HomeMy WebLinkAbout20190397_R-2566 Merger CP 4A Packet 7-19-17_revised_20170719NEPA/404 MERGEx CoNcuxx�NCE PoiNT 4A
TIP PROJECT R-2566B
WBS 37512.1.5
FEDE�L AID NUMBEx NHPP-O 150(004)
NC 105 IMPROVEMENTS FROM CLARKS CREEK ROAD (SR 1136) TO
NC 105 BYPASS (SR 1107) IN BOONE
WATAUGA COUNTY
SUMMARY INFORMATION
Meeting Purpose
The purpose of this meeting is CP 4A — To identify avoidance and minimization efforts.
Project Description
The North Carolina Department of Transportation (NCDOT) proposes to improve a 5.5-mile section of
NC 105 from Clarks Creek Road (SR 1136) to the NC 105 Bypass (SR 1107) in Boone, Watauga County.
Project R-2566B is included in the draft 2017-2028 State Transportation Improvement Program (STIP).
• Project R-2566B: Right of Way acquisition is currently scheduled to begin in Fiscal Year (FY)
2023, and construction is scheduled to begin in FY 2025.
• Project R-2566BA: Right of Way acquisition is scheduled for FY 2018, and constnxction is
scheduled to begin in FY 2019.
Merger History of Project
Concurrence Point 1
At a meeting in August 2014, the Merger team agreed on the logical termini and purpose and need for
Project R-2566B:
• Congestion: A primary purpose of the project is to reduce congestion on NC 105 in order to
achieve level of service (LOS) D or better in the design year (2040) during the average highest
week day, and to achieve LOS E or better in the design year during the average highest weekend
day.
NC 105 is used heavily by commuters during the week, but also is used by tourists and locals
visiting recreational sites on the weekends. The congestion goals for this project were chosen to
address the needs of commuters (LOS D during the week), but also to try to ensure that the road
didn't experience failure during the busy tourist times (LOS E on the weekends).
• Safety: Another primary purpose is to reduce rear-end and run-off-road crashes on NC 105.
Alternatives were analyzed using Highway Safety Manual methodologies.
• Bicycle Facilities: A secondary purpose is to improve bicycle facilities on NC 105 in areas where
capacity or safety improvements are proposed.
R-2566B CP 4A Meeting Packet 1 July 19, 2017
Page 2 Updated 7/19/17
Concurrence Point 2
At a meeting in August 2014, the Merger team agreed to carry forward a`Best-Fit Build Alternative" for
Project R-2566B, in addition to carrying forward the No Build Alternative.
Concurrence Point 2A
At a meeting in October 2015 (with final signatures in November 2015), the Merger team agreed to on the
following major drainage structures:
• Site 1— Remove and replace existing bridge over the Watauga River to 260' L X 90' W
• Site 2— Remove and replace existing culvert carrying a UT to Laurel Fork to 1@ 8'x6' RCBC
• Site 4— Remove and replace existing culvert carrying a UT to Laurel Fork to 1@ 8'x6' RCBC
• Site 6— Remove and replace existing culvert carrying a UT to Laurel Fork to 2@ 12'x7' RCBC
• Site 7a — On private property; more study recommended
• Site 7b — On private property; more study recommended
Concurrence Point 3
At a meeting in March 2017, the Merger team agreed to select the Best-Fit Build Alternative as the
LEDPA for Project R-2566B.
Typical Section
The design presented at the public hearing and shown on the attached figures includes the following
elements:
• No improvements are recommended for 1 mile along the project corridor from Clark's Creek
Road to Old Shull's Mill Road because traffic is anticipated to operate at acceptable levels of
service in the future design year (2040) on that section.
• Improvements are recommended for approximately 4.5 miles from Old Shull's Mill Road to
NC 105 Bypass, based on future traffic operations and safety concerns.
o The approximately 1.7-mile section between Old Shull's Mill Road and Broadstone Road
will consist of three 12-foot lanes (two southbound, one northbound) with 6-foot wide
paved shoulders on both sides.
o The approximately 2.8-mile section between Broadstone Road and NC 105 Bypass will
consist of four 12-foot lanes, a 23-foot wide raised median, and 6-foot wide paved
shoulders on both sides.
o The two intersections where Old Shull's Mill Road tees into NC 105 have safety
concerns due to the horizontal skew and limited sight distance at the intersection. To
address these issues, the southern intersection of Old Shull's Mill Road at NC 105 will be
realigned, and the northern intersection of Old Shull's Mill Road at NC 105 will be
closed.
