May 5, 2016
Mr. William Thacker
Duke Energy Progress
Roxboro Steam Electric Plant
1700 Dunnaway Rd
Roxboro, NC 27343
PAT MCCRORY
Govemor
DONALD R. VAN DER VAART
Secretary
S. JAY ZIMMERMAN
Director
MAY _ 9 2016
1tj'�014,IRAT1Ui P4QC�S�I,VG UNIT
NPDES Compliance Sampling Inspection
NPDES Wastewater Discharge
Permit No. NC00_034_25-
Person County
Dear Mr. Thacker:
On March 1, 2016, Autumn Romanski and Cheng Zhang of the Raleigh Regional Office
conducted a Compliance Sampling Inspection at the Roxboro Steam Electric Plant. The
effluent sampling results were sent to the Division of Water Resources Laboratory and
qualified lab results were received on April 18, 2016, which extended the inspection
completion date noted on the EPA Inspection Report. We greatly appreciated the cooperation
and assistance provided by Mr. Shannon Langley, Mr. Robert Howard, and Plant Staff to
complete the inspection and sampling.
The facility and the sampling results were in compliance with the permit requirements
reviewed the day of this inspection. No response to this inspection is required.
The complete compliance inspection report is attached. The following is a list of the site
observations.
1. The Wastewater Discharge Treatments are classified as a Class PC- 1 Wastewater
Plant. Your NPDES Individual Wastewater permit became effective July 1, 2009 and
expired on December 31, 2012.
2. The Primary ORC is Eric Satterwhite, a PC -1 (certification number #985810) NC
Certified Operator. There are several backup operators, all hold a PC -1 operator
certification. The ORC logbook, lab results, chain of custody forms, and DMR's were
readily available and in good order for review. The DMR month of December 2015
was reviewed with no discrepancies found. The staff should be commended as the
facility has had no Notice of Deficiency or Violation issued in the last 12 months, and
no Civil Penalty assessments.
State of North Carolina I Environmental Quality I Water Resources
1628 Mail Service Center I Raleigh, North Carolina 27609-1628
919 7914200
3. The sampling techniques, CST Checklist, and a brief lab inspection checklist was
completed. The facility was compliant with the checklist requirements reviewed over
the days of this sampling inspection. The checklists are attached.
4. The Roxboro Plant holds NC Field Parameter Certification #5080 for pH and
Temperature. The Roxboro Plant also used NC Certified Lab Pace Analytical through
2015.
5. The DWR conducted grab and composite effluent sampling at NPDES Effluent Outfall
003 and grab sampling at NPDES Effluent Outfall 006 over the days of the site visit.
The DWR Lab results are listed below:
Recent Average Flow reported in February 2016 for outfall 003 was 456.5 MGD and
0.79 MGD for outfall 006. Flow at both outfalls observed the days of the inspection
were clear and free of solids
The DWR Lab analyte results are attached to this inspection report and summarized in
the tables below.
Outfall 003 Analyte
Result
TSS
Undetected at 6.2 mg/1
Arsenic
Undetected at 2.0 ug/L
NH3 as N
0 02 mg/L
NO2 + NO3 as N
0.23 mg/L
Total Phosphorus
0.05 mg/L
Total Kjeldahl N as N
0 18 mg/L
Outfall 006 Analyte
Result
TSS
1.8 mg/L
There are currently no limits in the NPDES permit at Outfall 003 except in the case of
chlorine addition in which a TRC limit of 200 ug/L is in effect. There are internal
outfall limits for Oil and Grease and TSS at Outfall 002, but outfall 002 and other
internal outfalls were not sampled as part of this inspection. The results showed the
facility was in compliance with the NPDES permit TSS limit of 50 mg/L at Outfall
006. The Toxicity test results were forwarded in a separate letter and were Passes.
21 Page
If you have questions, please contact Autumn Romanski at 919-791-4255 c
Autumn.Romanski@ncdenr.gov.
