedure will be implemented. • The Construction Manager and Project Manager shall jointly prepare a formal contract correspondence letter with a copy of the original NCR attached advising the contractor of his failure to meet the corrective action requirements; • The letter will establish a date for when the corrective action must be satisfactorily completed and state that in the event of contractor failure to satisfactorily complete the corrective action by this date, the corrective action work will be performed by others with all associated costs being applied to his contract; • The letter shall state any other actions that Duke may take under the terms of the contract as a result of failing to resolve the NCR; • Copy distribution of all such follow-up NCR correspondence shall be the same as the original NCR and shall be filed in the appropriate NCR file. Duke Energy Carolinas, LLC 12 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 4.3 Environmental Deficiency Reports An Environmental Deficiency Report (EDR) shall be completed by the Environmental- Health & Safety Manager whenever a condition is discovered that could potentially be a detriment to the environment. The report shall be submitted to the Construction Manager for processing in accordance with Section 7.7. EDR's will be maintained by the Environmental- Health & Safety Manager and available for review until the end of the project. An EDR form is presented in Appendix D. 4.4 Other Periodic Reports Other periodic reports which document quality control issues are described in the following subparagraphs. 4.4.1 Coordination Meetings The Construction Manager and the General Construction Contractor shall jointly conduct daily safety and demolition coordination meeting. The main topics of the meeting will be project safety as it relates to the specific work planned for that day, schedule issues, coordination of work and supply activities, and quality control issues. Documentation of the meeting discussions shall be written in sentence and paragraph form with a new numbered sentence or paragraph for each item of business. The conclusion for each item discussed shall be recorded. The demolition coordination meetings shall be divided into four sections as follows. • Exceptions: The contractor shall be given an opportunity to take exception to the minutes of the previous week's meeting. If exceptions are taken, the item should be corrected. If no exceptions are taken, it should be so stated. • Old Business: Items discussed in previous meetings are carried under this section and shall be carried there until the item is resolved or eliminated. • New Business: New items of business are carried under this section. • Safety Meeting Discussions: Discussions or trainings involving safety will be carried under this section. The minutes of the meeting shall be prepared in memorandum form, and shall be published as soon as possible after the meeting. The Construction Manager and General Construction Contractor's Superintendent shall each sign the minutes prior to distribution. Duke shall receive 4 copies (copies shall be transmitted to appropriate person(s) as instructed by Duke) and each meeting attendee shall receive 1 copy of the meeting minutes. The original minutes shall be filed in the on-site files in accordance with the file procedure described in Duke's Record Keeping Procedures. Duke Energy Carolinas, LLC 13 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 4.4.2 Bi-weekly Demolition Progress Report Duke's Project Manager shall prepare a bi-weekly demolition progress report. A final demolition report shall be prepared which summarizes all aspects of the project demolition. The outline for the demolition progress report is presented in Appendix D. Distribution of the reports shall be as follows: • Duke (4 of copies - Internal distribution & filing) • FERC (3 of copies - Transmitted to FERC-PRO by Duke) • DTA (2 of copies - recipient(s)) 4.4.3 Test Reports This is not applicable for this project. However, if demolition work items require testing as part of the quality control and assurance specified in the General Construction Specification, the sampling and testing laboratory will provide test reports to document the testing. All testing reports should be filed in accordance with the filing procedures described in Section 4.4. Other periodic reports that will be developed include monthly status reports and monthly reports to the FERC. QCIP personnel will be involved in the development and provide input to these reports as appropriate. 4.5 Maintenance of Records The Construction Manager shall maintain at the jobsite, record copies of the latest revisions to project drawings, specifications, and shop drawings, the originals of all inspection reports, test reports, Project Design Engineer clarifications and interpretations of the Contract Documents, and resolved NCR's and EDR's. The Construction Manager shall make available for review at the job site copies of these reports. The main types of documentation are described in the following sections. 4.5.1 General Correspondence All documents, correspondence, and data pertaining to the project should be identified and filed in accordance with Duke's Record Keeping Procedures. 4.5.2 Manufacturer's Drawings Manufacturer's shop drawings should be maintained and filed in numerical order according the shop drawing number. Superseded shop drawings should be discarded and replaced with the revised drawings leaving only the latest issue in the files. 4.5.3 Contract Design Drawings and Specifications Unless otherwise changed by the Construction Manager, at least two field sets of contract design drawings and specifications will be maintained. The first set will be maintained as a record set and the other will be maintained as a work set. Duke Energy Carolinas, LLC 14 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 12118108 Final documentation shall be stored in fire-proof cabinets during demolition. At project completion, permanent records shall be turned over to the Licensee. 4.6 Photographs The Construction Manager shall be responsible for photographing significant demolition activities throughout the demolition period. Potential claim work items shall be photographed to provide future reference. A brief description of each item photographed shall be provided. Photographs shall be maintained in chronologically arranged electronic files through the duration of the project and shall then be edited for relevant content before being turned over at the conclusion of the project for permanent retention. Duke has the authority to request additional photographs during the construction process. 5. TRAINING Classroom training will not be needed for this project; however, this project will require on-site training with regards to knowledge and awareness of soil erosion and disturbance. Additionally, each morning before work starts there will be a safety meeting to identify the days work, its potential safety hazards and to discuss remedial measures. The Construction Manager will be responsible for seeing that this training is conducted on-site. 5.1 Study Materials Not applicable for this project. 5.2 Classroom Instruction Not applicable for this project. 5.3 On-the-job-training & Supervision Not applicable for this project. 5.4 Proficiency Testing and Certification Not applicable for this project. 5.5 Resume Update Not applicable for this project. 6. MATERIAL TESTING 6.1 Testing Schedule No quality control testing is planned during construction of this project. Duke Energy Carolinas, LLC 15 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 6.2 Testing Standards Since no quality control testing is planned during the course of this project, testing standards are not required. However, if a situation occurs where testing is required testing standards can be provided. 6.3 Inspection and Testing Organization Not applicable for this project. However, if the project requires Inspection and Testing, an independent inspection and testing firm would be applicable. 6.4 Adequacy of On-site Laboratory No on-site testing laboratory is anticipated for this project. 6.5 Adequacy of Off-site Laboratory Should testing become necessary for this project, the adequacy of the off-site laboratory personnel and their testing equipment shall be reviewed by the Construction Manager. Items which shall be reviewed and noted in the Daily Log include testing personnel qualifications, testing equipment calibration, and test reports. 