HomeMy WebLinkAbout20171114 Ver 1_Public Notice_20170911Burdette, Jennifer a
From: Spencer, Thekla M CIV USARMY CESAW (US) <Thekla.M.Spencer@usace.army.mil>
Sent: Tuesday, September 12, 2017 7:04 AM
Subject: US Army Corps of Engineers Public Notice
As you requested, you are hereby notified that Wilmington District, United States Army Corps of Engineers has
issued a Public Notice. The text of this document can be found on the Public Notices portion of the Regulatory
Division Home Page. Each Public Notice is available in ADOBE ACROBAT (.pdf) format for viewing, printing or
download at http://www.saw.usace.army.miI/Missions/ReguIatoryPermitProgram.aspx.
The current notice involves: The Wilmington District, Corps of Engineers (Corps) received an application from
the National Oceanic and Atmospheric Administration (NOAA) National Centers for Coastal Ocean Science
(NCCOS), Beaufort Lab seeking Department of the Army authorization to discharge 750 cubic yards of fill
material into two small open water areas with the marsh complex totaling 0.17 acre combined, associated with
a research project testing the effectiveness of applying dredged material to marsh ponds for marsh
enhancement in Onslow County, North Carolina.
Corps Action ID#: SAW -2017-01879
Issue Date: September 11, 2017
Applicant: NOAA/NCCOS
Ms. Carolyn Currin
101 Pivers Island Road
Beaufort, North Carolina 28516
Expiration Date: October 11, 2017
Point of Contact: Mr. Brad Shaver, Project Manager
Subscribe/Unsubscribe: This email was sent out as a result of subscribing to the Wilmington District
regulatory program public notices. Please email <mailto:Cindy.M.Corbett@usace.army.mil> with the subject or
message "unsubscribe" to remove your address from future mailings.
in
US Army Corps PUBLIC NOTICE
Of Engineers
Wilmington District
Issue Date: 9/11/2017
Comment Deadline: 10/11/2017
Corps Action ID Number: SAW -2017-01879
The Wilmington District, Corps of Engineers (Corps) received an application from the
National Oceanic and Atmospheric Administration (NOAA) National Centers for Coastal
Ocean Science (NCCOS), Beaufort Lab seeking Department of the Army authorization to
discharge 750 cubic yards fill material into two small open water areas within the marsh
complex totaling 0.17 acre combined, associated with a research project testing the
effectiveness of applying dredged material to marsh ponds for marsh enhancement in
Onslow County, North Carolina.
Specific plans and location information are described below and shown on the attached
plans. This Public Notice and all attached plans are also available on the Wilmington
District Web Site at
http://www.saw.usace.army.mil/Missions/Re ug latoryPermitPro rg am.aspx
Applicant: NOAA, NCCOS
Attn: Ms. Carolyn Currin
101 Pivers Island Road
Beaufort, NC 28516
AGENT (if applicable): US Army Corps of Engineers — Environmental
Attn: Ms. Emily Hughes
69 Darlington Ave
Wilmington, NC 28403
Authority
The Corps evaluates this application and decides whether to issue, conditionally issue, or
deny the proposed work pursuant to applicable procedures of the following Statutory
Authorities:
® Section 404 of the Clean Water Act (33 U.S.C. 1344)
® Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403)
❑ Section 103 of the Marine Protection, Research and Sanctuaries Act of 1972
(33 U.S.C. 1413)
Version 6.15.2017 Page 1
Location
Location Description:
Project Area (acres): +/-0.30 Nearest Town: Camp Lejeune
Nearest Waterway: Intracoastal Waterway River Basin: Onslow Bay
Latitude and Longitude: 34.546322N, -77.325469W
Existing Site Conditions
Inlet
Figure 1. Location Map, Mile Hammack Bay (proposed project area in red; DOD -funded study area in green)
Marsh ponds. The proposed project is located within the boundary of Marine Corps Base
Camp Lejeune in the Mile Hammock Bay salt marsh adjacent to the Atlantic Intracoastal
Waterway (AIWW). Existing conditions on the site are undisturbed coastal wetlands
dominated by Spartina alternifora, with S. patens, Salicornia spp., and Juncus spp.
occurring at higher elevations. The proposed project will occur at intertidal elevations,
within S. alterniflora habitat.
The two areas targeted for restoration are identified as Pond A and Pond B (see Figure 2).
