HomeMy WebLinkAboutNC0022406_Extension Request Approval_20170818Water Resources
Environmental Quality
August 18, 2017
Ed Sullivan
Duke Energy
526 South Church Street
Mail Code EC13K
Charlotte, North Carolina 28202
ROY COOPER
Governor
MICHAEL S. REGAN
Secretary
S. JAY ZIMMERMAN
Director
Subject: Belews Creek Steam Station Interim Action Plan Schedule Updates — Request for
Extension of Milestone Dates
Dear Mr. Sullivan:
The North Carolina Department of Environmental Quality (DEQ) received your request for
extension of the deadlines for completing the interim actions at the Belews Creek Steam Station
letter dated July 17, 2017 (attached). DEQ is hereby approving the request for extension. DEQ
understands that, meeting the milestone dates is contingent upon several things including issuance
of NPDES permits, permitting through other agencies, and DEQ review and comment on
additional submitted Basis of Design reports.
In the letter, Duke assumes that DEQ will review and return comments to the Basis of Design
packages within 10 business days. Please note that there are no regulatory requirements for
timeframes to review these documents and that DEQ may require additional time to review and
provide comments. The proposed schedules do not anticipate additional submittals after comments
are received for the 100% Basis of Design. However, DEQ will review and may provide comments
on the 100% Basis of Design package, which may require additional submittal(s) to address any
concerns. If the anticipated milestone dates in this request are altered, please inform the DEQ
Winston-Salem Regional Office and Central Office via email, documenting the reasons for any
changes.
If you have any questions, please feel free to contact Shuying Wang (Winston-Salem Regional
Office) at (336) 776-9800 or Steve Lanter (Central Office) at 919-807-6444.
State of North Carolina I Environmental Quality I Division of Water Resources
Water Quality Regional Operations Section
1636 Mail Service Center I Raleigh, North Carolina 27699-1636
919-707-9129
Sincerely,
S. ay 'mmerman, P.G., Director
Division of Water Resources
Attachment: Interim Action Plan Schedule Update — Belews Creek Steam Station letter from
Duke Energy dated July 17, 2017
cc: WSRO WQROS Regional Office Supervisor
WQROS Central File Copy
Page 2 of 2
DUKE
ENERGY.
July 17, 2017
Mr. S. Jay Zimmerman, Director
Division of Water Resources
North Carolina Department of environmental Quality
1611 Mail Service Center
Raleigh, North Carolina 27699-1611
Subject: Interim Action Plan Schedule Update
Belews Creek Steam Station
Dear Mr. Zimmerman:
526 South Church Street:
Mail Code EC13K
Charlotte, North Carolina 28202
980.373.3719
In a letter dated March 28, 2017, DEQ documented acceptance of Duke Energy's milestone
schedules for the Accelerated Remediation sites submitted in February 2017. In that letter DEQ
stated that, "If the anticipated milestone dates in this request are altered, please inform the
appropriate DEQ Regional Office and Central Office via email, documenting the reasons for any
changes:'
Duke Energy is providing the enclosed updated schedule for the Belews Creek project to
formally request schedule extension. The schedule has been adjusted for the following two
items:
1) the extended DEQ review period for the 60% Basis of Design,
2) uncertainty with timing of NPDES permit modifications that are required to complete
start-up of the systems.
If you have comments and/or questions, please direct them to me at 980-373-3719.
Sincerely,
D. Edwin M. Sullivan, PE
Director— Waste & Groundwater Programs
Environmental, Health & Safety
Enclosure: Interim Action Plan Schedule Updates - Belews Creek Steam Station
Cc: Jim Wells — Duke Energy
Enclosure
Belews Creek Steam Station
Interim Action Plan Schedule Update to DEQ
July 17, 2017
• 30% Design Submitted to DEQ
• 60% Design Submittal to DEQ
(DEQ review comments received June 30, 2017)
• 100% Design Submittal to DEQ
• Final Regulatory Approvals for Construction
(includes 100% BOD, Well Recovery, E&SC, etc. excludes NPDES Permit Modification)
• Begin Extraction Well and Treatment System Construction
• NPDES Permit or DEQ Authorization Anticipated
• Extraction Well and Treatment System Begin Operation
Completed December 29, 2016
Completed March 31, 2017
September 22, 2017
October 13, 2017
October 20, 2017
November 1, 2017
January 26, 2018
Note: For scheduling purposes and as directed by DEQ in the January 30, 2017 conference call, we assume DEQ will review and return
comments to the Basis of Design packages within 10 business days. Extraction Well and Treatment System operation schedule is
contingent upon receipt of the NPDES permit modification or other DEQ authorization to direct the extracted groundwater into the ash basin
on or before the anticipated date. The current schedule does not anticipate additional submittals after comments are received for the 100%
BOD (i.e. any additional required submittals after 100% BOD will delay the anticipated start date.)