HomeMy WebLinkAbout20081374 Ver 1_Stormwater Info_20081028 L Stormwater Management Calculations Belgate -Southern Tract Prepared for: Crescent Resources, LLC 400 S. Tryon Street, Suite 1300 Charlotte, North Carolina 28202 © Kimley-Hom and Associates, Inc. 2008 ? ? ? Kimley-Horn and Associates, Inc. OCT 2 8 ?018 DENk - STORMWATER BRANCH SANDS AND 1 C C C r L This document, together with the concepts and designs presented herein, as an instrument of service, is intended only for the specific t purpose and client for which it was prepared. Reuse of and improper reliance on this document without written authorization and adaptation by Kimley-Hom and Associates, Inc. shall be without liability to Kimley-Horn and Associates, Inc. ' i i U g - i 31 4 BELGATE - SOUTHERN TRACT CHARLOTTE, NORTH CAROLINA STORMWATER MANAGEMENT CALCULATIONS Prepared for: Crescent Resources, LLC 400 S. Tryon Street, Suite 1300 Charlotte, North Carolina 28202 Prepared by: Kimley-Horn and Associates, Inc. 4651 Charlotte Park Drive, Suite 300 Charlotte, Noirolina 28217 ?i ? i L t' Co A 1/111111t10 X0240$ OCTOBER 2008 KHA Ref: 018253026 TABLE OF CONTENTS OVERVIEW SITE MAPS SITE VICINITY MAP SCS SOIL SURVEY FEMA FIRM PANEL WATERSHED MAPS PRE-DEVELOPMENT WATERSHED MAP POST-DEVELOPMENT WATERSHED MAP WATER QUALITY WET POND CALCULATIONS VOLUME AND SURFACE AREA TABLES WET DETENTION BASIN SUPPLEMENT FORMS WATER QUANTITY CURVE NUMBER CALCULATIONS TIME OF CONCENTRATION CALCULATIONS HYDROCAD HYDROLOGY REPORT STORMWA TER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, NC L u Background OVERVIEW D i r r u n u This report contains the approach and results of a stormwater analysis conducted for the Belgate - Southern Tract Site. The 41-acre project site is located in the south east quadrant of the interchange of Interstate 85 and City Boulevard in the City of Charlotte (see vicinity map). The site has been mass graded per City of Charlotte permit number GRS-2007223. Existing Conditions The existing on-site conditions (before mass grading) consisted of woods and meadow therefore this ground cover was used in the analysis. The site topography varies from elevation 770 ft to elevation 720 ft. Site runoff discharges into an existing stream in the middle portion of the site. This stream drains to a culvert under City Blvd. Floodplain/Floodwgy The proposed site does not lie within a 100-year floodway boundary as determined by FIRM Panel # 3717900070C. Water Quality Water quality treatment by means of permanent Best Management Practices (BMP's) will be provided using two wet ponds as treatment. The ponds are designed to treat the first inch of runoff per the Stormwater Model Ordinance for North Carolina and will draw down over a period of two to five days. Wet Detention Basin 1 and Wet Detention Basin 2 have been designed to provide a minimum 90% average annual removal of Total Suspended Solids (TSS). Water Quantity The proposed wet detention ponds have been designed to address the water quantity requirements to match pre- and post-development peak runoff rates for the 1-year, 24-hour storm events. (These ponds will also control the peak runoff rates for the 10- and 25-year, 6-hour storm events per the City of Charlotte rezoning notes on Petition 2006-155. However, these water quantity requirements will be reviewed by the City of Charlotte when the site develops.) The 100-year, 24-hour storm event was checked for 6" of freeboard at the top of bank. Results Pre-development 1-yr, 24-hr storm Post-development 1-yr, 24-hr storm DA-1 2.63 cfs 1.80 cfs DA-2 1.57 cfs 1.43 cfs ' STORMWATER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, NC Conclusion The proposed wet detention basins were designed using methods prescribed by the aforementioned resources. HydroCAD software was utilized to evaluate the pre-development and post-development flow rates. HydroCAD utilizes TR-55 methods of calculating times of concentration (based on sheet, shallow concentrated, and channelized flows) and SCS curve number method of generating hydrographs (results are provided in Appendix C). Based on the analyses provided herein, the proposed system will be adequate to address the stormwater requirements of the North Carolina Department of Environment and Natural Resources, Division of Water Quality. STORMWATER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, NC 7 7 r D [7 SITE MAPS STORMWATER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, North Carolina FIGURE 1 THIS DOCUMENT. TOGE1MER WTI THE CONCEPTS AND DESIGNS PRESENTED HEREIN. AS AN INSTRUMENT OF SERWZ IS INTENDED ONLY FOR THE PURPOSE AND CLIENT FOR WHICH IT WAS PREPARED. REUSE OF AND IMPROPER RELIANCE ON THIS DOCUMENT WTIOUT WRITTEN AUTHORIZATION AND ADAPTATION BY KIMLEY-HORN AND ASSOCIATES. INC. SHALL BE WTHOUT LIABILITY TO MONEY-HORN AND ASSOCIATES. INC. K,\CHL_LDEV\018253 Crescent\026 Bel ate\Bel ate Stornwater Management Plan\Calculatlons\Parcel J\SoHs and VlcWWt Ma .dw ' PARCEL J ROADWAY SCS SOIL SURVEY FIGURE 0.0 Kimley-Horn and Associates, Inc. NTS 2 THIS DOCUMENT. TOGETHER " THE CONCEPTS AND DESIGNS PRESENTED M ON. AS AN INSTRUMENT OF SERVICE. IS INTENDED ONLY FOR THE PURPOSE AND CLIENT FOR WHICH IT WAS PREPARED. REUSE OF AND IMPROPER RELUNCE ON INS DOCUMENT WITHOUT MUTTEI AUTHORIZATION MCI ADAPTATION BY IOUEY--HORN AND ASSOCIATES. NC. SHALL BE w1THOUT UABLITY TO KNBEY-HORN AND ASSOCIATES. INC. N y D d ? C 7 ? m ? m - y C 3 y N ? O N d Y d R C m U E?voE z o z 55 OCD y a ` ZZ D d r N S 0 ? o? . o m = O E v co 3 Z o mm?"N d "LS In v b' dp D. m 11 .°Ew C u - Q d'EELL c - T- O A L. X O 5? C D Q D 0 ? U N LU 65 E a W D- U LL o c J o?=D Q - CS IF Y 2 c Qp 2 S m)=RatYi ` ?E 5 mL ? ILL U EL V L L d d Q m3m?E E d = p LL C._ y p O E O a?