Pond A has an area of 0.09 acre and is 30 feet from the shoreline, and Pond B is
approximately 0.08 acre and is 50 feet from the shoreline. Both ponds are approximately
300-350 feet from the center of the navigation channel, 200-250 feet from the edge of the
setback, and within the USACE AIWW Right -of -Way (see Figure 3). The borrow areas
for the project will be located directly waterward of the marsh ponds towards the
navigation channel.
Version 6.15.2017 Page 2
The ponds are located within an area of environmental concern (AEC) as defined by
Section 113A-113 of the North Carolina Coastal Area Management Act (LAMA).
Specifically, the proposed project will be occurring in the estuarine waters and public
trust waters AECs.
The Division of Marine Fisheries (DMF) has classified the project area as Primary
Nursery Area (PNA) (15A NCAC 07H .0208(a)(4)) and secondary nursery areas defined
by rule 15 NCAC 3N .0102(c). This area is also Essential Fish Habitat (EFH) for Coastal
Migratory Pelagics (king mackerel, Spanish mackerel, cobia) and is considered a Habitat
Area of Particular Concern (HAPC).
Submerged Aquatic Vegetation. Areas of SAVs are known to exist within 500 feet of the
project area northwest of Pond B (Figure 2). Submerged aquatic vegetation functions as
habitat for many fish and aquatic animals.
Subtidal soft bottom habitat. Although soft bottom habitat is defined as "unvegetated"
and lacks visible structural habitat, the surface sediments support an abundance of
microscopic plants called benthic microalgae and numerous burrowing animals are
hidden below the surface. Subtidal soft bottom habitat exists within the project area.
Oyster reef habitat. There is no oyster reef habitat present in either pond, as neither pond
is connected via a tidal creek to estuarine water.
The project is located within a section of the AIWW that is part of the White Oak River
Basin (Onslow Bay). The NC Division of Water Resources classifies the AIWW at the
project site as SA; HQW. The classification definitions are:
SA: Tidal salt waters that are used for commercial shellfishing or marketing purposes and
are also protected for all Class SC and Class SB uses. All SA waters are also HQW by
supplemental classification.
HQW: Supplemental classification intended to protect waters which are rated excellent
based on biological and physical/chemical characteristics through Division monitoring or
special studies, primary nursery areas designated by the Marine Fisheries Commission,
and other functional nursery areas designated by the Marine Fisheries Commission.
Borrow Areas. The material used to fill Ponds A and B will be dredged from the AIWW
directly adjacent to each of the ponds (Figure 2). Water depth in the area to be dredged is
expected to be between 6 — 12 feet, and material within the upper 12-18 inches is
expected to be predominantly sand. Both dredge boxes are located in open water habitat
approximately 100 feet from the shoreline and approximately 150 - 200 feet from the
ponds. There are no SAVs, oyster reefs, or soft bottom habitat within the borrow areas.
Version 6.15.2017 Page 3
I A'Vi:' L<. !-:t�j a r F rc I
0 750 Imagery Date: February 201
Figure 2. Project Map, Por7d A and Poria B targeted for restoration
Applicant's Stated Purpose
The applicant's stated purpose and need for this project is to demonstrate and test
effectiveness of applying dredged material to marsh ponds for research purposes and
study their response. The research hypothesis anticipates that this one-time application of
material will reduce fragmentation of the marsh surface, ameliorate shoreline erosion,
and provide opportunity for understanding the effects of material placement on the local
marsh platform.
Project Description
NOAA proposes to fill two ponds (Pond A and Pond B) with dredged sediment, bringing
the surface elevation up to that of the surrounding marsh, which is approximately 0 — 8"
NAVD88. After the elevation is restored, Spartina alterniflora will be planted over the
filled areas. The ponds are, on average, approximately 18-24" deep. Filling of Pond A
and B will require approximately 750 cubic yards of dredged material and will cover
Version 6.15.2017 Page 4
approximately 0. 17 acre (approximate volumes of Pond A and Pond B are 350 and 400
cubic yards, respectively).
To minimize damage to the marsh surface, NOAA will install 12" -wide grated, fiberglass
boardwalks over the marsh to temporarily accommodate the dredge pipe and to facilitate
monitoring. In addition, temporary boardwalks consisting of planks attached to plastic
crates, may be used during sediment application and monitoring activities to minimize
the impact of walking directly on the salt marsh.
