From: Steffens, Thomas A CIV USARMY CESAW (US) <Thomas.A.Steffens@usace.army.mil>
Sent: Tuesday, May 30, 2017 11:50 AM
To: Yeung, Hon F
Cc: Ward, Garcy
Subject: RE: Beaufort 110
Hon,
You have my verbal/email approval to start work on Beaufort 110. As discussed, the increase in impacts from 144 In ft to
163 In ft would normally trigger the threshold for mitigation (>/= to 150 In ft); in this case, I have waived that
requirement. I based that waiver on the fact the feature will remain open and not piped as originally planned and will
provide an opportunity for some storm water treatment.
As such, you may proceed with work and the revised permit will follow. See you onsite at 1300; Thursday 01 June 2017.
Thomas Steffens
Regulatory Project Manager
Washington Regulatory Field Office
2407 West 5th Street
Washington, NC 27889
o) (910)-251-4615
The Wilmington District is committed to providing the highest level of support to the public. We would appreciate your
feedback on how we are performing our duties. Our automated Customer Service Survey is located here:
http://corpsmapu.usace.army.mil/cm_apex/f?p=136:4:0
-----Original Message-----
From: Yeung, Hon F [mailto:hfyeung@ncdot.gov]
Sent: Friday, May 26, 2017 2:31 PM
To: Steffens, Thomas A CIV USARMY CESAW (US) <Thomas.A.Steffens@usace.army.mil>
Subject: [Non-DoD Source] Beaufort 110
To m,
Hope you are doing well. Glad to see you not having to wear a boot anymore and I hope you recover 100% soon. Just
wanted to follow up with you on Beaufort 110. Jay and I discussed with you in person about 2 weeks ago. The situation
is that the stream impact went from 144 LF to 163 LF due to the open ditch revision in lieu of the drainage pipes. Jay
forwarded to you the new plans and drawings through email. Do you need further info from me? If not, can we get a
verbal approval from you and wait for the actual permit? The Contractor is trying to start work on 6/1. I know this is
rushing and I apologize. Please let me know if I could be of further assistance.
Thank you,
Hon F. Yeung, PE
Division Project Engineer
Division of Highways - Division 2
North Carolina Department ofTransportation
(252) 439-2827 office
(252) 714-9189 mobile
hfyeung@ncdot.gov <mailto:hfyeung@ncdot.gov>
105 Pactolus Highway NC 33
PO Box 1587
Greenville, NC 27835-1587
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Facebook <Blockedhttps://www.facebook.com/NCDOT> Twitter <Blockedhttp://ncdot.gov/travel/twitter/> YouTube
<Blockedhttps://www.youtube.com/user/NCDOTcommunications>
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.