HomeMy WebLinkAbout20140957 Ver 2_NC detail sheets rev 1_20170920GENERAL NOTES AND COMMENTS:SYM.DATE BY REVISION INFORMATION PROJECT/TASK APP.
--ISSUED FOR PERMITTINGJR03/09/170
APP. FOR CONST.:
SCALE:
APP. FOR BID:
CHECKED:
DRAWN:
DIR/FILE:
DISTRICT:
TITLE:
COUNTY:DWG. NO.GROUP REV.STATE:
925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000
Atlantic Coast Pipeline, LLC
AS NOTED
08/02/2017SL
08/01/2017EB
11 OF 4ACP\North Carolina\Details
EROSION AND SEDIMENT CONTROL DETAILS
ATLANTIC COAST PIPELINE
NC
--ISSUED IN RESPONSE to NCDEQ COMMENTSEB08/01/171
36" SILT-SAVER
PRIORITY 2 FABRIC26"
22"
24"
6' MAX O.C.Black Band
TRENCH
FRONT ELEVATION
4' LONG WOOD POST (OAK)
SPACED AT 6'-0"
26"
22"
24"
8"
4"
10' TO TOE
OF SLOPE
FABRIC TO BE 24" ABOVE GROUND
WITH "J" IN TRENCH
FLOW
4" x 8"
Trench
SIDE VIEW
TOE IN AND COMPACT BACKFILL
4 STAPLES
(1" x 13
4")
BONDING STRIP
(1" x 3
8" x 24")
POST (OAK)
(1 1
8" x 1 1
8" x 48")
(OR EQUAL DENSITY)
GROUND LINE
BOTTOM OF
TRENCH LINE
REPAIR DETAIL
ATTACHING TWO SILT
FENCES
WHEN TRENCHING IS
USED
PLAN VIEW
GENERAL NOTES AND COMMENTS:SYM.DATE BY REVISION INFORMATION PROJECT/TASK APP.
--ISSUED FOR PERMITTINGJR03/09./20170
“”“”
NOTE: WHERE SUPER SILT FENCE IS SHOWN ON THE ALIGNMENT SHEETS AN
ACCEPTABLE SUBSTITUTE SHALL BE A PYRAMID STACK OF THREE 18 INCH
DIAMETER COMPOST FILTER SOCKS, SUBJECT TO THE APPROVAL OF THE EI.
APP. FOR CONST.:
SCALE:
APP. FOR BID:
CHECKED:
DRAWN:
DIR/FILE:
DISTRICT:
TITLE:
COUNTY:DWG. NO.GROUP REV.STATE:
925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000
Atlantic Coast Pipeline, LLC
AS SHOWN
08/02/2017SL
08/01/2017EB
12 OF 4ACP\North Carolina\Details
EROSION AND SEDIMENT CONTROL DETAILS
ATLANTIC COAST PIPELINE
NC
--ISSUED IN RESPONSE to NCDEQ COMMENTSEB08/01/171
GENERAL NOTES AND COMMENTS:SYM.DATE BY REVISION INFORMATION PROJECT/TASK APP.
--ISSUED FOR PERMITTINGJR03/09/20170
APP. FOR CONST.:
SCALE:
APP. FOR BID:
CHECKED:
DRAWN:
DIR/FILE:
DISTRICT:
TITLE:
COUNTY:DWG. NO.GROUP REV.STATE:
925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000
Atlantic Coast Pipeline, LLC
AS SHOWN
08/02/2017SL
08/01/2017EB
13 OF 4ACP\North Carolina\Details
EROSION AND SEDIMENT CONTROL DETAILS
ATLANTIC COAST PIPELINE
NC
--ISSUED IN RESPONSE to NCDEQ COMMENTSEB08/01/171
GENERAL NOTES AND COMMENTS:SYM.DATE BY REVISION INFORMATION PROJECT/TASK APP.
