HomeMy WebLinkAbout20161263 Ver 1_More Info Received_20170929September 28, 2017
STEWARTGraham Bruns, PE
Stewart Inc.
421 Fayetteville St, Suite 400,
Raleigh, NC 27601
Zan Price, P.E., Assistant Regional Supervisor
NCDEQ— Division of Water Resources
2090 U.S. Hwy. 70
Swannanoa, N.C. 28711
Mr. Price,
Thank you for working with our team to provide the additional information requested in
response to Beaucatcher Mountain Greenway Trail/DWR 2016-1263.
Below are the responses to the questions that you had before. We have provided
supporting documentation when appropriate via this Sharefile link: https://stewart-
eng.sharefile.com/d-s2d58cOd82d54de58.
Please use the link to download the information in response to each question below.
We have updated our drainage and pipe network from what has previously been
submitted showing dewatering streams to avoid a retaining wall to now new pipes that
will go under the retaining wall and keep the streams in the same location without
dewatering channels.
The flow rate is very small for each of these streams and our plans already have
sequencing in the notes that state if there is an active flow that an impervious dike be
construction and the pipes be replaced in a day. A temporary pump around will not be
required.
1. Based on our site visit (week of April 27', 2017) and field work completed by
Owen Carson at Equinox Environmental, impact sites S2, S3, S4, and S5 involve
jurisdictional streams (i.e. at least intermittent flow). DWR is good with the
proposed plan for S2 and S5. Additional clarification is needed for S3 and S4.
The proposed plan for S3 is to divert flows approximately 150 -linear feet along
the greenway trail and discharge the flow via an 18 -inch pipe. The proposed
flow diversion would dry up the baseflow in the existing receiving channel of S3
for an undermined length of channel. The permit application impact table
would need to include the dewatered channel length as an impact if this
proposed drainage plan is maintained. Please either update the impact table
or modify the proposed plan.
S3 is currently coming out of an 8" diameter corrugated metal pipe (CMP),
approximately 17 -ft long, that is in poor shape with an inlet that is buried below
grade along our alignment-L3REV- based on survey data and field investigations
by Equinox. We will be installing a 24" reinforced concrete pipe (RCP) parallel to
the existing 8" CMP pipe and grading the outlet to maintain the existing channel
downstream. The 8" CMP will be removed after the 24" RCP has been installed.
STRONGER BY DESIGN
421 FAYETTEVILLE ST. RALEIGH, NC T 919.380.8750
SUITE 400 27601 F 919.380.8752
Responses/Additional Information - Beaucatcher Mountain Greenway Trail - DWR 2016-1263
September 28, 2017
Page 2
The replacement pipe will be 27 -ft long as we will need to daylight further down
the hill because of a proposed retaining wall. The elevation of the proposed 24"
RCP will be lower than the existing 8" CMP to accommodate the footers on the
retaining wall.
There is another existing pipe that is a 15" CMP, 22 -ft long just uphill that
crosses our alignment-L1REV-. We will be replacing that pipe in place with a 24"
RCP that is 38 -ft long and will tie to a drainage structure and drop inlet above our
trail to catch any water that is coming down the hill.
We will tie the two new pipes into the same drainage structure (24A) and have
a drop inlet to catch any surface water at the intersection of the two trails. In this
way, we will be controlling the water velocities coming down and across our
corridor as well as cleaning up the area. Given that there isn't any adequate
aquatic passage with the existing pipe system and that there is not a true existing
upstream channel on the mountain (only the small existing ditch beside the old
roadbed), we are not proposing any aquatic passage and would like an
exemption/exception for this requirement on S3.
S4 is currently coming out of an 18" diameter corrugated metal pipe (CMP) that
approximately 28 -ft long. Based on survey data and field investigations by
Equinox, Stewart understands there is no existing defined upstream channel on
the mountain (only the small ditch adjacent to the existing roadbed). There does
appear to be a swale on the mountain above (just below the-L1REV- trail
roadbed), but the contours flatten out and the runoff appears to return to sheet
flow above the 18" culvert. We will be replacing the 18" CMP with at 28 -ft long
reinforced concrete pipe (RCP) and grading the outlet to maintain the existing
channel downstream.
