HomeMy WebLinkAbout20170651 Ver 1_401 Application_20170526/_ /
Letter of Transmittal
Civil & Environmental Consultants, Inc.
Description
250 Old Wilson Bridge Road
5/25/17
Date: 5/25/2017
Job No.: 144-040
Suite 250
Worthington, OH 43085
Landowner Authorization Form
Attention: Ms. Karen Higgins
Phone: (614) 540-6633 - Toll Free: (888) 598-6808
Fax: (614) 540-6638
Design Plans
To:
RE:
401 Oversight/Express Review Permitting Unit
UT to Falls Lake - Ward Property Stream Restoration
512 N. Salisbury Street - Archdale Building - 9th
Project
Floor
Raleigh, NC 27604
2 0 1 7 0 6 5 1
We are sending you attached via Other the following items:
❑Shop drawings ❑Prints✓❑Plans ❑Samples
❑Copy of letter ❑Change order ® PCN application
❑Specifications
Copies
Date
No.
Description
5
5/25/17
PCN form
5
5/25/17
Landowner Authorization Form
5
5/25/17
Design Plans
5
5/25/17
Figures
5
5/25/17
Photo Log
1
5/25/17
Check
0 For approval ❑ Approved as submitted ❑ Resubmit _ copies for approval
❑ For your use ❑ Approved as noted ❑ Submit _ copies for distribution
❑ As requested ❑ Returned for corrections ❑ Return _ prints
0 For review and comment ❑
❑ For bids due ❑ Prints returned after loan to us
Remarks: Please find enclosed an application for a 401 permit along with supporting documentation for the UT to Falls
Lake - Ward Property Stream Restoration Project in Durham County. If you have any questions, please give me call at
(919) 819-1996.
Thanks, Joshua White
Copy to:
Signed:
Joshua A. White PG, PE
MAY 2 6 2017,
Civil & Environmental Consultants, Inc.
May 23, 2017
Mr. Eric Alsmeyer
Raleigh Regulatory Field Office
Department of the Army, Corps of Engineers
3331 Heritage Trade Drive, Suite 105
Wake Forest, NC 27587
Ms. Karen Higgins
401 Oversight/Express Review Permitting Unit
512 N. Salisbury Street - Archdale Building - 9th Floor
Raleigh, NC 27604
Dear Mr. Alsmeyer and Ms. Higgins:
Subject: UT to Falls Lake - Ward Property Stream Restoration Project
401/404 Pre -Construction Notification Application
CEC Project 144-040
Enclosed for your consideration and approval is the Pre -Construction Notification for the US Army
Corps Nationwide Permit 27 and the Division of Water Quality's General Certification 3885 for
stream restoration and stabilization for the UT to Falls Lake - Ward Property Stream Restoration
Project. This project is located on Mr. Ward's property off Hamlin Road in Durham County.
Please note that we have requested the application be reviewed before mid-July 2017 to enable site
preparation to take place so that the riparian buffer may be planted during the appropriate dormant
season at the end of this year. Thank you in advance for your assistance.
This project meets the DWQ definition of stream restoration and funding was provided by
grant funding client. A permitting fee has been included with this package. This is not a
stream mitigation project.
If I can be of any further assistance, please contact me at (919) 819-1996.
Sincerely,y
CIVIL & ENVIRONMENTAL CONSULTANTS, INC. MFAY 2 a 2011 I
p -WA R OUR,T' S
4 BUFFER
Joshua White, PG, PE, CFM, CPESC Nathan Ober, PG
Project Manager Principal
Enclosures: PCN, Landowner Authorization Form, Figures, Photolog, and Check for fees
250 Old Wilson Bridge Road, Suite 250 1 Worthington, Ohio 43085 1 p: 614-540-6633 f: 614-540-6638 I www.cecinc.com
Office Use Only:
Corps action ID no.
DWQ project no.
Form Version 1.3 Dec 10 2008
Page 1 of 11
PCN Form — Version 1.3 December 10, 2008 Version
Pre -Construction Notification (PCN) Form
A.
Applicant Information
1.
Processing
1a.
Type(s) of approval sought from the
Corps:
®Section 404 Permit El Section 10 Permit
1b. Specify Nationwide Permit (NWP) number: 27 or General Permit (GP) number:
1c.
Has the NWP or GP number been verified by the Corps?
® Yes
❑ No
1d. Type(s) of approval sought from the DWQ (check all that apply):
® 401 Water Quality Certification — Regular ❑ Non -404 Jurisdictional General Permit
❑ 401 Water Quality Certification — Express ® Riparian Buffer Authorization
1e.
Is this notification solely for the record
because written approval is not required?
For the record only for DWQ 401
Certification:
❑ Yes ® No
For the record only for Corps Permit:
❑ Yes ® No
1f.
Is payment into a mitigation bank or in -lieu fee program proposed for mitigation
of impacts? If so, attach the acceptance letter from mitigation bank or in -lieu
fee program.
❑ Yes
® No
1g.
Is the project located in any of NC's twenty coastal counties. If yes, answer 1h
below.
❑ Yes
® No
1 h.
Is the project located within a NC DCM Area of Environmental Concern (AEC)?
❑ Yes
® No
2.
Project Information
2a.
Name of project:
UT to Falls Lake - Ward Property
2b.
County:
Durham
2c.
Nearest municipality / town:
Durham
2d.
Subdivision name:
2e. NCDOT only, T.I.P. or state
project no:
3.
Owner Information
3a.
Name(s) on Recorded Deed:
James O Ward
3b.
Deed Book and Page No.
Deed Book/Deed Page: 2011-E/1504
3c.
Responsible Party (for LLC if
applicable):
N/A
3d.
Street address:
3111 Hamlin Road
3e.
City, state, zip:
Durham, NC 27612
3f.
Telephone no.:
3g.
Fax no.:
3h.
Email address:
Page 1 of 11
PCN Form — Version 1.3 December 10, 2008 Version
4. Applicant Information (if different from owner)
4a. Applicant is:
❑ Agent ® Other, specify: Durham Soil & Water Conservation District
4b. Name:
4c. Business name
(if applicable):
Durham Soil & Water Conservation District
4d. Street address:
721 Foster Street
4e. City, state, zip:
Durham, NC 27701
4f. Telephone no.:
(919) 560-0525
4g. Fax no.:
4h. Email address:
eculberson@dconc.gov
5. Agent/Consultant Information (if applicable)
5a. Name:
Joshua White
5b. Business name
(if applicable):
Civil and Environmental Consultants, Inc.
5c. Street address:
250 Old Wilson Bridge Road, Ste. 250
5d. City, state, zip:
Worthington, OH 43085
5e. Telephone no.:
614-540-6633
5f. Fax no.:
5g. Email address:
jwhite@cecinc.com
Page 2 of 11
B. Project Information and Prior Project History
1. Property Identification
1a. Property identification no. (tax PIN or parcel ID):
0844-03-94-5831
1b. Site coordinates (in decimal degrees):
Latitude: 36.067886 Longitude: -78.832452
(DD.DDDDDD) (-DD.DDDDDD)
1c. Property size:
149.75 acres
2. Surface Waters
2a. Name of nearest body of water (stream, river, etc.) to
Falls Lake
proposed project:
2b. Water Quality Classification of nearest receiving water:
WS -IV, NSW, CA
2c. River basin: map is available at
Neuse
http://h2o.enr.state.nc.us/admin/maps/
3. Project Description
3a. Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this
application:
Stream reaches are experiencing excess vertical and lateral erosion that are creating additional
sedimentation into the nutrient sensitive Falls Lake Reservoir.
3b. List the total estimated acreage of all existing wetlands on the property:
0 acres. However, we would like to create wetlands as part of this stream project. The ACOE
property has wetlands due to its proximity to Falls Lake.
3c. List the total estimated linear feet of all existing streams (intermittent and perennial) on the property:
2,365 (reaches M2 and M3} intermittent
3d. Explain the purpose of the proposed project:
To restore, stabilize, and/or improve highly degraded streams. To provide permanent vegetative
buffers surrounding the stream to protect their integrity in the future.
3e. Describe the overall project in detail, including the type of equipment to be used:
Restoration of approximately 3,604' of a degraded headwater stream that drains to Falls Lake, a
state -designated nutrient sensitive water. Work to be conducted with track hoes, dozers, track
dump trucks, and other equipment typically used for stream restoration projects.
Page 3 of 11
PCN Form — Version 1.3 December 10, 2008 Version
4. Jurisdictional Determinations
4a. Have jurisdictional wetland or stream determinations by
the Corps or State been requested or obtained for this
El Yes ®No El Unknown
property / project (including all prior phases) in the past?
Comments:
4b. If the Corps made the jurisdictional determination, what
El Preliminary El Final
type of determination was made?
4c. If yes, who delineated the jurisdictional areas?
Agency/Consultant Company:
Name (if known):
Other:
4d. If yes, list the dates of the Corps jurisdictional determinations or State determinations and attach documentation.
5. Project History
5a. Have permits or certifications been requested or
obtained for this project (including all prior phases) in the
❑ Yes ® No ❑ Unknown
past?
5b. If yes, explain in detail according to "help file" instructions.
6. Future Project Plans
6a. Is this a phased project?
❑ Yes ® No
6b. If yes, explain.
Page 4 of 11
C. Proposed Impacts Inventory
1. Impacts Summary
la. Which sections were completed below for your project (check all that apply):
❑ Wetlands ® Streams - tributaries ® Buffers
❑ Open Waters ❑ Pond Construction
2. Wetland Impacts
If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted.
2a.
2b.
2c.
2d.
2e.
2f.
Wetland impact
Type of jurisdiction
number —
Type of impact
Type of wetland
Forested
(Corps - 404, 10
Area of impact
Permanent (P)
(if known)
DWQ — non -404, other)
(acres)
or Temporary T
W1 ❑ P ❑ T
❑ Yes
❑ Corps
❑ No
❑ DWQ
W2 El P ❑ T
ElYes
❑ Corps
❑ No
[--]DWQ
2g. Total wetland impacts
2h. Comments:
3. Stream Impacts
If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this
question for all stream sites impacted.
3a.
3b.
3c.
3d.
3e.
3f.
3g.
Stream impact
Type of impact
Stream name
Perennial
Type of
Average
Impact
number -
(PER) or
jurisdiction
stream width
length
Permanent (P)
intermittent
(Corps - 404, 10
(feet)
(linear
or Temporary (T)
(INT)?
DWQ — non -404,
feet)
other)
S1 ®P ❑ T
Stream
M2
❑ PER
❑ Corps
4.2
865
Restoration
® INT
❑ DWQ
S2 ®P ❑ T
Stream
Restoration
M3
[-]PER
® INT
El Corps
❑ DWQ
9.1
1,500
Stream
❑ PER
❑ Corps
S3 ®P ❑ T
Restoration
M1
❑ INT
DWQ
5.7
519
® EPH
Stream
❑ PER
❑ Corps
S4 ®P ❑ T
Restoration
UT1
❑ INT
❑ DWQ
4.4
364
® EPH
Stream
❑ PER
❑ Corps
S5 ®P ❑ T
Restoration
UT2
❑ INT
❑ DWQ
3.6
226
® EPH
Stream
❑ PER
❑ Corps
S6 ® P ❑ T
Restoration
UT3
❑ INT
❑ DWQ
5.4
159
® EPH
3h. Total stream and tributary impacts
3,633
3i. Comments: M1, UTI, UT2, & UT3 are Ephemeral channels
Page 5 of 11
4. Open Water Impacts
If there are proposed impacts to lakes, ponds, estuaries, tributaries, sounds, the Atlantic Ocean, or any other open water of
the U.S. then individually list all open water impacts below.
4a.
4b.
4c.
4d.
4e.
Open water
Name of
impact number
waterbody
Type of impact
Waterbody type
Area of impact (acres)
— Permanent
(if applicable)
(P) or
TemporaryT
01 ❑P❑T
4f. Total open water impacts
0
4g. Comments:
5. Pond or Lake Construction
If pond or lake construction proposed, then complete the chart below.
5a.
5b.
5c.
5d.
5e.
Wetland Impacts (acres)
Stream Impacts (feet)
Upland
Pond ID
Proposed use or
(acres)
number
purpose of pond
Flooded
Filled
Excavated
Flooded
Filled
Excavated
Flooded
P1
5f. Total
5g. Comments:
5h. Is a dam high hazard permit required?
❑ Yes ®No If yes, permit ID no:
5i. Expected pond surface area (acres):
5j. Size of pond watershed (acres):
5k. Method of construction:
6. Buffer Impacts (for DWQ)
If project will impact a protected riparian buffer, then complete the chart below. If yes, then individually list all buffer impacts
below. If any impacts require mitigation, then you MUST fill out Section D of this form.
6a.
® Neuse ❑ Tar -Pamlico ❑ Other:
Project is in which protected basin?
❑ Catawba ❑ Randleman
6b.
6c.
6d.
6e.
6f.
6g.
Buffer impact
number —
Reason for impact
Buffer
Zone 1 impact
Zone 2 impact
Permanent (P)
Stream name
mitigation
(square feet)
(square feet)
or Temporary
required?
T
B1 ®P ❑ T
Stream Restoration
Int mt2ittent
ElYes ® No
55,430
35,799
B2 ® P ❑ T
Stream Restoration
M3 -
❑ Yes ® No
96,471
58,324
Intermittent
B3 ® P ❑ T
Stream Restoration
M1 - Eph
❑ Yes ® No
32,462
21,312
B4 ® P ❑ T
Stream Restoration
UT1 - Eph
El Yes Z No
20,731
12,704
B5 ® P ❑ T
Stream Restoration
UT2 - Eph
❑ Yes 0 No
11,759
6,569
B6 ® P ❑ T
Stream Restoration
UT3 - Eph I
El Yes ® No
7,258
3,943
6h. Total buffer impacts
224,111
138,651
6i. Comments: Stream restoration practices are exempt from mitigation under the buffer rules. All areas disturbed will be replanted
in 50' native herbaceous and riparian vegetation.
Page 6 of 11
D. Impact Justification and Mitigation
1. Avoidance and Minimization
1a. Specifically describe measures taken to avoid or minimize the proposed impacts in designing project.
The existing stream channels are so incised and degraded that a new channel is being
designed in order to stabilize and restore stream function to this section of channel. The new
channel will have an opportunity to function with a floodplain again and help with nutrient
removal.
Sediment and Erosion control measures will be designed in order to keep sediment onsite and
to temp. stabilize the site.
b. Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques.
Sediment and Erosion control measures will be used in order to minimize the impact on the
stream ecosystem. Such measures will be rock dams, coir fiber matting, silt fence, wood mat
crossings, pump -around, geolifts, and working offline.
2. Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State
2a. Does the project require Compensatory Mitigation for
impacts to Waters of the U.S. or Waters of the State?
❑ Yes ® No
2b. If yes, mitigation is required by (check all that apply):
❑ DWQ ❑ Corps
2c. If yes, which mitigation option will be used for this
project?
❑ Mitigation bank
El Payment to in -lieu fee program
❑ Permittee Responsible Mitigation
3. Complete if Using a Mitigation Bank
3a. Name of Mitigation Bank:
3b. Credits Purchased (attach receipt and letter)
Type
Quantity
3c. Comments:
4. Complete if Making a Payment to In -lieu Fee Program
4a. Approval letter from in -lieu fee program is attached.
❑ Yes
4b. Stream mitigation requested:
linear feet
4c. If using stream mitigation, stream temperature:
❑ warm ❑ cool ❑cold
4d. Buffer mitigation requested (DWQ only):
square feet
4e. Riparian wetland mitigation requested:
acres
4f. Non -riparian wetland mitigation requested:
acres
4g. Coastal (tidal) wetland mitigation requested:
acres
4h. Comments:
5. Complete if Using a Permittee Responsible Mitigation Plan
Page 7 of 11
PCN Form — Version 1.3 December 10, 2008 Version
5a. If using a permittee responsible mitigation plan, provide a description of the proposed mitigation plan.
6. Buffer Mitigation (State Regulated Riparian Buffer Rules) — required by DWQ
6a. Will the project result in an impact within a protected riparian buffer that requires
El Yes ® No
buffer mitigation? If You will have to fill out this entire form — please
contact the State for more information.
6b. If yes, then identify the square feet of impact to each zone of the riparian buffer that requires mitigation. Calculate the
amount of mitigation required.
6c.
6d.
6e.