--ISSUED FOR PERMITTINGJR03/09/170
EROSION AND SEDIMENT CONTROL PLAN NARRATIVE
THE EROSION AND SEDIMENT (E&S) CONTROL MEASURES FOR THE PIPELINE CONSTRUCTION ACTIVITIES PRIMARILY CONSIST OF BUT ARE
NOT LIMITED TO COMPOST FILTER SOCK, BELTED SILT RETENTION FENCE, SUPER SILT FENCE, SLOPE BREAKERS, AND TEMPORARY AND
PERMANENT SEEDING AND MULCHING. BEST MANAGEMENT PRACTICES (BMP) SPECIFICATIONS FOR THE E&S CONTROL PLAN (E&SCP) ARE TO
BE UTILIZED BY THE CONSTRUCTION CONTRACTOR ACCORDING TO THE PROVIDED PLAN.
GENERAL CONSTRUCTION NOTES:
1.DISCHARGING SEDIMENT LADEN WATER WHICH WILL CAUSE OR CONTRIBUTE TO THE DEGRADATION OF A BENEFICIAL USE OF A WATER
OF THE STATE FROM THE CONSTRUCTION SITE, A DEWATERING SITE, OR SEDIMENT BASINTRAP INTO ANY SURFACE WATER WITHOUT
FILTRATION OR EQUIVALENT TREATMENT IS PROHIBITED.
2.THE DISCHARGER SHALL AMEND THE EROSION & SEDIMENT CONTROL PLAN WHENEVER THERE IS A CHANGE IN THE CONSTRUCTION OR
OPERATIONS, WHICH MAY EFFECT THE DISCHARGE OF POLLUTANTS TO SURFACE WATERS OR GROUNDWATER.
3.DISCHARGES ORIGINATING FROM OFF-SITE SOURCES, WHICH FLOW THROUGH OR ACROSS THE AREAS DISTURBED BY CONSTRUCTION,
MAY BE DIVERTED AROUND THE ACTIVE CONSTRUCTION AREA WHENEVER POSSIBLE.
4.PERFORM PERMANENT OR TEMPORARY SOIL STABILIZATION WITHIN 7 DAYS WHEN SITE IS AT FINAL GRADE AND ON SITES THAT ARE
NOT AT FINAL GRADE, BUT WILL REMAIN DORMANT FOR MORE THAN 14 DAYS.
5.DUE TO VARYING SITE CONDITIONS, ADDITIONAL SEDIMENT CONTROL BMPS MAY BE NECESSARY BEYOND THE MEASURES SHOWN ON
THE E&S CONTROL PLAN.
6.STAGING AREAS, ASSEMBLY AREAS, TEMPORARY EQUIPMENT AND NON-HAZARDOUS MATERIAL STORAGE AREAS SHALL BE LOCATED
OUTSIDE 100-YR FLOOD ZONES. HAZARDOUS MATERIAL STORAGE AREAS SHALL BE LOCATED AT LEAST 100 FEET BACK FROM SURFACE
WATER BODIES.
7.EQUIPMENT STORAGE IN CONSTRUCTION STAGING AREAS SHALL BE LOCATED A MINIMUM OF 100 FEET AWAY FROM WETLAND EDGE.
8.AT MINIMUM, ALL BMPS ARE TO BE INSPECTED ONCE EVERY SEVEN CALENDAR DAYS AND WITHIN 24 HOURS AFTER ANY STORM EVENT
GREATER THAN 0.5-INCH PER 24-HOUR PERIOD DURING THE ENTIRE PROJECT. A WRITTEN REPORT MUST ALSO BE COMPLETED,
DOCUMENTING EACH INSPECTION AND, IF NECESSARY, ANY REPAIR, REPLACEMENT OR MAINTENANCE ACTIVITY.
9.THE CONTRACTOR SHALL TAKE PRECAUTIONARY MEASURES TO PROTECT ANY EXISTING FACILITY SHOWN ON THE DRAWINGS, AND ANY
OTHER WHICH IS NOT ON RECORD OR NOT SHOWN ON THE DRAWINGS. THE CONTRACTOR SHALL POTHOLE EXISTING UTILITIES AT THE
POINTS OF CONNECTION AND ALL UTILITY CROSSINGS TO DETERMINE EXACT LOCATIONS PRIOR TO THE START OF WORK. ANY
DISCREPANCIES BETWEEN THESE DRAWINGS AND EXISTING CONDITIONS SHALL BE REPORTED TO THE ENGINEER OF RECORD
IMMEDIATELY.