Project Status/Schedule
Environmental Assessment
Public Hearing
Finding of No Significant Impact
Signed September 2016
November 7, 2016
Fa112017
R-2566B CP 4A Meeting Packet 2 July 19, 2017
Concurrence Point 4A — Avoidance and Minimization
General Avoidance and Minimization Efforts
To minimize or avoid impacts, the following issues were evaluated:
• Horizontal and vertical alignment shifts
• Slopes and right of way
• Construction techniques
• Bridge design
The typical section varies along the project corridor, and was selected so that the project would meet the
purpose and need of the project with the minimal footprint feasible. Of the 5.5-mile corridor studied, this
resulted in 1.7 miles of 3-lane road, 2.8 miles of 4-lane divided road, and 1 mile with no improvements.
Snecific Avoidance and Minimization Efforts
In addition, the following specific avoidance and minimization measures were included in the design and
noted on the attached figures (those noted with an * are related to the section just south of Broadstone
Road, which is an area of particular concern).
� Selected a best-fit alignment that minimizes impacts to Watauga River, Laurel Fork, and Big
Branch. The design widens asymmetrically into the mountain in the following locations to avoid
impacts to the streams:
o Sta 245+00 to Sta 252+80*
o Sta 256+40 to Sta 284+00
o Sta 307+00 to Sta 311+00
Added retaining walls and concrete barriers to further reduce impacts to streams. The design
includes retaining walls in the following locations:
o Sta 213+80 to Sta 214+87
o Sta 224+70 to Sta 227+90
o Sta 230+50 to Sta 234+10
o Sta 239+00 to Sta 243+50*
o Sta 251+70 to Sta 252+80*
o Sta 352+20 to Sta 358+00
o Sta 360+00 to Sta 365+00
Used steeper slopes to minimize or avoid impacts to streams at the following locations:
o Sta 243+50 to Sta 251+70 — Widened into the mountain using 0.75:1 cut slope*
o Sta 309+00 — 1.5:1 cut slope
o Sta 340+50 to Sta 341+50 — 1:1 cut slope
Individual stream and wetland impacts are shown on the attached figures and listed in Tables 1 and 2.
R-2566B CP 4A Meeting Packet 3 July 19, 2017
Avoidance and Minimization Commitments
Geotechnical survey and final designs are not yet available, and a work zone traffic control plan has not
been developed. Therefore, specific avoidance and minimization measures will be addressed in CP 4B
and 4C meeting. NCDOT proposes that the following commitments be included in the CP 4A agreement:
• Retaining walls will be built between NC 105 and the Watauga River, where feasible, from
Station 239+00 to Station 252+80. If retaining walls are not feasible in this section, the Merger
Team will revisit CP 4A.
• Permanent construction (retaining walls and pavement) and slope stakes will stay out of the 100-
year floodplain, floodway, and Watauga River.
• Where feasible, machinery will be placed outside of the floodplain, floodway, and Watauga River
between Station 239+00 and Station 252+80. The wark zone traffic control plan will investigate
potential to temporarily close lanes on NC 105 during this phase of construction.
• The USACE permit will include language restricting construction of Section BA until after the
Merger Team has reached concurrence on CP 4B and 4C for Section B. (Note, Section BA is not
anticipated to require CP 4B and 4C concurrence.)
Proposed Climbing Lane
NCDOT proposes extending the southbound climbing lane south of Broadstone Road for a distance of
approximately 5,000 feet. The existing southbound climbing lane is from station 180+00 to station
202+00 (2,200 feet). The proposed climbing lane is from station 178+00 to station 250+00 (7,200 feet).
NCDOT proposes this climbing lane to address a safety need. In addition, it helps bring the road up to
current design standards. These are summarized below, and additional supporting information is on pages
8-10 of this packet:
Existing and Future Conditions:
➢ Southbound NC 105 from Broadstone Road to Old Shull's Mill Road has a 4% upgrade with one
lane in each direction and no opportunities to add a passing zone. Due to the grade and truck
percentages, vehicles often must drive at below-posted speeds behind slower trucks. The resulting
degradation in traffic operations on the southbound section is a concern to NCDOT.
➢ As traffic volumes increase, this situation is expected to worsen.
Safety Need:
➢ NCDOT feels that a climbing lane in this section would improve safety by reducing the speed
differential between trucks and passenger vehicles. Climbing lanes have been shown to improve
safety on this type of facility.