Please contact myself if you have any questions or need any additional information. We
look forward to your response and to moving the project forward to construction.
Regards,
Graham Bruns, PE
Bicycle & Pedestrian Project Manager
STEWART
STRONGER BY DESIGN
421 FAYETTEVILLE ST. RALEIGH, NC T 919.380.8750
SUITE 400 27601 F 919.380.8752
E3 0� VJA �<G
o -r
Office Use Only:
Corps action ID no.
DWQ project no.
Form Version 1.4 January 2009
Page 1 of 10
PCN Form — Version 1.4 January 2009
Pre -Construction Notification (PCN) Form
A.
Applicant Information
1.
Processing
1 a.
Type(s) of approval sought from the Corps:
❑X Section 404 Permit Section 10 ❑ rmit
1 b.
Specify Nationwide Permit (NWP) number: 14 or General Permit (GP) number:
1c.
Has the NWP or GP number been verified by the Corps?
❑X Yes ❑ No
1 d.
Type(s) of approval sought from the DWQ (check all that apply):
❑X 401 Water Quality Certification — Regular ❑ Non -404 Jurisdictional General Permit
❑ 401 Water Quality Certification — Express ❑ Riparian Buffer Authorization
1 e.
Is this notification solely for the record
because written approval is not required?
For the record only for DWQ
401 Certification:
❑ Yes ❑X No
For the record only for Corps Permit:
❑ Yes ❑X No
1f.
Is payment into a mitigation bank or in -lieu fee program proposed for
mitigation of impacts? If so, attach the acceptance letter from mitigation bank
or in -lieu fee program.
❑ Yes ❑X No
1 g.
Is the project located in any of NC's twenty coastal counties. If yes, answer 1 h
below.
❑ Yes ❑X No
1 h.
Is the project located within a NC DCM Area of Environmental Concern (AEC)?
❑ Yes ❑X No
2.
Project Information
2a.
Name of project:
Beaucatcher Mountain Greenway Trail
2b.
County:
Buncombe
2c.
Nearest municipality / town:
Asheville
2d.
Subdivision name:
2e.
NCDOT only, T.I.P. or state project no:
3.
Owner Information
3a.
Name(s) on Recorded Deed:
City of Asheville
3b.
Deed Book and Page No.
Six parcels (book/page): 0100/0348; 5094/0774; 0730/0212; 4720/1011; 0043/0039;
3c.
Responsible Party (for LLC if
applicable):
Pete Wall - Landscape Architect & Project Manager
3d.
Street address:
70 Court Plaza [PO BOX 7148]
3e.
City, state, zip:
Asheville, NC 28802
3f.
Telephone no.:
(828) 259-5815
3g.
Fax no.:
(828) 259-5606; Parks & Rec General fax: (828) 251-4058
3h.
Email address:
pwall@ashevillenc.gov
Page 1 of 10
PCN Form — Version 1.4 January 2009
4.
Applicant Information (if different from owner)
4a.
Applicant is:
❑ Agent ❑X Other, specify: Engineering Company
4b.
Name:
Graham Bruns
4c.
Business name
(if applicable):
Stewart Inc.
4d.
Street address:
421 Fayetteville Street, Suite 400
4e.
City, state, zip:
Raleigh, NC 27601
4f.
Telephone no.:
(919) 526-0612
4g.
Fax no.:
(919) 380-8752
4h.
Email address:
gbruns@stewartinc.com
5.
Agent/Consultant Information (if applicable)
5a.
Name:
Owen Carson
5b.
Business name
(if applicable):
Equinox Environmental Consultation & Design, Inc.
5c.
Street address:
37 Haywood Street, Suite 100
5d.
City, state, zip:
Asheville, NC 28801
5e.
Telephone no.:
(828) 253-6856 x204
5f.
Fax no.:
(828) 253-8256
5g.
Email address:
owen@equinoxenvironmental.com
Page 2 of 10
B.
Project Information and Prior Project History
1.
Property Identification
1a.