10.ALL WORK WITHIN A PUBLIC RIGHT-OF-WAY SHALL BE COORDINATED WITH THE AGENCY HAVING JURISDICTION.
11.ALL REQUIRED PERMITS MUST BE OBTAINED PRIOR TO STARTING WORK.
12.DURING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR CONSTRUCTION, STABILIZATION AND MAINTENANCE OF ALL
EXISTING AND PROPOSED SITE EROSION & SEDIMENTATION CONTROL DEVICES AND FACILITIES.
13.THE CONTRACTOR AGREES THAT IN ACCORDANCE WITH GENERALLY ACCEPTED CONSTRUCTION PRACTICES, THE CONTRACTOR WILL
BE REQUIRED TO ASSUME SOLE AND COMPLETE RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF CONSTRUCTION
OF THE PROJECT, INCLUDING EROSION & SEDIMENTATION DEVICES AND SAFETY OF ALL PERSONS AND PROPERTY; THAT THIS
REQUIREMENT SHALL BE MADE TO APPLY CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING HOURS, AND CONSTRUCTION
CONTRACTOR FURTHER AGREES TO DEFEND, INDEMNIFY AND HOLD THE ENGINEER OF RECORD HARMLESS OF ANY AND ALL LIABILITY,
REAL OR ALLEGED, IN CONNECTION WITH THE PERFORMANCE OF WORK ON THIS PROJECT, EXCEPTING LIABILITY ARISING FROM THE
SOLE NEGLIGENCE OF ENGINEER OF RECORD.
14.AS SITE SPECIFIC CONDITIONS MAY WARRANT, THE E&SC PLAN MAY REQUIRE MINOR MODIFICATIONS TO ENSURE PROPER PROTECTION
OF RECEIVING WATERS. THE RESPECTIVE PROJECT ENVIRONMENTAL INSPECTOR (EI) WILL IDENTIFY SITE SPECIFIC AREAS WHERE A
CERTAIN BMP MODIFICATION(S) IS NECESSARY TO EITHER OMIT OR ENHANCE BMPS IN SUCH AREAS. THIS PROCESS ENTAILS THE EI TO
IDENTIFY LOCATIONS WHERE BMPS WILL NEED TO BE ALTERED, SUBSTITUTED OR OMITTED AND CONTACT THE DOMINION GAS
COMPLIANCE SPECIALIST TO REVIEW PROPOSED CHANGES. UPON REVIEW AND APPROVAL BY THE DOMINION COMPLIANCE SPECIALIST,
THE EI WILL REDLINE, DATE, AND SIGN THE E&SCP DRAWING(S) DEPICTING THE REDLINE CHANGE(S). ONCE THIS PROCESS IS
COMPLETED, THE EI WILL NOTIFY NCDEQ OF SUCH MINOR MODIFICATION REDLINE AMENDMENTS AS REQUIRED BY THE GENERAL
PERMIT.
SEQUENCE OF CONSTRUCTION
1. A PRE-CONSTRUCTION MEETING SHOULD TAKE PLACE PRIOR TO START OF CONSTRUCTION ACTIVITIES.
2. BEGIN CLEARING AND GRUBBING SITE. CLEAR AND GRUB ONLY THOSE AREAS NECESSARY FOR INSTALLATION OF THE EROSION CONTROL MEASURES.
3. INSTALL SILT FENCE AS SHOWN ON THE PLANS.
4. ONCE EROSION CONTROL MEASURES HAVE BEEN INSTALLED AND PRIOR TO SEDIMENT REMOVAL ACTIVITIES, THE SITE IS TO BE INSPECTED BY NCDENR - LAND QUALITY.
