HomeMy WebLinkAbout20170073 Ver 1_Approval Letter_20170530May 30, 2017
Camp Davis Industrial Park
Attn: Mr. Thomas C. Rollins
P 0 Box 38
Holly Springs, NC 28445
ROY COOPI R
MICL A L. SRI GAN
S. .IAA L11NINIL:R.MA
DWR # 17-0073
Onslow County
Subject: Approval of Individual 401 Water Quality Certification with Additional Conditions
Camp Davis Industrial Park Phases I & II
USACE Action ID. No. SAW -2013-02417
Dear Mr. Rollins:
Attached hereto is a copy of Certification No. 4118 issued to Mr. Thomas C. Rollins and Camp Davis
Industrial Park, dated May 30, 2017. Please note that you should get any other federal, state or
local permits before proceeding with the subject project, including those required by (but not
limited to) Sediment and Erosion Control, Non -Discharge, and Water Supply Watershed
regulations.
This approval and its conditions are final and binding unless contested. This Certification can be
contested as provided in Articles 3 and 4 of General Statute 150B by filing a written petition for an
administrative hearing to the Office of Administrative Hearings (hereby known as OAH) within sixty
(60) calendar days.
A petition form may be obtained from the OAH at http://www.ncoah.com/ or by calling the OAH
Clerk's Office at (919) 431-3000 for information. A petition is considered filed when the original
and one (1) copy along with any applicable OAH filing fee is received in the OAH during normal
office hours (Monday through Friday between 8:00am and 5:00pm, excluding official state
holidays).
The petition may be faxed to the OAH at (919) 431-3100, provided the original and one copy of
the petition along with any applicable OAH filing fee is received by the OAH within five (5) business
days following the faxed transmission.
State of North Carolina I Environmental Quality I Water Resources
1617 Mail Service Center I Raleigh, North Carolina 27699-1617
919 807 6300
Camp Davis Industrial Park
DWR# 17-0073
Individual Certification #4118
Page 2 of 7
Mailing address for the OAH:
If sending via US Postal Service: If sending via delivery service (UPS, FedEx, etc):
Office of Administrative Hearings Office of Administrative Hearings
6714 Mail Service Center 1711 New Hope Church Road
Raleigh, NC 27699-6714 Raleigh, NC 27609-6285
One (1) copy of the petition must also be served to Department of Environmental Quality:
William F. Lane, General Counsel
Department of Environmental Quality
1601 Mail Service Center
Raleigh, NC 27699-1601
Unless such a petition is filed, this Certification shall be final and binding.
This certification completes the review of the Division under section 401 of the Clean Water Act
and 15A NCAC 02H .0500. Please contact Robb Mairs at 910-796-7427 or robb.mairs@ncdenr.gov
or Jennifer Burdette at 919-807-6364 or jennifer.burdette@ncdenr.gov if you have any questions
or concerns.
Sincerely,
Karen Higgins, Supe visor
401 & Buffer Permitting Branch
cc: Dana Lutheran, Southern Environmental Group, Inc. (via dlutheran@segi.us)
USACE Wilmington Regulatory Field Office
Todd Bowers, EPA (via bowers.todd@epa.gov)
DWR WiRO 401 file
DWR 401 & Buffer Permitting Branch file
Filename: 170073CampDavislndustrialPark(Onslow)_401_IC_.docx
Camp Davis Industrial Park
DWR# 17-0073
Individual Certification #4118
Page 3 of 7
NORTH CAROLINA 401 WATER QUALITY CERTIFICATION
CERTIFICATION #4118 is issued in conformity with the requirements of Section 401, Public Laws
92-500 and 95-217 of the United States and subject to North Carolina's Regulations in 15A NCAC
02H .0500, to Mr. Thomas C. Rollins and Camp Davis Industrial Park, who have authorization for
the impacts listed below, as described within your application received by the N.C. Division of
Water Resources (Division) on January 19, 2017 and subsequent information on April 18, 2017 and
May 26, 2017, and by Public Notice issued by the U. S. Army Corps of Engineers and received by
the Division on February 17, 2017.
The State of North Carolina certifies that this activity will not violate the applicable portions of
Sections 301, 302, 303, 306, 307 of the Public Laws 92-500 and PL 95-217 if conducted in
accordance with the application, the supporting documentation, and conditions hereinafter set
forth.
This approval requires you to follow the conditions listed in the certification below.