Ponds A and B will receive material from borrow areas located directly waterward of the
marsh ponds, primarily within the USACE setback (Figure 3). The setback is a buffer
area outside the designated navigation channel that is not maintained by the USACE
(undisturbed), with a water depth that is approximately 6-12' deep. Dredge boxes will not
exceed 200' x 100' x 12-18" deep in both locations to minimize impacts to benthic
habitat. The dredge will be anchored within the borrow area with bow and stern spuds
while working sunrise to sunset, and at night it will dock at Mile Hammock Bay.
Application work is expected to take less than one week and will occur between
November 16 and March 31 to avoid impacts to fisheries within the PNA areas. NOAA
staff will be present during work hours to monitor and control the placement of material.
The dredge anticipated to do the proposed work is the SNELL, a multi-purpose vessel
owned by the USACE, Wilmington District. It is 104 feet in length and drafts 5' 6",
making it very versatile for working in shallow areas.
The SNELL is equipped with a 10" diesel -driven pump and a 6" hydraulic pump system
that can discharge up to 1,200 feet. A digging head lifts sediment off the bottom as the
suction pump draws the material in through the pipe and discharges it through the
opposite end. The pipe will be floated from the vessel to the shoreline, and once ashore,
the pipe will be supported by the fiberglass boardwalk and, if necessary, cradles made
from lumber. A crib structure that will elevate the discharge end of the pipe above the
marsh pond will also be constructed of lumber. A diffuser will be fixed to the end of the
pipe to spread the material and diffuse the energy, and silt fencing and hay bales (if
needed) will line the edges of each pond to minimize impacts to the surrounding marsh.
The dredged substrate is anticipated to have a high sand content and therefore the activity
is not expected to produce a plume of suspended fine particulates in the project area.
Version 6.15.2017 Page S
Figure 3. Perspective of ponds and Morrow areas from The USACE Navigation Channel (2014 imagery)
According to previous sediment testing conducted in 1989 and 1996, material in the
Atlantic Intracoastal Waterway (AIWW) federal channel within the project area consists
of —97% sand. For this particular study, material will be taken from just outside the
navigation channel limits and will be primarily from the surface of the waterway bed
(within upper 18").
Once the elevation within the ponds begins to reach the elevation of surrounding marsh,
the pumps will be shut off and the pipe and cribbing will be adjusted to uniformly fill in
remaining areas within the ponds. The end result will be a leveled surface (as much as
possible) to mimic the natural landscape. Vegetation planting of Spartina alterniflora will
occur in the spring following the fill activity (see Figure 4 for profile view of before and
after project). Silt fencing will be removed once the vegetation is established. If hay bales
are used they would be expected to break down naturally over time. Monitoring of both
sites will begin in the spring and continue for at least three growing seasons, or until
Spartina alterniflora percent coverage equals 75%.
Version 6.15.2017 Page 6
Temporary Silt Fencing Planted Spartina alterniflora
Figure 4. Profile view of pond before (left) and after (right) sediment application and planting.
Avoidance and Minimization
Additional impacts were avoided by eliminating a proposed pond located approximately
400 feet southeast of Pond A. This pond was considered "connected" and therefore more
critical EFH, resulting in the avoidance of 0.125 ac of marsh impacts. The ponds selected
for this project are "isolated" from open water and not directly accessible by fish or
marine mammals, while also closest to the channel, which reduces impacts of the dredge
pipe and the need for additional boardwalk.
Material excavated for the ponds will be dredged from the setback area adjacent to the
AIWW. Dredge boxes have been established to minimize bottom disturbance and
excavation depths will not exceed 12-18". Placement of dredged material in ponds will
not exceed the elevation of surrounding marsh to avoid creating high marsh and
introducing Phragmites spp.
The suggested November 16 — March 31 work window will be implemented to avoid
impacts to fisheries (finfish and shrimp). The dredge operator will abide by the USFWS
manatee guidelines to avoid any potential injury or harm to the protected species.
SAVs will be avoided to the maximum extent practicable; excavation will be within the
setback of the channel within waters too deep to support SAVs (typically 3 feet or less).
Nearest SAV colonies identified are 500 feet to the west of Pond B; nearest dredging will
occur 150+ feet beyond SAW
Compensatory Mitigation
Permanent impacts (fill) are designed to restore the sites to the original marsh elevation.
A diffuser will be fixed to the end of the pipe to spread the material and diffuse the
energy of the dredged material slurry. Temporary impacts during construction will not
permanently alter wetland functions and; therefore, mitigation is not proposed.