5. GRADE SITE ACCORDING TO CONTRACT DOCUMENTS. MAINTAIN EROSION CONTROL DEVICES AS NEEDED.
6. INSTALL STORM DRAINAGE AS INDICATED ON PLANS.
7. GRASS OR OTHERWISE STABILIZE ALL AREAS AS THEY ARE BROUGHT TO FINAL GRADES.
8. THE CONTRACTOR SHALL DILIGENTLY AND CONTINUOUSLY MAINTAIN ALL EROSION CONTROL DEVICES AND STRUCTURES TO MINIMIZE EROSION. INSPECT AND REPAIR MEASURES
AFTER EACH RAINFALL AND AS NEEDED THROUGHOUT THE PROJECT.
9. CONTRACTOR TO LEAVE ALL EROSION CONTROL DEVICES IN PLACE AT THE CONCLUSION OF THIS CONTRACT. CONTRACTOR IS TO CLEAN-OUT, REPAIR AND GRASS STABILIZE ALL
DENUDED AREAS. ALL AREAS WILL BE RETURNED TO THE STATE OF EXISTING CONDITIONS PRIOR TO CONTRACT AS A MINIMUM.
10. IT IS THE CONTRACTOR'S RESPONSIBILITY TO CONTAIN SEDIMENT ONSITE. ADDITIONAL EROSION CONTROL MEASURES MAY BE REQUIRED BY THE ENGINEER.
11. ALL EROSION CONTROL MEASURES TO BE IN ACCORDANCE WITH THE NORTH CAROLINA EROSION AND SEDIMENT CONTROL PLANNING AND DESIGN REQUIREMENTS AND LAND
DEVELOPMENT STANDARDS.
MAINTENANCE SCHEDULE
AFTER FULL REVEGETATION HAS BEEN ACHIEVED, ALL BMPS WILL BE REMOVED AND ANY LAND DISTURBED BY REMOVAL WILL BE PERMANENTLY STABILIZED. UNLESS OTHERWISE
SPECIFIED, ALL MAINTENANCE MUST BE COMPLETED IMMEDIATELY AFTER AN INSPECTION IDENTIFIES THAT A BMP IS NOT FUNCTIONING AS REQUIRED.
·THE ROW AND ESC DEVICES WILL BE INSPECTED DAILY AT THE ACTIVE CONSTRUCTION SITE AND AT LEAST ONCE EVERY SEVEN CALENDAR DAYS FOR ACTIVELY DISTURBED AREAS,
14 CALENDAR DAYS FOR RESTORED AREAS, AND WITHIN 24 HOURS AFTER ANY STORM EVENT GREATER THAN ONE-HALF-INCH PER 24-HOUR PERIOD.
·SEDIMENT MUST BE REMOVED WHERE ACCUMULATION REACHES ONE-HALF THE ABOVE GROUND HEIGHT OF THE CONTROL MEASURE.
·EROSION CONTROL MEASURES, WHICH HAVE BEEN UNDERMINED OR TOPPED, SHALL BE REPAIRED IMMEDIATELY.
·OTHER REQUIRED REPAIRS OR MAINTENANCE SHALL BE MADE IMMEDIATELY.
·TEMPORARY AND PERMANENT E&S CONTROL BMPS SHALL BE MAINTAINED AND REPAIRED AS NEEDED TO ASSURE CONTINUED PERFORMANCE OF THEIR INTENDED FUNCTION.
MATERIAL WASTE HANDLING AND RECYCLING
1.SOLID WASTE DISPOSAL SHALL BE HANDLED THROUGH ONE OF THE LOCAL LICENSED WASTE MANAGEMENT PROVIDERS AND PERMITTED DISPOSAL FACILITIES. THE CONTRACTOR
WILL PROVIDE MOBILE AND COVERED WASTE RECEPTACLES AS NEEDED ALONG THE PROJECT LIMITS. CONTRACTOR SHALL ALSO PROVIDE A COVERED DUMPSTER FOR
CONSOLIDATION OF WASTE FOR PICK UP AND DISPOSAL FOR THE DURATION OF THE PROJECT. ALL SOLID WASTE SHALL BE DISPOSED OF AT A LICENSED PERMITTED MUNICIPAL
LANDFILL.