+ D xm dam p) U mmmd o o ;`ca a - O' w by cA X N Z -,N7 Z i O :? ° LD (D 'A u \ ?' 5 s W.•''/ '` `? ?? ?? 65 ? W N \ \\ ?? . ?` ? 6$0 W ? \ a. .. \? ? ? J s64 661 N ` . \;;.. WQ cD J X _ W ue z > O' X N W w N S ?ry ? ? X `p \ ? y, N o q W s r, Z W O Z x N O 1 W W s O Z ` 6 N S m O y 'te m? C C d m ? ? N r ?o aw e o Lit 3 '? ? ? $ Z cf ul ? ? Q ? ? Q H Q " ?«' "? v 4 a 6 C3 `7 Q ° W m ? W " ? ? o b? ? o e m C ? O c i µ?. bye u W W Y y U= y 4 m Z z U m Z c ppi ?? i u W y at t a' ? 'Em E; mmr• J W O 7w W Z $ ?= S E v LL 4. ? z C Q 8 ? a y ? z?ss w @ P ? Y O II O H n i ' m p ^ O A ? y - y C 7 d N m 7 W W WQS o u pp D m'? E ry m G m Lmv O vLLOiI ms..? ° }. !b CAF QO C CM eD E uV D L i LAJ a ct Via.. " C? ,..'eY Z? y O U 6L c m ` m m D Q-O [- Q u Zoo d ie C C. F= v v . ? .o m o 15 c' m E p 5 z a a? °e "L ?? `wQZp " N Q W W Q O W _ .. iea C y `O L ... m .Nmmm ?(A d V d ? r0 . H V U C nn ? L p N W = C o m r W Q a O = Ri p? Z V O z o x z C7, ...A m U s : 09 u •"E'm '+ttm u u amDv E v- p m m p Y 0 E Eli o? `r 2 U U N Z Y ° -Em m m 2 D L O C W a x G " o a .. `. imp ca W j ULL ? L= IP = O Y = ° t 6? a C mV a OZ O t U p Q (? V Q O z I ? W ?I = u z f y m ?u ?`E y 4a mp u ` ' " m~ a? m Q- O c + ¦. z C a a °u v s u r i {S :.P+ fs. O E m L LL r LL L U Dp cu EL Q v p p 0 6.5 E E c C C p av l D C p LL C @ C 6 a 6 , fo P o u 9 9 9 @ 9 P 0 . m °o oa y ? ? ff.Y m c D E N y ? m m E? UO m m ®m m p tL ? D ? 0 L2- . o << Y = V e m O O O O O K to m CO CO n n n n n m m O O O to m m m m m m m o Lo to a a o m m m m m n m o co co \ D r i LL c D p U cv m m m m m m m m m co co Lo P7 [O t9 Pi [7 Y Lo U) L L L N N N N N N N N u N N N N N y ,,, O ``. \ \ E x m _ \ 3 l - N E c m o Q '? - - - r - - - - - - - - N m m m n m m m co n m m m N n m n T N CD C ro¢ N - - - - - - - - o m m m m m a ^ O m (7 N m O n - - - - - o m N m m ID Lp m -?\ ?\ •? ` i' m H H N n 1n n 1D m 7 m F a N N C m m m N n N n N n n N N l7 [7 t m m D m It m m m (D .` , L 6, \ p \` ?` `,•• m w w O w w w m °__ \ J m m } Q m U L] W LL () 2- '7 Y J } Q y Q m U W LL (,D = - "'? Y ' (L v m m m m i S 0 0 Na N9n0jln:)JW l^• 41, i bv? \` cv ui •.. \.? ?`??•.. OS W p c Z m LU u W 0 Q LL 0 N I u n 1 1-1 u I r N_ v L O O_ O ? y ?a V] U U ? N O C o •? Qo O i-LL O y ?s C C •- 0 .O ? m ? U O 4 W O O J Q U U) Q d W W 4i p ' Q D y met O v LAJ q Q Er Q Q `° =° C m v W z a ? «< ¢c? ¢ 9 ao a?S W? u rn O Q o e "` `r m ? W ? W ) ? mo o- W C m o ° E. U j i a W Q R. a_ i.? u ^i . Q C i = Z J F' C) x r o ° i, :oe ?M r v z V o p9 Z ms ice r u E ? " 'Ea G ° ?/ O .•7 x D4 H ° a ?? .? ? z ? v ?' ma ?es i ? ?? d z ? s• w + ? V Cli Q I W ?? ? eyD r„•oe m S fi e? u O Z o 8 f O ® t O O .. \ W } J ' \ W 00; w 4? \ ` \ O `. 1-4 U p V-4 r O U V 1 q t ID W Z > > \\\?: N by . m C- m D o L C m _ W D N d C m ? D E o9 o E 9 ms ? m ` LL R m o m ??cmm [ ?Z o ®m7r-. ?°DSa ic, Q m m ? ?oED?o m m E ry o EELL odm?? [[L W o J m = LL G C m V y L o mH n `o?ME ZIP ow IL L ? mD Dr ;wE m E m c LL 0 D O E C m y Y e m b c D E m m O m m W m_°; Q 3 `o . a .,V z +?r Li J ?. n c 43 1 PRE-DEVELOPMENT WATERSHED MAP STORMWA TER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, North Carolina ? eNOlcuau ur0 'aN - ? P 99ZBZ ON'3llOlWHa Z919Z'VNIIOUVa Nl!!ON ?' GM'316'133L16 NOAH1'6000 A1Nnooouf16N31NO3W'3llOIUVHO N ,?9, f i 5 Oll'63unos3H 1N3a63Na 'OA1B "DONV 99-1 dVW V3MV d ev3{ lit j I 3JVNIVL141N3WdOl3n30 Sad F o w € SN1nd 1N3W30VNVW V31VMWVOLS ?aispy o 1JtlM1 Na3N1f10S 31tl013B ?rww? e I Yf ? y r i I L ... w cl? Ay 1 11 :, ??8 I y .._- 1 f , i I r I ¦ \ t y p ya G ty??? ? %? @ NO i I ? ?? 9? ? - ? j I r ? ?, ¦ a i a p?w F' ` v co z I I co 0 \1 111 r rn ,9?? wf5 / ¢ Q V N ,I - S?I •I :?lrn ?' I j I,' ¦ ,?. 6 is U I ask ??_ ?# ? ? , ¦ I - -- ------------------ a? 3 ? 'r 7 i I ., ate. ,+ _?„•_,?, -??r'e?,? .aL??'??xti ° i? y m e; y C { -d "4w , u•p.r.,.. ae wow's _ .. .:" I , ', ?. ??:. U e ^2 (1yU, p PC ? e 1 1 1 1 1 1 POST-DEVELOPMENT WATERSHED MAP ' STORMWA TER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, North Carolina ? V MVO ON 90ZBZ ON'91101HVHO ZOZBZ VNIlOHVO KWON c` g g OOU 31S '133b1S NOANl'S 006 A1Nf100 Dan0N31)4o3W'31101UVHO o ^' E tom" L 011'S3O21O053tl 1N3OS3llO 'OA1S AlIO ONV 90-1 n i d N 1'g ,Y g dN3 dOI ? „ ? =s 1 )TI 30t/NIVaOlN3WdOl3N301SOd m o ?E? a €k a. SN 1OVa1 Na3HMOSa3 vem eS ?52 ?;!a??? o a ? sN3ro :tarom :ntu 0 E ? o ?$' C Z W CD W J /w V Q z Q elf 0 0 a ro z U ? Z Q O V U Q O Z_ 1 I I I i r ZU V C /r N II O t "1 { N U r - ... Z 6 f •? / t ?• I I ?l : 00 J 1 I ? f l ? J I al a_; ?pfit v S ice, - I I4e ?? ?- ?u i ) ¦ I I (,4 I' I 1 4 1 , I Z I u o I NOUN i! - Z til -- .-0) 1 a 7t. r /._...?\ j N O ?- 110 ,r ,y I y I N Q Z ,A c ) r r. Vii w rf ? •r I LJ ?-? - r. I 1_ _ I 1 r I j 1 ?'? r I I 1 1 I I 1 I \ I ? I 1 I I ! : ..._ ?•', ?-?? ----_-_777 \ I 1 I I I _ ? -•• ??? .. ?-M41 a _l r - f n•M'•wn xa Weco-s soot Yt ?w,w _ _ _ ._. ... - ooi-oi-smr•s•roa\r n+.•e\•w,.onco\w i:.:::.eoex .?o..:..,s .:.s.s\•ws=e stoNW.w.o cctaioWoryo\:x C r 0 WET POND CALCULATIONS STORMWA TER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, North Carolina C M FJ Kimley-Horn ® and Associates, Inc. WET DETENTION BASIN Project Information Project Name: Belgate - Southern Tract KHA Project #: 018253026 Designed by: BRR Date: 10/8/2008 Revised by: BRR Date: 10/27/2008 Revised by: Date: Site Information Sub Area Location: Drainage Area 1 Drainage Area (DA) = 7.2 Acres Impervious Area (IA) = 5.8 Acres Percent Impervious (1) = 80.0 % Required Surface Area Permanent Pool Depth: 4.25 ft SA/DA = 3.65 (90% TSS Removal via Pond) Min Req'd Surface Area = 11448 sf (at Permanent Pool) Required Storage Volume: Design Storm = 1 inch (Project Does Not Drain to SA waters) Determine Rv Value = 0.05 +.009 (1) = 0.77 in/in Storage Volume Required = 20125 cf (above