Property identification no. (tax PIN or parcel ID):
Project spans multiple PINS; see 3a for details;
1 b.
Site coordinates (in decimal degrees):
Latitude: 35.588 Longitude: -82543
1 c.
Property size:
7.32 acres
2.
Surface Waters
2a.
Name of nearest body of water to proposed project:
French Broad River
2b.
Water Quality Classification of nearest receiving water:
B
2c.
River basin:
French Broad
3.
Project Description
3a. Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this
application:
The greenway centerline goes through land that is mostly forested with a range of hardwoods; areas lacking forest occur along road edges and
intersections as well as at the top of the overlook. Surrounding tracts contain home -sites or small residential developments. Property PINs include:
964856680600000; 964855874900000; 964980206500000; 964970840800000; 964866179800000; 964856700400000; and adjacent rights-of-way;
3b.
List the total estimated acreage of all existing wetlands on the property: 0.089
3c.
List the total estimated linear feet of all existing streams (intermittent and perennial) on the property: 221
3d. Explain the purpose of the proposed project:
The greenway will add to the existing Asheville City trail network. This trail section will connect the Memorial Stadium Park with the Helen's Bridge Parl
communities, providing bicycle and pedestrian access to the aforementioned parks and greenway trails and extending the reach for
bicvcle and pedestrian travel between residential. a olovme t. commercial and institutional centers.
3e.
Asheville
Describe the overall project in detail, including the type of equipment to be used:
City proposes to construct approximately 2.3 miles of greenway located on City property and right of way between Memorial Stadium Park ar
4.
Jurisdictional Determinations
4a.
Have jurisdictional wetland or stream determinations by the
Corps or State been requested or obtained for this property /
project (includingall prior phases in the past?
❑ Yes ❑ No ❑X Unknown
Comments:
4b.
If the Corps made the jurisdictional determination, what type
of determination was made?
❑ Preliminary ❑ Final
4c.
If yes, who delineated the jurisdictional areas?
Name (if known):
Agency/Consultant Company:
Other:
4d.
If yes, list the dates of the Corps jurisdictional determinations or State determinations and attach documentation.
5.
Project History
5a.
Have permits or certifications been requested or obtained for
this project (including all prior phases) in the past?
❑X Yes ❑ No ❑ Unknown
5b. If yes, explain in detail according to "help file" instructions.
Permits have been applied for with City of Asheville Storm Water.
6.
Future Project Plans
6a.
Is this a phased project?
❑ Yes ❑X No
6b.
If yes, explain.
Page 3 of 10
PCN Form — Version 1.4 January 2009
C. Proposed Impacts Inventory
1. Impacts Summary
1 a. Which sections were completed below for your project (check all that apply):
❑X Wetlands Strea X — tributaries Buffers Open \❑ters P❑d Construction ❑
2. Wetland Impacts
If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted.
2a.
2b.
2c.
2d.
2e.
2f.
Wetland impact
Type of impact
Type of wetland
Forested
Type of jurisdiction
Area of
number
Corps (404,10) or
impact
Permanent (P) or
DWQ (401, other)
(acres)
Temporary T
W1 P
Fill
Small -Basin Wetland
No
Corps
0.089
W2 38
Choose one
Choose one
Yes/No
W3 -
Choose one
Choose one
Yes/No
W4 -
Choose one
Choose one
Yes/No
W5 -
Choose one
Choose one
Yes/No
W6 -
Choose one
Choose one
Yes/No
2g. Total Wetland Impacts:
0.089
2h. Comments:
Wetland W1 exists at the top of the Beaucather Overlook park area, at the southern extent of the alignment (see Figure 1, attached). It is rated in
USFWS National Wetlands Inventory as 'PUSAx', which indicates an excavated (human -made) Palustrine wetland type with an Unconsolidated
Shoreline that is temporarily flooded for only a small portion of the growing season. It is a result of the capping off of the White Fawn Reservoir in
1978; it was filled with concrete and now collects water and has wetland vegetation and soils, but with disconnected hydrology (upstream and down).
3. Stream Impacts
If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this
question for all stream sites impacted.
3a.
3b.
3c.
3d.