Conditions of Certification:
Impacts Approved
The following impacts are hereby approved provided that all of the conditions of the
Certification are met. No other impacts are approved, including incidental impacts. [15A
NCAC 02B .0506(b) & (c)]
Type of Impact
Amount Approved (units)
Permanent
Amount Approved (units)
Temporary
404/401 Wetlands
0.41 (acres)
0 (acres)
Open Water
3.53 (acres)
0 (acres)
2. Stormwater Management Plan
You are required to obtain a stormwater management plan (SMP) approval letter from the
Division of Energy, Mining and Land Resources (DEMLR) before any impacts authorized in this
certification occur. After it is approved, the SMP may not be modified without prior written
authorization from DEMLR. [15A NCAC 02H .0506(b)(5) & (c)(5)]
3. No waste, spoil, solids, or fill of any kind shall occur in wetlands, waters, or riparian areas
beyond the footprint of the impacts depicted in the application for this project. All
construction activities, including the design, installation, operation, and maintenance of
sediment and erosion control Best Management Practices shall be performed so that no
violations of state water quality standards, statutes, or rules occur. Approved plans and
specifications for this project are incorporated by reference and are enforceable parts of this
certification. [15A NCAC 02H .0501 and .0502]
Camp Davis Industrial Park
DWR# 17-0073
Individual Certification #4118
Page 4 of 7
4. Sediment and Erosion Control
Erosion and sediment control practices must be in full compliance with all specifications
governing the proper design, installation and operation and maintenance of such Best
Management Practices. If applicable, the project must comply with the specific conditions
and requirements of the NPDES Construction Stormwater Permit issued to the site and the
following requirements [15A NCAC 02H .0506(b)(3) and (c)(3)1:
Design, installation, operation, and maintenance of the sediment and erosion control
measures must be such that they equal or exceed the requirements specified in the
most recent version of the North Carolina Sediment and Erosion Control Manual. The
devices shall be maintained on all construction sites, borrow sites, and waste pile
(spoil) projects, including contractor -owned or leased borrow pits associated with the
project.
b. For borrow pit sites, the erosion and sediment control measures must be designed,
installed, operated, and maintained in accordance with the most recent version of
the North Carolina Surface Mining Manual.
c. Reclamation measures and implementation must comply with the reclamation in
accordance with the requirements of the Sedimentation Pollution Control Act and the
Mining Act of 1971.
d. Sufficient materials required for stabilization and/or repair of erosion control
measures and stormwater routing and treatment shall be on site at all times.
e. The sediment and erosion control designs must comply with the requirements set
forth in 15A NCAC 04B .0124 Design Standards in Sensitive Watersheds.
5. Sediment and erosion control measures shall not be placed in wetlands or waters.
Exceptions to this condition require application submittal to and written approval by the
Division. If placement of sediment and erosion control devices in wetlands and waters is
unavoidable, then design and placement of temporary erosion control measures shall not be
conducted in a manner that may result in dis-equilibrium of wetlands, stream beds, or banks,
adjacent to or upstream and downstream of the above structures. All sediment and erosion
control devices shall bel. removed and the natural grade restored within two (2) months of
the date that the Division of Energy, Mineral and Land Resources (DEMLR) or locally
delegated program has released the specific area within the project. [15A NCAC 02H .0501
and .0502]
Construction Stormwater Permit NCGO10000
An NPDES Construction Stormwater Permit is required for construction projects that disturb
one (1) or more acres of land. This Permit allows stormwater to be discharged during land
disturbing construction activities as stipulated in the conditions of the permit. If your project
is covered by this permit, full compliance with permit conditions including the erosion &
Camp Davis Industrial Park
DWR# 17-0073
Individual Certification #4118
Page 5 of 7
sedimentation control plan, inspections and maintenance, self-monitoring, record keeping
and reporting requirements is required. A copy of the general permit (NCG010000),
inspection log sheets, and other information may be found at:
http://portal.ncdenr.or/web/wq/ws/su/npdessw#tab-w. [15A NCAC 02H .0506(b)(5) and
(c)(5)]
Work in the Dry
All work in or adjacent to stream waters shall be conducted so that the flowing stream does
not come in contact with the disturbed area. Approved best management practices from the
most current version of the NC Sediment and Erosion Control Manual, or the NC DOT
Construction and Maintenance Activities Manual, such as sandbags, rock berms, cofferdams,
and other diversion structures shall be used to minimize excavation in flowing water. [15A
NCAC 02H .0506(b)(3) and (c)(3)]
8. If concrete is used during the construction, then all necessary measures shall be taken to
prevent direct contact between uncured or curing concrete and waters of the state. Water
that inadvertently contacts uncured concrete shall not be discharged to waters of the state
due to the potential for elevated pH and possible aquatic life/fish kills. [15A NCAC 02B .0200]
9. Placement of Culverts and Other Structures in Waters and Wetlands [15A NCAC 02H
.0506(b)(2) and (c)(2))
Culverts required for this project shall be installed in such a manner that the original stream
profiles are not altered and to allow for aquatic life movement during low flows. Existing
stream dimensions (including the cross section dimensions, pattern and longitudinal profile)
must be maintained above and below locations of each culvert.