incerel ,
Danny Smith
Raleigh Regional Operations Supervisor
Cc: Enclosures
RRO-WQROS
DWR- Central Files
via e-mail at
Ec: shannon.langleygduke-energy.com; robert.howard@duke-energy.com
3 1 P a g e
United States Environmental Protection Agency
Fort Approved
EPA Washington, D C 20460
OMB No 2040-0057
Water Compliance Inspection Report
Approval expires 8-31-98
Section A National Data System Coding (i e, PCS)
Transaction Code NPDES yr/mo/day Inspection Type Inspector Fac Type
1 2 15 I 3 I N00003425 111 12 16/04/18 17 181 o 1 19 L G I 201 I
=1
211'-1 1 1 1 1 1 1 1 1 11 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 I 1 1 1 1 1 11 1 1 1 1 166
Inspection Work Days Facility Self -Monitoring Evaluation Rating B1 QA Reserved
72 LJ 73 I74 7511 I I I I 80
67 70LJ 71 itJ
Section B Facility Data
Name and Location of Facility Inspected (For Industrial Users discharging to POTW, also include
Entry Time/Date
Permit Effective Date
POTW name and NPDES permit Number)
09 30AM 16/04/18
09/07/01
Roxboro Steam Electric Power Plant
Exit Time/Date
Permit Expiration Date
1700 Dunnaway Rd
Semora NC 27343
03 20PM 16/04/18
12/03/31
Name(s) of Onsite Representative(s)/Titles(s)/Phone and Fax Number(s)
Other Facility Data
///
Ronald D Easley/ORC/336-597-7332/
Name, Address of Responsible Official/Title/Phone and Fax Number
Contacted
William J Thacker, 1700 Dunnaway Rd Semora NC 27343/Plant
Manager/336-597-6101/ No
Section C Areas Evaluated During Inspection (Check only those areas evaluated)
Permit Flow Measurement Operations & Maintenance N Records/Reports
Self-Monitonng Program Sludge Handling Disposal Effluent/Receiving Waters
Section D Summary of Finding/Comments (Attach additional sheets of narrative and checklists as necessary)
(See attachment summary)
Name(s) and Signature(s) of Inspector(s) Agency/Office/Phone and Fax Numbers Date
Cheng Zhang ��� .� _ RRO WQH919-791-4200/ !
Autumn H Romanskt % � RRO WQ//919-791-4247/
S gnatu of Management Reviewer Agency/Office/Phone and Fax Numbers Date/
zz;�� /e�
EPA Form 356 (Rev 9-94) Previous editions are obsolete ✓
Page#
NPDES yr/mo/day Inspection Type
31 NC0003425 I11 12 16/04/19 17 18 S I
Section D Summary of Finding/Comments (Attach additional sheets of narrative and checklists as necessary)
The permittee was In compliance with the requirements reviewed and the Compliance Sampling
Inspection Checklist completed over the days of this Inspection
Page#
Permit: NC0003425 Owner - Facility: Roxboro Steam Electric Power Plant
Inspection Date: 04/18/2016 Inspection Type: Compliance Sampling
Permit Yes No NA NE
(If the present permit expires In 6 months or less) Has the permittee submitted a new ❑ ❑ ❑
application?
Is the facility as described In the permit?
M
❑
❑
❑
# Are there any special conditions for the permit?
❑
❑
❑
❑
Is access to the plant site restricted to the general public?
❑
❑
❑
❑
Is the inspector granted access to all areas for inspection?
N
❑
❑
❑
Comment The current NPDES Wastewater Discahrae
permit became effective July 1, 2009 and
Comment- The final NPDES outfall 003 effluent flow is reported from the influent flow readings
expired on March 31, 2012
(assumes all water taken In is discharged)
The facility was compliant with teh NPDES permit wastewater reauirements reviewed the
day of the inspection The application for permit renewal was received on October 10. 2011
as required An update to the application has also been submitted. The new permit has not
been issued vet, therefore, this inspection was conducted based on NPDES wastewater
discharge permit issued July 1, 2009 as these requirements remain in effect until the new
ermit is Issued.
Operations & Maintenance Yes No NA NE
Is the plant generally clean with acceptable housekeeping? N ❑ ❑ ❑
Does the facility analyze process control parameters, for ex MLSS, MCRT, Settleable ❑ ❑ ❑
Solids, pH, DO, Sludge Judge, and other that are applicable?
Comment: The facility does analyze process control parameters Operations and maintenance are
ongoing with proactive maintenance and operational planning evident The facility has
moved forward since the last NPDES inspection with useful life evaluation of the 1984
Domestic WWTP
Flow Measurement - Effluent
Yes No NA NE
# Is flow meter used for reporting?
❑
❑
0
❑
Is flow meter calibrated annually?
❑
❑
0
❑
Is the flow meter operational?
