HomeMy WebLinkAbout20141219 Ver 2_SUP 2013-003 Amendment 4 North dune at the New Inlet bridge site on PINWR_20150112
Carpenter,Kristi
From:Willis, Thomas C
Sent:Monday, January 12, 2015 9:09 AM
To:Ward, Garcy; tracey.l.wheeler@usace.army.mil; Daisey,
Greg
Subject:FW: SUP 2013-003 Amendment 4: North dune at the
New Inlet bridge site on PINWR
Attachments:SUP2013003 Amendment 4.pdf
Garcy,
I did not see you on this email list, so I am forwarding the USFWS amended SUP
for the dune placement on the north side of New Inlet.
Let me know if you guys need anything else. The contractor (Barnhill) is
currently working on the south side of the inlet and they plan to be completed by
the end of this week. If there is any way you all could give me a time frame on
when you think your permit modification might be available, I can then let the
contractor know. They were hoping to move from the south side to the north, but
if it is going to be a couple weeks before approval, then they will likely need to
move their equipment of site.
Thanks,
Clay
From: Stewart, Dennis \[mailto:dennis_stewart@fws.gov\]
Sent: Friday, January 09, 2015 9:43 AM
To: Jennings, Jerry D; Willis, Thomas C; Wheeler, Tracey L SAW; Daisey, Greg;
Brittingham, Cathy; Gary Jordan
Cc: Rochelle, Rodger D; Steve Thompson; Pete Benjamin; Scott Lanier; Mike
Bryant; Elizabeth Souheaver
Subject: SUP 2013-003 Amendment 4: North dune at the New Inlet bridge site
on PINWR
The attached letter is an amendment to Special Use Permit # 2013-003 issued for
the purpose of constructing a replacement bridge in the place of the temporary
bridge at New Inlet on Pea Island National Wildlife Refuge. Please forward to
anyone I may have inadvertently omitted. Call if you have questions.
Dennis
Dennis Stewart
Refuge Biologist
Alligator River National Wildlife Refuge
Pea Island National Wildlife Refuge
(252) 473-1132 x231 (252) 475-0962 (cell)
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.