Placement of culverts and other structures in waters, streams must be below the elevation of
the streambed by one (1) foot for all culverts with a diameter greater than 48 inches, and 20
percent of the culvert diameter for culverts having a diameter less than 48 inches, to allow low
flow passage of water and aquatic life.
Installation of culverts in wetlands must ensure continuity of water movement and be
designed to adequately accommodate high water or flood conditions. Additionally, when
roadways, causeways, or other fill projects are constructed across FEMA -designated floodways
or wetlands, openings such as culverts or bridges must be provided to maintain the natural
hydrology of the system as well as prevent constriction of the floodway that may result in
destabilization of streams or wetlands.
The establishment of native, woody vegetation and other soft stream bank stabilization
techniques must be used where practicable instead of rip rap or other bank hardening
methods.
Camp Davis Industrial Park
DWR# 17-0073
Individual Certification #4118
Page 6 of 7
10. Any riprap required for proper culvert placement, stream stabilization, or restoration of
temporarily disturbed areas shall be restricted to the area directly impacted by the approved
construction activity. All riprap shall be buried and/or "keyed in" such that the original stream
elevation and streambank contours are restored and maintained. Placement of riprap or other
approved materials shall not result in de -stabilization of the stream bed or banks upstream or
downstream of the area. [15A NCAC 02H .0506(b)(2)]
11. Any riprap used for stream stabilization shall be of a size and density to prevent movement by
wave action, current action, or stream flows and consist of clean rock or masonry material free
of debris or toxic pollutants. Riprap shall not be installed in the streambed except in specific
areas required for velocity control and to ensure integrity of bank stabilization measures. [15A
NCAC 02H .0506(b)(2)]
12. A one-time application of fertilizer to re-establish vegetation is allowed in disturbed areas
including riparian buffers, but is restricted to no closer than 10 feet from top of bank of
streams. Any fertilizer application must comply with all other Federal, State and Local
regulations. [15A NCAC 02B .0231]
13. This Certification does not relieve the applicant of the responsibility to obtain all other
required Federal, State, or Local approvals.
14. Continuing Compliance
Mr. Thomas C. Rollins and Camp Davis Industrial Park shall conduct construction activities in a
manner consistent with State water quality standards (including any requirements resulting
from compliance with section 303(d) of the Clean Water Act) and any other appropriate
requirements of State and Federal law. [15A NCAC 02B .0200] If the Division determines that
such standards or laws are not being met (including the failure to sustain a designated or
achieved use) or that State or federal law is being violated, or that further conditions are
necessary to assure compliance, the Division may reevaluate and modify this Certification.
Before modifying the Certification, the Division shall notify Mr. Thomas C. Rollins and Camp
Davis Industrial Park and the U.S. Army Corps of Engineers, provide public notice in accordance
with 15A NCAC 02H .0503 and provide opportunity for public hearing in accordance with 15A
NCAC 02H .0504. Any new or revised conditions shall be provided to Mr. Thomas C. Rollins and
Camp Davis Industrial Park in writing, shall be provided to the U.S. Army Corps of Engineers for
reference in any Permit issued pursuant to Section 404 of the Clean Water Act, and shall also
become conditions of the 404 Permit for the project.
Camp Davis Industrial Park
DWR# 17-0073
Individual Certification #4118
Page 7 of 7
15. This approval is for the purpose and design described in your application and as described in
the Public Notice. The plans and specifications for this project are incorporated by reference
and are an enforceable part of the Certification. If you change your project, you must notify
the Division and you may be required to submit a new application package with the
appropriate fee. If the property is sold, the new owner must be given a copy of this
Certification and is responsible for complying with all conditions. Any new owner must notify
the Division and request the Certification be issued in their name. [15A NCAC 02H .0501 and
.0502]
16. The applicant and/or authorized agent shall provide a completed Certificate of Completion
Form to the DWR 401 & Buffer Permitting Branch within ten days of project completion
(available at: http://portal.ncdenr.org/web/wq/swp/ws/401/certsandpermits/apply/forms).
[15A NCAC 02H .0502(f)]
17. This certification grants permission to the director, an authorized representative of the
Director, or DEQ staff, upon the presentation of proper credentials, to enter the property
during normal business hours. [15A NCAC 02H .0502(e)]
This approval to proceed with your proposed impacts or to conduct impacts to waters as
depicted in your application shall expire upon expiration of the 404 or CAMA Permit. The
conditions in effect on the date of issuance shall remain in effect for the life of the project,
regardless of the expiration date of this Certification. [15A NCAC 02H .0507(d)(2) and 15A NCAC
02H .05061
Non-compliance with or violation of the conditions herein set forth may result in revocation of
this Certification and may also result in criminal and/or civil penalties.
This the 30th day of May 2017
gw-m" ' —
cv�
Karen Higgins, Supervisor
401 & Buffer Permitting Branch
KAH/jab
4118