HomeMy WebLinkAbout20141169 Ver 7_USACE Correspondence_20170522Carpenter,Kristi
From: Steffens, Thomas A CIV USARMY CESAW (US)
<Thomas.A.Steffens@usace.army.mil>
Sent: Monday, May 22, 2017 5:48 PM
To: Johnson, Jay B; Ward, Garcy; Lane, Stephen
Cc: Vorwerk, Paul J; Mcmannen, Brad T
Subject: RE: Permit at Deep Gulley
AI I,
I much prefer the proposed work trestle over the 3000 sq. ft. of fill at this location. As
such, you may consider this transmission as an official approval of this proposal. A
permit mod will be unnecessary as the area has already been permitted for temporary
impacts and this is a large minimization.
Be advised that all S&E measures necessary for this proposal be installed and
maintained daily, especially on the slope leading to the trestle after its installed.
Previous experience indicates this high traffic area was often overlooked and led to
instances of avoidable loss.
And, without the benefit of contours or elevation profiles in the proposal, I'd also
recommend installing a temporary containment berm upslope (if there is an upslope) of
the trestle as a temporary restraint for the weekends. This action helped prevent losses
on several occasions on the previous project.
Thomas Steffens
Regulatory Project Manager
Washington Regulatory Field Office
2407 West 5th Street
Washington, NC 27889
o) (910)-251-4615
The Wilmington District is committed to providing the highest level of support to the
public. We would appreciate your feedback on how we are performing our duties. Our
automated Customer Service Survey is located here:
http://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0
-----Original Message-----
From: Johnson, Jay B [mailto:jbjohnson@ncdot.gov]
Sent: Monday, May 22, 2017 4:50 PM
To: Steffens, Thomas A CIV USARMY CESAW (US) <Thomas.A.Steffens@usace.army.mil>;
Ward, Garcy <garcy.ward@ncdenr.gov>; Lane, Stephen <stephen.lane@ncdenr.gov>
Cc: Vorwerk, Paul J<pvorwerk@ncdot.gov>; Mcmannen, Brad T
<btmcmannen@ncdot.gov>
Subject: [Non-DoD Source] FW: Permit at Deep Gulley
FYI
From: Vorwerk, Paul J
Sent: Monday, May 15, 2017 4:41 PM
To: Johnson, Jay B
Cc: Mcmannen, Brad T; 'jackson.provost@summitde.net'
Subject: FW: Permit at Deep Gulley
Jay,
Attached is a request from BBI for a reduction in temporary impacts at Deep Gulley
(R2514D). They plan on accomplishing this by building a 3-span work trestle.
Please let me know if you need anything else.
Thanks,
Paul
From: Distefano, Peter [mailto:PDistefano@bbiius.com]
Sent: Monday, May 15, 2017 4:32 PM
To: Mcmannen, Brad T; Vorwerk, Paul J
Cc: Jackson Provost
Subject: Permit at Deep Gulley
Gentlemen,
I tried to get feedback from Mr. Steffens on this scenario, but I am now told he is out for
a period of time.
With that said, attached is a change that we would like to implement at the Deep Gulley
Structure.
After hearing the concerns of the agencies regarding the water level fluctuations at this
location as well as the historic sediment losses on past projects, we do not want to use
the planned 3000 SF of "Temporary Impacts" shown in the permit for this structure
location. Instead we would like to install 3 spans of work trestle as shown and
highlighted Green in the attached. Our impact within that green area would be limited
to the necessary 24" trestle piles and would total less than 50 SF of impact area.
We do plan to begin this installation the week of June 5th. In the past, we have made
changes in work access plans reducing impact areas and we have not needed permit
modifications. However due to this timeline we are hoping you verify that this change
would be acceptable and let us know as soon as possible so that we can make
preparations to move in one direction or the other.
Thanks,
Peter D. Distefano � Balfour Beatty Infrastructure, Inc.
EA to: NC 133 Extension Project Manager � Maysville Bypass Project Manager
T: 910-452-1145 � M: 910-367-7800 � E: pdistefano@bbiius.com
<mailto:pdistefano@bbiius.com>
430 Eastwood Rd. Wilmington, NC 28403
Blockedwww.bbiius.com <Blockedhttp://www.bbiius.com/> � Linkedln
<Blockedhttps://www.linkedin.com/company/balfour-beatty-infrastructure-inc.>
Confidentiality Notice: The contents of this e-mail are confidential and are intended only
for the use of the recipient(s) unless otherwise indicated. If you have received this e-
mail in error, please notify the sender(s) immediately by telephone. Please destroy and
delete the message from your computer. Any form of reproduction, dissemination,
copying, disclosure, modification, distribution and/or publication of this e-mail is strictly
prohibited unless expressly authorized by the sender(s). No person, without written
confirmation of the contents of this e-mail, should rely on it. While this e-mail and the
information it contains are supplied in good faith, no member of the Balfour Beatty plc
group of companies shall be under any liability in respect of the contents of this e-mail
or for any reliance the recipient may place on it. This e-mail is sent for information
purposes only and shall not have the effect of creating a contract between the parties.
Email correspondence to and from this sender is subject to the N.C. Public Records Law
and may be disclosed to third parties.
Email correspondence to and from this sender is subject to the N.C. Public Records Law
and may be disclosed to third parties.