6.6 Evaluation of Testing Data and Actions Required Quality Control testing is not planned during demolition of this Project. Should testing be found necessary, the following would apply when the test result values are outside the acceptable range established in the General Construction Specification. The Project Design Engineer and testing laboratory will be consulted to reach an informed conclusion or judgment regarding such test results. Every field test which lies outside the acceptable range shall be documented in the daily log along with the justifications for acceptance or rejection. 6.7 Documentation The sampling and testing laboratory shall be responsible for supplying the documentation of the material testing. The documents shall be filed in accordance with the procedures described in Section 4.4. 7. EROSION CONTROL AND ENVIRONMENTAL COMPLIANCE 7.1 Environmental Compliance Plan The construction will comply with all applicable laws, acquired permit conditions, and governing agencies. 7.1.1 Disposal of Non Hazardous Waste Solid Construction Debris All solid demolition debris/waste will be legally disposed of by the Contractor. Duke's Construction Manager will be on-site full time to see that these procedures are followed. Duke Energy Carolinas, LLC 16 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 7.1.2 Hazardous Waste Inspection/Inventory A detailed hazardous waste inspection/inventory will be conducted at the powerhouse prior to Project demolition by qualified personnel. The inventory will include all solvents, lubricants, paints, oils, and the presence of asbestos and lead paint. The existing Dillsboro Spill Prevention, Control, and Countermeasure Plan (SPCC), or equivalent Oil Spill Response Manual, along with existing plant Material Safety Data Sheets will be reviewed and utilized during the inspection. The inventory shall include type and quantity of each substance. A Hazardous Waste Removal & Disposal Plan will be developed for the Dillsboro Project based on the inspection inventory. Potentially hazardous material will be removed from the powerhouse prior to commencing powerhouse superstructure demolition work by Duke. 7.1.3 Pollution Control The General Contractor will prevent the pollution of drains and watercourses by sanitary wastes, sediment, debris, and other substances resulting from demolition activities. No sanitary wastes will be permitted to enter any drain or watercourse other than sanitary sewers. No sediment, debris, or other substances will be permitted to enter sanitary sewers, and reasonable measures shall be taken to prevent such materials from entering any drain or watercourse. Duke's Construction Manager will be on-site full-time to ensure that these procedures are followed. 7.2 Erosion and Sediment Control Plan (ESC Plan) The General Contractor shall be responsible for developing a detailed implementation program for the ESC Plan to control erosion and transport of sediment from disturbed areas during the demolition of the Dillsboro Hydroelectric Project. The General Contractor shall provide copies of this program detailing the erosion control measures which will be taken in the specific areas of construction to the Construction Manager and the Environmental-Health & Safety Manager. The General Contractor shall ensure that updates or the latest revisions to this program are provided for the particular areas of construction activity prior to starting work. An erosion control plan is contained within the General Construction Specifications and Drawings. This plan has been submitted to the appropriate permitting agencies and is part of the Federal and State permit requirements. The Decommissioning and Removal Project SPCC will be prepared by the General Contractor. 7.3 License requirements Pursuant to the FERC project license, the contractor will required to take reasonable measures to prevent soil erosion or other forms of water pollution into adjacent waterways. Duke Energy Carolinas, LLC 17 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 7.4 Specialized Plans, Permits and Approvals Refer to Appendix F. 7.5 Frequency of Inspections Each day work is performed the Environmental-Health & Safety Manager shall visually assure that erosion control measures are adequate and that the Environmental Compliance Plan is being followed. 7.6 Documentation and Corrective Actions Construction Manager shall note in the daily work report any concerns or suggested improvements discussed with the General Contractor or the Environmental-Health & Safety Manager and the measures being taken for erosion and environmental control. 7.7 Environmental Deficiency Report The Environmental-Health & Safety Manager shall observe the work site daily for signs of erosion, stream degradation, or other environmental deficiencies and report any such occurrence to the Construction Manager using an Environmental Deficiency Report form provided in Appendix D. The report will reference the requirement violated, describe the nature of the deficiency, the type of corrective action required, and time frame to complete the correction. The Construction Manager shall notify the General Contractor and ensure that the deficiency is corrected. If the deficiency violates a license or permit requirement, the violation shall be noted in the report and the Environmental-Health & Safety Manager shall notify the appropriate parties in accordance with the permit requirements. & SCHEDULE 8.1 Start and Finish Dates The following milestone completion dates have been established for the decommissioning of the Dillsboro Hydroelectric Project and are subject to revision upon award of the Demolition Contract. The General Contractor's construction schedule is presented in Appendix E. A. Award Demolition Contract ......................................... . November 1, 2009 B. Start Demolition Activities .......................................... ...... January 2, 2010 C. Complete Removal of Powerhouse Superstructure ............. .... January 30, 2010 D. Complete Removal of Notch in Dam for Controlled Release . .. February 16, 2010 E. Complete Removal of Spillway, Piers and Gate Structure ..... ......... April 4, 2010 F. Partial Removal of Powerhouse Substructure .................... ........ April 6, 2010 G. Complete Final Grading, Restoration, & Re-Vegetation of .... ........ July 19, 2010 Riverbed and embankments Duke Energy Carolinas, LLC 18 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal 8.2 Anticipated Demolition Sequence 1. Mobilization; 2. Install sediment and erosion control measures; 3. Notch Spillway for Controlled Release; 4. Remove Superstructure of Powerhouse; 5. Remove Spillway, Piers and Gate Structure; 6. Partial Removal of Powerhouse Substructure; Revision No.: Review 2 Issue Date: 12118108 7. Final Grading, Restoration, & Re-Vegetation of Riverbed and embankments; 8.3 Staged Construction The project will be completed in the following three stages: • Stage 1: Includes the removal of the powerhouse superstructure, removal of generating equipment, and establishing water passage through the notch in Spillway. Consideration shall be given to salvaging as much of the turbine- generator equipment as possible. • Stage 2: This stage consists of removing the dam, pier and gate structures. • Stage 3: The third and final stage involves the partial removal of the powerhouse substructure. (The activities of Stage 2 & 3 may be conducted simultaneously.) To provide stability of the embankment along the river at the powerhouse, the training walls and powerhouse basement wall will be evaluated during construction to determine if they can be left in place. However, if the structures are removed a slope stabilizing system shall be installed to support embankment. Refer the project schedule for details of the work schedule. 9. PLANNED USE OF CONSULTANTS 9.1 Areas of Inspection and Review DTA is the Project Design Engineer and as such will periodically visit the site when requested to observe key demolition activities. DTA will also be available to provide demolition engineering services, if required, during the field execution of the project. 9.2 Specialized Consultant Names and Resumes Not applicable for this project. Duke Energy Carolinas, LLC 19 of 19 Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal APPENDIX A Organizational Chart Revision No.: Review 2 Issue Date: 1211812008 Duke Energy Carolinas, LLC Appendix A Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 1211812008 d ? DILLSBORDHYDRCIELECTRIC'PRC1,lEC'TDEC'011IAH SIONIN(; a (DILLSBORO EYDROELECTRIC PROJECT, FERC WO. 2602) Duke Energy carolinas, LLC CO.7.VTR I'tCTIU.1' .11.4.1'.4GE.,IfE.1'T ORGJAIZA TION CHART n ? a? nnk.??r CI?almas, PLC Ou?+?) ?, TII:&,Depa?szu ° Corsad F4rsarDcsaalNn. Dy.Stmc s i 'laltwa bffvRq{d*vG67ii 4sacm CC N C 1 1 i Du1.baw Cud-.LLCV) Duktbav Cacff",LLC(I) Dev?tiaslh?a Assaades(Y) B=KMM" t1I-Htahh& Safety Me ax CMUUd= NMVT R*d Dos* akv ma C%L4aPcsaro CardactPus<at C%=Pmsan CUM N.). cmwt Na: C%W No City, S[ata Dabs HydmIechic Rpd SIDr Ch ULA.NoAh Carolina CMR31 CWThudim CCDV XW's Nava) Detvse'1sazA .