➢ NCDOT also is concerned that narrowing from four lanes to two lanes at Broadstone Road
without providing a climbing lane for southbound traffic will result in vehicles making unsafe
maneuvers to try to avoid being behind large trucks on the 4% upgrade, which may translate into
accidents.
➢ The climbing lane could prevent congestion caused by accidents that may occur without it in
place. It also is anticipated to reduce delays for southbound vehicles by increasing the average
speed.
Design Standards:
➢ A southbound climbing lane is warranted based on AASHTO guidelines.
➢ When improving a road, it is NCDOT's standard practice to bring the road up to current design
standards to the extent practicable.
R-2566B CP 4A Meeting Packet 4 July 19, 2017
Table L Anticipated Stream Impacts
Stream Name Map ID Impacts* Minimization/ Figure
(linear ft) Avoidance Measure No.
Watauga River Watauga �** Asymmetrical Widening 1B, IC
River and Retaining Walls
UT to Watauga River SFU 37 1A
UT to Watauga River SFV 277 lA
UT to Watauga River SFW 92 1 A
UT to Watauga River SGD 150 1B
UT to Watauga River SGE 42 Retaining Wall 1 B
UT to Watauga River SGG 38 1B
UT to Watauga River SGH 107 1B
UT to Watauga River SGI 25 1B
UT to WataLiga River SGJ 42 Retaining Wall 1B
UT to Watauga River SGO 51 1 B
UT to Watauga River SGP 104 1B
UT to Watauga River SGS 71 1C
Laurel Forlc Laurel Fork 179 Asyminetrical Widening 1C, 1D,
and Retaining Walls 1 E, 1 F
UT to Laurel Fork SGT 76 1 C
UT to Laurel Fork SGU 54 1C
UT to Laurel Fork SGX ll 1 C
UT to Laurel Fork SGZ l45 1C
UT to Laurel Fork SHB 114 1 D
UT to Laurel Fork SHC 22 l D
UT to Laurel Fork SHK 142 lE
UT to Laurel Forl< SHO 9 1 E
UT to Laurel Fork SHW 209 lE
UT to Laurel Fork SHZ 36 lE
UT to Laurel Fork SIC 72 IE
UT to Laurel Forlc SID 5 lE
UT to Laurel Forlc SIF 13 Retaining Wall � E
UT to Laurel Fork SIG 258 1F
UT to Laurel Fork SIJ 18 1 F
Total 2,400
* Impacts based on a 25-foot buffer around the preliminary design slope stakes
** No impacts; included in table as part of the list of minimization and avoidance measures
R-2566B CP 4A Meeting Packet 5 July 19, 2017
Table 2. Anticipated Wetland Impacts
Map ID Impacts* (acres) Figure No. Minimization/
Avoidance Measure
WBZ 0.06 1 A
WCE 0.02 1B
WCF 0.02 1 B
WCG 0.03 1B
WCI 0.06 1B
WCK 0.05 1B
WCQ 0.03 1D
WCU 0.01 1 E
WCV 0.01 IE
WCX 0.02 lE
WDA < 0.01 1 E Retaining Wall
WDB < 0.01 1 F
WDC < 0.01 1 F
Total 0.31
* Impacts based on a 25-foot buffer around the prelimina�y design slope stakes
R-2566B CP 4A Meeting Packet 6 July 19, 2017
Section 404/NEPA Interagency Agreement
Concurrence Point 4A
Avoidance and Minimization Measures
Project Title: NC 105 Improvement from Clarks Creek Road to NC 105 Bypass
TIP Project No.: R-2566B
WBS No.: 37512.1.1
The Project Team has concurred on this date to use the following measures to minimize or avoid impacts.
The typical section varies along the project corridor, and was selected so that the project would meet the
purpose and need of the project with the minimal footprint feasible. Of the 5.5-mile corridor studied, this
resulted in 1.7 miles of 3-lane road, 2.8 miles of 4-lane divided road, and 1 mile with no improvements.
In addition, the following avoidance and minimization measures were included in the design:
Selected a best-fit alignment that minimizes impacts to Watauga River, Laurel Fork, and Big
Branch, including widening asymmetrically in several locations.
Added several retaining walls and concrete barriers to further reduce impacts to streams.
Used steeper slopes to minimize or avoid impacts in several locations.
The following commitments have been made, and will be discussed again at the CP 4B and 4C meetings:
• Retaining walls will be built between NC 105 and the Watauga River, where feasible, from
Station 239+00 to Station 252+80. If retaining walls are not feasible in this section, the Merger
Team will revisit CP 4A.
