Loading...
HomeMy WebLinkAbout20170426 Ver 1_More Info Letter_20170601ROY COOPER Governor r1o. MICHAEL S. REGAN Secretary S. JAY ZIMMERMAN Director Water Resources Environmental Quality June 1, 2017 DWR # 20170426 Buncombe County Duke Energy Attn: Steve Cahoon 411 Fayetteville St Raleigh NC 27601 Subject: REQUEST FOR ADDITIONAL INFORMATION Asheville Combined Cycle Project Laydown Area Dear Mr. Cahoon: On April 7, 2017, the Division of Water Resources — Water Quality Programs (Division) received your application dated March 30, 2017, requesting an Individual Water Quality Certification from the Division for your project. The Division has determined that your application is incomplete and cannot be processed. The application is on -hold until all of the following information is received: Section 6.2.1 of the application document states that "Laydown area 3, with impacts, will provide approximately 5.9 acres of usable area". It also states that "The proposed impacts... within Laydown Area 3 are necessary for establishing the basin and piping, while site grading is required to provide a suitably sized pad to accommodate laydown material and equipment. Please provide plans/sketches that visually show the final layout of the site, including any sediment and erosion control measures and/or post construction stormwater measures that will be required by the local government. [15A NCAC 02H .0502(b)] 2. Please provide a detailed engineering plan, profile view, and cross-section of all proposed culverts. These drawings must include details regarding stream alignment in relation to pipe alignment, pipe slope, pipe burial, and any dissipater pads that may be required by the sediment and erosion control authority. [15A NCAC 02H .0502(b)] 3. All work must be done "in the dry" to protect downstream water quality, therefore dewatering methods will be necessary to temporarily dewater the stream channel and pond during pipe installation. Please provide a construction sequence that details the method of dewatering to be utilized at the site and the sequence of construction events to be followed to ensure compliance with this condition. In addition, please ensure that the location of the temporary impacts are shown on the construction drawings and clearly indicated in the revised impact table. [15A NCAC 02H .0502(b)(3)]. State of North Carolina I Environmental Quality 450 W. Hanes Mill Road, Suite 300, Winston-Salem, North Carolina 27105 Phone: 336-776-98001 FAX: 336-776-9797 Duke Energy DWR# 20170426 Request for Additional Information Page 2 of 2 4. The classification of Stream 22 as "intermittent" must be verified by the Division. Please contact Zan Price, Assistant Regional Supervisor — Asheville Regional Office, 828 296 4662 or zan.price@ncdenr.gov to schedule a site visit. 5. If the U.S. Army Corps of Engineers requests a response to any comments received as a result of the Public Notice, please provide the Division with a copy of your response to the USACE. [15A NCAC 02H .0502(c)] Pursuant to Title 15A NCAC 02H .0502(e), the applicant shall furnish all of the above requested information for the proper consideration of the application. If all of the requested information is not received in writing within 30 calendar days of receipt of this letter, the Division will be unable to approve the application and it will be returned. The return of this project will necessitate reapplication to the Division for approval, including a complete application package and the appropriate fee. Please respond within 30 calendar days of receipt of this letter by submitting all of the above requested information through this link: https://edocs.deg.nc.gov/Forms/Supplemental-Information-Form. Please note that the DWR# that is requested on the link is referenced above. Please be aware that you have no authorization under the Water Quality Certification Rules for this activity and any work done within waters of the state may be a violation of North Carolina General Statutes and Administrative Code. Please contact me at 336-776-9693 or Sue.Homewood@ncdenr.gov if you have any questions or concerns. Sincerely, Sue Homewood Winston-Salem Regional Office cc: Dicky Harmon, Amec Foster Wheeler Environment & Infrastructure Inc (via email) David Brown, USACE Asheville Regulatory Field Office (via email) DWR ARO 401 files DWR 401 & Buffer Permitting Unit