2.THE CONTRACTOR WILL BE RESPONSIBLE FOR ANY PERMITS AN DOR DISPOSAL FEES. THE CONTRACTOR SHALL BE SOLELY RESPONSIBLE TO ASSURE THAT ALL MATERIALS AREA
HANDLED AND DISPOSED OF IN ACCORDANCE WITH APPLICABLE LAWS, RULES, AND REGULATIONS, INCLUDING BUT NOT LIMITED TO THOSE ISSUED BY THE ENVIRONMENTAL
PROTECTION AGENCY, NCDEQ, AND OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION.
3.CONTRACTOR SHALL PRACTICE GOOD HOUSEKEEPING FOR THE DURATION OF THE PROJECT INCLUDING THE ROUTINE REMOVAL AND DISPOSAL OF SOLID WASTE.
4.CONTRACTOR SHALL KEEP RECORDS OF PROPER SOLID WASTE DISPOSAL AND PROVIDE COPIES TO THE EI.
POLLUTANT CONTROLS
·SPILLS OCCURRING DURING CONSTRUCTION, OPERATION, AND MAINTENANCE ARE TO BE
REPORTED IMMEDIATELY TO THE MONITORING CENTER IN ACCORDANCE WITH DOMINION
POLICIES, PLANS, AND PROCEDURES. DOMINION'S ENVIRONMENTAL HEALTH AND SAFETY
DEPARTMENT WILL BE RESPONSIBLE FOR CONTACTING THE APPROPRIATE AGENCIES, EXCEPT AS
PROVIDED FOR BELOW.
·ANY FACILITY OWNER/OPERATOR WHO IS SUBJECT TO THE SPCC RULE MUST COMPLY WITH THE
REPORTING REQUIREMENTS FOUND IN 40 CFR 112.4. A DISCHARGE MUST BE REPORTED TO THE
EPA REGIONAL ADMINISTRATOR (RA) WHEN THERE IS A DISCHARGE OF:
··MORE THAN 1,000 GALLONS OF OIL IN A SINGLE DISCHARGE TO NAVIGABLE WATERS OR
ADJOINING SHORELINES,
··MORE THAN 42 GALLONS OF OIL IN EACH OF TWO DISCHARGES TO NAVIGABLE WATERS OR
ADJOINING SHORELINES OCCURRING WITHIN ANY TWELVE-MONTH PERIOD.
·IF A DOMINION REPRESENTATIVE CANNOT BE PROMPTLY CONTACTED AND THE SPILL HAS IMPACTED
WATER, THE PERSON DISCOVERING THE SPILL OR RELEASE WILL CONTACT THE NATIONAL
RESPONSE CENTER AT 1-800-424-8802 AND REPORT THE RELEASE. THAT PERSON WILL CONTINUE
CALLING DOMINION UNTIL A REPRESENTATIVE IS REACHED.
STABILIZATION TIMEFRAMES
PERIMETER DIKES, SWALES, DITCHES, SLOPES 7 DAYS
HIGH QUALITY WATER (HQW) ZONES 7 DAYS
SLOPES STEEPER THAN 3:1 7 DAYS
SLOPES 3:1 OR FLATTER 14 DAYS
ALL OTHER AREAS (Slopes flatter than 4:1) 14 DAYS
APP. FOR CONST.:
SCALE:
APP. FOR BID:
CHECKED:
DRAWN:
DIR/FILE:
DISTRICT:
TITLE:
COUNTY:DWG. NO.GROUP REV.STATE:
925 White Oaks Blvd. Bridgeport, West Virginia 26330 / 681-842-8000
Atlantic Coast Pipeline, LLC
AS SHOWN
08/02/2017SL
08/01/2017EB
14 OF 4ACP\North Carolina\Details
EROSION AND SEDIMENT CONTROL DETAILS
ATLANTIC COAST PIPELINE
NC
BMP INSTALLATION AND REMOVAL SEQUENCE
CONSTRUCTION MUST BE IN ACCORDANCE WITH THE FOLLOWING SEQUENCE. THIS SEQUENCE IS DESIGNED
TO MINIMIZE SOIL EROSION AND SEDIMENTATION. THE CONTRACTOR MAY DEVIATE SLIGHTLY FROM THE
STAGING OF PERMANENT SITE IMPROVEMENTS, BUT NO DEVIATION FROM THE RELATIVE ORDER OF EROSION
AND SEDIMENTATION CONTROL MEASURES WILL BE ALLOWED.