&Assodatm(l) Ge al. Cam ax F>mam?mui Camylianct kepala Cmitadpwo t CmtUtPmml cfEw NO. car",. No. PaDsbeso Ilydxekct k Pmjttt$ik Chml9ut,Uff(h Cnka ?aawisntm Iane [eralandcaNaane 'hm>?issimaLaae em nnff CacaattPersarCmaactNa. D WbmnHplmkcrkPmjtdSmr TYPE OFCORSTRUCT101; CATEGORY- IA CONS TRUCTION CONTRACTOW) UN DER S EPARATE CONTRACT VATH LIC EN S EE N N 6 LABELS: 0 (1) TNDICAMAUTHORTIY7)STOPMRKDUETIOADVERSEQUALITY,SAFETY, ORDEFECTIVE MRKCONDITIONS (2) INDICATESAUTHORITY TORECOMMEND STOPWURKTOPERSONNEL LABELED (1). r Duke Energy Carolinas, LLC Appendix A Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal APPENDIX B QCIP Personnel Resumes Revision No.: Review 2 Issue Date: 1211812008 1) Jack Jenkins, Duke's Project Manager 2) Duke's Construction Manager 3) Duke's Environmental-Health & Safety Manager 4) J. Chris Ey, DTA's Project Design Engineer 5) DTA's Environmental Compliance Inspector 6) General Contractor's Project Manager 7) General Contractor's Superintendent Duke Energy Carolinas, LLC Appendix B Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal APPENDIX C List of Contract Documents Additional Documents Revision No.: Review 2 Issue Date: 1211812008 1. Dillsboro Hydroelectric Project Decommissioning & Removal Specifications 2. Public Safety and Traffic Control Plan 3. Demolition Evacuation Plan (CEP) 4. Site Restoration Plan 5. Sediment Management Plan 6. Biological Opinion from USFWS Drawing List 1. 024-0029-00 - Dillsboro Hydroelectric Project Decommissioning and Removal Cover Sheet 2. 024-0029-01 - Sediment & Erosion Control Plan and Limits of Disturbance 3. 024-0029-02 - Powerhouse, Spillway and Flood Gate Removal Plan 4. 024-0029-03 - Rock Slope, Fence and Handrail Locations Reference Documents 1. Dillsboro Reservoir Dredging Plan Duke Energy Carolinas, LLC Appendix C Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal APPENDIX D Example of Reports to be Used 1) Nonconforming Item Report 2) Environmental Deficiency Report 3) Demolition Progress Report Outline Revision No.: Review 2 Issue Date: 1211812008 Duke Energy Carolinas, LLC Appendix D Dillsboro Hydroelectric Project, FERC No. 2602 POr D uke Energy? Contractor Documents Violated NONCONFORMING ITEM REPORT ................................................................................................... Identification Method: ? Tape ? Not Practical ? Other Duke Energy Carolinas, LLC DILLSBORO HYDROELECTRIC PROJECT FERC Project No. 2602 Serial No: Location Of Item: Description of NCR Originator: Technical Review: Date: Date: Responsibility for NCR Disposition: ? Construction Manager ? Design Engineer ? other Disposition of NCR: ? Rework ? Repair Disposition Description: ? Use As Is ? Reject Resolved By: Date: Technical Review & Approval: Date: Action Taken to Implement Disposition and Control NCR: Assigned To Performed By Date Statement of Completed Actions: QA Inspector Date Distribution Project Manager Construction Coordinator Contractor Project Engineer QA Number Initial POr D uke Energy? of Copies Final Final Technical Review Date: Deficiency Number Documents Violated ENVIRONMENTAL DEFICIENCY REPORT ................................................................................................... Duke Energy Carolinas, LLC DILLSBORO HYDROELECTRIC PROJECT FERC Project No. 2602 TO: DATE: TIME: PLEASE CORRECT THE SUBJECT ENVIRONMENTAL DEFICIENCY BY NO LATER THAN: Description of Deficiency Please sign and return when corrective actions are completed: QC Inspector Date: Signature: Sketch Date: POr D uke Energy? Final Review: EH&S Manager Date Duke Energy Project Manager Date Distribution: 1. 2. 3. 4. 5. Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 1211812008 Outline for Bi-weekly Demolition Progress Report 1. Progress of Work 2. Status of Demolition 3. Demolition Difficulties 4. Contract Status 5. Critical Events and Dates 6. Source of Major Demolition Material 7. Material Testing and Results 8. Photographs 9. Erosion Control and Other Environmental Measures 10. Other Items of Interest Duke Energy Carolinas, LLC Appendix D Dillsboro Hydroelectric Project, FERC No. 2602 Quality Control Inspection Program Dillsboro Hydroelectric Project Decommissioning & Removal APPENDIX E Contractor's Schedule Revision No.: Review 2 Issue Date: 1211812008 Duke Energy Carolinas, LLC Appendix E Dillsboro Hydroelectric Project, FERC No. 2602 APPENDIX F Specialized Plans, Permits and Approvals Clean Water Act Section 401: Water Quality Certification 2. Clean Water Act Section 404: Nationwide Permit 27 3. Surrender Order 2008 4. Surrender Order 2007 5. Mining Permits DEMOLITION EVACUATION PLAN (DEP) DILLSBORO HYDROELECTRIC DECOMMISSIONING & REMOVAL PROJECT DILLSBORO HYDROELECTRIC PROJECT (FERC NO. 2602) (Addressing Paragraph D of the FERC Decommissioning Order 120 FERC 61,054) Prepared for: P Duke Ener gY Duke Energy Carolinas, LLC 526 South Church Street Charlotte, North Carolina 28201-1006 By: TA. Devine Tarbell & Associates, Inc. Contiuldn{ Eru,inreny Scirntitits, & Regulawn Specialists 400 S. Tryon Street, Suite 2401 Charlotte, NC 28285 December 18, 2008 Demolition Evacuation Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12-18-08 TABLE OF CONTENTS 1.0 NOTIFICATION FLOWCHART ............................................................... 1 2.0 STATEMENT OF PURPOSE ..................................................................... 1 3.0 PROJECT DESCRIPTION ........................................................................ 1 4.0 EMERGENCY DETECTION, EVALUATION AND CLASSIFICATION .............. 2 5.0 GENERAL RESPONSIBILITIES UNDER THE CEP ....................................... 2 5.1 Licensee Responsibilities ......................................................................... 2 5.2 Responsibility for Notification ................................................................... 2 5.3 Responsibility for Evacuation .................................................................... 3 5.4 Responsibility for Duration, Security, Termination and Follow-up ........................ 3 5.5 CEP Coordinator Responsibility ................................................................. 3 6.0 PREPAREDNESS .................................................................................... 3 6.1 Surveillance ................................................................. ........................ 3 6.2 Response during Periods of Darkness ................................... ........................ 3 6.3 Access to Site ............................................................... ........................ 3 6.4 Response during the Weekends and Holidays ......................... ......................... 3 6.5 Response during Periods of Adverse Weather ......................... ......................... 4 6.6 Alternative Systems of Communication ................................ ......................... 4 6.7 Emergency Supplies and Information ................................... ......................... 4 7.0 INUNDATION MAPS ................................................................................ 4 FIGURES Figure 1: Site Vicinity Map Figure 2: Aerial of Project Site APPENDICES Appendix A - Notification Flow Chart Duke Energy Carolinas, LLC I of I Dillsboro Hydroelectric Project, FERC No. 2602 Demolition Evacuation Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12-18-08 This report has been prepared in accordance with the October 2007, Emergency Action Plans described in Chapter VI of the "Federal Energy Regulatory Commission's (FERC) Engineering Guidelines for the Evaluation of Hydropower Projects ". 1.0 NOTIFICATION FLOWCHART Refer to Appendix A for the Notification Flowchart for this project. The Notification Flowchart shall be posted in prominent locations at the project site and local Emergency Operations Center, as appropriate. 