Version 6.15.2017 Page 7
Essential Fish Habitat
Pursuant to the Magnuson -Stevens Fishery Conservation and Management Act, this
Public Notice initiates the Essential Fish Habitat (EFH) consultation requirements. The
Corps' initial determination is that the proposed project may adversely affect EFH or
associated fisheries managed by the South Atlantic or Mid Atlantic Fishery Management
Councils or the National Marine Fisheries Service. The applicant is completing the
Essential Fish Habitat Assessment which will be forwarded to NOAA Fisheries upon
completion for conservation recommendations.
Cultural Resources
Pursuant to Section 106 of the National Historic Preservation Act of 1966, Appendix C of
33 CFR Part 325, and the 2005 Revised Interim Guidance for Implementing Appendix C,
the District Engineer consulted district files and records and the latest published version
of the National Register of Historic Places and initially determines that:
❑ Should historic properties, or properties eligible for inclusion in the National
Register, be present within the Corps' permit area; the proposed activity requiring
the DA permit (the undertaking) is a type of activity that will have no potential to
cause an effect to an historic properties.
® No historic properties, nor properties eligible for inclusion in the National
Register, are present within the Corps' permit area; therefore, there will be no
historic properties affected. The Corps subsequently requests concurrence from
the SHPO (or THPO).
❑ Properties ineligible for inclusion in the National Register are present within the
Corps' permit area; there will be no historic properties affected by the proposed
work. The Corps subsequently requests concurrence from the SHPO (or THPO).
❑ Historic properties, or properties eligible for inclusion in the National Register,
are present within the Corps' permit area; however, the undertaking will have no
adverse effect on these historic properties. The Corps subsequently requests
concurrence from the SHPO (or THPO).
❑ Historic properties, or properties eligible for inclusion in the National Register,
are present within the Corps' permit area; moreover, the undertaking may have an
adverse effect on these historic properties. The Corps subsequently initiates
consultation with the SHPO (or THPO).
❑ The proposed work takes place in an area known to have the potential for the
presence of prehistoric and historic cultural resources; however, the area has not
been formally surveyed for the presence of cultural resources. No sites eligible
for inclusion in the National Register of Historic Places are known to be present
Version 6.15.2017 Page 8
in the vicinity of the proposed work. Additional work may be necessary to
identify and assess any historic or prehistoric resources that may be present.
The District Engineer's final eligibility and effect determination will be based upon
coordination with the SHPO and/or THPO, as appropriate and required, and with full
consideration given to the proposed undertaking's potential direct and indirect effects on
historic properties within the Corps-indentified permit area.
Endangered Species
Pursuant to the Endangered Species Act of 1973, the Corps reviewed the project area,
examined all information provided by the applicant and consulted the latest North
Carolina Natural Heritage Database. Based on available information:
❑ The Corps determines that the proposed project would not affect federally listed
endangered or threatened species or their formally designated critical habitat.
® The Corps determines that the proposed project
may affect, not likely to adversely affect federally listed endangered or threatened
species or their formally designated critical habitat. The listed Species identified
from the Heritage database include; Shortnose Sturgeon (Acipenser brevirestrum),
Atlantic Sturgeon (Acipenser oxyrinchus), Loggerhead Seaturtle (Caretta
caretta), Green Seaturtle (Chelonia mydas) and West Indian Manatee (Trichechus
manatus) within the project area.
❑ The Corps initiates consultation under Section 7 of the ESA and will not make
a permit decision until the consultation process is complete.
® NOAA NCCOS will consult under Section 7 of the ESA and the Corps will
not make a permit decision until the consultation process is complete.
❑ The Corps has initiated consultation under Section 7 of the ESA and will not
make a permit decision until the consultation process is complete.
❑ The Corps determines that the proposed project may affect federally listed
endangered or threatened species or their formally designated critical habitat.
Consultation has been completed for this type of activity and the effects of the
proposed activity have been evaluated and/or authorized by the National Marine
Fisheries Service (NMFS) in the South Atlantic Regional Biological Opinion or
its associated documents, including 7(a)(2) & 7(d) analyses and Critical Habitat
assessments. A copy of this public notice will be sent to the NMFS.
❑ The Corps is not aware of the presence of species listed as threatened or
endangered or their critical habitat formally designated pursuant to the
Endangered Species Act of 1973 (ESA) within the project area. The Corps will
make a final determination on the effects of the proposed project upon additional
Version 6.15.2017 Page 9
review of the project and completion of any necessary biological assessment
and/or consultation with the U.S. Fish and Wildlife Service and/or National
Marine Fisheries Service.
