From:Willis, Thomas C
Sent:Friday, December 19, 2014 8:58 AM
To:tracey.l.wheeler@usace.army.mil; Ward, Garcy; Daisey,
Greg
Cc:Brittingham, Cathy; Dennis_Stewart@fws.gov
Subject:additional proposed dune construction on the
Northside of New Inlet
Attachments:NorthSide_DuneWork_NewInlet.pdf
Tracey, Garcy and Greg,
Our maintenance department decided they wanted to put a dune on the north side of
New Inlet. I will be requesting a modification of CAMA Major 104-11 for this dune
project. The alignment is shown on the attached aerial. I will revise the New Inlet Bridge
drawings, as I did for the south side. This area was claimed as jurisdictional surface
waters during the previous jurisdictional call, therefore, the proposed dune alignment
will result in an additional 0.2 acres of surface water impact. This will bring the total
surface water impacts up to approximately 0.47 acres. However, this area is currently all
filled in with sand. I wanted to know if you all needed to meet in the field to discuss
anything and also, do we need the Mean High Water marked. If we need the MHW
marked, I assume the COE will determine that based on the wet sand line. Please, let me
know, so we can schedule a time that works for everyone. If not, I can go ahead and put
the request together and send it out. Dennis Stuart with the refuge is okay with us
extending the temporary easement on this side for the dune, and will be sending out an
authorization letter, after Christmas.
Thanks,
Clay