2.0 STATEMENT OF PURPOSE This Demolition Evacuation Plan (DEP) has been prepared to protect the contractor's personnel from possible hazardous situations during the decommissioning and removal of Dillsboro Powerhouse & Dam. This project does not have an Emergency Action Plan (EAP) because of its classification as a "low hazard" dam. 3.0 PROJECT DESCRIPTION The Dillsboro Hydroelectric Project is located in Western North Carolina on the Tuckasegee River near the town of Dillsboro, at River Mile 31.7, in Jackson County, NC. Duke owns and operates the Dillsboro Hydroelectric Project in a limited storage mode. The project has an installed capacity of 225 kW. The project's reservoir is filled to near capacity with an estimated 100,000 to 120,000 cubic yards of sediment. Channel depths for about 500 feet upstream of the powerhouse range from 8 to 12 feet. Most of the remaining portions of the reservoir are 3 to 7 feet deep. Historically, Duke has operated the project in a run-of-river mode, maintaining the headpond within 6 inches of full pond elevation. Project operation depends on available flow in the Tuckasegee River, which is regulated by Duke's upstream East Fork and West Fork projects (Project Nos. 2698 and 2686, respectively). The Order Accepting Surrender and Dismissing Application for Subsequent License were issued by FERC on July 19, 2007. A subsequent Order on Rehearing and Clarification was issued on April 22, 2008. These Orders accept an application made by Duke to remove the Dillsboro Hydroelectric Project. In ordering paragraph (D) of the Order Accepting Surrender and Dismissing Application for Subsequent License, the FERC requires Duke to provide "a detailed description of activities and schedule for removing the project features and restoring the site." The detailed activities schedule provided covers the removal of all project features through site restoration and has been developed in consultation with the North Carolina Division of Water Quality, North Carolina Division of Water Resources, North Carolina Wildlife Resource Commission, U.S. Fish and Wildlife Service, North Carolina Department of Environmental and Natural Resources, and the Eastern Band of Cherokee Indians. The removal is scheduled to be Duke Energy Carolinas, LLC I of 4 Dillsboro Hydroelectric Project, FERC No. 2602 Demolition Evacuation Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12-18-08 removed during the mid-winter to early spring months (i.e. December to March time period) in accordance with Application for Surrender of License (Duke Energy 2004). The decommissioning of the Project includes the full removal to grade of the existing Spillway, piers, and gate; along with the partial removal of the Powerhouse structure. The Spillway is to be removed to the original riverbed over the full width of the river and no rock ledge will be removed. There will be a partial removal of the Powerhouse structure. The river will be returned to its assumed pre-dam bank-to-bank width and depth. Removal will be accomplished by use of hydraulic equipment to remove the dam and powerhouse structures in accordance with a staged demolition plan. An excavator with a hoe- ram attachment or similar mechanism will demolish the dam, with an excavator and a track loader used to remove sediment, if necessary, and remove rubble/concrete. Additionally, mechanical sediment removal will be performed in the forebay area to help conduct flows during the demolition process. During the demolition process, river flow will be diverted through a notch in the dam, and/or passed over the partially demolished crest. 4.0 EMERGENCY DETECTION, EVALUATION AND CLASSIFICATION The General Contractor and Construction Manager shall inspect the jobsite each day to verify that all safety components are working properly. The General Contractor and Construction Manager shall also inspect structures being demolished for stability and safety prior to leaving the job site on a daily basis. Any structure being demolished shall be secure or in no danger of harming the public or contaminating the river while unattended. 5.0 GENERAL RESPONSIBILITIES UNDER THE CEP 5.1 Licensee Responsibilities The responsibilities of the Licensee are (but not limited to) the following: • Explain to personnel involved of the importance of the DEP and why it is necessary; • How to communicate the emergency situation to those who need to be contacted along with samples of typical communications; • Specific actions to be taken after implementing the DEP notification procedures; • Describe the chain of command (i.e. Notification Flowchart); • Provide direction concerning predetermined remedial action to delay, moderate, or alleviate the severity of the emergency condition. 5.2 Responsibility for Notification Refer to the Notification Flowchart in Appendix A for details. Duke Energy Carolinas, LLC 2 of 4 Dillsboro Hydroelectric Project, FERC No. 2602 Demolition Evacuation Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12-18-08 5.3 Responsibility for Evacuation The licensee is responsible for notifying the appropriate emergency management officials when flooding is anticipated, a dam failure is imminent or has occurred, or a potentially hazardous situation is developing. 5.4 Responsibility for Duration, Security, Termination and Follow-up The Construction Manager shall be the designated person for on-site monitoring of the situation at the dam and keep local authorities informed of developing conditions at the dam from the time that an emergency starts until the emergency has been terminated. The Construction Manager shall determine the security measures to be taken during the emergency. 5.5 CEP Coordinator Responsibility The Construction Manager shall be the designed DEP Coordinator who will be responsible for DEP-related activities, including (but not limited to) preparing revisions to the DEP, establishing training seminars, coordinating exercises, etc. This person is the contact if any involved parties have questions about the plan. 6.0 PREPAREDNESS 6.1 Surveillance During the decommissioning and removal of the Dillsboro Hydroelectric Project the General Contractor and the Construction Manager shall evaluate the jobsite on a daily basis to observe anything out of the ordinary. If any demolition personnel other than that stated above observes any potential dangerous situation on the project the General Contractor's Superintendent and the Construction Manager should be notified immediately. 6.2 Response during Periods of Darkness Not applicable for this project. 6.3 Access to Site Not applicable for this project. 6.4 Response during the Weekends and Holidays The Construction Manager & General Contractor shall be accessible by phone in case of an emergency situation on-site. Refer to the Notification Flowchart for further details in Appendix A. Duke Energy Carolinas, LLC 3 of 4 Dillsboro Hydroelectric Project, FERC No. 2602 Demolition Evacuation Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12-18-08 6.5 Response during Periods of Adverse Weather The Construction Manager & General Contractor shall be accessible by phone in case of an emergency situation on-site. Refer to the Notification Flowchart for further details in Appendix A. Also, any construction equipment, if possible, should be removed from area of the river to the construction staging area. 6.6 Alternative Systems of Communication Cellular phones shall be the alternative means of communication during an emergency. Appropriate personnel shall be provided the cellular phone numbers of essential personnel during an emergency if the main form of communication is not functional. 6.7 Emergency Supplies and Information Not applicable for this project. 7.0 INUNDATION MAPS Not applicable for this project. Duke Energy Carolinas, LLC 4 of 4 Dillsboro Hydroelectric Project, FERC No. 2602 Demolition Evacuation Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12-18-08 APPENDIX A Notification Flowchart Duke Energy Carolinas, LLC Appendix A Dillsboro Hydroelectric Project, FERC No. 2602 Demolition Evacuation Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12-18-08 NOTIFICATION FLOWCHART Observer of Emergency Condition Pumped Storage Hydro Mgr. Hydro Central J. S. Hammond (704) 382-6836 (2) (864) 944-4001 (W) (704) 382-6837 (864)888-2660(H) (704) 382-6838 1-877-210-3818 (Pager) (3) F. A Nicholson (Alt) (864) 944-4005 (W) (864) 710-9344 (Cell) 1-888-703-7101 (Pager) Jackson County 911 24 HR Contact No. (1) Hydro Engineering National Weather Service (1) B. T. Keaton Jackson County Sheriff (864) 848-9972 (704) 382-1951 (W) Contact Person (704) 400-4497 (Cell) (1) Work Contact No. (877) 777-3929 (Pager) 24 HR Contact No. Jackson County EMU Public Affairs (2) Contact Person A. F. Alexander (2) Work Contact No. (828) 369-4534 (W) 24 UR Contact No. (828) 524-8652 (H) Satellite Contact No. (877) 620-9267 (Pager) TO) FERC - RO State EMU C. D. Wagner (3) (800) 858-0368 (678) 245-3000 (W) (770)307-4197(H) Hydro Elec. & Water Res. Engr. J. C. Ey * Sheriff will call Pumped Storage Hydro (704) 342-7385 (W) (4) Mgr. if 911 is notified by non-utility observer (704) 849-8359 (H) W. A. Maynard (Alt) (704) 342-7384 (W) (704)846-2960(H) Duke Energy Carolinas, LLC Appendix A Dillsboro Hydroelectric Project, FERC No. 2602 Demolition Evacuation Plan Dillsboro Hydroelectric Project Decommissioning & Removal FIGURES Figure 1: Site Vicinity Map Figure 2: Aerial of Project Site Revision No.: Review 2 Issue Date: 12-18-08 Duke Energy Carolinas, LLC Figures Dillsboro Hydroelectric Project, FERC No. 2602 PUBLIC SAFETY AND TRAFFIC CONTROL PLAN DILLSBORO HYDROELECTRIC DECOMMISSIONING & REMOVAL PROJECT DILLSBORO HYDROELECTRIC PROJECT (FERC NO. 2602) (Addressing Paragraph D of the FERC Decommissioning Order 120 FERC 61,054) Prepared for: P Duke Energy Duke Energy Carolinas, LLC 526 South Church Street Charlotte, North Carolina 28201-1006 By: D Z.A Devine Tarbell & Associates, Inc. Cnn?uWng Engineen, Seirntists, & Regulawn SPeeialisN 400 S. Tryon Street, Suite 2401 Charlotte, NC 28285 December 18, 2008 Public Safety and Traffic Control Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 TABLE OF CONTENTS 1.0 INTRODUCTION ..................................................................... 