3e.
3f.
3g.
Stream impact
Type of impact
Stream name
Perennial (PER) or
Type of
Average
Impact
number
intermittent (INT)?
jurisdiction
stream
length
Permanent (P) or
width
(linear
Temporary (T)
(feet)
feet)
S1 T
Culvert
UT to French Broad
PER
DWQ
1
28
S2 T
Culvert
UT to French Broad
PER
DWQ
1
43
S3 T
Culvert
UT to French Broad
PER
DWQ
1
65.00000000
S4 T
Culvert
UT to French Broad
PER
DWQ
771
28.00000000
S5
221 Culvert
UT to French Broad
INT
DWQ
1
35
S6 -
Choose one
3h. Total stream and tributary impacts
199.000000
3i. Comments:
Project proposes to replace existing undersized and non-functioning culverts with appropriately sized, functional ones.
Page 4 of 10
PCN Form — Version 1.4 January 2009
4. Open Water Impacts
If there are proposed impacts to lakes, ponds, estuaries, tributaries, sounds, the Atlantic Ocean, or any other open water of
the U.S. then indivi ually list all open water impacts below.
4a.
Open water
impact number
Permanent (P) or
Temporary T
4b.
Name of waterbody
(if applicable)
4c.
Type of impact
4d.
Waterbody
type
4e.
Area of impact (acres)
01
Choose one
Choose
02 -
Choose one
Choose
03 -
Choose one
Choose
O4 -
Choose one
Choose
4f. Total open water impacts
4g. Comments:
5. Pond or Lake Construction
If pond or lake construction proposed, the complete the chart below.
5a.
Pond ID number
5b.
Proposed use or
purpose of pond
5c.
Wetland Impacts (acres)
5d.
Stream Impacts (feet)
5e.
Upland
(acres)
Flooded
Filled
Excavated
Flooded
Filled
Excavated
P1
Choose one
P2
Choose one
5f. Total:
5g. Comments:
5h. Is a dam high hazard permit required?
❑ Yes ❑ No If yes, permit ID no:
5i. Expected pond surface area (acres):
5j. Size of pond watershed (acres):
5k. Method of construction:
6. Buffer Impacts (for DWQ)
If project will impact a protected riparian buffer, then complete the chart below. If yes, then individually list all buffer impacts
below. If any impacts require mitigation, then you MUST fill out Section D of this form.
6a. Project is in which protected basin?
❑ Neuse ❑ Tar -Pamlico Dawba C]ndleman Other
6b.
Buffer Impact
number —
Permanent (P) or
Temporary T
6c.
Reason for impact
6d.
Stream name
6e.
Buffer
mitigation
required?
6f.
Zone 1
impact
(square
feet)
6g.
Zone 2
impact
(square
feet
B1 -
Yes/No
B2 -
Yes/No
B3 -
Yes/No
B4 -
Yes/No
B5 -
Yes/No
B6 -
Yes/No
6h. Total Buffer Impacts:
6i. Comments:
Page 5 of 10
D.
Impact Justification and Mitigation
1.
Avoidance and Minimization
1a. Specifically describe measures taken to avoid or minimize the proposed impacts in designing project.
Avoidance and minimization is achieved as nearly the entire project is utilizing existing roadbeds.
1 b. Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques.
Waterway crossings are readily accessible, so culverts will be replaced as needed as part of the construction sequence.
2.
Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State
2a.
Does the project require Compensatory Mitigation for
impacts to Waters of the U.S. or Waters of the State?
❑ Yes ❑X No
2b.
If yes, mitigation is required by (check all that apply):
❑ DWQ ❑ Corps
2c.
If yes, which mitigation option will be used for this
project?
❑ Mitigation bank
El Payment to in -lieu fee program
❑ Permittee Responsible Mitigation
3.
Complete if Using a Mitigation Bank
3a.
Name of Mitigation Bank:
3b.
Credits Purchased (attach receipt and letter)
Type: Choose one
Type: Choose one
Type: Choose one
Quantity:
Quantity:
Quantity:
3c.
Comments:
4.
Complete if Making a Payment to In -lieu Fee Program
4a.