Permanent Pool) Elevations Area (s.f.) Bank Elevation = 732.00 ft Top of Pond Elevation = 732.00 ft Temporary Pool Elevation = 727.60 ft 16,278 Permanent Pool Elevation = 726.00 ft 11,541 Shelf Beginning Elevation = 726.50 ft Forebay Weir = 728.00 ft Shelf Ending Elevation = 725.50 ft Bottom Elevation = 718.00 ft Wet Basin Areas/Volumes Area @ Top of Temporary Pool = 16278 sf (Elevation = 727.60) Area @ Top of Permanent Pool = 11541 sf (Elevation = 726.00) Volume of Temporary Storage = 22255 cf Side Slopes of Pond = 3 :1 Side Slopes of Shelf = 1 0 :1 Side Slopes of Pond (below shelf) = 3 :1 Is Permanent Pool Surface Area Sufficient (yes/no)? Yes ( 11541 > 11448) sf Volume of Storage Provided 22255 cf Total Volume Sufficient (yes/no)? Yes Orifice Size = 2.30 inches WET DETENTION BASIN Project Information Project Name: Belgate - Southern Tract KHA Project #: 018253026 Designed by: BRR Date: Revised by: Date: Revised by: Date: Site Information Sub Area Location: Drainage Area 1 Drainage Area (DA) = 7.2 Acres Impervious Area (IA) = 5.8 Acres Percent Impervious (1) = 80.0 _% (Drainage Area) Orifice Sizing Q2 Days = 0.3381 cfs (Flowrate required for a 2 day drawdown) Qs Days = 0.1352 cfs (Flowrate required for a 5 day drawdown) Orifice Size = 2.70 in (Diameter) Q Office = 0.135 cfs Drawdown Time = 5 days less than 5 days (yes/no) ? yes greater than 2 days (yes/no) ? yes Orifice Equation: Q=cNV(2gh) Q2 < Q < Q5 c=0.6 A9= Area of Pipe = n/4D2 g = gravity = 32.2 ft/s2 h = orifice head = 1/3 (TPE-PPE-1/2D) TPE = Temporary Pool Elevation PPE = Permanent Pool Elevation D = Diameter 10/19/2008 C?? Kimley-Horn ® , and Associates, Inc. WET DETENTION BASIN Project Information Project Name: Belgate - Southern Tract KHA Project #: 0182 53026 Designed by: BRR Date: 10/8/2008 Revised by: BRR Date: 10/19/2008 Revised by: Date: Site Information Sub Area Location: Drainage Area 2 Drainage Area (DA) = 23.9 Acres Impervious Area (IA) = 16.1 Acres Percent Impervious (1) = 67.5 % Required Surface Area Permanent Pool Depth: 4.25 ft SA/DA = 2.975 (90% TSS Removal via Pond) Min Req'd Surface Area = 30985 sf (at Permanent Pool) Required Storage Volume: Design Storm = 1 inch (Project Does Not Drain to SA waters) Determine Rv Value = 0.05 +. 009 (1) = 0.66 in/in Storage Volume Required = 57036 cf (above Permanent Pool) Elevations Area (s.f.) Bank Elevation = 725.00 ft Top of Pond Elevation = 725.00 ft Temporary Pool Elevation = 720.60 ft 38,785 Permanent Pool Elevation = 719.00 ft 34,238 Shelf Beginning Elevation = 719.50 ft Forebay Weir = 722.00 ft Shelf Ending Elevation = 718.50 ft Bottom Elevation = 707.00 ft Wet Basin Areas/Volumes Area @ Top of Temporary Pool = 38785 sf (Elevation = 720.60) Area @ Top of Permanent Pool = 34238 sf (Elevation = 719.00) Volume of Temporary Storage = 58418 cf Side Slopes of Pond = 3 :1 Side Slopes of Shelf = 1 0 :1 Side Slopes of Pond (below shelf) = 3 :1 Is Permanent Pool Surface Area Sufficient (yes/no)? Yes ( 34238 > 30985) sf Volume of Storage Provided 58418 cf Total Volume Sufficient (yes/no)? Yes Orifice Size = 2.70 inches 1 1 1 1 1 1 WET DETENTION BASIN Project Information Project Name: Belgate - Southern Tract KHA Project M 018253026 Designed by: BRR Date: Revised by: Date: Revised by: Date: Site Information Sub Area Location: Drainage Area 2 Drainage Area (DA) = 23.9 Acres Impervious Area (IA) = 16.1 Acres Percent Impervious (1) = 67.5 % (Drainage Area) Orifice Sizing Q2 Days = 0.3381 cfs (Flowrate required for a 2 day drawdown) Qs Days = 0.1352 cfs (Flowrate required for a 5 day drawdown) Orifice Size = 2.70 in (Diameter) Q orrfrf ce = 0.135 cfs Drawdown Time = 5 days less than 5 days (yes/no) ? yes greater than 2 days (yes/no) ? yes Orifice Equation: Q=CAgd(2gh) Q2 < Q < Q5 c = 0.6 A9= Area of Pipe = Ti/4D 2 g = gravity = 32.2 ft/s2 h = orifice head = 1/3 (TPE-PPE-1/2D) TPE = Temporary Pool Elevation PPE = Permanent Pool Elevation D = Diameter 10/19/2008 VOLUME AND SURFACE AREA TABLES t STORMWA TER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, North Carolina ti c U1 m c_ m ° o 2 y a?i Q E a Y cca pp, ?I co O O N r O N N N 0 0 c N C) Q N M L LO v N O W w 0- r- O 3 Ln f0 m E rI O c O R E v E 3k > > L M a Q Z '0 v v a _. ++ L a c v v 00 L ? L) v o Q > > Ln v v a) L 2 O it 1= •o a Y CL c m c O v N 0 v O (.0 LD Ln U') 0) N N v ? 00 Ln m o m ri m 00 r-1 .-1 =3 u o ;T u i w r-i N Ql 00 r-I l0 d' t\ n Q r-i M r- 11 ri N I?r Ln r- Ol Ql v E N M rl Ln LD r-4 ?i ON Ln N U O ri r-I -It ri ri Ln N Ln 0o N •• j .. c-I N M Ln t\ M c-I ri ri N O ct LD Ln N n m M N N Ln lD d' C O ri M LD M M M ? c-I 00 LD LO U L 0 0 0 0 0 r-I r1 N m m d' Ln J z3 a O O O O O O O O O O O O 0 0 0 0 0 0 0 0 0 0 O O O r Q N w cf' ri m r, Ln LO r r-i lD N M 4 ? 00 r-4 cn t 0 ? r, C) r4 l 0 m 1 W -- Q ? . r -I N LD 00 0 r -I ? NO N Ix 0 LL W n 00 M O r-I N M I Ln LD n co ri r-I ri N N N N N N N N N N t\ t\ t\ n c ++ O Q- O O L L6 L B E a ? v L v a 0 ID Cl) ri Cl) ri N O r 1 Ql r Ln Qi O Ln O > c ? v co c v E L L o v U_ a v 1 1-1 Ol ? Ln m (.0 O 00 ri Ln (N N oo N -1 64 64 N Lr? Lj E ? l D O N M Ln n LD Q) Ln ? 00 :T LD r- LD Ln TT U 7 O "D N N n Ql ' ri Ln O 00 Ln O) N n R* Q p N ri r, "T N ri Ln O r, v m O c 'IT .-i r-I r-I N M Ln Ln lfl n 00 0) r4 r-I r- v I'D O L.0 00 m 00 00 M lzt r, m Ln r\ o O o m E r-I Ln m N O -1 r-I Ol N lD 00 Ln N N m ri U O lD LO 00 ri Ln r N N ri ct M lD 00 00 Ol 75 v N M -z*' l0 r, 00 00 ch u') l0 ' (T l0 Ol N :t l0 N ? N N N N 0 W j ? m 00 00 m r-I n n n LO Ql Q) O N V N Ln Ln ri J rU Q) O O Ln l0 00 00 00 Ln -:T 00 Ql m O r-i w m N CU r- Ql N Ln 00 00 00 O LO N d' n Q) O t Q) ct Q v 0 0 o ri r•i r-I r-1 ci r,4 N m m m m Ln Ln Ln l0 0 0 0 0 0 0 0 0 0 O O O O 0 0 0 0 0 0 Z O t w Ln , N o 00 W m o m n v w= v w -, L n m -i ? TI - o L n i- 'n v r -I O N TT N N N N (n N 1-1 m r N fV O ^ 00 00 00 Ql W Q N m Ln lD a0 00 W oo ri ri rrl 1-1 .