Zone
Reason for impact
Total impact
Multiplier
Required mitigation
(square feet)
(square feet)
Zone 1
3 (2 for Catawba)
Zone 2
1.5
6f. Total buffer mitigation required:
6g. If buffer mitigation is required, discuss what type of mitigation is proposed (e.g., payment to private mitigation bank,
permittee responsible riparian buffer restoration, payment into an approved in -lieu fee fund).
6h. Comments: Stream restoration and invasive control projects are an allowable practice within the
buffer rules. After construction, the entire disturbed area will be replanted in native herbaceous
and riparian vegetation.
Page 8 of 11
E. Stormwater Management and Diffuse Flow Plan (required by DWQ)
1. Diffuse Flow Plan
1a. Does the project include or is it adjacent to protected riparian buffers identified
® Yes ❑ No
within one of the NC Riparian Buffer Protection Rules?
1 b. If yes, then is a diffuse flow plan included? If no, explain why.
comments: A diffuse flow plan is not required for stream restoration
❑ Yes ® No
activity.
2. Stormwater Management Plan
2a. What is the overall percent imperviousness of this project?
<1%
2b. Does this project require a Stormwater Management Plan?
❑ Yes ® No
2c. If this project DOES NOT require a Stormwater Management Plan, explain why: A stormwater management plan
is not required for stream restoration activity.
2d. If this project DOES require a Stormwater Management Plan, then provide a brief, narrative description of the plan:
❑ Certified Local Government
2e. Who will be responsible for the review of the Stormwater Management Plan?
❑ DWQ Stormwater Program
❑ DWQ 401 Unit
3. Certified Local Government Stormwater Review
3a. In which local government's jurisdiction is this project?
❑ Phase II
3b. Which of the following locally -implemented stormwater management programs
❑ NSW
❑ USMP
apply (check all that apply):
❑ Water Supply Watershed
❑ Other:
3c. Has the approved Stormwater Management Plan with proof of approval been
❑ Yes ❑ No
attached?
4. DWQ Stormwater Program Review
❑ Coastal counties
[_1 HQW❑
4a. Which of the following state -implemented stormwater management programs apply
ORW
(check all that apply):
❑ Session Law 2006-246
❑ Other:
4b. Has the approved Stormwater Management Plan with proof of approval been
attached?
❑ Yes ❑ No
5. DWQ 401 Unit Stormwater Review
5a. Does the Stormwater Management Plan meet the appropriate requirements?
❑ Yes ❑ No
5b. Have all of the 401 Unit submittal requirements been met?
❑ Yes ❑ No
Page 9 of 11
PCN Form — Version 1.3 December 10, 2008 Version
F. Supplementary Information
1. Environmental Documentation (DWQ Requirement)
la. Does the project involve an expenditure of public (federal/state/local) funds or the
® Yes ❑ No
use of public (federal/state) land?
1 b. If you answered "yes" to the above, does the project require preparation of an
environmental document pursuant to the requirements of the National or State
❑ Yes ® No
(North Carolina) Environmental Policy Act (NEPA/SEPA)?
1 c. If you answered "yes" to the above, has the document review been finalized by the
State Clearing House? (If so, attach a copy of the NEPA or SEPA final approval
letter.)
comments: This project is not for mitigation; as per 15A NCAC
❑ Yes ❑ No
016C.0408, stream restoration is a minor construction activity and
does not require an environmental document.
2. Violations (DWQ Requirement)
2a. Is the site in violation of DWQ Wetland Rules (15A NCAC 2H .0500), Isolated
Wetland Rules (15A NCAC 2H .1300), DWQ Surface Water or Wetland Standards,
❑ Yes ® No
or Riparian Buffer Rules (15A NCAC 2B .0200)?
2b. Is this an after -the -fact permit application?
❑ Yes ® No
2c. If you answered "yes" to one or both of the above questions, provide an explanation of the violation(s):
3. Cumulative Impacts (DWQ Requirement)
3a. Will this project (based on past and reasonably anticipated future impacts) result in
❑ Yes ® No
additional development, which could impact nearby downstream water quality?
3b. If you answered "yes" to the above, submit a qualitative or quantitative cumulative impact analysis in accordance with the
most recent DWQ policy. If you answered "no," provide a short narrative description.
This project seeks to improve water quality and reduce sediment on an unnamed tributary (UT) to Falls Lake.
4. Sewage Disposal (DWQ Requirement)
4a. Clearly detail the ultimate treatment methods and disposition (non -discharge or discharge) of wastewater generated from
the proposed project, or available capacity of the subject facility.
N/A
Page 10 of 11
PCN Form — Version 1.3 December 10, 2008 Version
5. Endangered Species and Designated Critical Habitat (Corps Requirement)
5a. Will this project occur in or near an area with federally protected species or
❑ Yes ® No
habitat?
5b. Have you checked with the USFWS concerning Endangered Species Act
® Yes ❑ No
impacts?
® Raleigh
5c. If yes, indicate the USFWS Field Office you have contacted.
❑ Asheville
5d. What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical
Habitat?
NCWRC Natural Heritage website (no known species within 2 miles as on 04/20/2017), USFWS as of 04/20/2017
6. Essential Fish Habitat (Corps Requirement)
6a. Will this project occur in or near an area designated as essential fish habitat?
❑ Yes ® No
6b. What data sources did you use to determine whether your site would impact Essential Fish Habitat?
United States Fish and Wildlife
7. Historic or Prehistoric Cultural Resources (Corps Requirement)
7a. Will this project occur in or near an area that the state, federal or tribal
governments have designated as having historic or cultural preservation
❑ Yes ® No
status (e.g., National Historic Trust designation or properties significant in
North Carolina history and archaeology)?
7b. What data sources did you use to determine whether your site would impact historic or archeological resources?
North Carolina Office of Archives and History website was searched. A letter was also sent to the SHPO office and have
not received any correspondance yet. We will forward on any responses.
8. Flood Zone Designation (Corps Requirement)
8a. Will this project occur in a FEMA -designated 100 -year floodplain?
❑ Yes ® No
8b. If yes, explain how project meets FEMA requirements:
8c. What source(s) did you use to make the floodplain determination? NC Flood Maps Website and Durham GoMaps
Joshua White
t1-
5/22/2017
Applicant/Agent's Signature
Applicant/Agent's Printed Name
(Agent's signature is valid only if an authorization letter from the applicant
Date
is provided.)
Page 11 of 11
AGENT AUTHORI ZATI ON FORM
PROPERTY LEGAL DESCRIPTION:
LOT NO. PLAN NO. PARCEL I D: 0844-03-94-5831 , 0844-04-84-3128
-------------------------------------------------
STREET ADDRESS: 3111 HAMLIN RD
--------------------------------------------------
DURHAM, NC 27704-
---------------- -----------------------------------
Please print: JAMES O WARD
Property Owner:
----------------------------------------------------
Property Owner:
....................................................
The undersigned, registered property owners of the above noted property, do hereby authorize
Joshua White, PG, PE Civil & Environmental Consultants, Inc.
- ----------------,of- --- --- ----------------
(Contractor % Agent) (Name of consulting firm)
to act on my behalf and take all actions necessary for the processing, issuance and acceptance of
this permit or certification and any and all standard and special conditions attached.
Property Owner's Address (if different than property above):
4812 CARTERET DR, RALEIGH, 27612
-------------------------------------------------------------
Telephone: _ 9Iq 7I _�Cj'�_
We hereby certify the above information submitted in this application is true and accurate to the
best of our knowledge.
---------------- - -------------
thorized Signature
Date: ------------
----------------
Authorized Signature
Date:-------------------------------
Legend
......•• Mountains to Sea Trail
Tributaries to be Restored (-3,900)
Rivers, Streams, & Lakes
James Ward Parcel
Natural Heritage Program Natural Areas
- NCEEP Targeted Watersheds
�a Zora
app Falls Lake
O\
<itt�e Riper
F
CONSERVATION DISTRICT
Neuse River Basin
0302030103
Targeted Watershed
0302020105
0 1,250 2,500 5,000
Feet
Greek
Falls Lake
Falls Lakel
lw�
Figure 1 - Vicinity
Ward Property
Durham County, NC
M3
Legend
Area of Interest
Tributaries to be restored -3.900'
OWard Parcel
Durham Parcels
■ ■ Mountains to Sea Trail
Soils
Ch-Chewacla and Wehadkee soils, 0 to 2 percent slopes, frequently flooded
Cp-Congaree silt loam, 0 to 2 percent slopes. frequently flooded
CrB-Creedmoor sandy loam, 2 to 6 percent slopes
CrC-Creedmoor sandy loam, 6 to 10 percent slopes
I Gu-Gullied land, clayey materials
HeB-Helena sandy loam, 2 to 6 percent slopes
IrC-Iredell loam, 6 to 10 percent slopes
MfB-Mayodan sandy loam, 2 to 6 percent slopes
MfC-Mayodan sandy loam, 6 to 10 percent slopes
MfD-Mayodan sandy loam, 10 to 15 percent slopes
QW -Water
QWn-Wehadkee silt loam, 0 to 2 percent slopes, frequently flooded
QWsB-While Store sandy loam, 2 to 6 percent slopes
QWsC-White Store sandy loam, 6 to 10 percent slopes
QWsE-White Store sandy loam, 10 to 25 percent slopes
� a
CONSERVATION DISTRICT
Hamlin Road
M2
14
Ilk
r- 01111
askad.addl-a-mg 10J 4, .4. L J I
�r
r
1,200 Figure 3
Feet Ward Property
Durham County, NC
♦ a
4
I
■ !" *rrrr■• fir. ,
•fir
� r
I
r
Y,
r *•
Legend
Area of Interest
Tributaries to be restored -3.900'.
QWard Parcel Y�
Durham Parcels
■ ■ ■ Mountains to Sea Trail _ - • ,'�
SOIIS
® Ch-Chewacla and Wehadkee soils, 0 to 2 percent slopes, frequently flooded
OCp-Congaree silt loam, 0 to 2 percent slopes, frequently flooded
Q CrB-Creedmoor sandy loam, 2 to 6 percent slopes
Hamlin Road -
QCrC-Creedmoor sandy loam. 6 to 10 percent slopes ,,,,,, � •- ,.� . '
QGu-Gullied land, clayey materials
QHeB-Helena sandy loam, 2 to 6 percent slopes
IrC-Iredell loam, 6 to 10 percent slopes
QM1B-Mayodan sandy loam, 2 to 6 percent slopes
® MfC-Mayodan sandy loam, 6 to 10 percent slopes .
® MfD-Mayodan sandy loam, 10 to 15 percent slopes
QW -Water 11
Wn-Wehadkee silt loam, 0 to 2 percent slopes, frequently flooded t f lot
QWsB-White Store sandy loam. 2 to 6 percent slopes I
® WsC-White Store sandy loam, 6 to 10 percent slopes r "r
® WsE-White Store sandy loam, 10 to 25 percent slopes -
DURHAM
SOIL & WATER 0 300 600 1,200 Figure 4
Feet ward Property
Durham County, NC
DURHAM COUNTY, NORTH CAROLINA — SHEET NUMBER 14
( Cc ( \WX2
1I r f Mf)\•'' I
cp
Mfc' fi �
MfC �� } %" A .-/',�� •'oc<.... -;
Cc MfC, G,B
v• � / /tip' f % `- •„
GrH v
o �� CrC MfB WsC ,` I � AIA �i
MfC Cr8 } � �
MIR Wn
MfD / ..- / If .i
G 'ti (n 1 / MiE3 9..
/ �
GrC W. r _
cP I,
_..
r8 CrC
J Cu
Y ��
drB GryVsB f i ALj� . J"
'�. f,..,.rr,.
• " y -' war i '�'` Al
f"7'' Ch :. �. ,....:�GrB
Ch
•"_ ) I POOL
c
,S
CP
G�.fAf _ SCP
V
� !NvC2
I _ W5
Q�
�. ��NE
CR DAIS
Gr8'
` Ch AIB
- C WSB
�. _.._._._ C P / f
Y �.....V
•
� Wrt
(
AIA
WsC
Cc.�
Ch WsB Wn r Ei
'M f8
CCh
P
.-
HeB MfC,.
WSB CrB Q CrB CrC
Ir f WsE � .1
IrWSB j IrC Mf6
ti WsC Q WsC
CP '" WSB \
Ch H�Vx p CrB
� W s E L L G W
sB
C p \ �J
Cr8
Ch--� CSG wn t / WsC �� ��"• "i Heb HeB RWIC
.'i Mf0 ' I
Mf6 ��� �9�'•+.
PfE WsC CrB
WSE
WSE
Hamlin Road
Crc
LlfB
MfE K's 6
CrB �� WsB _
3 3" Gu WIC H
W H
MtH C� Wn m WsC WSB
n r> CrC
HeB MfB� {' HeB 3
111 Crc CrB
Wn W� p m W
" 03
IrC WsG IrC
,,✓' �- WSC �,` - s �: C, fi
MfB =' 1�5 Ws m
Cr8
C
MfC /
N � Mfc' 1 �h Ro Cr Ch
CrC � v W56
Mfr MfC MID
NC DWQ Stream Identification Form Version 4.11
Date:
Project/Slte: l4
Latitude: �� O 7
Evaluator: IAICounty:
v6`ty 4,1
Longitude: 2� 53,2 sz�
Total Points:
Stream is at least irnemunent /
Stream Determination (circle one)
Other (/��/ /�%�
if t 19 rennial ift 317 C/ r
Ephemeral Intermittent Perennial
e.g. Quad Name:
A. Geomorphology Subtotal =
Absent
Weak
Mod ate
Strong
19, Continuity of channel bed and bank
0
1Oy
2
3
2. Sinuosity of channel along thalweg
0
1
2
3
3. In -channel structure: ex. riffle -pool, step -pool,
ripple -pool sequence
0
�j
2
3
4. Particle size of stream substrate
0
1
2
3
5. Active/relict floodplain
0
022
1
3
6. Depositional bars or benches
0
1)
2
3
7. Recent alluvial deposits
0
a2
1
3
8. Headcuts
0
FACW = 0.75; OBL = 1.5 Othr = 0--
2
3
9. Grade control
0
.5
1
1.5
10. Natural valley
0
0.5,
1
1.5
11. Second or greater order channel
No = 0
Yes = 3
o •� -� ; S ie r
affiic cal ditches are not rated; see discussions in manual
B. Hvdroloav (Subtotal= ) l
12. Presence of Baseflow
0
2
2
3
13. Iron oxidizing bacteria
/0
1
2
3
14. Leaf litter
1.5
1
0.
0
15. Sediment on plants or debris
00.
1
1
1.5
16. Organic debris lines or piles
0
0.5
1
1.5
17. Soil -based evidence of high water table?
No =,W
1
Yes = 3
C. Biology (Subtotal = ,C _ " 1
18. Fibrous roots in streambed
3
2
0
19. Rooted upland plants in streambed
3
2
0
20. Macrobenthos (note diversity and abundance)
1
2
3
21. Aquatic Mollusks
1
2
3
22. Fish
0
0.5
1
1.5
23. Crayfish
0.5
1
1.5
24. Amphibians
CO.
1
1.5
25. Algae
_9 l
0.5
1
1.5
26. Wetland plants in streambed
FACW = 0.75; OBL = 1.5 Othr = 0--
'perennial streams may also be identified using other methods. See p. 35 of manual.
Notes: -
Sketch: �� 5'� r4 dd i
o •� -� ; S ie r
�.
NC DWO Stream Identification Form Version 4.11
Date: -�!� - ��
Project/Site:
Latitude: 3(0, U( 7 g$(o
Evaluator: Ae
County: �oM
Longitude: -79, 83,)Vsa
Total Points: /
Stream is at least intermittent
Stream Determination (circle one)
Other lJ% e2
Na 19 or rental Ht 30' l
Ephemeral Intermi
Intermittent Perennial
e.g. Quadame:
NN t<vvr lv
A. Geomorphology (Subtotal=
Absent
Weak
Mode
to Strong
1", Continuity of channel bed and bank
0
1
14. Leaf litter
3
2. Sirmosity of channel along thalweg
0
('177
2
3
3. In -channel structure: ex. riffle -pool, step -pool,
sequence
0/�
r i
2
3
4. Particle size of stream substrate
0
Yes = 3
2
3
5. Active/relict floodplain
0
0.5
2
3
6. Depositional bars or benches
0
2
3
7. Recent alluvial deposits
0
6>
2
3
8. Headcuts
0
1
2
3
9. Grade control
0
0,
1
1.5
10. Natural valley
0
0.5
1
11. Second or greater order channel
;' No= 0
Sketch:
Yes = 3
artificial ditches are not rated; see discussions in manual
B. Hvdroloav (Subtotal = / r
12. Presence of Baseflow
1
2
3
13. Iron oxidizing bacteria
0 1
3
3
14. Leaf litter
1.5 1
X0.5
0
15. Sediment on plants or debris
0 0
1
1.5
16. Organic debris lines or piles
0
1
1.5
17. Soil -based evidence of high water table?
o = 0)
Yes = 3
1
G. Biology (Subtotal = r , j ) -
18. Fibrous roots in streambed
3
2
0
19. Rooted upland plants in streambed
3
2
.IJ
0
20. Macrobenthos (note diversity and abundance)
(Q
1
2
3
21. Aquatic Mollusks
1
2
3
22. Fish
0.5
1
1.5
23. Crayfish
0
0.5
1
1.5
24. Amphibians
0
1
1.5
25. Algae
0.5
1
1.5
26. Wetland plants in streambed
FACW = 0.75: OBL = 1.5 Other = 0
'perennial streams may also be identified using other methods. See p. 35 of manual.