1 1.1 Purpose ............................................................................................... 1 1.2 Background .......................................................................................... 1 2.0 SCOPE ................................................................................... 2 2.1 Staged Demolition ................................................................................... 2 2.2 Type of Structures to be Demolished ............................................................. 2 2.3 Description of Construction ....................................................................... 3 3.o HAZARDOUS FEATURES AT PROJECT ..................................... 3 4.0 PUBLIC SAFETY MEASURES ................................................... 4 4.1 Public Awareness and Information ............................................................... 4 4.2 Barriers & Fencing to Protect the Public ........................................................ 4 4.3 Lights on for Safety ................................................................................ 4 4.4 Traffic Control ...................................................................................... 4 5.0 TRAFFIC CONTROL PLAN ...................................................... 5 5.1 Traveler Information ............................................................................... 5 5.2 Work Zone Standards .............................................................................. 5 5.3 Temporary Traffic Control Plan .................................................................. 5 5.4 Work Coordination and Safety Meetings ........................................................ 5 5.5 Worker Safety and Training ...................................................................... 5 5.6 Plan Modifications ................................................................................. 5 FIGURES Figure 1: Site Vicinity Map Figure 2: Project Access Location Duke Energy Carolinas, LLC I ofI Dillsboro Hydroelectric Project, FERC No. 2602 Public Safety and Traffic Control Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 1. INTRODUCTION This report has been prepared in accordance with the March 1992, "Guidelines For Public Safety at Hydropower Projects" published by the Federal Energy Regulatory Commission's (FERC) Division of Dam Safety and Inspections. 1.1 Purpose Duke Energy Carolinas, LLC (Duke) intends to decommission the Dillsboro Hydroelectric Project (FERC No. 2602) located in Western North Carolina on the Tuskasegee River. Based on the FERC Order, Duke Energy of Carolinas, LLC (Duke) is required to submit a Public Safety and Traffic Control Plan for operations during the decommissioning of the Hydroelectric Project. 1.2 Background The Dillsboro Hydroelectric Project is located in Western North Carolina on the Tuckasegee River near the town of Dillsboro, at River Mile 31.7, in Jackson County, NC. Duke owns and operates the Dillsboro Hydroelectric Project in a limited storage mode. The project has an installed capacity of 225 kW. The project's reservoir is filled to near capacity with an estimated 100,000 to 120,000 cubic yards of sediment. Channel depths for about 500 feet upstream of the powerhouse range from 8 to 12 feet. Most of the remaining portions of the reservoir are 3 to 7 feet deep. Historically, Duke has operated the project in a run-of-river mode, maintaining the headpond within 6 inches of full pond elevation. Project operation depends on available now in the Tuckasegee River, which is regulated by Duke's upstream East Fork and West Fork projects (Project Nos. 2698 and 2686, respectively). The Order Accepting Surrender and Dismissing Application for Subsequent License were issued by FERC on July 19, 2007. A subsequent Order on Rehearing and Clarification was issued on April 22, 2008. These Orders accept an application made by Duke to remove the Dillsboro Hydroelectric Project. In ordering paragraph (D) of the Order Accepting Surrender and Dismissing Application for Subsequent License, the FERC requires Duke to provide "a detailed description of activities and schedule for removing the project features and restoring the site." The detailed activities schedule provided covers the removal of all project features through site restoration and has been developed in consultation with the North Carolina Division of Water Quality, North Carolina Division of Water Resources, North Carolina Wildlife Resource Commission, U.S. Fish and Wildlife Service, North Carolina Department of Environmental and Natural Resources, and the Eastern Band of Cherokee Indians. The removal is scheduled to be removed during the mid-winter to early spring months (i.e. December to March time period) in accordance with Application for Surrender of License (Duke Energy 2004). Duke Energy Carolinas, LLC I of 5 Dillsboro Hydroelectric Project, FERC No. 2602 Public Safety and Traffic Control Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 2. SCOPE 2.1 Staged Demolition The project will be completed in the following three stages: • Stage 1: This phase includes the removal of the powerhouse superstructure, removal of generating equipment, and establishing water passage through the notch removed in Spillway. Consideration shall be given to salvaging as much of the turbine-generator equipment as possible. • Stage 2: The second phase consists of removing the dam, pier and gate structures. • Stage 3: The third and final phase involves the partial removal of the powerhouse substructure. To provide stability of the embankment along the river at the powerhouse, the training walls and powerhouse basement wall will be evaluated during demolition to determine if they can be left in place. However, if the structures are removed a slope stabilizing system shall be installed to support embankment. The Dillsboro Hydroelectric Project is to be decommissioned and removed to restore the Tuckasegee River back to the original riverbed over the full width of the river and rock ledges will not be removed. The following sections will explain the type of structures present and demolition to be anticipated. The main access to the demolition site will be at the intersection of Mockingbird Lane and Monroe Buchanan Road. Access will also be necessary from North River Rd during the demolition of the Powerhouse structure. 2.2 Type of Structures to be Demolished The Dillsboro Hydroelectric Project consists of a Powerhouse, spillway overflow dam, piers, and gates. The Dillsboro Spillway is a concrete masonry structure that is about 310 feet in length and 12 feet high. Major components of the Dillsboro Dam are listed below, beginning at the left abutment (facing downstream). All elevations are referenced in U. S. Geological Survey (USGS) datum and are expressed in feet above mean sea level (MSL). Main components of the dam include: • A concrete masonry, non-overflowing section with a crest elevation of 1978.2 feet above MSL; • An uncontrolled 14 foot-wide spillway section with a crest elevation of 1972.0 feet above MSL; • A 20-foot wide spillway section with two six foot wide spill gates. The gates sill elevation is at 1961.0 feet above MSL; Duke Energy Carolinas, LLC 2 of 5 Dillsboro Hydroelectric Project, FERC No. 2602 Public Safety and Traffic Control Plan Dillsboro Hydroelectric Project Decommissioning & Removal Revision No.: Review 2 Issue Date: 12118108 • A 197-foot uncontrolled spillway with a crest elevation of 1972 feet above MSL; • A 64.5-foot wide powerhouse with a brick and concrete superstructure and concrete substructure; • An 80-foot long intake section; • A concrete masonry, non-overflowing section with a crest elevation of 1980 feet above MSL. The powerhouse consists of a 64.5-foot wide reinforced concrete substructure and a wood/steel superstructure. Inside the powerhouse are two generating units. The unit closest to the open spillway, Unit No. 1, consists of an S. Morgan Smith vertical Francis-type turbine rated at 276 horsepower (hp) under 12-foot of head and 225 revolutions per minute (rpm) connected to a 219 kilovolt-ampere (kVa) Westinghouse generator at 0.80-power factor and a DC exciter. Unit No. 2 has a Leffel Type - Z turbine rated at 44 hp under 12-foot of head and 200 rpm connected to a 62.5 kVa General Electric generator at 0.80-power factor and a DC exciter. Each unit has an open pit concrete penstock. The rated hydraulic capacities of the turbines are 190 cubic feet per second (cfs) for Unit No. 1 and 44 cfs for Unit No. 2. 