From:Herndon, T. Mason
Sent:Monday, August 07, 2017 11:23 AM
To:Lane, Stephen; Shaver, Brad ; Steenhuis, Joanne
Subject:Brunswick Bridge 13 Dolphin Repairs
Attachments:B 13 Brunswick Bridge 13 Dolphin Repairs.pdf
NCDOT Bridge Inspectors have found critical issues with the dolphins on the Holden
Beach Bridge fender system that need immediate attention. Per their findings the SE
Dolphin has 5 broken piles, the NW Dolphin has 1 broken pile and 1 pile that is hollow
with just a ¾” shell and the SW Dolphin has 1 broken pile. The NCDOT Ferry
Maintenance Crew is currently working at Fort Fisher and when they finish, we are
proposing to have them mobilize to this site and replace the 8 dolphin piles listed
above. We are anticipating that this will occur in a couple of weeks.
Attached is a copy of the report which includes a location map and sketch of the
bridge. Please let me know if we need anything from your respective agencies to
proceed.
Thanks!
Mason Herndon
Environmental Program Supervisor
Division 3
NCDOT- Division of Highways
910-341-2036 office
910-604-0050 mobile
tmherndon@ncdot.gov
5501 Barbados Blvd
Castle Hayne, NC 28429
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.
1