Notes: - r,
Sketch:
NC DWO Stream Identification Form Version 4.11
Date: ���L� _/�
Project/Site:
Latitude: 3(-.06 lag (-" e
Evaluator: D5 h (4N
County:
Longitude:
Total Points:Stream
Stream is at least intermittent /%5--
Determination (circle one)
Ephemeral Intermittent Perennial
Other 617
e.g. Quad Name:
if z 1 g or perennial if i 30'
2. Sinuosity of channel along thalweg
if/ - f %c �,•�
A. Geomorphology Subtotal = 161, `
Absent
Weak
Moderate
Strong
1 a Continuity of channel bed and bank
0
1
0
3
2. Sinuosity of channel along thalweg
1.5
1
2
3
3. In -channel structure: ex. riffle -pool, step -pool,
ripple -pool sequence
0
Yes = 3
2
3
4. Particle size of stream substrate
0
0.5
2
3
S. Active/relict floodplain
0
1
1
3
6. Depositional bars or benches
0
0.5
2
3
7. Recent alluvial deposits
0
0.5
2
3
S. Headcuts
0
FACW = 0.75; OBL = 1.5
2
3
9. Grade control
0
0
1
1.5
10. Natural valley
0
.5
1
1.5
11. Second or greater order channel
No = 0
Yes = 3
Sketch:
artificial ditches are not rated; see discussions in manual
B. Hvdroloav (Subtotal = A <" t
12. Presence of Baseflow
1 2
3
13. Iron oxidizing bacteria
1 2
3
14. Leaf litter
1.5 1
0
15. Sediment on plants or debris
0 1
1.5
16. Organic debris lines or piles
0 0 1
1.5
17. Sod -based evidence of high water table?
o = 0
Yes = 3
C. Biology (Subtotal = ",4 < 1
18. Fibrous roots in streambed
3
2
0
19. Rooted upland plants in streambed
3
2
1
0
20. Macrobenthos note diversity and abundance)
(0•)
1
2
3
21. Aquatic Mollusks
1
2
3
22. Fish
0.5
1
1.5
23. Crayfish
0
.5
1
1.5
24. Amphibians
0.5
1
1.5
25. Algae
(_d
0.5
1
1.5
26. Welland plants in streambed
FACW = 0.75; OBL = 1.5
OthoL5
'perennial streams may also be identified using other methods. See p. 35 of manual.
Notes:
Sketch:
NC DWO Stream Identification Form Vercion 4.11
Date: 11. %1�--� �j
Project/Site:
Latitude:
Evaluator: 1,61-1f<
County:
Longitude: '74 z,;) -/S.2 p
Total Points:
Stream is at least intermittent
Stream Determination (circle one)
Other 14'�
if219 or Perennial H 2 30'
Ephemeral Intermittent Perennial
e.g. Quad Name:
A. Geomorphology Subtotal =
Absent
Weak
Moderate
Strong
10* Continuity of channel bed and bank
0
1
2
3
2. Sinuosity of channel along thalweg
0
1
0.5
3
3. In -channel structure: ex. riffle -pool, step -pool,
ripple -pool sequence
0
1
1
3
4. Particle size of stream substrate
0
0.5
2
3
5. Active/relict floodplain
0
1w
Yes = 3
3
6. Depositional bars or benches
0
Ckd-)
2
3
7. Recent alluvial deposits
0
0.5
2
3
B. Headcuts
0
FACW = 0.75; OBL = 1.5
r2
3
9. Grade control
0
0.5
1.5
10. Natural valley
0
0.5
a
1.5
11. Second or greater order channel
No = 0
Yes = 3
Sketch:
- artificial ditches are not rated; see discussions in manual
B. Hvdroloav (Subtotal = V, 5- )
12. Presence of Baseflow
0
2
2
3
13. Iron oxidizing bacteria
3
1
2
3
14. Leaf litter
1.5
1
0.5
0
15. Sediment on plants or debris
0
0.5
1
1.5
16. grganic debris lines or piles
1 0 1
0.5
1
1.
17. Soil -based evidence of high water table?
I < No= 0
0.5
Yes = 3
1.5
G. Bioloav (Subtotal = '-/,r S' )
18. Fibrous roots in streambed
3
2
0
19. Rooted upland plants in streambed
3
2
1
0
20. Macrobenthos (note diversity and abundance)
1
2
3
21. Aquatic Mollusks
1
2
3
22. Fish
0.5
1
1.5
23. Crayfish
_
0.5
1
1.5
24. Amphibians
0
Ckd-)
1
1.5
25. Algae
0
0.5
1
1.5
26. Wetland plants in streambed
FACW = 0.75; OBL = 1.5
r = 0
'perennial streams may also be identified using other methods. See p. 35 of manual.
Notes: In
Sketch:
NC DWO Stream identification Form Version 4.11
Date: �J-�y /(p
Project/Site: /�/�/�
Latitude: YK,, 06 0 44 0
-
Evaluator:: �U ��'
County: UL
Longitude: -79. 3a115,O
Total Points:
Stream is least intermittenti
I Stream Determination (circle one)
,Other /f'f 3
at
if a 19 or erennial if 2 30'
Ephemeral Intermittent Perennial
, e.g. Quad Name:��
A. Geomorphology (Subtotal=) r Absent Weak Moderate i Strong
18 Continuity of channel bed and bank
2. Sinuosity of channel along thalweg
0
0
1
1 13
2 -
3
{
3. In -channel structure: ex. riffle -pool, step -pool,
ripple -pool sequence
0
1
2
3
4. Particle size of stream substrate
0
1
0.5
3-
5. Active/relict floodplain
0
1
(1
3
6. Depositional bars or benches
0
1
2
3
7. Recent alluvial deposits
0
0
1
1
2
3
3
8. Headcuts
9. Grade control
0
0.5
1.5
10. Natural valley
0
0.5
1.5
11. Second or greater order channel -
(No= 0
Yes = 3
-
a artificial ditches are not rated; see discussions in manual
B. Hydrology (Subtotal = -5-
12.
S
12. Presence of Baseflow
0
�-
2 -
3
13. Iron oxidizing bacteria
0
0
2
3
14. Leaf litter
1.5
U
0.5
0
15. Sediment on plants or debris
0
0.5
(1
1.5
16. Organic debris lines or piles
0
0.5
1.5
1.5
17. Soil -based evidence of high water table?
1
No = 0)
Yes = 3
0.5
C. Biology (Subtotal=___ 4;- )
18. Fibrous roots in streambed 3
C
1
0
19. Rooted upland plants in streambed 3
(
1
0
20. Macrobenthos (note diversity and abundance)
1
2
3
21. Aquatic Mollusks
1
1
2
3
22. Fish V
0.5
1
1.5-
23. Crayfish 0
.5
1
1.5
_
24. Amphibians 0
1
1.5
25. Algae
0.5
1
1.5
_
26. Wetland plants in streambed FACW = 0.75; OBL = 1.5
'perennial streams may also be identified using other methods. See p. 35 of manual.
Wher = 0
Notes: f Ir!_no / /',s hoc ij (/ r ' : - A
r7 hr 4 roe /t
Sketch:
I
ti
_ ate" � ,. • � �,
dig � r n `=�- ' . ,� ..;�, 'fit !tet{A •_� � � ,
. ' .�. �� .,. � _ • ice,
r-
�r�'�°*. �' ►' v -fir' } 5 - � �
M.
IRE
MOM
SHEETINDEX
DRAWING
NO.
SHEET TITLE
EC000
COVER SHEET
EC100
GENERAL NOTES
EC101
GEOMORPHIC
PARAMETERS
EC200
SITE PLAN
EC201
SITE PLAN
EC202
SITE PLAN
EC203
EROSION
CONTROL
EC300
PROFILES
EC301
PROFILES
EC302
PROFILES
EC400
DETAILS
EC401
DETAILS
EC402
DETAILS
EC403
DETAILS
EC500
PLANTING PLAN
EC600
BUFFER ZONE
I 5
DURHAM COUNTY, NORTH CAROLINA
STREAM RESTORATION PLANS
WARD PROPERTY
NEUSE RIVER BASIN- 030202010304
MAY 2017
STREAM RESTORATION PROJECT AREA
PROJECT STANDARDS
THE FOLLOWING STANDARDS AS THEY APPEAR IN THE
"NC EROSION CONTROL PLANNING AND DESIGN
MANUAL" AND ARE APPLICABLE TO THIS PROJECT AND
BY REFERENCE HEREBY ARE CONSIDERED PART OF
THE PLANS.
6.06 TEMPORARY GRAVEL CONSTRUCTION ACCESS
6.60 TEMPORARY SEDIMENT TRAP
6.62 SILT FENCE
6.63 TEMPORARY ROCK DAM
SCALE IN FEET
0 500 1000
REFERENCE
1. TOPOGRAPHIC INFORMATION BASED UPON SURVEY CONDUCTED BY WITHERSRAVENEL,
IN OCTOBER 2016.
2. COORDINATE SYSTEM IS NAD 83 NORTH CAROLINA STATE PLANE FEET.
3. AERIAL IMAGERY SHOWN ON ALL PLAN SHEETS ARE FROM: USGS BING IMAGES
2017
N 36.068361' �..
W-78.832875' 3
�nD��r rii,� 4 ��ifPt[05,�5
4
coz
x
sts lqd
Weaver
nor Redwo
:sot Gorman
Cbftli Rd
,`
l it ® 2010• NAVTEQ AND ®2017 Microsoft Corporation Y
VICINITY MAP
SCALE IN FEET
0 5000 ,0000
PROJECT LENGTH
REACH
EXISTING (LF)
PROPOSED (LF)
M1
519
535
M2
865
914
M3
1,500
1,427
UT1
364
356
UT2
226
200
UT3
159
172
TOTAL
3,633
3,604
1
D
0
W
0
MAY 2 6 2017 Z
H
ul
cc
ENGINEER
CIVIL & ENVIRONMENTAL CONSULTANTS, INC.
250 OLD WILSON BRIDGE ROAD, SUITE 250
WORTHINGTON, OHIO 43085
PHONE: (614) 540-6633
CONTACT: JOSHUA WHITE
EMAIL: jwhite@cecinc.com
SURVEYOR
WITHERSRAVENEL
115 MACKENAN DRIVE
CARY, NC 27511
PHONE: (919) 469-3340
CONTACT: MARSHALL WIGHT, PLS
PREPARED FOR
DURHAM SOIL & WATER
CONSERVATION DISTRICT
721 FOSTER STREET
DURHAM, NC 27701
PHONE: (919) 560-0558
CONTACT: EDDIE CULBERSON
DURHAM
SOIL & WATER
DNS EBVATIL
\N +CA 1/11�
. o off. si •yy.'
SEAL T.
39208
•,,syr • . • � �.
i�///A A'r\e\\
FOR PERMITTING PURPOSES
NOT FOR CONSTRUCTION
T
MNG NO A
EC000
ET i OF 16
1
0:1
;B
'A
CONSTRUCTION SEQUENCE
A CEC PROJECT MANAGER WILL PROVIDE CONSTRUCTION QUALITY ASSURANCE DURING THE
CONSTRUCTION PHASE OF THIS PROJECT. THE FOLLOWING CONSTRUCTION SEQUENCE SHALL
BE USED DURING IMPLEMENTATION OF THE PLAN.
1. PRIOR TO BEGINNING ANY LAND DISTURBING ACTIVITIES, NOTIFICATION AND APPROVAL MUST
BE GRANTED FROM US ARMY CORP OF ENGINEERS AND NCDWR DIVISION OF WATER
QUALITY.
2. THE CONTRACTOR SHALL CONTACT NORTH CAROLINA 811 CENTER (1.800.632.4949) AND
LAND QUALITY (919.791.4200) BEFORE ANY EXCAVATION.
3. THE CONTRACTOR WILL MOBILIZE EQUIPMENT AND MATERIALS TO THE SITE BY INSTALLING
AND USING THE CONSTRUCTION ENTRANCE (THAT ARE SHOWN ON THE PLANS) OFF HAMLIN
AND MORTON ROADS.
4. THE CONTRACTOR WILL UTILIZE THE HAUL ROADS AND STREAM CROSSING AS SHOWN ON
THE PLANS. CONSTRUCTION TRAFFIC SHALL BE RESTRICTED TO THE AREA DENOTED AS
'UMITS OF DISTURBANCE'ON THE CONSTRUCTION PLANS.
5. THE CONTRACTOR SHALL INSTALL TEMPORARY SILT FENCE AROUND THE STAGING AREAS.
THE CONTRACTOR WILL NOT PLACE EXCAVATED FILL INTO THE OLD CHANNEL UNTIL THE
NEW CHANNEL IS COMPLETE AND WATER HAS BEEN DIVERTED INTO THE NEW CHANNEL.
6. THE CONTRACTOR SHALL INSTALL ALL TEMPORARY STREAM CROSSINGS AS SHOWN ON
PLANS IN ACCORDANCE WITH THE NC EROSION AND SEDIMENT CONTROL PLANNING AND
DESIGN MANUAL. DITCHES AND STREAM REACHES ON SITE WILL BE LEFT OPEN DURING
THE INITIAL STAGES OF CONSTRUCTION TO ALLOW FOR DRAINAGE AND TO KEEP SITE
ACCESSIBLE.
7. CONTRACTOR SHALL BEGIN CONSTRUCTION ON EACH STREAM REACH AND COMPLETE THAT
SPECIFIC STREAM REACH BEFORE MOVING TO THE NEXT REACH. THE NEW CHANNEL
SECTIONS SHALL BE LEFT OPEN ON THE DOWNSTREAM END TO ALLOW FOR DRAINAGE
DURING RAIN EVENTS. AT NO TIME WILL CLEARING AND GRUBBING PROGRESS BEYOND
THE SECTION OF CHANNEL THAT IS BEING CUT UNLESS WORKING WITH MORE THAN ONE
CREW (I.E. CANNOT REMOVE TREES ON BETWEEN STATIONS 14+22 TO 16+00 WHEN YOU
ARE WORKING BETWEEN STATIONS 10+00 TO 14+00 ALONG THE MAIN STEM).
8. MAJORITY OF THE PROJECT IS ONLINE CONSTRUCTION, CONTRACTOR WILL INSTALL TYPICAL
PUMP AROUND OPERATION WHEN SUFFICIENT FLOW IS PRESENT.
MAINSTEM OF UT TO FALLS LAKE (Ml M2 M3) & TRIBS (UTI UT2 UTZ) CONSTRUCTION
9. ONCE STAGING AND TEMPORARY E ORARY CROSSINGS ARE COMPLETE, THE CONTRACTOR WILL START
WITH UT2. UT2 IS AN EPHEMERAL CHANNEL AND TYPICALLY DOESN'T FLOW. IF
SUFFICIENT FLOW IS PRESENT, THEN A PUMP -AROUND IS NEEDED (SEE /22 AND #23
FOR PUMP -AROUND INSTRUCTIONS).
10. ONCE THE SECTIONS OF UTZ HAVE BEEN EXCAVATED TO DESIGN GRADES, INSTALL
IN -STREAM STRUCTURES, INSTALL 10' CHANNEL PLUGS (STATION 11+00 AND 11+35),
SEED AND MAT, AND READY THE CHANNEL TO ACCEPT FLOW. ONE REACH SHOULD BE
COMPLETE WITH ALL STRUCTURES, SEED, AND MATTING BEFORE MOVING ONTO THE NEXT
REACH.