-i N N N N Z c C h Oo 00 O) O ri N M CY Ln Ln LD LD n 00 (1 O ri N a M - -4 n ri t\ N n N r? N n N n N r- N r- N N f? N N t\ N i'`r N n N f\ m N m n M n N r- n ? O O p v a w a c Ln cu Q `0 O C -C V ) i ro m L v w w U E c O O O Ln O O m E M- CL CL D O E O 0 61 r- ?Ilj co 1 d - , I 00 m v Ln Ln Ln Ln O r-I Lr) r-I >?VV) v v C C E E L L v v a iZ CS ai c 'a 0 0 2 w co Q Ea Y co I a! Q a7 V W 3 N C (0 ai E 75 co O 0 N m 0 O r O N a) N 04 0 CY) U L C) O N O CO c O E Z .O = u a to Ln r+ a1 p Q 41 N L 2 0 tY •? a Y N c ro m c O 4,1 O N 0 N aJ ; E Ln Ln O r, dt Ln ri N Ln N Ln L U O O N N N N O O O r- In O f\ 00 00 00 Q O N N Q1 Ln r1 00 00 ri N N N v E Ln O t" 00 ri r, _3 C --l N N O O O O r? In ? M -i M ^ ? r- M m O - O v N d' Ln . Ln 1.0 r > , O U m m Ln N Ln r, m N l0 00 r- Ct W - lD in Ln Ln 4.0 m ri Kt 00 M m Ln CO t\ 00 m e-i N m Ln lO o 0 0 0 0 o ri r1 -i ci ri ? 0 0 0 0 0 0 0 O O O O J L o a fa ri 00 00 O lD It Ln L7) LD l0 00 a) M ri M m r? 0) ':t N I?t rn r- Q L v O S 00 N r- N 00 [t O LO M m Q N N N m m CF Ln l0 lD r, W O p00 N M t Ln to r, m a, O r-I N r-1 ri ri ri e-i r•i r-I ri N N N N t\ t\ t\ ? n N N n N t\ n O O O O 0_ } 4? Q c c L ai E L a, Q_ 0 m of N Ln 00 M 00 co N ? c-I O 0 4- O fi3 v E L L O a, LL_ a cu m a) m ^ LL 1 ri 00 ri ri m a) Ln ? r- O r- r- r` -tt rn N ? ri O1 ri M O N O N e-I O 0 p r? Ln M m Ln a) Ln m m Ln zt r-4 m m Qo ri r-I Q p t ri O r-I R Q1 m co Ln m l0 N M ri L? Ln m m Ln n m r-I M ct lD 00 O N lD r-I l0 N N ri ri r-I ri ri N N N M m 4 ?t O M n d• 00 l0 00 M O co ri Ln M O M r? E r, I?t r- Ln r-I r, r? N 00 O N m r, m rn v- u p r? t\ m Q1 ri -t Ln 00 Ol N 00 ri O N ct lzt LO m O M Ln m l0 co N Ln ri 00 Ln 00 _ m c-I r•i r-I N N N ri ri ri c1 N ri ct ? Ln Ln +' O W ? U r0 ?- Ln 00 Ln I- M O o co (n m d 't m N m ri P? to ri oo m lD r, O w oo et J- o v m o Ln o r-I lD O Ln O Ln ri M N N M M ri r, m O 00 0 m m m t d' Ln Ln w w r, m o0 0o m m N M M 0 0 0 0 0 0 0 0 0 0 0 0 0 o ri r-I ri 2 a Q. Lv lD oo Ol Ln d• M Ln ri a-I O . O r-I rn LI) r-I Ct m O M _ r\ r? m , m Ln tO r, 4 Ln M ri oo 4 N r-I Ln Ch Z Q m Ln r r- 00 rn O N N Ct Ln l0 r, r? r- ri rn Ln r4 n F, oo oo LT Ln N m m m lD ri O W r-I ri ri ri N N N N M m m M m 4 Ln Ln to Z w N m ct Ln lO r- m u? am f O l0 ri N M Ln a ri c-I ei ri e-i ri ri 00 r-I Ol N O N N N N N N n n n w v O O p t ?- O L/) CL Z a 4? t Q O C a In L to -Y c L U G O L 0 (m m L iL O t6 E Q O_ o o ~ E o m a u 0- 0 n l0 IZI, ri O 0) Ln m N 00 `? d. M c•i > vQi N +? aJ a) c c E E (U aa) a n. WET DETENTION BASIN SUPPLEMENT FORMS ' STORMWATER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, North Carolina Permit (to be provided by DWQ) e ???? W aT ?ROv r ? y NCDENR STORMWATER MANAGEMENT PERMIT APPLICATION FORM 401 CERTIFICATION APPLICATION FORM WET DETENTION BASIN SUPPLEMENT This form must be filled out, printed and submitted. The Required Items Checklist (Part III) must be printed, filled out and submitted along with all of the required information. 1. PROJECT INFORMATION` Project name Belgate Southern Tract Contact person Beverly Rosenbloom, El Phone number 704-319-7699 Date 10/24/2008 Drainage area number 1 II DESIGN INFORMATION Site Characteristics Drainage area 313,632.00 ft2 Impervious area 250,905.60 ftz % impervious 80.00 % Design rainfall depth 1.00 in Storage Volume: Non-SR Waters Minimum volume required 20,125.00 ft3 Volume provided 22,255.00 ft3 Storage Volume: SR Waters 1-yr, 24-hr runoff depth in Pre-development 1-yr, 24-hr runoff ft3 Post-development 1-yr, 24-hr runoff ft3 Minimum volume required ft3 Volume provided ft3 Peak Flow Calculations 1-yr, 24-hr rainfall depth 2.58 in Rational C, pre-development 0.28 (unitless) Rational C, post-development 0.89 (unitless) Rainfall intensity: 1-yr, 24-hr storm 0.12 in/hr Pre-development 1-yr, 24-hr peak flow 2.63 ft3/sec Post-development 1-yr, 24-hr peak flow 9.31 ft3/sec Pre/Post 1-yr, 24-hr peak flow control 6.68 -ft'/sec Basin Elevations Basin bottom elevation 718.00 It Sediment cleanout elevation 719.00 ft Bottom of shelf elevation 725.50 ft Permanent pool elevation 726.00 it SHWT elevation ft Top of shelf elevation 726.50 ft Temporary pool elevation 727.60 ft Form SW401-Wet Detention Basin-Rev.4 Parts I. & II. Design Summary, Page 1 of 2 ' Permit No. (to be provided by DWQ) 11. DESIGN INFORMATION ' ' Volume and Surface Area Calculations SA/DA ratio 3.65 (unitless) Surface area at the bottom of shelf 8,955.00 flz Volume at the bottom of shelf 45,466.00 ft3 ' Permanent pool, surface area required 11,448.00 f' Permanent pool, surface area provided 11,541.00 e OK Permanent pool volume 50,590.00 ft3 ' Average depth for SA/DA tables 4.38 ft OK Surface area at the top of shelf 14,328.00 ff2 Volume at the top of shelf 57,058.00 ft3 Forebay volume 9,712.00 ft3 Forebay % of permanent pool volume 19.20 % OK Temporary pool, surface area provided 16,278.00 ftz ' Drawdown Calculations Treatment volume drawdown time 2.60 days OK Treatment volume discharge rate 0.10 ft3/s Pre-development 1-yr, 24-hr discharge 2.63 ft3/s OK ' Post-development 1-yr, 24-hr discharge 1.83 ft3/s OK Additional Information Diameter of orifice 2.3 in Design TSS removal 90 % ' Basin side slopes 3.00 :1 OK Vegetated shelf slope 10.00 - :1 OK Vegetated shelf width 10.00 ft OK ' Length of flowpath to width ratio 4.40 :1 OK Length to width ratio 3.30 :1 OK Trash rack for overflow & orifice? id F b d d Y 2 25 (Y or N) ft OK OK 13ASEb ON C ITY of CFfr4?.oT? ?E5161v STajZWf prov ree oar e . ' Vegetated filter provided? N (Y or N) Design must be based on 90% TSS removal ZS-1f R t f?