Approval letter from in -lieu fee program is attached.
❑ Yes
4b.
Stream mitigation requested:
linear feet
4c.
If using stream mitigation, stream temperature:
Choose one
4d.
Buffer mitigation requested (DWQ only):
square feet
4e.
Riparian wetland mitigation requested:
acres
4f.
Non -riparian wetland mitigation requested:
acres
4g. Coastal (tidal) wetland mitigation requested:
acres
4h.
Comments:
5.
Complete if Using a Permittee Responsible Mitigation Plan
5a.
If using a permittee responsible mitigation plan, provide a description of the proposed mitigation plan.
Page 6 of 10
PCN Form — Version 1.4 January 2009
6. Buffer Mitigation (State Regulated Riparian Buffer Rules) — required by DWQ
6a. Will the project result in an impact within a protected riparian buffer that requires
❑ Yes ❑ No
buffer mitigation?
6b. If yes, then identify the square feet of impact to each zone of the riparian buffer that requires mitigation. Calculate the
amount of mitigation required.
6c.
6d.
6e.
Zone
Reason for impact
Total impact
Multiplier
Required mitigation
(square feet)
(square feet)
Zone 1
3 (2 for Catawba)
Zone 2
1.5
6f. Total buffer mitigation required:
6g. If buffer mitigation is required, discuss what type of mitigation is proposed (e.g., payment to private mitigation bank,
permittee responsible riparian buffer restoration, payment into an approved in -lieu fee fund).
6h. Comments:
Page 7 of 10
E.
Stormwater Management and Diffuse Flow Plan (required by DWQ)
1.
Diffuse Flow Plan
1 a.
Does the project include or is it adjacent to protected riparian buffers identified
❑ Yes X❑ No
within one of the NC Riparian Buffer Protection Rules?
1 b.
If yes, then is a diffuse flow plan included? If no, explain why.
❑ Yes ❑ No
2.
Stormwater Management Plan
2a.
What is the overall percent imperviousness of this project?
10.76%
2b.
Does this project require a Stormwater Management Plan?
❑x Yes ❑ No
2c.
If this project DOES NOT require a Stormwater Management Plan, explain why:
2d.
If this project DOES require a Stormwater Management Plan, then provide a brief, narrative
description of the plan:
All
upslope stormwater runoff is proposed to be directed to clean -water ditches and appropriately -sized riprap dissipator pads. All proposed
impervious
area of the greenway extension is proposed to sheet flow into the vegetated downstream buffer. By the Asheville UDO subsection 7-12-
2(f)2d the development utilizes sheetflow measures and can be waived of subsection 7-12-2(f)(1) and (2). Maintaining sheetflow is more
beneficial
than concentrating the flow.
2e.
Who will be responsible for the review of the Stormwater Management Plan?
City of Asheville
3.
Certified Local Government Stormwater Review
3a.
In which localgovernment's jurisdiction is thisproject?
City of Asheville
❑x Phase II
❑ NSW
3b.
Which of the following locally -implemented stormwater management programs
❑ USMP
apply (check all that apply):
❑ Water Supply Watershed
❑ Other:
3c.
Has the approved Stormwater Management Plan with proof of approval been
❑ Yes ❑ No
attached?
4.
DWQ Stormwater Program Review
❑Coastal counties
❑ HQW
4a.
Which of the following state -implemented stormwater management programs apply
❑ORW
(check all that apply):
❑Session Law 2006-246
❑ Other:
4b.
Has the approved Stormwater Management Plan with proof of approval been
❑ Yes ❑ No
attached?
5.
DWQ 401 Unit Stormwater Review
5a.
Does the Stormwater Management Plan meet the appropriate requirements?
❑ Yes ❑ No
5b.
Have all of the 401 Unit submittal requirements been met?
❑ Yes ❑ No
Page 8 of 10
PCN Form — Version 1.4 January 2009
F.
Supplementary Information
1.
Environmental Documentation (DWQ Requirement)
1 a.
Does the project involve an expenditure of public (federal/state/local) funds or the
❑ Yes ❑X No
use of public (federal/state) land?