2.3 Description of Demolition The decommissioning of the Project includes the full removal to grade of the existing Dillsboro Spillway and partial removal of the Powerhouse structures. The Spillway is to be removed to the original riverbed over the full width of the river and no rock ledge will be removed. The Powerhouse superstructure will be completely removed with a partial removal of the substructure. The river will be returned to its assumed pre-dam bank-to-bank width and depth. Removal will be accomplished by use of hydraulic equipment to remove the dam and powerhouse structures in accordance with a staged demolition plan. An excavator with a hoe-ram attachment or similar mechanism will demolish the spillway, with an excavator and a track loader used to remove sediment, if necessary, and remove rubble/concrete. Additionally, mechanical sediment removal will be performed in the forebay area to help conduct flows during the demolition process. During the demolition process, river now will be diverted through the notch in the dam, and/or passed over the partially demolished crest. 3. HAZARDOUS FEATURES AT PROJECT The two main areas that will be impacted by the demolition are the powerhouse area and upstream and downstream areas of the river near the spillway & gate sections of the dam. In the area of the powerhouse, the powerhouse basement walls could become unstable during demolition. Also, the roadways on either side of the river will be impacted either by drivers having their attention diverted away due to the ongoing demolition activities and/or construction traffic entering/exiting at Mockingbird Lane and on North River Rd. Duke Energy Carolinas, LLC 3 of 5 Dillsboro Hydroelectric Project, FERC No. 2602 Public Safety and Traffic Control Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 4. PUBLIC SAFETY MEASURES The following public safety measures are planned and will be undertaken based on the characteristics of the project location, the high public use of the immediate area the nature of the decommissioning work. 4.1 Public Awareness and Information Information about demolition activities will be provided to local organizations to distribute to the public. Also, signage along the roadways will be provided to warn and inform the public of potential hazards being approached. Also, signage with lighting for nighttime visibility will be posted up and downstream along the river to warn and inform the boaters and canoeist of potential hazards being approached. Furthermore, the signs along the river shall inform canoeists and kayakers required portage around the dam. 4.2 Barriers & Fencing to Protect the Public 4.2.1 Spillways & Overflow Gates Due to the high recreational use of the river, boat barriers or buoys will be utilized to keep boaters and canoeist out of the construction areas. Also signs will be place upstream to warn the public of demolition activities and dangers as previously discussed. 4.2.2 Powerhouse Area Due to the powerhouse's close proximity to North River Road all construction traffic will enter the site from Mockingbird Lane as shown in Figure 2, except during Powerhouse structural demolition. A temporary fence will be required to keep the public from entering the demolition site along North River Road. Also, the demolition staging and access area (off of Mockingbird Lane) shall be secured as well to keep the public from entering from this location. 4.3 Lights on for Safety Project vehicle lights will be illuminated during all hours of operation for safety and visibility. 4.4 Traffic Control In addition to public awareness and intelligently scheduling work around peak hours of operation for the access roads, a plan for safely controlling traffic is a major component of this public safety plan. Section 5 discusses the Traffic Control Plan for this project. Duke Energy Carolinas, LLC 4 of 5 Dillsboro Hydroelectric Project, FERC No. 2602 Public Safety and Traffic Control Plan Revision No.: Review 2 Dillsboro Hydroelectric Project Decommissioning & Removal Issue Date: 12118108 5. TRAFFIC CONTROL PLAN During the Dillsboro Hydroelectric decommissioning project traffic control measures will be implemented on Mockingbird Lane (Old Franklin Hwy) during spillway/dam removal process and on North River Road during removal of the Powerhouse structure. Traffic control measures will meet the standards of the Federal Highway Administration's Manual of Uniform Traffic Control Devices (MUTCD) and North Carolina Supplement to the MUTCD. The traffic control plan will include the following components. 5.1 Traveler Information In addition to the public information and awareness measures described in Section 3, the North Carolina Department of Transportation 511 Traveler Information System will be used to inform the traveling public of conditions and delays that might result on the roads indicated herein as a result of this project. 5.2 Work Zone Standards Traffic controls in work zones will meet the requirements of the MUTCD. Traffic control personnel will be trained and experienced individuals in construction traffic control. 5.3 Temporary Traffic Control Plan A temporary traffic control plan will be used periodically as activities at the powerhouse and dam removal areas require in accordance with MUTCD standards and North Carolina Supplement indicated herein. 5.4 Work Coordination and Safety Meetings In order to reduce or avoid impacts to traffic and in the interest of public safety, the contractor will conduct each morning a briefing with all project workers to review and coordinate the days activities, to conduct a safety briefing specific to that day's work activities and to plan ahead for activities that will impact traffic as well as the safety of the traveling public and project personnel working on-site. 5.5 Worker Safety and Training Project personnel will receive awareness training on how to work next to motor vehicle traffic in a way to promote their personal safety and that of the traveling public. Workers will wear high-visibility safety vests when working around operating demolition equipment and while in or near the roads named herein. 5.6 Plan Modifications Modifications to the traffic control plan may be appropriate during the course of the project due to changed conditions or a determination of better methods of safely and efficiently handling road users. Duke Energy Carolinas, LLC 5 of 5 Dillsboro Hydroelectric Project, FERC No. 2602 4 5 6 ~ 8 REV. 2 3 1 DWG. No. 024-0029-00 - A A ECT JJ AL S • ~ ~ ~ ~ 441 / 74 74 _ 23 107 SYLVA B B ~ TUCKASE E VER DILLSB ~ PROJECT SITE 23 W STER 441 116 x H x 0 z z C C PROJECT DESCRIPTION VIRGINIA THIS PROJECT INCLUDES THE COMPLETE REMOVAL OF THE SPILLWAY, FLOOD GATES, PIERS AND SUPERSTRUCTURE, ALONG WITH THE PARTIAL REMOVAL OF THE SUBSTRUCTURE OF THE DILLSBORO HYDROELECTRIC POWERHOUSE. THESE STRUCTURAL ELEMENTS WILL BE REMOVED TO NEAR RIVERBED ELEVATION. THIS PROJECT ALSO WILL INVOLVE SOME SITE RESTORATION AND SEDIMENT REMOVAL. TENNESSEE DILLSBORO HYDROELECTRIC PROJECT SITE VICINITY 1VIA SCALE: NTS ~ D D JACKSON COUNTY SOUTH CAROLINA DRAWING LIST DRAWING N0. TITLE 024-0029.00 COVER SHEET 024-0029-O1 SEDIMENT & EROSION CONTROL PLAN AND LIMITS OF DISTURBANCE d 024-0029-02 POWERHOUSE, SPILLWAY AND FLOOD GATE REMOVAL PLAN 024-0029-03 ROCK SLOPE, FENCE AND HANDRAIL LOCATIONS SHEET E, E M P Y T IN L R H T R N ADDITIONAL CONTRACT DOCUMENTS SCALE;NTS GENERAL NOTES 1. DILLSBORO HYDROELECTRIC DECOMMISSIONINGAND REMOVAL SPECIFICATIONS (SPECIFICATION N0. 024.0029.0000.) 1. PROPERTY BOUNDARIES, POWERHOUSE STRUCTURE, SPILLWAY 2. QUALITY CONTROL INSPECTION PROGRAM (QCIP) -FEDERAL ENERGY REGULATORY COMMISSION -FERC STRUCTURE LOCATIONS AND SITE TOPOGRAPHY WERE BASED ON JACKSON COUNTY GIS INFORMATION. THE DATUM USED FOR TOPOGRAPHY WAS NAD83, US SURVEY FEET. 3. PUBLIC SAFETY AND TRAFFIC CONTROL PLAN -FERC 4. DEMOLITION EVACUATION PLAN -FERC 2. POWERHOUSElSPILLWAY OVERALL LAYOUT, PLAN VIEW OF POWERHOUSE AND CROSS-SECTION THROUGH POWERHOUSE WERE PROVIDED BY DUKE ENERGY, ALONG WITH ELEVATIONS OF KEY 5. SITE RESTORATION PLAN -FERC COMPONENTS OF THE POWERHOUSE AND SPILLWAY STRUCTURES. 