-1? Recorded drainage easement provided? Y (Y or N) OK Capures all runoff at ultimate build-out? Y (Y or N) OK ' Drain mechanism for maintenance or emergencies 24-HR EMERGENCY PUMP 1 ' Form SW401-Wet Detention Basin-Rev.4 Parts I. & II. Design Summary, Page 2 of 2 Permit No. (to be provided by DWQ) 111. REQUIRED ITEMS CHECKLIST Please indicate the page or plan sheet numbers where the supporting documentation can be found. An incomplete submittal package will result in a request for additional information. This will delay final review and approval of the project. Initial in the space provided to ' indicate the following design requirements have been met. If the applicant has designated an agent, the agent may initial below. If a requirement has not been met, attach justification. Pagel Plan Initials Sheet No. 1. Plans (1" 50' or larger) of the entire site showing: ' Design at ultimate build-out, Off-site drainage (if applicable), Delineated drainage basins (include Rational C coefficient per basin), Basin dimensions, ' Pretreatment system, High flow bypass system, Maintenance access, ' - Proposed drainage easement and public right of way (ROVE, Overflow device, and Boundaries of drainage easement. ' C-4 2. Partial plan (1" = 30' or larger) and details for the wet detention basin showing: Outlet structure with trash rack or similar, Maintenance access, ' - Permanent pool dimensions, Forebay and main pond with hardened emergency spillway, Basin cross-section, - Vegetation specification for planting shelf, and ' - Filter strip. _ 3. Section view of the dry detention basin (1" = 20' or larger) showing: ' Side slopes, 3:1 or lower, Pretreatment and treatment areas, and Inlet and outlet structures. ' 4. If the basin is used for sediment and erosion control during construction, clean out of the basin is specified on the plans prior to use as a wet detention basin. eAL( 9CID14 5. A table of elevations, areas, incremental volumes & accumulated volumes for overall pond and for forebay, ' to verify volume provided. 6. A construction sequence that shows how the wet detention basin will be protected from sediment until the entire drainage area is stabilized. ' C?k 7. The supporting calculations. ' 8. A copy of the signed and notarized operation and maintenance (0&M) agreement. 9. A copy of the deed restrictions (if required). ' 10. A soils report that is based upon an actual field investigation, soil borings, and infiltration tests. County soil maps are not an acceptable source of soils information. Form SW401-Wet Detention Basin-Rev.4 Part III. Required Items Checklist, Page 1 of 1 Permit No (to be provided by DWQ) WNATFRO O T NCDENR STORMWATER MANAGEMENT PERMIT APPLICATION FORM 401 CERTIFICATION APPLICATION FORM WET DETENTION BASIN SUPPLEMENT This form must be filled out, printed and submitted. The Required Items Checklist (Part 111) must be printed, filled out and submitted along with all of the required information. L PROJECT INFORMATION Project name Belgate Southern Tract Contact person Beverly Rosenbloom, El Phone number 704-319-7699 Date 10/24/2008 Drainage area number 2 II. DESIGN INFORMATION Site Characteristics Drainage area 1,041,519.60 ff2 Impervious area 702,622.80 ff % impervious 67.46 % Design rainfall depth 1.00 in Storage Volume: Non-SR Waters Minimum volume required 57,036.00 ft3 Volume provided 60,545.00 -ft' Storage Volume: SR Waters 1-yr, 24-hr runoff depth in Pre-development 1-yr, 24-hr runoff ft3 Post-development 1-yr, 24-hr runoff ft3 Minimum volume required ft3 Volume provided ft3 Peak Flow Calculations 1-yr, 24-hr rainfall depth 2.58 in Rational C, pre-development 0.28 (unitless) Rational C, post-development 0.74 (unitless) Rainfall intensity: 1-yr, 24-hr storm 0.12 in/hr Pre-development 1-yr, 24-hr peak flow 1.57 ft3/sec Post-development 1-yr, 24-hr peak flow 21.76 ft3/sec Pre/Post 1-yr, 24-hr peak flow control 20.19 -ft'/sec Basin Elevations Basin bottom elevation 707.00 ft Sediment cleanout elevation 708.00 ft Bottom of shelf elevation 718.50 ft Permanent pool elevation 719.00 ft SHWT elevation ft Top of shelf elevation 719.50 ft Temporary pool elevation 720.60 ft Form SW401-Wet Detention Basin-Rev.4 Parts I. & II. Design Summary, Page 1 of 2 ' Permit No. (to be provided by DWQ) IL DESIGN INFORMATION ' Volume and Surface Area Calculations SAIDA ratio 2.98 (unitless) Surface area at the bottom of shelf 27,740.00 ft' Volume at the bottom of shelf 133,518.00 ft3 ' Permanent pool, surface area required ftz Permanent pool, surface area provided 31,750.00 ft3 OK Permanent pool volume 148,391.00 ft3 Average depth for SAIDA tables 4.67 ft OK Surface area at the top of shelf 35,931.00 ft2 Volume at the top of shelf 165,311.00 ft3 Forebay volume 28,852.00 ft3 Forebay % of permanent pool volume 19.44 % OK Temporary pool, surface area provided 41,443.00 ftz ' Drawdown Calculations Treatment volume drawdown time 5.00 days OK Treatment volume discharge rate 0.14 ft3/s Pre-development 1-yr, 24-hr discharge 1.57 ft3/s OK ' Post-development 1-yr, 24-hr discharge 1.43 ft3/s OK Additional Information Diameter of orifice 2.7 in Design TSS removal 90 % ' Basin side slopes 3.00 :1 OK Vegetated shelf slope 10.00 :1 OK Vegetated shelf width 10.00 ft OK ' Length of flowpath to width ratio 4.10 :1 OK Length to width ratio 120 :1 OK Trash rack for overflow & orifice? Y 1 40 (Y or N) ft OK OK BASED OF-3 CtT1 of CH't?Rl.°TlG pE51(oN Freeboard provided . " ' Vegetated filter provided? N (Y or N) l a RM , ZS ?!}2? 