❑
❑
N
❑
(If units are separated) Does the chart recorder match the flow meter?
❑
❑
N
❑
Comment- The final NPDES outfall 003 effluent flow is reported from the influent flow readings
(assumes all water taken In is discharged)
A flow meter is located at internal outfall 002 prior to mixing
with the heated water discharge.
The final Outfall 003 receives flow from multiple wastewater and stormwater discharges
Effluent Samplina
Yes No NA NE
Is composite sampling flow proportional?
❑
❑
❑
Is sample collected below all treatment units?
❑
❑
❑
Page# 3
Permit: NC0003425 Owner - Facility Roxboro Steam Electric Power Plant
Inspection Date- 04/18/2016 Inspection Type Compliance Sampling
Yes No NA NE
Is the basin aerated?
Effluent Sampling
Yes No NA NE
Is proper volume collected?
M
❑
❑
❑
Is the tubing clean?
M
❑
❑
❑
# Is proper temperature set for sample storage (kept at less than or equal to 6 0 degrees
0
❑
❑
❑
Celsius)?
❑
Are all pumps operable?
❑
❑
Is the facility sampling performed as required by the permit (frequency, sampling type
M
❑
❑
❑
representative)?
❑
Are audible and visual alarms operable?
❑
❑
Comment No composite sampling is required by the permit except toxicity A toxicity sample was
collected on 3/1 and 3/3 along with grab samples collected as part of a Compliance
Sampling Inspection on on 3/1 The sampling results are included with this reportThe
toxicity result was a Pass at both outfalls and the results were reported in a separate letter
The location of the composite sampler is on the pier located by Outfall 003 The outfall
outlet is large with flow, current and turbulance Logistically, it is not Dossible to place a
composite sampler and tubing set up in the effluent stream so the sampler is placed on the
Pier to the far right of the effluent stream( in the Lake) Grab samples are also collected
from the pier - due to safety concerns - the pier is logistically safer for personnel and
access by boat would be needed to sample the main effluent stream at outfall 003
Egualization Basins
Yes No NA NE
Is the basin aerated?
❑
❑
M
❑
Is the basin free of bypass Imes or structures to the natural environment?
❑
❑
M
❑
Is the basin free of excessive grease?
❑
❑
M
❑
Are all pumps present?
❑
❑
M
❑
Are all pumps operable?
❑
❑
0
❑
Are float controls operable?
❑
❑
M
❑
Are audible and visual alarms operable?
❑
❑
❑
# Is basin size/volume adequate?
❑
❑
M
❑
Comment The FGD West and East Basin water levels and the hinrpartnr hnrkwnQh hair, %mora
Record Keeping
Yes No NA NE
Are records kept and maintained as required by the
permit?
❑
❑
❑
Is all required information readily available, complete
and current?
❑
❑
❑
Are all records maintained for 3 years (lab reg required
5 years)?
❑
❑
❑
Are analytical results consistent with data reported
on DMRs?
M
❑
❑
❑
Is the chain -of -custody complete?
❑
❑
❑
Dates, times and location of sampling j
Name of individual performing the sampling
Page# 4
Permit. NC0003425
Inspection Date: 04/18/2016
Record Keening
Results of analysis and calibration
Dates of analysis
Name of person performing analyses
Transported COCs
Are DMRs complete do they Include all permit parameters?
Owner - Facility Roxboro Steam Electric Power Plant
Inspection Type: Compliance Sampling
Has the facility submitted Its annual compliance report to users and DWQ?
(If the facility Is = or > 5 MGD permitted flow) Do they operate 24/7 with a certified operator
on each shift?
Is the ORC visitation log available and current?
Is the ORC certified at grade equal to or higher than the facility classification?
Is the backup operator certified at one grade less or greater than the facility classification?
Is a copy of the current NPDES permit available on site?
Facility has copy of previous year's Annual Report on file for review?
Yes No NA NE
❑ ❑ ❑
M ❑ ❑ ❑
■ ❑ ❑ ❑
M ❑ ❑ ❑
M ❑ ❑ ❑
M ❑ ❑ ❑
❑ ❑ ■ ❑
Comment The facility holds field parameter certification for Temperature and PH. It was explained that
the facility has an inline temperature reading at the final outfall 003. A temperature is ran In
the lab when composite samples for toxicity are collected. Both temperature meaurements
were checked against an NIST thermometer - records indicated, the last check was done
12/10/2015
Page# 5