THE STAGING OF EARTHMOVING ACTIVITIES FOR THIS PROJECT IS A GENERAL DESCRIPTION OF THE WORK
REQUIRED. ALL WORK SHALL BE COMPLETED IN ACCORDANCE WITH COMPANY STANDARDS, THE NORTH
CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY REGULATIONS AND ALL OTHER APPLICABLE FEDERAL,
STATE OR LOCAL REQUIREMENTS.
THE APPROVED EROSION AND SEDIMENTATION CONTROL PLAN INCLUDING THE SOIL EROSION CONTROL
DRAWINGS AND NARRATIVE SHALL BE AVAILABLE ON SITE AT ALL TIMES DURING EARTH DISTURBANCE.
1.STAKE AND/OR FLAG ALL LIMITS OF DISTURBANCE FOR CONSTRUCTION ACTIVITIES, CLEARLY
IDENTIFYING WETLAND AND STREAM EDGES. INSTALL SIGNS TO DESIGNATE THE AREA TO IDENTIFY
IMPORTANT PROJECT ATTRIBUTES SUCH AS WETLANDSTREAM BOUNDS, EXCLUSION AREAS ETC.
2.INSTALL ROCK CONSTRUCTION ENTRANCES IMMEDIATELY BEFORE INITIAL DISTURBANCES. THE ROCK
CONSTRUCTION ENTRANCES TO BE UNDERLAIN BY FILTER FABRIC. ALL CONSTRUCTION TRAFFIC
SHOULD USE ONLY ROCK CONSTRUCTION ENTRANCE FOR INGRESS AND EGRESS. ALL MUD OR
SEDIMENT TRACKED ONTO THE EXISTING ROADWAY SHALL BE REMOVED BY THE CONTRACTOR AS
NECESSARY.
3.INSTALL SILT FENCE AND COMPOST FILTER SOCKS AS NECESSARY ALONG THE ACCESS ROADS TO
PREVENT SEDIMENT LADEN RUNOFF FROM ENTERING DOWNSTREAM WATER BODIES. MAINTAIN THE
ACCESS ROADS AS REQUIRED, ASSOCIATED DITCHES, AND NECESSARY OUTLET PROTECTION.
4.PRIOR TO AND SIMULTANEOUS WITH GRADING AND EXCAVATION, INSTALL REMAINING EROSION
CONTROL DEVICES (ECD) SHOWN ON THE PLANS.
5.COMMENCE GRADING AND ASSOCIATED CUT AND FILL SLOPES. THE EARTH MOVING ACTIVITY SHALL BEGIN
IN AREA OF CUT SO THAT THE CUTS CAN BE PLACED IN AREAS OF FILL. REMOVE TOPSOIL FROM AREAS TO
RECEIVE FILL PRIOR TO FILLING.
6.FINALIZE UTILITY INSTALLATION AND ROADWAY GRADES AND PLACE TOPSOIL ON THE CUT AND FILL
AREAS. STABILIZE CUT AND FILL SLOPES, AFTER PLACEMENT OF STOCKPILED TOPSOIL ON EXCAVATED
SLOPES, AND AS DIRECTED.