1o-11*R Design must be based on 90% TSS removal 5 Recorded drainage easement provided? Y (Y or N) OK Capures all runoff at ultimate build-out? Y (Y or N) OK ' Drain mechanism for maintenance or emergencies 24-HR EMERGENCY PUMP ' Form SW401-Wet Detention Basin-Rev.4 Parts I. & II. Design Summary, Page 2 of 2 ' Permit No. (to be provided by DWO) IIL REQUIRED ITEMS CHECKLIST ' Please indicate the page or plan sheet numbers where the supporting documentation can be found. An incomplete submittal package will result in a request for additional information. This will delay final review and approval of the project. Initial in the space provided to indicate the following design requirements have been met. If the applicant has designated an agent, the agent may initial below. If a requirement has not been met, attach justification. Page/ Plan Initials Sheet No. C 1. Plans (1" 50' or larger) of the entire site showing: Design at ultimate build-out, ' Off-site drainage (if applicable), Delineated drainage basins (include Rational C coefficient per basin), Basin dimensions, ' Pretreatment system, High flow bypass system, Maintenance access, Proposed drainage easement and public right of way (ROW), ' Overflow device, and Boundaries of drainage easement. C-4 2. Partial plan (1" = 30' or larger) and details for the wet detention basin showing: Outlet structure with trash rack or similar, Maintenance access, ' Permanent pool dimensions, Forebay and main pond with hardened emergency spillway, Basin cross-section, Vegetation specification for planting shelf, and ' Filter strip. C -4 3. Section view of the dry detention basin (1" = 20' or larger) showing: Side slopes, 3:1 or lower, ' Pretreatment and treatment areas, and Inlet and outlet structures. ' 4. If the basin is used for sediment and erosion control during construction, clean out of the basin is specified on the plans prior to use as a wet detention basin. CALL bODY- 5. A table of elevations, areas, incremental volumes & accumulated volumes for overall pond and for forebay, ' to verify volume provided. 6. A construction sequence that shows how the wet detention basin will be protected from sediment until the entire drainage area is stabilized. CALL. eb!DIC 7. The supporting calculations. 8. A copy of the signed and notarized operation and maintenance (0&M) agreement. 9. A copy of the deed restrictions (if required). ' 10. A soils report that is based upon an actual field investigation, soil borings, and infiltration tests. County soil maps are not an acceptable source of soils information. Form SW401-Wet Detention Basin-Rev.4 Part III. Required Items Checklist, Page 1 of 1 CURVE NUMBER CALCULATIONS STORMWATER MANAGEMENT CALCULATIONS Belgate - Southern Tract, Charlotte, North Carolina C]M Kmley-Horn M" aid Associates, hc. Pre vs. Post Runoff Analysis Composite Curve Number (CN) Project Information Project Name: Parcel J KHA Project #: 018253020 Designed by: BRR Revised by: Revised by: Date: 10/612008 Date: Date: Drainage Area Name Drainage Location Cover/Soil Name (Type) Cover Description' Hydrologic Soil Group Curve # (CN)" Area (ac) Product of CN x area Composite Curve Number (CN) PRE-DEVELOPMENT DA-1 OUTFALL 1 Mecklenburg, Enon, Wilkes Woods Good Condition C 70 5.04 353 70 Meadow Good Condition B 71 5.04 358 71 ? 10.08 711 70.5 , DA-2 OUTFALL 1 Mecklenburg, Enon, Wilkes Woods Good Condition C 70 2.95 207 70 Mecklenburg, Enon, Wilkes Meadow Good Condition C 71 2.95 209 71 Cecil Meadow Good Condition B 58 10.69 620 58 Cecil Woods Good Condition B 55 10.69 588 55 27.28 1624 59.5 Total Pre-development Area = 37.36 POST DEVELOPMENT DA-1 POND 1 Impervious 98 6.48 635 98 Mecklenburg, Enon, Wilkes Open Space - Good Condition C 74 0.72 53 74 7.20 688.04 95.60 UND DA-1 OUTFALL 1 Mecklenburg, Enon, Wilkes Open Space - Good Condition C 74 110 81 74 1.10 81.50 74.00 DA-2 POND 2 Impervious 98 13.23 1297 98 Mecklenburg, Enon, Wilkes Open Space - Good Condition C 74 0.90 67 74 Cecil Open Space - Good Condition B 61 5.71 348 61 Roadway - Impervious 98 2.90 284 98 Mecklenburg, Enon, Wilkes Roadway - Open Space C 74 1.06 78 74 Cecil Roadway - Open Space B 61 0.10 6 61 23.91 2080.60 87.03 UND DA-2 OUTFALL 2 Mecklenburg, Enon, Wilkes Open Space - Good Condition C 74 2.65 196 74 Cecil Open Space - Good Condition B 61 3.76 230 61 1 1 6.42 425.96 66.38 Total Post-development Area = 38.62 ' Cover Descriptions per TR-55 Manual " From TR-55 Manual, Table 2-2 a & c K:\CHL_LDEV\018253 Crescent\022\Parcel J\Calculations\Storm\Stormwater Calculations_2008-10-06.xis 1 of 1 n 0 1 0 J 1 u r n TIME OF CONCENTRATION CALCULATIONS EROSION CONTROL CALCULATIONS New Towne Gardens, Union County, North Carolina u rn T c f6 O Q ? L O N ? O H U O p IL d i E_ m~ a` 0 0 N 0 O O O E U a Z ? O d d _ O C O d > > raio O Y c m 'o a Ex F- c l0 F- H N ? U N Q U ? 3 L R v ? a v O N ? E N a ca 4- N Q Lp Ul ? 2 C ?? O O U LL O CO O ? O (D N > d Lp C a ? -m ? C T ? v 3La ~ N N C N - CD C C t . C O O ? U N C CL 0 N L m 41 E O LL 0 n U N N U 0 t N H N C O U J Z W a 'O OJ L O z 3 w IL IL O' O V UD O M N J 0 a M O N O II N N?' N I o a II C E o v II E E v v ° F F C O C O d o c d V C o O U ° O U O d E d E i- j N W 0 M I I 0 III ? ? I 04 ?I ri I I 0 O O o 04 o o o o o O M M M 0 0 o o o o o) N O M M m C -p "O D ''. L I ? C U '.i 'O L O O O ol U > O O,I O O U j Z I Z m ! m? . N. O N I y N U L l0 N C fn L tp C N i co CO ., 0 O I. L U U , U'?, U N I O J ? J J LL J LL D O O i QI' ' N Q i . O 0 N O N N N 0 0 5 W JI U Y HYDROCAD HYDROLOGY REPORT 1? 