1 b.
If you answered "yes" to the above, does the project require preparation of an
environmental document pursuant to the requirements of the National or State
❑ Yes ❑ No
(North Carolina) Environmental Policy Act (NEPA/SEPA)?
1 c.
If you answered "yes" to the above, has the document review been finalized by the
State Clearing House? (If so, attach a copy of the NEPA or SEPA final approval
❑ Yes ❑ No
letter.)
Comments:
2.
Violations (DWQ Requirement)
2a.
Is the site in violation of DWQ Wetland Rules (15A NCAC 2H .0500), Isolated
Wetland Rules (15A NCAC 2H .1300), DWQ Surface Water or Wetland Standards,
F] Yes ❑X No
or Riparian Buffer Rules (15A NCAC 2B .0200)?
2b.
Is this an after -the -fact permit application?
F1 Yes ❑X No
2c.
If you answered "yes" to one or both of the above questions, provide an explanation of the violation(s):
3.
Cumulative Impacts (DWQ Requirement)
3a.
Will this project (based on past and reasonably anticipated future impacts) result in
❑Yes ❑X No
additional development, which could impact nearby downstream water quality?
3b.
If you answered "yes" to the above, submit a qualitative or quantitative cumulative impact analysis in accordance with the
most recent DWQ policy. If you answered "no," provide a short narrative description.
4.
Sewage Disposal (DWQ Requirement)
4a.
Clearly detail the ultimate treatment methods and disposition (non -discharge or discharge) of wastewater generated from
the proposed project, or available capacity of the subject facility.
Page 9 of 10
PCN Form — Version 1.4 January 2009
5. Endangered Species and Designated Critical Habitat (Corps Requirement)
5a. Will this project occur in or near an area with federally protected species or
❑ YesX❑ No
habitat?
5b. Have you checked with the USFWS concerning Endangered Species Act
❑X Yes ❑ No
impacts?
5c. If yes, indicate the USFWS Field Office you have contacted.
Asheville
5d. What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical
Habitat?
Used USFWS IPAC Tool (on-line) to generate potential resource impacts; compared potential species/habitat lists kicked back from IPAC to existing
conditions on site, found no species or habitats present.
6. Essential Fish Habitat (Corps Requirement)
6a. Will this project occur in or near an area designated as essential fish habitat?
❑ Yes ❑X No
6b. What data sources did you use to determine whether your site would impact Essential Fish Habitat?
The National Oceanic and Atmospheric Administration (NOAA) interactive on-line Essential Fish Habitat Mapper Tool (EFH Mapper)
7. Historic or Prehistoric Cultural Resources (Corps Requirement)
7a. Will this project occur in or near an area that the state, federal or tribal
governments have designated as having historic or cultural preservation
❑ Yes ❑X No
status (e.g., National Historic Trust designation or properties significant in
North Carolina history and archaeology)?
7b. What data sources did you use to determine whether your site would impact historic or archeological resources?
HPOWEB Map
8. Flood Zone Designation (Corps Requirement)
8a. Will this project occur in a FEMA -designated 100 -year floodplain?
❑ Yes ❑X No
8b. If yes, explain how project meets FEMA requirements:
8c. What source(s) did you use to make the floodplain determination?
Most current (2010) FEMA Floodplain Geospatial Data; FEMA Flood Map Viewer
Applicant/Agent's Printed Name
Date
Applicant/Agent's Signature
(Agent's signature is valid only if an authorization
letter from the applicant is provided.
Page 10 of 10
Existing conditions shown have been
compiled from a variety of sources to
include; City of Asheville, Stewart, GIS
and NC Floodmaps LiDAR Bare Earth.
Contractor shall field verify existing
conditions before commencing construction
activities and notify engineer immediately
upon noting any discrepancies that may
affect design and/or construction activities.