Other Required Authorizations
The Corps forwards this notice and all applicable application materials to the appropriate
State agencies for review.
North Carolina Division of Water Resources (NCDWR): The Corps will generally not
make a final permit decision until the NCDWR issues, denies, or waives the state
Certification as required by Section 401 of the Clean Water Act (PL 92-500). The receipt
of the application and this public notice, combined with the appropriate application fee, at
the NCDWR Central Office in Raleigh constitutes initial receipt of an application for a
401 Certification. A waiver will be deemed to occur if the NCDWR fails to act on this
request for certification within sixty days of receipt of a complete application. Additional
information regarding the 401 Certification may be reviewed at the NCDWR Central
Office, 401 and Buffer Permitting Unit, 512 North Salisbury Street, Raleigh, North
Carolina 27604-2260. All persons desiring to make comments regarding the application
for a 401 Certification should do so, in writing, by 10/11/2017 to:
NCDWR Central Office
Attention: Ms. Karen Higgins, 401 and Buffer Permitting Unit
(USPS mailing address): 1617 Mail Service Center, Raleigh, NC 27699-1617
Or,
(physical address): 512 North Salisbury Street, Raleigh, North Carolina 27604
North Carolina Division of Coastal Management (NCDCM):
® The application did not include a certification that the proposed work complies
with and would be conducted in a manner that is consistent with the approved
North Carolina Coastal Zone Management Program. Pursuant to 33 CFR 325.2
(b)(2) the Corps cannot issue a Department of Army (DA) permit for the
proposed work until the applicant submits such a certification to the Corps and
the NCDCM, and the NCDCM notifies the Corps that it concurs with the
applicant's consistency certification. As the application did not include the
consistency certification, the Corps will request, upon receipt, concurrence or
objection from the NCDCM.
❑ Based upon all available information, the Corps determines that this application
for a Department of Army (DA) permit does not involve an activity which would
affect the coastal zone, which is defined by the Coastal Zone Management (CZM)
Act (16 U.S.C. § 1453).
Version 6.15.2017 Page 10
Evaluation
The decision whether to issue a permit will be based on an evaluation of the probable
impacts including cumulative impacts of the proposed activity on the public interest.
That decision will reflect the national concern for both protection and utilization of
important resources. The benefit which reasonably may be expected to accrue from the
proposal must be balanced against its reasonably foreseeable detriments. All factors
which may be relevant to the proposal will be considered including the cumulative effects
thereof, among those are conservation, economics, aesthetics, general environmental
concerns, wetlands, historic properties, fish and wildlife values, flood hazards, flood plain
values (in accordance with Executive Order 11988), land use, navigation, shoreline
erosion and accretion, recreation, water supply and conservation, water quality, energy
needs, safety, food and fiber production, mineral needs, considerations of property
ownership, and, in general, the needs and welfare of the people. For activities involving
the discharge of dredged or fill materials in waters of the United States, the evaluation of
the impact of the activity on the public interest will include application of the
Environmental Protection Agency's 404(b)(1) guidelines.
Commenting Information
The Corps of Engineers is soliciting comments from the public; Federal, State and local
agencies and officials, including any consolidated State Viewpoint or written position of
the Governor; Indian Tribes and other interested parties in order to consider and evaluate
the impacts of this proposed activity. Any comments received will be considered by the
Corps of Engineers to determine whether to issue, modify, condition or deny a permit for
this proposal. To make this decision, comments are used to assess impacts on endangered
species, historic properties, water quality, general environmental effects and the other
public interest factors listed above. Comments are used in the preparation of an
Environmental Assessment (EA) and/or an Environmental Impact Statement (EIS)
pursuant to the National Environmental Policy Act (NEPA). Comments are also used to
determine the need for a public hearing and to determine the overall public interest of the
proposed activity.
Any person may request, in writing, within the comment period specified in this notice,
that a public hearing be held to consider the application. Requests for public hearings
shall state, with particularity, the reasons for holding a public hearing. Requests for a
public hearing will be granted, unless the District Engineer determines that the issues
raised are insubstantial or there is otherwise no valid interest to be served by a hearing.
The Corps of Engineers, Wilmington District will receive written comments pertinent to
the proposed work, as outlined above, until 5pm, 10/11/2017. Comments should be
submitted to Brad Shaver, Project Manager, Wilmington Regulatory Field Office,
69 Darlington Avenue, Wilmington, North Carolina 28403 , at (910) 251-4611.
Version 6.15.2017 Page 11