11. THE CONTRACTOR WILL MOVE TO LITT WHEN UT2 IS COMPLETE. UTI IS ALSO AN
EPHEMERAL CHANNEL AND TYPICALLY DOESN'T FLOW. IF SUFFICIENT FLOW IS PRESENT,
THEN A PUMP -AROUND IS- NEEDED (_SEE #22 AND #23 FOR PUMP -AROUND
INSTRUCTIONS).
12. ONCE THE SECTIONS OF UT1 HAVE BEEN EXCAVATED TO DESIGN GRADES, INSTALL
IN -STREAM STRUCTURES, INSTALL 10' CHANNEL PLUGS (STATION 12+15 AND 12+50),
SEED AND MAT, AND READY THE CHANNEL TO ACCEPT FLOW. ONE REACH SHOULD BE
COMPLETE WITH ALL STRUCTURES, SEED, AND MATTING BEFORE MOVING ONTO THE NEXT
REACH.
13. THE CONTRACTOR WILL MOVE TO M1 WHEN LITT IS COMPLETE. M1 IS ALSO AN
EPHEMERAL CHANNEL AND TYPICALLY DOESN'T FLOW. IF SUFFICIENT FLOW IS PRESENT,
THEN A PUMP -AROUND IS NEEDED (SEE /22 AND #23 FOR PUMP -AROUND
INSTRUCTIONS).
14. ONCE THE SECTIONS OF Mi HAVE BEEN EXCAVATED TO DESIGN GRADES, INSTALL
IN -STREAM STRUCTURES, INSTALL 10' CHANNEL PLUGS (STATION 12+00 AND 12+25)
SEED AND MAT, AND READY THE CHANNEL TO ACCEPT FLOW. ONE REACH SHOULD BE
COMPLETE WITH ALL STRUCTURES, SEED, AND MATTING BEFORE MOVING ONTO THE NEXT
REACH.
15. THE CONTRACTOR WILL MOVE TO M2 WHEN MI IS COMPLETE. M2 IS ALSO AN
EPHEMERAL CHANNEL AND TYPICALLY DOESN'T FLOW. IF SUFFICIENT FLOW IS PRESENT,
THEN A PUMP -AROUND IS NEEDED (SEE -/22 AND #23 FOR PUMP -AROUND
INSTRUCTIONS).
16. ONCE THE SECTIONS OF M2 HAVE BEEN EXCAVATED TO DESIGN GRADES, INSTALL
IN -STREAM STRUCTURES, INSTALL 10' CHANNEL PLUGS (STATION 17+85, 21+65, 21+95,
22+65, 22+90, 23+45, AND 24+15), SEED AND MAT, AND READY THE CHANNEL TO
ACCEPT FLOW. ONE REACH SHOULD BE COMPLETE WITH ALL STRUCTURES, SEED, AND
MATTING BEFORE MOVING ONTO THE NEXT REACH.
17. THE CONTRACTOR WILL MOVE TO M3 WHEN M2 IS COMPLETE. M3 IS AN INTERMITTENT
CHANNEL AND FLOWS SOMETIMES THROUGHOUT THE YEAR. IF SUFFICIENT ROW IS
PRESENT, THEN A PUMP -AROUND IS NEEDED (SEE #22 AND #23 FOR PUMP -AROUND
INSTRUCTIONS).
18. ONCE THE SECTIONS OF M3 HAVE BEEN EXCAVATED TO DESIGN GRADES, INSTALL
IN -STREAM STRUCTURES, INSTALL 10' CHANNEL PLUGS (STATION 24+80, 26+65. 34+00,
36+25, AND 36+80), SEED AND MAT, AND READY THE CHANNEL TO ACCEPT ROW. ONE
REACH SHOULD BE COMPLETE WITH ALL STRUCTURES, SEED, AND MATTING BEFORE
MOVING ONTO THE NEXT REACH.
19. THE CONTRACTOR WILL MOVE TO UT3 WHEN M3 IS COMPLETE. UT3 IS ALSO AN
EPHEMERAL CHANNEL AND TYPICALLY DOESN'T ROW. IF SUFFICIENT ROW IS PRESENT,
THEN A PUMP -AROUND IS NEEDED (SEE /22 AND /23 FOR PUMP -AROUND
INSTRUCTIONS).
20. ONCE THE SECTIONS OF UT3 HAVE BEEN EXCAVATED TO DESIGN GRADES, INSTALL
IN -STREAM STRUCTURES, SEED AND MAT, AND READY THE CHANNEL TO ACCEPT ROW.
ONE REACH SHOULD BE COMPLETE WITH ALL STRUCTURES, SEED, AND MATTING BEFORE
MOVING ONTO THE NEXT REACH.
21. IMMEDIATELY UPON COMPLETION OF BANK GRADING, THE SLOPE WILL BE RESEEDED,
MULCHED, AND MATTED WITH EROSION CONTROL FABRIC. THE CONTRACTOR SHALL ONLY
WORK IN AREAS THAT CAN BE SEEDED, MULCHED, AND MATTED WITHIN THE SAME DAY.
22. THE SECTIONS ALONG LITT (10+00 TO 13+56), UT2 (10+00 TO 12+00), UT3 (10+00 TO
11+72), AND ALONG THE MAINSTEM (10+00 TO 38+76), ARE AREAS OF STRUCTURE
INSTALLATION AND REQUIRE THE USE OF A TEMPORARY PUMP -AROUND OPERATION WHEN
SUFFICIENT ROW IS PRESENT. PUMP -AROUND OPERATIONS ARE TO BE USED IN ORDER
TO DIVERT ROW AROUND THE STREAM SECTION BEING CONSTRUCTED TO THE EXISTING
CHANNEL DOWNSTREAM. THE CONTRACTOR SHALL INSTALL TEMPORARY ROCK DAMS AND
PUMP -AROUND OPERATIONS WHENEVER ROW IS SUFFICIENT. THE PORTION OF THE
CHANNEL ISOLATED SHALL BE DEWATERED AND THE REMOVED WATER SHALL ROW
THROUGH A SPECIAL STILUNG BASIN. THE CONTRACTOR WILL NOT PLACE EXCAVATED FILL
INTO THE OLD CHANNEL UNTIL THE NEW CHANNEL IS COMPLETE AND WATER HAS BEEN
DIVERTED INTO THE NEW CHANNEL.
CONSTRUCTION SEQUENCE (CONTINUED)
23. ONCE CONSTRUCTION IN A PUMP -AROUND AREA HAS BEEN COMPLETED, REMOVE ALL
PUMP -AROUND MATERIALS AND TURN THE WATER INTO THE NEW CHANNEL.
24. UPON COMPLETION OF THE NEW CHANNEL, ALL DISTURBED FLOODPLAIN AREAS INCLUDING
STAGING AREAS AND HAUL ROADS, SHALL BE SEEDED AND COVERED WITH MULCH. TREES
SHALL BE PLANTED IN ACCORDANCE WITH THE PLANTING PLAN. PERMANENT SEEDING
MIXTURES SHALL BE APPLIED AS SHOWN ON THE VEGETATION PLAN. TEMPORARY SEEDING
SHALL BE APPLIED IN ALL AREAS SUSCEPTIBLE TO EROSION (I.E. DISTURBED DITCH BANKS,
STEEP SLOPES, AND SPOIL AREAS) SUCH THAT GROUND COVER IS ESTABLISHED WITHIN 21
WORKING DAYS FOLLOWING COMPLETION OF ANY PHASE OF GRADING. PERMANENT
GROUND COVER SHALL BE ESTABLISHED FOR ALL DISTURBED AREAS WITHIN 15 WORKING
DAYS OR 90 CALENDAR DAYS (WHICHEVER IS SHORTER) FOLLOWING COMPLETION OF
CONSTRUCTION.
25. ALL AREAS SHOULD BE SEEDED AND MULCHED BEFORE LEAVING THE PROJECT REACH.
REMOVE TEMPORARY STREAM CROSSINGS. ALL WASTE MATERIAL MUST BE REMOVED FROM
THE PROJECT REACH.
26. THE CONTRACTOR SHALL ENSURE THAT THE REACH IS FREE OF TRASH AND LEFTOVER
MATERIALS PRIOR TO MOBILIZATION OF EQUIPMENT FROM THE REACH.
SPECIAL NOTES FOR NATURAL STREAM DESIGN
A. AS -BUILT DRAWINGS - DURING CONSTRUCTION, THE CONTRACTOR AND THE ENGINEER
SHALL WORK TOGETHER TO MAINTAIN A SET OF PRINTS SHOWING ANY CHANGES OR
CORRECTIONS IN RED. THESE PRINTS SHALL BE SUBMITTED TO THE ENGINEER AT THE
COMPLETION OF THE WORK.
B. STREAM RESTORATION DEFINITIONS
I. BANKFULL ELEVATION - BANKFULL ELEVATION IS THE POINT OF INCIPIENT FLOODING IN AN
ALLUVIAL CHANNEL.
2. FLOODPLAIN SIL - A FLOODPLAIN SILL IS THE BURIED EXTENSION OF THE STRUCTURE
AND IS PERPENDICULAR TO THE FLOW DIRECTION OF THE BANKFULL CHANNEL ACROSS
THE BANKFULL BENCH OR FLOODPLAIN
3. FOOTER BOULDERS - FOOTER BOULDERS ARE PLACED TO PROVIDE A FOUNDATION FOR
THE SURFACE BOULDERS IN EACH HYDRAULIC STRUCTURE. THE LOWEST COURSE OF
FOOTER BOULDERS ARE BURIED IN THE CHANNEL TO A DEPTH BELOW THE CALCULATED
OR MEASURED SCOUR DEPTH. FOOTER BOULDERS SHALL BE DURABLE LIMESTONE WITH
DIMENSIONS SHOWN IN THE DETAILS. TYPICALLY, FOOTER BOULDERS ARE BURIED IN THE
CHANNEL BOTTOM AND NOT SEEN WHEN THE STRUCTURE IS COMPLETED. ALL SURFACE
BOULDERS FOR ALL STRUCTURES REQUIRE FOOTER BOULDERS UNLESS BEDROCK IS
ENCOUNTERED AT THE PROPOSED ELEVATION OF FOOTER BOULDERS.
4. SURFACE BOULDERS - SURFACE BOULDERS ARE THE TOP -MOST COURSE OF BOULDERS
USED IN EACH CROSS -VANE OR OTHER ROCK STRUCTURE. ALL SURFACE BOULDERS CAN
BE SEEN PROTRUDING FROM THE WATER SURFACE DURING EXTREMELY LOW FLOWS.
SURFACE- BOULDERS SHALL BE DURABLE LIMESTONE WITH DIMENSIONS SHOWN IN THE
DETAILS.
5. THALWEG - THE THALWEG IS THE LOWEST POINT OF THE BANKFULL CHANNEL DESCRIBED
BY THE STREAM PROFILE. THIS ELEVATION IS THE REFERENCE FOR ALL ELEVATIONS ON OR
ALONG THE CHANNEL AND HYDRAULIC STRUCTURES DESCRIBED IN THIS SECTION AND IN
THE PROJECT DRAWINGS.
6. VANE ANGLE - THE VANE ANGLE IS THE SMALLEST ANGLE MEASURED BETWEEN A VANE
AND A LINE TANGENT TO THE BANKFULL ELEVATION AT THE POINT WHERE THE VANE
INTERSECTS THE BANK. THE VANE ANGLE SHALL BE BETWEEN TWENTY PERCENT (20%)
AND THIRTY PERCENT (30%), OR AS SPECIFIED IN THE STREAM RESTORATION DATA TABLE.
7. VANE LENGTH - THE VANE LENGTH IS THE DISTANCE BETWEEN THE UPSTREAM LIMIT OF
THE VANE ARM AT THE CHANNEL BED TO THE DOWNSTREAM INSERTION POINT OF THE
VANE ARM INTO THE STREAM BANK.
8. VANE SLOPE - THE VANE SLOPE IS THE SLOPE OF THE VANE ARM FROM THE UPSTREAM
LIMIT AT THE CHANNEL BED TO THE DOWNSTREAM INSERTION POINT OF THE VANE ARM
INTO THE STREAM BANK. THE VANE SLOPE SHALL BE BETWEEN TWO PERCENT (2%)
AND SEVEN PERCENT (7%) OR AS SPECIFIED IN THE STREAM RESTORATION DATA TABLE
AND THE VANE ARMS SHALL TIE INTO THE BANKS AT HALF TO THREE QUARTERS OF THE
13ANKFULL ELEVATION.
9. SUBSTRATE RESTORATION - SUBSTRATE RESTORATION IS DESIGNED TO REPLACE AND
RESTORE COARSE SUBSTRATE (GRAVEL,. COBBLE, AND BOULDER) TO THE STREAM CHANNEL
IN CASES WHERE COARSE SUBSTRATES OR BEDROCK ARE ABSENT FOLLOWING CHANNEL
EXCAVATION. THE PURPOSE OF SUBSTRATE RESTORATION IS TO PROVIDE NATURAL
SUBSTRATE AND EROSION AND SCOUR PROTECTION IN THE CHANNEL.
10. BASE BLOW - FOR THE PURPOSE OF THESE STREAM DESIGN SPECIFICATIONS, A FLOW
EQUAL TO ONE CUBIC FOOT PER SECOND PER SQUARE MILE OF DRAINAGE AREA.
C. FLOODPLAIN AND CHAN EL CONS�UCTION
1. THE CONTRACTOR SHALL STAKE OUT THE PROPOSED STREAM CENTERLINE AND STRUCTURE
LOCATIONS FOR APPROVAL BY THE ENGINEER BEFORE INITIATING EXCAVATION. DEPENDING
ON THE SITE CONDITIONS, SOME SHIFTING OF THE STREAM CHANNEL AND VANE
STRUCTURES MAY BE NECESSARY. ANY COST ASSOCIATED WITH CHANGING CHANNEL
ALIGNMENT AND STRUCTURE LOCATIONS SHALL BE CONSIDERED INCIDENTAL TO
CONSTRUCTION.
2. THE PROPOSED STREAM CHANNEL SHALL BE CONSTRUCTED BY FIRST EXCAVATING THE
FLOODPLAIN TO THE ELEVATIONS AND DIMENSIONS SPECIFIED ON THE STREAM MITIGATION
GRADING PLAN. THE PROPOSED STREAM CHANNEL SHALL THEN BE EXCAVATED TO THE
PROPER DEPTHS INDICATED ON THE PROFILE AND CROSS-SECTIONS. THIS SHALL BE DONE
AS UNCLASSIFIED EXCAVATION AND IS TYPICALLY ACCOMPLISHED WITH A TRACK EXCAVATOR
WITH HYDRAULIC THUMB. ANY STOCKPILING OR DOUBLE -HANDLING OF MATERIALS
NECESSARY TO BUILD THE CHANNEL SHALL BE CONSIDERED INCIDENTAL TO CONSTRUCTION.
D. FILTER FABRIC
1. NON -WOVEN FILTER FABRIC SHALL ONLY BE USED WHEN COVERING THE ROCK SECTION
OF A STRUCTURE. CONTRACTOR SHALL USE US FABRICS US205NW FABRIC OR EQUIVALENT.
2. WOVEN FILTER FABRIC SHALL ONLY BE USED WHEN COVERING THE WOODY SECTION OF A
STRUCTURE. CONTRACTOR SHALT. USE US FABRICS US315 FABRIC OR EQUIVALENT.
- ALL DEFINITIONS MAY NOT BE USED ON THIS PROJECT
GENERAL NOTES
WORK THIS PLAN SET WITH THE EROSION AND SEDIMENT CONTROL PLANS.
CONTRACTOR SHALL REVIEW ALL APPLICABLE PERMITS FOR THIS PROJECT AND ALL WORK
SHALL BE IN STRICT CONFORMANCE WITH THE CONDITIONS OF EACH PERMIT.
RNIN - SP IFI eVONS
THE NORTH CAROLINA EROSION AND SEDIMENT CONTROL PLANNING AND DESIGN MANUAL,
DATED MAY 2013, SHALL BE THE GOVERNING PROVISIONS FOR STORMWATER POLLUTION
PREVENTION ASSOCIATED WITH CONSTRUCTION ACTIVITIES.
BENCH MARKS
THE CONTRACTOR SHALL BE RESPONSIBLE FOR HOLDING BENCH MARK LOCATIONS
THROUGHOUT THE LIFE OF THE PROJECT. IN THE EVENT THAT A BENCH MARK IS DISTURBED,
THE CONTRACTOR, AS DIRECTED BY THE ENGINEER, WILL RELOCATE OR REESTABLISH THE
BENCH MARK. NO ADDITIONAL PAYMENT OR COMPENSATION WILL BE MADE FOR THIS WORK.