6. SEDIMENT MANAGEMENT PLAN -FERC F 7. BIOLOGICAL OPINION -UNITED STATES FISH AND WILDLIFE SERVICE (USFWS) F SPECIAL PERMITS 1. CLEAN WATER ACT SECTION 401: WATER QUALITY CERTIFICATION -NORTH CAROLINA DIVISION OF WATER QUALTI'Y (NCDWQ) 2. CLEAN WATER ACT SECTION 404: NATIONWIDE PERMIT 27 -UNITED STATES ARMY CORPS OF ENGINEERS (USAGE) 3. SURRENDER ORDER 2008 -FERC 4. SURRENDER ORDER 2007 -FERC 5. MINING PERMIT (DREDGING) -NORTH CAROLINA DIVISION OF LAND QUALITY (NCDLQ) 6. MINING PERMIT (LAND DISTURBANCE) -NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (EPA NPDES) G G DRAWN BY. CIVIL DUKE ENERGY CAROLINAS, LLC Rv LAw JC EY DILLSEORO HYDROELECTRIC PROJECT DESIGNED BY: MECHANICAL late5 r1C. RV LAW eV111e are SSOC , CHECKED BY: ELECTRICAL DECGMMISSO(~ING 8C REMOVAL H H Consultin En ineers, Scientists, & Regulatory Specialists g 9 JC EY nnv~R ~NFFT i APPROVED BY: DATE: vv v 400 South Tryon Street a Charlotte, NC 28285 JC EY 2/31 /08 ISSUED FOR REVIEW. RVL RVL JCE JCE JCE - PROJECT NO. SCALE: DRAWING NO. REV. CONFIDENTIAL & PROPERTY OF OEI/INE TAf?BELL & ASSOCIATES INC _ 1 N0. DATE REVISION VISION DRN DSGN CHKD APPR CIVIL ELEC MECH 024.0029 NONE 024-0029-00 - 4 5 3 6 7 8 1 2 1 2 3 4 5 6 '7 g REV. NOTES FOR NOTES FOR GRAVEL CONSTRUCTION ENTRANCE: D WG ~ f J ~ ~ ~ ~ 4 - ~ ~ ~ 9 - e,. 1. THE E 1. THE ENTRANCE SHALL BE MAINTAINED IN A CONDITION WHICH WILL WILL PREVENT TRACKING OR DIRECT FLOW OF MUD ONTO . STREE STREETS. PERIODIC TOP DRESSING WITH STONE WILL BE FLOTATION ~ OIL BOOM NECESSARY. NECE', 0 z SENSITIVE AREA;. WORK TO A,, ~ 2. ANY REMAIN CLEAR OF RESIDENCES z ~ , . oNTo 2. ANY SEDIMENT SPILLED, DROPPED, WASHED, OR TRACKED A ......AND ROAD. ONTO PUBLIC STREETS MUST BE REMOVED IMMEDIATELY. WATER SURFACE _ _ t' . , 3. LOCH' ~ ' INGRE 3. LOCATE GRAVEL CONSTRUCTION ENTRANCE AT ALL POINTS OF 15' POWERHOUSE INGRESS AND EGRESS UNTIL SITE IS STABILIZED. PROVIDE FRE t f SITE ACCESS ANI~ W ORKING FREQUENT CHECKS OF THE CONSTRUCTION ENTRANCE AND TIMELYMAINTENANCE. RNER FLOW WATER SILT FENCE t AREA FOR POWERHOUSE ~ REMOVAL ; 4. USE /4 0 ~ 4. USE CLASS "A" STONE OR OTHER COARSE AGGREGATE WEIGHT (STONE, / ~ ~ O APPR( . APPROVED BY THE ENGINEER, WITH A MINIMUM DEPTH OF 8 RIVER BOTTOM / BLOCKS, BRICK, ETC.) INCHES. TYPICALLY 2 TO 3 INCH COARSE AGGREGATE FOR 50' 1 INCHE CONSTRUCTION WORK ~ ~•,.0 `t`0 GRAV GRAVEL CONSTRUCTION ENTRANCE. R30' R30' BOUNDARY / Thr ~ 5. PLACE FILTER FABRIC BENEATH STONE. / ; , ~ / ~ ~ , ~ : ~ / ~ B ~ /54 . ~ / PUBLIC ROAD ' / ' WATER SILT FENCE DETAIL B ~ ACCESS PAD FOR REMOVING POWERH / OUSE SPILLWAY , • ~ SUPERSTRUCTURE, PORTIONS OF SCALE: NTS / / SUBSTRUCTURE AND ACCESSING SPILLWAY ~ gk j ~ ~ ~ TO REMOVE SECTIONS FOR IlVITIAL NOTES FOR WSF: ' ~ CONTROLLED RELEASE. (TO BE f / DETERMINED BY CONTRACTOR 1. FILTER FABRIC SEAMS SHALL BE JOINED WITH • ~ ) SUITABLE STAPLES, TIE WIRE, OR HOG RINGS ACCESS PAD AND ROAD FOR REMOVING SPILLWAY AND FLOOD ...FLOOD GATES ~ • ~ GRAVEL CONSTRUCTION ENTRANCE FASTENED TO PREVENT TEAR[NG AND SAGGING OF FABRIC. ~ ~ GATES. 0 BE DETERMINED BY - SCALE; NTS 2. SECURE FABRIC TO FLOTATION. ~ CONTRACTOR) ~ . 3. MATERIAL USED TO HOLD FILTER FABRIC IN PLACE ' ~ _ kp SHALL BE REMOVED AFTER DEMOLITION IS wr ~s~;, W , l , COMPLETED, RIVER ROCKBOULDERS ARE NOT , ; , PERMITTED. . - v ~ 5 -0 STEEL P0, 5'-0" STEEL POST a C ~ ACCESS"ROAD ' `I' . (TY (TYP) 8'-0" MAX WITH WIRE MESH N o WIItE MESH C (TO B, DETERMINED L;' a. BY CONTRACTOR) ~ SILT FENCE _ o \ v ~ ~ , WIRE MESH o ' OC , ~ , kr i FILTER FABRIC C , L N EXISTING ~ I ~ o ~II SEDIMENTATION Y \ K ~ FLOW BASIN ..A.. P ~ \ 30.. ,.y , 36 32 TO . ~ . 2" TO 36" 30" ``x -GROUND 24" MAX. ( SURFACE ~ , ` ~ ~ ti GROUND iL ~ ~ r SURFACE jj iK i i r . \ 8 MIN ~ 'I - ' ' . I ~ ~ _ I, I 24" MIN D - EXISTING 1 4~~ MIN ~ ; D SEDIMENTATION BASIN B , EMBED FILTER FABRIC A , GRAVEL CONSTRUCTION MINIMUM OF 8" VERTICALLY FILTER FABRIC ~ AND 4" FORWARD ALONG THE . ~ . ~ ~ ENTRANCE (MAIN ENTRANCE) TRENCH BENEATH GROUND COMPACTED FILL TO 4 SURFACE ANCHOR FILTER FABRIC , ' , US' TYPICAL SILT FENCE DETAIL SECTION 1 SCALE: NTS - _I r ; NOTES FOR TYPI SCALE: NTS 024-0029-01 OTES FOR TYPICAL SILT FENCE DETAIL; ~ ~ IATERIALS; CONSTRUCTION; MAINTENANCE: MATERIALS; 1. USE A SYT 1. USE A SYNTHETIC FILTER FABRIC IN ACCORDANCE WITH 1. CONSTRUCT THE FILTER FABRIC FROM A CONTINUOUS ROLL CUT TO THE 1. FILTER BARRIERS SHALL BE INSPECTED IMMEDIATELY TABLE 6.6 E TABLE 6.62B OF THE NORTH CAROLINA EROSION AND LENGTH OF THE BARRIER TO AVOID JOINTS. WHEN JOINTS ARE AFTER EACH HALF INCH RAINFALL F.VENT, AT LEAST SEDIMENT BASED OI SEDIMENT CONTROL PLANNING AND DESIGN MANUAL NECESSARY, SECURELY FASTEN THE FILTER CLOTH ONLY AT A SUPPORT ONCE EVERY EVEN DAYS, AND AT LEAST DAILY E BASED ON SILT FENCE TYPE SHOWN ON PROJECT POST WITH 4 FEET MBVIMUM OVERLAP TO THE NEXT POST. DURING PROLONGED RAINFALL. ANY REPAIRS - ~ ~ DRAWING. DRAWING. 2, WIRE OR PLASTIC ZIP TIES USED TO FASTEN WIRE MESH AND FILTER NEEDED SHALL BE MADE IMMEDIATELY. . i ~ ~ 2. ENSURE TF ~ ~ ` i STEEL. MA 2. ENSURE THAT POSTS FOR SEDIMENT FENCES ARE 1.33 LB/LF FABRIC TO POST SHALL HAVE A MINIMUM 50 POUND TENSILE STRENGTH. 2, SHOULD THE FILTER FABRIC DECOMPOSE OR BECOME STEEL. MAKE SURE THAT STEEL POSTS HAVE PROJECTIONS 3. DO NOT ATTACH FILTER FABRIC TO EXISTING TREES. INEFFECTIVE PRIOR TO PROJECT COMPLETION, THE ' ' TO FACILIT TO FACILITATE FASTENING THE FABRIC. FILTER FABRIC SHALL BE REPLACED PROMPTLY. S ~W 3. THE WBZE 0 ' A MINIMUT 3. THE WIRE MESH USED FOR REINFORCEMENT SHALL HAVE 4. USE WIRE MESH A MINIMUM OF 32" IN WIDTH. 3. SEDIMENT DEPOSITS SHOULD BF, REMOVED WHEN A MINIMUM 14 GAUGE AND A MAXIMUM MESH SPACING OF 5. USE FILTER FABRIC A MINIMUM OF 36" IN WIDTH. DEPOSITS REACH APPROXIMATELY HALF THE HEIGHT ~ , 6 INCHES, 6 INCHES, OR PREFABRICATED POLYMER MESH OF 6. DO NOT INSTALL SILT FENCE ACROSS STREAMS, DITCHES, WATERWAYS, OF THE BARRIER. ANY SEDIMENT DEPOSITS ' E UIVALEI Q EQUNALENT STRENGTH. REMAINING IN PLACE AFTER THE SILT FENCE IS i~ . : OR OTHER AREAS OF CONCENTRATED FLOW. REMOVED SHALL BE DRESSED TO CONFORM TO THE Z TURN SILT FENCE UP SLOPE AT ENDS TO PREVENT FLOW AROUND END OF EXISTING GRADE, PREPARED AND SEEDED. SEDIMENT SILT FENCE SILT FENCE FENCE. DEPOSITS NEED TO BE DISPOSED OF PROPERLY. SILT FENCE POST 8. DISTURBED DRAINAGE AREA CAN NOT BE GREATER THAN 0.25 ACRE PER F 100 FEET OF SILT FENCE. , ' I I ~ Tr 9. SLOPE LENGTHS CAN NOT EXCEED CRITERIA SHOWN IN TABLE 6.62A OF F i~ . J ~ THE NORTH CAROLINA EROSION AND SEDIMENT CONTROL PLANNING L. ' AND DESIGN MANUAL. i I II ; ~ CENTERLINE OF CENTERLINE OF SILT FENCE POST NOTES FOR SILT FENCE WITH ROCK OUTLET ~ ~ SILT FENCE POST OFF/FLOW _ ~ ~ 2" MIN NC DOT #5 OR 1. SILT FENCE PORTION SAME AS FOR TYPICAL 60 30 0 60 120FT RUNOFF/FLOW ~ ~ ~ 3„ ~ (`I'1'P) PL , N IE W SCALE:1 60 ~ y ~ ~ #57 WASH STONE ~ r ~ SILT FENCE. APPLY APPLICABLE NOTES FROM SCALE:1"= 60' ' ! ABOVE FOR SILT FENCE WITH ROCK OUTLET. ; _ LEGEND ' ! 2 GROUND 2 2 12" 1~ ~1 2. REMOVED SEDIMENT SHALL BE DEPOSITED TO ~ 024 Ol SURFACE ~ s RUNOFFIFLOW I PROPERTY BOUNDARY NOTES; _ AN AREA THAT WILL NOT CONTRIBUTE EXISTING 5 FT CONTOURS SEDIMENT OFFSITE AND CAN BE PERMANENTLY ' ~ ~ STABILIZED. 1. REFER TO DRAWING N0. 021.0029.00 FOR LIST OF ADDITIONAL 4. PLAN VIEW, SECTIONS AND DETAILS OF THE EX[STING DILLSBORO G EXISTING 10 FT CONTOURS CONTRACT DOCUMENTS AND GENERAL NOTES. HYDROELECTRIC PROJECT STRUCTURES WHERE PROVIDED BY -WSF- WATER SILT FENCE 2. MAINTAIN D DUKE ENERGY CAROLINAS, LLC. (EXHIBIT F DATED NLY 15, 2003) ~ I ~ ~I CLASS A & B RIP RAP ~ 3. SILT FENCE SHALL BE PLACE ON SLOPE RAINAGE, SEDIMENT & EROSION CONTROL AND BASIN -SF- SILT FENCE FEATURES FROM DREDGING OPERATION, ALONG WITH NEW 5. DIMENSIONS & ELEVATIONS PROVIDED FOR SPILLWAY AND G ~ ~ ~ 1 MIN (9~~ MAXIMUM) CONTOURS TO MAXIMIZE PONDING ~I i i ' EFFICIENCY. ° • - • - • CONSTRUCTIONT WORK BOUNDARY FEATURES SHOWN HEREIN AS REQUIRED. POWERHOUSE STRUCTURES ARE APPROXIMATE. CONTRACTOR I SECTIOl\ ~ 4. THF. MAXIMUM STORAGE HEIGHT SHALL BE 9". WATER LINE 3. TOPOGRAPHY, PROPERTY BOUNDARIES, AND WATERLINES SHOWN SHALL FIELD VERIFY DIMENSIONS IF REQUIRED BY OWNER. a ~ _ _ _ j - - - PR[OR DREDGING OPERATION SITE ARE BASED ON DATA PROVIDED BY JACKSON COUNTY GIS AND 6. ALL WORK SHALL BE COMPLETED IN ACCORDANCE WITH THE SCALE; NTS 024-0029-O1 FEATURES ARE APPROXIMATE. THE DATUM UTILIZED WAS NORTH CAROLINA PROJECT DRAWINGS, SPECIFICATIONS AND APPLICABLE PERMITS STATE PLANE, US SURVEY FEET, NAD83. ILT F E~ SILT FENCE WITH ROCK OUTLET SCALE: NTS KALE: NTS DRAWN BY: CIVIL DUKE ENERGY CAROLINAS, LLC Rv LAw DILLSBORO HYDROELECTRIC PROJECT evine are ssoclates n c. DESIGNED BY: MECHANICA Rv LAw DECOMMISSIONING 8c REMOVAL PLAN H Consuitin En ineers Scientists & Re g g gulatory Specialists CHECKED BY: ELECTRICAL H dM Cni ~+h Tnrnn C+rooF t,.,.