• Permanent construction (retaining walls and pavement) and slope stakes will stay out of the 100-
year floodplain, floodway, and Watauga River.
• Where feasible, machinery will be placed outside of the floodplain, floodway, and Watauga River
between Station 239+00 and Station 252+80. The work zone traffic control plan will investigate
potential to temporarily close lanes on NC 105 during this phase of construction.
• The USACE permit will include language restricting construction of Section B until after the
Merger Team has reached concurrence on CP 4B and 4C. (Note, Section BA is not anticipated to
require CP 4B and 4C concurrence.)
Name A�encv Date
n
USEPA
USACE
NCDOT
NCWRC
NCSHPO
7' �.
Discussion of Need for the Proposed Climbing Lane
WHAT: NCDOT proposes extending the southbound climbing lane south of Broadstone Road for a
distance of approximately 5,000 feet. The existing southbound climbing lane is from station 180+00 to
station 202+00 (2,200 feet). The proposed climbing lane is from station 178+00 to station 250+00 (7,200
feet).
WAY (Needs and Benefits): NCDOT proposes this climbing ]ane to address a safety need. In addition, it
helps bring the road up to current design standards.
Existing and Future Conditions:
➢ Southbound NC 105 from Broadstone Road to Old Shull's Mill Road has a 4% upgrade with one
lane in each direction and no opportunities to add a passing zone. Due to the grade and truck
percentages, vehicles often must drive at below-posted speeds behind slower trucks. The resulting
degradation in traffic operations on the southbound section is a concern to NCDOT.
➢ As traffic volumes increase, this situation is expected to worsen.
Safety Need:
➢ NCDOT feels that a climbing lane in this section would improve safety by reducing the speed
differential between trucks and passenger vehicles. Cliinbing lanes have been shown to improve
safety on this type of facility.
➢ NCDOT also is concerned that narrowing from four lanes to two lanes at Broadstone Road
without providing a cliinbing lane for southbound traffic will result in vehicles making unsafe
inaneuvers to try to avoid Ueing behind large trucks on the 4% upgrade, which may translate into
accidents.
➢ The cliinUing lane could prevent congestion catised by accidents that may occur without it in
place. It also is anticipated to reduce delays for soutlibound vehicles by increasing the average
speed.
Design Standards:
➢ A southbound climbing lane is warranted based on AASHTO guidelines.
➢ When improving a road, it is NCDOT's standard practice to bring the road up to current design
standards to the extent practicable.
Safety Need
NCDOT recommends a climbing lane to improve safety on NC 105.
A. Research on the safeiy beiaefits of climbing lanes:
The Highway Safety Manual (Uased on researched sponsored by FHWA) recominends a crasl�
modificarion factor of 0.75 (or a 25% reduction) for total crashes in both directions of travel tluoughout
the extent of the climbing lane where climbing lanes are warranted. Additional research sponsored by
Micl�igan DOT reports a crash reduction of 33°/o.
B. Reaso�is for the saf'ety benefits of'climbing lanes:
In areas where a passing zone is not feasible due to sight distance limitations, a cliinbing lane helps
reduce the speed differential between slow-moving trucics and other vehicles. It also helps linut tl�e
percent time vehicles spend following other vehicles. These two factors — the speed differential and the
percent time spent following — both can contribute to rear-end crashes.
R-2566B CP 4A Meeting Packet 8 June 23, 2017
C. If the climbing lane is extended but not all the way to Broadstone Road, it will create a relatively small
gap between the 4-lane section and the climbing lane. Having this gap may be counter to driver
expectations, resulting in increased safety concerns.
• This gap would require slower moving vehicles to make additional lane shifts which creates
additional conflicts.
• Leaving a gap may create a new safety situation which currently does not exist.
• If the project is built to include a gap between the Broadstone Road intersection and the climbing
lane, and if this design creates safety problems as anticipated, it would be difiicult to retroiit a
"iix" at a future time.
• Current congestion during peak periods constrains speeds and increases speed differentials
between vehicles. As congestion is reduced (by adding two more lanes north of Broadstone Road)
and speeds increase correspondingly, the differential of vehicle speeds between slow-moving
trucks and other traffic is likely to also increase. As a result, the likelihood of accidents increases.
D. Crash data for this corridor.•
Traffic volumes from 2003-2008 were similar to projected 2040 traffic volumes. Traffic volumes
decreased in the 2008-2014 period.
