HomeMy WebLinkAbout20170922 Ver 1_ Todd's COE Screech Owl Field Notes 20170725_20170725Date: July 25,2017
Meeting Type: Preliminary (Post -Contract) Field Review
Site Name: Screech Owl
Provider: NCDMS/RES
Action ID:
County: Alamance
Attendees
Todd Tugwell, USACE
Kim Browning, USACE
Mac Haupt, DWR
Jeff Shaeffer, DMS
Lindsay Crocker, DMS
Melonie Allen, DMS
George Lankford
Brad Breslow, RES
Daniel Ingram, RES
Travis Wilson, WRC
Notes from Field Review
• Planting plan calls for natural recruitment
• Upper end of G2 is marginally jurisdictional, not eligible for credit until at least lower
intermittent or perennial; however, if included, it may justify slightly higher ratio (5:1. Vs.
7.5:1) on perennial stream down the same trib.
• E2 reaches on site are already in good condition. Maybe 7.5:1 ratio due to limited buffer
improvement.
• Need to have County PM done JD
• Area above gas pipeline is not E2 at 2.5:1 or even 5:1. Maybe 7.5:1.
• Wetland restoration hydrology in 2 zones. On slope 8-10%, n flats 10-12%
• Existing wetland near stream is alr already JD
• No cattle access to any streams on site currently
• E1 at bottom was ok.
• E1 in mid -channel are was ok, except probably too long. Only ok in old pon bed area.
• RES to submit modified basic concept plan for review and to justify proposed ratios. Will
probably ask for 5:1 on all E2 reaches but this would be too high in my opinion due to
current conditions which are relatively high functioning.