~.,++,, nir ~o~oc C~f11~~F~IT o~in ~Rncin~i rnniTQni of n~i „yU u~~uai vuc, ivv cvwo / vv jr , jw , ` - 9 ` , . VV LI - v uv 111 NV L \V.11MY V\~/IV 11\\JL I LP"1IV APPROVED BY: DATE: & LIMITS OF DISTURBANCE JC EY CONFIDENTIAL & PROPERTY OF DEFINE 7,4,1?,gELL & A SOCIA rES INC - 12/31/08 ISSUED FOR REVIEW. RVL RVL JCE JCE JCE - - PROJECT NO. SCALE: DRAWING NO. REV. NO. DATE REVISION ;ION DRN DSGN CHKD APPR CIVIL ELEC MECH 024.0029 NOTED 024-0029-01 - 1 2 3 4 5 6 8 _ _ _ _ - 2 3 4 5 1 6 '7 ~ REV. 0 DWG. No. 024-0029-02 N 0 z o) STEP Z: REMOVE INITIAL SPILLWAY SECTION FOR N CONTROLLED RELEASE. REFER TO DEMOLITION . s~ ! 5I STEP 1: REMOVE ° SEQUENCING, HEREIN FOR MORE DETAILS. SUPERSTRUCTURE • CONCRETE 1 \ STEP 3: CONTINUE REMOVAL OF SPILLWAY, SPILLWAY A x ' \ A H SUPERST UCTURE GATES, AND PIERS TO EMBANI~IviENT c4 \ ° 0 ' 20'f- I4' z U ' MAX LIFTS TYP Ay TOP OF PIERS Typ ( ) ~ CONCRETE SPILLW INSTALL RIP RAP, NATURAL BOULDERS, ETC, IN ACCORDANCE z WITH CONTRACT DOCUMENTS AND OWNER'S INSTRUCTIONS. 40' MAX (CREST EL 1972.0)t EL 1978.0 ' REFER TONOTE 6 FOR DETAILS. SEE RIP RAP DETAILS ON \ ET 024-0029--03. ` ~ SUBSTR CTURE SHE ' ~ 04 / ~ . POWERHOUSE STRUCTURE ~...___e- I--... w... / ` . ; / ~ ' ~5 \ , J / ~ • ~ STEP 4: PARTIAL REMOVAL OF ~ SUBSTRUCTURE [OVAL OF ~ cv tUCTURE ° CONCRETE SPILLWAY N STEEL FLOOD FOUNDATION ELEVATION VARIES N GATES ~ B B X54 ~ / / WATER SILT FENCE ELEVATION A / 54 ~ SCALE: NTS 024-0029-02 / CORR. G.S. ROOFING 2 X 6 DIMENSIONAL / LUMBER 4 SITE ACCESS AND WORKING 0 6 X 8 DIMENSIONAL AREA FOR POWERHOUSE / REMOVAL LUMBER / / ' S4 ~ ~ / U 4 X 6 DIMENSIONAL / ~ 4X6D1 / ~ 3 4 X 6 DIMENSIONAL LUMBER TEMPORARY ACCESS UPSTREAM SIDE DOWNSTREAM SIDE ® ~ LUMBE / ~ 024-0029-02 / LUMBER PAD/DRIVE C C ° • w CONSTRUCTION WORK BOUNDARY 4 CLASS "B" RIPRAP ~ l-- EXISTING CONCRETE g/ ~5 / ~ ~ SPILLWAY . coRR. G.S. coxcxET~rsTOx~ 12 X 12 TIMBER SILL 15 ~ / / SIDING ® sussTeuc~ 6 INCHES OF CLASS "A" RII'RAP _ _ y___J (2 TO 3 INCH SIZE AGGREGATE) 1 ~ / - EL 1980.0E ~I e ~ r-RIVERBED 5`~ ® ~ ~ ~ SURFACE ~ .-r • - / • / • ~ - ACCE55 PAD FOR REMOVING ~ ~ / , U 13'-3"t t ' S4 POWERHOUSE SUPERSTRUCTURE, ~ (EL 1972.0)t EL 1974.7E NORMAL HEAD WATER VARIES / ~ / PORTIONS OF SUBSTRUCTURE AND ~ 3'-3"f - FILTER FABRIC ACCESSING SPILLWAY TO REMOVE ~ / ~ / SECTIONS FOR INITIAL ~ UPSTREAM SIDE NOTES• / CONTROLLED RELEASE. TO BE ® ( DETERMINED BY CONTRACTOR } • • 0~ _ ) 1. CONCRETE SPILLWAY GEOMETRY VARIES ALONG LENGTH. ,r. I' 6"t ; ' ' ~ ' " ' 2. THIS IS A SUGGESTED ACCESS PAD/DRIVE WITHIN RIVER D D • / SPILLWAY / ~ CONTRACTOR MAY SUBMIT ALTERNATIVES FOR APPROVAL. . DOWNSTREAM SIDE . / / 8'- f k F--8'-6°t----?~9'f ' ~5 - GROUND SURFACE 8-6 / , SECTION 2 / ~'E 0 / - - / Ih • / . SCALE: NTS 024-0029-02 / , 04 - / / ~ , / / - / • E TI FLOOD GATES SECTION 1 DEMOLITION SEQUENCING. ,I _ - 'e ACCESS PAD AND ROAD FOR REMOVING SCALE: NTS 024-0029-02 - - - SPILLWAY AND FLOOD GATES. AL O, (TO BE DETERMINED BY CONTRACTOR) 1. REMOVE ALL POWERHOUSE EQUIPMENT AND POWERHOUSE SUPERSTRUCTURE IN ACCORllANCE E E - WITH PROJECT SPECIFICATIONS AND CONTRACT DOCUMENTS. / _ - - ~ • _ - ' 2. REMOVE A MAXIMUM OF A 40 FOOT SECTION IN THE SPILLWAY STRUCTURE, AS SHOWN ABOVE / - ' - 10'f 32'f IN ELEVATION A, FOR A CONTROLLED DRAWDOWN OF RESERVOIR, IN LIFTS NOT TO EXCEED 4 \ FEET, TO THE ORIGINAL RIVERBED ELEVATION. A MAXIMUM FLOW OF 800 CFS FROM THE UPSTREAM SIDE CONTROLLED RELEASE CUT SECTION IS ALLOWED AT EACH CUT OF THE CONTROLLED SECTION - \ Oti _ - _ - _ . UNTIL THE RIVERBED IS EXPOSED. NATURAL BOULDERS AND RIVER ROCK SHALL NOT BE 4, - _ - REMOVED. ITEMS N0.1 AND 2 MAY BE COMPLETED CONCURRENTLY. - 3. ONCE THE WATER LEVEL EQUALIZES, PROCEED TO REMOVE REMAINING SPILLWAY AND FLOOD - d5 3S GATE STRUCTURES TO NEAR RIVERBED ELEVATION. NATURAL BOULDERS AND RIVER ROCK _ - - - SHALL NOT BE REMOVED. AS THE STRUCTURES ARE REMOVED ANY STONE OR RIP RAP PLACED • „ w p S FOR ACCESS AND/OR STABILITY SHALL BE REMOVED, ALONG WITH ANY SEDIMENT BELOW OR AROUND WORKING PADS OR ACCESS DRIVES WITHIN THE RIVER BED. ANY DEMOLITION DEBRIS - STONElGRAVEL ACCESS ROAD 1 --?I I~--3'} ~ r-3'} WITHIN THE RIVERBED IS ALSO TO BE REMOVED. (TO BE DETERMINED BY CONTRACTOR) 3'f 35 3'f 12'-10"~ 12'-5"t 12'-2"f 4. REMOVE PORTIONS OF SUBSTRUCTURE SHOWN ABOVE AND/OR AS INSTRUCTED BY OWNER. THE ~ ~ 43'f BOULDERS/STONE WALL ON THE SPILLWAY SIDE OF THE POWERHOUSE SHALL BE REMOVED TO F ~ WATER SURFACE. ANY NATURAL STONES OR BOULDERS REMOVED SHALL BE PLACED ON THE SF EMBANKMENTS AGAINST REMAINING PORTIONS OF THE POWERHOUSE SUBSTRUCTURE WALLS UP THE EMBANKMENT AND AT BASE OF STONE WALL REMAINING RUNNING PARALLEL WITH ! 25'-6"t RIVER. OWNER HA5 AUTHORITY TO DIRECT THE PLACEMENT OF ADDITIONAL EMBANKMENT t PROTECTION IN OTHER AREAS OF THE PROJECT SITE. ITEM N0. 4 CAN BE COMPLETED t • CONCURRENTLY WITH ITEM N0.3. Sp 20 10 0 20 40FT 5. RESTORE RNERBED AND EMBANKMENTS ACCORDING TO APPLICABLE CONTRACT DOCUMENTS. L VIEW P ~ SCALE: I 20' SCALE:1"= 20' LEGEND 7Tf - ~ STONE WALL - PROPERTY BOUNDARY NOTES: DOWNSTREAM SIDE EXISTING 5 FT CONTOURS EXISTING 10 FT CONTOURS 1. REFER TO DRAWING NO. 024.0029.00 FOR LIST OF ADDITIONAL 4. PLAN VIEW, SECTIONS AND DETAILS OF THE EXISTING DILLSBORO G -WSF- WATER SILT FENCE CONTRACT DOCUMENTS AND GENERAL NOTES. HYDROELECTRIC PROJECT STRUCTURES WHERE PROVIDED BY E TI( SECTION 3 G I N ONTROL AND BASIN DUKE ENERGY CAROLINAS, LLC. (EXHIBIT F DATED JULY 15, 2003) -SF- SILT FENCE 2. MAINTAIN DRAINAGE, SEDIMENT & EROS 0 C - • - • - • CONSTRUCTION WORK BOUNDARY FEATURES FROM DREDGING OPERATION, ALONG WITH NEW 5. DIMENSIONS & ELEVATIONS PROVIDED FOR SPILLWAY AND SCALE: NTS SCALE: NTS 024-0029-02 FEATURES SHOWN HEREIN AS REQUIRED. POWERHOUSE STRUCTURES ARE APPROXIMATE. CONTRACTOR WATER LINE SHALL FIELD VERIFY DIMENSIONS IF REQUIRED BY OWNER. DREDGING OPERATION SITE 3. TOPOGRAPHY, PROPERTY BOUNDARIES, AND WATERLINES SHOWN ARE BASED ON DATA PROVIDED BY JACKSON COUNTY GIS AND 6. ALL WORK SHALL BE COMPLETED IN ACCORDANCE WITH THE FEATURES ARE APPROXIMATE. THE DATUM UTILIZED WAS NORTH CAROLINA PROJECT DRAWINGS, SPECIFICATIONS AND APPLICABLE PERM[TS. STATE PLANE, US SURVEY FEET, NAD83. DRAWN BY: CIVIL DUKE ENERGY CAROLINAS, LLC Rv LAw JcE DILLSBORO HYDROELECTRIC PROJECT DESIGNED BY: MECHANICAL rates nc. evlne are ssoc , Rv LAw DECOMMISSIONING 8c REMOVAL PLAN H Consulting Engineers, Scientists, & Regulatory Specialists CHECKED BY: ELECTRICAL H JC EY POWERHOUSE, SPILLWAY AND FLOOD GATE -qqftftmz.7- 400 South Tryon Street e Charlotte, NC 28285 APPROVED BY: DATE: REMOVAL PLAN JC EY CONEIDENTAL & PROPERTY OF DEIONE TARBELL & ASSOCIATES, INC. - 12/31/08 ISSUED FOR REVIEW. RVL RVL JCE JCE JCE - - PROJECT NO. SCALE: DRAWING NO. REV. N0. DATE REVISION VISION DRN DSGN CHKD APPR CIVIL ELEC MECH 024.0029 NOTED 024-0029-02 - 3 4 5 1 2 6 7 8 1 2 3 4 5 6 ~ g DWG. No. 024-0029-03 REV. r x H x o z A U Z A j, r ~ , i B ' B CONSTRUCTION WORK BOUNDARY r•-.., O • , • • ~ • O 4•' p Ory 1 a ~f C 1 ~ ~ \ • C r'~ 1 • i 1 ~ ~ I 1 1 CHAIN LINK FENCE N! 1 n •i 1 ELEVATION VARIES ~ 0 HANDRAIL x ~ oQ F D ` EXISTING SLAB O i ON GRADE EL 1966 f D oQ NCDOT CLASS 2 RIP RAP EL 1960 f ~ w w ~ ~0~ ~ o FILTER FABRIC M ~ (INSTALL PER CONSTRUCT TOE OF THE SLOPE MANUFACTURERS USING EXISTING NATURAL STONE SPECIFICATIONS) REMOVED FROM POWERHOUSE SUB-STRUCTURE PRIOR TO PLACING r' NCDOT CLASS 2 RIP RAP AS SHOWN. r' E ®~r... SECTION 4 E i SCALE: NTS 024-0029-03 .e i i• r' PLA N IE V W II' 8 6 4 8 6 4 2 0 4 8FT SCALE;1"=8' SCALE:1"= 8' F LEGEND NOTES: EXISTING 5 FT CONTOURS 1. REFER TO DRAWING N0. DRAWING N0. 024-0029-00 FOR LIST OF ADDITIONAL CONTRACT DOCUMENTS AP DOCUMENTS AND GENERAL NOTES. EXISTING 10 FT CONTOURS CJ - • - • • ~ CONSTRUCTION WORK BOUNDARY 2. ALL HANDRAILS, GUARDS, AILS, GUARDS, AND CHAIN LINK FENCES USED SHALL BE IN ACCORDANCE WITH 2 --~n--a- CHAIN LINK FENCE tDANCE WITH 2006 NORTH CAROLINA STATE BUILDING CODE AND PROJECT SPECIE] HANDRAIL GUARDS, AND CHAIN LIN] 'ROJECT SPECIFICATIONS. DRAWINGS FOR HANDRAILS, G SID CHAIlV LINK FENCES SHALL BE SUBMITTED TO OWNER FOR APPROVAL, APPROVAL, DRAWN BY: CIVIL . . DUKE ENERGY CAROLINAS, LLC RP uHLENHAKE ~cE DILLSBORO HYDROELECTRIC PROJECT evine are ssociate n s c. DESIGNED BY: MECHANICAL H Consultin En inee g g rs, Scientists, & Regulatory Specialists Rv LAw DECOMP~ISSIONINC ~ REMOVAL PLAN CHECKED BY: ELECTRICAL H dM finuth Tn~nn C+rocl rh~~i,.++„ nir ~o~oc vv... w vu v~r• VIIPIIUtl6IYV GUGOJ JC EY KUUK SLUHE' FENCE AND HANDRAIL APPROVED BY: DATE: LOCATIONS SHEET CCNFIDENTIAL & PROPERTY OF DES/NE TA/?BELL & ASSOCIATES, INC - 12/31/08 ISSUED FOR REVIEW. JC EY RPU RVL JCE JCE JCE - PROJECT NO. SCALE: DRAWING NO. RFV. N0. DATE REVISION ON DRN DSGN CHKD APPR CIVIL ELEC MECH 024.0029 NOTED 024-0029-03 - 1 2 3 4 5 6 8