ELEVATIONS
ALL ELEVATIONS SHOWN REFER TO THE NATIONAL GEODETIC VERTICAL DATUM OF 1988 (NGVD
88)
COORDINATES
THE PROJECT DATUM ON THESE PLANS ARE BASED UPON THE SOUTH ZONE OF THE NORTH
CAROLINA STATE PLANE SYSTEM. THE HORIZONTAL DATUM IS BASED ON THE NORTH
AMERICAN DATUM OF 1983 (NAD 83). GRID FACTORS ARE NOT REQUIRED WHEN MAKING
FIELD MEASUREMENTS.
VERIFICATIONS OF DIMENSIONS
THE CONTRACTOR IS RESPONSIBLE FOR VERIFICATION OF ALL PLAN AND ELEVATION
DIMENSIONS PRIOR TO ORDERING MATERIALS FOR THE CONSTRUCTION OF THE VARIOUS BID
ITEMS IN THIS CONTRACT.
WASTE MATERIAL
ALL MATERIAL EXCAVATED AND NOT REUSED IN THE CONSTRUCTION OF THIS PROJECT SHALL
BE REMOVED FROM THE PROJECT AND DISPOSED OF BY THE CONTRACTOR.
FILTER FABRIC
FILTER FABRIC SHALL BE PLACED BELOW ALL DUMP ROCK GUTTERS AND SCOUR BASINS AND
AT ALL LOCATIONS INDICATED ON THE TYPICALS.
Intl ITIFC
THE CONTRACTOR IS RESPONSIBLE FOR THE INVESTIGATION, LOCATION, SUPPORT, PROTECTION,
AND RESTORATION OF ALL EXISTING UTILITIES AND APPURTENANCES WHETHER SHOWN ON
THESE PLANS OR NOT. IT IS THE CONTRACTOR'S RESPONSIBILITY TO ASCERTAIN THE STATUS
AND LOCATION OF EACH UTILITY WHEN PERFORMING WORK WHICH MAY AFFECT THESE
FACILITIES, INCLUDING PROBING, EXCAVATION, OR ANY OTHER PRECAUTION REQUIRED TO
CONFIRM LOCATION. THE CONTRACTOR SHALL EXPOSE ALL UTILITIES OR STRUCTURES PRIOR TO
CONSTRUCTION TO VERIFY THE VERTICAL AND HORIZONTAL EFFECT ON PROPOSED
CONSTRUCTION. THE CONTRACTOR SHALL CALL, TOLL FREE, NORTH CAROLINA 811
(1-800-632-4949) TWO DAYS PRIOR TO CONSTRUCTION AND SHALL NOTIFY ALL UTILITY
COMPANIES AT LEAST 48 HOURS PRIOR TO WORK IN THE VICINITY OF THEIR UNDERGROUND
LINES. THE CONTRACTOR WILL BE RESPONSIBLE FOR ANY DAMAGE OR DISRUPTION TO UTILITY
LINES WHICH ARE KNOWN ACTIVE AND ARE TO REMAIN IN OPERATION.
EROSION AND SEDIMENT CONTROL
DETAILS NOT SHOWN IN THE PLANS SHALL BE IN ACCORDANCE WITH THE NORTH CAROLINA
EROSION AND SEDIMENT CONTROL PLANNING AND DESIGN MANUAL, DATED MAY 2013. IN THE
EVENT THAT THE TEMPORARY EROSION AND POLLUTION CONTROL MEASURES ARE ORDERED BY
THE ENGINEER DUE TO THE CONTRACTOR'S NEGLIGENCE, CARELESSNESS, OR FAILURE TO
INSTALL PERMANENT CONTROLS AS PART OF THE WORK AS SCHEDULED. SUCH WORK SHALL
BE PERFORMED BY THE CONTRACTOR AT HIS OWN EXPENSE.
THE FIRST ORDER OF WORK FOR THE CONTRACTOR IS TO INSTALL SEDIMENT CONTROL
STRUCTURES, SILT FENCE, ETC. TO ESTABLISH EROSION CONTROL AT THE EARLIEST POSSIBLE
DATE. INITIAL CLEARING AND GRUBBING IS TO ONLY BE WHAT IS NECESSARY IN ORDER TO
ACCOMPLISH THESE OPERATIONS.
IN ADDITION, THE 'CONTRACTOR IS TO NAME AN INDIVIDUAL TO REVIEW THE EROSION CONTROL
FEATURES AT A MINIMUM OF ONCE A WEEK DURING PERIODS OF HEAVY PRECIPITATION
AND/OR ACTIVE CONSTRUCTION TO ASSESS THE SUCCESS OF THE EROSION CONTROL
STRUCTURES, REVEGETATION EFFORTS, AND SEE THAT REPLACEMENT, CLEANING, AND/OR
INSTALLATION OF ADDITIONAL FEATURES IF NECESSARY ARE CARRIED OUT.
MAINTENANCE SHALL BE IN ACCORDANCE WITH THE NORTH CAROLINA EROSION AND SEDIMENT
CONTROL PLANNING AND DESIGN MANUAL, DATED MAY 2013.
FEDERA STAT AND O e AWS ANO S �ETY R ATIONS
THE CONTRACTOR AND ANY SUB -CONTRACTORS SHALL CONFORM TO APPLICABLE OSHA SAFETY
REGULATIONS. THE CONTRACTOR AND ANY SUB -CONTRACTORS SHALL BE SOLELY RESPONSIBLE
FOR COMPLYING WITH ALL FEDERAL, STATE, AND LOCAL SAFETY REQUIREMENTS TOGETHER WITH
EXERCISING PRECAUTIONS AT ALL TIMES FOR THE PROTECTION OF PERSONS INCLUDING
EMPLOYEES AND PROPERTY. IT IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR AND
SUB -CONTRACTOR TO INITIATE, MAINTAIN, AND SUPERVISE ALL SAFETY REQUIREMENTS,
PRECAUTIONS, AND PROGRAMS IN CONNECTION WITH THE WORK.
CLEARING & GRUBBING LIMITS
CLEARING LIMITS SHALL BE EXTENDED TO A MAXIMUM LIMIT NECESSARY FOR CONSTRUCTION
MATERIALS AND SHALL NOT EXTEND BEYOND CONSTRUCTION BOUNDARIES WHERE EARTHWORK
ACTIVITIES ARE TO BE PERFORMED. GRUBBING SHALL ONLY TAKE PLACE WITHIN THE AREA AS
NECESSARY. ALLCOSTS ASSOCIATED WITH CLEARING & GRUBBING SHALL BE CONSIDERED
INCIDENTAL TO BID ITEM CLEARING AND GRUBBING.
LAND QUALITY E&S GROUND COVER STABILIZATION
NOTIFICATION OF LAND RESOURCES SEDIMENT &
EROSION CONTROL SELF -INSPECTION PROGRAM
THE SEDIMENTATION POLLUTION CONTROL ACT WAS AMENDED IN
2006 TO REQUIRE THAT PERSONS RESPONSIBLE FOR
LAND -DISTURBING ACTIVITIES INSPECT A PROJECT AFTER EACH
PHASE OF THE PROJECT TO MAKE SURE THAT THE APPROVED
EROSION AND SEDIMENTATION. CONTROL PLAN IS BEING FOLLOWED.
RULES DETAILING THE DOCUMENTATION OF THESE INSPECTIONS
TAKE EFFECT OCTOBER 1, 2010. THE SELF -INSPECTION PROGRAM
IS SEPARATE FROM THE WEEKLY SELF-MONITORING PROGRAM OF
THE NPDES STORMWATER PERMIT FOR CONSTRUCTION ACTIVITIES.
THE FOCUS OF THE SELF -INSPECTION REPORT IS THE INSTALLATION
AND MAINTENANCE OF EROSION AND SEDIMENTATION CONTROL
MEASURES ACCORDING TO THE APPROVED PLAN. THE INSPECTIONS
SHOULD BE CONDUCTED AFTER EACH PHASE OF THE PROJECT,
AND CONTINUED UNTIL PERMANENT GROUND COVER IS
ESTABLISHED. THE SELF -INSPECTION REPORT FORM WILL ALSO BE
AVAILABLE AS AN EXCEL SPREADSHEET FROM THE LAND QUALITY
WEB SITE. HTTP://PORTAL.NCDENR.ORG/WEB/LR/EROSION. IF YOU
HAVE QUESTIONS, PLEASE CONTACT THE LAND QUALITY SECTION AT
A DEO REGIONAL OFFICE AT 919.791.4200.
1. THE CONTRACTOR IS REQUIRED TO INSTALL INSTREAM
STRUCTURES USING A TRACK HOE WITH A HYDRAULIC
THUMB OF SUFFICIENT SIZE TO PLACE (3' X 2' X 1')
BOULDERS, LOGS, AND ROOTWADS.
2. WORK IS BEING PERFORMED AS AN ENVIRONMENTAL
RESTORATION PLAN. THE CONTRACTOR SHOULD MAKE ALL
REASONABLE EFFORTS TO REDUCE SEDIMENT LOSS AND
MINIMIZE DISTURBANCE OF THE SITE WHILE PERFORMING
THE CONSTRUCTION WORK.
3. CONSTRUCTION IS SCHEDULED TO BEGIN SUMMER 2017.
4. CONTRACTOR SHOULD CALL NORTH CAROLINA 811 BEFORE
EXCAVATION STARTS. (1-800-632-4949)
5. CONTRACTOR IS RESPONSIBLE FOR RESTORATION OF ACCESS
AREA AND LIABLE FOR DAMAGES TO EXISTING STI UTILITIES IN
ACCESS AREA.
6. CONTRACTOR WILL INSPECT THE DEPTH OF THE UTILITIES
AND IS RESPONSIBLE FOR 0 MAKING SURE THE LINES ARE
PROTECTED DURING CONSTRUCTION.
7. CONTRACTOR IS RESPONSIBLE FOR INSTALLING SAFETY /
WARNING SIGN ADJACENT TO ALL CONSTRUCTION ENTRANCES.
STRUCTURES LEGEND
TOE WOOD W/BRUSH LAYERING
® ROCK CONSTRUCTED RIFFLE
LOG VANE, ROCK J -HOOK AND ROOT WAD
ROCK J -HOOK
BOULDER CASCADE
ROOT WAD
SEDIMENT & EROSION CONTROL LEGEND
S - SILT FENCE
KEW STAORMATION TIMEFRAMES
Site Area Deser"on
Stabilization
Timetrame Exceptions
OPerimeter Chkes, swales, ditches anc slopes
7 days
None
�I High Quality Water (HQW) Zones
7 days
None
Slopes steeper than 3� 1
7 days
It slopes are i0' or less in length and are not
steeper than 2:1, 14 days are allowed.
F- Slopes 3:1 or ffatter
14 days
7 days for siopes greater than 50' in length.
0. AN other areas with slopes flatter than 4:1
14 days
None, except for perimeters and HOW Zones. I
GROUNDCOVER SHALL BE IN ACCORDANCE WITH NPDES CONSTRUCTION
STORMWATER GENERAL PERMIT NCGO10000 AND PERMANENT GROUNOCOVER FOR
ALL DISTURBED AREAS WITHIN 15 WORKING DAYS OR 90 CALENDAR DAYS
(WHICHEVER IS SHORTER) FOLLOWING COMPLETION OF CONSTRUCTION OR
DEVELOPMENT.
- TEMPORARY CONSTRUCTION ENTRANCE
ROCK DAM
- TEMPORARY STREAM CROSSING
����lll6lll6®®
CAR����
AL
39208 n o
I I
it •��y�.�
/� O� •. Cil NE ®i
O
IY
O
W
2
Z
O
H
2
W Q
W J
a a D
Z
WOU
°dal=x
O cc cc oC
chaOO
�a Z
cc
i C
W
In
EC100
R 2 IF16
m
r/1 =
O
CF
4 o
453� F
L
o m
U E
a
I
C o m
N
ii fA ra v
1 ,
o o
¢ N
0
ii ern 'r
.r 'o m
m
E
W
,'a O
o
N
W Q
W J
a a D
Z
WOU
°dal=x
O cc cc oC
chaOO
�a Z
cc
i C
W
In
EC100
R 2 IF16
a:l
'1
_D,
` \
N ///
0.7w�w`���
�.A r
�D:� MoD •Dd
i 4•l�
Co
ter' d. ••'�
L7 x
1
A$
m
d
m
m
d m
d
8 g
�
A A
U
D G
U
G W
A
q •Y
T p
4 0�
�
S S'.
3
m
g F
� �
�
g
'�m
£ 8
� �
�
01
�
ii
'oA
o
$
,�
� 3
_
�
M �
F
� �
m
� �
� �
"r S
iS �
�
B, fi
�
3 ,Q�
�
E.
�
o•�
N �
3 �
ry
g
�
4
'o
o
R
u
N
�•
?
o
s
A
_�
O
s
#D y
e
3 a
@q
a
Y }n
c
EQQl
g
a
V
F
$
m
2
O
y
A
g
c�
e#
u B
a
W
€
g
n
3
A
O W
O W
A
•� N
W P
W
A
P W
l0
p H
CD O
,g
Qs0 N
P+
H W
fJ W
yl O
pp
Ip
P
D+
V
P W
P+
N (•
N O
N+
N+
N P
Q
p We
$
O
O
g
p ��
Q
y
l�l
4y1
S
w
N
o p
O
$
O N
((UNllOI��
p
tp UI
41 O
W O
W
N IJ
O W
P J
9
V�
q
W N
J
W
V N
V
N p pp
p p
(4�ttWWfWANH41
W
W O.
V W
N-4
> `�
+
+ O
W+
N P
�. J+
O+
O
N N
P O
W3OV
m
g
A
IP
4
V Q
to p
W O
W
O Yl
G W
IV
N
pO
O$
O
O H
_
A
[1 N
O N
E+
Q
N B
Gl W
9
rp
lJ
IIV�l
N y
W N+
P
W N+
O H
IJ O
C
p p
N A
W
�o C'1
[V o
V fWli
A,
? W+
W
(y
O
N m+
W N
V W
4l O
N W
N+
N+
N P
W O
0 T
A
p
m
a
m
k
O
P W
G 8
41
W
O W
O N
O A
G
W O
a
C
o g
O O
OcH
U1
+
G
P+
ip IA
J N
Y O
m N
G1 O
W
Go
N u
(n H
N?+
O W
J
A
;
-
R
N
V ,j
V IJ
W
tJ
-V G
W
Op
N O
OO
O W
p
R,
OO p
+ W
N
!p�jer1
IU 2S
�
41 0
V W
IG O
V W
N
W>
N G
4 W
O N
G N
O O
N W
N
GI N
N
N N
G p
b P
S
a
O
P'
Ul J
G
J G
IPII P
N p
S
p N
G W
N
�[
P
O Q P
O P
+
+p O
O+
N+
+ W
m
b
fUl1�
N V
N A
V
O
P P
V
O o
O
O W
Q
N
Q Q
r� jj��^
P+
t0
J
W C
m 0
p G
0 P
G
r W
H
N N
Z Z
N P
P N
W P+
PPi
+ N
O+
�,
N O
-
N W
P
O W
m
?�
,4�i W
:14
fi
Z5
W
J
G$
<!� �
C
IO N
41 O
W
W
VV �Wp
o g
W W
P V
V
O
N W
J
O + W+
§
p+p
p O
j
V
W
p W.
p W
p N
jp
W +W
A+
W+
O
W+
N P+
V+
O+
O
N
O1
O
O
O
H
O
O
W
+
K
�
Sn
1p
tJ C+
iD H
N
W W
V
O
P
W N
W W
V
O
1135
o Q
W
p
A
O
W �I
W
>
N
iD W+
xi ap
O
o W
W W
v W
�, N
H A
N W
A
J
1NJ
P N
O W
Z Z
J N
A IJ
fly N
P A
N J+
i0 IJ
W
IJ W
W++
W
Gl V
O
V Ill
N
p
N O
V P
W T
A
NA
=
a
3
"a_
OR
W
N
Ol N
N m
W
N
oo
+ N
O
G
��pp
A c.
W
4{lll
V
ffJJ
w
P b
3
3
N
V
O O
o OOb
0
N (p+J
o
w W N
N
o
W N
W o
W
W
N
N No
N
A
N+
m iV
pp
W
po
N
N
�UU4y1ll
N U
NN11
O O
r 41
G
r Cl
Ca A
(n
Go W
C Ill
G m
O G
N G1
..