EST 2 TONS CLASS
'I' RIP RAP EST 8 SY
FILTER FABRIC
VELOCITY
DISSIPATOR PAD
PSRM DITCH #14
SEE DETAIL 1
EST 6 TONS CLASS 'I' RIP RAP
EST 18 SY FILTER FABRIC
VELOCITY DISSIPATOR PAD
CITY OF ASHEVILLE
D.B. 4720, PG. 1011
P. B. 124, PGe 48
PIN 964866179800000
30 15 0 30 60
■ ■ ■
SCALE: 1"=30'
1-1
DETAIL 1
SPECIAL CUT DITCH
( Not to Scale)
Front
o Ditch
Natural `L1 et Slope
Ground ?'I D F\d
d
Type of Liner= PSRM
Min. D= 1.0 Ft.l
Max d = 1.0 Ft.
FROM STA. 18 + 00 TO STA. 22 + 20 -L3 REV- RT
FROM STA. 25 + 30 TO STA. 26 + 00 -L3 REV- RT
DETAIL 2
SPECIAL CUT DITCH
( Not to Scale)
Fr(
Natural v�\at Di
G ou d ?')
ID\O��et SI<
d
Min. D= 1.1
Type of Liner= COIR FIBER Max d= 1.(
FROM STA. 22 + 20 TO STA. 24 + 80 -L3 -REV- R
END WALL 6A
—L3_REV— STA. 26+00.00
OFF 7.00' LT
PSRM MAT DITCH #28
SEE DETAIL 1
CITY OF ASHEVILLE
D.B. 4720, PG. 1011
P. B. 124, PGo 48
PIN 964866179800000
2 TONS CLASS
RIP RAP EST 8 SY
Z FABRIC VELOCITY
DISSIPATOR PAD
PSRM DITCH #16
SEE DETAIL 1
0
-L3 REV-
, O
".x".....x
HW
15 - 10' 8 -
N c
,\------------_ ---------�
i1t1� f_
EXISTING 18" CMP PIPE
TO BE REMOVED AND
REPLACED WITH 18" RCP
COIR FIBER MAT DITCH #18
SEE DETAIL 2
COIR FIBER MAT
DITCH #26
SEE DETAIL 2
END STANDARD SPLIT RAIL FENCE
BEGIN SAFETY RAIL (TYPE 1)
BEGIN WALL 6A
—L3—REV— STA. 23 + 60.00
OFF 7.00' LT
EST 6 TONS CLASS 'I' RIP RAP
EST 18 SY FILTER FABRIC
VELOCITY DISSIPATOR PAD
GRADE TO MATCH
EXISTING STREAM BED
INSTALL SIGN
—L3_REV— STA. 24 + 901 81LT
W7-5
(18"x18")
< dt N0/4000
O
b
HW 19 �
-- x
M.
10' m
295.
P30
-
rDl
20
�
RF( -,IN STANDARD —J �
SPLIT RAIL FENCE J
—1 -3 -EV-- -STA 22 + 50-00'
OFF 7.00' LT
COIR FIBER MAT DITCH #20--==�,,
SEE DETAIL 2
26 c
ti
0 F
CO �(
IIg z
40>
•...uu..' ..xu.n . ,
/�— 24C INSTALL SIGN
—1-3 REV— STA. 25 + 30 8 RT
HW -lc W7-5 (18"x18")
j . � i
CA �C
INV.: 2320.58'
/
�_�2335
40
24
COIR FIBER MAT
ai
DITCH #22
SEE DETAIL 2
l i7� ���il���•
-7 D
REMOVE EXISTING 8"
PIPE AND REPLACE
r WITH 24" RCP co
}
0
DI246 REMOVE EXISTING 15" <
CMP PIPE AND Uj
REPLACE WITH 24" U,
RCP g
CITY OF ASHEVILLE
D.B. 4720, PG. 1011
P.B. 124, PG. 48
PIN 964866179800000
FOR -1-1 REV- PLAN AND PROFILE VIEW, SEE SHEETS 14,14A, 15 & 15A
FOR -1-3- PROFILE VIEW, SEE SHEET 6A
o •-i o E
ooin