7.RE-DISTRIBUTION OF WET SEDIMENT FROM DEVICES AND FACILITIES SHALL ONLY BE PERMITTED UPHILL
OF AN EFFECTIVE SEDIMENT CONTROL DEVICE OR FACILITY. SEDIMENT LADEN RUNOFF SHALL NOT BE
ALLOWED TO FLOW DIRECTLY INTO WATER BODIES.
8.ANY EXPOSED TOPSOIL PILES SHOULD BE STABILIZED & SEEDED PER THE PERMIT REGULATIONS, AND
BY TABLES SHOWN ON THE APPROVED EROSION CONTROL PLANS AND MULCHED WITH STRAW AS
SPECIFIED BY THE PROJECT OWNER.
9.UPON MINIMUM 70% UNIFORM PERENNIAL VEGETATIVE GROWTH, REMOVE TEMPORARY SEDIMENT
CONTROLS. REMOVE ACCUMULATED SEDIMENTS WITHIN THE TRAPS, RE-GRADE TRAPS TO FINAL
CONTOURS. STABILIZE SITE PER THE PLANS.
SEEDING AND MULCHING
SEE SEED MIXES, SOIL AMENDMENTS, AND MULCH SPECIFICATIONS SPECIFIED IN THE ACP
RESTORATION AND REHABILITATION PLAN.
1.SEEDBED PREPARATION: AREAS TO BE SEEDED SHALL BE DISKED TO A DEPTH OF 4-IN TO
6-IN WHENEVER FEASIBLE, AND SMOOTHLY GRADED.
2.IN TOPSOILED AREAS, SOIL TO BE REDISTRIBUTED EVENLY AND STABILIZED PRIOR TO
SEEDING.
3.STABILIZATION MEASURES SHALL BE INITIATED AS SOON AS PRACTICABLE IN PORTIONS OF
THE SITE WHERE CONSTRUCTION ACTIVITIES HAVE TEMPORARILY OR PERMANENTLY
CEASED, BUT IN NO CASE MORE THAN 21 DAYS AFTER THE CONSTRUCTION ACTIVITY IN
THAT PORTION OF THE SITE HAS PERMANENTLY CEASED.
4.WHERE THE INITIATION OF STABILIZATION MEASURES WITHIN 7 DAYS AFTER
CONSTRUCTION ACTIVITY TEMPORARILY OR PERMANENTLY CEASES IS PRECLUDED BY
SNOW COVER, STABILIZATION MEASURES SHALL BE INITIATED AS SOON AS CONDITIONS
ALLOW.
5.WHERE CONSTRUCTION ACTIVITY WILL RESUME ON A PORTION OF THE SITE WITHIN 21
DAYS FROM WHEN ACTIVITIES CEASED (E.G., THE TOTAL TIME PERIOD THAT CONSTRUCTION
ACTIVITY IS TEMPORARILY HALTED IS LESS THAN 21 DAYS), THEN STABILIZATION MEASURES
DO NOT HAVE TO BE INITIATED ON THAT PORTION OF THE SITE BY THE SEVENTH DAY AFTER
CONSTRUCTION ACTIVITIES HAVE TEMPORARILY CEASED.
6.AREAS WHERE THE SEED HAS FAILED TO GERMINATE ADEQUATELY (UNIFORM PERENNIAL
VEGETATIVE COVER WITH A DENSITY OF 70%) WITHIN 30 DAYS, SEEDING AND MULCHING
MUST BE RE-SEEDED IMMEDIATELY, OR AS SOON AS WEATHER PERMITS.
EROSION AND SEDIMENT CONTROL DETAIL NOTES
1.THE DETAILS ON EROSION AND SEDIMENT CONTROL DETAIL SHEETS 1 THROUGH 3 CORRESPOND TO E&S CONTROL MEASURES
SPECIFICALLY IDENTIFIED ON THE E&SC PLAN. DETAILS ON SHEET 4 CORRESPONDS TO E&S CONTROL MEASURES THAT WHILE NOT
SPECIFICALLY IDENTIFIED ON THE E&SC PLANS, COULD POTENTIALLY BE REQUIRED.
--ISSUED IN RESPONSE to NCDEQ COMMENTSEB08/01/171