N
IA
1J
I
o OO
hlFFa
N
W
G
N
G
!
O
o W
W O
e
in
P
G ih
V
O iaN
N
m
G
O
+
H�
O
�
W
1V
o b
ttJJ _
oF.
A
m W
p
Cl N
P W
3
m
p1
O
Cl G
O
A
W
!.] O
O+
1S
f
A A
OI
p
A
N {T
N O+
OD
W
'•J, i0
�p G+
A V
D D
A 4)
i0 O
o W
10 O
O N+
CD W
O
O++
N 10
W
O Al
p
P O
IJ N
pW T
W A
b
$
l0
W
GC +
O,
o
QJ
o
73
iS
O
O P
CD
W
N
W
P
O P
O$
OO
N Gi
UUII
N
C
W P
p 0
N N
Ip O
W W
C N
Ct.
J
Ol
U N
V N
O pP
N
r
N W
W A
N
Ill
Q A
N
Ll S
01
P R
g
Aol Oo
9 N+
((JJ
W P
�WW�llll
O O
y Ill
�y.l P
'N
Q, G
y P
I.0
m
fJ
O j
V
O W
O Gl
O G
(P
�
Ip 'J
W
A
O N
Ill
N OWp
G SP1
A
G
N�4
Ip O
y
N A
pJ O
fJ
N m
p O
N
mJ
N N
C p
VV
N V
p m
o-lO
O O
p
G�
G O
+
p m
b
(
b.P O
O C
t
H
N N
b W
m
m
p
Wp�
OI
N W
+ N
W
O
pl
p+
N b
W+
p O O
8
oCN+
IA W
4444801111
N
p p
P ,p
W W
INV
UWl
Li
W
V
N IJ
W W
p C
P
P m
41 ,y
Z Z
D D
A A
V
P W
W O
O
V V
P V
W N
N++
41
. 41
D P
. N
N
A+
10
V
N
GI (n
Ul
p
N Q
i0
0
O
H
4f F
W
W
71
o jV
�, Ill
0 iD
O
to
W W
iVi
3
A
O$
N N
O
m 0Wj
O
m N
O b
N
5
O
O
O O
♦♦♦b
O
NNNR
O
CG_l O
�.1
W
,�1
lJ
W
N P
W O
fNll N
y
0
W
N �,
P fl
- O O
W N
N
N
G
P Fu
W N
N
A W
W y
n
N
O
N W
A
W J
m L
W P
V
N N
N H
W ((1nl
O
g
A
N
G
W
N
U
V
N
N
G
N
O
S
n
A
�
y
@
W
O
O
N
N
G
y
G
A
C
VA
G
G
b
P
ry
j
P
O
W
N
N
N
O
N
p
w
3
OREVISION RECORD
T NO DATE DESCRIPTION _
■ . GEOMORPHIC PARAMETERS DURHAM SOIL & WATER ,� A 1AM 7
W n:. WARD PROPERTY
DATE: MAY 2017 1 DRAWN BY:DPM STREAM RESTORATION PROJECT Civil & Environmental Consultants, Inc.
O DWG SCALE: ASSHOWNCHECKEOBY: JAW DURHAM, NORTH CAROLINA 250 Old Wilson Bridge Road• Suite 250• Worthington, OH 43085
m PROJECT NO 144.040.EC01 614-540-6633 • 888-598-6808
PP
AROVED BY: JAW W W W.cednc.com
D 01 10 10 im IT Li 2
H
N ROP9
NpMv
NORTH
WARD JAMES 0
0844-03-94-5831
BEGIN CONSTRUCTION
UT2 - STA 10+00
AT EXISTING 78' RCP
INV 330.63'
PROPOSED STREAM
CHANNEL SI
.1
1.
1
EXISTING STREAM
CHANNEL
I
1-1
/ PROPOSED STREAM
/ ' BEGIN CONSTRUCTION CHANNEL Uit
UTI -STA 10+00
AT EXISTING 18• RCP
INV - 332.87'
'LIMITS OF DISTURBANCE = 7.29 ACRES*
NOTES
i 1. ANY HARDWOOD TREES GREATER THAN 12'
R C MUST BE INCORPORATED WITHIN THE STREAM
PROJECT, PER DIRECTION OF ENGINEER.
2. TOEWOOD MAY BE INSTALLED IN LIEU OF
ROOTWADS, PER DIRECTION OF ENGINEER.
3. CONTRACTOR WILL REMOVE ANY INVASIVE OR
EXOTIC SPECIES WITHIN THE PROJECT AREA.
LAND QUALITY NOTES
1. ALL IN -STREAM WORK WILL HAVE A
PUMP -AROUND SET UP BEFORE ANY WORK
BEGINS AND MUST PUMP 24 HOURS A DAY
6 UNTIL THE WORK IN THAT SECTION IS 100%
COMPLETE AND STABILIZED WITH SEED, MULCH,
AND MATTING.
2. ALL STREAMS THAT MUST BE CROSSED, EXISTING
OR NEW, WILL REQUIRE THE WOOD MAT
B TEMPORARY CROSSING, IF THAT SECTION OF
STREAM IS ACTIVELY FLOWING.
3. DO NOT CLEAR AND GRUB MORE THAN 300 FEET
OF THE OFF -UNE STREAM WORK AT ONE TIME.
ALL WORK MUST BE COMPLETED IN THAT
SECTION BEFORE CLEARING THE NEXT 300 FEET.
4. DO NOT CLEAR MORE IN THE LIVE STREAM WORK
AREA, BANKS INCLUDED, THAN CAN BE FINISHED
AND STARIUZED BY THE END OF THE DAY.
5. THE OLD CHANNEL CANNOT BE BACKFILLED UNTIL
THE NEW CHANNEL FOR THAT SECTION HAS BEEN
COMPLETED AND STABILIZED.
3
g REFERENCE
1. TOPOGRAPHIC INFORMATION BASED UPON SURVEY CONDUCTED BY
WITHERSRAVENEL, IN OCTOBER 2016.
A 2. COORDINATE SYSTEM IS NAD 83 NORTH CAROLINA STATE PLANE
I FEET.
3. AERIAL IMAGERY SHOWN ON ALL PLAN SHEETS ARE FROM: USGS
BING IMAGES 2017
7
e
1
'a PROPOSED LIMITS
COSTING STREAM OF DISTURBANCE
$ �
CHANNEL
327 \\
PROPOSED BOULDER
CASCADE (TYP)
Wbkfp - 4.90'
Dmax-1.06 225'2.1
1
TYPICAL POOL SECTION
M'bkf = 4.90'
Dmax-0.53' 1.12' 1.33'
TYPICAL RIFFLE SECTION
Abkf = BANKFULL AREA
Wbkf = BANKFULL WIDTH
Dmax=MAXIMUM BANKFULL DEPTH
Dbkf =MEAN BANKFULL DEPTH
UTI, UT2, Mi
TYPICAL STREAM SECTIONS
I
N.T.S.
END CONSTRUCTION
UTI - STA 13+56
UT2 - STA 12+00
BEGIN CONSTRUCTION
M1 - STA 10+00
SCALE IN FEET
0 30 60
WARD JAMES 0
0844-03-94-5831
LEGEND
— — EXISTING PROPERTY UNE
APPROXIMATE LIMIT OF DISTURBANCE
— 1030 — PROPOSED INDEX CONTOUR
1032 PROPOSED INTERMEDIATE CONTOUR
o+oo �- 5 PROPOSED RELOCATED STREAM CENTERLINE
PROPOSED BANKFULL
PROPOSED STREAM CHANNEL
PROPOSED ACCESS ROAD
® PROPOSED COMPACTED FILL
PROPOSED EXCAVATION
PROPOSED CHANNEL PLUG
WARD JAMES 0
0844-03-94-5831
I
HgMCdy ROgO
PROPOSED STREAM �J
CHANNEL M7
FLOW \
J•4
END CONSTRUCTION
MI - STA 15+35
BEGINCONSTRUCTION
M2 - STA 15+35 �r�2�' `
10
mmm
N
V 0]
Rh
F.y a
,N O
C
iA F
0
O o
E
ii N t7
M7
� N
O R
¢ N
� � a
m
W `o E
rI a
U N
W Q
3Z
CC LLLI - J
Q } Q CC D
Z
3w0U
n• F— _
O cr cc
U) 0 0
�DCC �Z
Ix
D _
0�
W D
cc0
Q W Q
� C �
O
e
\\ ��CA
®O ®®
w
n z
00
sEk P'
"�� •� \
rA All `��` �°\\
4/ �'!
IIk..1et
U W
ORAYANG NO.. A
EC200
pHt_- d 1= 16
7 6 5 4 3 2
I
I
H END CONSTRUCTION
I M 1 - STA 15+35 F1
BE
gN CONSTRUCTION
I M2 - STA 15+35
TRANSION FROM M2 TYPICAL SECTION
.- - WARD JAMES 0 TO M2 HG TYPICAL SECTION STA 23+32 NORTH
PROPOSED LOG 0844-03-94-5831 p o
J -HOOK (TYP) I t r
I W
I cc
FLOW O
PROPOSED UMfTS _ fA
\ _
OF DISTURBANCE _ _
W
cc
G 31
F I A Jp /EXISTING
STREAM
CHANNEL
c F
\ ohm
EEp
PROPOSED ROCK I \ :�
J -HOOK (TYPJ PROPOSED TOE 3
• WOOD (TYP)
EIS PROPOSED STREAM O o
TS m
li CHANNEL M2 / ' ` O S v ;
END CONSTRUCTION I of v
�'W' WARD JAMES 0 \ \ / WARD JAMES 0 M2(HG) - STA 24+49 J '5 '6
E 0844-03-94-5831 \ / 0844-03-94-5831 BEGIN CONSTRUCTION In
\ M3 - STA 24+49 i. C E
JIB � m
PROPOSED ROCK i
CONSTRUCTED :. :2
RIFFLE 0YP) _ w i O
'\ 0
I v N
SCALE IN FEET ~
U
0 30 60 W Q
3Z
0�
D-2.30'Wbkf = 9.72• W— y( d O fJ
C D-2.30' 2.00' 1.53' FQ r Z
Wbkfp = 8.93'
7.0 Dmax=1.50' 3.18' W O V
1 JOQF-
t
Z,(j)
0cr or�2.0 0.7 z.t a00
�ONZ
TYPICAL POOL SECTION TYPICAL POOL SECTION = Q LLI
Q
1 M�2_
C Wbkf = 6.48' Wbkf = 6.93' Q
Dmax=0.70' 1,49' 1.76' Dmax=0.75' 1.59' 1 1.88' W C
��S 2.5
TYPICAL RIFFLE SECTIONTYPICAL RIFFLE SECTION a a w a
Abkf = BANKFULL AREA
Wbkf = BANKFULL WIDTH Abkf = BANKFULL AREA v
Dm1Gx=MAXIMUM BANKFULL DEPTH Wbkf = LL WIDTH
3 Dbkf -MEAN BANKFULL DEPTH Dmax=MAXIMUMXIMUM BANKFULL DEPTH
Dbkf =MEAN BANKFULL DEPTH
R M2 M2 HG -
? TYPICAL STREAM SECTIONS TYPICAL STREAM SECTIONS \>ff g z 6 B
s N.T.S. N.T.S. �D��ii d n Z
9
6
• L SEAL �-;
39208
'ice✓O•t�`�Giva..
A 11.'0��
// \ f]RAWINGNO.. 0 2 A
f''" "`��� EC201
SHEET 5 OF 16
7 6 5 4 3 2
7
END CONSTRUCTION
M2(HG) - STA 24+49
BEGIN CONSTRUCTION
H _ _ - M3 - STA 24+49
I
PROPOSED TOE
WOOD (TTP)
2,30
6 5 4 3
PROPOSED LIMITS BUNCH RICHARD E III
OF DISTURBANCE BUNCH LISA R C, ,rye
0844-04-83-6046
WARD JAMES 0
0844-03-94-5831
/
PROPOSED LOG
J -HOOK (TYP) /
ENO CONSTRUCTION PROPOSED STREAM / / 280-
UT3 - STA 11+72 CHANNEL M3 / EXISTING STREAM
CHANNEL
1 1
y
F zt
z. _ . _ . — . . — . _ . — . — . — . — . — • — • — • — . — .
/ / • PROPOSED BOULDER
• �� CASCADE (TIP.)
• PROPOSED STREAM
CHANNEL UT3
BEGIN CONSTRUCTION
FLOW PROPOSED ROCK
UT3 - STA 10+00 CONRIFFLSTRUCTED -
E (TYP)
I
WARD JAMES 0
E I 0844-03-94-5831
KNIGHT JEAN P
0844-04-73-9602
1
\ H
\ k
NORTH �N
o
SCALE IN FEET �"' O¢ d
0 30 60 \ W w
a:Lu
o
K
m
v x
4�0
_ o
t� F
�.� 0 r m
n O o
WbkfP - 4.90'
m
Dmcx>•1.061 2' - 25'
Ij——il ii Ul cf
2.1 \ cc
m N
y O 4
> D
TYPICAL POOL SECTION � m`
E
W 0
a
Wbkf = 4.90' 3
rl �
Dmax=.0.53'1I - 12' _ L33' � 0
m
1 N
�- 2.5
TYPICAL RIFFLE SECTION L)
�►�i�� U
CA � Abkf Wbkf - BANKFULL. AREA n Z
BANKFULL WIDTH w Q
/ Dmax=MAXIMUM BANKFULL DEPTH W 0 J
Dbkf =MEAN BANKFULL DEPTH �•- d O D
UNITED STATES OF AMERICA ®✓°�' s Q
0844-04-74-8943 o°� ���� �..' NORTH UT3 3 w O U
�a.� SCALE IN FEET TYPICAL STREAM SECTIONS a1
��2N.T.S. —I Och CL p o
Q H
S) -a
r7•'
EXISTINGSTREAM i" U °d'il ° ���® Wbkf - 12.62' Q inCHANNEL W
Dmax=2.90' ir
cc
1
7.0 cc0 C
H
U)
1 1 a a a
•osgl �- ♦w .b�
I
I � I
7 B
N PROPOSED ROCK
CONSTRUCTED J
�rn RIFFLE 0-YP)
WARD JAMES —.—.—. .—•—. .-.�.I
0844-03-94-5831 -
VERNAL POOL
I• PROPOSED LIMITS
A OF DISTURBANCE
I
I
7 6 5 4
2.0
0.7
Gaul
O
"•
KNIGHT JEAN P
e
D
Wbkf = 8'41
0844-04-84-3355
M3 -STA 36+76
1.93'
Z
3
m U
�w
B
• T '
2.5
_ - PROPOSED TOE
WOOD (TYP)
WARD JAMES 0
/
w
\
PROPOSED LOG 0844-03-94-5831
/
TYPICAL RIFFLE SECTION
• \
J -HOOK (TYP)
/•
a
•
FLOW
•$
`
/
Wbkf = BANKFULL WIDTH
C G
DmaX-MAXIMUM BANKFULL DEPTH
Dbkf =MEAN BANKFULL DEPTH
1
\ H
\ k
NORTH �N
o
SCALE IN FEET �"' O¢ d
0 30 60 \ W w
a:Lu
o
K
m
v x
4�0
_ o
t� F
�.� 0 r m
n O o
WbkfP - 4.90'
m
Dmcx>•1.061 2' - 25'
Ij——il ii Ul cf
2.1 \ cc
m N
y O 4
> D
TYPICAL POOL SECTION � m`
E
W 0
a
Wbkf = 4.90' 3
rl �
Dmax=.0.53'1I - 12' _ L33' � 0
m
1 N
�- 2.5
TYPICAL RIFFLE SECTION L)
�►�i�� U
CA � Abkf Wbkf - BANKFULL. AREA n Z
BANKFULL WIDTH w Q
/ Dmax=MAXIMUM BANKFULL DEPTH W 0 J
Dbkf =MEAN BANKFULL DEPTH �•- d O D
UNITED STATES OF AMERICA ®✓°�' s Q
0844-04-74-8943 o°� ���� �..' NORTH UT3 3 w O U
�a.� SCALE IN FEET TYPICAL STREAM SECTIONS a1
��2N.T.S. —I Och CL p o
Q H
S) -a
r7•'
EXISTINGSTREAM i" U °d'il ° ���® Wbkf - 12.62' Q inCHANNEL W
Dmax=2.90' ir
cc
1
7.0 cc0 C
H
U)
1 1 a a a
•osgl �- ♦w .b�
I
I � I
7 B
N PROPOSED ROCK
CONSTRUCTED J
�rn RIFFLE 0-YP)
WARD JAMES —.—.—. .—•—. .-.�.I
0844-03-94-5831 -
VERNAL POOL
I• PROPOSED LIMITS
A OF DISTURBANCE
I
I
7 6 5 4
2.0
0.7
Gaul
O
TYPICAL POOL SECTION
e
END CONSTRUCTION
Wbkf = 8'41
M3 -STA 36+76
1.93'
Z
3
m U
�w
B
2.5
WARD JAMES 0
w
S 3
0844-03-94-5831U)
TYPICAL RIFFLE SECTION
r =
N
a
Abkf = BANKFULL AREA
Wbkf = BANKFULL WIDTH
DmaX-MAXIMUM BANKFULL DEPTH
Dbkf =MEAN BANKFULL DEPTH
M3
TYPICAL STREAM SECTIONS
ui p
a
a
DRAWING NO..