o d -,o r� o
NCO U
o�
U ,Uoa},
o��nzrn E
2: o; �
�
� �rn�
r= LL
.S-1
� ~
E
Q
LLQ
V)
1)
GREENWAY ENGINEER:
l.'01%4611040
.�qg�t� '�►4Q�
�DocuSign,,��:�
04(
.�F7F1�3�4LFFJ.�O• 9 �j
• o SEAL �9� ••
039211
i 4j 0)%2 017
PROJECT NO.:
H13002.001
Q
z
w
°C
o
(D
�
V)�
�
�
m
LU
z0�
U
�
w
I-
LU
w
Q
�
_
U
=
w
m
r WITH 24" RCP co
}
0
DI246 REMOVE EXISTING 15" <
CMP PIPE AND Uj
REPLACE WITH 24" U,
RCP g
CITY OF ASHEVILLE
D.B. 4720, PG. 1011
P.B. 124, PG. 48
PIN 964866179800000
FOR -1-1 REV- PLAN AND PROFILE VIEW, SEE SHEETS 14,14A, 15 & 15A
FOR -1-3- PROFILE VIEW, SEE SHEET 6A
o •-i o E
ooin
o d -,o r� o
NCO U
o�
U ,Uoa},
o��nzrn E
2: o; �
�
� �rn�
r= LL
.S-1
� ~
E
Q
LLQ
V)
1)
GREENWAY ENGINEER:
l.'01%4611040
.�qg�t� '�►4Q�
�DocuSign,,��:�
04(
.�F7F1�3�4LFFJ.�O• 9 �j
• o SEAL �9� ••
039211
i 4j 0)%2 017
PROJECT NO.:
H13002.001
O
sFF,cti
OFA
x ' ," %clic
O
O/ti Q �' •
Ftp 61p F�f'
DA 14 O/ p�f' y y!y
-140
61c
°'� F� y Qin
6 �s
F"0 CAI
�
Cqc40F / j 1/ �6 �.
�'' h \ CITY 6
OF �O
od
FlF
oo D.B. 4720, PG1 II LF
P.B. 124, PG. 4 ZO�/`r%�196�'Cp /� QFd' ti 40 tiPIN 96486617980 00� O/�
P c
pw
f�5S/9� 0 w
�. �P/�o 4'A � w
0
SILT FENCE OUTLET �TYPICAL � W
DC
.�
oz�z w
szl�PF
\ w
\ Tf - F �/ \ U LL J
Ov°TP/SFO to �� — °F�` �F v `�� O�Lu / W
40/
O -
CiLo
� TP/SF
zz
TP. SF
�V�7 Y
toui
+++ T.B.M. � � � � LD �LD
REBAR W/CAP
ELEVATION: 2347 ?1' 771— TA SF
o 0 L,
C H EC K DAM �\ ` � . c - � // �, �ti;,L 2:TYPICAL �,� `° r—
a (u� —�
�0 E
CLEAN WATER >
LL
DITCH DIVERSION -<---
DA D D Ll REV 03 CO/ co
0 40
uiCLEAN WATER DIVERSION DITCH FF CiS,� �°/' �'� -,0440 °q�F Q
STABILIZE AND PROTECT PRIOR TO CONSTRUCTION F � u' F,PT/, w
El /.o O� CLEAN WATER �
CITY OF ASHEVILLE F F
PG. 1011 /%,y -9,V �c DITCH DIVERSION GREENWAY ENGINEER:
D.B. 4720, CLEAN WATER '�'F O "�"/S DA -D124
P.B. 124, PG. 48 DITCH DIVERSION C, �O 2�'' 'f'F,o��/� ..Ro��•,,
PIN 964866179800000 DA Ll REV 04 �F.o A,o �F �C,,o '�51 �' ;•► �o�; .��'•,
�cA �9c /A4 F�/S C`�c cp
REPLACE EXISTING CULVERT � 042574 h
HYDRAULICS ENGINEER:
DocuS
IMPERVIOUS DIKE �����;',,,
.CCCCCC//44,
.
• SEAL 9•'
039211
�1 a 1WkI2 017
PROJECT NO.:
H13002.00
30 15 0 30 60 SEE DETAIL 1 ON SHEET G-313 FOR SILT/COMBINATION FENCE
INSTALLATION AT CULVERT OUTLETS. G- 14
SCALE: 1"=30'