➢ There were 43% more crashes and only 20% more vehicles during the 2003-2008 period
compared to the 2009-2014 period. If traffic volumes increase in future years, as
projected, it is reasonable to expect that crashes would increase by a similar rate as
experienced in the past. The relationship between traffic volumes and traffic crashes is
often not linear, particularly as a roadway approaches capacity.
➢ During the 2003-2008 period, the total crash rate, non-fatal injury crash rate, and wet
crash rate exceeded the critical crash rate.
Several specific deficiencies on NC 105 contribute to crashes:
➢ The paved shoulder is narrow (1-2 feet). Improving the clear zones would give vehicles
who depart the road an opportunity to recover or stop without crashing, and may reduce
the number of rear end crashes by providing space to maneuver if drivers encounter a
stopped vehicle unexpectedly.
➢ There are some horizontal and vertical curves that limit sight distance, both along NC
105 and at some intersections. This is particularly dangerous in areas with a high number
of rear end crashes that involve vehicles stopped in the through lanes waiting to turn left.
➢ Scattered development and driveway frequency contributes to the pattern of rear end
crashes. Along NC 105, many businesses have pull-in parking, multiple driveways, or
open frontage that allows vehicles to enter into the parking lot along the entire property
length.
The majority of crashes were in the southbound direction (updated data, 2/1/11 — 1/31/16).
➢ 66% of the crashes from just south of the NC lOSBroadstone Road intersection to the
approximate end of the current climbing lane occurred in the southbound direction.
➢ Discounting animal crashes, the percentage is 75%.
R-2566B CP 4A Meeting Packet 9 June 23, 2017
Operation and Design Standards for Adding a Climbin� Lane
NCDOT proposes a climbing lane to address three operational and design concerns.
.9. The cliirabif7g lane is ��arrayited based ora AASHTO guideli�2es. NCDOT follows AASHTO
recomnaenciations to the extent practicable. It is wa����ara�ted based on t�l�e following three cr�iteria (listed ora
page 3-127 of the AASHTO Green Book):
Overall volume criteria:
o Thr�eshold: Warranted if there are a total of 200 vehicles per hour (vph) up-grade.
o Project.• The traffic forecast projects 740 vph in the 2040 Build scenario.
Truck volume criteria:
o Threshold: Warranted if fl�ere is an up-grade truck flow rate of 20 trucics per hour.
o P��oject.� The traffic forecast projects 6°/o trucks (4% duals + 2% TTSTs), for a total of 45
trucks in the 2040 Build scenario (15 TTST + 30 duals). Major sonrces of trucks along
the corridor include the quarry, concrete plant, and asphalt plant.
Speed or level of service (LOS) reduction criteria:
o Thresholcl: Warranted if tl�ere is either (a) 10 mph reduction in speed for heavy truclzs, or
(b) LOS E or F on the grade, or (c) reduction of LOS by two or inore levels.
o Project: The average upgrade from Broadstone to Old Schull's is 4% for 5400 feet. Per
AASHTO (Figure 3-28) this shows an anticipated reduction ii1 speed approaching 25
mph.
B. The climbing lane will aid ilz climbing sight distance for southbour�d traffic.
Stopping Sight Distance requirements have been met through the climbing lane section. The
minimum stopping sight distance for horizontal and vertical curves is 495' for posted speed of 55
mph and 570' for design speed of 60 mph.
o The horizontal alignment through this section meets a 60 mph design speed except from
station 185+17 to 191+77, where it meets the 55 mph posted speed reqLiireinents. This
radius was not flattened to minimize impacts and higher cost due to associated extensive
cut into the inountainside.
o The vertical alignment through this section meets a 60 mph design speed except from
station 185+20 to 194+25, where it ineets the 55 mph posted speed requirernents. The
grade was not changed tlle additional 1`/z feet necessary to minimize ii�pacts and higher
project costs due to associated fills and right of way impacts.
Passing Sight Distance is not met. The passing lane will aide traffic safety in the southbound
direction.
C. The existiizg cliinbing layie may be underutilized.
• It is likely that the existing climbing lane may be �mderutilized because drivers of slow-moving
vehicles have difficulry �nerging back into faster traffic that has accuinulated behind. Due to the
short length of the cliinbing lane, accuinulated traffic may not have had sufficient distance to pass
the slow-inoving vehicles when the cliinbing lane ends.
R-2566B CP 4A Meeting Packet 10 June 23, 2017