A
N.T.S.
EC202
SHEET 6
OF
16
3
2
1
7 1 6
BEGIN CONSTRUCTION
UT2 - STA 10+00
AT EXISTING 18" RCP
H CONSTRUCTION INV = 330.63'
ENTRANCE
1 V8�
�\ PROPOSED
®` LIMITS
STAGING --'• \ OF
STOCKPILE �•� - �.L DISTURBANCE
DITCH PLUG 327-
HAUL ROAD R "^ 'a..
_ END CONSTRUCTION PROPOSEDSTREAN� '\
Say - UT1 - STA 13+56 CHANNEL M1
UT2 - STA 12+00
BEGIN CONSTRUCTION
Ml - STA 10+00 •�
BEGIN CONSTRUCTION •\
UTI - STA 10+00
AT EXISTING 18" RCP
INV = 332.81'
FI
6
WARD JAMES 0
0844-03-94-5831
k9MGN
RpgO
END CONSTRUCTION
M1 - STA 15+35
BEGIN CONSTRUCTION
�pO2n�GG•
M2 - STA 15+35
J'
r� gyp!
DITCH PLUG
� 2
Y'
GAUSE LEE B
A, ,n
'g O�
MCNAIR R L 57
0844-04-83-428
\ •
BANE SS THF
GAUSE
R LRE B
LSR
` \
•
•� - •
4-04
MCNA
0844-04-83 508
\
sr
` 93-0486
\
�''P
\ • '•� •�>MCNAIR
�l'• .
LEE 8
` • o u,•o "'a�
GAUSE-
0844-04-83-6782
�8
DITCH PLUG
WARD JAMES 0
p
-
0844-03-94-5831
CAUSE LRELB5
EXISTING STREAM
_
--
-
MCNAIR 6870
0844-04-83-
CHANNEL
•�
DITCH PLUG
BUNCH RICHARD E JR
\1
TRANSITION FROM M2 TYPICAL SECTIONBUNCH
3-6866
0844-04-83
TO M2 HG TYPICAL SECTION STA 23+32
..a
a
RICHARD E JR
a ^
BUNCH 11
VERELLE
END CONSTRUCTION
/
BUNCH
0844-0 4-83-G964
M2(HG) - STA 24+49
�.
BEGIN CONSTRUCTION
`O•,b, �`.
DITCH PLUG
M3 - STA 24+49
°•pO
,� „>p
;O
\
9
BUNCH RICHARD E III
A
BEGIN CONSTRUCTION
•� a�
BUNCH LISA R
-S4-6048
-
z
UT3 STA 10+00
0844_p4
p
TEMPORARY
CROSSING
STREAM
'-.
-_:,
9 a�,� •
A
rn CONSTRUCTION
ENTRANCE
`
WARD JAMES 0
END CONSTRUCTION
UT3 - STA 11+72
0844-04-84-6128
_STAGING
STOCKPILE
1
NORTH
Oa
w
z o
w
W
w
HAUL ROAD -� • \ ¢
� ' \ KNIGHT JEAN P
4 �
TEMPORARY STREAM 0844-04-84-3355
J KNIGHT JEAN P
\ '� \ 0844-04-73-9602
CROSSING ti
�\ a
EXISTING STREAM
$ \ CHANNEL
UNITED STATES
x,w
a�\0►I�CA ��� �s
e y~7 -
SEAL
39208 '7 r
fA lAlvv.X\�e
4 3
OF AMERICA
0844-04-74-8943 2 m w
\ \ 2 3 v 8
• � \o„ U a v
\n Z
END CONSTRUCTION p n C
•� - M3 - STA 38+76 O H
\.' w a
ROCK DAM
w�
wg
S NU
DRAWING NO.: A
SCALE IN FEET EC203
�r
0 100 200 5MEE 7 OF 16
2 1 1
ELEVATION (FT)
J
+
N
N
I c)
ELEVATION (FT) ,
c
r ° A�
a REVISION RECORD
m = 11A
-,-,-
NO DATE DESCHIPTION
n°PROFILES DURHAM SOIL & WATER � �
WARD PROPERTY
OSTREAM RESTORATION PROJECT Civil & Environmental Consultants, Inc.
DATE: MAY 2017 ]DRAWN BY: DPM
DWG SCALE: ASSHOWN CHECKEDBY: JAW DURHAM, NORTH CAROLINA 250 Old Wilson Bridge Road Suite 250 Worthington, OH 43085
m O PROJECT NO 144-040.EC01 614-540-6633 - 888-598-6808
APPROVED BY: JAW W W W.CBCInC.Gom
D p0 () O m T O =
}
O
O
a5
b
+
O
O
a5(
0
b
yCA =
m A
N
O
}
O
O
a5a
ut
Z ON
X
D
mq
Z
nO
m
m
N
m
O
Om
Z
m
r
m
0
a5o
N
N
+
0
I c)
ELEVATION (FT) ,
c
r ° A�
a REVISION RECORD
m = 11A
-,-,-
NO DATE DESCHIPTION
n°PROFILES DURHAM SOIL & WATER � �
WARD PROPERTY
OSTREAM RESTORATION PROJECT Civil & Environmental Consultants, Inc.
DATE: MAY 2017 ]DRAWN BY: DPM
DWG SCALE: ASSHOWN CHECKEDBY: JAW DURHAM, NORTH CAROLINA 250 Old Wilson Bridge Road Suite 250 Worthington, OH 43085
m O PROJECT NO 144-040.EC01 614-540-6633 - 888-598-6808
APPROVED BY: JAW W W W.CBCInC.Gom
D p0 () O m T O =
aI
W
ELEVATION (FT)
N01
01
V J
ONO
o
N
O
N
4 N
o
I
SIA - 32 h15 EEEV _ 27289
M SIA - 32+27 ELEV - R7].4
O
O o
M SfA - 12f ] Elft/ - 271.64
m p
0
V m
v
—M . a80 —Y-272.45
- J
C
11 SIn - 1+12 - 271,11
M SIA - 3+4 - 71.54
STA - ]]+ fi 270—
- 7 .
n+94
3+ 4 EL - 289.84
m
O
09 E EV -
M SIA - >•i]3 ELFT - 269.94
A . 4+51 aEY - 2 1.78
M SIA - 3M b EI£V - 2--
85646.0
6.0
M STA ]5+11 E - 288.01
PV .7
i I
- - __—STA . 5+ 1
f67 EEn - zm.a
(N STA - 3s+81 8- - 267.53
- 6+15 EIEV - 267.11
M STA - mo1 - RB8.00
PVI SIA . ]Bi _ 1
M SIA - 36+8] ELLV - 285.11
6S
M . 37+27 65.29
�
n
M STA - 37+45 N.W
-
A - a80 EtfV - 2N.99
I
M 64.08
M STA _ FtEV fiJ.50
m
I
z
0
------
8+63 E - 20.1 0
CA
M STA - 36aJ3.
SB+76 lfV . 262."2-1
N ONpS1 N
O (NA O (ill
N
O
N
IVA1
N
O
ELEVATION (FT)
L
ELEVATION (FT)
D-:
O
J
A O
zo
rn D
3K
Z
m C0
rn
o �
m
m O
� a
Z F�A r
z m N
m o
+d
b
O
fst
W
O
O
O
a51
O
O
o9••••... -----
�• •. . w, PA . 3-1 +5LU 7 4
OPrmn
o�bJw�
o �,o D y.'a'-
i�1" �'IV N N o cNJi1 0 o u o
�Q
®oo • �r ^Q ELEVATION (FT)
o
REVISION RECORD
f NO DATE DESCRIPTION
- m //JFAW A
o PROFILES DURHAM SOIL & WATER
(` WARD PROPERTY
o A DATE: MAY 20
W717 DRAWN BY: DPM STREAM RESTORATION PROJECT Civil &Environmental Consultants, Inc.
T O DWOBCAj AS SHOWN CHECKED BY: JAW DURHAM NORTH CAROLINA 250 Old Wilson Bridge Road- Suite 250- Worthington, OH 43085
� PROJECT NO: 144-O40.EC01 1
614-540-6633 886-598.6808
APPROVED BY: JAW W W W. cECinC.COm
y Ot [) O m T1 L7 2
D m C, O
ELEVATION (Fr)
T I m
ELEVATION (FT)
ELEVATION (FT)
1 c'
11,
0
M SG - IOhm EI1V _ ]30.]9 '
M h1J ELEV _ J .97
M SIA _ 10i I] ELEV - 13(1.50
M STA . 14N1 J0.
M SIA - 10423 ELEV - 329.58
104]0 ELN - 3]001 M SIA - ) E1fV _ JJ0.11 1 19.89
M STA - OaJt
M SiA - IO4J1 0.fl - ]2902
M 043
7 E—
A .329.55
M = 104{1 fV =
N M SIA - 10+41 ELEV
w =O }28.82._
10+5 EL _ 328.fi0
.'V M M-- - 1 +55 ELEV _ 327.fi5
U _ Prl SIA _ l0i - }2B.IB
O 2 OM SIA - 10482 ELEV _ J. O Tl
Z M _ 10+85 0. _ ]26.9]
iSiA _ 10489 EIfV _ ]2).50
X m " S _ 10+72 ElEV _ 327.28 m O
y C A. 10+7 ElEV� ]28.o
1047
rel PN A _ f0«B2 EIEV - 328.62 m
qq N MSIA- —86 ]5.
M STA - 10+90 EIEV - 328.09
r V 10+97 E—
m
LEV
m O O M 5, ♦ 11«01
m " -
O M SIA - 11+07 0. 4.25
M STA * 11+11 24.7 ] D
1 H SIA - 11 Ss2 O
1142] ELEV _ 321.05
RI M VA . —21
OLINER_ 11+ .11
Z m M STA - 114]2 RiY _ 3
- 11♦ flfV - J .8D /
Z M SIA ^11+]8 - 322.57
A - 11— EIEV - ]2 .I
D
Eg
- 3
srA M srA - 11+boa - 321 s
O M SfA - 47I1 EIEV - ]21.238
M e ELEV - ]31.701a>1 - ] 1 y,
A 11a M STA - I480 ELEV _ 320.88 7
M A - 1148] EIEV - ]21.32 +8 Q
M STA = BI ELFV = .511
N M Sf .111«95 J2—
+ E1EV ]20.90
®® O
°® W G W W U W W U
(Oil O In O N O U O
ELEVATION (FT)
e0
51���s ..9 B ..40 ®®
REVISION RECORD
O o PROFILES DURHAM SOIL & WATER AZAW , ,= NO DATE DESCRIPTION
WARD PROPERTY
7
CA) DATE: MAY 2017DRAWN BY: DPM STREAM RESTORATION PROJECT Civil & Environmental Consultants, Inc.
O DWOBCALE: ASSHOWN CHECKEDBY: JAW DURHAM, NORTH CAROLINA 250 Old Wilson Bridge Road • Suite 250•Worthington, OH 43085
N PROJECT NO: tasoao.ECOt 614-540-6633.888-598.6808
APPROVED BY: JAW1 W W W..CeCInC.COm
D m (l O m ITt O _
0
0
0
N
m A
Z O
x
x
r�E y�y
r
50
<
C
A
—1 rnrn
yO
r
V
AO0
T
W
r+
z
m
o
m
N
Z
m�
0
+sa
_
W
T I m
ELEVATION (FT)
ELEVATION (FT)
1 c'
11,
0
M SG - IOhm EI1V _ ]30.]9 '
M h1J ELEV _ J .97
M SIA _ 10i I] ELEV - 13(1.50
M STA . 14N1 J0.
M SIA - 10423 ELEV - 329.58
104]0 ELN - 3]001 M SIA - ) E1fV _ JJ0.11 1 19.89
M STA - OaJt
M SiA - IO4J1 0.fl - ]2902
M 043
7 E—
A .329.55
M = 104{1 fV =
N M SIA - 10+41 ELEV
w =O }28.82._
10+5 EL _ 328.fi0
.'V M M-- - 1 +55 ELEV _ 327.fi5
U _ Prl SIA _ l0i - }2B.IB
O 2 OM SIA - 10482 ELEV _ J. O Tl
Z M _ 10+85 0. _ ]26.9]
iSiA _ 10489 EIfV _ ]2).50
X m " S _ 10+72 ElEV _ 327.28 m O
y C A. 10+7 ElEV� ]28.o
1047
rel PN A _ f0«B2 EIEV - 328.62 m
qq N MSIA- —86 ]5.
M STA - 10+90 EIEV - 328.09
r V 10+97 E—
m
LEV
m O O M 5, ♦ 11«01
m " -
O M SIA - 11+07 0. 4.25
M STA * 11+11 24.7 ] D
1 H SIA - 11 Ss2 O
1142] ELEV _ 321.05
RI M VA . —21
OLINER_ 11+ .11
Z m M STA - 114]2 RiY _ 3
- 11♦ flfV - J .8D /
Z M SIA ^11+]8 - 322.57
A - 11— EIEV - ]2 .I
D
Eg
- 3
srA M srA - 11+boa - 321 s
O M SfA - 47I1 EIEV - ]21.238
M e ELEV - ]31.701a>1 - ] 1 y,
A 11a M STA - I480 ELEV _ 320.88 7
M A - 1148] EIEV - ]21.32 +8 Q
M STA = BI ELFV = .511
N M Sf .111«95 J2—
+ E1EV ]20.90
®® O
°® W G W W U W W U
(Oil O In O N O U O
ELEVATION (FT)
e0
51���s ..9 B ..40 ®®
REVISION RECORD
O o PROFILES DURHAM SOIL & WATER AZAW , ,= NO DATE DESCRIPTION
WARD PROPERTY
7
CA) DATE: MAY 2017DRAWN BY: DPM STREAM RESTORATION PROJECT Civil & Environmental Consultants, Inc.
O DWOBCALE: ASSHOWN CHECKEDBY: JAW DURHAM, NORTH CAROLINA 250 Old Wilson Bridge Road • Suite 250•Worthington, OH 43085
N PROJECT NO: tasoao.ECOt 614-540-6633.888-598.6808
APPROVED BY: JAW1 W W W..CeCInC.COm
D m (l O m ITt O _
7 1 6 1 5 1 4 1 3 f 2
6 15 14
2
-vy/�Ay��
LOQ "�(
w
A -POINT OF
/ CURVATURE
J\ B (THIS DETAIL)
F
POINT OF CURVATURE 'i��
LOOS IF LIMED
ON-SITEAVAILABLE). 7HERMSIE USE (A B 'uL UNDER STREAMBED
(� V/J
NON -WOVEN @
GEOTEXTILE FABRIC W �J f y1
ON-SITE STREAM ALLUVIUM (IF
AVAILABLE). OTHERWISE USE A WELL
GRADED MIX OF CLASS A, CLASS B.
HEADER PAST r. SILLLL
BOULDERS
O
o
WELL G
WELL GRADED MIX OF CLASS A B'Wkf).,. TOP OF BOULDER
CLASS B, AND 057 STONE A I3 -K AT INVERT ELEV.
MIXTURE AND WELL O TOP OF BOULDER 5 FT. SILL
(TYPE B) \,�
HEADER BOULDERS
AND 057 STONE A MIXTURE OF
ALLUVIUM AND WELL GRADED MIX
¢
O
U
a
y
A HEADER AT INVERT ELEV.
IX MAY ALSO i
MIX MAY AL50 BE USED / 4 LOG PAST
ON-SITE STREAM %MAY
t -J
ALSO BE USED FOR BACKFILL
_
BANIff71LL _
W
Q
a
FOR BACKFILL
FOR BA BANKFULL
ALLUVIUM (IF "Z
...