11 ' EROSION CONTROL CALCULATIONS New Towne Gardens, Union County, North Carolina I 1 F 1 L 1S 2S 4S Pre-dev DA-1 Post-d v DA-1 Post-dev ND DA-1 3P v 8P Pond 1 Outfall 1 5S 6S 8S Pre-dev DA-2 Post-d v DA-2 Post-dev ND DA-2 7P 9P Pond 2 Subca Reach and Lin k Outfall 2 D D Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 HydroCADO 8.50 s/n 005123 © 2007 HydroCAD Software Solutions LLC Page 2 Time span=0.00-24.00 hrs, dt=0.05 hrs, 481 points Runoff by SCS TR-20 method, UH=SCS Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method Subcatchment 1S: Pre-dev DA-1 Runoff Area=10.080 ac 0.00% Impervious Runoff Depth>0.53" Tc=25.2 min CN=71 Runoff=2.63 cfs 0.443 of Subcatchment 2S: Post-dev DA-1 Runoff Area=7.200 ac 0.00% Impervious Runoff Depth>2.14" Tc=5.0 min CN=96 Runoff=9.31 cfs 1.283 of Subcatchment 4S: Post-dev UND DA-1 Runoff Area=1.100 ac 0.00% Impervious Runoff Depth>0.65" Tc=5.0 min CN=74 Runoff=0.45 cfs 0.060 of Subcatchment 5S: Pre-dev DA-2 Runoff Area=27.280 ac 0.00% Impervious Runoff Depth>0.19" Tc=25.0 min CN=60 Runoff=1.57 cfs 0.441 of Subcatchment 6S: Post-dev DA-2 Runoff Area=23.910 ac 0.00% Impervious Runoff Depth>1.38" Tc=5.0 min CN=87 Runoff=21.76 cfs 2.744 of Subcatchment 8S: Post-dev UND DA-2 Runoff Area=6.420 ac 0.00% Impervious Runoff Depth>0.36" Tc=5.0 min CN=66 Runoff=1.22 cfs 0.191 of Pond 3P: Pond 1 Peak Elev=728.07' Storage=34,996 cf Inflow=9.31 cfs 1.283 of Outflow=1.68 cfs 0.613 of Pond 7P: Pond 2 Peak Elev=721.82' Storage=106,572 cf Inflow=21.76 cfs 2.744 of Outflow=0.31 cfs 0.297 of Pond 8P: Outfall 1 Inflow=1.80 cfs 0.673 of Primary=1.80 cfs 0.673 of Pond 9P: Outfall 2 Inflow=1.43 cfs 0.489 of Primary=1.43 cfs 0.489 of Total Runoff Area = 75.990 ac Runoff Volume = 5.162 of Average Runoff Depth = 0.82" 100.00% Pervious = 75.990 ac 0.00% Impervious = 0.000 ac i u u I I 1 C Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 HydroCADO 8.50 s/n 005123 © 2007 HydroCAD Software Solutions LLC Page 3 Summary for Subcatchment 1S: Pre-dev DA-1 Runoff = 2.63 cfs @ 12.77 hrs, Volume= 0.443 af, Depth> 0.53" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Area (ac) CN Description ' 10.080 71 10.080 Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 25.2 Direct Entry, From spreadsheet Subcatchment 1S: Pre-dev DA-1 Hydrograph 2.63 cfs Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr 2 Rainfall=2.5$" Runoff Area=10.080 ac Runoff Volume=0.443 of LL Runoff Depth>0.53" 1 Tc=25.2 min CN=71 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours) ¦ Runoff I 0 0 CI' C L C Belgate - Southem Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 HydroCADO 8.50 s/n 005123 © 2007 HydroCAD Software Solutions LLC Page 4 Summary for Subcatchment 2S: Post-dev DA-1 [49] Hint: Tc<2dt may require smaller dt Runoff = 9.31 cfs @ 12.40 hrs, Volume= 1.283 af, Depth> 2.14" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Area (ac) CN Description 7.200 96 7.200 Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, From spreadsheet 1 a U. L Subcatchment 2S: Post-dev DA-1 Hydrograph ¦ Runoff 9.31 cfs Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Runoff Area=7.200 ac Runoff Volume=1.283 of Runoff Depth>2.14" Tc=5.0 min CN-96 1 o - 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours) [1 n ' Belgate - Southem Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 HydroCAD® 8.50 s/n 005123 © 2007 HydroCAD Software Solutions LLC Page 5 Summary for Subcatchment 4S: Post-dev UND DA-1 [49] Hint: Tc<2dt may require smaller dt ' Runoff = 0.45 cfs @ 12.45 hrs, Volume= 0.060 af, Depth> 0.65" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" ' Area (ac) CN Description 1.100 74 ' 1.100 Pervious Area Tc Length Slope Velocity Capacity Description _(min) (feet) (ft/ft) (ft/sec) (cfs) 5.0 Direct Entry, Subcatchment 4S: Post-dev UND DA-1 ' Hydrograph n 0.5 0.45 0.4 0.35 0.3 0.25 0 LL 0.2 0.15 0.1 0.45 cfs Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2,58" Runoff Area=1.100 ac Runoff Volume=0.060 of Runoff Depth>0.65 Tc=5.0 min CN=74 ¦ Runoff ' V 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours) D ' Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 ' HydroCAD® 8.50 s/n 005123 @2007 HydroCAD Software Solutions LLC Page 6 Summary for Subcatchment 5S: Pre-dev DA -2 ' Runoff = 1.57 cfs @ 13.04 hrs, Volume= 0.441 af, Depth> 0.19" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Area (ac) CN Description 27.280 60 27.280 Pervious Area ' Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 25.0 Direct Entry, From Spreadsheet ' Subcatchment 5S: Pre-dev DA-2 Hydrograph ¦ Runoff 1.57 cfs Charlotte 24-hr ' 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Runoff Area=27.280 ac ?F 1- Runoff Volume=0.441 of U. Runoff Depth>0.19 ' Tc=25.0 min CN=60 1 O iTi i iTi a iTi i i iTi i iT...,T, „ iTi 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours) Belgate - Southem Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 ' HydroCAD® 8.50 s/n 005123 © 2007 HydroCAD Software Solutions LLC Page 7 Summary for Subcatchment 6S: Post-dev DA-2 [49] Hint: Tc<2dt may require smaller dt ' Runoff = 21.76 cfs @ 12.41 hrs, Volume=- 2.744 af, Depth> 1.38" Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" ' Area (ac) CN Description 23.910 87 ' 23.910 Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) ' 5.0 Direct Entry, Subcatchment 6S: Post-dev DA-2 ' Hydrograph 24- 23- unoff ' 21.76 cfs 22- 21- Charlotte 24-hr 20- 19- 1-yr 24.00hrs 1 yr - 24 hr ' 17 Rainfall=2'.58„ 16 15 Runoff Area=23.910 ac ' 13 Runoff Volume=2.744' of 12 Runoff Depth>1.38" LL ?? 