\ ;�
_ ... _ ..
`J�\
/ HEADER
ON-SITE STREAM ALLIMUM (IF SILLRAD
AVAILABLE). OTHERWISE USE A BWLOERS LDER
AVAILABLE), OTHERWISE TOP OF BOULDER % \\'.�
AT INVERT ELEV. �\
MIX OF CLASS G A. 20. TO 30 V
STREAMBED
Z
G
y
HEADER LOG WELL GRADED MIX OF CLASS A BMNKFULL
20'-30 CLASS B, AND 7 STONE A
W
CLASS B. AND 057 J" � J
F
\\ \
/\\
) �.
uj
uj
\ MIXTURE OF ALI UAI AND WELL - \ �\ . �i\\
NON -WOVEN GEOTEXTILE FABRIC GRADED MIX MAY ALSO BE USED
ALLUVIUM AND WELL
GRAUSD MICR Y ALSO c`'BP
/
(TYPE IQ FOR BACKFILL ,\: \ ; \\
�
-eO / ,4
HEADER BOULDERS
NON -WOVEN GEOTEXTILE FABRIC/' �\Tj \\-/
ROOTWASMALL
EMEND INTO (TYPE II)
TO BANK �
A
DETAIL)
BOULDERS
A MIN. OF 10 FT. \ FOOTER
A (THIS DETAIL) LOG FOOTER BOULDERS
_ (THIS
/� - �
NON -WOVEN
w
o
/
Oct\' SECTION A -A
`
SILL /J FOOTER BouLDERs
GEOFABRIC
SECTION A -A
/MIDPOINT EXISTING GROUND
5 FT. SILL
ROOTWAD INSTALLED OF CURVE PAST
BOULDERS)
(TYPE II)
0
UNDER LOG VANE / BANKFULL BANKFULL
_
MID POINT
6 FE. SILL
() m
ANCHOR BOULDER `�// '\\\'
AN
OF CURVE
PAST BMKFUU.
00
�y
B FOOTER BOULDERS%/\>> v
(THIS SHEET) \\.•,\\�7\\,���
SILL
BOULDERS
HEADER BOULDERS
IH a
/\„
BANKFULL
- - BANKFULL
O
• \\� ''.\ \ /
POINT OF TANGENCY ' / \%�\\ \\, -• \. ' �/ �\
POINT OF
TANGENCY
-
O
HEADER AND FOOTER LOGS
- �.
V'VVE
COPE STREAMBED
SHALL BE PLACED INTO
STREAMBED
o
THE RATE
SECTION B-B``r�Cb
PLAN
/AA v .
E
8
NOTES,10
FOOTER BOULDERS WILL BE PLACED
-\� \ -44
06
6. NON -WOVEN GEOTEXTILE FABRIC (TYPE III SWILL BE INSTALLED ON THE UPSTREAM SIDE OF
1. A HYDRAULIC EXCAVATOR, WITH A HYDRAULIC THUMB. SHALL BE USED TO PLACE BOULDERS THE ROCK J -HOOK 1/4 -INCH FROM THE TOP OF THE ROCK. THE NON -WOVEN GEOTEXTILE
AND LOGS.
PLAN VIEW
INTO THE EXISTING SUBSTRATE A
MINIMUM HE BOULDER DIAMETER OF Tco
\ N�'
FABRIC SHALL BE BURIED IN THE BOTTOM OF THE CHANNEL AND SHAT BE PLACED THE
NOTES:
2. LOGS SHALL BE RELATIVELY STRAIGHT, HARDWOOD, AND RECENTLY HARVESTED AND EXTENDED ENTIRE LENGTH OF STRUCTURE.
SECTION B -B
1 v b
INTO THE BANK 6 -FT. 7. ROOT WAD SHALL BE PLACED BENEATH THE HERDER LOG AND PLACED SO THAT R LOCKS
1. ALL BOULDERS SHALL BE A MINIMUM DWAETER OF 1.5 Ff.
' O a
c
\
THE HEADER LOG INTO THE BANK.
3. TAG VANE SHALL EXTEND FRO THE BOTTOM OF THE BED ELEVATION 70 THE HEAD OF THE
2. GAPS BETWEEN BOULDERS SHALL BE MINIMIZED BY FITTING BOULDERS TOGETHER, AND PLUGGING WITH STRUCTURE STONE CLASS A AND SELECT
MATERIAL AND LINED WITH FILTER FABRIC. THE CONTRACTOR WILL BE REQUIRED TO FR BOULDERS TIGHTLY.
Q y
S4 pT e
OF //M
VANE AT A MIN. 2X 4%. HEADER DEPTH FOOTER LOGS SFWl BE TIm SECURELY INTO THE B.W. THE LOG VANE ARM K IN SUCHEAOF B. KA EXCAVATED(I AV) OTHERWISE
•�J
USE WELL GRADED MWiX OF CIASS A CLASS B. ALIO /SAID STONE.UVIUM
MVIXTURE OAF
WAY MAT EUMINATES THE POSSIBILITY OF STREAM FLOW DIVERTING MOUND THEM. AND WELL GRADED MIX MAY ASO BE USED FOR BACKFILL
3. DIMENSIONS AND SLOPES MAYBE ADJUSTED TO Fff B7 THE ENGINEER.
m
4. NON -WOVEN 9. SOIL SHALL BE COMPACTED WELL AROUND BURIED PORTIONS OF LOG WHILE CREATING A
FABRIC (TYPE 10 SHALL BE INSULTED ON THE SIDE OF SMALL POCKET BETWEEN THE HERDER LOG AND THE OUTSIDE BANK.
THE STRUCTURE
4. A DOUBLE FOOTER BOULDER SWILL BE UTUZED IN SHAD BED MATERIAL
S. VINE ARM SWILL TIE THE BANK
W O
w
I�
REO1/4 DI
1/4 DIAMETER LENGTH FROM THE TOP OF THE LOG. THE
E NAILS SHALL
NAILS SHALL BE
NO GREATER THAN 72 INCHES ON CENTER. THE WOVEN GEOTEXTILE FABRIC SHALL BE
INTO HALFWAY BETWEEN THE CANNEL INVERT AND BANKFULL ELEVATIONS.
THE CHANNEL INVERT AT AN MLLE OF 20-30 DEG FROM THE ADJACENT TANGENT LINE
THE ARM SHALL RISE AT 21I-4[ FROM
BURIED IN THE BOTTOM OF THE CHANNEL AND SHAT BE PLACED THE ENTIRE LENGTH OF 10. ALL MATERIALS ARE TO BE APPROVED BY ENGINEER OR ENGINEER'S ON-SITE CONSTRUCTION
STRUCTURE
-FILTER
OBSERVER
6. FABRIC SHALL BE PLACED ON THE UPSTREAM SIDE OF THE VANE STRUCTURE TO PREVENT WASHOUT OF SEDIMENT THROUGH BOULDER GAPS.
FILTER FABRIC
SHALL EXTEND FROM THE BOTTOM OF THE FOOTER BOULDER TO THE FINISHED GRADE
THE
ELEVATION AND SHALL BE PLACED THE ENTIRE
�y O
5. BOULDERS SHALL BE PLACED ON 70P OF HEADER LOG FOR MCHORING. 1 /3 OF THE WAY 11. ITEMS IN THIS DETAIL AR� A GRAPHICAL ILLUSTRATION AND p0 NOT SPECIFY DHE ACTUPL
ACROSS TME CHANNEL FROM THE OUTSIDE BANK, THE HEADER ROCK SHILL PLACED
LENGTH OF STRUCTURE
0
IN
. r. QUANTITY OF MATERIALS I.E. LOGS, BOULDERS, STONE. ETC.) TO BE USED FOR
THE CHANNEL INVERT ELEVATION. HEADER BOULDERS TO BE PLACED 0.10 -FT. TO 0.25-Ff. CONSTRUCTION.
7. ALL MATERIALS ARE M BE APPROVED BY THE ENGINEER OR THE ENGINEER'S ON-STTE CONSTRUCTION OBSERVER.
MART HARM MINIMUM DIAMETER OF 1.$ Ff.
DETAIL NO. 2
DETAIL NO. 1
ROCK J -HOOK
~
U
LOG J -HOOK
N.T.S.
w Q
N.T.S.
�Z
Cc O
NOTES,
Ir
1. CONSTRUCTEDALLLMN. RIFFLES ARE GRADE CONTROL AND HABITAT ENHANCEMENT MEASURES THAT ARE USED
A M MAINTAIN GRADE
CC Z Q
OF UPSTREAM POOLS, OXYGENATE WATER, AND PROVIDE HABITAT FOR EPIFAUNA AND FISH.
\
THIS DETAIL CAN BE E STRUCTURES ARE TYPICALLY
FOR CONSTRUCTING RIFFLESSUUS NG NATURAL WITH ALLUVIUM CONSISTING OF BOULDERSLESS THAN .
W O U
a
\ -•' COBBLES, AND GRAVEL OR SPECIFIED SELECT MATERIAL
J a
.I 2. COGEONSTRUCTED ALLUVIAL RIFFLES SHOULD BE PLACED AT THE STATIONS, OFFSETS ELEVATIONS AND
lTFlON PLAN, AND
SITIONS INDICATED ON THE STREAMAS
ccO
ON
THIS DETAIL, ORMORPHC
DIRECTED BY THE ENGINEER. AT,A MNMUMTION , THE BATA M ICFUUL ER BERM, AND
a O
LOW -FLOW CHANNEL WIDTHS; INVERT ELEVATIONS AT HERD AND BOTTOM OF RIFFLE; ESTIMATED ROCK
I I THRESHOLD SIZE; AND ALLUVIUM OR SELECT MATERIAL CLASSIFICATION AND DEPTH SHOULD BE SPECIFIED IN
c 0 f- Z
(( • THE STREAM MITIGATION DATA TABLE.
C V)
r 3. REFER TO SPECIAL NOTES FOR STREAM DESIGN'.
LLI
Q
-
'- 4. CONSTRUCTED ALLUVIAL RIFFLES ARE PLACED IN THE STRAIGHT SECTIONS OF THE CHANNEL BETWEEN MEANDER
ON-SITE STREAM ALLUVIUM (IF AVAILABLE),
Q
cc
BENDS (I.E., BETWEEN UPSTREAM POINT OF TANGENCY AND DOWNSTREAM POINT OF CURVATURE), AS INDICATED
OTHERWISE USE A WELL GRADED MIX OF CLASS ON THE STREAM MITIGATION PLANS.
-
CC
D C
A CLASS B, AND 057 STONE A MIXTURE OF
• f
Q CC
ALLUVIUMAND WELL GRADED MIX MAY ALSO BE 5. ALLUVIUM OR SELECT MATERIAL FOR CONSTRUCTED RIFFLES SHALL CONSIST OF COARSE SUBSTRATE (GRAVEL,
I USED FOR BACKFILL COBBLE, AND BOULDER). A MIXTURE OF SIZES OF ALLLMUM OR SELECT MATERIALS, AS SPECIFIED ON THE
Q
W D
A STREAM RESTORATION PLAN SHEETS, SHOULD BE USED FOR SUBSTRATE IN RIFFLE AND RUN HABITATS.Q
\ COARSE ALLUVIUM EXCAVATED FROM THE EXISTING STREAM BED, WHICH MEETS THE SPECIFIED SIZE
CLASSIFICATION, IS THE PREFERRED MATERIAL M USE FOR SUBSTRATE RESTORATION. REFER TO SUBSTRATE
CONTROL POINT \ RESTORATION INFORMATION.
POINT OF TANGENCY
(HT) \ 6. CONSTRUCT A LUNIAL RIFFLES BY:
THE
a '
Q
6.1. SHAPE CHANNEL MD FLOODPWN M THE SPECIFIED GRADES AND DIMENSIONS.
6.2. EXCAVATE ENOUGH BED MATERIAL TO PLACE SUBGRADE MATERIA. IF SPECIFIED, AND COARSE ALLUNIAM OR
PLAN SELECT MATERIAL FOR THE RIFFLE TO ACHIEVE THE SPECIFIED INVERT ELEVATIONS. IF THE CHANNEL IS
DESIGNED WITH AN INNER BERM, KEY THE COARSE ALLUVIUM OR SELECT MATERIAL INTO THE BANK S
EXTENDING ENTIRELY UNDER THE INNER BERM. IF THE CHANNEL LACKS AN INNER BERM. KEY THE COARSE
BANKFULL WIDTHALLUVIUM OR SELECT MATERIAL INTO THE BANKS EXTENDING ALONG THE TOE
COIR FIBER EROSION (Wbkf7 COIR FIBER EROSION 6.3. PLACE THE COARSE ALLUVIUM OR SELECT MATERIAL IN SIX-INCH LIFTS AND COMPACT EACH UFT WITH THE
e
CONTROL BLANKET CONTROL BLANKET BUCKET OF THE EXCAVATOR.
LOW 6.4. INSTALL THE ALLUVIAL RIFFLE AT THE INVERTS SPECIFIED IN THE PLANS AND THEN CHECK THE ELEVATIONS
OF THE INVERTS WITH SURVEY EQUIPMENT.
Nd 6.5. PLACE SOIL OVERTHE TOP OF THE COARSE ALLUVIUM OR SELECT MATERIAL KEYED INTO THE INNER BERM
- OR STREAM BANK AND GRADE THE INNER BERM/BANKS TO THE SPECIFIED ELEVATIONS.
7. THE CONSTRUCTED ALLUVIAL RIFFLE MATERIAL SHALL BE FINISHED M CREATE A SMOOTH PROFILE, WITHOUT AN
m
ABRUPT JUMP/TRRVSMON BETWEEN THE UPSTREAM POOL -GLIDE AND THE RIFFLE, OR AN ABRUPT
DROP/TRANSMON BETWEEN THE RIFFLE AND THE DOWNSTREAM RUN OF
-POOL THE FINISHED CROSS-SECTION
SECTION B -B ON-SITE STREAM ALLUVIUM (IF AVAILABLE), THE kIFFLE MATERIAL SHALL GENERALLY MATCH THE SHAPE AND DIMENSIONS SHOWN ON THE RIFFLE TYPIGL
- OTHERWISE USE A WELL GRADED MIX OF CLASS SECTION WITH SOME VARIABILITY OF THE THALWEG LOCATION AS A RESULT OF PLACEMENT OF LARGER
`
y
Q
SUBSTRATE, SUCH AS BOULDERS.
HERD OF RIFFLE A CLASS B. AND 057 STONE A MIXTURE OF
r
^ _
ALLUVIUM AND WELL GRADED MIX MAY ALSO BE
/w�
` "• O ��
LU
3
B. THE END E RIFFLE CONTROL POINT MAY TE IN TO A DRAINAGE STRUCTURE OR OTHER IN -STREAM
USED FOR BACKFILL (E.G. - VANE. LOG OR BWLDER SILL, ETC.). AT A MINIMUM COR FIBER ROLLS SHOULD
\
\ `
\ ® /
E s
O
N
a =
RHOOK
BE CONSIDERED
GAS BE CONSIDERED TO PROTECT THE OUTER BEND DOWNSTREAM OF THE CONSTRUCTED ALLUVIAL RIFFT.E.
16' MIN. DEPTH
`\ • 4
��' y
Q A_ �"
Q
9. RE -DRESSING OF CFIANNEL AND BANKFULL BENCMC /FLOODPWN WILL LIKELY BE REQUIRED FOLLOWING
. !. -�� INSTA LATION OF IN -STREAM STRUCTURES
= A "/ �.� I
P� AND SHWIALLLL BE CONSIDERED INCIDENTAL M CONSTRUCTION.
SEA L
- 10. COIR FIBER EROSION CONTROL BLANKET SHALL BE INSTALLED ABOVE THE LOW -FLOW CHANNEL OF THE RIFFLE
Q A
O
'
SECTION A -A "- POOL 11. ALL MATERIALS ARE M BE APPROVED BY ENGINEER OR ENGINEER'S ON-SITE CONSTRUCTION OBSERVER.
�. " "
o
12. CONSTRUCTED ALLUVIAL RIFFLES PAYMENT SHALL INCLUDE ALL MATERIALS, EQUIPMENT, AND LABOR TO
CONSTRUCT THE ALLIMAI RIFFLE.
✓.,� (;. -� \
OeQ
�DETAIL
DRAG
N. 3jsVy��j
ROCK CONSTR CTED RIFFLE
��,1```l��
A o0
N.T.S.
SHEET 11 OF 16
6 15 14
2