10 ' 9 Tc=5.0 min 8- CN=87 5 4 3 2 1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours) 0 L D ' Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 ' HydroCAM 8.50 s/n 005123 © 2007 HydroCAD Software Solutions LLC Page 8 Summary for Subcatchment 8S: Post-dev UND DA-2 ' [49] Hint: Tc<2dt may require smaller dt Runoff = 1.22 cfs @ 12.51 hrs, Volume= 0.191 af, Depth> 0.36" ' Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" ' Area (ac) CN Description 6.420 66 ' 6.420 Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) ' 5.0 Direct Entry, Subcatchment 8S: Post-dev UND DA-2 ' Hydrograph ¦ Runoff ' 1.22 cfs Charlotte 24-hr 1-yr 24.00 hrs 1 yr 24 hr ' Rainfall=2.58" Runoff Area-6:420 ac Runoff Volume=0.191 of LL Runoff Depth>0.36" Tc=5.0 min ' CN=66 C 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours) D ' Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 ' HydroCAD® 8.50 s/n 005123 @2007 HydroCAD Software Solutions LLC Page 9 Summary for Pond 3P: Pond 1 ' Inflow Area = 7.200 ac, 0.00% Impervious, Inflow Depth > 2.14" for 1 yr - 24 hr event Inflow = 9.31 cfs @ 12.40 hrs, Volume= 1.283 of Outflow = 1.68 cfs @ 13.35 hrs, Volume= 0.613 af, Atten= 82%, Lag= 57.2 min ' Primary = 1.68 cfs @ 13.35 hrs, Volume= 0.613 of Routing by Stor-Ind method, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs ' Peak Elev= 728.07'@ 13.35 hrs Surf.Area= 19,601 sf Storage= 34,996 cf Plug-Flow detention time= 285.6 min calculated for 0.611 of (48% of inflow) Center-of-Mass det. time= 167.9 min ( 959.6 - 791.7 ) Volume Invert Avail.Storage Storage Description #1 726.00' 128,745 cf Custom Stage Data (Prismatic) Listed below (Recalc) ' Elevation Surf.Area Inc.Store Cum.Store (feet) (sq-ft) (cubic-feet) (cubic-feet) ' 726.00 13,220 0 0 727.00 17,234 15,227 15,227 728.00 19,423 18,329 33,556 729.00 21,832 20,628 54,183 ' 730.00 23,807 22,820 77,003 731.00 25,853 24,830 101,833 732.00 27,972 26,913 128,745 ' Device Routing Invert Outlet Devices #1 Primary 726.00' 36.0" x 51.0' long Culvert RCP, square edge headwall, Ke= 0.500 Outlet Invert= 724.50' S=0.0294'/' Cc= 0.900 n=0.013 ' #2 Device 1 726.00' 2.3" Vert. Orifice/Grate C= 0.600 #3 Device 1 727.75' 2.50' W x 0.75'H Vert. Orifice/Grate C=0.600 #4 Device 1 729.00' 2.50' W x 0.67' H Vert. Orifice/Grate C=0.600 ' #5 Device 1 729.50' 3.00' x 4.00' Horiz. Orifice/Grate Limited to weir flow C=0.600 Primary OutFlow Max=1.67 cfs @ 13.35 hrs HW=728.07' (Free Discharge) t1=Culvert (Passes 1.67 cfs of 25.56 cfs potential flow) ' 2=Orifice/Grate (Orifice Controls 0.20 cfs @ 6.77 fps) 3=Orifice/Grate (Orifice Controls 1.48 cfs @ 1.83 fps) -Orifice/Grate ( Controls 0.00 cfs) ' 5=Orifice/Grate ( Controls 0.00 cfs) iI II Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 HydroCAD® 8.50 s/n 005123 @2007 HydroCAD Software Solutions LLC Page 10 Pond 3P: Pond 1 Hydrograph ? 1 1 w 0 LL 11 ¦ Inflow ¦ Primary 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours) ' Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainf611=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 ' HydroCADO 8.50 s/n 005123 © 2007 HydroCAD Software Solutions LLC Page 11 Summary for Pond 7P: Pond 2 ' Inflow Area = 23.910 ac, 0.00% Impervious, Inflow Depth > 1.38" for 1 yr - 24 hr event Inflow = 21.76 cfs @ 12.41 hrs, Volume= 2.744 of ' Outflow 0.31 cfs @ 24.00 hrs, Volume= 0.297 af, Atten= 99%, Lag= 695.2 min Primary 0.31 cfs @ 24.00 hrs, Volume= 0.297 of Routing by Stor-Ind method, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs ' Peak Elev= 721.82'@24.00 hrs Surf.Area= 42,040 sf Storage= 106,572 cf Plug-Flow detention time= 420.6 min calculated for 0.297 of (11 % of inflow) ' Center-of-Mass det. time= 249.5 min ( 1,088.9 - 839.5 ) Volume Invert Avail.Storage Storage Description #1 719.00' 275,997 cf Custom Stage Data (Prismatic) Listed below (Recalc) ' Elevation Surf.Area Inc.Store Cum.Store (feet) (sq-ft) (cubic-feet) (cubic-feet) ' 719.00 31,750 0 0 720.00 37,219 34,485 34,485 721.00 39,841 38,530 73,015 722.00 42,524 41,183 114,197 ' 723.00 53,616 48,070 162,267 724.00 56,850 55,233 217,500 725.00 60,143 58,497 275,997 ' Device Routing Invert Outlet Devices #1 Primary 719.00' 36.0" x 36.2' long Culvert RCP, square edge headwall, Ke= 0.500 ' Outlet Invert= 716.00' S= 0.0829'/' Cc= 0.900 n= 0.013 #2 Device 1 719.00' 2.7" Vert. Orifice/Grate C= 0.600 #3 Device 1 723.60' 4.00' x 3.00' Horiz. Orifice/Grate Limited to weir flow C=0.600 #4 Device 1 722.00' 1.50' W x 0.50'H Vert. Orifice/Grate C=0.600 ' Primary OutFlow Max=0.31 cfs @ 24.00 hrs HW=721.82' (Free Discharge) L1=Culvert (Passes 0.31 cfs of 39.42 cfs potential flow) 1:3=Orifice/Grate Orifice/Grate (Orifice Controls 0.31 cfs @ 7.92 fps) ( Controls 0.00 cfs) Orifice/Grate ( Controls 0.00 cfs) I 11 Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr- 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 HydroCAD® 8.50 s/n 005123 @2007 HydroCAD Software Solutions LLC Page 12 Pond 7P: Pond 2 Hydrograph ¦ Inflow ¦ Primary N w V 3 O LL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours) Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr - 24 hr Rainfall=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 HydroCAD® 8.50 s/n 005123 © 2007 HydroCAD Software Solutions LLC Page 13 Summary for Pond 8P: Ouffall 1 [40] Hint: Not Described (Outflow= Inflow) Inflow Area = 8.300 ac, 0.00% Impervious, Inflow Depth > 0.97" for 1 yr - 24 hr event Inflow = 1.80 cfs @ 13.30 hrs, Volume= 0.673 of Primary = 1.80 cfs @ 13.30 hrs, Volume= 0.673 af, Atten= 0%, Lag= 0.0 min Routing by Stor-Ind method, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs Pond 8P: Outfall 1 Hydrograph ¦ Inflow ¦ Primary 3 0 U. 1I 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours) Belgate - Southern Tract SWMP Charlotte 24-hr 1-yr 24.00 hrs 1 yr- 24 hr Rainfal1=2.58" Prepared by Kimley-Horn and Associates, Inc. Printed 10/27/2008 HydroCAD® 8.50 s/n 005123 @2007 HydroCAD Software Solutions LLC Page 14 Summary for Pond 9P: Outfall 2 [40] Hint: Not Described (Outflow= Inflow) Inflow Area = 30.330 ac, 0.00% Impervious, Inflow Depth > 0.19" for 1 yr - 24 hr event Inflow = 1.43 cfs @ 12.52 hrs, Volume= 0.489 of Primary = 1.43 cfs @ 12.52 hrs, Volume= 0.489 af, Atten= 0%, Lag= 0.0 min Routing by Stor-Ind method, Time Span= 0.00-24.00 hrs, dt= 0.05 hrs Pond 9P: Outfall 2 Hydrograph ¦ Inflow ¦ Primary 1 w v 3 0 LL 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time (hours)